Micula v. Government of Romania ( 2019 )


Menu:
  •                            UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    _________________________________________
    )
    IOAN MICULA, et al.,                      )
    )
    Petitioners,                        )
    )
    v.                           )                  Case No. 17-cv-02332 (APM)
    )
    GOVERNMENT OF ROMANIA,                    )
    )
    Respondent.                         )
    _________________________________________ )
    MEMORANDUM OPINION
    I.     INTRODUCTION
    Petitioners Viorel Micula, Ioan Micula, and three entities they control have asked this court
    to confirm an arbitration award entered in their favor against Respondent Government of Romania
    (“Romania”) by a tribunal convened under the International Convention on the Settlement of
    Investment Disputes between States and Nationals of Other States. Confirming the award would
    render it an enforceable judgment in the United States. Romania raises a host of objections to
    confirming the award, including a challenge to the court’s subject matter jurisdiction. The
    European Commission, appearing as amicus curiae, also advocates against confirming the award.
    For the reasons that follow, the court grants the petition to confirm the arbitration award
    and enters judgment in favor of Petitioners.
    II.    BACKGROUND
    A.      Factual Background
    1.      The ICSID Convention
    The International Convention on the Settlement of Investment Disputes between States and
    Nationals of Other States (“Convention”) is “a multilateral treaty aimed at encouraging and
    facilitating private foreign investment in developing countries.” Mobil Cerro Negro, Ltd. v.
    Bolivarian Republic of Venezuela, 
    863 F.3d 96
    , 100 (2d Cir. 2017). The Convention carries out
    that purpose by providing a legal framework and procedural mechanism to resolve disputes between
    private investors and governments. See Convention on the Settlement of Investment Disputes
    between States and Nationals of Other States Preamble, Mar. 18, 1965, T.I.A.S. No. 6090, 17 U.S.T.
    1270. The Convention establishes the International Centre for Settlement of Investment Disputes,
    or “ICSID,” as an international institution that operates under the auspices of the World Bank.
    See Mobil Cerro 
    Negro, 863 F.3d at 101
    . ICSID convenes arbitration panels “to adjudicate disputes
    between international investors and host governments in ‘Contracting States.’” 
    Id. Romania and
    Sweden are signatories to the ICSID Convention. So, too, is the United States.
    “Any Contracting State or any national of a Contracting State” may ask ICSID to convene
    an arbitral tribunal to resolve a dispute. Convention art. 36. The tribunal is tasked with adjudicating
    the dispute and, if warranted, issuing a written award that addresses “every question submitted to
    the Tribunal” and “state[s] the reasons upon which [the award] is based.” 
    Id. art. 48.
    A party may
    contest the tribunal’s decision, consistent with the procedures set forth in the Convention. See 
    id. arts. 51–52.
    But critically, “except to the extent that enforcement [is] stayed,” the tribunal’s ruling
    is “binding on the parties and shall not be subject to any appeal or to any other remedy” other than
    2
    those afforded under the Convention. 
    Id. art. 53.
    In other words, the domestic courts of member
    countries lack the authority to review the merits of a decision by an ICSID tribunal.
    The Convention does not, however, confer upon ICSID the power to enforce arbitral awards.
    It left that function to its Contracting States. Article 54(1) of the Convention provides: “Each
    Contracting State shall recognize an award rendered pursuant to this Convention as binding and
    enforce the pecuniary obligations imposed by that award within its territories as if it were a final
    judgment of a court in that State.” 
    Id. art. 54(1).
    Contracting States that, like the United States,
    have a federal system of government “may enforce such an award in or through [their] federal courts
    and may provide that such courts shall treat the award as if it were a final judgment of the courts of
    a constituent state.” 
    Id. The ICSID
    Convention also is not self-executing. See Medellin v. Texas, 
    552 U.S. 491
    ,
    505–06 (2008) (explaining when a treaty obligation requires legislation to become domestic law).
    Contracting States must “take such legislative or other measures as may be necessary for making
    the provisions of this Convention effective in [their] territories.” Convention art. 69. In the United
    States, Congress gave the ICSID Convention domestic effect by passing the Convention on the
    Settlement of Investment Disputes Act of 1966. See Convention on the Settlement of Investment
    Disputes Act of 1966, Pub. Law 89–532, 80 Stat. 334 (1966) (codified at 22 U.S.C. §§ 1650 and
    1650a). Section 3 of the Act addresses the enforcement of ICSID arbitration awards in the United
    States. It provides in relevant part: “The pecuniary obligations imposed by [an ICSID] award shall
    be enforced and shall be given the same full faith and credit as if the award were a final judgment
    of a court of general jurisdiction of one of the several States.” 22 U.S.C. § 1650a(a). Federal courts
    are vested with “exclusive jurisdiction over actions and proceedings” to enforce ICSID awards.
    
    Id. § 1650a(b).
    3
    2.     Events Leading to the ICSID Arbitration
    This case arises out of a dispute between Swedish investors and Romania. Following the
    overthrow of the communist regime of Nicolae Ceausescu in December 1989, the country of
    Romania found itself in dire economic and social circumstances. See Ioan Micula, et al. v.
    Romania, ICSID Case No. ARB/05/20 (Dec. 11, 2013), ECF No. 1-1–1-4 [hereinafter Final
    Decision], ¶ 137. In response to these problems, Romania adopted a series of measures designed
    to attract and promote investment. 
    Id. ¶¶ 138–144.
    Among the measures was Emergency
    Government Ordinance No. 24/1998 (“EGO 24”), which established a framework for granting
    incentives to invest in “disfavored” regions of Romania. 
    Id. ¶ 145.
    The petitioners in this case are Swedish nationals Viorel and Ioan Micula, along with three
    companies they control, S.C. European Food S.A., S.C. Starmill S.R.L., and S.C. Multipack S.R.L.
    See Petition to Confirm ICSID Award, ECF No. 1 [hereinafter Pet.], ¶¶ 8–12. Starting in 1998, in
    reliance on the incentives offered by EGO 24, Petitioners began to build an integrated food platform
    designed to produce consumer products and beverages for the Romanian market. Final Decision
    ¶¶ 166–172.
    In August 2004, Romania thwarted Petitioners’ plans when it announced that it would repeal
    EGO 24, effective February 22, 2005. 
    Id. ¶ 241.
    Romania made the repeal decision as part of the
    process of becoming a member of the European Union (“EU”). 
    Id. ¶¶ 234–239.
    The action
    followed Romania’s receipt of advice from the European Commission—an institution of the
    European Union that is responsible for ensuring the proper application of EU treaties—that the
    incentives constituted “state aid” that was incompatible with the EU’s prohibition of such
    anticompetitive schemes. 
    Id. The incentives’
    repeal caused Petitioners to suffer cash constraints
    4
    that prevented them from completing the projects they had planned in reliance on EGO 24. 
    Id. ¶ 172.
    2.      The ICSID Arbitration
    In 2002, Romania entered a bilateral investment treaty (“Sweden-Romania BIT”) with the
    Kingdom of Sweden, which entered into force on April 1, 2003. Final Decision ¶ 226. That treaty
    granted certain protections to each country’s investors who invested in the other country, including
    the right to arbitrate investment disputes. See Agreement between the Government of the Kingdom
    of Sweden and the Government of Romania on the Promotion and Reciprocal Protection of
    Investments art. 2, Swed.-Rom., May 29, 2002, Law No. 541/2002 (Rom.) [hereinafter Sweden-
    Romania BIT].        Pertinent to the parties’ dispute is Article 7 of the Sweden-Romania BIT.
    See generally Ioan Micula, et al. v. Romania, ICSID Case No. ARB/05/20 (Sept. 24, 2008), ECF
    No. 62-2. It provides that disputes concerning investments are to be settled by international
    arbitration, before either an ICSID arbitral tribunal or an ad hoc tribunal established under the
    Arbitration Rules of the United Nations Commission on International Trade Law. See 
    id. ¶ 57;
    Sweden-Romania BIT art. 7.
