Sierra Club v. United States Department of Agriculture ( 2011 )


Menu:
  • UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    SIERRA CLUB,
    Plaintiff,
    v. Civ. Action No. 07-O1860(EGS)
    UNITED STATES DEPARTMENT OF
    AGRICULTURE, RURAL UTILITIES
    SERVICE, et al
    Defendants,
    and
    SUNFLOWER ELECTRIC POWER
    CORPORATION,
    Defendant-Intervenor.
    ``/\./``/\@\/``/»»\/\/\J\/\_/\/\./ \/\/``_,``/``./\/\/
    MEMORANDUM OPINION
    Plaintiff Sierra Club filed this action on October l6, 2007,
    alleging that the Department of Agriculture’s Rural Utilities
    Service and certain officials in the Department of Agriculture
    (collectively, “the federal defendants”) violated the National
    Environmental Policy Act of 1969 by failing to produce an
    environmental impact statement in connection with its involvement
    in the expansion of Sunflower Electric Power Corporation’s
    (“Sunflower”) coal-fired generating plant in Holcomb, Kansas.
    Sunflower has intervened as a defendant. Pending before the
    Court are Sunflower's motion to dismiss the complaint as moot,
    plaintiff’s motion for summary judgment (consolidated with its
    motion for a preliminary injunction pursuant to Federal Rule of
    Civil Procedure 65(a)(2)), the federal defendants’ cross-motion
    for summary judgment, and Sunflower's cross-motion for summary
    judgment.
    Upon consideration of the motions, the responses and replies
    thereto, the applicable law, the entire record, and for the
    reasons set forth below, Sunflower's motion to dismiss the
    complaint as moot is DENIED, plaintiff’s motion for summary
    judgment is GRANTED, the federal defendants’ cross-motion for
    summary judgment is DENIED, and Sunflower’s cross-motion for
    summary judgment is DENIED.
    I. BACKGROUND
    Briefly stated, plaintiff maintains that the Rural Utilities
    Service (“RUS”) should have performed an environmental impact
    statement (“EIS”) in conjunction with RUS's involvement in the
    project to expand a power plant facility. As is discussed in
    more detail below, the National Environmental Policy Act (“NEPA”)
    requires federal agencies to include an EIS “in every
    recommendation or report on proposals for legislation and other
    major Federal actions significantly affecting the quality of the
    human environment[.]” 42 U.S.C. § 4332.
    The Rural Electrification Act of 1936 gives the Secretary of
    Agriculture authority, which has been delegated to RUS, to “make
    loans in the several States and Territories of the United States
    for rural electrification and for the purpose of furnishing and
    improving electric and telephone service in rural areas,
    and for the purpose of assisting electric borrowers to implement
    demand side management, energy efficiency and conservation
    programs, and on-grid and off-grid renewable energy systems.”
    7 U.S.C. § 902(a). The Rural Electrification Act further
    authorizes RUS to make loans for rural electrification to
    corporations organized “for the purpose of financing the
    construction and operation of generating plants, electric
    transmission and distribution lines or systems for the furnishing
    and improving of electric service to persons in rural areas[.]”
    7 U.S.C. § 904(a). (RUS’s predecessor was the Rural
    Electrification Administration (“REA”).)
    According to plaintiff, RUS’s involvement in the expansion
    of the Holcomb power plant in connection with certain loans and
    loan guarantees to Sunflower, amounted to'a “major federal
    action” within the meaning of NEPA such that an EIS was required.
    In particular, plaintiff argues that RUS's approvals relating to
    the expansion of the power plant, as well as the financial
    assistance provided by RUS, in the form of debt forgiveness and
    consent to a lien subordination, qualified RUS's involvement as a
    major federal action.
    A. 1980 Approval of Loan and Loan Guarantee
    In 1980, after preparing an EIS, the REA approved a loan and
    loan guarantees to Sunflower Electric Cooperative, Inc. (“Old
    Sunflower"). The loan and loan guarantees, totaling
    approximately $543 million, were provided to Old Sunflower for
    the construction of a coal-fired generating station (“Holcomb
    Unit l”) to be located near Holcomb, Kansas. Administrative
    Record (“AR”) O3866.
    B. 1987 Restructuring and Issuance of Promissory Notes
    Soon after the construction of Holcomb Unit 1, Old Sunflower
    became unable to meet its debt repayment obligations to REA and
    other creditors. AR O4546. Accordingly, in 1987 Old Sunflower
    entered into an agreement, the 1987 Debt Restructure Override
    Agreement and Amended and Restated Credit Agreement (the “1987
    DRA”), with REA and its other creditors to restructure its debt.
    AR 03871-3975. Under the 1987 DRA, Old Sunflower issued three
    classes of promissory notes, referred to as the A Notes, B Notes,
    and C Notes, AR O0149. REA’s share of the principal balance on
    the A Notes was $294.5 million; on the B Notes it was $98.3
    million; on the C Notes it was $61.4 million. Fed. Defs.’
    Statement of Facts Supp. Cross-Mot. Summ. J. (“Fed. Defs.'
    Statement of Facts”) ll 5-7. The A Notes required regularly
    scheduled payments, but payment on the B Notes was required only
    when Old Sunflower had excess cash, as defined by the 1987 DRA.
    AR 0O168-169. Each year, any unpaid interest on the B Notes was
    capitalized and added to the outstanding principal balance. As
    for the C Notes, payments were to begin only after the B Notes
    were fully repaid, and any remaining balance on the C Notes would
    expire in December 20l9. AR OO169. Furthermore, in order to
    secure the notes it issued under the 1987 DRA, Sunflower granted
    a lien to REA and its other secured creditors on substantially
    all of its assets. AR OO276.
    C. The 2002 Corporate and Debt Restructuring
    After the 1987 restructuring, Old Sunflower was able to
    remain current on the A Notes, but it made no payments on the B
    Notes or C Notes. Because the interest was capitalized on the B
    Notes, the principal owed to RUS on these notes had increased
    from the $98.3 million owed in 1987 to $413.9 million in 2002.
    Because Old Sunflower was at risk of defaulting, Old Sunflower
    and its creditors elected to negotiate another restructuring. AR
    OOOO4-11.
    The 2002 corporate and debt restructuring (the “2002
    Restructuring”) divided Old Sunflower’s assets between two new
    corporations, Sunflower Electric Power Corporation (“New
    Sunflower” or “Sunflower”) and the Holcomb Common Facilities
    (“HCF”). New Sunflower, the defendant-intervenor in this action,
    purchased Old Sunflower’s assets with certain exceptions. AR
    OO2l6-247.1 In particular, New Sunflower did ngt purchase a
    segment of land on the Holcomb site that the parties recognized
    could be used by a potential additional generating facility
    (“Holcomb Unit 2”). In addition to this land footprint that
    could be used by a second generating unit, New Sunflower also did
    not purchase certain “Common Facilities” such as coal handling
    and storage facilities, a solid waste landfill, and a sewage
    treatment plant, The Common Facilities support the operation of
    Holcomb Unit l, but they could also support the operation of
    additional generating units. These leftover assets not purchased
    by New Sunflower, namely the land footprint for a potential
    Holcomb Unit 2 and the Common Facilities, were acquired by HCF.
    HCF is a wholly owned subsidiary of Old Sunflower.
    Significantly for purposes of the instant action, New
    Sunflower purchased Old Sunflower’s assets by issuing an entirely
    new set of notes to the holders of the old A, B and C Notes
    discussed above. AR OOl73-l75. The new classes of notes issued
    to RUS can be categorized as the new A Notes, the new B notes,
    the Residual Value Notes, and the Holcomb 3 Notes. New
    Sunflower’s payments on the new A Notes, identical in amount to
    the old A Notes, were credited against Old Sunflower’s A Notes.
    AR OOl73. The new A Notes have since been paid in full.
    1 New Sunflower was initially named SEP Corporation.
    6
    with respect to the remaining classes of new notes,
    including new B Notes, the Residual Value Notes, as well as the
    Holcomb 3 Notes, any payments made by Sunflower are all credited
    against Old Sunflower’s debt under the old B Notes. AR OOl74.
    However, the monetary value of the old B Notes issued pursuant to
    the 1987 DRA was substantially different than the value of these
    new notes, The new B Notes are non-interest bearing notes with a
    fixed payment schedule, issued in the total amount of $88.4
    million. (However, for every payment that Sunflower makes on
    time on the new B Notes, the principal balance is reduced such
    that if Sunflower makes all its payments in a timely fashion, it
    will only pay a total of $44.2 million. AR OOl74.) On the
    Residual Value Notes, New Sunflower is not required to make any
    regularly scheduled payments. Instead, the Residual Value Notes
    are redeemable in December 2016 for the greater of either $125
    million or 43% of the fair market value of Holcomb Unit l. AR
    O0l75. Finally, the Holcomb 3 Notes issued by Sunflower are
    interest-bearing notes, but they are payable only if and when
    Sunflower builds or becomes the operator of a third generating
    plant at the Holcomb Site. AR OOl75. RUS’s share of the Holcomb
    3 Notes was $l.8 million. If a third plant is not built or
    operated by Sunflower by December 202l, the Holcomb 3 notes are
    cancelled. AR 0Ol75.
    Unlike New Sunflower, HCF (the other new entity formed in
    conjunction with the 2002 Restructuring) did not issue new
    promissory notes. Instead, for the purchase of the Holcomb Unit
    2 land footprint and the Common Facilities, RUS and the other
    creditors received a security interest in HCF and an assignment
    of annual rent payments from the use of the Holcomb Unit 2 site
    and Common Facilities. AR O0l90.
    The 2002 Restructuring also affected the lien held by RUS on
    Old Sunflower’s assets. As mentioned above, prior to the 2002
    Restructuring, RUS held a first priority lien on the Holcomb
    site. RUS has not yet released this lien. However, pursuant to
    the 2002 Restructuring, RUS agreed that it will, in the future,
    release the portion of its lien covering the Holcomb Unit 2 site
    and the Common Facilities, if and when the Holcomb Unit 2
    generating plant is developed. In exchange, Sunflower agreed to
    grant to RUS a security interest in the rent paid for the use of
    the Common Facilities and the Holcomb Unit 2 site.2
    Old Sunflower, RUS, and other creditors executed an
    Agreement and Consent to Sunflower Restructuring on September 30,
    2002. AR 002l6-247. ln connection with the 2002 Restructuring,
    in particular as outlined in the amended loan contract and
