Seeger v. United States Department of Defense ( 2018 )


Menu:
  •                         UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    __________________________________
    )
    MATTHEW SEEGER, et al.,             )
    )
    Plaintiffs,             )
    )
    v.                            )    Civil Action No. 17-639 (RMC)
    )
    UNITED STATES DEPARTMENT            )
    OF DEFENSE, et al.,                 )
    )
    Defendants.             )
    _________________________________   )
    MEMORANDUM OPINION
    Major Matthew Seeger of the United States Army, Michael Schwartz, Cheryl
    Bormann, and Edwin Perry are lawyers employed by the United States Department of Defense
    (DoD) who represent detainees before a military commission at U.S. Naval Station Guantanamo
    Bay, Cuba (NSGB). They bring this action under the Administrative Procedure Act (APA), 
    5 U.S.C. §§ 500
     et seq (2012). They allege that DoD, the U.S. Navy, and the Director of the
    Office of Military Commissions and Convening Authority have failed to investigate adequately
    environmental hazards, including airborne formaldehyde and other carcinogens, present at Camp
    Justice, where Plaintiffs are assigned to work and in some cases sleep while at Guantanamo Bay.
    They further allege that Navy’s investigation into these alleged hazards was incomplete and
    flawed, rendering arbitrary and capricious DoD’s conclusions that Plaintiffs can continue safely
    to live and work at Camp Justice. Plaintiffs ask the Court to require further investigation of the
    alleged hazard mitigation, as well as alternative living and working facilities until that is done,
    for which they seek a preliminary injunction until this litigation concludes.
    1
    Because the issuance of a Final Report, which is now public, renders Plaintiffs’
    complaint of unreasonable delay moot, the Court will dismiss Counts Two and Three. However,
    because Defendants’ orders that Plaintiffs live and work in the allegedly contaminated areas are
    final actions subject to review under the APA, the Court will deny Defendants’ Motion to
    Dismiss Count One. Plaintiffs’ Motion for a Preliminary Injunction will be denied because
    Plaintiffs have not adequately demonstrated that they are likely to succeed on the merits or that
    they are likely to suffer irreparable harm if a preliminary injunction is not granted.
    I. BACKGROUND
    A. Camp Justice and Potential Environmental Hazards
    Camp Justice is a complex at NSGB that was built in 2007 on the site of a former
    airfield. It serves as the location of the Office of Military Commissions Office of the Convening
    Authority (OMC). See Compl. ¶ 19 [Dkt. 1].1 Within Camp Justice is a fenced area called the
    Expeditionary Legal Complex (ELC) which includes a Secure Compartmented Information
    Facility (SCIF), at which most of the intensive work of the OMC occurs due to the classified
    nature of the underlying information. The ELC is comprised of several structures: a sheet metal
    structure (ELC-1) that contains a courtroom and office areas; three trailers (ELC-3, ELC-4, ELC-
    5) that function as office spaces; and three CONEX shipping containers (ELC-8, ELC-9, ELC-
    10). See Ex. 17, Motion for Preliminary Injunction, Indoor Air Quality Assessment Report [Dkt.
    4-19] at 1-4. Camp Justice includes three additional workspaces outside the ELC: Buildings
    1
    “The Office of the Convening Authority is responsible for the overall management of the
    military commissions process, including logistics and personnel support. The Convening
    Authority is empowered to convene military commissions, refer charges to trial, negotiate pre-
    trial agreements, and review records of trial.” Office of Military Commissions Organization
    Overview, http://www.mc.mil/ABOUTUS/OrganizationOverview.aspx (last visited Mar. 29,
    2018).
    2
    AV-29 and AV-34, which are fixed structures, and AV-32, a former hangar. See 
    id. at 1-3
    . Most
    of Plaintiffs’ work is done in the SCIF, which is inside prefabricated structures that Plaintiffs
    allege to be contaminated. See Tr. of Prelim. Inj. Hr’g (PI Tr.) [Dkt. 30] at 18 (testimony of
    Major Seeger regarding structures of ELC). Plaintiffs also have dedicated office space in AV-
    34, outside the ELC, but that is a less convenient space, and Plaintiffs use it less frequently than
    spaces within the ELC, because classified documentation cannot be taken outside the SCIF. 
