Hawa Construction, LLC v. Pollock ( 2009 )


Menu:
  •                              UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    HAWA CONSTRUCTION, LLC,              )
    )
    Plaintiff-Counterdefendant, )
    )
    v.                              )                 Civil Action No. 09-1728 (RMC)
    )
    RICHARD M. POLLOCK,                  )
    )
    Defendant-Counterclaimant. )
    )
    MEMORANDUM OPINION
    This dispute arises from Hawa Construction, LLC’s renovation of Richard M.
    Pollock’s residence in Washington, D.C.1 Pending before the Court is Hawa Construction’s motion
    to dismiss Count I of Mr. Pollock’s counterclaim [Dkt. # 9], which seeks disgorgement of $205,646
    paid to Hawa Construction for change orders requested by Mr. Pollock and performed by Hawa
    Construction but not reduced to writing as required by District of Columbia home improvement
    regulations.2 For the reasons explained herein, the motion will be granted.
    I. FACTS3
    Mr. Pollock engaged the services of Hawa Construction to renovate and expand his
    residence located in Northwest Washington, D.C. The parties entered into a written contract
    whereby Hawa Construction would perform the renovation work for $2,129,057.
    1
    The Court has diversity jurisdiction under 
    28 U.S.C. § 1332
    (a).
    2
    All parties agree that District of Columbia law applies.
    3
    The facts are taken from Mr. Pollock’s counterclaim [Dkt. # 4] and are assumed to be true.
    Hawa Construction began work on the project in February 2008. Thereafter Mr.
    Pollock considered requesting change orders to the specifications of the work and inquired whether
    such contemplated change orders would cause him to incur additional costs. When Hawa
    Construction responded that Mr. Pollock’s contemplated change orders would not increase the total
    cost of the project, Mr. Pollock requested the change orders to the specifications of the work, and
    Hawa Construction performed the change orders.
    During the course of performance of the contract, Hawa Construction submitted nine
    payment applications to Mr. Pollock and Mr. Pollock paid Hawa Construction a sum of
    $1,903,405.07. After having done so, on June 4, 2009, Hawa Construction informed Mr. Pollock
    that several subcontractors were owed substantial amounts of money for work they had performed
    on the project, which surprised Mr. Pollock because he believed that Hawa Construction had fully
    paid all subcontractors from the monies he paid to Hawa Construction.4 On June 17, 2009, Hawa
    Construction abandoned the project. Thereafter Mr. Pollock paid the subcontractors a sum of
    $69,815.84.
    Of the $1,903,405.07 that Mr. Pollock paid Hawa Construction, $205,646 was for the
    work associated with change orders # 1 through # 13, which Hawa Construction submitted in writing
    to Mr. Pollock on June 17, 2009, after the work had been completed. Mr. Pollock never signed
    change orders # 1 through # 13. In Count I of his counterclaim, Mr. Pollock alleges that change
    orders # 1 through # 13 are void and unenforceable under the District of Columbia’s home
    improvement regulations because they were not approved by him in writing, and he seeks
    4
    In each payment application Hawa Construction certified under oath that “all amounts have
    been paid by the contractor for work which previous Certificates for Payment were issued and
    payments received from the Owner.” Countercl. ¶ 12.
    -2-
    disgorgement of the $205,646 that he paid Hawa Construction for work associated with those change
    orders.
    II. LEGAL STANDARD
    A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) challenges
    the adequacy of a complaint on its face, testing whether a plaintiff has properly stated a claim.
    Federal Rule of Civil Procedure 8(a) requires that a complaint contain “a short and plain statement
    of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a). A complaint must
    be sufficient “to give a defendant fair notice of what the . . . claim is and the grounds upon which
    it rests.” Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555 (2007) (internal citations omitted).
    Although a complaint does not need detailed factual allegations, a plaintiff’s obligation to provide
    the grounds of his entitlement to relief “requires more than labels and conclusions, and a formulaic
    recitation of the elements of a cause of action will not do.” 
    Id.
     The facts alleged “must be enough
    to raise a right to relief above the speculative level.” 
    Id.
     Rule 8(a) requires an actual showing and
    not just a blanket assertion of a right to relief. 
    Id.
     at 555 n.3. “[A] complaint needs some
    information about the circumstances giving rise to the claims.” Aktieselskabet Af 21. Nov. 2001 v.
    Fame Jeans, Inc., 
    525 F.3d 8
    , 16 n.4 (D.C. Cir. 2008) (emphasis in original).
    A court must treat the complaint’s factual allegations as true, “even if doubtful in
    fact.” Twombly, 
    550 U.S. at 555
    . But a court need not accept as true legal conclusions set forth in
    a complaint. Ashcroft v. Iqbal, 
    129 S. Ct. 1937
    , 1949 (2009). “Threadbare recitals of the elements
    of a cause of action, supported by mere conclusory statements, do not suffice.” 
    Id.
