Wildearth Guardians v. U.S. Bureau of Land Management ( 2014 )


Menu:
  • UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    WILDEARTH GUARDIANS et al., )
    )
    Plaintiff, )
    )
    v. ) Civil Case No. 1:11-cv-148l (RJL)
    )
    BUREAU OF LAND MANAGEMENT, )
    )
    Federal Defendant )
    )
    )
    )
    STATE OF WYOMING, et al., ) F I L E D
    > MAR 3 1 2014
    )
    Defendant-Intervenors
    C|erk, U.S. District & Bankruptc\_/
    courts for the District of Co|umb\a
    47»~
    MEMoRANDoM oP1N1oN
    Mar¢h§ 2014 [## 38, 41, 431
    Plaintiffs WildEarth Guardians, Defenders of Wildlife, and the Sierra Club
    (collectively, "plaintiffs") brought suit against defendant United States Bureau of Land
    Management ("BLM") in connection with BLM’s decision to lease two coal tracts in
    Wyoming’s PoWder River Basin ("PRB")-the Belle Ayr North ("BAN") and Caballo
    West ("CW") tracts.l Plaintiffs claim that BLM violated the National Environmental
    Policy Act ("NEPA"), 42 U.S.C. §§ 4321-4335, and the Federal Land Policy
    Management Act ("FLPMA"), 43 U.S.C. §§ 1701-1784, because the agency failed to
    l Following initiation of this action, the state of Wyoming, Alpha Wyoming Land Company,
    LLC, and Peabody Energy Company intervened as party defendants (collectively, "defendant-
    intervenors").
    adequately consider the impacts on air quality and climate change resulting from the two
    leases before deciding to authorize those leases. Before the Court are plaintiffs’ Motion
    for Summary Judgment, defendant’s Cross-Motion for Summary Judgment, and
    defendant-intervenors’ Cross-Motion for Summary Judgment.z Upon consideration of
    the pleadings, record, and relevant law, plaintiffs’ motion is DENIED, defendant’s
    motion is GRANTED, and defendant-intervenors’ motion is GRANTED.
    BACKGROUND
    I. Statutory and Regulatory Framework
    This case concerns the leasing of public lands for coal mining. The Mineral
    Leasing Act ("MLA"), 30 U.S.C. § 181 et seq., authorizes the Secretary of the interior to
    lease publicly-owned lands for coal mining through a competitive bidding process. 30
    U.S.C. § 20l(a)(l). Pursuant to the MLA’S implementing regulations, BLM may conduct
    competitive lease sales under one of two processes-competitive leasing based on
    regional leasing levels, or leasing-by-application ("LBA"). See 43 C.F.R. pt. 3420.
    Under the LBA process, which was used in the instant case, an applicant identifies and
    proposes specific tracts of public land for leasing. See 43 C.F.R. subpt. 3425.
    2 See Pls.’ Mot. for Summ. J. and Mem. of P. & A. in Supp. [Dkt. # 38] ("Pls.’ Mem."); Federal
    Def.’s Cross-Mot. for Summ. J. and Combined Mem. of Law in Supp. [Dkt. # 43] ("Def.’s
    Mem."); Def.-Intervenors’ Cross-Mot. for Summ. J. and Mem. of P. & A. in Supp. [Dkt. # 4l]
    ("Def.-Intervenors’ Mem."); see also Reply in Supp. of Pls.’ Mot. for Summ. J. and Response in
    Opp’n to Def.’s and Intervenors’ Cross-Mots. for Summ. J. [Dkt. # 48] ("Pls.’ Reply"); Federal
    Def.’s Reply Brief in Supp. of its Cross-Mot. for Summ. J. [Dkt. # 52] ("Def.’s Reply"); Def.-
    Intervenors’ Reply Mem. in Supp. of their Cross-Mot. for Summ. J. [Dkt. # 5l] ("Def.-
    Intervenors’ Reply").
    procedural injury: an agency’s failure to prepare a statutorily required environmental
    impact statement before taking action with potential adverse consequences to the
    environment."); Pls.’ Mem. at 8. When conducting a standing inquiry for a plaintiff
    claiming a procedural injury, "the courts relax-while not wholly eliminating-the issues
    of imminence and redressability[.]" Ctr. for Law and Ea'uc. v. Dep ’t of Ea’uc., 396 F.3d
    ll52, 1157 (D.C. Cir. 2005); see also Lujan, 504 U.S. at 572 n.7. 7 That is, plaintiffs here
    need not show that the alleged environmental harms resulting from BLM’s authorization
    of the leases are imminent, or about to occur. See ia'. Nor need they show that the
    preparation of an adequate EIS will necessarily protect their rights. See NB ex rel.
    Peacock, 682 F.3d at 86 ("[A] ‘plaintiff who alleges a deprivation of a procedural
    protection to which he is entitled never has to prove that if he had received the procedure
    333
    the substantive result would have been altered. (quoting Sugar Cane Growers Coop. of
    Fla. v. Veneman, 
    289 F.3d 89
    , 94 (D.C. Cir. 20()2))).
    On the other hand, however, the injury in fact and causation requirements of
    standing are not similarly relaxed in the procedural injury context. See Ctr. for Law and
    Ea’uc., 396 F.3d at 1157; Summers v. Earth Island Inst., 
    555 U.S. 488
    , 497 (2009) ("the
    requirement of injury in fact is a hard floor of Article III jurisdiction that cannot be
    removed by statute"); Fla. Aua'ubon Soc j), 94 F.3d at 669 (requiring showing of
    causation "ensure[s] that NEPA cannot foster a procedural right ‘in the air"’; failing to
    7 "[O]ne living adjacent to the site for proposed construction of a federally licensed dam has
    standing to challenge the licensing agency’s failure to prepare an environmental impact
    statement, even though he cannot establish with any certainty that the statement will cause the
    license to be withheld or altered, and even though the dam will not be completed for many
    years." Lujan, 504 U.S. at 572 n.7.
    ll
    "require that a[n] [EIS] plaintiff show that its particularized injury resulted from the
    government action at issue would effectively void the particularized injury requirement").
    Accordingly, to establish standing, plaintiffs here must show that they have a concrete
    interest that is affected by the alleged procedural deprivation. See Fla. Audubon S0c ’y,
    94 F.3d at 664-65; see also Summers, 555 U.S. at 496 ("[D]eprivation of a procedural
    right without some concrete interest that is affected by the deprivation-a procedural
    right in vacuo~is insufficient to create Article IIl standing.").g
    In this case, as in WestAntelope I, plaintiffs allege that the FEIS failed to
    adequately consider two categories of environmental impacts: (l) impacts to local air
    quality in the PRB area resulting from coal mining activity on the BAN and CW lease
    tracts, and (2) impacts on climate change of GHG emissions resulting from both coal
    mining operations on the lease tracts and the subsequent burning of that mined coal to
    generate electricity. Pls.’ Mem. at 22, 30; see WestAntelope 1, 880 F. Supp. 2d at 83.
    And plaintiffs argue that they have standing to challenge the sufficiency of the FEIS’s
    consideration of both categories of impacts. While much ink has been spilled by the
    parties on the extent of plaintiffs’ standing, our Circuit Court’s decision in West Am‘elope
    11 squarely controls this issue and dictates that plaintiffs here do, in fact, have standing to
    argue that the FEIS failed to adequately address both categories of impacts.
    8 A plaintiff may bring a procedural injury claim pursuant to a "citizen suit" provision in the
    applicable statute. See, e.g., Lujan, 504 U.S. at 571-72. In cases involving statutes without such
    provisions, however_such as NEPA_a plaintiff may bring a claim under the APA instead, as
    plaintiffs do here. See Fla. Audubon Soc ’y, 94 F.3d at 665.