    Id.
    Personnel housing units under OMC’s direct control within Camp Justice are
    primarily located in Containerized Housing Units, also known as CHUs or “Cuzcos.” Fifty of
    the Cuzcos provide housing; they are air-conditioned trailers, each with two single bedrooms and
    a shared bathroom, comprising 100 beds total. OMC can also house personnel in 360 beds in
    air-conditioned tents with plywood floors. Of these, 60 beds are in “improved” tents with
    partitions and the other 300 are cots rather than beds. Both the Cuzcos and the tents are located
    on what used to be an aircraft runway called McCalla Field, made of asphalt. OMC also rents
    four nearby transient-housing townhomes from the NSGB Commanding Officer, two each for
    prosecution and defense trial teams (predominately used during trial). Other convenient on-base
    housing options include 202 beds managed by Navy Gateway Inns & Suites (NGIS), as well
    rooms at the Navy Lodge. See Defs.’ Opp’n to Pls.’ Appl. for a Prelim. Inj. and Mot. to Dismiss
    (Mot. to Dismiss) [Dkt. 10] at 8-10 (describing the on-base housing options). While some
    Plaintiffs have stayed in these facilities during work trips, availability is not guaranteed and
    demand can sometimes outstrip capacity.
    In addition, OMC can use 53 beds, to the extent they are available, in Building
    AV-624, a permanent structure on the opposite, or leeward, side of Guantanamo Bay, that is, the
    physical water inlet for which the Naval Station is named, from the ELC. Transportation to AV-
    3
    624 is relatively inconvenient, because access is by ferry only and takes approximately 25
    minutes. Plaintiffs argue that their ability to work would be severely hindered if they were
    forced to stay on the leeward side of the bay, in particular because much of their work must be
    done in or near the SCIF, and ferry service is limited. See PI Tr. at 32 (Plaintiffs’ counsel
    arguing that “[i]t’s not the New York Subway. So for folks who are working very long days, it
    cuts down on the amount of time they can work while they’re there.”).
    OMC’s Housing Policy, issued on May 19, 2011, requires “all OMC personnel”
    and contractors to stay in the Cuzcos or tents at Camp Justice. See Mot. to Dismiss at 9.
    Although the lead counsel representing detainees who are charged with capital crimes are
    considered contractors, they are exempt from the requirement that they stay in the Cuzcos or
    tents, under an exception in the policy that permits members of prosecution and defense trial
    teams to stay in the four townhouses. 
    Id.
     Other limited exceptions have been made on a case-
    by-case basis and “in an ad hoc manner based upon requests,” including requests from the
    Military Commissions Defense Organization for trial team members to stay in other NSGB
    housing when available. Id.2 Members of trial teams who are also enlisted military are not
    eligible for these exceptions. In practice, Ms. Bormann, Mr. Schwartz, and Mr. Perry have
    stayed in preferred “hard housing,” such as the Navy Lodge, for all or most of their trips to
    NSGB since 2014; Major Seeger, as an Army officer, is always required to stay in the Cuzcos.
    PI Tr. at 44-47. To receive a housing assignment, the prospective traveler submits a request to
    OMC, which then assigns housing based on the request, availability, and other demands.
    Plaintiffs allege that the Navy “assigns a lower priority to providing hard housing to military
    2
    Other individuals connected to the work of the OMC, “such as the Military Judge, witnesses,
    in-court simultaneous translators, and victims and family members,” are not required to stay in
    OMC housing and have the option of requesting base housing through NSGB personnel. 
    Id.
    4
    commissions personnel than to other individuals residing at the Naval Station, such as base
    contractors, visitors, and other temporary personnel.” Compl. at ¶ 27.
    At the heart of their case, Plaintiffs complain that Camp Justice is contaminated
    with cancer-causing and otherwise hazardous chemicals and other materials including
    formaldehyde, benzo(a)pyrene, asbestos, lead-based paint, and mold. During a discovery
    teleconference on June 23, 2017, Plaintiffs’ attorneys indicated that the primary hazard at issue is
    airborne formaldehyde, which allegedly leaches out of materials in modular units at Camp
    Justice. Plaintiffs report, and Defendants do not contest, that the Environmental Protection
    Agency (EPA) has classified formaldehyde as a “probable human carcinogen.” Pls.’ Mem. in
    Support of Mot. for Prelim. Inj. (Mot. PI) [Dkt. 4-1] at 6.
