Luna v. Rambo , 841 F. Supp. 2d 193 ( 2012 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    RICHARD LUNA,
    Plaintiff,
    v.                                          Civil Action No. 09-2331 (JEB)
    RONALD RAMBO,
    Defendant.
    MEMORANDUM OPINION
    In 2006, Plaintiff Richard Luna entered into a contract with an entity called the SCS
    Contracting Group, LP to renovate his home in Northeast Washington. Dissatisfied with its
    work after two months, Luna ordered SCS to vacate the premises in March 2007. He then sued
    SCS and its principals in D.C. Superior Court the next month, asserting various claims for
    misrepresentation, negligence, and violations of D.C. law. Two years later, the parties entered
    into a settlement agreement. One month later, Plaintiff turned around and filed this suit against
    Ronald Rambo, one of SCS’s supervisors. Rambo has now moved for summary judgment,
    arguing that the settlement agreement and the doctrine of res judicata preclude this suit.
    Agreeing with the latter point, the Court will grant the Motion.
    I.      Background
    On Dec. 8, 2006, Plaintiff and SCS entered into an agreement, whereby SCS was to
    renovate Plaintiff’s residence at 1230 Linden Pl., N.E., in exchange for $158,500. See Compl.,
    Exh. A (Agreement). Stephen C. Sieber, as owner of SCS, signed the contract. See id. at 4.
    Defendant Rambo started working full time for SCS in late 2005 or early 2006 and was a field
    1
    manager and later a master supervisor there. See Motion, Exh. 1 (Declaration of Ronald Rambo)
    at 1.
    The Complaint alleges that SCS began work on Jan. 19, 2007, following which Luna
    believed work was being improperly done, causing him ultimately to notify SCS to secure the
    house and vacate it. See Compl. at 4-5. Luna had paid SCS over $100,000 by the time he asked
    it to cease work. Id. at 7. Consistent with the contract, Luna paid some of that sum in checks
    made out to Sieber and some in checks made out to Rambo. See Compl., Exh. D (images of
    checks); Agreement at 4. He also alleges that he now has incurred over $200,000 in additional
    costs to return the home to a habitable condition. See Compl. at 2.
    On April 11, 2007, Plaintiff filed an action in the Superior Court against SCS, Sieber, and
    another SCS officer named Christopher Petito. See Mot., Exh. 12 (Sup. Ct. Complaint). In his
    23-page Complaint, which lists 27 separate counts, Plaintiff alleged myriad misrepresentations
    and violations of D.C. consumer-protection laws, all arising from the work SCS did on his house.
    Id. As the docket sheet from this case amply demonstrates, the case, which included
    counterclaims, was extensively litigated until the parties agreed that all claims and counterclaims
    would be dismissed in Nov. 2009. See Motion, Exh. 9 (docket sheet). The dismissal finally
    occurred because the parties had entered into a settlement agreement on Oct. 28, 2009. See
    Motion, Exh. 13 (Settlement Agreement).
    According to the Agreement, entered into among Luna, Sieber, and SCS, the parties
    “desire to end the litigation between them because it has grown excessively burdensome to them,
    and [they] further desire to foreclose new litigation.” Id. at 1. All parties to the Agreement
    consented to the dismissal of all claims against one another in any court. Id. at 2. The other
    terms demonstrated the parties’ intent for a broad agreement and release of claims.
    2
    This Agreement notwithstanding, Luna then filed the current suit on Dec. 8, 2009, less
    than a month after his preceding suit had been dismissed as settled. In the instant Complaint he
    sues only Rambo, but makes the same claims arising out of the same facts as his prior case. This
    Court, believing that a resolution of the preclusive effect of the settlement agreement was
    advisable before engaging in full litigation, permitted limited discovery and briefing on this issue
    only. See Order of June 6, 2011. Rambo has now filed his Motion for Summary Judgment.
    II.      Legal Standard
    Summary judgment may be granted if “the movant shows that there is no genuine dispute
    as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.
    56(a); see also Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247–48 (1986); Holcomb v.
    Powell, 
    433 F.3d 889
    , 895 (D.C. Cir. 2006). “A party asserting that a fact cannot be or is
    genuinely disputed must support the assertion by citing to particular parts of materials in the
    record.” Fed. R. Civ. P. 56(c)(1)(A). “A fact is ‘material’ if a dispute over it might affect the
    outcome of a suit under the governing law; factual disputes that are ‘irrelevant or unnecessary’
    do not affect the summary judgment determination.” Holcomb, 
    433 F.3d at 895
     (quoting Liberty
    Lobby, Inc., 
    477 U.S. at 248
    ). An issue is “genuine” if the evidence is such that a reasonable
    jury could return a verdict for the nonmoving party. See Scott v. Harris, 
    550 U.S. 372
    , 380
    (2007); Liberty Lobby, Inc., 
    477 U.S. at 248
    ; Holcomb, 
    433 F.3d at 895
    .
    The party seeking summary judgment “bears the heavy burden of establishing that the
    merits of his case are so clear that expedited action is justified.” Taxpayers Watchdog, Inc. v.
    Stanley, 
    819 F.2d 294
    , 297 (D.C.Cir.1987). “Until a movant has met its burden, the opponent of