    In response to Romania’s decision to revoke financial incentives, Petitioners initiated
    arbitration proceedings against Romania before an ICSID tribunal on August 2, 2005. Final
    Decision ¶ 10. Petitioners claimed that they had made investments in certain regions of Romania
    in reliance on the economic incentives. 
    Id. ¶ 131.
    The revocation of those incentives, Petitioners
    alleged, caused them to suffer significant financial losses, for which Romania was liable. 
    Id. ¶¶ 131,
    262. The ICSID tribunal agreed. In December 2013, the tribunal ruled for Petitioners and awarded
    monetary damages of 376,433,229 Romanian Leu (RON)—the equivalent of $116,317,868—plus
    5
    interest at the rate of the three-month Romanian Interbank Offer Rate, plus 5%, compounded on a
    quarterly basis with respect to certain amounts and periods (“the Award”). 
    Id. ¶ 1329.
    3.         Romania Joins the European Union
    Meanwhile, in parallel with the ICSID arbitral tribunal proceedings, Romania continued
    taking steps necessary to join the EU. 
    Id. ¶¶ 246–47.
    Romania formally joined the EU on January
    1, 2007—after Petitioners invoked their right to arbitration under the Sweden-Romania BIT but
    before the ICSID tribunal ruled in favor of Petitioners. 
    Id. ¶¶ 247–49.
    Shortly after the ICSID tribunal issued the award, the European Commission advised
    Romania that implementing or executing the Award would constitute impermissible new state aid,
    about which Romania would be required to notify the Commission. See Commission Decision
    (EU) 2015/1470 of 30 March 2015, ECF No. 51-2 [hereinafter State Aid Decision], ¶ 2. Three
    months later, in May 2014, the Commission issued a “suspension injunction,” prohibiting Romania
    from taking any action to fulfill any part of the Award not yet paid until the Commission reached
    a final decision on whether the Award constituted state aid. 
    Id. ¶ 6.
    As a result of the suspension injunction, Romania returned to ICSID. Invoking Article 52
    of the Convention, Romania asked ICSID to convene an ad hoc tribunal for the purpose of annulling
    the Award. 
    Id. ¶ 28.
    ICSID did so, and on August 7, 2014, the tribunal agreed to stay enforcement
    of the Award.       
    Id. It conditioned
    the stay, however, on Romania’s committing, without
    qualification, to pay the full Award if the ICSID tribunal decided not to annul the Award. 
    Id. Romania declined
    to provide the unconditional commitment to pay. 
    Id. ¶ 29.
    The tribunal then
    lifted the stay of enforcement on September 7, 2014. 
    Id. Nearly a
    year after issuing the suspension injunction, on March 30, 2015, the Commission
    issued its decision on whether the Award constituted state aid in violation of EU law (“the State
    6
    Aid Decision”). The Commission found that it did. 
    Id. ¶ 125.
    The Commission concluded that,
    because the benefits generated by Romania’s incentive law was unlawful state aid, so too was the
    Award, which sought to compensate Petitioners for the advantages negated by the incentives’
    repeal. 
    Id. ¶¶ 95,
    109–24. The Commission rejected Petitioners’ view that the ICSID Convention
    controlled, reasoning that EU law superseded the Sweden-Romania BIT. 
    Id. ¶¶ 126–29.
    The State
    Aid Decision concluded by ordering Romania not to pay any further amounts on the Award and
    to recover any amounts already paid. 
    Id. at 33,
    art. 2. Petitioners filed an appeal of the State Aid
    Decision with the General Court of the Court of Justice of the European Union, a constituent court
    of the EU’s highest court, the Court of Justice of the European Union (CJEU).
    In the meantime, the annulment proceedings before the ICSID ad hoc tribunal continued.
    Almost a year after the State Aid Decision, the ad hoc tribunal issued its final decision on February
    26, 2016. It rejected Romania’s effort to annul the Award. See Ioan Micula, et al. v. Romania,
    ICSID Case No. ARB/05/20 (Feb. 26, 2016), ECF No. 1-5. In so doing, the tribunal summarily
    rejected the argument put forward by the European Commission, which had intervened, that the
    Award was incompatible with EU law on state aid. See 
    id. ¶¶ 308–28.
    The ICSID ad hoc tribunal’s
    decision thus created a direct conflict with the Commission’s State Aid Decision.
    B.       Petitioners’ Efforts to Confirm the Award in the United States
    As Petitioners and Romania duked it out before the Commission and ICSID over the
    validity of the Award, Petitioners came to the United States to attempt to “confirm” the Award
    under 22 U.S.C. § 1650a. 1 A confirmed Award would render it an enforceable judgment in United
    1
    To be clear, the court uses the verb “confirm” in this Memorandum Opinion to mean the judicial act of “enforcing”
    an Award under § 1650a. As the Second Circuit and this court have held, § 1650a does not contemplate a
    “confirmation” or “recognition” procedure that is separate from “enforcing” an ICSID award. See Mobil Cerro 
    Negro, 863 F.3d at 118
    –20 & 118 n.18; Micula v. Gov’t of Romania, 
    104 F. Supp. 3d 42
    , 49 (D.D.C. 2015). Nevertheless,
    because Petitioners repeatedly use the term “confirm,” for sake of consistency the court does as well.
    7
    States courts. See generally Micula v. Gov’t of Rom., 
    104 F. Supp. 3d 42
    , 44 (D.D.C. 2015)
    [hereinafter Micula I]. Petitioners’ efforts to confirm the Award, and Romania’s corresponding
    efforts to resist confirmation, have proceeded on a long, winding road over five years along the I-
    95 corridor from Washington, D.C., to New York City, and back to Washington, D.C.
    The opening act took place here, before this court. On April 11, 2014, Petitioner Viorel
    Micula, proceeding only on his own behalf, filed a petition to confirm the Award. Citing the
    practice of the federal District Courts in the Southern District of New York (“SDNY”), Viorel
    urged this court to confirm the Award though an ex parte, summary proceeding. See 
    id. at 46.
    For
    that reason, Viorel never served the Government of Romania, and Romania did not formally
    appear. See 
    id. at 47.
    This court, however, refused to confirm the Award in an ex parte proceeding.
    See 
    id. at 52.
    The court held that § 1650a did not permit ex parte confirmation of an ICSID award,
    but instead required a petitioner to “file a plenary action, subject to the ordinary requirements of
    process under the Foreign Service Immunities Act [“FSIA”].” 
    Id. Viorel elected
    not to file such
    an action and voluntarily dismissed his petition.
    Five days after this court ruled, the other Petitioners, later joined by Viorel, sought a
    presumably more favorable legal terrain and filed a petition for confirmation in the SDNY. They
    initially found success. On April 21, 2015, the court confirmed the Award in an ex parte, summary
    proceeding, thereby converting the Award to a judgment. See Micula v. Gov’t of Rom., No. 15
    MISC. 107, 
    2015 WL 4643180
    , at *2 (S.D.N.Y. Aug. 5, 2015) (allowing proceeding to move
    forward ex parte). Romania later appeared and asked another judge in the SDNY to vacate the
    judgment on the ground that the ex parte proceeding violated the FSIA. See 
    id. at *3.
    Also, the
    European Commission filed an amicus brief in those proceedings, and it urged the court either to
    abstain from exercising jurisdiction or vacate the judgment on the grounds of foreign comity, the
    8
    act of state doctrine, and the foreign compulsion doctrine, each argument premised on the ongoing
    proceedings in Europe. See 
    id. at *2,
    *6–8. The court in the SDNY rejected all of these arguments
    and re-affirmed the judgment against Romania. See 
    id. at *3–8;
    see also Micula v. Gov’t of Rom.,
    No. 
