Bradley v. Dc Public Schools ( 2015 )


Menu:
  •                                                      UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    _________________________________________
    )
    Cheryl Bradley,                           )
    )
    Plaintiff,                          )
    )
    v.                          )                               Civil No. 14-cv-01444 (APM)
    )
    D.C. Public Schools,                      )
    )
    Defendant.                          )
    _________________________________________ )
    MEMORANDUM OPINION AND ORDER
    Before the court is Defendant District of Columbia Public Schools’ (“DCPS”) Second
    Consent Motion to Extend Fact Discovery. ECF No. 25 [hereinafter Def.’s Second Consent Mot.].
    DCPS’ lack of diligence in pursuing discovery in this matter leaves the court little choice but to
    deny its motion.
    A Scheduling Order is “intended to serve as the unalterable road map (absent good cause)
    for the remainder of the case.” Dag Enters., Inc. v. Exxon Mobil Corp., 
    226 F.R.D. 95
    , 104 (D.D.C.
    2005) (citation omitted) (internal quotation marks omitted). It “is not a frivolous piece of paper,
    idly entered, which can be cavalierly disregarded by counsel without peril.” 
    Id. (citation omitted)
    (internal quotation marks omitted). Because the deadline for discovery has now passed—DCPS
    filed its Second Consent Motion on October 13, 2015, one day after discovery closed—DCPS
    must demonstrate “good cause” to modify the Scheduling Order. See Dag 
    Enters., 226 F.R.D. at 105
    ; Fed. R. Civ. P. 16(b); LCvR 16.4.1 “Rule 16(b)’s ‘good cause’ standard primarily considers
    the diligence of the party seeking the amendment. The district court may modify the pretrial
    1
    Although the court’s Minute Order dated July 8, 2015, stated that it would not grant any further extensions absent
    “extraordinary circumstances,” the court nevertheless will apply the “good cause” standard.
    schedule if it cannot reasonably be met despite the diligence of the party seeking the extension.”
    Dag 
    Enters., 226 F.R.D. at 105
    (citations omitted) (internal quotation marks omitted). “Mere
    failure on the part of counsel to proceed promptly with the normal processes of discovery” is not
    considered good cause. See 
    id. (citation omitted)
    (internal quotation marks omitted). “If a party
    that seeks to extend the scheduling order to take untimely discovery was not diligent, the inquiry
    should end.” 
    Id. (citation omitted)
    (internal quotation marks omitted).
    The procedural history of this matter shows DCPS’ lack of diligence—for that matter, both
    parties’ lack of diligence—in pursing timely discovery. On March 18, 2015, the court set a fact
    discovery deadline of August 7, 2015, and a final discovery deadline of September 11, 2015.
    Order, ECF No. 16. This schedule gave the parties nearly six months to complete discovery—
    notably, more time than they requested in their Local Rule 16.3 submission. Id.; Jt. Rpt., ECF No.
    15, at 2 (seeking “160 days for discovery”). In their Joint Status Report, filed on June 16, 2015,
    the parties assured the court that they were “working cooperatively to move discovery forward,”
    and reported (1) that Plaintiff anticipated serving discovery requests by June 19, 2015—even
    though three months had passed since the court had entered the Scheduling Order—and (2) that
    DCPS anticipated deposing Plaintiff the week of July 20, 2015. Jt. Status Rpt., ECF No. 19.
    None of those events came to pass. On July 8, 2015, Plaintiff filed a consent motion
    seeking to extend the discovery deadlines by an additional month. See Consent Mot. for Ext. of
    Time to Complete Disc., ECF No. 20 [hereinafter Pl.’s Consent Mot.]. Plaintiff represented that
    “the remaining discovery period is not sufficient to complete the necessary discovery in this
    litigation, specifically depositions, based on events out of the control of counsel”; that the “current
    discovery deadline does not provide adequate time to schedule, prepare, and depose deponents”;
    and that additional time was needed “to insure that there is an efficient and workable schedule in
    place.” Mem. of P&A, ECF No. 20-1, at 1-2. The court granted the motion for additional time
    2
    and extended the remaining discovery deadlines, as requested, by one month. Min. Order, July 8,