    B. The Navy’s Investigation into Environmental Hazards at Camp Justice
    Following an initial complaint about potential environmental hazards, the Navy
    undertook a multi-step process, comprising repeated site visits and several reports prepared both
    internally and by external consultants. Beginning in August 2015, the Navy conducted a
    “preliminary investigation” at Camp Justice, including a review of available documents
    concerning prior use, a walk-through, and air sampling; it concluded that “the buildings, tents,
    and trailers where people live and work are habitable for occupancy.” Mot. PI, Ex. 16,
    NMCPHC, Public Health Report for Camp Justice (Aug. 21, 2015) [Dkt. 4-18] at 4. While the
    Navy did not find any immediate health risks, it did determine that there were “data gaps,”
    particularly related to exposure to carcinogens, which did not render the buildings uninhabitable
    but did warrant further environmental sampling and analysis. 
    Id.
    The Navy and Marine Corps Public Health Center (NMCPHC) continued to
    investigate. In October 2015, it conducted sampling at Camp Justice and tested the samples for
    5
    known toxins including formaldehyde. The samples in question were taken in workspaces—
    Buildings AV-29 and AV-32 and spaces in the ELC—and in 16 of the 50 Cuzcos used as living
    spaces. See Mot. for PI at 6-7; Mot. PI, Ex. 3, Expert Report of Dr. Mark A. Killen (Killen
    Report) [Dkt. 4-5] at 9.3 DoD characterizes this stage of testing as incorporating various
    “conservative” measures of potential harm such as “EPA screening levels . . . and OSHA
    permissible exposure limits,” or PELs. Mot. to Dismiss at 4. Some samples tested at higher
    concentrations than these “conservative” screening levels, although the Final Report stated that
    they were all under the minimum “likely to be a human carcinogen” established by the World
    Health Organization (WHO). NMCPHC, Final Public Health Review Report, Camp Justice,
    Naval Station Guantanamo Bay, Cuba (Mar. 3, 2017) (Final Report) [Dkt. 14] at 61.
    As the Final Report acknowledges, the WHO standard is significantly less
    stringent than EPA standards. 
    Id. at 60-61
    . The Navy contends that the EPA standard for
    noncancer risks—7.8 parts per billion (ppb)—is so very low that any measurement of
    formaldehyde that shows a concentration lower than 7.8 ppb establishes essentially no risk, while
    measurements above 7.8 may or may not indicate risk. 
    Id. at 60
    . According to the Final Report,
    WHO standards establish that any indoor-air formaldehyde value under 100 ppb is “considered
    safe for the entire population against sensory irritation,” and that any value under 80 ppb is “not
    likely to be a human carcinogen.” 
    Id. at 61
    . “Indoor air concentrations of formaldehyde at
    3
    Diagrams, included in one of the reports prepared for the Navy by consulting experts, report
    indicate that air samples were taken from 16 of the 50 Cuzcos, each from one of the two sleeping
    areas in each Cuzco. See NMCPHC, Final Public Health Review Report: Camp Justice, Naval
    Station Guantanamo Bay, Cuba (Mar. 3, 2017) [Dkt. 14], App’x L, Resolution Consultants
    Supplemental Environmental Investigation for the Formaldehyde Sampling Results (May 6,
    2016) (May 2016 Resolution Supplemental Formaldehyde Results) [Dkt. 14-47] at 12-13. In his
    report, Plaintiffs’ expert states that “84 CUZCOs located at Camp Justice were never tested”; it
    would have been more accurate to say that 34 out of the 50 Cuzcos, or 84 out of the 100 Cuzco
    bedrooms, were not tested. Killen Report at 9.
    6
    Camp Justice ranged from 1.9 to 61 ppb and the average concentration was 15.4 ppb.” 
    Id. at 61
    .
    In other words, the values were well below WHO levels for noncancer and cancer risks, but
    averaged above the EPA screening levels.