    15 Misc. 107
    (LGS), 
    2015 WL 5257013
    (S.D.N.Y. Sept. 3, 2015) (rejecting second motion
    for reconsideration by Romania). Romania appealed.
    Petitioners’ victory proved to be fleeting. At the same time Romania was prosecuting its
    appeal, another sovereign, the Bolivarian Republic of Venezuela, was also fighting an SDNY
    District Court’s ex parte confirmation of an ICSID award in the Second Circuit. On July 11, 2017,
    the Second Circuit issued its decision in Mobil Cerro Negro, Ltd. v. Bolivarian Republic of
    Venezuela. The case involved three key holdings. The first was that the FSIA provides the sole
    basis for subject matter jurisdiction for proceedings under § 1650a, and that § 1650a does not itself
    confer such 
    jurisdiction. 863 F.3d at 112
    –15. Second, the court held the FSIA controls the manner
    of obtaining personal jurisdiction over a sovereign, and therefore confirming an ICSID award
    pursuant to a summary, ex parte proceeding was improper. See 
    id. at 116–21.
    Finally, the court
    found that a proceeding pursuant to § 1650a must be initiated like a procedure to enforce a state
    court judgment—by way of a plenary action with service upon the foreign sovereign. See 
    id. at 121–24.
    Based on these rulings in Mobil Cerro Negro, another panel of the Second Circuit on
    October 23, 2017, vacated the judgment against Romania. See Micula v. Gov’t of Romania, 714
    Fed. App’x 18, 21–22 (2d Cir. 2017). The panel also made clear that, under the FSIA’s venue
    provision, venue was proper only in the District of Columbia, see 
    id., thereby forcing
    Petitioners
    to return to this District Court.
    9
    C.       Proceedings Before this Court: To Stay or Not to Stay?
    If this case were a hypothetical in a law school class on Civil Procedure, Romania would
    get a failing grade. Its procedural maneuvers have caused confusion and unnecessary delay, and
    no doubt increased expenses for Petitioners.
    On November 6, 2017, Petitioners initiated this action once more before this court, filing
    their Petition to Confirm ICSID Arbitration Award and Enter Judgment.                              See Pet.      After
    overcoming Romania’s numerous objections to the validity of service under the FSIA—a process
    that took nearly a year 2—the court entered an Order setting November 6, 2018, as the deadline for
    Romania to answer the Petition. See Order, ECF No. 50 at 3. It also set November 20, 2018, as
    the due date for Petitioners’ renewed motion to confirm the arbitral award, and December 11,
    2018, as the due date for Romania’s opposition. See 
    id. Romania never
    answered the Petition. Instead, on November 6, 2018, it filed a lengthy
    memorandum of law in “Opposition” to the Petition. See Resp.’s Mem. of Law in Opp’n to Pet.,
    ECF No. 51 [hereinafter Resp’t Opp’n]. Its Opposition asserted that Romania had satisfied the
    Award and that the act of state and the foreign sovereign compulsion doctrines required the court
    to deny the Petition. See generally 
    id. Romania did
    not dispute the court’s subject matter
    jurisdiction. See 
    id. Petitioners timely
    filed their Motion for Judgment on the Pleadings or, In the
    Alternative, Summary Judgment on November 20, 2018. See Pet’rs Mot. for J. on the Pleadings
    or, In the Alternative, Summ. J., ECF No. 55. This is the operative motion before the court. 3 But
    Romania did not file an opposition to the Petition, as ordered. Instead, it moved to stay the
    2
    See Order, ECF No. 15; Order, ECF No. 16; Order, ECF No. 23; Order, ECF No. 50.
    3
    But it is not Petitioners’ first dispositive motion. Petitioners filed an initial Motion for Judgment and Confirmation
    of Arbitral Award, ECF No. 26, on June 28, 2018. Romania opposed the Motion, see ECF No. 29, and it became ripe
    on July 19, 2018, see ECF No. 34. As of that date, the status of proper service on Romania remained uncertain. As a
    result, Petitioners agreed to re-serve process on Romania, in a manner to which it did not object. See Notice, ECF No.
    36. Petitioners renewed service operated as a reset of the proceedings. On October 31, 2018, the court deemed moot
    the Motion filed on June 28, 2018, by Petitioners. See Order, ECF No. 50.
    10
    proceedings and asked the court to extend time to file a “responsive pleading” to the Petitioners’
    Motion for Judgment. See Resp’t Motion to Stay Proceedings, ECF No. 57 [hereinafter Resp’t
    Mot. to Stay]; Resp’t Mot. for Extension of Time to File Responsive Pleading, ECF No. 58. The
    reasons for Romania’s requested stay were Petitioners’ pending appeal of the State Aid Decision
    to the General Court of the Court of Justice of the European Union, as well as bankruptcy
    proceedings in Romania involving the entity Petitioners. See Resp’t Mem. of Law in Support of
    Resp’t Mot. to Stay, ECF No. 57-1. On December 26, 2018, Petitioners filed oppositions to these
    motions, as well as a reply in support of its Motion for Judgment, even though Romania had not
    filed an opposition to their motion. See ECF Nos. 61, 63, 64. Romania moved to strike Petitioners’
    reply, setting off yet another series of briefings. See ECF Nos. 65, 66, 69. To date, Romania has
    yet to formally oppose Respondents’ Motion for Judgment.
    The European Commission entered these proceedings as amicus curiae on December 11,
    2019. See Br. of Amicus Brief the European Commission in Support of Romania, ECF No. 60
    [hereinafter EC Amicus Br.]. The Commission took the position that the court must deny the
    Petition.   It argued that the court lacked subject matter jurisdiction under the FSIA and,
    correspondingly, lacked authority under § 1650a to confirm the Award. Of particular note, the
    Commission drew the court’s attention to a recent decision of the European Court of Justice in
    Slovak Republic v. Achmea BV. See 
    id. at 7–8
    (citing Slovak Republic v. Achmea, Case C0284/16
    (6 March 2018), ECLI:EU:C:108:158, ECF No. 51-3). More on Achmea below. But for present
    purposes it suffices to say that the Commission argued that the decision in Achmea rendered the
    arbitration agreement in the Sweden-Romania BIT invalid and unenforceable and, for that reason,
    the court lacked subject matter jurisdiction under the FSIA. See 
    id. at 7–8
    , 10–12. In addition to
    this jurisdictional argument, the Commission also contended, as it had in the SDNY proceedings,
    11
    that the act of state doctrine and the foreign compulsion doctrine barred confirmation.
    See generally 
    id. Petitioners opposed
    the Commission’s arguments. See Pet’rs Mem. of Law in
    Response to Br. of Commission, ECF No. 62.
    The Commission’s brief apparently triggered a eureka moment for Romania. In its reply
    brief in support of its Motion for Stay, Romania asserted for the first time that the court lacks
    subject matter jurisdiction to confirm the Award. See Resp’t Reply Mem. in Support of Resp’t
    Mot. to Stay, ECF No. 68 [hereinafter Resp’t Reply], at 14–17. Like the European Commission,
    Romania rooted its jurisdictional argument in the Achmea decision. See 
    id. at 16–17.
    4 Romania
    also reasserted that a stay was needed to allow the European court to resolve the appeal of the State
    Aid Decision. See 
    id. at 17–21.
    This is where the case stood as of June 2019. And then came one more unexpected turn.
    D.       The General Court Rules
    On June 18, 2019, the General Court of the European Court of Justice issued its ruling on
    Petitioners’ appeal of the State Aid Decision. See Pet’rs Notice of Suppl. Auth., ECF No. 74;
    European Food S.A. et al. v. European Commission, Ioan Micula v. European Commission, and
    Viorel Micula et al. v. European Commission, Case Nos. T-624/15, T-694/15, and T-704/15 (June
    18, 2019), ECF No. 74-1 [hereinafter General Court Decision]. It held that the State Aid Decision
    “must be annulled in its entirety.” 
