Lopez Castro v. Fidelity and Deposit Company of Maryland , 39 F. Supp. 3d 1 ( 2014 )


Menu:
  •                               UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    JAVIER LOPEZ CASTRO, et al.,
    Plaintiffs,
    v.                                           Civil Action No. 13-818 (JEB)
    FIDELITY AND DEPOSIT COMPANY
    OF MARYLAND, et al.,
    Defendants.
    MEMORANDUM OPINION
    Plaintiffs, who worked as laborers for a sub-subcontractor in the construction of a District
    of Columbia building, allege that they were underpaid for their efforts. They have sued under
    the federal Davis-Bacon Act (DBA), 40 U.S.C. § 3141 et seq., in an effort to collect against the
    prime contractor’s construction bond, which was secured pursuant to the District of Columbia’s
    Little Miller Act (DCLMA), D.C. Code § 2-201.02 et seq. Defendant insurance companies
    guaranteed the bond as co-sureties. In moving to dismiss, they now maintain that Plaintiffs are
    not eligible to sue on the bond, and that even if they were, they have failed to comply with a one-
    year statute of limitations. Plaintiffs counter that they are not only eligible, but that they also
    benefit from a two-year limitations statute, which applies to suits brought by workers, as opposed
    to suppliers and sub-contractors. The Court ultimately agrees with Plaintiffs and holds both that
    they have stated a claim under the DBA and that their action is timely.
    I.     Background
    Plaintiffs were employed by S & J Acoustics, a second-tier subcontractor (or sub-
    subcontractor) retained to complete ceiling installation on the Consolidated Forensic Laboratory,
    1
    a building owned by the District of Columbia. See Am. Compl., ¶¶ 2, 5. Pursuant to the DBA,
    40 U.S.C. § 3141, et seq., and the DCLMA, D.C. Code § 2-201.01, et seq., the project’s prime
    contractor, Whiting-Turner Contracting Co., provided a payment bond to the District of
    Columbia as an assurance that project laborers would receive payment at Department of Labor-
    mandated hourly rates. See Am. Compl., ¶¶ 3, 8. In bringing this action against Defendants (1)
    Fidelity and Deposit Company of Maryland and (2) Travelers Casualty and Surety Company of
    America, who insured Whiting-Turner’s bond as co-sureties, see 
    id., ¶ 3,
    Plaintiffs allege that
    they were not paid for their contributions to the project in accordance with these designated wage
    rates. See 
    id., ¶¶ 16-18,
    21. As background, the DCLMA requires contractors on government-
    funded projects to secure payment bonds to protect the interests of suppliers of materials and
    subcontractors, and the DBA establishes prevailing wage rates for workers who contribute to
    government-funded construction projects.
    Prior to initiating this action, Plaintiffs filed an administrative complaint with DOL,
    requesting that payments to the project’s prime contractor be withheld until an investigation
    could be completed and Plaintiffs compensated for the alleged back wages. See 
    id., ¶¶ 23-25.
    As the project had since wound up and all payments had been released to Whiting-Turner, the
    DOL investigator closed the case without making any findings on Plaintiffs’ eligibility for relief
    under the DBA. See 
    id., ¶¶ 24-25.
    After Plaintiffs brought suit and Defendants filed their
    Motion to Dismiss, the Court sua sponte raised the issue of subject-matter jurisdiction,
    questioning whether Plaintiffs had sufficiently exhausted their administrative remedies with
    DOL. See Order to Show Cause at 2-3. Out of deference to DOL’s plenary role in making DBA
    back-wage determinations, the Court issued a temporary stay in the proceedings and ordered
    Plaintiffs to return to DOL and request that conclusive findings be made. See ECF No. 16
    2
    (Order) at 4. Plaintiffs did so, but without success. DOL refused to take further action on the
    ground that the government had already made all payments to the prime contractor and had no
    further funds to withhold. See Joint Status Report, ¶¶ 6-7 & Exh. A. Satisfied that Plaintiffs had
    made all efforts to exhaust remedies with DOL, the Court concluded that it did have subject-
    matter jurisdiction under the DBA and could consequently address the substance of their claims
    and Defendants’ pending Motion to Dismiss. See Castro v. Fid. & Deposit Co. of Maryland, No.
    13-818, 
    2014 WL 495464
    (D.D.C. Feb. 7, 2014).