    The Navy insists that tests showing screening levels in excess of initial EPA
    standards did not establish a clear risk, but was only a signal that further investigation was
    warranted. Indeed, the record demonstrates that the Navy undertook further investigation and
    remediation measures following the initial testing. Plaintiffs’ expert, Dr. Mark A. Killen, who
    holds degrees in civil, agricultural, and chemical engineering and is a licensed environmental
    engineer, characterized these initial results as exceeding “the EPA nine month resident cancer
    exposure risk.” Killen Report at 9.
    Resolution Consultants, a contractor hired by the Navy to examine air quality in
    the Cuzcos, issued an “Indoor Air Quality Assessment Report” in January 2016. Mot. PI, Ex. 17,
    Indoor Air Quality Assessment Report (Jan. 12, 2016) [Dkt. 4-19]. In this January 2016
    assessment, the consultants recommended asbestos sampling, cleaning ceiling light covers and a
    closet ceiling and wall where excessive moisture or suspected microbial growth had been
    observed, actions to reduce moisture and humidity levels, and an inspection of heating,
    ventilation, and air conditioning (HVAC) systems to address low airflow. 
    Id. at 22-23
     (chapter
    4.0). Plaintiffs complain that the Navy “has never suggested in any of its subsequent reports that
    it has taken any of the recommended steps.” Mot. PI at 13.
    Shortly thereafter, in February 2016, NMCPHC published the results of a
    “preliminary public health screening risk assessment,” which had found that levels of certain
    toxins measured in indoor air in certain structures, including some Cuzcos, “were of potential
    concern and warranted further evaluation.” Final Report at 6. The toxins of potential concern
    7
    included formaldehyde. 
    Id.
     Specifically, the Navy had concluded that formaldehyde levels in
    the Cuzcos were “of potential concern” because, although below applicable limits set by the
    Occupational Safety and Health Administration (OSHA) for U.S. workplaces, further study was
    needed to “take into consideration risks related to multiple constituents and pathways of
    exposure.” Final Report App’x H, NMCPHC Preliminary Public Health Screening Risk
    Assessment Report for Camp Justice (Feb. 23, 2016) (February 2016 Navy Preliminary
    Assessment) [Dkt. 14-32] at 4. The February 2016 Navy Preliminary Assessment recommended
    certain actions, which were taken, to improve HVAC systems in modular buildings in order to
    remediate airborne formaldehyde; their experts determined that formaldehyde levels had been
    reduced and did not pose a health risk to occupants of the structures in question. See PI Tr. at
    40-41. The Navy had previously concluded that it was safe for people to live and work at Camp
    Justice in the meantime. See Final Report at 26.
    On April 7, 2016, Resolution Consultants issued its “Overseas Baseline
    Environmental Assessment Report,” which assessed the site’s historic use as an airfield and
    concluded that environmental conditions at Camp Justice were acceptable for its current uses.
    Mot. to Dismiss at 4-5. On April 11, 2017, Resolution Consultants completed its
    “Environmental Investigation Report” (EIR), which included the results of extensive
    environmental sampling and site visits. 
    Id. at 5
    . Resolution Consultants also reported the results
    of follow-up air sampling of formaldehyde levels in May 2016. See May 2016 Resolution
    Supplemental Formaldehyde Results. Based on these and other testing results, Defendants’
    expert Dr. Paul B. Gillooly, the Navy’s experienced Health Risk Assessor and an expert in
    industrial hygiene and occupational safety, concluded that there was “[n]o evidence that there are
    complete exposure pathways (air, water[,] soil) resulting in risks to carcinogens above the
    8
    acceptable risk range established by the [EPA].” Mot. to Dismiss, Ex. 1, Declaration of Paul B.
    Gillooly (Gillooly Decl.) [Dkt. 10-1] at 11.
    Finally, in March 2017, NMCPHC completed its Final Public Health Review
    Report, which was filed with the Court under seal on May 25, 2017, and is now public. See Final
    Report.4 The Report assessed the historic uses of the Camp Justice location, analyzed
    environmental sampling, and included a review of relevant medical records of personnel who
    have been stationed at Camp Justice since 2004. Taking these findings and risk factors into
    account, the Navy’s Final Report concluded that “[c]urrent and future potential cancer risks
    related to environmental sources within Camp Justice . . . were within the [EPA] acceptable risk
    range of 1E-06 to 1E-04 (e.g., 1 in 1,000,000 to 1 in 10,000). The cumulative cancer risk for
    Camp Justice for all [chemicals of potential concern] ranged from 1.2E-07 to 6.1E-05.” Final
    Report at 7.