    Id. ¶ 111.
    The General Court’s decision turned on its
    determination that EU law became applicable to Romania only upon its accession to the EU on
    January 1, 2007. 
    Id. ¶¶ 66–67.
    Based on that premise, the court concluded the Commission lacked
    the “competence” to declare that the investment incentives—which Romania offered before
    4
    To be fair, Romania did cite to Achmea repeatedly in its opposition brief, see Resp’t Opp’n at 1–3, 16–17, 24, 27–
    28, but only in connection with its arguments under the act of state and foreign sovereign compulsion doctrine
    doctrines. It did not challenge subject matter jurisdiction based on Achmea.
    12
    acceding to the EU—violated EU rules on state aid. 
    Id. ¶¶ 67,
    79. The General Court also found
    that, because the ICSID tribunal’s Award compensated Petitioners for Romania’s pre-EU-
    accession repeal of the incentives, satisfying the Award would not constitute illegal state aid, even
    though it was entered after accession. See 
    id. ¶¶ 74–75,
    80, 90-93, 95.
    As a result of the General Court’s decision, this court denied as moot Romania’s request
    for a stay. See Order, ECF No. 75. It also denied Romania’s motion for additional time to respond
    to Petitioners’ Motion for Judgment. See 
    id. The court
    indicated that it would consider the
    arguments made by Romania in its prior filings to collectively comprise its opposition to
    Petitioners’ Motion. See 
    id. The court
    also ordered further briefing on the impact of the General
    Court’s nullification of the State Aid Decision. See 
    id. The parties
    and the European Commission
    filed their supplemental briefs in July 2019, 5 and the Commission subsequently advised that it had
    lodged an appeal of the General Court’s decision with the CJEU. See European Comm’n’s Notice
    of Suppl. Auth., ECF No. 84 [hereinafter EC Not. of Suppl. Authority].
    At long last, five years after this matter first arrived in this District, the court now turns to
    the merits of whether to confirm the Award.
    III.    LEGAL STANDARD
    A federal court’s role in enforcing an ICSID award is limited. As discussed, the ICSID
    Convention vests the power to enforce ICSID awards in the domestic courts of Contracting States.
    In the United States, Congress granted federal courts exclusive jurisdiction to enforce ICSID
    awards. See 22 U.S.C. § 1650a(b). Such awards “shall be enforced and shall be given the same
    full faith and credit as if the award were a final judgment of a court of general jurisdiction of one
    5
    In yet another instance of Romania not adhering to a court order, its supplemental response rehashed procedural
    history and arguments that had little or nothing to do with the General Court’s decision. The court struck Romania’s
    response and allowed Romania to re-file a brief responsive to the court’s request, see Minute Order, July 9, 2019,
    which it did on July 26, 2019, ECF No. 82.
    13
    of the several States.” 22 U.S.C. § 1650a(a). A federal court is “not permitted to examine an ICSID
    award’s merits, its compliance with international law, or the ICSID tribunal’s jurisdiction to render
    the award.” Mobil Cerro 
    Negro, 863 F.3d at 102
    , 118 (stating that an “ICSID-award debtor would
    be a party to the action . . . but would not be permitted to make substantive challenges to the
    award”); TECO Guatemala Holdings, LLC v. Republic of Guatemala, Civ. No. 17-102 (RDM),
    
    2018 WL 4705794
    , at * 2 (D.D.C. Sept. 30, 2018) (citing Mobil Cerro Negro). Instead, the court
    “may do no more than examine the judgment’s authenticity and enforce the obligations imposed
    by the award.” Mobil Cerro 
    Negro, 863 F.3d at 102
    , 121 (stating that the ICSID-award debtor can
    make “non-merits challenges” to an award, such as “the authenticity of the award presented for
    enforcement, the finality of the award, or the possibility that an offset might apply to the award
    that would make execution in the full amount improper”).            This limited role “reflects an
    expectation [under the Convention] that the courts of a member nation will treat the award as
    final.” 
    Id. IV. DISCUSSION
    With these principles in mind, the court turns to the challenges raised by Romania.
    It advances four arguments. Romania asserts: (1) the court lacks subject matter jurisdiction under
    the FSIA, (2) it has fully satisfied the Award, (3) the act of state doctrine prohibits the Award’s
    enforcement, and (4) so, too, does the foreign sovereign compulsion doctrine. See Resp’t Opp’n.
    at 17–29; Resp’t Mot. to Stay; Resp’t Reply. The European Commission joins in each of these
    arguments, except Romania’s contention that it has satisfied the Award. See EU Amicus Br. at
    10–20.
    14
    A.       Subject Matter Jurisdiction
    The court begins, as it must, with its subject matter jurisdiction to enforce the Award. The
    FSIA is “the sole basis for obtaining jurisdiction over a foreign state in the courts of the [United
    States].” Belize Soc. Dev. Ltd. v. Gov’t of Belize, 
    794 F.3d 99
    , 101 (D.C. Cir. 2015) (quoting
    Argentine Republic v. Amerada Hess Shipping Corp., 
    488 U.S. 428
    , 443 (1989)); see also
    28 U.S.C. §§ 1605–1607. Pursuant to the FSIA, “a foreign state is presumptively immune from
    the jurisdiction of the United States courts[,] unless a specified exception applies.” Saudi Arabia
    v. Nelson, 
    507 U.S. 349
    , 355 (1993). Because “subject matter jurisdiction in any such action
    depends on the existence of one of the specified exceptions to foreign sovereign immunity” laid
    out in the FSIA, as a “threshold” matter in every action against a foreign state, a district court
    “must satisfy itself that one of the exceptions applies.” Verlinden B.V. v. Cent. Bank of Nigeria,
    
    461 U.S. 480
    , 493–94 (1983); see 28 U.S.C. § 1605(a). Once a plaintiff establishes as a threshold
    matter that an exception applies, “the burden of proof in establishing the inapplicability of these
    exceptions is upon the party claiming immunity.” Transamerican S.S. Corp. v. Somali Democratic
    Republic, 
    767 F.2d 998
    , 1002 (D.C. Cir. 1985).
    1.        Arbitration Exception and the Achmea decision
    Here, Petitioners rest jurisdiction primarily on the FSIA’s arbitration exception. See Pet’rs
    Resp. to EC Br., ECF No. 62 [hereinafter Pet’rs Resp. to EC].6 That exception provides:
    A foreign state shall not be immune from the jurisdiction of courts
    of the United States or of the States in any case . . . in which the
    6
    Petitioners also assert in a footnote that the court has jurisdiction over this matter under the FSIA’s “implied waiver”
    exception, because Romania did not challenge the court’s subject matter jurisdiction either in its motion opposing
    confirmation of the Award or its motion to stay proceedings. See Pet’rs Resp. to EC at 4 n.3 (“Because Romania did
    not raise subject matter jurisdiction under the FSIA in its responsive pleading, the ‘implied waiver’ exception under
    Section 1605(a)(1) also applies here.”). The court rejects this assertion for two reasons. First, the court need not
    “consider cursory arguments made only in a footnote.” Hutchins v. District of Columbia, 
    188 F.3d 531
    , 539 n.3 (D.C.
    Cir. 1999). Second, the implied waiver doctrine applies only “narrowly” and includes an “implicit . . . requirement
    that the foreign state have intended to waive its sovereign immunity.” Creighton Ltd. v. Gov’t of State of Qatar, 
    181 F.3d 118
    , 122 (D.C. Cir. 1999). “[C]ourts rarely find that a nation has waived its sovereign immunity . . . without
    15
    action is brought[ ] . . . to confirm an award made pursuant to such
    an agreement to arbitrate, if . . . the agreement or award is or may be
    governed by a treaty or other international agreement in force for the
    United States calling for the recognition and enforcement of arbitral
    awards.