    mortgage agreement, Sunflower also agreed to obtain approval from
    RUS before undertaking a variety of activities or entering
    2 As discussed below, this final aspect of the agreement
    was later modified.
    certain types of contracts, Among others, Sunflower agreed:
    (i) that it would not “enter into any agreement or other
    arrangements . . . for the development of Holcomb Unit 2 without
    the prior written approval of RUS” and “[a]ny RUS approval will
    be on such terms and conditions as RUS, in its sole discretion,
    may require at such time” (AR 04391); (ii) that it would not
    “enter into any agreement or arrangement . . . for Holcomb Site
    Development . . . or for other use of the Holcomb Unit 1 site,
    the fair market value of which would exceed $l million
    annually[,] without the prior written approval of RUS” and “[a]ny
    RUS approval will be on such terms and conditions as RUS, in its
    sole discretion, may require at such time” (AR 0439l); (iii) that
    it will not “[c]onstruct, make, lease, purchase or otherwise
    acquire any extensions or additions to its system or enter into
    any contract therefore” without the prior written approval of RUS
    (AR 04389); (iv) that it will not “[p]urchase, lease or otherwise
    acquire any parcel or parcels of land or enter into any contract
    therefore” without the prior written approval of RUS (AR 04389);
    (v) that it will not enter into any contracts or arrangements
    regarding power purchase or sale arrangements, power supply and
    delivery arrangements, power marketing contracts, system
    management and maintenance contracts, or any contracts relating
    to financial products such as options, futures or hedges without
    the prior written approval of RUS (AR O4389-04390); (vi) that it
    would not “charge, assign, pledge, mortgage or otherwise encumber
    any of its property” without prior written approval from RUS (AR
    04459); and (vii) Sunflower agreed to limitations on mergers,
    sale of its business or assets, leases and transfers of its
    capital assets in the absence of prior approval from RUS (AR
    04467-O4468).
    D. The 2007 Agreements
    Since the 2002 Restructuring, Sunflower has sought approval
    from RUS on a number of occasions in accordance with the
    conditions outlined above. Most relevant to this action, on
    several occasions Sunflower sought approvals relating to the
    development of new generating plants at the Holcomb Unit 2 site.
    As noted above, the 2002 Debt Restructuring agreements required
    Sunflower to seek approval from RUS before “enter[ing] into any
    agreement or other arrangements . . . for the development of
    Holcomb Unit 2 without the prior written approval of RUS.” AR
    O4391.3
    ln October of 2005, RUS granted conditional approval of
    Sunflower’s execution of a Memorandum of Agreement (“MOA”) with
    Tri-State Generation and Transmission Association, Inc. (“Tri-
    State”) regarding the proposed development of two new generating
    units at the Holcomb site. AR 04574. Subsequently, in September
    3 The parties have referred to the plans involving the
    development of additional generating units at the Holcomb site as
    the “Holcomb Expansion Project,” and the Court will do the same.
    10
    of 2006, RUS granted conditional approval for Sunflower to enter
    into a Purchase Option and Development Agreement (“PODA”) with
    Tri-State, as well as various other related agreements, again for
    the proposed development of two new generating units at the
    Holcomb site. AR 04610-46ll.
    As a condition of its approval of all of these agreements,
    RUS initially demanded that Sunflower deposit all funds it
    received pursuant to the agreements into an escrow account until
    “RUS and Sunflower have reached a definitive agreement on the
    amount of additional consideration due to RUS for Holcomb Site
    Development.” AR 04574; AR 004610. Because Sunflower objected
    to the use of an escrow account in its dealings with Tri-State,
    further negotiations between RUS and Sunflower took place in
    early 2007. Ultimately, RUS agreed that the funds could be
    placed in a “Development Account” rather than an escrow account.
    Accordingly, in a July 26, 2007 letter, RUS approved Sunflower’s
    execution of an updated PODA with Tri-State and several related
    agreements. AR 07444. ln addition to the development of Holcomb
    Unit 2, the agreements provided for the potential construction of
    a Holcomb Unit 3 and a Holcomb Unit 4.
    In addition, also on July 26, 2007, RUS also provided
    Sunflower with a separate letter, referred to by the parties as
    the “Additional Consideration Letter.” AR 082l8-8216. As
    mentioned above, in connection with the 2002 Restructuring, RUS
    ll
    and the other creditors had received a security interest in HCF
    and an assignment of annual rent payments for the use of the
    Holcomb Unit 2 site and Common Facilities. However, the terms of
    the Additional Consideration Letter modified this arrangement.
    Instead, for each additional power plant being considered for the
    Holcomb site, RUS received yet another set of promissory notes,
    With respect to Holcomb Unit 2, Sunflower issued promissory notes
    (the “2007 Holcomb 2 Notes”) in the amount of $52 million; with
    respect to the 2007 Holcomb 3 Notes, the amount was $23 million;
    and with respect to the 2007 Holcomb 4 Notes, the amount was $16
    million. AR 08228, 08239, 08244. These notes are interest
    bearing, but payment is due only if and when the respective
    generating unit is placed into commercial operation.
    Furthermore, each of these 2007 promissory notes, totaling $9l
    million, will be cancelled on December 3l, 2021 if the respective
    generating unit has not been placed into commercial operation.
    II. Mbotness
    As a threshold matter, the Court must consider Sunflower’s
    motion to dismiss the complaint pursuant to Fed. R. Civ. P.
    l2(b)(1), on the ground that the Court lacks subject-matter
    jurisdiction because plaintiff's Amended Complaint is moot.4 As
    4 In addition to its assertion that the case is moot on
    constitutional grounds, Sunflower argues that the case should be
    dismissed on the grounds of prudential mootness. Prudential
    mootness allows the court to exercise its discretion and dismiss
    a case that, although not actually moot, “is so attenuated that
    12
    discussed in more detail below, the Court concludes that, because
    Sunflower has failed to demonstrate that no effective relief is
    available, the case is not moot,
    A. Legal Framework
    The purpose of the mootness doctrine is to “ensure[] that
    federal courts only decide ongoing cases and controversies.”
    Cody v. Cox, 
    509 F.3d 606
    , 608 (D.C. Cir. 2007) (citing Clarke v.
    United States, 
    915 F.2d 699
    , 700-701 (D.C. Cir. 1990). “A case
    is moot when ‘the challenged conduct ceases such that there is no
    reasonable expectation that the wrong will be repeated’ in
    circumstances where ‘it becomes impossible for the court to grant
    any effectual relief whatever to the prevailing party.'” United
    States v. Philip Morris USA, Inc., 
    566 F.3d 1095
    , 1135 (D.C. Cir.
    2009) (quoting City of Erie v. Pap's A.M;, 
    529 U.S. 277
    , 287
    (2000); see also Lemon v. Geren, 514 F.3d 13l2, 1315 (D.C. Cir.
    2008) (“A case becomes moot when ‘intervening events make it
    impossible to grant the prevailing party effective relief.'”)
    (quoting Burlington N. R.R. Co. v. Surface Transp. Bd., 
    75 F.3d 685
    , 688 (D.C. Cir. 1996)). “The burden of demonstrating
    mootness is a heavy one.” Daingerfield Island Protective Soc’y
    considerations of prudence and comity for coordinate branches of
    government counsel the court to stay its hand, and to withhold
    relief it has the power to grant.” Chamber of Commerce v. Dep’t
    of Energy, 
    627 F.2d 289
    , 291 (D.C. Cir. 1980). In the instant
    case, the Court concludes that it would be inappropriate to
    exercise its discretion in this manner.
    13
    v. Lujan, 
    920 F.2d 32
    , 35 (D.C. Cir. 1990) (quoting Cnty. of Los
    Angeles v. Davis, 
    440 U.S. 625
    , 631 (l979)). “[E]ven the
    availability of a partial remedy is sufficient to prevent a case
    from being moot.” Byrd v. EPA, 
    174 F.3d 239
    , 244 (D.C. Cir.
    1999) (quoting Calderon v. Moore, 
    518 U.S. 149
    , 150 (1996)); see
    also FTC v. Whole Foods Market, Inc., 
    548 F.3d 1028
    , 1034 (D.C.
    Cir. 2008).
    Sunflower argues that plaintiff's claims are
    constitutionally moot for two reasons. First, Sunflower argues
    that the transactions and approvals at issue, namely the 2002
    Restructuring and the 2007 approvals, have been completed and are
    therefore no longer subject to judicial review. Second,
    Sunflower argues that no effective relief is available to
    plaintiff to address RUS’s completed approvals. Each of these
    arguments is addressed below in turn.
    B. Judicial Review of Completed Transactions and Approva1s
    Sunflower first argues that, because the transactions and
    approvals at issue in this case have already been completed by
    RUS, plaintiff's claims are no longer subject to judicial review
    and are therefore moot.5 This analysis misstates the applicable
    5 Sunflower goes so far as to assert that plaintiff may not
    have ever had an opportunity to challenge RUS's actions in
    connection with the 2002 Debt Restructuring. According to
    Sunflower, “[b]ecause the RUS approval and the closing of the
    transactions occurred on the same day, under the analytical
    framework applied when the focus is on the object of the federal
    agency action, there was a short or non-existent window between
    14
    standard. ln fact, contrary to Sunflower’s assertion, this
    Circuit has held that effective relief is available to
    plaintiffs, under certain circumstances, when NEPA has been
    violated even if the transaction at issue has been completed.
    For example, in Lemon, the court concluded that the case was not
    moot despite the fact that the land transfer at issue had already
    been completed because “[i]f unraveling the transfer is necessary
    after the district court decides the merits, it will be within
    the court's power to do so.” 514 F.3d at 1316;6 see also
    Muckleshoot Indian Tribe v. Forest Serv., 
    177 F.3d 800
    , 815 (9th
    Cir. 1999) (rejecting mootness argument despite completion of
    property transfer because “[c]onveyance of a property to another
    does not moot a case”).7
    the point in time when a challenge to the 2002 restructuring
    became ripe and the point in time when the challenge became
    moot.” Sunflower Mot. to Dismiss at 15.
    6 While the holding in Lemon rested at least in part on the
    court's conclusion that all the parties to the transaction were
    before the court, 514 F.3d at 1316, this Court notes that RUS and