     “While legal
    conclusions can provide the framework of a complaint, they must be supported by factual
    -3-
    allegations. When there are well-pleaded factual allegations, a court should assume their veracity
    and then determine whether they plausibly give rise to an entitlement to relief.” 
    Id. at 1950
    .
    III. ANALYSIS
    In Count I of his Counterclaim, Mr. Pollock alleges that Hawa Construction violated
    Section 808.13 of title 16 of the District of Columbia Municipal Regulations, which provides that
    “[t]here shall be no change in specifications [of home improvement contracts] without the written
    approval of the homeowner.” 16 DCMR § 808.13. This is so, Mr. Pollock argues, because he never
    approved change orders # 1 through # 13 in writing. See Countercl. ¶ 35.
    The Court agrees that the regulation requires the homeowner’s written approval to
    changes in specifications of home improvement contracts. However, because Hawa Construction
    had fully performed the work associated with the requested change orders, Section 808.13 does not
    operate to retroactively invalidate the executed oral agreement changing the specifications of the
    work. See Thompson v. Wolfrey, 
    483 A.2d 636
    , 638 (D.C. 1984). In Thompson, the homeowner
    argued that the contractor’s failure to put in writing the terms of their contract violated Section 808.1
    of title 16 of the District of Columbia Municipal Regulations, which provides that “[n]o home
    improvement contractor . . . shall accept any payment for home improvement work to be performed
    for a homeowner until after the understanding between the homeowner and contractor . . . has been
    reduced to writing . . . .” 16 DCMR § 808.1. In rejecting that argument, the District of Columbia
    Court of Appeals reasoned that “[w]e agree that the regulation requires such contracts to be in
    writing” but “because appellee Wolfrey had fully performed his part of the contract before filing suit,
    we hold that the regulation does not prevent Wolfrey from recovering what Thompson owes him.”
    Thompson, 
    483 A.2d at 637
    . The court explained:
    -4-
    Wolfrey’s claim against Thompson was not predicated on “home
    improvement work to be performed” but rather on work already
    completed. Wolfrey had fully performed under the oral contract,
    therefore section [808.1] does not render the oral contract
    unenforceable, and the trial court committed no error in entering a
    $300 money judgment in his favor.
    
    Id. at 638
    . The court found that the writing requirement in the home improvement regulations “is
    akin to a statute of frauds.” Id. at n.6. “Courts have repeatedly reiterated that the Statute of Frauds
    only applies to executory, as distinguished from executed contracts; if an oral contract, otherwise
    within the Statute, is completely executed or performed, it is taken out of the operation of the
    Statute.” Id. (quotation marks and citations omitted). “Under the same principle, appellee Wolfrey’s
    performance of the contract in this case took it out of the operation of section [808.1] of the
    regulations.” Id.
    Mr. Pollock argues that the fact that Hawa Construction fully performed his requested
    change orders does not prevent him from stating a claim for Hawa Construction’s violation of
    Section 808.13. See Opp’n to Mot. to Dismiss [Dkt. # 15] at 9. However, the District of Columbia
    Court of Appeals specifically rejected the argument that the writing requirement in the home
    improvement regulations could be used defensively as a shield in an action to enforce an executed
    oral home improvement contract. See Thompson, 
    483 A.2d at 637-38
    . That being the case, the
    Court cannot agree that Mr. Pollock can affirmatively use the writing requirement in the home
    improvement regulations as a sword to compel Hawa Construction to disgorge monies paid to it for
    having performed oral change orders requested by him. Mr. Pollock’s attempt to do so is contrary
    to the principle that a statute of frauds, which Section 808.13 is akin to, is not normally a source for
    affirmative relief. See District of Columbia Hous. Fin. Agency v. Harper, 
    707 A.2d 53
    , 56 n.5 (D.C.
    -5-
    1998) (noting that “the statute historically was intended to be used as a defense rather than as a basis
    for affirmative relief”); Tauber v. District of Columbia, 
    511 A.2d 23
    , 27 n.11 (D.C. 1986) (“We also
    note that the statute’s intended use is as a defense rather than a basis for affirmative relief.”);
    Hackney v. Morelite Constr., 
    418 A.2d 1062
    , 1066 (D.C. 1980) (“The statute’s intent was not to
    invalidate any oral agreement in one of the enumerated classes, but merely to suspend its
    enforcement until the statute is satisfied by the reduction of it to writing.”) (quotation marks and
    citation omitted). Because Mr. Pollock is attempting to use what is at bottom a statute of frauds to
    affirmatively invalidate an executed contract, Count I of his counterclaim fails to state a claim upon
    which relief can be granted, and will be dismissed.
    IV. CONCLUSION
    For the foregoing reasons, the Court will grant Hawa Construction’s motion to
    dismiss Count I of Mr. Pollock’s counterclaim [Dkt. # 9]. A memorializing Order accompanies this
    Memorandum Opinion.
    Date: December 18, 2009                                     /s/
    ROSEMARY M. COLLYER
    United States District Judge
    -6-