    28 U.S.C. § 1605(a)(6). Courts consistently have held that the FSIA’s arbitration exception
    confers subject matter jurisdiction over petitions to enforce ICSID awards. See Blue Ridge Invs.,
    L.L.C. v. Republic of Argentina, 
    735 F.3d 72
    , 85 (2d Cir. 2013) (“[E]very court to consider whether
    awards issued pursuant to the ICSID Convention fall within the arbitral award exception to the
    FSIA has concluded that they do.”). Petitioners thus have satisfied their initial burden of
    identifying an applicable exception under the FSIA to sovereign immunity.                                  See Phoenix
    Consulting, Inc. v. Republic of Angola, 
    216 F.3d 36
    , 40 (D.C. Cir. 2000).
    Romania says this case is different than those finding the arbitration exception applicable.
    It contends that the arbitration exception does not confer jurisdiction “because the arbitration
    clause in the Sweden-Romania BIT has been declared invalid.” Resp’t Reply at 15. This argument
    rests on the European Court of Justice’s decision in Achmea. Specifically, Romania points to that
    part of the Achmea opinion stating that EU law “preclud[es] a provision in an international
    agreement concluded between Member States . . . under which an investor from one of those
    Member States may, in the event of a dispute concerning investments in the other Member State,
    bring proceedings against the latter Member State before an arbitral tribunal.” Resp’t Reply at 16
    (quoting Achmea ¶ 60). Applying that principle here, Romania contends that the arbitration clause
    in the Sweden-Romania BIT is “invalid as of Romania’s accession to the E.U.” 
    Id. The European
    strong evidence that this is what the foreign state intended.” Foremost-McKesson, Inc. v. Islamic Republic of Iran,
    
    905 F.2d 438
    , 444 (D.C. Cir. 1990). Such “strong evidence” is lacking here. Since appearing in this matter, Romania
    has resisted this court’s jurisdiction, at first on the ground that Petitioners failed to secure jurisdiction through proper
    service of process under the FSIA. See Mot. to Dismiss for Insufficient Service of Process, ECF No. 7. Once served,
    Romania again contested the court’s subject matter jurisdiction under the arbitration exception, albeit belatedly in a
    reply brief. See Resp’t Reply at 14–17. Though Romania should have raised its arbitration-exception challenge in an
    opening brief, the record lacks the “strong evidence” required to make a finding of implied waiver.
    16
    Commission shares this view of the effect of Achmea. See EC Amicus Br. at 11 (arguing that
    Achmea “applies foursquare to the arbitration agreement in the Romania-Sweden BIT”).
    Petitioners, on the other hand, insist that Achmea is not controlling. Pet’rs Resp. to EC at
    5–7. They argue that Achmea is materially distinguishable from this case on the facts. See 
    id. Specifically, Petitioners
    maintain that Achmea does not apply to the Sweden-Romania BIT
    because: (1) the Slovak Republic in Achmea had joined the EU before the arbitral tribunal
    commenced in that case, whereas here Romania acceded two years after the ICSID proceedings
    began, and (2) Achmea involved an arbitration under another treaty, not the ICSID Convention.
    
    Id. They also
    assert that the General Court’s decision overturning the State Aid Decision confirms
    the inapplicability of Achmea and the continuing validity of the Sweden-Romania BIT’s arbitration
    agreement. See Pet’rs Reply in Support of Notice of Suppl. Auth., ECF No. 82, at 6.
    At issue in Achmea was a 1992 bilateral investment treaty between the Netherlands and the
    Czech and Slovak Republic (“Slovak Republic”). That treaty, like the one at issue here, contained
    a provision providing for dispute resolution through international arbitration. Achmea ¶ 4. In May
    2004, the Slovak Republic joined the EU. See 
    id. ¶ 6.
    That same year, in response to the country’s
    liberalization of its private medical insurance market, Achmea, a subsidiary of a Netherlands
    insurance group, set up a company in the Slovak Republic to sell private medical insurance. See 
    id. ¶ 7.
    A mere two years later, the Slovak Republic began to partially roll back the market reforms.
    See 
    id. ¶ 8.
    Asserting financial harm as a result of these actions, Achmea invoked the bilateral
    investment treaty’s arbitration clause and filed arbitration proceedings against the Slovak Republic
    in October 2008. 
    Id. ¶ 9.
    In December 2012, the arbitral tribunal awarded Achmea damages in
    the amount of EUR 22.1 million. 
    Id. ¶ 12.
    17
    The case eventually made its way to the CJEU, where the court was presented with the
    following question:
    Does [EU law] preclude the application of a provision in a bilateral
    investment protection agreement between Member States . . . under
    which an investor of a Contracting State, in the event of a dispute
    concerning investments in the other Contracting State, may bring
    proceedings against the latter State before an arbitral tribunal where
    the investment protection agreement was concluded before one of
    the Contracting States acceded to the European Union but arbitral
    proceedings are not to be brought until after that date?
    
    Id. ¶ 23.
    7 To address the question, the court turned first to the Treaty on the Functioning of the
    European Union, which sets forth the EU’s authority to legislate and key principles of EU law.
    The court explained that among the Treaty’s aims was to establish the primacy of European law
    over the law of the Member States, see 
    id. ¶¶ 32–34,
    and a judicial system that operates through
    national courts and tribunals and the CJEU to “ensure consistency and uniformity in the
    interpretation of EU law,” 
    id. ¶ 35.
    In resolving the issue posed, the CJEU asked three questions.
    First, it inquired whether the dispute before the arbitral tribunal related to the interpretation or
    application of EU law. It did. See 
    id. ¶¶ 39–42.
    Next, the court asked whether the arbitral tribunal
    “is situated within the judicial system of the EU.” It was not. See 
    id. ¶¶ 43–49.
    Finally, the court
    questioned whether the arbitral award was subject to review by a court of a Member State. It was
    not—the bilateral investment treaty at issue provided that the decision of the arbitral tribunal was
    final. See 
    id. ¶¶ 50–56.
    In view of these considerations, the CJEU ruled that the bilateral
    investment treaty’s arbitration provision was inconsistent with EU law because permitting
    arbitration outside of the EU system could prevent disputes “from being resolved in a manner that
    7
    Achmea arrived at the CJEU by a process analogous to a federal court in the United States certifying a question of
    state law to a state supreme court. The Slovak Republic had filed an action in the domestic courts of Germany to
    nullify the award, and the German court then referred the question presented to the CJEU. See 
    id. ¶¶ 12–13.
    18
    ensures the full effectiveness of EU law, even though they might concern the interpretation of
    application of that law.” 
    Id. ¶ 56.
    The CJEU thus held:
    [EU law] must be interpreted as precluding a provision in an
    international agreement concluded between Member States . . .
    under which an investor from one of those Member States may, in
    the event of a dispute concerning investments in the other Member
    State, bring proceedings against the latter Member State before an
    arbitral tribunal whose jurisdiction that Member State has
    undertaken to accept.
    
    Id. ¶ 60.
    Having carefully considered the Achmea decision, this court finds that Romania has failed
    to carry its burden of showing that Achmea forecloses this court’s jurisdiction under the FSIA’s
    arbitration exception. The CJEU’s reasoning in Achmea turned on protecting the “the autonomy
    of EU law.” 
    Id. ¶ 59.
    The court there deemed the arbitration provision invalid because, in short,
    the dispute called upon the arbitral tribunal to interpret or apply EU law and the tribunal’s ultimate
    resolution of any question of EU law was not subject to review by a court or tribunal within the
    EU’s judicial system. Here, Romania has not shown that the concern that animated Achmea—the
    un-reviewability of an arbitral tribunal’s determination of EU law by an EU court—is present in
    this case. The court so concludes for three reasons.