    Sunflower were the only two parties to at least some of the
    transactions and approvals at issue in the instant action, Thus,
    if anything, this may affect the scope of the remedy available to
    the plaintiff, but it does not indicate that relief is
    unavailable.
    7 As is evident in the cases cited by Sunflower itself,
    completion is a potentially relevant factor in the mootness
    analysis when it relates, not merely to the agency's action, but
    rather to the actual project at issue, For example, in Fund for
    Animals, Inc. v. Bureau of Land Management, 
    460 F.3d 13
     (D.C.
    Cir. 2006), plaintiff's case challenging the federal agency's
    plan relating to gathers of wild horses and burros was held to be
    moot because the gathers had already occurred and could not be
    15
    C. Awailability of Effective Relief
    Second, Sunflower argues that effective relief is not
    available to plaintiff, (i) because NEPA is a procedural statute
    with no ability to provide retroactive relief, and (ii) because
    RUS has no authority to impose ongoing environmental mitigation
    measures on Sunflower in a manner that would offer prospective
    relief to plaintiff.
    Sunflower’s argument that NEPA is a procedural statute with
    no ability to provide retroactive relief, has been contradicted
    by this Circuit. See, e.g., Lemon, 514 F.3d at l315. Sunflower
    is correct that NEPA guarantees a process, rather than a
    particular result. See, e.g,, DOT v. Public Citizen, 
    541 U.S. 752
    , 756-757 (2004) (“NEPA itself does not mandate particular
    results . . . . Rather, NEPA imposes only procedural requirements
    on federal agencies with a particular focus on requiring agencies
    to undertake analyses of the environmental impact of their
    proposals and actions.”) (internal quotation marks omitted).
    Such a conclusion does not, however, preclude the availability of
    undone; therefore, “it was impossible for the court to grant any
    effectual relief whatever.” Id. at 22; see also Feldman v.
    Bomar, 
    518 F.3d 637
    , 643 (9th Cir. 2008) (holding that a
    challenged action relating to the killing of feral pigs was moot
    because, by the time the court heard the case, the pigs had
    already been killed and plaintiffs had already “suffered whatever
    harm could conceivably result from the challenged agency
    action.”) The instant case, however, differs substantially from
    these two cases in an obvious way. Here, as far as the Court has
    been made aware, the Holcomb Expansion Project has not yet
    resulted in the construction of an actual power plant.
    16
    retroactive relief when the federal agency has failed to provide
    that process in accordance with NEPA.8 This Circuit has, for
    example, enjoined a construction project when the approval
    process associated with that construction process failed to
    comply with NEPA. ln Reality Income Trust v. Eckerd, 
    564 F.2d 447
     (D.C. Cir. l977), the court held that:
    Ordinarily when an action is being undertaken in
    violation of NEPA, there is a presumption that
    injunctive relief should be granted against
    continuation of the action until the agency brings
    itself into compliance. The fact that the present
    project is currently under construction by no means
    insulates it from the equity power of a court: The
    substantial additional costs which would be caused by
    court-ordered delay may well be justified by the
    compelling public interest in the enforcement of NEPA.
    Id. at 456 (internal quotation marks omitted).
    Sunflower’s remaining argument is that RUS lacks the
    authority to impose ongoing environmental mitigation measures on
    Sunflower and, therefore, there can be no effective relief for
    3 Sunflower cites the Supreme Court decision in Tennessee
    Valley Auth. v. Hill, 437 U.S. l53, 174 n.18 (l978), for the
    proposition that NEPA is not “intended . . . to afford
    retroactive relief.” Sunflower Mot. to Dismiss at 12. However,
    this reading of Hill is erroneous. The decision in Hill
    addressed the scope of a particular provision of the Endangered
    Species Act, and the footnote cited by Sunflower merely states
    that “the dissent’s position logically means that an agency would
    be obligated to comply with § 7 [of the Endangered Species Act]
    only when a project is in the planning stage. But if Congress had
    meant to so limit the [Endangered Species] Act, it surely would
    have used words to that effect, as it did in the National
    Environmental Policy Act, 42 U.S.C. §§ 4332 (2)(A),(C).” Hill,
    437 U.S. at 174 n.18.
    17
    plaintiff.9 ln particular, Sunflower argues that RUS has “no
    statutory or regulatory authority to modify its past approvals in
    an environmentally mitigating manner” and, furthermore, that
    “none of the contracts between RUS and Sunflower provide RUS
    ongoing environmental mitigation authority over Sunflower.”
    Sunflower Mot. to Dismiss at 21, 22.
    Sunflower is correct that the ability of a court to grant
    effective relief in the context of a NEPA action involving a non-
    federal party can depend on whether the agency has maintained
    authority to impose mitigation measures. Karst Envtl. Educ. &
    Prot., Inc. v, EPA, 
    475 F.3d 1291
    , 1298-1299 (D.C. Cir. 2007)
    (plaintiff’s claims against one of the federal agency defendants
    were moot because the plaintiff failed to allege that the federal
    agency had authority to impose mitigation measures upon the [non-
    federal party). Here, however, plaintiff has sufficiently
    alleged that RUS has maintained authority over Sunflower, The
    authority of a federal agency to impose mitigation measures need
    not be a statutory authority; a contractual agreement may also
    create the authority. See Karst, 475 F.3d at 1298 (“if (the
    9 Sunflower also claims that the approvals granted by RUS
    were “ministerial approvals,” and therefore RUS lacked the
    ability, even at the time the approvals were issued, to impose
    environmental conditions. Sunflower Mot. to Dismiss at 23.
    However, this argument essentially asserts that NEPA is wholly
    inapplicable to these approvals, an issue more appropriately
    addressed as part of the merits determination. (Sunflower has
    also made this argument in their cross-motion for summary
    judgment, and the Court therefore addresses this argument below.)
    18
    federal agency] actually has authority - whether by statute,
    regulation, contract, or otherwise - to impose mitigation
    measures upon [the non-federal party], [plaintiff's] claim might
    well remain justiciable.”) (citing Vieux Carre Prop. Owners,
    Residents, & Assocs. v; Brown, 
    948 F.2d 1436
    , 1446 (5th Cir.
    1991).
    The Amended Complaint cites to the terms of the loan
    contract signed as part of the 2002 Debt Restructuring which
    require, in part, that Sunflower seek approval from RUS before it
    “enter{s] into any agreement or other arrangements . . . for the
    development of Holcomb Unit 2 without the prior written approval
    of RUS.” AR 04391. Plaintiff has also alleged that “the parties
    contemplate that RUS will provide lien releases and/or
    subordinations, and authorizations for releases of funds from the
    Holcomb Development Account in the future. Further, Sunflower is
    to operate all of the new coal-fired electric generating units,
    and RUS’s extensive control over Sunflower’s business will remain
    in place at least until such time as all loans to the United
    States are repaid.” Am. Compl. 1 137. Therefore, the Court
    finds plaintiff has also adequately alleged that RUS maintains
    the same level of authority over Sunflower as existed in 2007
    when it granted the approvals challenged by plaintiff.
    The Court concludes that, while fashioning a remedy may be
    difficult under the complicated circumstances that exist in the
    19
    instant action, the practical difficulties identified by
    Sunflower both with respect to prospective and retroactive relief
    “are more appropriately considered when weighing the equities of
    any particular remedy.” Tinoqui-Chalola Council v. Dep’t of
    Energy, 232 F.3d l300, 1305 (9th Cir. 2000). Accordingly,
    Sunflower’s motion to dismiss the action as moot is hereby
    DENIED,
    III. P1aintiff’s Claims Under NEPA
    A. Legal Standards
    i. Administrative Procedure Act
    Under the Administrative Procedure Act (“APA”), a reviewing
    court may set aside agency actions, findings or conclusions that
    are “arbitrary, capricious, an abuse of discretion, or otherwise
    not in accordance with law.” 5 U.S.C. § 706(2)(A). Courts thus
    typically review an agency action to determine whether the agency
    has “relied upon factors which Congress has not intended it to
    consider, entirely failed to consider an important aspect of the
    problem, offered an explanation for its decision that runs
    counter to the evidence before the agency, or is so implausible
    that it could not be ascribed to a difference in view or the
    product of agency expertise.” Motor Vehicle Mfrs. Ass’n v. State
    Farm Mut. Auto. Ins., 
    463 U.S. 29
    , 42 (l983). However, a federal
    agency's determination that NEPA is wholly inapplicable to its
    actions, as defendants argue in the instant case, is “‘not
    20
    entitled to the deference that courts must accord to an agency's
    interpretation of its governing statute' and is instead ‘a
    question of law, subject to de novo review.'" Mineral Policy Ctr.
    v. Norton, 
    292 F. Supp. 2d 30
    , 54-55 (D.D.C. 2003) (quoting
    Citizens Against Rails-to-Trails v. Surface Transp. Bd., 
    267 F.3d 1144
    , 1150-51 (D.C. Cir. 2001)).
    ii. National Environmental Policy Act
    In enacting NEPA, Congress “recogniz[ed] the profound impact
    of man’s activity on the interre1ations of all components of the
    natural environment, particularly the profound influences of
    population growth, high-density urbanization, industrial
    expansion, resource exploitation, and new and expanding
    technological advances[.]” 42 U.S.C. § 433l. The goals of NEPA
    reflect “the continuing policy of the Federa1 Government, in
    cooperation with State and local governments, and other concerned
    public and private organizations, to use all practicable means
    and measures, including financial and technical assistance, in a
    manner calculated to foster and promote the general welfare, to
    create and maintain conditions under which man and nature can
    exist in productive harmony, and fulfill the social, economic,
    and other requirements of present and future generations of
    Americans.” Id. “Two fundamental principles underlie NEPA's
    requirements: federal agencies have the responsibility to
    consider the environmental effects of major actions significantly
    21
    affecting [the] environment, and the public has the right to
    review that consideration.” Found. on Econ. Trends v. Heckler,
    