    12
    A. Plaintiffs Have Standing to Challenge Impacts of BLM’s Leasing
    Decisi0n on Local Air Quality
    Plaintiffs first allege that BLM’s FEIS failed to adequately address the impacts of
    the leasing decisions on local air quality. To establish standing to raise this claim,
    plaintiffs allege that BLM’s authorization of the BAN and CW leases will cause harm to
    the aesthetic and recreational interests of their members in the PRB area as a result of
    impacts to air quality from coal mining on the lease tracts. Compl. 111 16, 79. I agree-
    and neither defendant nor defendant-intervenors dispute-that plaintiffs have standing on
    this ground, see Def.’s Mem. at 10; Def.-Intervenors’ Mem. at 10, and our Circuit Court’s
    analysis in WestAntelope 11 confirms this conclusion.
    First, plaintiffs have shown injury in fact because their alleged procedural injury-
    the allegedly deficient FEIS-is tied to their members’ concrete aesthetic and
    recreational interests. See Wesz‘Antelope II, 738 F.3d at 305. Environmental interests,
    such as the aesthetic and recreational interests of people who use the areas in question,
    are cognizable interests for standing purposes, and damage to them can constitute injury
    in fact. See Sz``erra Club v. Morton, 
    405 U.S. 727
    , 734 (1972); Friends of the Earth, Inc.
    v. Laia'law Envtl. Servs., Inc., 
    528 U.S. 167
    , 183 (2000) ("environmental plaintiffs
    adequately allege injury in fact when they aver that they use the affected area and are
    persons for whom the aesthetic and recreational values of the area will be lessened by the
    challenged activity" (internal quotation marks and citation omitted)). Here, coal mining
    activity on the two lease tracts will generate ozone precursors and PM]@, and ozone and
    PM]O are air pollutants regulated under the Clean Air Act, 42 U.S.C. § 7401 et seq.,
    13
    through applicable Nationa1 Ambient Air Quality Standards ("NAAQS"). Comp1. 1111 41-
    46; P1s.’ Mem. at 9. Further, plaintiffs have submitted a declaration from a member who
    uses areas near the BAN and CW lease tracts and has concrete plans to return, stating that
    viewing these air pollutants diminishes his aesthetic and recreational enjoyment. See
    Pls.’ Mem. at 9-1(); Decl. of Jeremy Nichols [Dkt. # 38-5], at 1111 5-8, 10-15; see Lujan,
    504 U.S. at 564 (environmenta1 plaintiff must show concrete plans to visit affected area
    in the future in order to show injury in fact). Thus, plaintiffs have shown that some of
    their members will be injured by the increase in pollution generated by coal mining on
    the BAN and CW tracts.
    Next, plaintiffs can show causation because BLM concedes that development of
    the two lease tracts will result in increased emissions of certain air pollutants. AR 1713,
    1684. To show causation in this procedural injury context, plaintiffs must show two
    causal links: one between the allegedly deficient EIS and BLM’s leasing decision, and
    one between that leasing decision and p1aintiffs’ particularized injury. See WestAntelope
    II, 738 F.3d at 306 (citing Fla. Aua’ubon S0c ’y, 94 F.3d at 668). The first link is easily
    found here because plaintiffs need only "show that the procedural step was connected to
    the substantive result," Massachusetts v. EPA, 
    549 U.S. 497
    , 518 (2007) (citation
    omitted), not that but for the alleged procedural deficiency BLM would have reached a
    different substantive result, see West Am‘elope II, 738 F.3d at 306. As to the second link,
    plaintiffs must "demonstrate a causal connection between the agency action and the
    alleged injury," City ofDania Beach, Fla. v. FAA, 
    485 F.3d 1181
    , 1186 (D.C. Cir. 2007),
    and plaintiffs have done so here "because the local pollution that causes their members’
    14
    aesthetic and recreational injuries follows inexorably from the decision to authorize
    leasing" on the BAN and CW tracts. See West Antelope II, 738 F.3d at 306.
    Finally, plaintiffs meet the low threshold for showing redressability in a
    procedural injury action because all that is required is "some possibility that the requested
    relief will prompt the injury-causing party to reconsider the decision that allegedly
    harmed the litigant." Massachusetts v. EPA, 549 U.S. at 518; see also West Antelope II,
    738 F.3d at 306 ("Vacatur of the BLM order would redress the Appellants’ members’
    injuries because, if the BLM is required to adequately consider each environmental
    concem, it could change its mind about authorizing the lease offering."). Therefore,
    plaintiffs have standing to challenge the alleged deficiencies in the FEIS’s consideration
    of local air quality impacts based on their members’ aesthetic and recreational injuries
    caused by local pollution in areas near the BAN and CW lease tracts. See West Antelope
    II, 738 F.3d a_t 306.
    B. Plaintiffs Have Standing to Challenge Impacts of BLM’s Leasing
    Decision on Climate Change
    Plaintiffs also allege that BLM’s FEIS failed to adequately address the impacts of
    the leasing decisions on climate change. To establish standing to raise this claim,
    plaintiffs allege that BLM’s authorization of the BAN and CW leases will cause harm to
    the aesthetic, recreational, and economic interests of their members due to climate
    change. According to plaintiffs, GHG emissions from both mining operations and the
    future combustion of the mined coal to generate electricity will "exacerbate climate
    change" by contributing to sea level rise in New Jersey and Florida and deleterious
    15
    ecosystem changes in the Western United States. Pls.’ Mem. at l2-l7; Decl. of Michael
    C. MacCracken [Dkt. #38-4], at 1111 13, 23, 37, 38, 4l.
    Plaintiffs advance two arguments to establish their standing with respect to BLM’s
    consideration of climate change impacts. First, relying on our Circuit Court’s prior
    decisions in Centerfor Biologz``cal Dz``versily v. U.S. Department of the Im‘erior, 
    563 F.3d 466
     (D.C. Cir. 2009) and Sz'erra Club v. Adams, 578 F.Zd 389 (D.C. Cir. 1978), they
    argue for what might be called a form of "derivative" standing. That is, because
    plaintiffs undisputedly have standing to challenge the adequacy of the FEIS with regard
    to its analysis of local air quality impacts (as discussed above), they contend that, by
    extension, they also have standing to challenge any other alleged inadequacies in the
    FEIS_including its analysis of climate change impacts-because all of the alleged
    inadequacies are part of the same NEPA claim. See Pls.’ Mem. at ll-l2; Pls.’ Reply at
    2-4. Second, relying in large part on the declaration of climate scientist Dr. Michael
    MacCracken, plaintiffs argue that their alleged climate change related injuries provide an
    independent basis for standing under the traditional three-part standing inquiry. Pls.’
    Mem. at 12-20. Fortunately, however, I need not navigate the troubled waters of the
    "derivative" standing issue, nor need I decide whether plaintiffs have established a
    separate injury in fact caused by climate change, because our Circuit Court’s discussion
    of this issue in Wesz‘ Antelope 11 controls my analysis and makes clear that plaintiffs here
    do, in fact, have standing to challenge the FEIS’s consideration of climate change
    impacts on a procedural injury theory.
    16
    In West Antelope II, the same conservation organizations that are plaintiffs in this
    case appealed the District Court’s grant of summary judgment in favor of def``endants,
    including its ruling that the plaintiffs did not have standing to argue that BLM’s FEIS
    failed to adequately address the impact of the leasing decision on global climate change.