    Plaintiffs have since moved to amend their Complaint in order to clarify the contractual
    arrangement in effect between prime contractor Whiting-Turner and S&J Acoustics, Plaintiffs’
    employer. See Am. Compl., ¶ 5 & Exh. B. The Court permitted the amendment without
    objection from Defendants, who argue that dismissal is nevertheless appropriate.
    II.    Legal Standard
    In evaluating a Motion to Dismiss under Federal Rule of Civil Procedure 12(b)(6), the
    Court must “treat the complaint’s factual allegations as true . . . and must grant plaintiff ‘the
    benefit of all inferences that can be derived from the facts alleged.’” Sparrow v. United Air
    Lines, Inc., 
    216 F.3d 1111
    , 1113 (D.C. Cir. 2000) (quoting Schuler v. United States, 
    617 F.2d 605
    , 608 (D.C. Cir. 1979)) (internal citation omitted); see also Jerome Stevens Pharms., Inc. v.
    FDA, 
    402 F.3d 1249
    , 1253 (D.C. Cir. 2005). The Court need not accept as true, however, “a
    legal conclusion couched as a factual allegation,” or an inference unsupported by the facts set
    forth in the Complaint. Trudeau v. Fed. Trade Comm’n, 
    456 F.3d 178
    , 193 (D.C. Cir. 2006)
    (quoting Papasan v. Allain, 
    478 U.S. 265
    , 286 (1986)) (internal quotation marks omitted).
    III.   Analysis
    In weighing Defendants’ Motion, the Court must consider the respective scopes of
    3
    application of sections of the three statutes implicated in this case – namely, § 2-201.02 of the
    DCLMA, § 3144(a)(2) of the DBA, and § 255 of the Portal-to-Portal Act, 29 U.S.C. § 251, et
    seq. – and the interrelationships among them. Application of these statutes, Defendants contend,
    demonstrates that Plaintiffs do not qualify for any remedy. But even if they did so qualify,
    Defendants nevertheless maintain that Plaintiffs’ suit is untimely.
    To support these positions, Defendants offer a number of justifications that intersect and
    overlap, making them somewhat challenging to parse. What is evident is that this suit poses
    novel issues, and that neither Plaintiffs nor Defendants have much in the way of precedent to
    guide them. To date, the opinions that have discussed the DBA, the DCLMA (and its model, the
    Federal Miller Act), and the PPA have done so in piecemeal fashion, providing only a limited
    analytical framework for cases such as this one. In responding to Defendants’ arguments,
    therefore, the Court must traverse largely uncharted territory. It thus begins with a discussion of
    whether a remedy is available under either the DCLMA or DBA and then proceeds to consider
    the limitations question.
    A. Availability of Remedy
    Defendants first argue that Plaintiffs cannot invoke the DCLMA to sue on Whiting-
    Turner’s payment bond because eligibility under the statute is restricted to those suppliers of
    labor and materials that have been retained either by the prime contractor or by an immediate
    subcontractor. See Mot. to Dismiss at 9; Reply at 1-2. Since Plaintiffs were hired by a second-
    tier subcontractor, Defendants suggest that they fall outside of the scope of the statute. See
    Supp. to Mot. to Dismiss at 3.
    Defendants further maintain that Plaintiffs also have no remedy under the DBA. They
    premise this argument on the text of DBA § 3144(a)(2), which provides that “laborers and
    4
    mechanics have the same right [of] action . . . as is conferred by law on persons furnishing labor
    or materials.” See Reply at 4. The use of the phrase “same right,” according to Defendants,
    demonstrates that § 3144(a)(2) does not actually grant aggrieved workers an independent cause
    of action, but merely references the applicable bond statute – in this case, DCLMA § 2-201.02.
    See Mot. to Dismiss at 9; Reply at 1 (“Plaintiffs do not have separate cause [sic] of action against
    the Defendants in this case under the DBA . . . .”). Alternatively, even if § 3144(a)(2) does
    create a freestanding cause of action, Defendants reason that the result should be the same
    because “the rights, if any, that were conferred [by §3144(a)(2)] were limited by the express
    terms of the bond statute.” Reply at 7. The DBA, by this logic, merely duplicates the DCLMA,
    mirroring its procedural requirements and limitations on eligibility.