    756 F.2d 143
    , 147 (D.C. Cir. 1985) (citing Balt. Gas & Elec. Co.
    v. Natural Res. Def. Council, Inc., 
    462 U.S. 87
     (l983).
    NEPA requires federal agencies to prepare an environmental
    impact statement (“ElS") under certain circumstances, ln
    particular, NEPA mandates that:
    [A]ll agencies of the Federal Government shall
    include in every recommendation or report on proposals
    for legislation and other major Federal actions
    significantly affecting the quality of the human
    environment, a detailed statement by the responsible
    official on (i) the environmental impact of the
    proposed action, (ii) any adverse environmental effects
    which cannot be avoided should the proposal be
    implemented, (iii) alternatives to the proposed action,
    (iv) the relationship between local short-term uses of
    man’s environment and the maintenance and enhancement
    of long-term productivity, and (v) any irreversible and
    irretrievable commitments of resources which would be
    involved in the proposed action should it be
    implemented,
    42 U.S.C. § 4332.
    Although the REA prepared an E1S before approving the
    original loan and loan guarantees to Old Sunflower in l980, it is
    the defendants’ position that NEPA does not apply to the agency's
    subsequent involvement in Sunflower. Accordingly, no EIS was
    prepared in connection with any of RUS’ actions related to the
    Holcomb Expansion Project. Plaintiff claims that the federal
    defendants violated NEPA by failing to do so.
    ln response to plaintiff's assertion that NEPA applies,
    22
    Sunflower and the federal defendants have made several arguments.
    First, Sunflower argues that there has never been a “proposal”
    within the meaning of § 4332 and, therefore, the statute does not
    apply. Second, the defendants argue that RUS has not taken a
    “major federal action” within the meaning of § 4332 and the
    accompanying regulations. Third, Sunflower argues that RUS was
    contractually prohibited from imposing environmental standards as
    a condition of its approvals. Fourth, Sunflower argues that RUS
    lacked the requisite discretion to impose environmental
    conditions. Finally, the defendants argue that RUS regulation 7
    C.F.R. § l794.3 exempts its actions related to the Holcomb
    Expansion Project from NEPA.
    For the reasons discussed below, the Court agrees with the
    plaintiff that NEPA does apply to RUS’s actions in connection
    with both the 2002 Restructuring, as well as the approvals
    granted in 2007.
    B. Whether a “Proposal” Occurred Sufficient to Trigger
    NEPA Requirements
    ln its cross-motion for summary judgment, Sunflower first
    argues that no ElS was necessary in connection with the Holcomb
    Expansion Project because NEPA requires an ElS only when an
    agency has made “proposals for legislation and other major
    Federal actions significantly affecting the quality of the human
    environment[.]” 42 U.S.C. § 4332. According to Sunflower, no
    “proposal” was ever made.
    23
    The Council on Environmental Quality (“CEQ”), established by
    NEPA and charged with “formulat[ing] and recommend[ing] national
    policies to promote the improvement of the quality of the
    environment,” 42 U.S.C. § 4342, has promulgated a regulation
    explaining the “proposal” requirement in § 4332. lt states:
    ‘Proposal’ exists at that stage in the development of
    an action when an agency subject to the Act has a goal
    and is actively preparing to make a decision on one or
    more alternative means of accomplishing that goal and
    the effects can be meaningfully evaluated. Preparation
    of an environmental impact statement on a proposal
    should be timed . . . so that the final statement may
    be completed in time for the statement to be included
    in any recommendation or report on the proposal. A
    proposal may exist in fact as well as by agency
    declaration that one exists.
    40 C.F.R § l508.23.
    Sunflower, relying heavily on the Supreme Court’s decision
    in Kleppe v. Sierra Club, 
    427 U.S. 390
     (l976), asserts that
    “[f]or the ‘proposal’ element to be satisfied, a ‘coherent plan’
    must exist, and it must be ‘specific.’” Sunflower Opp’n Summ. J.
    at 5-6 (citing Kleppe, 427 U.S. at 401 n.12). According to
    Sunflower, no specific plans yet exist with respect to the
    Holcomb Expansion Project, such as the exact number and size of
    potential new generating units, and an EIS is therefore not yet
    required.
    The Court does not find Sunflower’s reliance on Kleppe
    persuasive. In Kleppe plaintiffs sought a “comprehensive
    environmental impact statement under [NEPA] on the entire
    24
    [Northern Great P1ains Region]” in connection with various coal-
    related operations. Kleppe, 427 U.S. at 395. However, the
    Kleppe court concluded that “there is no evidence in the record
    of an action or a proposal for an action of regional scope,” Id.
    at 400 (emphasis added). Instead, all of the proposals were “for
    actions of either local or national scope.” Id. at 399.
    Although the court in Kleppe concluded that no proposal for a
    regional plan existed, the court nonetheless stated that for
    “both an individual coal-related action and the new national
    coal-leasing program, an agency deals with specific action of
    known dimensions. With appropriate allowances for the
    inexactness of all predictive ventures, the agency can analyze
    the environmental consequences and describe alternatives as
    envisioned by [NEPA].” Id. at 402 n.14.
    ln contrast to Kleppe, there is a sufficiently defined
    proposal in the instant case, As plaintiff points out, the major
    federal action taken by RUS is not the Holcomb Expansion Project
    itself; rather, the major federal action at issue is the agency's
    decision to maintain federal control over, provide assistance to,
    and grant approvals for an otherwise non-federal project. These
    actions have not only been sufficiently defined, they have
    already been executed. Furthermore, to the extent that more
    than one option for the Holcomb Expansion Project existed, this
    does not excuse RUS from complying with NEPA. On the contrary,
    25
    CEQ regulations instruct the federal agency to “integrate the
    NEPA process with other planning at the earliest possible time to
    insure that planning and decisions reflect environmental values,
    to avoid delays later in the process, and to head off potential
    conflicts.” 40 C.F.R. § 1501.2. By doing so, an agency is able
    to “[s]tudy, develop, and describe appropriate alternatives to
    recommended courses of action in any proposal which involves
    unresolved conflicts concerning alternative uses of available
    resources[.]” 40 C.F.R. §1501.2(c)(emphasis added).
    Accordingly, this Court concludes that a “proposal” within
    the meaning of 42 U.S.C. § 4332 and CEQ regulation 40 C.F.R
    § 1508.23 did exist with respect to the agency's involvement in
    the Holcomb Expansion Project,
    C. Whether a Major Federal Action Took Place
    One of the main disputes between the parties is whether
    RUS's involvement in the Holcomb Expansion Project has risen to
    the level of a “major federal action.” As explained above, NEPA
    requires that an ElS be prepared in connection with any
    “recommendation or report on proposals for legislation and other
    major Federal actions significantly affecting the quality of the
    human environment.” 42 U.S.C. § 4332. The Court concludes that
    RUS's involvement in the Holcomb Expansion Project constituted a
    major federal action, both in connection with the 2002
    Restructuring and in connection with the approvals granted in
    26
    2007,
    “major federal action.”
    provides,
    40 C.
    itself a non-federal action,
    for the reasons discussed in more detail below.
    i. Regulatory Framework
    The CEQ has issued regulations further defining the term
    ln particular, 40 C.F.R. § 1508.18
    in relevant part, that:
    ‘Major Federal action’ includes actions with effects
    that may be major and which are potentially subject to
    Federal control and responsibility Actions
    include the circumstance where the responsible
    officials fail to act and that failure to act is
    reviewable by courts or administrative tribunals under
    the Administrative Procedure Act or other applicable
    law as agency action,
    (a) Actions include new and continuing activities,
    including projects and programs entirely or partly
    financed, assisted, conducted, regulated, or approved
    by federal agencies; new or revised agency rules,
    regulations, plans, policies, or procedures; and
    legislative proposals.
    (b) Federal actions tend to fall within one of the
    following categories:
    (4) Approval of specific projects, such as
    construction or management activities located
    in a defined geographic area. Projects
    include actions approved by permit or other
    regulatory decision as well as federal and
    federally assisted activities.
    F.R. § 1508.18.
    Plaintiff, conceding that the Holcomb Expansion Project is
    has sought to demonstrate that RUS's
    actions fall within the scope of § 1508.l8 on two primary
    grounds.
    First, plaintiff argues that RUS's actions with respect
    27
    to Sunflower amounted to approvals of the Holcomb Expansion
    Project such that the project was “potentially subject to Federal
    control and responsibility” within the meaning of § l508.18.
    Second, plaintiff argues that RUS provided sufficient financial
    and other assistance to the Holcomb Expansion Project to make its
    involvement a major federal action under NEPA. As discussed
    below, the Court concludes plaintiff has demonstrated that RUS's
    involvement in the Holcomb Expansion Project amounted to major
    federal action under either analysis.
    ii. Federal Approva1s
    As noted above, CEQ regulation § 1508.l8 provides that
    actions by a federal agency “with effects that may be major and
    which are potentially subject to Federal control and
    responsibility” are major federal actions such that the
    requirements of NEPA apply. 40 C.F.R. § l508.18. Furthermore,
    “[a]ctions include new and continuing activities, including
    projects and programs . . . approved by federal agencies.” 40
    C.F.R. § 1508.l8(a). ln addition, § 1508.18(b)(4) states in its
    non-exhaustive list of major federal actions that actions include
    “[a]pproval of specific projects,” such as “actions approved by
    permit or other regulatory decision as well as federal and
    federally assisted activities.” 40 C.F.R. § 1508.18(b)(4).
    Although defendants concede that a federal agency's involvement
    in a non-federal project may in some instances constitute a major
    28
    federal action, they argue that “affirmative conduct taken or
    approval given by a federal agency alone is not enough to turn a
    non-federal project into a major federal action.” Fed. Defs.'
    Opp'n Summ. J. at 8.
    This Circuit has addressed this issue in Fbundation on
    Economic Trends v. Heckler, 
    756 F.2d 143
    , in which the court
    affirmed a preliminary injunction enjoining the National
    Institutes of Health, a federal agency, from approving an
    experiment that would release genetica1ly engineered organisms
    into the open environment until an appropriate environmental
    assessment was complete. Id. Federal regulations require that
    any entity seeking to deliberately release such organisms obtain
    approval from the NlH before doing so. Id. at 149. The court
    concluded that the approval granted by the agency amounted to a
    major federal action such that NEPA applied. Id.; see also
    Citizens Alert Regarding Env’t v. EPA, 
    259 F. Supp. 2d 9
    , 20
    (D.D.C. 2003) (“[A] project may be deemed a major federal action
    even where federal money has not actually been provided. This
    happens most often in circumstances where federal entities have
    sufficient authority over the local project so as to control or
    influence its outcome.”)”
    w 0ther Circuits have reached the same conclusion. See,
    e.g., Md. Conservation Council, Inc. v. Gilchrist, 808 F.2d lO39,
    1042 (4th Cir. 1986) (“A non-federal project is considered a
    ‘federal action’ if it cannot ‘begin or continue without prior
    approval of a federal agency.’”) (quoting Biderman v. Mbrton, 497
    29
    Furthermore, an otherwise non-federal project can be
    “potentially subject to Federal control and responsibility”
    within the meaning of 40 C.F.R. § l508.18 as a result of
    contractual terms agreed upon between the federal agency and the
    non-federal parties involved in the project. For example, in
    Morris Cnty. Trust for Historic Pres. v. Pierce, 
    714 F.2d 271
    (3rd Cir. 1983), the court concluded that the terms of the
    contract between a federal agency, the Department of Housing and
    Urban Development (“HUD”) and the non-federal party “provided HUD
    with sufficient authority over the [project] to constitute major
    federal action.” Id. at 278.
    Turning now to the instant case, it is apparent that,
    throughout the long history of RUS's involvement in Sunflower,
    the federal agency retained substantial control over the Holcomb
    site, particularly as it related to the potential development of
    additional power plants, such as the Holcomb Expansion Project,
    As described in detail above, Sunflower’s debt to RUS was
    restructured twice, first in 1987 and then again in 2002. ln
    each instance, RUS conditioned its approval of the restructuring
    on its continued control over Sunflower.
    Crucially, one of the ways in which RUS elected to maintain
    F.2d 1141, 1147 (2d Cir. 1974)); NAACP v. Med. Ctr., Inc., 
    584 F.2d 619
    , 633 (3d Cir. 1978) (“[W]hen a federal agency gives a
    legally necessary discretionary approval enabling another
    significantly to impact on the environment, the agency may be
    required to file an ElS.”).
    30
    control over Sunflower was to require Sunflower, by the terms of
    the 2002 Restructuring, to agree that it would not “enter into
    any agreement or other arrangements . . . for the development of
    Holcomb Unit 2 without the prior written approval of RUS.” AR
    04391. Furthermore, Sunflower agreed that “[a]ny RUS approval
    will be on such terms and conditions as RUS, in its sole
    discretion, may require at such time.” AR 04391 (emphasis
    added). By this agreement, and in a myriad of other ways
    described above, RUS ensured that Sunflower would be unable to
    proceed with the development of a second power plant without the
    approval of RUS.” The approvals granted by RUS to Sunflower in
    2007 reflect the intention of the parties, made explicit during
    the 2002 Debt Restructuring, that RUS would maintain the ability
    “ In addition to the relevant contractual provisions,
    plaintiff identifies a series of RUS regulations which, according
    to plaintiff, “dictate that RUS approval for Sunflower’s actions
    was required.” Pl.’s Mem. Supp. Summ. J. at lO. The regulations
    cited include 7 C.F.R. § 1717.l202(b), as well as 7 C.F.R.
    § l7l7.608, 7 C.F.R. § l7l7.6l6, 7 C.F.R. § l717,657, 7 C.F.R.
    § l717.853, 7 C.F.R. § 1717 subpart M, and 7 C.F.R. § 1717
    subpart R. Section l717.1202(b), for example, is a provision in
    the subpart of RUS regulations dealing with the policies and
    standards of RUS with respect to the settlement of debts. lt
    states that “modifications regarding the debt owed by a borrower
    may be granted under the authority of the Administrator only by