    On appeal, our Circuit Court agreed that the appellant conservation organizations did not
    have standing under the three-part standing inquiry based on the effects of global climate
    change. WestAntelope II, 738 F.?)d at 307. Notwithstanding that conclusion, however,
    the Court went on to hold that appellants’ injury in fact resulting from local pollution
    sufficed to give them standing to challenge each of the alleged deficiencies in the FEIS,
    including the FEIS’s allegedly inadequate analysis of the impacts of the leasing decisions
    on global climate change, "because each [alleged inadequacy] constitutes a procedural
    injury connected to their members’ recreational and aesthetic injuries: Their members’
    injuries are caused by the allegedly unlawful ROD and would be redressed by vacatur of
    the ROD on the basis of any of the procedural defects identified in the FEIS." Ia’. at 308;
    see also id. at 307 ("The Appellants’ aesthetic injury follows from an inadequate FEIS
    whether or not the inadequacy concerns the same environmental issue that causes their
    injury. If we vacate the BLM order, their injury will be redressed regardless whether the
    FEIS’s specific flaw relates to local or global environmental impacts; either way, the
    remedy is ‘limited to the inadequacy’~here, a deficient FEIS_‘that produced the injury
    in fact that the plaintiff has established."’ (citation omitted)).9
    9 In reaching this holding, our Circuit Court declined to rely on its prior decision in Adarns-in
    which it held that where plaintiffs had established standing to challenge the adequacy of an EIS
    17
    So too here. Plaintiffs in the instant case, just like appellants in Wesl Antelope II,
    have established standing on a procedural injury theory to challenge BLM’s analysis of
    local air quality impacts, based on the harm to plaintiffs’ members’ concrete aesthetic and
    recreational interests caused by local pollution that follows from the leasing decisions.
    See ia’. at 306. And since our Circuit Court expressly declined to adopt a requirement
    "that the specific type of pollution causing the Appellants’ aesthetic injury-here, local
    pollution-be the same type that [plaintiffs allege] was inadequately considered in the
    FEIS," _z'a’. at 307, then plaintiffs here also "may challenge each of the alleged
    inadequacies in the FEIS" because "[t]heir members’ injuries are caused by the allegedly
    unlawful ROD and would be redressed by vacatur of the ROD on the basis of any of the
    procedural defects identified in the FEIS," see id. at 308. Accordingly, plaintiffs also
    have standing to challenge the alleged deficiencies in BLM’s FElS relating to its
    consideration of climate change impacts,
    II. The Merits
    In assessing the merits of plaintiffs’ NEPA and FLPMA claims, this Court must
    apply the APA’s arbitrary and capricious standard of review. WestAntelope II, 738 F.3d
    at 308; 5 U.S.C. § 706(2)(A). In the specific context of an agency’s preparation of an
    EIS pursuant to NEPA, our Circuit Court has described this deferential standard as a
    "rule of reason" standard. See Citizens Against Burlz``ngton, Inc. v. Busey, 938 F.2d l90,
    on at least one ground, they could also raise other inadequacies in the EIS based on "the ‘public
    interest’ in requiring government officials to discharge faithfully their statutory duties under
    NEPA," Aa’ams, 578 F.2d at 392_and expressed "no opinion" on the continuing validity of the
    "public interest" rationale in light of intervening Supreme Court precedent. West Antelope II,
    738 F.3d at 307-08.
    18
    195~96 (D.C. Cir. l99l). If the agency’s decision is "fully informed and well-considered,
    it is entitled to judicial deference and a reviewing court should not substitute its own
    policy judgment." Transmission Access P0licy Stua’y Grp. v. FERC, 
    225 F.3d 667
    , 736
    (D.C. Cir. 2000) (internal quotation marks and citation omitted). Put differently, the
    Court’s role "is not to ‘flyspeck an agency’s environmental analysis, looking for any
    deficiency no matter how minor."’ West Antelope II, 738 F.3d at 308 (quoting Nevada v.
    Dep ’t of Energy, 
    457 F.3d 78
    , 93 (D.C. Cir. 2006)). Instead, it is "simply to ensure that
    the agency has adequately considered and disclosed the environmental impact of its
    actions and that its decision is not arbitrary or capricious," ia’. (citations and quotation
    marks omitted)_that is, to ensure that the agency took the required "‘hard look’ at the
    environmental effects of its proposed action," Theoa’ore Roosevelt Conservation P ’shz'p v.
    Sczlczzar, 
    661 F.3d 66
    , 75 (D.C.Cir.201l). See also New York v. NRC, 681 F.3d 47l, 476
    (D.C. Cir. 2012) ("NEPA is an ‘essentially procedural’ statute intended to ensure ‘fully
    informed and well-considered’ decisionmaking, but not necessarily the best decision."
    (quoting Vt. Yankee Nuclear Power Corp. v. Natural Res. Def Council, Inc., 435 U.S.
    5l9, 558 (1978))).
    Plaintiffs in this case have raised several challenges to the sufficiency of the FEIS,
    but plaintiffs’ complaint, at bottom, is that BLM did not analyze certain issues in the
    manner or level of detail plaintiffs would have preferred, and therefore this Court should
    vacate the FEIS. Unfortunately for plaintiffs, the applicable standard of review neither
    contemplates nor countenances that type of judicial second-guessing of agency
    decisionmaking, and therefore I find that plaintiffs’ claims are without merit.
    19
    A. Plaintiffs’ NEPA Claims Are Without Merit
    Under NEPA, an EIS must examine the proposed project’s direct, indirect, and
    cumulative impacts, as well as alternatives to the proposed project. 42 U.S.C. §
    4332(2)(€); 40 C.F.R. §§ 1502.16, 1508.25. Direct impacts "are caused by the action
    and occur at the same time and place," 40 C.F.R. § l508.8(a), whereas indirect impacts
    "are caused by the action and are later in time or farther removed in distance, but are still
    reasonably foreseeable," 40 C.F.R. § l508.8(b). And in doing a cumulative impact
    analysis, the agency "must assess the impact the proposed project will have in
    conjunction with other projects in the same and surrounding areas . . . and must include
    past, present, and reasonably foreseeable future actions of any agency or person."
    Theodore Roosevelt Conservatz``on P’shlp v. Salazar, 
    616 F.3d 497
    , 503 (D.C. Cir. 2010);
    40 C.F.R. § 1508.7.
    In this case, plaintiffs allege that the FElS prepared by BLM violated NEPA for
    three reasons. First, they claim that BLM failed to take the required "hard look" at the
    local air quality impacts from coal mining on the leases. Compl. 1111 75-76, 79-82; Pls.’
    Mem. at 22-30. Second, they claim that BLM failed to take a "hard look" at the climate
    change impacts of GHG emissions, including COZ, resulting from lease development~
    i.e. both the mining of the coal itself, and the eventual combustion of the mined coal.
    Compl. 1111 75-77; Pls.’ Mem. at 30-39. And third, plaintiffs claim that BLM failed to
    consider "reasonable alternatives" to prevent or minimize GHG emissions, to include
    mitigation measures. Compl. 111 78-82; Pls.’ Mem. at 40-42. Addressing each in turn, l
    20
    Before acting on a lease app1ication, BLM must conduct an environmental review
    pursuant to NEPA. Under NEPA, all federal agencies are required to prepare an
    Environmental Impact Statement ("EIS") for any proposed "major Federal actions
    significantly affecting the quality of the human environment." 42 U.S.C. § 4332(2)(€);
    40 C.F.R. § 1502.3; see also Grand Canyon Trust v. FAA, 
    290 F.3d 339
    , 340 (D.C. Cir.
    2002). NEPA’s requirement to prepare an EIS serves two purposes: it ensures that the
    agency "will have available, and will carefully consider, detailed information concerning
    significant environmental impacts" before making a decision on the proposed action, and
    it "guarantees that the relevant information will be made available to the larger audience
    that may also play a role in both the decisionmaking process and the implementation of
    that decision." Robertson v. Methow Valley Citizens Councz'l, 
    490 U.S. 332
    , 349 (l989).