    To address Defendants’ contentions, the Court first analyzes the scope and requirements
    of the DCLMA. It then turns to an examination of § 3144(a)(2) of the DBA to determine
    whether it provides an independent remedy with its own terms and conditions.
    1. The DCLMA
    The DCLMA, D.C. Code § 2-201.02 et seq., is modeled after the federal Miller Act, 40
    U.S.C. § 3131, and opinions interpreting the latter statute provide persuasive authority for
    disputes under the former. See Hartford Acc. & Indem. Co. v. D.C., 
    441 A.2d 969
    , 972 (D.C.
    1982). First promulgated as the Heard Act of 1894, see Act of August 13, 1894, ch. 280, 28 Stat.
    278, as amended by Act of February 24, 1905, ch. 778, 33 Stat. 811, the Miller Act was designed
    to address a relatively narrow yet significant dilemma posed by federally funded construction
    projects. Ordinarily, when a supplier or subcontractor contributes to a private construction
    project, it can protect itself against default by the prime contractor by securing a lien against the
    underlying property. Government property, by contrast, cannot generally be subject to a lien.
    5
    See Dep’t of Army v. Blue Fox, Inc., 
    525 U.S. 255
    , 264 (1999). The principle of “sovereign
    immunity [leaves] suppliers . . . without the protection of the [materialman’s and] mechanics’
    liens normally available in private industry.” U.S. ex rel. E & H Steel Corp. v. C. Pyramid
    Enterprises, Inc., 
    509 F.3d 184
    , 186 (3d Cir. 2007) (citing Blue Fox, 
    Inc., 525 U.S. at 264-65
    ).
    Recognizing this imbalance, the Miller Act was “intended to provide an alternative remedy to
    protect the rights of these suppliers,” F. D. Rich Co. v. U.S. ex rel. Indus. Lumber Co., Inc., 
    417 U.S. 116
    , 122 (1974), by requiring every contractor on a federal contract valued above a certain
    threshold to secure a payment bond in advance of construction. See 40 U.S.C. § 3131(b). The
    DCLMA was adopted to serve the same end, “protect[ing] subcontractors supplying labor and
    material to a [District of Columbia] government project.” Hartford Acc. & Indem. 
    Co., 441 A.2d at 972
    .
    Suppliers and contractors have few procedural hurdles to contend with when they sue on
    a prime contractor’s bond. If a supplier has not received payment within a 90-day period, it need
    only notify the prime contractor of its intention to collect on the bond before initiating a suit.
    See § 3131(b); D.C. Code § 2-201.02(a). Neither the Miller Act nor the DCLMA require the
    aggrieved party to seek administrative review of a claim before turning to the courts. See 
    id. Congress did
    impose sharp restrictions on the scope of the Miller remedy, however, and
    only those parties with close links to the prime contractor can claim the protections of the bond.
    Those who have an attenuated connection to a project and operate further down the chain of
    commerce are excluded from coverage. See F. D. Rich Co., 
    Inc., 417 U.S. at 122
    . The
    limitations on Miller’s coverage are geared to avoid the risk that a prime contractor could be held
    to account for the debts of a third party simply because that third party’s materials happened to
    make their way to a job site. See, e.g., id.; U.S. ex rel. E & H Steel 
    Corp., 509 F.3d at 187
    . As
    6
    the Supreme Court has recognized, the Miller bond remedy was designed “to extend no further
    than to sub-subcontractors,” J.W. Bateson Co. v. U.S. ex rel. Bd. of Trustees, 
    434 U.S. 586
    , 591
    (1978) (emphasis added), leaving “[t]hose in more remote relationships, including persons
    supplying labor or material to a mere materialman” without protection. F. D. Rich 
    Co., 417 U.S. at 122
    .
    In addition to excluding those beyond two degrees of contractual privity to the prime
    contractor, the Miller Act has another limitation. Unlike the DBA and other federal labor and
    wage statutes, Miller was not designed with the welfare of workers in mind, but was instead
    tailored to protect suppliers and subcontractors. In the Supreme Court’s reading, the Miller Act
    “exclude[s] ordinary laborers” from its scope, only extending to those “who perform[] for and
    take[] from the prime contractor a specific part of the labor or material requirements of the
    original contract.” Clifford F. MacEvoy Co. v. U.S. ex rel. Calvin Tomkins Co., 
    322 U.S. 102
    ,
    109 (1944).