    means of the explicit written approval of the Administrator in
    each case.” 7 C.F.R. § l717.1202(b). However, while
    § l7l7.l202(b) and the other cited regulations perhaps prevent
    Sunflower from proceeding with the plans for the Holcomb
    Expansion Project in the manner the company desired without RUS
    approval, plaintiff has not persuaded this Court that the
    provisions generally prevent a borrower from undertaking this
    type of project without RUS approval.
    31
    to influence the Holcomb Expansion Project. Simply put,
    Sunflower, without the prior approval of RUS, would not have been
    able to enter into the agreements with Tri-State relating to the
    Holcomb Expansion Project.
    The federal defendants do concede that if “approval of a
    substantial portion of the project is required,” a non-federal
    project becomes a major federal action, Fed. Defs.' Opp'n Summ.
    J. at 10. However, they argue that a major federal action only
    exists if the federal agency has “control over the entire non-
    federal project[.]” Fed. Defs.' Opp'n Summ. J. at 8 (emphasis
    added). Defendants’ argument relies largely on cases in which
    the involvement of the federal agency was limited to a discrete
    segment of a larger project. In those cases, the courts
    generally find that, while the federal agency might be expected
    to prepare an ElS with respect to the small segment in which they
    are involved, the federal agency was not required to prepare and
    ElS with respect to the entire project.” The instant case,
    m This is commonly seen in the cases involving the
    construction of a highway, a rail line or a power line. ln these
    instances, courts have repeatedly held that, while the federal
    agency might be expected to consider environmental impacts with
    respect to the small segment in which it was involved, the agency
    was not required to consider the environmental impact of the
    entire project if it had no involvement in the remaining portions
    of the project. See, e.g., Coal. for Underground Expansion v.
    Mineta, 
    333 F.3d 193
    , 198 (D.C. Cir. 2003) (holding that although
    “other parts of the [rail transit] system are federally funded,
    [this] does not make the discrete Clayton-Shrewsbury Extension
    federally funded.”); Weiss v. Kempthorne, 580 F. Supp. 2d l84,
    189 (D.D.C. 2008) (concluding that the consent by the National
    32
    however, does not involve a federal agency that gave an approval
    for a small, segmented portion of a larger project. The Holcomb
    Expansion Project, in its entirety, required approvals from RUS
    to proceed. Defendants’ reliance on case law involving this type
    of segmented construction projects is thus unpersuasive.
    Defendants also argue that the control maintained by RUS is
    irrelevant because the control reflected RUS's financial
    concerns, rather than environmental concerns, According to
    defendants, the restructuring agreements reflected “RUS’s primary
    concern . . . [to] mak[e] sure that Sunflower does not enter any
    financial relationships that would jeopardize its further and
    continued ability to repay RUS. . . . Under these loan documents,
    RUS has retained the authority to approve certain financial
    arrangements that Sunflower enters with regard to further
    development of the Holcomb Expansion Project in order to ensure
    repayment of its loans and loan guarantees.” Fed. Defs.' Opp'n
    Summ. J. at 21. Even assuming that RUS's primary objective in
    2002 and afterward has been to maximize federal debt recovery,
    the fact remains that in 2002 RUS elected to retain authority
    over the Holcomb Expansion Project and later, in 2007, gave
    necessary approvals which allowed the project to proceed. As
    Park Service to lease 22 acres of a public park as part of a 500
    acre development project did not make the entire, otherwise non-
    federal, development a major federal action).
    33
    such, RUS's actions became major federal actions within the
    meaning of NEPA.
    iii. Federal Assistance
    Actions which are “approved by federal agencies” are only
    one type of major federal action. CEQ regulations also define
    “major federal action” to include non-federal projects “entirely
    or partly financed . . . by federal agencies.” 40 C.F.R.
    § l508.l8(a). Accordingly, “federal funding is a significant
    indication that a project constitutes a major federal action[.]”
    Sw. Williamson Cnty. Cmty Ass’n v. Slater, 
    243 F.3d 270
    , 279 (6th
    Cir. 200l); see also Citizens Alert, 259 F. Supp. 2d at 19.“
    “ Regarding the lien subordination at issue in the instant
    case, the Court notes that federal assistance need not come in
    the form of monetary assistance to qualify as a major federal
    action. For example, in fund for Animals v. Clark, 27 F. Supp.
    2d 8, 13 (D.D.C. l998), the court concluded that the federal
    agency was “so intimately involved in the discussion and planning
    of the [bison] hunt, the federal defendants cannot now claim to
    have no responsibility under NEPA with respect to the hunt or the
    supplemental feeding programs.” Id.; see also Fund For Animals v.
    Mainella, 
    283 F. Supp. 2d 418
    , 432 (D. Mass. 2003) (“The
    administrative record reveals that [the federal agency] makes a
    substantial contribution of personnel and equipment to the
    management of the Seashore's hunting program, . . . Accordingly,
    there is sufficient federal participation to make [the program] a
    ‘major Federal action.’”). ln Scottsdale Mall v. Indiana, 
    549 F.2d 484
     (7th Cir. l977), the state defendants even attempted to
    avoid compliance with NEPA by returning federal funds and
    withdrawing a state highway project from a federal aid highway
    program, Id. at 485. The Seventh Circuit nonetheless held that
    NEPA applied. Id. at 489 (“0ur review of the record indicates
    federal participation in the programming, location, design,
    preliminary engineering, and right of way acquisition stages [of
    the highway by-pass project]. Hence, we have no difficulty
    concluding on the basis of the record before us that the entire
    by-pass project is a ‘major federal action’ within the meaning of
    34
    Furthermore, if the level of federal involvement in the non-
    federal project amounts to the creation of a joint venture or
    partnership between the federal agency and a non-federal entity,
    federal courts have considered the arrangement to be a major
    federal action such that even the non-federal entity may be
    enjoined from violating NEPA. See, e.g., Fund for Animals v.
    Lujan, 962 F.2d 139l, 1397 (9th Cir. l992) (“[A] nonfederal actor
    that enters into a partnership or joint venture whereby the
    federal government provides goods, services, or financing may be
    enjoined from violating NEPA.”); Landmark West! v. USPS, 840 F.
    Supp. 994, 1000 (S.D.N.Y. 1993); Dalsis v. Hills, 
    424 F. Supp. 784
     (W.D.N.Y. 1976).
    Federal funding provided solely for the purpose of
    conducting an ElS or other type of preliminary appraisal, prior
    to other involvement in the project, is generally considered
    insufficient to constitute a major federal action. In Macht v.
    Skinner, 
    916 F.2d 13
     (D.C. Cir. 1990), for example, the D.C.
    Circuit declined to apply NEPA to a non-federal project for the
    construction of a light rail system, in part, because, although
    the relevant federal agency granted the state $2.5 million, the
    funding was for the purpose of performing an EIS for possible
    extensions to the light rail system. The court stated that
    because “the Light Rail Project does not yet involve major
    42 U.S.C. § 4332(C) and that an ElS is required[.]”).
    35
    federal action, we do not decide whether NEPA may require an
    environmental analysis if [the federal agency] ultimately decides
    to fund construction of the extensions. . . . If such an
    eventuality occurs, appellants may renew their claim that an ElS
    is required prior to the disbursement of federal funds or
    question the scope of the ElS[.]” Id. at 17; see also Citizens
    Alert, 259 F. Supp. 2d at 17 (“[B]ecause ‘federal financial
    assistance to the planning process in no way implies a commitment
    by the federal agency to . . . undertake, fund, or approve any
    action that directly affects the human environment,’ such funding
    does not render an otherwise state or local project sufficiently
    federal to make NEPA applicable.”) (quoting Atlanta Coal. Transp.
    Crisis v. Atlanta Reg’l Comm’n, 599 F.2d l333, 1347 (5th Cir.
    1979)).“
    In situations in which a project is only partially funded by
    the federal agency, federal courts have in some instances looked
    to the proportion of federal funding to non-federal funding to
    determine whether there is a major federal action. lf the amount
    of federal funding is insignificant or only provided with respect
    “ ln Ka Makani, 
    295 F.3d 955
    , the Ninth Circuit came to a
    similar conclusion as the court in Macht. Addressing the
    question of whether federal funding for the development of a
    water resource system constituted a major federal action, the
    court concluded that NEPA did not apply, in part, because the
    federal funding was “clearly designated for use in the
    preparation of an ElS, and at most, other preliminary activities
    that would have no real impact on the physical environment[.]"
    Ka Makani, 295 F.3d at 962.
    36
    to a small segment of the project, the involvement of the federal
    agency may not constitute a “major federal action.” See, e.g.,
    Rattlesnake Coal. v. EPA, 
    509 F.3d 1095
    , 1101 (9th Cir. 2007)
    (“While significant federal funding can turn what would otherwise
    be a state or local project into a major federal action,
    consideration must be given to a great disparity in the
    expenditures forecast for the local and federal portions of the
    entire program.”) (internal quotation marks omitted); Ka Makani,
    295 F.3d at 960 (same); Sancho v. Dep’t of Energy, 578 F. Supp.
    2d 1258, 1267 (D. Haw. 2008) (holding that the contribution by a
    federal agency of $531 million toward a project did not
    constitute a major federal action because the funding represented
    less than 10% of the $5.84 billion project cost); but cf. Sierra
    Club v. Fish & Wildlife Serv., 
    235 F. Supp. 2d 1109
     (D. Or. 2002)
    (“Given the overwhelming percentage of federal dollars involved,
    and the fact that the amount itself, regardless of the percentage
    it represents, is more than $3 million, the federal funding
    contribution alone is probably sufficient to ‘federalize' the
    project.”).
    Finally, “where the federal government has not made a ‘firm
    commitment' to fund the project, the non-federal actor’s mere
    anticipation of that money does not convert an otherwise local
    project into a federal one.” Citizens Alert, 259 F. Supp. 2d at
    24 (citing Macht, 916 F.2d at 17); see also Los Ranchos de
    37
    Albuquerque v. Barnhart, 906 F.2d l477, 1481 (10th Cir. 1990)
    (“[B]ecause [the non-federal parties] are only eligible for
    federal assistance, that eligibility in itself is not sufficient
    to establish a major federal action requiring the [federal
    agency] to comply with the requirements of NEPA.”).
    1n the instant case, plaintiff argues that RUS gave
    sufficient financial assistance to Sunflower to qualify as a
    major federal action. ln particular, plaintiff asserts that RUS
    gave substantial financial assistance to Sunflower in connection
    with the 2002 Restructuring, during which RUS “effectively wrote
    off hundreds of millions of dollars in Sunflower’s loans so that
    the project could proceed.” Pl.’s Mem. Supp. Summ. J. at 19-20.
    Defendants, on the other hand, assert that “not a single cent of
    Old Sunflower’s debt was written off as a result of the
    restructuring.” Sunflower’s Opp'n Summ. J. at 18.
    The Court agrees with the plaintiff that, while defendants
    may be correct that Old Sunflower’s debts were not explicitly
    written off, the consequence of the restructuring was to leave
    Old Sunflower with no assets or ability to pay its own debts off.
    As discussed in detail above, under the terms of the 1987 DRA,
    Old Sunflower issued three classes of promissory notes, the A
    Notes, B Notes, and C Notes. REA's share of the principal
    balance on the A Notes was $294.5 million; on the B Notes it was
    $98.3 million; on the C Notes it was $61.4 million. With respect
    38
    to the B Notes in particular, Old Sunflower was at risk of
    defaulting by 2002. With the capitalized interest, the principal
    owed to RUS on these notes had risen to $413.9 million. When New
    Sunflower purchased most of Old Sunflower’s assets during the
    2002 Debt Restructuring, it issued new promissory notes to RUS.
    While it may be true that RUS has a chance of recovering more
    money as a result of the 2002 Restructuring than it would have if
    it had not approved the restructuring and Old Sunflower had
    defaulted, the new set of promissory notes nonetheless amounted
    to substantially less debt for New Sunflower than Old Sunflower
    had been burdened with.” As a consequence, RUS effectively
    provided financing to Sunflower for the Holcomb Expansion
    Project.
    The federal defendants themselves seem to concede that RUS
    will, in the future, write some portion of Sunflower’s debt off;
    they merely deny that the amount is known. See, e.g., Fed.
    Defs.' Opp'n Summ. J. at 24 (“RUS has not written any of [Old]
    Sunflower’s debt off to date. The exact and final amount of the
    RUS loss will not be known until as late as 2021, when all the
    notes have matured.”).
    Defendants’ arguments that any financial assistance provided
    to Sunflower was not substantial enough to be considered a major
    ” See discussion, supra, of the new B Notes, the Residual
    Value Notes, and the Holcomb 3 Notes issued in connection with
    the 2002 Debt Restructuring.
    39
    Redacted
    federal action are unpersuasive. Neither party offers a
    definitive estimate of how much Sunflower’s debt was reduced
    overall, but a comparison of the notes issued under the 1987 DRA
    and those issued under the 2002 Debt Restructuring convinces this
    Court that it is indeed substantial. Furthermore, the Court
    notes that the administrative record reflects, and the parties
    agree, that Sunflower realized a tax benefit as a result of the
    2002 Debt Restructuring in the amount of  AR
    1-
    Defendants assert that, even assuming Sunflower obtained
    financial assistance from RUS in connection with the 2002
    Restructuring, such assistance was unrelated to the Holcomb
    Expansion Project specifically. However, the record reflects
    otherwise. Crucially, the agency provided this assistance to
    Sunflower in conjunction with the 2002 Restructuring - the
    direct, intended consequence of which was to divide Old
    Sunflower’s assets such that Holcomb Unit 1 and most other assets
    were acquired by New Sunflower (the entity now burdened with the
    debt to RUS), whereas the land and common facilities necessary
    for the Holcomb Expansion Project were acquired by a separate
    entity, namely HCF. Additiona1ly, RUS agreed to release its lien
    on the Holcomb Unit 2 site. RUS's actions reflect the agency's
    intention to make the Holcomb Expansion Project possible through
    the assistance provided in 2002.
    40
    Federa1 defendants repeatedly cite to National Organization
    for Reform of Marijuana Laws v. Drug Enforcement Administration,
    