    The EIS must analyze the direct, indirect, and cumulative impacts of the proposed action
    on the environment, 40 C.F.R. §§ l502.16, 1508.7, as well as "alternatives to the
    proposed action," 42 U.S.C. § 4332(2)(C)(iii). To satisfy NEPA, the agency must take a
    "hard look" at the environmental consequences of a proposed action before proceeding,
    but the statute does "not require agencies to elevate environmental concerns over other
    appropriate considerations." Balt. Gas & Elec. Co. v. Natural Res. Def Council, Inc.,
    
    462 U.S. 87
    , 97 (1983). NEPA thus mandates a process, not a particular substantive
    result. See Robertson, 490 U.S. at 350.
    BLM is also subject to the statutory regime of FLPMA. Under that statute, BLM
    is responsible for managing the public lands. 43 U.S.C. § 1732. For a given area, BLM
    first develops a "land use plan," or Resource Management Plan ("RMP"), which sets
    3
    conclude for the following reasons that BLM did, indeed, consider all of the relevant
    factors and did not commit a clear error of judgment.
    1. BLM Adequately Discussed and Analyzed Impacts on L0cal Air
    Quality
    Plaintiffs first claim that BLM failed to take the required "hard look" at the local
    air quality impacts from coal mining on the leases in two respects-the direct and
    cumulative impacts to air quality of ozone emissions from coal mining, and the direct
    impacts of particulate matter (PM]@) emissions. Compl. 111 75-76, 79-82; Pls.’ Mem. at
    22-30.
    a) BLM Adequately Discussed and Analyzed Ozone Impacts
    on Air Quality
    Plaintiffs argue that BLM inadequately discussed and analyzed the direct and
    cumulative impacts of ozone emissions on local air quality. Compl. ll 58; Pls.’ Mem. at
    22-25. Plaintiffs emphasize that the FElS did not include a specific analysis of the direct
    impacts of ozone that will result from lease development, and they claim that the agency
    "simply provided a table of ozone levels from 2001 through 2008 and did no more." Pls.’
    Mem. at 23. Further, in an effort to steer this Court away from reaching the same
    conclusion as my colleague did in West Antelope 1 that BLM’s ozone analysis complied
    with NEPA, plaintiffs argue that the court’s discussion of ozone in that case was flawed
    because its reliance on BLM’s finding that the area was in "attainment" for ozone
    NAAQS improperly conflated the agency’s obligation to analyze the "affected
    environment" with its separate obligation to analyze the "environmental consequences"
    21
    of the proposed action. Pls.’ Mem. at 23. Compare 40 C.F.R. § 1502.15 (affected
    environment), with 40 C.F.R. § 1502.16 (environmental consequences). Plaintiffs’
    arguments, however, are not only unpersuasive, but they fail to withstand scrutiny under
    our Circuit Court’s analysis of this very issue of ozone impacts in its West Antelope 11
    opinion.
    In the FEIS for the South Gillette area lease tracts, including the BAN and CW
    tracts, BLM discussed ozone in multiple places, see AR l506, 1682-84, 1713-18; Def.’s
    Mot at 22-23, and the agency’s analysis demonstrates the required "hard look." First, the
    FEIS explained that ground level ozone ("03") is a pollutant formed when nitrogen
    oxides ("NOX") emissions and volatile organic compounds react with sunlight. AR l684.
    ln other words, mining operations produce NOX emissions but not ozone itself, see AR
    l7l6, and thus BLM noted that it was including ozone in its discussion of NOX emissions
    because NOX is one of the main precursors to the formation of ground-level ozone, AR
    l7l3. The FEIS then identified background concentrations of ozone at 132 p/m3 for past
    years 2005-2008 and found that they were within the "attainment" status of 147 u/m3 set
    by the applicable NAAQS. AR 1683.]0 Next, the FEIS looked to the future and, based
    on long-term modeling, estimated that "currently projected mine activities will be in
    compliance with the annual NOX [air quality standards]" for the life spans of both the
    Belle Ayr and Caballo mines. AR 1717-18; Def.’s Mem. at 23. Moreover, BLM
    identified and discussed the environmental consequences of NOX emissions, as well as
    10 While the EPA has established NAAQS for ozone and nitrogen dioxide ("NO;"), a type of
    NOX, there is no NAAQS standard for NOX. See West Antelope II, 738 F.3d at 31 l.
    22
    the health risks associated with the inhalation of both ground-level ozone and NOX. AR
    1719-20.
    Not surprisingly, plaintiffs take issue with this mode of analysis, arguing that
    BLM’s discussion of the ozone precursor, NOX, was inadequate because NOX "cannot
    serve as a proxy for ozone concentration" since there are no established NAAQS for NOX
    and it is measured in different units. Pls.’ Mem. at 24. But plaintiffs’ argument that
    "analysis of NOX emissions is not equivalent to an analysis of ozone emissions," Pls.’
    Mem. at 24, falls well short of showing that the agency failed to consider relevant factors
    and make appropriate disclosures. Indeed, plaintiffs’ argument on this point is
    specifically foreclosed by our Circuit Court’s decision in West Antelope II, which
    affirmed the adequacy of BLM’s ozone analysis for nearby lease tracts using precisely
    the same method of analysis. See WestAntelope 1I, 738 F.3d at 311-12 (confirming "the
    appropriateness of the BLM’S use of NOX as a proxy for ozone" and observing, "[i]t may
    have been possible or even prudent for the BLM to separately model future ozone levels
    but we think that, given the limitations on such modeling and the critical role NOX plays
    in ozone formation, the BLM’s projections and extensive discussion of NOX and NOZ
    emissions suffice.").
    Indeed, I think BLM’s decision to address ozone in its analysis of NOX emissions,
    rather than devote an exclusive section of the FEIS to ozone, was particularly reasonable
    in light of the fact that mining activities emit NOX, not ozone itself-which is only
    formed subsequently when NOX reacts with other compounds in the presence of sunlight,
    making ozone forecasting imprecise. See Def.’s Mem. at 24. Though plaintiffs suggest
    23
    that BLM could have considered ozone modeling performed by the Westem Regional Air
    Partnership, see Pls.’ Reply at 19-20, such a complaint is a far cry from showing that the
    agency failed to consider ozone at all, and under the "rule of reason" standard, such
    detailed second-guessing of an agency’s choices is not the proper role of this Court. See
    West Antelope I, 880 F. Supp. 2d at 88 ("‘It is of course always possible to explore a
    subject more deeply and to discuss it more thoroughly,’ but ‘[t]he line-drawing decisions
    397
    necessitated by this fact of life are vested in the agencies, not the courts. (quoting Coal.
    on Sensible Transp., Inc. v. Dole, 826 F.2d 6(), 66 (D.C.Cir.l987))).
    In sum, BLM made the reasonable choice to address ozone in its NOX discussions
    because NOX can serve as a "proxy" for ozone, see AR 1506, 1682, 1684, and it is hard
    to see why further analysis would be necessary given that the FEIS demonstrated that
    past ozone concentrations were within the "attainment" status of the applicable NAAQS
    and modeling projected future compliance with air quality standards. Much like Judge
    Kollar-Kotelly in West Antelope 1 (and as affirmed by our Circuit Court), I see no reason
    to require BLM to perform a more detailed analysis of ozone.
    b) BLM Adequately Discussed and Analyzed Particulate
    Matter Impacts on Air Quality
    Next, plaintiffs contend that BLM also failed to take the requisite "hard look" at
    the direct air quality impacts of PM\O emissions from development of the BAN and CW
    tracts. Compl. 11 79; Pls.’ Mem. at 26-30. Plaintiffs emphasize that the FEIS does not
    consider whether the PM]O emission levels from mining activities would approach or
    24
    exceed the 24-hour NAAQS standard, or the extent to which these emissions would
    degrade short-term air quality. Id.