    a summary judgment motion is under no obligation to present any evidence.” Gray v.
    Greyhound Lines, East, 
    545 F.2d 169
    , 174 (D.C. Cir. 1976). When a motion for summary
    3
    judgment is under consideration, “the evidence of the non-movant is to be believed, and all
    justifiable inferences are to be drawn in [its] favor.” Liberty Lobby, Inc., 
    477 U.S. at 255
    ; see
    also Mastro v. Potomac Electric Power Co., 
    447 F.3d 843
    , 849–50 (D.C. Cir. 2006); Aka v.
    Washington Hospital Center, 
    156 F.3d 1284
    , 1288 (D.C. Cir. 1998) (en banc); Washington Post
    Co. v. U.S. Dep't of Health and Human Services, 
    865 F.2d 320
    , 325 (D.C. Cir. 1989).
    The nonmoving party's opposition, however, must consist of more than mere unsupported
    allegations or denials and must be supported by affidavits, declarations, or other competent
    evidence, setting forth specific facts showing that there is a genuine issue for trial. Fed. R. Civ.
    P. 56(e); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 324 (1986). The nonmovant is required to
    provide evidence that would permit a reasonable jury to find in its favor. Laningham v. United
    States Navy, 
    813 F.2d 1236
    , 1242 (D.C. Cir. 1987). If the nonmovant's evidence is “merely
    colorable” or “not significantly probative,” summary judgment may be granted. Liberty Lobby,
    Inc., 477 U.S. at 249–50; see Scott, 
    550 U.S. at 380
     (“[W]here the record taken as a whole could
    not lead a rational trier of fact to find for the non-moving party, there is ‘no genuine issue for
    trial.’”) (quoting Matsushita Electric Industrial Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587
    (1986)).
    III.      Analysis
    In moving for summary judgment, Defendant Rambo first argues that the Agreement bars
    this suit because Luna expressly released SCS, which includes Rambo. See Motion at 8-15. It is
    not disputed that under the Agreement, “Luna consents to the dismissal of all claims he may
    have against Stephen C. Sieber and the SCS Contracting Group, LP, in any Court . . . .” See
    Agreement at 2. The question is whether Rambo, as an agent of SCS, is protected by such
    4
    release from a suit against him individually. The Court, however, need not decide this because
    the doctrine of res judicata provides Defendant an alternative avenue of relief.
    “Under the doctrine of res judicata, ‘a prior judgment on the merits raises an absolute bar
    to the relitigation of the same cause of action between the original parties or those in privity with
    them.’” Washington v. H.G. Smithy Co., 
    769 A.2d 134
    , 138 (D.C. 2001)(citation omitted;
    emphasis added). In considering whether the doctrine applies, the Court focuses on: (1) whether
    the claim was adjudicated finally in the first action; (2) whether the present claim is the same as
    the claim that was raised or that might have been raised in the prior proceeding; and (3) whether
    the party against whom the plea is asserted was a party or in privity with a party in the prior case.
    Patton v. Klein, 
    746 A.2d 866
    , 870 (D.C. 1999). All three requirements are met here.
    First, given that Plaintiff’s case was dismissed with prejudice, see Motion, Exh. 10
    (Order of Dismissal), there was a final adjudication on the merits. “[I]n civil suits, dismissal
    ‘with prejudice’ is said to operate as an adjudication on the merits, is entitled to res judicata
    effect, and thus bars further litigation between the parties on the same cause of action.” United
    States v. Lindsey, 
    47 F.3d 440
    , 444 (D.C. Cir. 1995)(citing 9 Wright & Miller, Federal Practice
    & Procedure: Civil § 2364 (1995)), vacated on other grounds, Robinson v. United States, 
    516 U.S. 1023
     (1995).
    Second, the current Complaint tracks the previous one in all material respects. First, both
    arise out of identical facts: SCS and its employees’ work on Plaintiff’s house. See Drake v.
    FAA, 
    291 F.3d 59
    , 66 (D.C. Cir. 2002) (“Whether two cases implicate the same cause of action
    turns on whether they share the same nucleus of facts.”) (citation and internal quotation omitted).
    Second, the causes of action in the second suit all appear in the first: fraud, misrepresentation,
    lack of licensure, and violation of D.C. Consumer Protection Procedures Act. Third, the relief
    5
    requested is materially identical: disgorgement of monies paid, incidental and compensatory
    damages, punitive damages, and treble damages under the DCCPA. The only significant
    difference is that now the person sued is Rambo, as opposed to his superiors Sieber, Petito, and
    SCS. In addition, there is no dispute that Plaintiff could have sued Rambo in the initial action;
    after all, he sued two of the other principals of SCS. See 
    id.
     (“Under res judicata, a final
    judgment on the merits of an action precludes the parties or their privies from relitigating issues
    that were or could have been raised in that action.”) (quoting Allen v. McCurry, 
    449 U.S. 90
    , 94
    (1980)) (emphasis added by Drake).
    Third, Rambo is in privity with the defendants in the earlier suit. "A privy is one so
    identified in interest with a party to the former litigation that he or she represents precisely the
    same legal right in respect to the subject matter of the case." Patton, 
    746 A.2d at 870