    545 F. Supp. 981
     (D.D.C. 1982), in support of their argument on
    this point. However, the Court finds this comparison flawed. ln
    Marijuana Laws, although the Drug Enforcement Agency (“DEA”)
    provided financial and other support to the state of Florida for
    marijuana law enforcement generally, the specific project at
    issue the Marijuana Laws case was the plan to eradicate marijuana
    plants through an herbicidal spraying program, Id. With respect
    to the spraying program in particular, the court concluded that
    “federal funding, federal control, and federal ‘go-ahead’ actions
    are lacking.” Id. at 984.“ ln contrast to Marijuana Laws, RUS
    provided significant federal assistance to enable the Holcomb
    Expansion Project.
    ln addition to the financial benefits granted to Sunflower
    through the debt restructuring, RUS provided additional
    w Similarly, defendants’ reliance on Citizens Alert, 259 F.
    Supp. 2d 9, is misplaced. The construction of the pipeline at
    issue in Citizens Alert was largely funded under an indirect EPA
    program whereby the EPA granted sums of money to states, who in
    turn “disperse[d] this money for projects of their [the states’]
    choosing[.]” Id. at 13-14. ln contrast to RUS's decision to
    provide direct assistance to Sunflower, the EPA regulations at
    issue in Citizen Alert explicitly delegated the environmental
    review process to the state. Id. at 14 n.2. lt is also
    significant that the court in Citizens Alert noted that the EPA
    was considering directly funding a small portion of the project.
    The court stated that it assumed for the purposes of the dispute
    before it, that “if EPA actually provides the $l.7 million
    appropriated by Congress . . . that funding decision would itself
    be a ‘major federal action.’” Id. at 16.
    41
    assistance to Sunflower when it committed to releasing its lien
    on the Holcomb Unit 2 site and the Common Facilities, if and when
    the Holcomb Unit 2 generating plant is developed. Defendants
    argue that the release relates only to “a very small portion of
    the total Holcomb site.” Fed. Defs.' Opp'n Summ. J. at 25.
    However, the portions of the Holcomb site containing the Holcomb
    Unit 2 site and the Common Facilities contain all the necessary
    properties for the development of the Holcomb Expansion Project.
    At issue in this action is the assistance provided by RUS in
    support of the Holcomb Expansion Project, not the entire Holcomb
    site.
    According1y, the Court finds that the involvement of RUS
    in Sunflower amounted to a project “entirely or partly financed”
    by a federal agency. 40 C.F.R. § l508.l8(a). Contrary to
    defendants’ arguments, RUS did not merely provide assistance to
    some discrete aspect of the Holcomb Expansion Project, nor was
    its contribution insignificant. Accordingly, its actions were
    subject to the requirements of NEPA.
    ln sum, the Court concludes that, both because RUS gave
    necessary approvals for the Holcomb Expansion Project and because
    RUS provided financial assistance to the project, the Holcomb
    Expansion Project was subject to “Federal control and
    responsibility”, 40 C.F.R. § l508.l8, and therefore RUS's
    42
    involvement amounted to a major federal action within the meaning
    Of NEPA.
    D. Whether RUS was Contractually Prevented from Exercising
    Contro1 Over the Holcomb Expansion Project
    Sunflower makes the additional argument that, although some
    provisions of the loan contracts between Sunflower and RUS
    require Sunflower to seek approval from RUS before engaging in
    certain activities, an attempt by RUS to impose environmental
    standards as a condition of its approval would have been a breach
    of the agreements between the parties, Citing Centex Corporation
    v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005), Sunflower
    argues that, as a matter of federal common law governing the
    interpretation of contracts to which the United States is a
    party, each party is under an obligation “not to act so as to
    destroy the reasonable expectations of the other party.”
    Sunflower Opp'n Summ. J. 13-14 (quoting Centex, 395 F.3d at
    1304).
    According to Sunflower, “RUS was created by Congress to
    serve as a lender, not a regulator,” and it “was with RUS's
    statutorily defined role as a lender, and only a lender, in mind
    that Sunflower agreed to the terms of the contracts.” Sunflower
    Opp'n Summ. J. at 14. Therefore, Sunflower “could not reasonably
    have expected that RUS could review or impose conditions on the
    design details of any new generating units,” and “nothing in the
    contract provisions . . . gives RUS the authority to alter plans
    43
    or withhold its approval or consent for a particular project for
    environmental reasons.” Sunflower Opp'n Summ. J. at 15, l7. ln
    light of Sunflower’s expectations at the time the contracts were
    signed, Sunflower now argues that “RUS would have been acting in
    bad faith and in an objectively unreasonable manner had it
    attempted to impose environmental standards as a condition of its
    consents.” Sunflower Opp'n Summ. J. at 16.
    The Court disagrees with Sunflower’s position. First, the
    terms of the 2002 Restructuring explicitly gave RUS broad
    authority to place conditions on any approvals it granted in
    connection with the Holcomb Expansion Project. AR 04391.
    Sunflower has not pointed to any restriction, explicit or
    otherwise, in the agreements between RUS and Sunflower that would
    bar RUS from considering the environmental impacts of the Holcomb
    Expansion Project or conditioning its approval on a reduction of
    the environmental impact of the Holcomb Expansion Project.
    Furthermore, while it is undeniable that the focus of the Rural
    Electrification Act of 1936, 7 U.S.C. §§ 901-818, was indeed to
    give the Secretary of Agriculture the authority to make loans for
    rural electrification projects, Congress no less clearly intended
    the provisions of NEPA to apply to all federal agencies. 42
    U.S.C. § 4332. The agency may not contractually or otherwise
    avoid those statutorily defined obligations.
    44
    E. Whether RUS Had the Requisite Discretion
    In support of their assertion that NEPA does not apply to
    RUS's involvement in the Holcomb Expansion Project, defendants
    also argue that they lack the discretion to review the
    environmental impacts of the Holcomb Expansion Project. ln the
    words of the federal defendants:
    RUS has no discretion to meaningfully consider the
    alleged impacts from the Holcomb Expansion Project on
    global warming from carbon dioxide emissions, or on air
    quality from the emissions of other air pollutants.
    This is delegated to the Environmental Protection
    Agency and the State of Kansas. . . . RUS's authority
    over its borrowers is solely as a lender interested in
    repayment of a borrower’s debt to the Government in the
    agreed-upon time.
    Fed. Defs.' Opp'n Summ. J. at 30.
    This argument is wholly unpersuasive. NEPA not only
    explicitly gives all federal agencies the authority to consider
    environmental impacts, it compels them to do so. See 42 U.S.C.
    §4332; Fbund. on Econ. Trends, 756 F.2d at l47; Clark, 27
    F. Supp. 2d at 12 (“NEPA requires that all federal agencies
    prepare a detailed statement with respect to any major federal
    action significantly affecting the quality of the human
    environment.”).
    NEPA plainly applies to all federal agencies, irrespective
    of their primary functions. The defendants themselves concede
    that, not only did RUS conduct an E1S before granting Old
    Sunflower the loan in 1980, but also that “RUS’s actual approval
    45
    of a new loan . . . would be subject to NEPA.” Fed. Defs.' Reply
    at 6. Nor does defendants’ argument that the State of Kansas and
    the EPA also have regulatory authority over the Holcomb Expansion
    Project persuade the Court that RUS may ignore its
    responsibilities under NEPA.
    Defendants’ reliance on the Supreme Court’s decision in DOT
    v. Public Citizen, 
    541 U.S. 752
     (2004), is similarly
    unpersuasive. ln Public Citizen, a federal agency within the
    Department of Transportation proposed rules relating to safety
    regulations of Mexican motor carriers operating within the United
    States. Public Citizen, 
    541 U.S. 752
    , The regulations were
    promulgated in accordance with an executive order lifting the
    moratorium on Mexican motor carriers pursuant to the North
    American Free Trade Agreement (“NAFTA”). The federal agency
    prepared an environmental assessment (“EA”), a more limited
    document than the EIS, in which it evaluated a variety of
    environmental impacts in different scenarios. However, the EA
    did not evaluate the environmental effects that would result from
    the actual increase in cross-border operations of Mexican motor
    carriers; instead it focused on other effects, such as an
    increase in the number of roadside inspections. Plaintiffs
    challenged this omission, arguing that the agency violated NEPA
    by failing to consider the environmental impact of the increase
    in Mexican motor carriers in the EA. The Supreme Court ruled in
    46
    favor of the federal agency, concluding that the federal agency
    properly omitted this issue from consideration because the
    federal agency “has no ability to countermand the President's
    lifting of the moratorium or otherwise categorically to exclude
    Mexican motor carriers from operating within the United States,”
    and holding that “it would not . . . satisfy NEPA's ‘rule of
    reason' to require an agency to prepare a full E1S due to the
    environmental impact of an action it could not refuse to
    perform.” Id. at 766, 769.
    In contrast to Public Citizen, defendants in the instant
    action can point to no authority, executive or otherwise, that
    prohibits RUS from imposing conditions on Sunflower related to
    any identified environmental impacts of the Holcomb Expansion
    Project, nor have they cited any authority preventing RUS from
    modifying its course of action based on those environmental
    impacts, 0n the contrary, NEPA and the accompanying regulations
    explicitly grant RUS the requisite discretion, There is no
    material difference between the discretion RUS had in 1980, when
    it granted Old Sunflower the initial loan after preparing an EIS,
    and the discretion the agency has in connection with its more
    recent involvement in Sunflower.
    Sunflower’s argument, in particular, that RUS lacks
    discretion ignores a fundamental feature of prior case law on
    this subject, namely that an agency's role must be considered
    47
    “merely ministerial” to avoid the application of NEPA. As this