    Again, however, the record reflects that BLM performed adequate analysis of
    PMlo direct impacts on air quality. In the FEIS, the agency discussed the sources of PM\O
    pollution, the applicable air quality standards (both 24-hour and annual), natural
    background concentrations of PMlo in the region, and the health impacts of PM,@. AR
    1681-1692; Def.’s Reply at 9. In particular, BLM examined historic concentrations of
    PMlo in the area and noted that both 24-hour and annual concentrations were below
    applicable standards and thus in "attainment" status; found that no exceedances of either
    the 24-hour or annual standards had occurred at the Belle Ayr or Caballo mines; and
    disclosed exceedances that had occurred at other mines outside the South Gillette area in
    the years 2001-2007. Def.’s Mem. at 25-26; AR 1500-0l, 1685, 1691-92, 2290-91.
    Regarding future estimates, BLM explained that the rate of mining operations at the BAN
    and CW tracts would be similar to those at the existing mines, AR l685, and, using long-
    term modeling based on that assumption, predicted that no exceedances of the annual
    PMlo standard would occur at either the BAN or CW tracts. Def.’s Mem. at 26; AR
    15()0-01, 1691-92, 2290-92. Based on this past data and future estimates, BLM
    concluded that PMm emissions resulting from the two leases could be expected to remain
    within applicable NAAQS standards. AR l693, 1702.
    The crux of plaintiffs’ complaint, then, is that BLM used annual modeling to
    predict short-term (24-hour) levels of PM;O, and therefore BLM’s analysis adequately
    considered cumulative impacts but not direct (i.e. 24-hour) impacts. Pls.’ Mem. at 27.
    25
    But the agency candidly disclosed that no appropriate model exists to accurately predict
    24-hour impacts, and thus it instead relied on available modeling data showing
    compliance with applicable air quality standards on an annual basis. AR l69l; Def.’s
    Reply at 9-10.]' In light of past data, expected mining activity on the two leases, and
    available modeling estimates, it was reasonable for BLM to conclude that PM,O
    concentrations could be expected not to exceed 24-hour or annual air quality standards.
    Plaintiffs essentially demand a better, more detailed model for 24-hour PM]O emissions,
    but this is a far cry from showing that BLM utterly failed to consider a "relevant factor."
    See Moz‘or Vehicle Mfrs. Ass ’rz, 463 U.S. at 43. Accordingly, BLM’s analysis complies
    with the "rule of reason" in light of the information available to the agency, and is
    sufficiently thorough to comply with NEPA.
    2. BLM Adequately Discussed and Analyzed Climate Change
    Impacts
    Plaintiffs next argue that BLM failed to take a "hard look" at the climate change
    impacts of GHG emissions, including COZ, resulting from lease development_i.e. both
    the mining of the coal itself, and the eventual combustion of the mined coal. Compl. 111
    75-77; Pls.’ Mem. at 30-39. Specifically, plaintiffs allege that BLM’s analysis was
    inadequate in three ways. First, they contend that BLM failed to analyze direct impacts
    to climate from COZ emissions from coal mining on the two leases. Second, they contend
    that BLM failed to analyze cumulative impacts to climate resulting from coal mining on
    ll In the FEIS, BLM disclosed that short-term, 24-hour modeling did predict some exceedances
    for the larger PRB area, but also noted that such short-term modeling is not reliable because it
    over-predicts 24-hour concentrations of PM]@. AR 1966, 1691-92.
    26
    the two leases in combination with coal mining on ten other federal leases in the PRB.
    And third, they contend that BLM failed to analyze the indirect impacts to climate
    resulting from the combustion of coal mined from the two leases in combination with that
    mined from the ten other federal leases in the PRB. See Pls.’ Mem. at 30. I disagree and
    find that BLM’s analysis adequately considered climate change and the reasonably
    foreseeable impacts of its leasing decisions; the level of specificity plaintiffs would prefer
    in BLM’s analysis is neither possible based on current science, nor required by law.
    BLM’s FEIS examined climate change in two places, Chapter 3 ("Affected
    Environment and Environmental Consequences") and Chapter 4 ("Cumulative
    Environmental Consequences"). BLM discussed the role of GHG emissions in climate
    change and the greenhouse effect. AR l920. Moreover, BLM acknowledged that GHGs
    will be released during coal mining operations, provided annual data on GHG emissions
    at the South Gillette area mines in 2007, and then estimated expected annual GHG
    emissions that would likely result from coal mining operations at those mines with the
    new lease tracts. AR 1922. Specifically, BLM estimated that coal mining at the South
    Gillette area mines, including the four proposed leases (which include the two leases
    challenged here) would collectively emit l.l82 million metric tons of COZ annually,
    representing 1.7 percent of the projected 2020 state-wide emissions for Wyoming, see
    AR l922; Pls.’ Mem. at 32, and that such South Gillette area coal mining, in combination
    with coal mining at other PRB mines and with other pending leases, would emit 4.229
    million metric tons annually, see AR 2042. The EIS then acknowledged that although
    "use of the coal after it is mined is . . . not determined at the time of leasing . . . almost all
    27
    of the coal that is currently being mined in the Wyoming PRB is being used by coal-fired
    power plants to generate electricity," AR 2032, and thus went on to discuss emissions and
    by-products of coal combustion, AR 2046, as well as estimate the COZ emissions
    resulting from coal combustion from all PRB mines for the year 2006 at 7l6.9 million
    metric tons, or 33.6 percent of all estimated COZ emissions from coal combustion in the
    United States. AR 2041. Finally, BLM discussed studies that recognized global
    warming and potential impacts of climate change in the Western United States, AR 2034-
    38, but specifically noted that "there are uncertainties regarding how climate change may
    affect different regions," AR 2()36.
    Plaintiffs take issue with this level of detail in BLM’s analysis, arguing that the
    FEIS failed to sufficiently analyze the climate impacts of GHG emissions from mining
    operations on the leases and subsequent combustion of the mined coal. See Pls.’ Mem. at
    30-39. In plaintiffs’ view, "estimates [of GHG emissions] alone without an analysis of
    the impacts to climate resulting from these emission levels do not comply with NEPA’s
    hard look requirement." Pls.’ Mem. at 32. But it is precisely because current climate
    science is uncertain (and does not allow for specific linkage between particular GHG
    emissions and particular climate impacts) that evaluating GHG emissions as a percentage
    of state-wide and nation-wide emissions, as BLM did here, is a permissible and adequate
    approach. See West Antelope II, 738 F.3d at 309; see also Bczrnes v. U.S. Dep ’t of
    Transp., 655 F.3d ll24, 1139 (9th Cir. 201 l) (because "the effect of [GHGs] on climate
    is a global problem[,] a discussion in terms of percentages is therefore adequate for
    [GHG] effects," and the agency’s analysis of GHGs need not be specific to the locale).
    28
    Indeed, as our Circuit Court held in West Antelope II, "[b]ecause current science does not
    allow for the specificity demanded by the Appellants, the BLM was not required to
    identify specific effects on the climate in order to prepare an adequate EIS." West
    Antelope II, 738 F.3d at 309; see also z'a’. (citing draft guidance from the Council on
    Environmental Quality that notes "it is not currently useful for the NEPA analysis to
    attempt to link specific climatological changes, or the environmental impacts thereof, to
    the particular project or emissions, as such direct linkage is difficult to isolate and to
    understand. The estimated level of GHG emissions can serve as a reasonable proxy for
    assessing potential climate change impacts . . ."). Accordingly, the FEIS’s discussion of
    climate impacts was adequate here.