    First, the facts here are materially different than Achmea. The applicability of EU law to
    the dispute in Achmea was clear, as both the challenged government action occurred, and the
    arbitration proceeding therefore commenced, after the Slovak Republic entered the EU. See ¶¶ 6,
    8, 9. Here, on the other hand, all key events to the parties’ dispute occurred before Romania
    acceded to the EU on January 1, 2007. See General Court Decision ¶ 13. The Sweden-Romania
    BIT entered into force nearly four years earlier on July 1, 2003. See 
    id. ¶ 14.
    Romania repealed
    the incentives upon which Petitioners relied in making their investments the following year, in
    19
    August 2004. See 
    id. ¶ 12.
    That revocation took legal effect on February 22, 2005, see 
    id., thereby “giving
    rise to the damage for which the compensation at issue was awarded,” 
    id. ¶ 72.
    And, five
    months later, on July 28, 2005, Petitioners invoked their right to convene an ICSID arbitral tribunal
    pursuant to Article 7 of the BIT. See 
    id. ¶ 15.
    Thus, unlike in Achmea, in which the contested
    government action occurred when the Slovak Republic was already an EU Member State and
    governed by EU law, Romania’s challenged actions occurred when it remained outside the EU and
    subject, at least primarily, to its own domestic law. 8
    Second, a close inspection of the Final Decision shows that the dispute before the ICSID
    arbitral tribunal did not “relate to the interpretation or application of EU law” in the sense that
    concerned the court in Achmea. Achmea ¶ 39. Before the ICSID tribunal, Petitioners and Romania
    agreed that the claims put forward were based on the Sweden-Romania BIT and that the BIT’s
    “substantive rules” supplied the “applicable law.” Final Decision ¶¶ 288, 318 (“There is no dispute
    among the Parties that the primary source of law for this Tribunal is the BIT itself.”). Insofar as
    EU law was concerned, the tribunal held, Romania had not yet acceded to the EU at the time it
    repealed the economic incentives and so “EU law was not directly applicable to Romania.”
    
    Id. ¶ 319.
    The tribunal did determine, however, that “EU law forms part of the ‘factual matrix’ of
    the case.” 
    Id. ¶ 328.
    “The overall context of EU accession in general and the pertinent provisions
    of EU law in particular may be relevant to the determination of whether, inter alia, Romania’s
    8
    The court uses the word “primarily” for a reason. The Commission points out that, on February 1, 1993, Romania
    signed the Europe Agreement, which established an association between the EU and Romania and provided a legal
    framework for the accession process. See Resp. of Amicus Curiae the European Commission to Pet.’s Notice of Suppl.
    Authority, ECF No. 76 [hereinafter EC Resp. to Suppl. Authority], at 7 n.; Final Decision ¶ 179. The Europe
    Agreement came into force on February 1, 1995, long before the dispute at issue here arose. Final Decision ¶ 185.
    According to the Commission, the Europe Agreement “forms part of E.U. law.” EC Resp. to Suppl. Authority at 7 n.
    The suggestion is that, because Romania was subject to the Europe Agreement, the arbitral tribunal passed on
    questions of European law. But, as discussed below, although the tribunal considered EU law as part of its decision-
    making, it did not make the kind of pronouncements about EU law that would invite the type of autonomy concerns
    expressed in Achmea.
    20
    actions were reasonable in light of all the circumstances, or whether Claimants’ expectations were
    legitimate.” 
    Id. Thus, in
    resolving the dispute before it, the ICSID arbitral tribunal considered EU
    law, but it did so for factual context, not as a source of controlling law. Indeed, the tribunal
    expressly passed on deciding whether “any payment of compensation arising out of this Award
    would constitute illegal state aid under EU law and render the Award unenforceable within the
    EU.” 
    Id. ¶¶ 330,
    340. The tribunal therefore did not decide a question of EU law in a way that
    implicates the core rationale of Achmea. See Achmea ¶ 58 (expressing concern that an arbitral
    tribunal’s application or interpretation of EU law would “call into question not only the principle
    of mutual trust between the Member States but also the preservation of the particular nature of the
    law established by the [governing EU] Treaties”).
    Finally, the General Court’s ruling overturning the State Aid Decision confirms that the
    ICSID arbitral tribunal did not tread upon substantive EU law and, for that reason, Achmea does
    not affect the Award’s validity. The General Court held that “EU law became applicable in
    Romania only as from its accession to the European Union on 1 January 2007.” General Court
    Decision ¶ 67. It found that the events giving rise to the Award occurred before January 1, 2007,
    and that “the arbitral tribunal confined itself to determining the exact damage suffered by the
    applicants on the basis of the infringements committed by Romania in 2005.” 
    Id. ¶ 77.
    The
    Commission thus lacked the competence to review Romania’s pre-accession actions and the
    Award’s compatibility with EU state aid law. See 
    id. ¶ 86.
    Based on these determinations, the
    General Court distinguished the present case from Achmea: “[I]t must be pointed out that, in the
    present case, the arbitral tribunal was not bound to apply EU law to events occurring prior to the
    accession before it, unlike the situation in the case which gave rise to the judgment of 6 March
    2018, Achmea (C-284/16, EU:C:2018:158, paragraphs 38 to 41).” 
    Id. ¶ 87.
    Romania fails to
    21
    acknowledge this key passage in the General Court’s ruling. See Resp’t Resp. to Pet’rs Notice of
    Suppl. Authority, ECF No. 79 [hereinafter Resp’t Resp. to Suppl. Authority], at 5–6. The General
    Court’s ruling therefore explicitly refutes Romania’s position that the CJEU’s decision in Achmea
    nullified the arbitration agreement contained in the Sweden-Romania BIT.
    Accordingly, this court possesses subject matter jurisdiction over this matter under the
    FSIA’s arbitration exception.
    B.      The Act of State and Foreign Sovereign Compulsion Doctrines
    Having satisfied itself of jurisdiction, the court turns to Romania’s other arguments.
    Romania contends that two related doctrines—the act of state and foreign sovereign compulsion
    doctrines—require the court to reject confirming the Award and to dismiss the Petition. See Resp’t
    Opp’n at 25–30. The Commission supports Romania’s position. See EC Amicus Br. at 18–22.
    Under the act of state doctrine, “the courts of one state will not question the validity of public acts
    (acts jure imperii) performed by other sovereigns within their own borders, even when such courts
    have jurisdiction over a controversy.” Republic of Austria v. Altmann, 
    541 U.S. 677
    , 700 (2004).
    Similarly, the foreign sovereign compulsion doctrine “shields from . . . liability the acts of parties
    carried out in obedience to the mandate of a foreign government.” See Mannington Mills, Inc. v.
    Congoleum Corp., 
    595 F.2d 1287
    , 1293 (3d Cir. 1979). The court accepts, for present purposes,
    that the Commission qualifies as a “sovereign” under these doctrines. Cf. European Cmty. v. RJR
    Nabisco, Inc., 
    764 F.3d 129
    , 144 (2d Cir. 2014), rev’d and remanded on other grounds, 
    136 S. Ct. 2090
    , 
    195 L. Ed. 2d 476
    (2016) (holding that the European Community “is an organ of a foreign
    state” for purposes of the FSIA).
    The original rationale for invoking these doctrines has been overtaken by events. Romania,
    at first, argued that the State Aid Decision required the court to deny relief. See Resp’t Opp’n at
    22
    25–30. But the General Court’s decision then “annulled” the State Aid Decision. General Court
    Decision ¶ 111. Following this development, Romania pivoted and asserted that, notwithstanding
    the General Court’s ruling, the doctrines still require not confirming the Award, because
    Petitioners never challenged either the Commission’s decision to open a state aid investigation
    against Romania or the suspension injunction issued during the investigation. See Resp’t Resp. to
    Suppl. Authority at 6. Because the General Court’s decision does not purport to affect these
    “preparatory acts,” Romania claims, it remains barred under EU law from paying any portion of
    the Award. Therefore, the act of state and foreign sovereign compulsion doctrines carry the same
    force and effect as they did before the General Court’s ruling. See 
    id. Romania cites
    no more than
    a single case—Spain v. Commission, Case C-415/96, ECLI:EU:C:1998:533—to support its
    position, Resp’t Resp. to Suppl. Authority at 6.