    Circuit has explained, “[i]f . . . the agency does not have
    sufficient discretion to affect the outcome of its actions, and
    its role is merely ministerial, the information that NEPA
    provides can have no effect on the agency's actions, and
    therefore NEPA is inapplicable.” Citizens Against Rails-to-
    Trails, 267 F.3d at 1151; see also Sugarloaf Citizens Ass'n v.
    FERC, 
    959 F.2d 508
    , 513 (4th Cir. l992) (addressing the role of a
    federal agency in granting certifications to certain types of
    power production facilities, and holding that the federal agency
    “does not have discretion to deny certification to any facility
    which meets the enumerated criteria and that its certification of
    this project was therefore merely a ministerial act.”).
    RUS's role in the Holcomb Expansion Project has not been
    “merely ministerial.” The complex new arrangements negotiated in
    2002 and then in 2007 evidence a significant amount of authority
    and discretion entrusted to this agency. As noted above,
    Sunflower agreed in 2002 that it would not “enter into any
    agreement or other arrangements . . . for the development of
    Holcomb Unit 2 without the prior written approval of RUS” and
    “[a]ny RUS approval will be on such terms and conditions as RUS,
    in its sole discretion, may require at such time[.]” AR 0439l
    (emphasis added). The federal defendants themselves acknowledge
    that RUS has the authority to decide “whether to finance, what to
    48
    finance, and the terms and conditions of a loan[.]” Fed. Defs.'
    Opp'n Summ. J. at 3l." This discretion gives the agency
    sufficient leverage to take the environmental impacts of its
    actions into account when making decisions.
    F. Whether RUS Regu1ations at 7 C.F.R. Pt. 1794 Exempt the
    Holcomb Expansion Project From NEPA Review
    Finally, defendants argue that RUS's actions are exempt from
    NEPA pursuant to environmental policy and procedure regulations
    implemented by RUS. These regulations, set forth in 7 C.F.R.
    Part l794, “contain[] the policies and procedures of [RUS] for
    implementing the requirements of [NEPA].” 17 C.F.R. § 1794.l.
    They are “intended to help RUS officials make decisions that are
    based on an understanding of environmental consequences, and take
    actions that protect, restore, and enhance the environment.” 7
    C.F.R. § l794.l(b). Defendants point specifically to 7 C.F.R.
    § l794.3 which states:
    The provisions of [7 C.F.R. Part l794] apply to actions
    by RUS including the approval of financial assistance
    pursuant to the Electric, Telecommunications, and Water
    and Waste Programs, the disposal of property held by
    RUS pursuant to such programs, and the issuance of new
    or revised rules, regulations, and bulletins.
    Approvals provided by RUS pursuant to loan contracts
    and security instruments, including approvals of lien
    accommodations, are not actions for the purposes of
    " The Court notes that the federal defendants have stated
    that they “do not entirely agree with Sunflower’s
    characterization of the consents and approvals as ‘ministerial.'
    Although some of the consents were ministerial, others are
    not[.]” Fed. Defs.' Resp. to Sunflower’s Mot. Dismiss at 7 n.4.
    49
    this part and the provisions of this part shall not
    apply to the exercise of such approvals.
    7 C.F.R. § l794.3 (emphasis added). Defendants argue that RUS’
    approvals amounted to no more than “[a]pprovals provided by RUS
    pursuant to loan contracts” and, accordingly, are exempt from
    NEPA under § 1794.3.
    As a threshold matter, the Court must determine whether
    defendants’ interpretation of § l794.3 is entitled to deference.
    Although ordinarily “an agency's construction of its own
    regulations is entitled to substantial deference,” Martin v.
    Occupational Safety and Health Review Commission, 
    499 U.S. 144
    ,
    150 (1991), an agency's “litigating positions are not entitled to
    deference when they are merely appellate counsel's post hoc
    rationalizations for agency action, advanced for the first time
    in the reviewing court.” Id. at 156; see also Bowen v.
    Georgetown Univ. Hosp., 
    488 U.S. 204
    , 212 (l998)(“[W]e have
    declined to give deference to an agency counsel's interpretation
    of a statute where the agency itself has articulated no position
    on the question, on the ground that ‘Congress has delegated to
    the administrative official and not to appellate counsel the
    responsibility for elaborating and enforcing statutory
    commands.’”) (quoting Inv. Co. Inst. v. Camp, 401 U.S. 6l7, 628
    (1971)).
    50
    An agency's litigation position is nevertheless given
    deference in certain limited circumstances, as stated in Auer v.
    Robbins, 
    519 U.S. 452
     (1997). As this Circuit has explained:
    There are at least three preconditions for applying
    this so~called Auer deference. First, the language of
    the regulation in question must be ambiguous, lest a
    substantively new rule be promulgated under the guise
    of interpretation. Second, there must be ‘no reason to
    suspect that the interpretation does not reflect the
    agency's fair and considered judgment on the matter in
    question.' Finally, the agency's reading of its
    regulation must be fairly supported by the text of the
    regulation itself, so as to ensure that adequate notice
    of that interpretation is contained within the rule
    itse1f.
    Drake v. FHA, 
    291 F.3d 59
    , 68 (D.C. Cir. 2002) (citing Auer, 519
    U.S. at 461-462).
    In the instant case, the Court concludes that the
    defendants’ position with respect to § l794.3 is not entitled to
    substantial deference. First, at least with respect to RUS's
    commitment to release the lien on the Holcomb 2 site and the
    Common Facilities, § l794.3 is ambiguous in light of conflicting
    language in another RUS regulation, namely 7 C.F.R. § 1717.850.
    Section l717.850 states that “[u]nder certain circumstances, such
    as when the project does not qualify for a categorical exclusion,
    the environmental requirements of 7 CFR part 1794 may apply to
    applications for lien accommodations, subordinations, and
    releases.” Id. (emphasis added). Second, defendants point to no
    evidence in the record that the agency itself evaluated whether
    NEPA applied to its actions during the 2002 Restructuring or the
    51
    subsequent approvals in 2007. Finally, for the reasons that
    follow, the Court cannot conclude that the agency's reading of
    the regulation is “fairly supported by the text of the regulation
    itself.” Drake, 291 F.3d at 68. Specifically, the Court does
    not find the agency's actions can be fairly stated to amount to
    mere “approva1s provided by RUS pursuant to loan contracts.” 7
    C.F.R. § l794.3.
    With respect to the 2002 Restructuring, the federal
    defendants argue that the approvals provided by RUS were granted
    pursuant to the 1987 DRA. ln support of their argument, the
    federal defendants point to text in the 2002 agreements that
    identifies provisions in the 1987 DRA requiring Sunflower to seek
    written approval from RUS before it undertook specified actions,
    See Fed. Defs.' Reply at 5-6 (citing AR 222, AR 3952).
    However, Sunflower did more than simply request approval
    from RUS pursuant to these old loan contracts, and RUS did more
    than simply grant the approval. Instead, entirely new agreements
    were drafted, entirely new and different obligations were
    created, including new promissory notes, and entirely new parties
    were subject to those obligations. With respect to the RUS's
    release of the lien on the Holcomb 2 site, RUS also did not
    approve the lien subordination as an approval pursuant the then~
    existing 1987 DRA. Instead, the lien subordination was part of
    the new arrangements created in 2002.
    52
    Although it is perhaps a closer call with respect to the
    approvals granted in 2007, ultimately the Court concludes that
    here too, the agency did not simply grant approvals pursuant to
    pre-existing loan contracts. Once again, new promissory notes
    were issued and entirely new agreements between RUS and Sunflower
    were created, such as the Additional Consideration Letter.
    The Court also finds that, even assuming RUS's actions were
    consistent with its own regulation § 1794.3, such an
    interpretation would be invalid as applied in the instant case
    because it would conflict with NEPA and the implementing
    regulations promulgated by the CEQ. The agency is not entitled
    to substantial deference with respect to the interpretation of
    the CEQ regulations, including § 1508.18 defining “major federal
    action.” See, e.g., Grand Canyon Trust v. FAA, 
    209 F.3d 339
    , 342
    (6th Cir. 2002) (“Although federal agencies have discretion to
    decide whether a proposed action is significant enough to warrant
    preparation of an E1S, the court owes no deference to the
    [Federal Aviation Administration’s] interpretation of NEPA or the
    CEQ regulations because NEPA is addressed to all federal agencies
    and Congress did not entrust administration of NEPA to the
    [Federal Aviation Administration] alone.”)(internal quotation
    marks omitted); see also (Citizens Against Rails-to~Trails, 267
    F.2d at 1150 (“Because NEPA’s mandate is addressed to all federal
    agencies, the [Surface Transportation Board’s] determination that
    53
    NEPA is inapplicable . . . is not entitled to the deference that
    courts must accord to an agency's interpretation of its governing
    statute.”); Mcrris Cnty., 714 F.2d at 276 (“CEQ guidelines are
    entitled to substantial deference in interpreting the meaning of
    NEPA provisions, even when CEQ regulations are in conflict with
    an interpretation of NEPA adopted by one of the Federal
    agencies.”) (citing Andrus v. Sierra Club, 
    442 U.S. 347
    ,
    358(1979)).
    Accordingly, under NEPA and the relevant CEQ regulations,
    RUS's actions taken with respect to Sunflower and the Holcomb
    Expansion Project are properly considered major federal actions
    and are therefore subject to the requirements of NEPA, in
    particular 42 U.S.C. § 4332.
    IV. CONCLUSION
    For the foregoing reasons, Sunflower’s motion to dismiss the
    complaint as moot is DENIED, plaintiff's motion for summary
    judgment is GRANTED, federal defendants’ cross-motion for summary
    judgment is DENIED, and Sunflower’s cross-motion for summary
    judgment is DENIED. Furthermore, defendants’ request for an
    additional opportunity to brief the issues relating to the
    appropriate remedy is hereby GRANTED. An appropriate Order
    accompanies this Memorandum Opinion.
    SIGNED: Emmet G. Su11ivan
    United States District Court Judge
    March 29, 2011
    54
    