    The restricted scope of application of these bond statutes means that Plaintiffs cannot
    qualify under the terms of the DCLMA alone because they neither worked in the capacity of
    suppliers or subcontractors, nor were they hired by Whiting-Turner or an immediate
    subcontractor. Indeed, if the DCLMA furnishes the only available remedy in cases such as this
    one, many workers employed directly at a job site would never be able to collect on a prime
    contractor’s bond, either because they were hired beyond a certain orbit of contractual privity,
    see J.W. Bateson 
    Co., 434 U.S. at 591
    , or because they only qualify as “ordinary laborers,” who
    are ineligible under the Supreme Court’s reading of the bond statute.
    2. DBA § 3144(a)
    The game is not over, however, because the DBA protects precisely those “ordinary
    7
    laborers” that the Miller Act appears to exclude. The DBA applies to any construction contracts
    for public works and public projects that exceed $2,000 in value and to which either the Federal
    Government or the District of Columbia is a party. See 40 U.S.C. § 3142(a). It obliges
    contractors on such projects to pay workers in accordance with prevailing wage rates, established
    by the Secretary of Labor. See 
    id. In the
    event that contractors do not comply with prevailing
    wage rates, a worker may seek redress through the mechanism set out in DBA § 3144(a)(2).
    Promulgated in 1935 – just six days after the federal Miller Act was updated to reflect its current
    language – § 3144(a)(2) is broadly worded, granting a right of action to “all the laborers and
    mechanics who have not been paid the wages required” pursuant to the DBA. In contrast to the
    Miller Act and DCLMA, which condition their protections on a requisite level of contractual
    proximity to the prime contractor, DBA eligibility appears to hinge upon a laborer’s presence at
    the job site. Section 3144(a)(2) stipulates that each “contractor or subcontractor” involved in a
    “contract” governed by the DBA “shall pay all mechanics and laborers employed directly on the
    site of the work, unconditionally and at least once a week . . . regardless of any contractual
    relationship which may be alleged to exist between the contractor or subcontractor and the
    laborers and mechanics.” § 3142(c)(1) (emphasis added).
    Although the DBA does not separately delineate the terms “contract,” “contractor,”
    “subcontractor,” or “laborer,” these terms are defined in corresponding regulations promulgated
    by the Secretary of Labor. See 29 C.F.R. § 5.2. The term “contract” comprises “any prime
    contract which is subject . . . to the labor standards provisions of [the DBA] and any subcontract
    of any tier thereunder, let under the prime contract.” § 5.2(h) (emphasis added). This definition,
    unlike that in the DCLMA, is not limited by a particular degree of separation from the prime
    contractor. The regulations, in fact, expressly disavow any requirement that a worker
    8
    demonstrate a particular contractual relationship, instead providing that “[e]very person
    performing the duties of a laborer or mechanic in the construction . . . of a public building or
    public work . . . is employed regardless of any contractual relationship alleged to exist between
    the contractor and such person.” § 5.2(o). The regulatory definition of “laborer” is governed by
    function, not by contractual formality, and extends to “at least those workers whose duties are
    manual or physical in nature.” § 5.2(m).
    Even in the unlikely event that a court were to find the text of the DBA ambiguous, it
    would still be bound to apply DOL’s regulatory definitions in making its decision. “Because the
    Secretary of Labor has interpreted the Act,” courts must defer to the Secretary’s judgment
    provided that these “interpretations are reasonable.” AKM LLC v. Sec’y of Labor, 
    675 F.3d 752
    , 754 (D.C. Cir. 2012) (citing Chevron, U.S.A., Inc. v. Natural Res. Def. Council, 
    467 U.S. 837
    , 843 (1984)). In this case, the regulatory interpretations are more than merely reasonable –
    they are grounded in the most basic common sense. Because a prime contractor should have
    ample notice of laborers working at its project site, it can institute sufficient controls to ensure
    that they are accounted for and paid for their contributions, regardless of any particular
    contractual arrangement. In contrast to the situation with suppliers, who may come and go
    without any physical connection to a job site, there is far less risk that laborers will be
    completely “[un]known to the prime contractor,” U.S. ex rel. E & H Steel 
    Corp., 509 F.3d at 187
    , and thereby expose it to unforeseen liability.