    3. BLM Considered a Reasonable Range of Alternatives
    In addition to requiring a "hard look" at environmental impacts, NEPA also
    requires federal agencies to include in an EIS "a detailed statement. .. [of] alternatives to
    the proposed action. 42 U.S.C. § 4332(2)(C)(iii); Transmissz``on Access Policy Stua’y
    Grp., 225 F.3d at 735. The agency "bears the responsibility for deciding which
    alternatives to consider in an [EIS]," and when reviewing the agency’s consideration of
    alternatives, this Court must, again, apply the "rule of reason" standard. Citz'zens Against
    Burlz``nglon, ]nc., 938 F.2d at 195; z'a’. ("this rule of reason governs both which alternatives
    the agency must- discuss, and the extent to which it must discuss them" (internal quotation
    marks and citation omitted)). Here, plaintiffs urge this Court to find BLM’s FEIS
    deficient because it failed to consider the alternatives that plaintiffs proposed to address
    GHG emissions and climate change_requiring emissions capture and sequestration,
    29
    more efficient mine hauling trucks, and carbon offsets for the leases. Pls.’ Mem. at 40-
    41; AR 4255-56. Unfortunately for plaintiffs, however, I find that under the "rule of
    reason" standard BLM considered a reasonable range alternatives and was not required to
    specifically consider plaintiffs’ proposed measures.
    NEPA requires only that an agency consider alternatives that are feasible or
    reasonable. Citz``zens Against Burlington, Inc., 938 F.Zd at 195 (citing 40 C.F.R. §§
    l502.l4(a)-(c), l508.25(b)(2)). The agency is responsible for deciding which alternatives
    to consider in an EIS, and its selection of them, as well as the extent to which it discusses
    them, need only be reasonable in relation to the objective or purpose of the planned
    action. See id. at 195-96. ln other words, an agency’s consideration of alternatives is not
    legally inadequate "simply because the agency failed to include every altemative device
    and thought conceivable by the mind of man." Vt. Yankee, 435 U.S. at 55 l.
    In this case, BLM prepared an EIS in response to LBA applications it received. In
    that context, BLM’s objective and purpose was to act upon the applications. See
    Theodore Roosevelt Conservatz'on P ’shzp, 661 F.3d at 73-74. Its options were necessarily
    limited to: (l) holding competitive sealed-bid lease sales for the tracts as applied for, (2)
    holding such sales for modified tracts, or (3) rejecting the applications and not offering
    the tracts for lease. AR l568; see also 43 C.F.R. §§ 3425.l-9, 3425.1-8. And in making
    a decision on the applications, BLM had to account for "the needs and goals of the parties
    involved in the application" as well as "the views of Congress . . . [as expressed] in the
    agency’s statutory authorization to act, as well as in other congressional directives."
    Citz``zens Agaz``nst Burlz``ngton, Inc., 938 F.2d at l96. Here, BLM considered the objectives
    3()
    forth objectives for managing resources on those lands. Ia’. § l712(a); Def.’s Mem. at 4.
    BLM’s land use planning must "observe the principles of multiple use and sustained
    yield." 43 U.S.C. § 1712(0)(1); see also id. § 1732(a). Multiple use means "the
    management of the public lands and their various resource values so that they are utilized
    in the combination that will best meet the present and future needs of the American
    people," and "a combination of balanced and diverse resource uses that takes into account
    the long-term needs of future generations for renewable and nonrenewable resources,
    including, but not limited to, recreation, . . . minerals, . . . and natural scenic, scientific
    and historical values . . ." Ia'. § l702(c). Sustained yield means "achievement and
    maintenance in perpetuity of a high-level annual or regular periodic output of the various
    renewable resources of the public lands consistent with multiple use." Ia’. § l702(h).
    Further, BLM’s land use plans must "provide for compliance with applicable pollution
    control laws, including State and Federal air, water, noise, or other pollution standards or
    implementation plans." Ia’. § l7l2(c)(8). Speciflc resource management actions by
    BLM, such as leasing the coal tracts at issue in this case, must conform to the applicable
    RMP. 43 C.F.R. § l6lO.5-3(a).
    II. Factual and Procedural Background
    The Powder River Basin ("PRB"), located in Wyoming and Montana, is the single
    largest source of coal in the United States, se``e Administrative Record ("AR") 9378,
    l l 148, and over 90 percent of its coal deposits are owned by the federal government, AR
    93 89. Plaintiffs WildEarth Guardians, Defenders of Wildlife, and the Sierra Club, are
    of the applicants to secure "access to a continuing supply of low sulfur compliance coal
    which would be mined and sold to power plants for the purpose of electric power
    generation." AR 1569. The agency also considered its own role of administering the
    federal coal leasing program under the MLA, which "encourages the development of
    domestic coal reserves and reduction of the U.S. dependence on foreign sources of
    energy," as well as considered the national goals to "add energy supplies from diverse
    sources" per the National Energy Policy, "meet the nation’s future energy needs" by
    continued coal extraction, and help "provide a stable supply of power to meet increasing
    demand without a potentially significant increase in power costs." AR 1568-70.
    In light of these factors, BLM’s consideration of altematives in the FEIS,
    including a "No Action" option, under which the tracts would not be leased, AR 1580-
    1622, was sufficient under the "rule of reason" standard. First, BLM was not required to
    consider plaintiffs’ proposals simply because they raised them in public comments on the
    FEIS. Put simply, an agency need not adjust course for every comment received at any
    stage in the process of taking an action, especially where, as here, those comments were
    submitted late in the proceedings at the FEIS stage. See Def.’s Mem. at 31-32; West
    Antelope II, 738 F.3d at 310-l l (rejecting plaintiffs’ argument that BLM failed to analyze
    a reasonable range of alternatives to address GHG emissions and climate change when
    BLM did not consider a list of alternatives proposed by plaintiffs, noting that plaintiffs’
    submission of such alternatives at the FEIS stage (rather than the scoping or draft EIS
    stage) was "sandbagging," and "the last-ditch, kitchen-sink nature of WildEarth’s
    suggestions bears on the extent to which the BLM was required to address them"); see
    31
    also Vt. Yankee, 435 U.S. at 553-54 ("administrative proceedings should not be a game or
    a forum to engage in unjustified obstructionism . . ."). To the contrary, the agency is
    responsible for deciding which alternatives to consider in an EIS. Citz``zens Against
    Burlington, Inc., 938 F.Zd at 195-96.
    Second, and more importantly, BLM considered a full range of alternatives,
    including an option not to lease the tracts at all, and in doing so evaluated the potential
    environmental impacts of each. Plaintiffs’ specific proposals about measures to reduce
    GHG emissions once mining of the tracts commences, therefore, do not represent some
    broad category of "reasonable but unexamined alternatives" the FElS should have
    addressed. See Friends of Soulheast ’s Future v. Morrison, 
    153 F.3d 1059
    , 1065 (9th Cir.
    1998). Instead, they are more aptly categorized as mitigation measures relevant to the
    later mining and combustion of coal and associated permitting by other agencies, rather
    than to the leasing itself. See WestAntelope II, 738 F.3d at 31 l. Indeed, NEPA does not
    require BLM to include in its FEIS "a detailed explanation of specific measures which
    will be employed to mitigate the adverse impacts of a proposed action." Robertson, 490
    U.S. at 353 (internal quotation marks and citation omitted). In sum, l find that BLM’s
    consideration of alternatives was adequate under the "rule of reason."