Document Info

Docket Number: Civil Action No. 2007-1860

Judges: Judge Emmet G. Sullivan

Filed Date: 4/18/2011

Precedential Status: Precedential

Modified Date: 9/5/2016

Authorities (37)

southwest-williamson-county-community-association-inc-a-non-profit , 243 F.3d 270 ( 2001 )

County of Los Angeles v. Davis , 99 S. Ct. 1379 ( 1979 )

daingerfield-island-protective-society-v-manuel-lujan-jr-secretary , 920 F.2d 32 ( 1990 )

Vieux Carre Property Owners, Residents and Associates, Inc. ... , 948 F.2d 1436 ( 1991 )

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

Sierra Club v. United States Fish & Wildlife Service , 235 F. Supp. 2d 1109 ( 2002 )

foundation-on-economic-trends-v-margaret-m-heckler-secretary-of-the , 756 F.2d 143 ( 1985 )

Ctzn Agnst Rails v. STB , 267 F.3d 1144 ( 2001 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Coalition for Underground Expansion v. Mineta , 333 F.3d 193 ( 2003 )

sugarloaf-citizens-association-karen-kalla-j-houston-miller-beverly-thoms , 959 F.2d 508 ( 1992 )

national-association-for-the-advancement-of-colored-people-puerto-rican , 584 F.2d 619 ( 1978 )

Feldman v. Bomar , 518 F.3d 637 ( 2008 )

Andrus v. Sierra Club , 99 S. Ct. 2335 ( 1979 )

Fund for Animals, Inc. v. U.S. Bureau of Land Management , 460 F.3d 13 ( 2006 )

Rattlesnake Coalition v. U.S. Environmental Protection ... , 53 A.L.R. Fed. 2d 723 ( 2007 )

Centex Corp. v. United States , 395 F.3d 1283 ( 2005 )

Fund for Animals v. Mainella , 283 F. Supp. 2d 418 ( 2003 )

Dalsis v. Hills , 424 F. Supp. 784 ( 1976 )

NATIONAL ORG'N v. US Drug Enforcement Admin. , 545 F. Supp. 981 ( 1982 )

View All Authorities »