    3. Interplay Between Statutes
    Regardless of the DBA’s general scope of application, Defendants nevertheless argue that
    § 3144(a)(2) does not create a freestanding cause of action, and even if it does, whatever remedy
    it provides is functionally identical to that offered by the DCLMA. This is evident, Defendants
    9
    argue, in the text of § 3144(a)(2), which offers workers only the “same right . . . as is conferred
    by law on persons furnishing labor or materials.” See Mot. to Dismiss at 9; Reply at 1, 4-8.
    Neither common sense nor a holistic reading of § 3144(a)(2) supports such a result.
    Clearly titled as a “[r]ight of action,” DBA § 3144(a)(2) provides that, if the Secretary of
    Labor’s withholdings under the terms of a contract are “insufficient to reimburse all the laborers
    and mechanics who have not been paid the wages required[,] . . . the laborers and mechanics
    have the same right to bring a civil action and intervene against the contractor and the
    contractor’s sureties as is conferred by law on persons furnishing labor or materials.” (Emphasis
    added). Two points are notable here. First, the express title of § 3144(a)(2) indicates that
    Congress believed that it was creating a new and fully functional right of action, and not merely
    a superficial reference to remedies already available under the bond statutes. While many battles
    have been waged over whether or not an aggrieved worker can claim an implied right of action
    under the DBA and thereby circumvent the administrative-exhaustion requirements of § 3144(a),
    see, e.g., Univers. Research Ass’n v. Coutu, 
    450 U.S. 754
    , 780 (1981), courts have long
    recognized that § 3144(a)(2) furnishes an express cause of action once remedies have been
    exhausted. See, e.g., U.S. ex rel. Bradbury v. TLT Const. Corp., 
    138 F. Supp. 2d 237
    , 241
    (D.R.I. 2001).
    Second, the formulation “all the laborers . . . who have not been paid” sets an expansive
    scope of application that is not obviously restricted by what follows. If Congress had intended to
    limit the scope of eligibility to sue on a bond to the narrow class of workers who might qualify
    under the terms of the Miller Act, it stands to reason that the legislature would have said so in
    clear and unambiguous terms or, more plausibly, would have completely omitted § 3144(a)(2)
    from the DBA. If Defendants are correct, § 3144(a)(2) would be mere surplusage, offering
    10
    nothing of value over and above the remedies already available via the Miller Act and DCLMA.
    The Court cannot ignore the “‘cardinal principle of statutory construction’ that ‘a statute ought,
    upon the whole, to be so construed that, if it can be prevented, no clause, sentence, or word shall
    be superfluous, void, or insignificant.’” TRW Inc. v. Andrews, 
    534 U.S. 19
    , 31 (2001) (quoting
    Duncan v. Walker, 
    533 U.S. 167
    , 174 (2001)).
    Perhaps even more troubling, Defendants’ assessment of § 3144(a)(2) would create two
    arbitrary classes of workers – first, those who satisfy the technical qualifications imposed by the
    terms of the Miller Act and DCLMA, and second, all otherwise DBA-eligible workers. If the
    Court were to endorse Defendants’ highly restrictive interpretation, it might encourage prime
    contractors to insulate themselves behind several layers of subcontracts and thus opt out of the
    obligation to pay DBA-mandated wages, particularly as a project draws to a close and the
    government is no longer able to withhold funds. It should be obvious, accordingly, that all
    laborers present on the worksite of a DBA-eligible project should stand to benefit from the Act’s
    protections, regardless of contractual formalities. The Court thus concludes that § 3144(a)(2) of
    the DBA creates an independent cause of action that grants the ability to collect on a prime
    contractor’s bond to all eligible on-site workers, regardless of who hired them.
    B. Applicable Statute of Limitations
    Defendants’ final challenge pertains to the timeliness of this action. Because Plaintiffs
    narrowly missed the cut-off point for the DCLMA’s one-year statute of limitations, see D.C.