    32
    B. Plaintiffs’ FLPMA Claims Are With0ut Merit
    Finally, plaintiffs claim that BLM violated FLPMA by failing to ensure that its
    leasing decisions would result in compliance with federal air quality standards. See
    Compl. 1111 83-92. However, plaintiffs point to no legal authority supporting their
    assertion of a legal "duty" BLM owes to ensure compliance, and therefore these claims
    must also fail.
    FLPMA requires the Secretary of the Interior to "manage the public lands . . . in
    accordance with the land use plans," 43 U.S.C. § 1732(a), and land use plans must
    "provide for compliance with applicable pollution control laws, including State and
    Federal air, water, noise, or other pollution standards or implementation plans," z'd. §
    1712(0)(8). Pointing to the Buffalo RMP, the land use plan that covers the PRB,
    plaintiffs argue that BLM has violated its legal duties under FLPMA by (l) failing to do
    "the requisite analysis" to determine whether its lease authorizations will comply with
    ozone NAAQS, and (2) authorizing the leases while "knowing" that PM,O emissions from
    mining the lease tracts "will result in exceedances of the 24-hour PM]O NAAQS." Pls.’
    Mem. at 43-44; Compl. 111 89, 91. I disagree.
    Not only are these claims "duplicative" of plaintiffs’ NEPA claims, see West
    Amelope 1, 880 F. Supp. 2d at 94, but plaintiffs supply no legal authority for their
    assertion that BLM has a "legal obligation to impose concrete emission-reduction
    measures" on the leases, Pls.’ Mem. at 44, or a "substantive duty under FLPMA to follow
    the dictates of the RMP, rather than passing its responsibility on" to the lessee and the
    Wyoming state regulatory body, P1s.’ Mem. at 45. To the contrary-and as my
    33
    colleague noted in West Antelope 1 regarding an identical claim by these plaintiffs-
    "neither the FLPMA nor the implementing regulations required BLM to analyze whether
    and to what degree the leasing of the . . . tracts would comply with national ozone, PMlo,
    and NO; standards." West Antelope I at 94. Instead, applicable regulations require only
    that BLM draft land use authorizations, including leases, such that they "[r]equire
    compliance with air and water quality standards established pursuant to applicable
    Federal or State law. 43 C.F.R. § 2920.7(b)(3). BLM has done exactly that by including
    clauses in the BAN and CW leases requiring compliance with air and water quality
    standards. AR 2l49. According1y, plaintiffs’ FLPMA claims are without merit.
    CONCLUSION
    Thus, for all of the foregoing reasons, the Court DENIES plaintiffs’ Motion for
    Summary Judgment, GRANTS defendant’s Cross-Motion for Summary Judgment, and
    GRANTS defendant-intervenors’ Cross-Motion for Summary Judgment. An Order
    consistent with this decision accompanies this Memorandum Opinion.
    RIC `` ON
    United States District Judge
    34
    non-profit conservation organizations with members located across the nation, including
    members who live, work, and recreate in the PRB. Compl. [Dkt. # 1] 111 13-15.
    In 2004 and 2006, coal mining companies operating existing mines in the PRB
    applied to defendant BLM under the LBA regulations to lease the two coal tracts at issue
    in this case_the Belle Ayr North ("BAN") and Caballo West ("CW") tracts. On July 6,
    2004, RAG Coal West, Inc. (predecessor to defendant-intervenor Alpha Wyoming Land
    Company, LLC) filed an application to lease the BAN tract, which includes an estimated
    221.7 million tons of minable coal. AR 3, 14. On March l5, 2006, Caballo Coal
    Company (predecessor to BTU Westem Resources, Ino., which in turn is predecessor to
    defendant-intervenor Peabody Energy Company) applied to lease the CW tract, which
    includes an estimated 130.2 million tons of minable coal. AR 49, 58.
    Pursuant to its obligations under NEPA, BLM published in the Federal Register a
    notice of its intent to prepare an EIS analyzing four proposed coal leases in the South
    Gillette area, including the BAN and CW tracts. See 72 Fed. Reg. 14,828 (Mar. 29,
    2007). After publishing a draft EIS in October 2008 and accepting public comments,
    BLM prepared a final EIS ("FEIS") in August 2009 that spanned more than 600 pages.
    AR 3386, 2299-2489; see also 74 Fed. Reg. 41,430 (Aug. l7, 2009). The FEIS analyzed
    three alternatives for the BAN and CW tracts: (l) competitive lease sales of the two tracts
    as applied for; (2) a No Action alternative, in which the two tracts would not be leased
    ("Altemative l"); and (3) competitive lease sales of the two tracts as reconfigured by
    BLM ("Alternative 2"). AR 1489-97; Compl. 1111 53-54. Plaintiffs submitted comments
    on both the draft EIS and the FEIS, and proposed alternative measures that would
    5
    "reduce, eliminate, or mitigate" carbon dioxide ("CO;"), ozone, nitrogen dioxide
    ("NOQ"), and particulate matter ("PM]@") emissions, as well as adverse climate change
    impacts, from the proposed leases. Pls.’ Mem. at 5; Compl. 11 55; AR 4035-53, 4125-27,
    4111-20, 4245-67.
    In July 2010, BLM approved two Records of Decision ("ROD") authorizing
    competitive lease sales for the BAN and CW tracts. See Compl. 11 53; Pls.’ Mem. at 5;
    Def.’s Mem. at 1. Plaintiffs filed an administrative Notice of Appeal and Petition for
    Stay with the Interior Board of Land Appeals ("IBLA") in August 2010, challenging both
    RODs, AR 10770-10835. The IBLA denied the Petition for Stay in October 2010. AR
    11718-25. Before it could rule on the merits of plaintiffs’ challenge, however, plaintiffs
    moved to voluntarily dismiss their appeals in June 2011, and the IBLA granted that
    request in August 201 1. AR 11775-76, 11778-80. Meanwhile, BLM offered the BAN
    tract for sale on July 13, 201 l, and BTU Western Resources, Inc. placed the winning bid.
    Compl. 11 27; Def.’s Mem. at 8. BLM then offered the CW tract for sale on August 17,
    2011, and Alpha Wyoming Land Company, LLC won the bid. Def.’s Mem. at 8-9.
    Plaintiffs filed a complaint in this Court on August 16, 2011, bringing one count
    under NEPA and one count under FLPMA. Plaintiffs, who allege that their members
    have recreational, aesthetic, and economic interests in the public lands of the PRB,
    Compl. 1111 13-15, claim that BLM violated NEPA by authorizing the leases of the BAN
    and CW tracts without adequately considering the decisions’ impacts on air quality and
    climate change, Compl. 1111 71-82. Specifically, plaintiffs claim that BLM’s FEIS was
    legally inadequate because it failed to analyze the direct, indirect, and cumulative impacts
    6
    on air quality of ozone, PM]O, and NOZ emissions resulting from coal mining on the lease
    tracts, Compl. 11 79, 3 as well as the direct, indirect, and cumulative effects on climate
    change of greenhouse gas ("GHG") emissions, including COZ, resulting from lease
    development, Compl. 1111 75-77. Plaintiffs also allege that BLM failed to sufficiently
    consider mitigation measures and reasonable alternatives to minimize emissions. Compl.
    1[11 78, 80-81. Finally, under FLPMA, plaintiffs claim that BLM’s authorization of the
    leases failed to comply with federal air quality standards. Compl. 1111 83-92. Plaintiffs
    therefore seek declaratory and injunctive relief, including vacatur of the FEIS and the two
    RODs authorizing the leases. Compl. at 22-23.