    . A privy
    includes "'those who control an action although not parties to it . . . and those whose interests are
    represented by a party to the action.” 
    Id.
     Plaintiff has alleged in his Complaint that “[a]t all
    relevant times, RAMBO held himself out as an agent of The SCS Contracting Group, LP,” see
    Compl. at 3, that he was “the person who selected, hired, directed, and supervised all relevant
    subcontractors, agents, materials and methods for SCS for the work,” id. at 4-5, and that he
    accepted payments. Id. at 6. In such an instance, there can be little doubt that Rambo’s interests
    in the previous suit were identical to those of SCS, Sieber, and Petito. See Advantage Health
    Plan, Inc. v. Knight, 
    139 F. Supp. 2d 108
     (D.D.C. 2001) (granting motion to dismiss on res
    judicata grounds where plaintiff asserted same claims against executives of company it had
    previously sued successfully, but was unable to recover from when company filed for
    bankruptcy; defendant executives “were agents of [company] in all relevant respects . . . and thus
    were in privity with [it]”).
    6
    Plaintiff in his Opposition does not seem to argue with the above analysis, but instead
    contends that summary judgment “is not proper primarily because the Sieber Settlement and the
    resulting dismissal . . . were rendered ineffective by Sieber’s numerous breaches of the Sieber
    Settlement.” Opp. at 2. In other words, Plaintiff maintains that dismissal of the earlier action
    “will not bar a subsequent action for the same cause when the defendant does not carry out the
    agreement and the plaintiff does not receive the benefit of the bargain.” 
    Id.
     at 3 (citing
    Interdonato v. Interdonato, 
    521 A.2d 1124
    , 1132 (D.C. 1987)). There are several flaws in this
    position.
    To begin with, Luna claims that Sieber breached the Agreement by “attempt[ing] to
    contact Mr. Luna numerous times by telephone and e-mail, often successfully.” Opp. at 4. This
    is hardly a material breach. See America v. Mills, 
    643 F.3d 330
    , 331-32 (D.C. Cir. 2011)
    (breach of settlement agreement must be material). It is true that in the Agreement Sieber agreed
    “not to contact or attempt to contact [Luna or his family], whether in person, by telephone, mail,
    e-mail, or any other means,” see Agreement at 2, but this term appears quite minor when
    considered in the context of the Agreement itself and the preceding litigation. For example,
    there is nothing mentioned in the initial six “Whereas” clauses about a desire to terminate
    contact; instead, Luna desires to end “burdensome” litigation and “foreclose new litigation.” Id.
    at 1. The central obligations Sieber undertook were to release and discharge Luna from all
    claims known and unknown and to dismiss all of his claims in all pending lawsuits. Id. at 2. The
    sole sentence about not contacting Luna appears as a “[f]urthermore” at the conclusion of a
    paragraph. The Court believes that, as a matter of law, this breach does not “relate[] to a matter
    of vital importance.” America, 
    643 F.3d at 332
     (internal quotation and citation omitted).
    7
    In addition, Luna himself concedes, “[i]n the interest of disclosure,” that Sieber may have
    been contacting Luna in regard to a “prior, unsuccessful mediation.” See Opp. at 5. If so, then
    these calls, “giving Sieber the benefit of the doubt,” see 
    id.,
     may well not have been intentional
    breaches of the Agreement at all.
    Even if the breach were material and intentional – both of which the Court finds are not
    the case – Plaintiff could not recover here. In Interdonato, the sole case upon which Plaintiff
    relies, the D.C. Court of Appeals held: “‘Even though a suit is discontinued in accordance with
    an agreement of settlement, such discontinuance will not bar a subsequent action for the same
    cause where the defendant does not carry out the agreement and the plaintiff therefore receives
    no consideration for the discontinuance.’” 
    521 A.2d at 1132
     (quoting 47 Am. Jur. 2d Judgments
    § 1096, at 153 (1969)) (footnote omitted). Given that Plaintiff received the central benefit of his
    bargain – namely, Sieber’s release and dismissal of all claims – this is not a case in which Luna
    “receive[d] no consideration for the discontinuance.” See Tsintolas Realty Co. v. Mendez, 
    984 A.2d 181
    , 187 (D.C. 2009) (no material breach where, even if failure to adhere to confidentiality
    provision, “discernible consequences . . . were nil”).
    Finally, it makes little sense here to permit Luna to sue Rambo even if Sieber had
    violated the Agreement merely by contacting Plaintiff. This might be a different case if Sieber
    had agreed to pay money or perform further construction and then reneged, leading Plaintiff to
    seek recovery from Sieber’s agent. But here Sieber’s calling or emailing Luna cannot by itself
    establish a basis for Luna to circumvent res judicata and sue Rambo on the very monetary
    damage claims he had just voluntarily dismissed against Sieber and SCS.
    8
    IV.      Conclusion
    As the Court finds that the doctrine of res judicata bars this case, it will issue a
    contemporaneous order granting Defendant’s Motion.
    /s/ James E. Boasberg
    JAMES E. BOASBERG
    United States District Judge
    Date: January 27, 2012
    9
    