    Code § 2-201.02, due in large part to their efforts to exhaust administrative remedies with DOL,
    Defendants urge the Court to dismiss the suit. See Mot. to Dismiss at 3-4; Reply at 4. Plaintiffs,
    however, assert that they benefit from a two-year period conferred by Section 255 of the Portal-
    to-Portal Act. Having already argued that all of the DCLMA’s terms and conditions – including
    11
    its statute-of-limitations provision – are incorporated by reference into the DBA § 3144(a)(2),
    see Mot. to Dismiss at 9; Reply at 1, Defendants maintain that the Portal-to-Portal Act did not
    alter the limitations period available under the DBA, at least for suits on a prime contractor’s
    bond. See Reply at 5-6. To further support this argument, Defendants rely upon past Supreme
    Court dictum that describes the PPA and Miller Act statutes of limitations as “incompatible,” and
    which might be read as obliquely questioning whether the PPA period applies to suits on a prime
    contractor’s bond. See 
    id. (citing Coutu,
    450 U.S. at 779-82). Ultimately, the Court agrees with
    Plaintiffs, finding that the plain language of PPA § 255, along with its drafting history and
    certain practical considerations, demonstrates Congress’s intention to afford workers a two-year
    window for actions such as this one.
    The Court begins with the text of the PPA, which offers convincing evidence that a two-
    year statute of limitations should govern in DBA suits to collect back wages against a prime
    contractor’s bond. PPA § 255(a) provides, in relevant part:
    Any action . . . to enforce any cause of action for unpaid minimum
    wages, unpaid overtime compensation, and liquidated damages . . .
    under the Fair Labor Standards Act . . . the Walsh-Healey Act, or
    the Davis-Bacon Act . . . may be commenced within two years
    after the cause of action accrued, and every such action shall be
    forever barred unless commenced within two years after the cause
    of action accrued, except that a cause of action arising out of a
    willful violation may be commenced within three years after the
    cause of action accrued.
    (Emphasis added.)
    As Plaintiffs note, the language “any action . . . to enforce any cause of action for unpaid
    wages” is expansive and appears to embrace all civil suits brought by workers to enforce DBA
    wage requirements. See Opp. at 7. While this limitation period has been found to apply to suits
    involving other statutes specifically named in § 255(a), particularly the Walsh-Healey Act, see
    12
    Unexcelled Chem. Corp. v. United States, 
    345 U.S. 59
    , 63-65 (1953), this Court is not aware of
    any opinion that has definitively addressed whether this longer period controls when an
    aggrieved worker seeks to collect on a Miller bond pursuant to DBA § 3144(a)(2). In the Walsh-
    Healey context, the Supreme Court has explained that where the “cause of action seems to be
    precisely described by and expressly included” in the text of the PPA, that limitations provision
    should control. See 
    id. at 65.
    Accordingly, “when Congress, though perhaps mistakenly or
    inadvertently, has used language which plainly brings a subject matter into a statute, its word is
    final.” 
    Id. It is
    not the role of the courts to conclude “that Congress did not mean what it said.”
    
    Id. This reasoning
    is no less compelling in the DBA context.
    The PPA’s background and drafting history also support a literal reading of § 255. As
    the Supreme Court has explained, the PPA was “intended to curtail the numerous suits for unpaid
    compensation and liquidated damages under the FLSA,” following an earlier decision holding
    that workers could seek back-wage compensation for the time incurred transiting to and from
    their places of employment. 
    Coutu, 450 U.S. at 780
    (citing Anderson v. Mount Clemens Pottery
    Co., 
    328 U.S. 680
    (1946)). In addition to prohibiting workers from claiming such “portal-to-
    portal” compensation under the FLSA, the Walsh-Healey Act, and the DBA for time spent
    commuting to and from their jobs, the PPA also established a single limitations period for any
    back-wage and overtime-compensation claim brought pursuant to these three statutes. “Although
    no portal-to-portal suits had been filed under the Davis-Bacon [Act] . . . Congress chose to
    include [the DBA] within the scope of the Portal-to-Portal Act on the ground that [the DBA],
    like the FLSA, related to minimum wages and [was] therefore affected by the Mount Clemens
    decision.” 
    Id. (internal citations
    omitted).
    The Supreme Court has examined the interactions among the DBA, the Miller Act, and
    13
    the PPA’s statute-of-limitations provision on just one occasion, and only tangentially. See 
    id. at 779-82.