    STANDARD OF REVIEW
    Challenges to agency action are reviewed under the Administrative Procedure Act
    ("APA"), 5 U.S.C. § 551 et seq. Under the APA, a court must set aside agency action if
    it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with
    law." 5 U.S.C. § 706(2)(A). This standard of review is "highly deferential and presumes
    the validity of agency action." Neighborhood Assistance Corp. of Am. v. CFPB, 907 F.
    Supp. 2d ll2, 125 (D.D.C. 2012) (citing AT&T Corp. v. FCC, 
    220 F.3d 607
    , 616 (D.C.
    Cir. 2000)) (internal quotation marks omitted)). The court maynot "substitute its
    judgment for that of the agency." Motor Vehz'cle Mfrs. Ass ’n of the U.S., Inc. v. State
    Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983). Rather, the court will only set aside
    3 Based on Judge Kollar-Kotelly’s ruling on a similar challenge in WildEarth Guardians v.
    Salazar ("WestAnz‘elope 1"), 
    880 F. Supp. 2d 77
    , 90-91 (D.D.C. 2012), plaintiffs do not pursue
    the allegation in their complaint that BLM failed to adequately analyze the impacts to air quality
    of NO; emissions from the leases. See Pls.’ Mem. at 2 n.l.
    7
    agency action as arbitrary and capricious if the agency committed a "clear error of
    judgment," such as when "the agency has relied on factors which Congress has not
    intended it to consider, entirely failed to consider an important aspect of the problem,
    offered an explanation for its decision that runs counter to the evidence before the
    agency, or is so implausible that it could not be ascribed to a difference in view or the
    product of agency expertise." Ia’. So long as the agency "examined the relevant data and
    articulated a satisfactory explanation for its action including a rational connection
    between the facts found and the choice made," its action will be upheld. Mz'lk Ina’us.
    Founa’. v. Glz``ckmcm, 
    132 F.3d 1467
    , 1476 (D.C. Cir. 1998) (internal quotations, citations,
    and modifications omitted).‘l
    ANALYSIS
    In WildEarth Guardians v. Salazar ("West Am‘elope I"), 
    880 F. Supp. 2d 77
    (D.D.C. 2012), my colleague, Judge Kollar-Kotelly, considered a nearly identical
    challenge by these same plaintiffss to BLM’s decision to lease two different coal tracts
    also located in Wyoming’s PRB. Judge Kollar-Kotelly granted summary judgment in
    favor of the government defendants, and recently_while the parties’ cross-motions for
    summary judgment were pending in the instant action_our Circuit Court affirmed that
    4 When reviewing final agency action under the APA, the summary judgment standard of Fed. R.
    Civ. P. 56 "does not apply because of the limited role of a court in reviewing the administrative
    record." Citizensfor Responsibz'lity and Ethz``cs in Washington v, SEC, 
    916 F. Supp. 2d 141
    , 144
    (D.D.C. 2013). The district court "deterrnine[s] whether or not as a matter of law the evidence in
    the administrative record permitted the agency to make the decision it did." Ia'. at 145 (internal
    quotation marks and citation omitted).
    5 In WestAntelope I, the plaintiffs were the three conservation organization plaintiffs in the
    instant action, as well as the Powder River Basin Resource Council following consolidation of
    two suits.
    decision. Wz'ldEarz‘h Guardz'ans v. Jewell ("WestAntelope Il"), 
    738 F.3d 298
     (D.C. Cir.
    2013). In view of the similarities, both factual and legal, between that case and this one,
    our Circuit Court’s West Antelope 11 opinion provides instructive analysis-and,
    regarding certain issues, binding authority-that help guide my decision here.
    The gravamen of the plaintiffs’ complaint in each case is that BLM failed to
    adequately address impacts to air quality and climate change resulting from the respective
    coal leases, in violation of NEPA and FLPMA. Here, as in WestAntelope I, the parties
    dispute plaintiffs’ standing to raise certain of their challenges to the sufficiency of the
    FEIS. Accordingly, I will first address plaintiffs’ standing, and for the reasons explained
    below I find that they have standing to raise all of their challenges to the FEIS. Next,
    turning to the merits, l conclude that BLM complied with NEPA and FLPMA when
    preparing the FEIS and authorizing the two leases.
    I. Standing
    The Constitution limits the role of federal courts to resolving cases and
    controversies. U.S. Const. art. III, § 2; Cir. for Bz'ological Dz``versz``ty v. U.S. Dep ’t of the
    Im‘erz``or, 
    563 F.3d 466
    , 475 (D.C. Cir. 2009). Accordingly, plaintiffs must show they
    have standing to bring their claims as a "predicate to any exercise of [this Court’s]
    jurisdiction." Fla. Audubon Soc’y v. Bentsen, 
    94 F.3d 658
    , 663 (D.C. Cir. l996). In
    order to satisfy the "irreducible constitutional minimum" of Article III standing, plaintiffs
    must satisfy three requirements:
    First, the plaintiff must have suffered an injury in fact_an invasion of a
    legally protected interest which is (a) concrete and particularized, and (b)
    actual or imminent, not conjectural or hypothetical. Second, there must be
    9
    a causal connection between the injury and the conduct complained of_the
    injury has to be fairly traceable to the challenged action of the defendant,
    and not the result of the independent action of some third party not before
    the court. Third, it must be likely, as opposed to merely speculative, that
    the injury will be redressed by a favorable decision.
    Um``tecz’ Staz‘es v. Wz``na’sor, 
    133 S. Ct. 2675
    , 2685-86 (2013) (quoting Lujcm v. Defenders of
    Wz'ldlz``f``e, 
    504 U.S. 555
    , 560-61 (l992) (quotations, citations, and modifications omitted)).
    As the party invoking federal jurisdiction, plaintiffs "bear[] the burden of establishing the
    factual predicates of jurisdiction by a preponderance of the evidence." Erby v. Um'tecz’
    States, 424 F. Supp. 2d 18(), 182 (D.D.C. 2006) (citing, inter alia, Lujan, 504 U.S. at
    561). And for purposes of considering whether plaintiffs have Article III standing, this
    Court "must assume arguendo the merits of [their] legal claim[s]." Parker v. Distrz``ct of
    Columbz``a, 
    478 F.3d 370
    , 377 (D.C. Cir. 20()7); NB ex rel. Peacock v. Disz‘rict of
    Columbz'a, 
    682 F.3d 77
    , 81 (D.C. Cir. 2012).
    In this case, plaintiffs allege a procedural (rather than substantive) injury.6 In fact,
    their complaint sets out the "archetypal procedural injury" in arguing that BLM failed to
    take a "hard look" at the environmental impacts of the leases and prepare a legally
    adequate EIS under NEPA. See Naz"l Parks Conservation Ass ’n v. Manson, 414 F.3d l,
    5 (D.C. Cir. 2005) ("The hypothetical in footnote 7 of Lujan represents the archetypal
    6 Plaintiffs are non-profit conservation organizations with members located in the PRB and
    across the nation. Compl. 1111 l3-l5. "[A]n association has standing to bring suit on behalf of its
    members when: (a) its members would otherwise have standing to sue in their own right; (b) the
    interests it seeks to protect are germane to the organization’s purpose; and (c) neither the claim
    asserted nor the relief requested requires the participation of individual members in the lawsuit."
    Hunt v, Wash. State Apple Aa’ver. Comm ’n, 
    432 U.S. 333
    , 343 (1977). None of the parties
    dispute the latter two elements of associational standing; the only issue is whether the members
    of WildEarth Guardians, Defenders of Wildlife, and the Sierra Club would otherwise have
    standing to raise all of the legal claims alleged in plaintiffs’ c0mplaint.
    10