Document Info

Docket Number: Civil Action No. 2009-2331

Citation Numbers: 841 F. Supp. 2d 193, 2012 WL 251916, 2012 U.S. Dist. LEXIS 9557

Judges: Judge James E. Boasberg

Filed Date: 1/27/2012

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (18)

Interdonato v. Interdonato , 1987 D.C. App. LEXIS 292 ( 1987 )

Advantage Health Plan, Inc. v. Knight , 139 F. Supp. 2d 108 ( 2001 )

elton-e-gray-individually-and-on-behalf-of-all-other-persons-similarly , 545 F.2d 169 ( 1976 )

Etim U. Aka v. Washington Hospital Center , 156 F.3d 1284 ( 1998 )

Scott v. Harris , 127 S. Ct. 1769 ( 2007 )

Tsintolas Realty Co. v. Mendez , 2009 D.C. App. LEXIS 601 ( 2009 )

Washington Post Company v. U.S. Department of Health and ... , 865 F.2d 320 ( 1989 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

America v. Mills , 643 F.3d 330 ( 2011 )

United States v. Albert G. Lindsey, United States of ... , 47 F.3d 440 ( 1995 )

Mastro, Brian A. v. Potomac Elec Power , 447 F.3d 843 ( 2006 )

Holcomb, Christine v. Powell, Donald , 433 F.3d 889 ( 2006 )

Washington v. H.G. Smithy Co. , 2001 D.C. App. LEXIS 62 ( 2001 )

Ross J. Laningham v. United States Navy , 813 F.2d 1236 ( 1987 )

Allen v. McCurry , 101 S. Ct. 411 ( 1980 )

Patton v. Klein , 1999 D.C. App. LEXIS 116 ( 1999 )

Richard Drake v. Federal Aviation Administration , 291 F.3d 59 ( 2002 )

View All Authorities »