    Petitioners answer Romania by submitting a declaration on EU law from Sir Nicholas
    Forwood Q.C., a barrister of the Bars of England and Wales and of Ireland. See Pet’rs Reply in
    Support of Suppl. Authority, ECF No. 82, Decl. of Sir Nicholas Forwood, ECF No. 82-1. Forwood
    explains that in his view of EU law, when, as here, a Commission ruling is declared void, the
    Commission “cannot take any steps that would be incompatible with the Court’s findings,” and
    must in fact “take account of the grounds of the judgment which have [led] to the finding of
    illegality.” 
    Id. ¶¶ 13–14.
    Applying that principle here, Forwood posits, the General Court’s
    decision not only directly annulled the State Aid Decision, but by its rationale it also makes
    “untenable” the view that the decision to open the investigation and the suspension injunction
    remain effective. 
    Id. ¶ 16.
    The General Court’s decision was premised on the legal determination
    that Romania was not subject to EU law until it acceded to the EU and therefore the Commission
    lacked the “competence” to declare payment of the Award to be unlawful state aid. See 
    id. ¶ 15.
    23
    By that logic, Forwood explains, the Commission also lacks the “competence” to open an
    investigation or to issue a suspension injunction with regard to Romania’s acts that are not subject
    to EU law. See 
    id. ¶¶ 17–19.
    So, in his view, by virtue of the General Court’s ruling, neither the
    decision to open the investigation nor the suspension injunction bars Romania from making
    payment on the Award.
    The court finds Forwood’s interpretation of EU law persuasive. The authority that
    Forwood relies upon for the proposition that the “Commission must take account of the grounds
    of the judgment which have [led] to the finding of illegality” is Société Nationale Maritime Corse
    Méditerranée (SNCM), Case T-1/15, ECLI:EU:T:2017:470. 
    Id. ¶ 14.
    In that case, a General Court
    acknowledged that, under EU law,
    annulment of a Community act does not necessarily affect
    preparatory acts. The annulment of an act terminating an
    administrative procedure consisting of different phases does not
    necessarily entail the annulment of the entire procedure prior to the
    adoption of the contested act, regardless of the grounds, the
    substance or the procedure, the annulment judgment.
    SNCM ¶ 66. 9 Yet, the court also stated that, “[i]n order to comply with a judgment of annulment
    and to give it full effect, the institutions are required to respect not only the operative part of the
    judgment but also the reasons which led to it and which constitute its support necessary, in that
    they are indispensable for determining the exact meaning of what has been judged in the device.”
    
    Id. ¶ 64.
    As Forwood correctly notes, taking account of the reasons for the General Court’s
    judgment means that the Commission’s “preparatory acts” in this case are equally as invalid as the
    final State Aid Decision. Again, the logic of the General Court’s decision is that Romania was not
    subject to EU law at the time it repealed the economic incentives and therefore an Award intended
    9
    Available at https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:62015TJ0001 (English translation
    electronically generated).
    24
    to remedy that harm cannot be incompatible with EU state aid rules, as those rules did not apply
    at the relevant time. The same logic applies to the Commission’s acts of opening an investigation
    and issuing the suspension injunction. They, too, were premised on the Commission’s belief that
    it had the authority to scrutinize Romania’s actions under EU law. The General Court’s decision
    makes clear that the Commission lacked the power to undertake even such preparatory steps. The
    court therefore finds that, as a consequence of the General Court’s decision, the Commission’s
    preparatory acts of opening an investigation and issuing a suspension injunction do not bar
    Romania’s payment of the Award.
    The sole decision upon which Romania relies—Spain v. Commission 10—is not to the
    contrary. There, the court said that the “annulment of a Community measure does not necessarily
    affect the preparatory acts.” Spain ¶ 32 (emphasis added). The court annulled the Commission’s
    decision in Spain because the Commission had not fully analyzed the matter before it in the manner
    required by EU law. The court did not, however, foreclose the Commission from correcting its
    error. Instead, because the reliability of the Commission’s findings were not challenged, the court
    left it open for the Commission to resume its inquiry. See 
    id. ¶ 34.
    In other words, the Commission
    was permitted to pick up from the point of error, leaving the preparatory acts intact. See 
    id. ¶¶ 33–
    34.      This case, obviously, is quite different than Spain.      Here, the Commission lacked
    “competence” from the start to investigate a state aid violation by Romania because Romania’s
    disputed acts all took place before it acceded to the EU. The decision to open the investigation
    and the suspension injunction were as beyond the Commission’s competence as the final State Aid
    Decision. So, the Commission cannot now simply pick up where it left off, as was the case in
    Spain. Accordingly, there is no extant sovereign act that Romania would risk defying if it were
    10
    Available at https://perma.cc/JA7U-V8K2.
    25
    ordered to pay the Award. The court thus finds that Romania has not made a sufficient showing
    that either the act of state or foreign sovereign compulsion doctrine forecloses confirming the
    Award.
    For its part, the Commission, which has appealed the General Court’s decision, see EC Not.
    of Suppl. Authority, points out that the General Court’s decision is “merely a judgment of the
    lower of two courts in the EU judicial system” and is thus subject to reversal, see EC Resp. to
    Suppl. Authority at 4. That may be, but this court’s task is simply to consider whether to grant the
    pending petition and convert the Award to a judgment under § 1650a based on the legal landscape
    as it presently stands. As the Second Circuit has explained, the text of § 1650a “suggest[s] an
    expectation” on the part of Congress “that actions to enforce ICSID awards would not be
    protracted.” Mobil Cerro 
    Negro, 863 F.3d at 121
    ; 
    id. at 117
    (“Litigation on actions to enforce
    awards need not be protracted.”). Nearly six years have passed since the ISCID tribunal entered
    the Award for Petitioners, and almost two years have elapsed since Petitioners re-initiated these
    enforcement proceedings. Moreover, the Commission in taking an appeal to the CJEU did not
    seek to suspend the General Court’s decision pending appeal. See Pet’rs Resp. to European
    Comm’n’s Not. of Suppl. Authority, ECF No. 85. The court is not prepared to delay confirmation
    any longer based on the mere possibility that the CJEU, at some undefined time in the future, might
    reverse the General Court’s decision.
    C.     Romania’s Claimed Satisfaction of the Award
    Romania’s final argument is that the court should deny the Petition because it has satisfied
    the Award in full. See Resp’t Opp’n at 17–25; Resp’t Mot. to Stay at 7–11. Romania contends
    that it has done so through a series of tax setoffs and forced executions on accounts held by the
    26
    Romanian Ministry of Public Finance, and that the court must recognize the validity and effect of
    these actions taken under Romanian law. See Resp’t Opp’n at 19–25.
    As a threshold matter, Petitioners contend that, in these proceedings, the court cannot
    consider Romania’s argument that it has satisfied the Award. See Pet’rs Mem. in Support of Pet’rs
    Mot. [hereinafter Pet’rs Mem.], ECF No. 55-1, at 16–18. Petitioners insist that “Romania’s
    contention that it has ‘satisfied’ the Award is no defense to the confirmation of a binding, final
    ICSID Award.” 
    Id. at 18.
    That assertion is wrong. It rests on the mistaken understanding that,
    under § 1650a, there is a “confirmation” proceeding that is separate and distinct from an
    enforcement proceeding. There is not. 
    See supra
    n.1. Section 1650a speaks only of “enforcement”
    of an ICSID award. See Mobil Cerro 
    Negro, 863 F.3d at 118
    n.18; Micula 
    I, 104 F. Supp. 3d at 49
    . In such a proceeding, the defense of setoff or satisfaction is available. See Mobil Cerro 
    Negro, 863 F.3d at 121
    (identifying as a defense in a proceeding under § 1650a the “possibility that an
    offset might apply to the award that would make execution in the full amount improper”); see also
    Restatement (Second) of Conflict of Laws § 116 (1971) (“A judgment will not be enforced in other
    states if the judgment has been discharged by payment or otherwise under the local law of the state
    of rendition.”).