    2015. The deadline for fact discovery thus was reset to September 7, 2015, and the deadline for
    all discovery was reset to October 12, 2015. 
    Id. The court’s
    Minute Order warned that “[n]o
    further extensions shall be granted absent extraordinary circumstances.” 
    Id. Evidently, the
    extra month was not enough. On September 8, 2015—one day after the fact
    discovery deadline expired—DCPS filed a consent motion seeking to extend fact discovery until
    October 12, 2015, the date for the conclusion of all discovery. See Consent Mot. for Ext. of Time
    to Complete Disc., ECF No. 22 [hereinafter Def’s First Consent Mot.]. The consent motion
    showed that the parties had been less than diligent in their discovery efforts. Even though the
    parties had represented in their Joint Status Report that Plaintiff anticipated serving her written
    discovery on June 19, 2015, see Jt. Status Rpt. at 1, the First Consent Motion reported that she did
    not do so until nearly two months later on August 8, 2015, Def.’s First Consent Mot. at 1.
    Similarly, although the parties’ Joint Status Report had represented that DCPS anticipated
    deposing Plaintiff during the week of July 20, 2015, see Jt. Status Rpt. at 1, the First Consent
    Motion disclosed that Plaintiff’s deposition was not set until August 18, 2015, but then was
    cancelled at her counsel’s request, Def.’s First Consent Mot. at 1. In seeking extra time, DCPS
    represented that “the parties believe that they can complete fact discovery within [the requested]
    timeframe” and, again, that the “parties [were] working cooperatively to complete discovery.” 
    Id. at 1.
    It also told the court that it “can be confident that discovery is moving forward.” 
    Id. The court’s
    confidence was misplaced. Even though the court extended the fact discovery
    deadline to October 12, 2015, to coincide with the close of all discovery, see Min. Order, Sept. 8,
    2015, DCPS filed its Second Consent Motion on October 13, 2015, one day after discovery had
    closed. The Second Consent Motion showed that the parties had done little, if anything, during
    the additional time. See Def.’s Second Consent Mot. It also showed an absence of “good cause”
    3
    to further extend the discovery deadline.
    According to DCPS’s Second Consent Motion, DCPS still had not provided Plaintiff with
    its written discovery responses, despite having received Plaintiff’s requests over two months
    earlier. Def.’s Second Consent Mot. at 1. The only explanation DCPS offered is that: “Although
    counsel for the District was hopeful that the responses would be completed in time to allow the
    parties to complete discovery by the extended deadline. Unfortunately, counsel requires more time
    to coordinate a response with DCPS.” 
    Id. An unspecified
    reason for misfortune, however, is not
    “good cause.” Moreover, seven months after the start of discovery, the parties seemingly have
    taken no depositions. The Defendant’s Second Consent Motion again assured the court that the
    parties “continue to work cooperatively to schedule depositions.” 
    Id. But DCPS
    did not explain
    why it has been unable to schedule any depositions since its last extension request. Offering no
    cause, obviously, is not “good cause.”2
    CONCLUSION
    “Courts in this District have routinely denied requests for discovery beyond a cut-off date
    where a party has shown a lack of diligence during the allowed time period.” Dag 
    Enters., 226 F.R.D. at 105
    . Sadly, this is another such case. The court, therefore, denies DCPS’s Second
    Consent Motion to Extend Fact Discovery.                            The parties shall appear for a post-discovery
    conference, as scheduled, on October 22, 2015.
    Dated: October 16, 2015                                                Amit P. Mehta
    United States District Judge
    2
    Plaintiff’s counsel is not without blame for the present state of affairs. Though discovery commenced in March
    2015, she waited almost five months to issue written discovery requests on August 8, 2015. Two months later, even
    though DCPS had not responded to her requests, she had not filed a motion to compel. Instead, she allowed the
    discovery period to expire.
    4
    

Document Info

Docket Number: Civil Action No. 2014-1444

Judges: Judge Amit P. Mehta

Filed Date: 10/16/2015

Precedential Status: Precedential

Modified Date: 10/16/2015