    In Coutu, the plaintiff argued that the presence of differing limitations periods in the
    PPA and the Miller Act “affirm[ed] the existence of a private cause of action under the [DBA]”
    in addition to the express cause of action found in § 3144(a)(2). See 
    id. The Supreme
    Court
    disagreed, chastising the plaintiff for reading too much into the PPA and commenting that, “even
    if the [PPA] had been intended to create a longer statute of limitations” for DBA actions on a
    bond, this did not prove that the DBA contained an implied cause of action in addition to the §
    3144(a)(2) remedy. 
    Id. According to
    the Court, “Congress simply did not recognize that it had
    created two incompatible statutes of limitations under the Davis-Bacon Act.” 
    Id. The Coutu
    opinion did not further explore the relationship among the PPA, the DBA, and the Miller Act,
    nor did it definitively rule on which limitations period should control in a case such as this.
    Defendants nevertheless argue that because the Court described the two periods as
    “incompatible,” the “applicability of the Miller Act one (1) year limitation is evidenced by the
    fact that the Supreme Court did not strike either one of the acts down.” Reply at 6.
    More likely, the Court’s response was only intended to discredit the theory that the
    difference between the PPA and Miller Act limitations periods amounted to congressional
    affirmation that the DBA offered two avenues for worker redress – the express remedy of
    § 3144(a)(2) and a functionally separate implied remedy. The discrepancy between the two
    periods was simply not on Congress’s radar at the time it promulgated the PPA.
    Later observations in the Coutu case, also in dictum, further undermine Defendants’
    argument. In its review of the Act’s drafting history, the Court observed that remarks made
    during Senate debate on the PPA “strongly suggest[] that the limitations period . . . was designed
    to apply to the explicit statutory remedy set forth in [§ 3144(a)(2) of] the Davis-Bacon Act.”
    14
    
    Coutu, 450 U.S. at 780
    n.34 (citing 93 Cong. Rec. 2252 (1947) (statement of Sen. McGrath)).
    Indeed, during debate over the PPA limitations period, Senator J. Howard McGrath of Rhode
    Island argued that a two-year window might not be generous enough for DBA actions because
    the “administrative procedures which are necessary to determine the validity of the workman’s
    claim for back wages under the Davis-Bacon Act frequently take a considerable length of time
    which may very easily run for a period of more than 2 years.” 
    Id. When considered
    in this historical context, there appears to be even less support for
    Defendants’ argument that, due to the supposed incompatibility between the limitations periods
    in the PPA and Miller Act, back-wage suits initiated under the DBA – unlike those brought
    under the FLSA and Walsh-Healey Act – must be initiated within a one-year window. The
    difference between the two limitations periods can, in this Court’s view, be explained by the
    dissimilar conditions facing workers and suppliers when they sue against the prime contractor’s
    bond – conditions that Congress took into account when promulgating the PPA. As already
    discussed above, the Miller Act and DBA § 3144(a) protect two distinct groups of aggrieved
    persons and impose different prerequisites for bringing a civil action. To repeat: suppliers and
    subcontractors, unlike workers, are not required to exhaust any administrative remedies before
    initiating an action in federal court; if they have not been paid within a 90-day period, they can
    seek immediate redress. See 40 U.S.C. § 3133; see also D.C. Code § 2-201.02(a). Workers,
    however, must first seek a remedy with DOL, proceeding against the prime contractor’s bond
    only after the government determines that it has not withheld sufficient funds under the contract.
    See Lopez Castro, 
    2014 WL 495464
    , at *5. Congress would thus have had good reason to afford
    workers a longer limitations period.
    The facts of this case provide an apt example. Although Plaintiffs promptly notified the
    15
    prime contractor of their alleged underpayment and filed an administrative complaint with DOL
    in July of 2012, see Am. Compl., ¶¶ 22-23, DOL did not assign the matter to an investigator until
    February of 2013 or provide any response to Plaintiffs until April of the same year. See 
    id., ¶¶ 24-25.
    The shorter limitations period would thus punish people like Plaintiffs for delays largely
    beyond their control.
    The Court, therefore, concludes that because Plaintiffs’ DBA action is subject to a two-
    year statute of limitations, it is timely.
    IV.     Conclusion
    For the forgoing reasons, this Court will issue a contemporaneous Order this day denying
    Defendants’ Motion to Dismiss.
    /s/ James E. Boasberg
    JAMES E. BOASBERG
    United States District Judge
    Date: April 14, 2014
    16