    A second threshold consideration concerns the choice of law. What law must the court
    apply in deciding whether a claimed payment actually discharges the Award? Neither side
    meaningfully addresses this issue. Romania assumes that its domestic law applies. See Resp’t
    Opp’n at 18–20. Petitioners cite District of Columbia law for general legal principles, see Pet’rs
    Mem. at 18, but do not squarely challenge Romania’s assertion that Romanian law controls the
    legal effect of its claimed payments, see 
    id. at 18–24.
    The court therefore assumes that the law of
    Romania governs whether a claimed payment satisfies a portion of the Award.
    27
    With these threshold matters resolved, the court turns to Romania’s arguments on the
    merits. Romania first claims that a “de jure offset” occurred between Romania and Petitioner
    European Food on December 11, 2013. See Resp’t Opp’n at 17. On January 14 and 15, 2014, the
    Romanian Ministry of Finance issued setoff decisions in the amount of RON 337,492,864 (EUR
    76 million) against tax debts owed by European Foods to Romania. 
    Id. Romania asserts
    that,
    “[u]nder Romanian law, the satisfaction of the Award, occurred when the conditions for the legal
    setoff were met: the first date that European Food owed back taxes and when it, and the other
    Petitioners, won the Award in arbitration, December 11, 2013.” 
    Id. But Romania
    fails to
    acknowledge that a Romanian court declared the asserted tax setoffs to be unlawful under
    Romanian law. See Decl. of Oana Popa, ECF No. 55-12, ¶¶ 15–16 and Ex. L, ECF No. 55-24.
    The Romanian court reasoned that the setoff violated Romanian law because (1) the setoff law
    relied upon by the Romanian finance authorities can be used to offset the state’s fiscal obligations,
    but not civil liabilities, such as the Award, and (2) the setoff improperly applied only to one of the
    Petitioners, European Foods, and not the others. See 
    id. Apparently, Romania
    appealed the court’s
    ruling, but the appeal was stayed pending the outcome of the General Court review of the State
    Aid Decision. See Popa Decl. ¶ 17. The parties have not alerted this court of any developments
    related to the stayed appeal since the General Court issued its decision. With the claimed tax
    setoffs at present annulled, Romania cannot rely on them to satisfy the Award. 11
    Next, Romania asserts that, on March 9, 2015, the Romanian Ministry of Public Finance
    transferred RON 472,788,675 (EUR 106.5 million) into a specially created, legislatively
    authorized Treasury account in Petitioners’ names to satisfy the Award. See Resp’t Opp’n at 21.
    11
    Petitioners also respond to various assertions made by Romania’s Romanian law expert, Professor Radu Bufan,
    concerning the legal effect of the Romanian court’s decision. See Pet’rs Mem. at 20–22. But because Romania itself
    does not advance those arguments in its legal briefs, the court does not consider them.
    28
    But as Petitioners point out, and Romania does not dispute, Romania actually controlled the
    account, Petitioners never had access to it, and Romania subsequently withdrew the funds from
    the account after the State Aid Decision. See Popa Decl. ¶¶ 23–25. Petitioners therefore have not
    received any of the money from the Treasury account in satisfaction of the Award. Under
    Romanian law, absent actual receipt of payment, a judgment is not deemed satisfied. See Popa
    Decl., Ex. O, Legal Op. of Adriana Almasan, ECF No. 55-27, ¶¶ 11–17. The funds transferred on
    March 9, 2015, therefore cannot be applied against the Award.
    The last set of payments Romania identifies as satisfying the Award are certain seizures of
    funds from the Romanian Ministry of Public Finance’s account. See Resp’t Opp’n at 20.
    Petitioners do not dispute that they have received some money from Romania through these forced
    executions and that such sums are appropriately offset against the Award. See Pet’rs Mem. at 26.
    Petitioners estimate the total amount obtained to be slightly more than $11.2 million. See 
    id. This amount
    therefore is properly reduced from the final judgment.
    Before concluding, the court addresses a handful of other arguments that Romania makes
    concerning satisfaction of the Award. First, Romania contends that the General Court’s decision
    “acknowledges that Romania has paid the Award.” Resp’t Resp. to Suppl. Authority at 2. The
    General Court did no such thing. The paragraphs that Romania cites from the General Court’s
    decision—paragraphs 78, 80, and 82, see Resp’t Resp. to Suppl. Authority at 2—merely refer to
    historic events leading up to the court’s ruling. The General Court nowhere acknowledged that
    Romania had satisfied the Award.
    Romania also contends that the court should not convert the Award into a judgment,
    because the General Court’s decision “creates confusion as to the amount of the Award that
    qualifies as state aid, and any amount Romania had the right to recoup per the Decision.” 
    Id. at 3.
    29
    The argument is premised on a suggestion made by the General Court that some portion of the
    Award might be subject to EU state aid rules because it constitutes compensation for the period
    after Romania’s accession to the EU, when no one disputes it was subject to EU law. See 
    id. at 3–
    4. The General Court, however, declined to make any division of the Award, because “the
    Commission did not draw a distinction between the periods of compensation for the damage
    suffered by the applicants before or after accession.” General Court Decision ¶ 91. In other words,
    the Commission forfeited any such argument. Romania cannot convert the General Court’s non-
    holding into a basis to decline to confirm the Award. The contention that some portion of the
    Award violates EU law goes to the merits of the ICSID panel’s determination. That argument
    must be taken to the ICSID arbitral panel, and it is not a valid ground on which to reject converting
    the Award in full to a judgment. See Convention art. 53 (“The award shall be binding on the
    parties and shall not be subject to any appeal or to any other remedy except those provided for in
    this Convention.”).
    Finally, Romania claims that the doctrine of international comity requires the court to
    recognize that Romania has fully satisfied the Award. See Resp’t Resp. to Suppl. Authority at 7.
    But international comity concerns play no role here.           See Société Nationale Industrielle
    Aérospatiale v. U.S. District Court for the Southern District of Iowa, 
    482 U.S. 522
    , 543 n.27 (1987)
    (“Comity refers to the spirit of cooperation in which a domestic tribunal approaches the resolution
    of cases touching the laws and interests of other sovereign states.”). At Romania’s suggestion, the
    court has applied Romanian law to assess whether Romania has satisfied the Award. It has not.
    Accordingly, international comity provides no ground to decline to enforce the Award.
    30
    V.      CONCLUSION AND ORDER
    For the foregoing reasons, the court grants the Petition to Confirm Arbitration Award,
    ECF No. 1, as well as Petitioners’ Motion for Judgment on the Pleadings, ECF No. 55.
    It is further ordered that judgment shall be entered in favor of Petitioners and against
    Romania in the amount of $331,557,687, 12 which reflects the sum total of the Award net payments
    made by Romania, in addition to pre-judgment interest as of November 2, 2018, at the rate
    identified in the Award. See Pet’rs Mem. at 13–15 (setting forth calculations for final judgment).
    Petitioners shall submit by September 18, 2019, a draft Final Judgment that reflects the
    foregoing amount plus all additional prejudgment interest accrued between November 3, 2018,
    and September 18, 2019.
    Dated: September 11, 2019                                            Amit P. Mehta
    United States District Court Judge
    12
    Petitioners asked the court to convert the Award to U.S. Dollars as of the date of the Award. See Pet’rs Mem. at
    11–12. Romania has not objected to that request. In any event, conversion of ICSID awards is the norm in proceedings
    under § 1650a. See Belize Bank Ltd. v. Gov’t of Belize, 
    191 F. Supp. 3d 26
    , 39–40 (D.D.C. 2016).
    31