    The Final Report further noted that sampling conducted in April 2016, during the
    course of the investigation, confirmed that HVAC modifications and other recent risk-
    management actions had effectively reduced formaldehyde exposure risks. See Final Report at
    28; see generally Final Report App’x F, Status of Previous Public Health Review Risk
    Management Recommendations (Feb. 2017) (App’x F Status Report) [Dkt. 14-30] (describing
    the recommendations and modifications made to date). The Navy also determined that
    formaldehyde levels in the Cuzcos were comparable to those considered typical by the Centers
    for Disease Control and Prevention (CDC) for similar housing structures, such as mobile homes
    constructed of the same materials, in the United States. See PI Tr. at 40-41; Final Report at 59.
    4
    The Final Report was ultimately released to the public and is available at
    https://www.cnic.navy.mil/regions/cnrse/installations/ns_guantanamo_bay/om/environmental_su
    pport/Guantanamo_Bay_PHR.html (last visited Mar. 27, 2018).
    9
    C. Procedural Background
    Plaintiffs bring the following causes of action in their Complaint:
    Count One: Plaintiffs allege that DoD violated the APA by
    arbitrarily and capriciously deciding that Camp Justice is safe and
    habitable, based on an inadequate investigation.
    Count Two: Plaintiffs allege that DoD violated the APA by
    unreasonably delaying the completion of an adequate risk
    assessment and also delaying the implementation of adequate
    controls to address environmental contamination and other
    unhealthy conditions at Camp Justice.
    Count Three: Plaintiffs ask the Court to issue a writ of mandamus
    requiring Defendants to complete the investigation and risk
    assessment and implement appropriate remediation measures at
    Camp Justice.
    Compl. ¶¶ 129-39.5 Plaintiffs allege that the Navy’s investigation and conclusions violate Navy
    and DoD Directives, Instructions, and other internal policies and guidelines, in particular DoD
    Instruction (DoDI) 6055.01, which governs DoD’s safety and occupational health program. See
    Compl. ¶ 66.
    Related to these allegations, Plaintiffs ask the Court to: (1) declare that
    Defendants’ decisions regarding the safety and habitability of Camp Justice are arbitrary and
    capricious and set them aside; (2) order Defendants to conduct a thorough and timely
    investigation and risk assessment; (3) order Defendants to implement appropriate remediation on
    a timely basis; (4) enjoin Defendants from assigning Plaintiffs to live or work at Camp Justice
    until—after a proper investigation, risk assessment, and appropriate remediation—it is found to
    be safe and habitable; (5) retain jurisdiction to monitor and enforce compliance; and (6) award
    attorneys’ fees and costs. Compl. at 38.
    5
    The Complaint lists these claims as the first, second, and third “Cause of Action.” For the sake
    of verbal economy, this Opinion will refer to them as Counts One, Two, and Three throughout.
    10
    Plaintiffs filed their Complaint on April 11, 2017, and, three days later, moved for
    a preliminary injunction to require provision of alternative accommodations pending the
    outcome of this lawsuit. See Mot. PI.6 At the Court’s hearing on Plaintiffs’ motion for a
    preliminary injunction on July 26, 2017, the Court requested supplemental briefing on its
    subject-matter jurisdiction. See 7/27/2017 Minute Order (setting schedule for supplemental
    briefing). The parties filed supplemental briefs on jurisdiction. The Motion to Dismiss and
    Motion for a Preliminary Injunction are ripe for review. Because briefing on the Motion to
    Dismiss was completed before the hearing on the Motion for a Preliminary Injunction, the Court
    considers both motions in this Opinion.7
    II.       LEGAL STANDARDS
    A. Motion to Dismiss
    1. Rule 12(b)(1)—Lack of Subject-Matter Jurisdiction
    a. Federal-Question Jurisdiction
    The APA does not confer subject-matter jurisdiction on a district court. Rather, a
    court has subject-matter jurisdiction over an APA claim if (1) the claim alleges a violation of
    another statute, which in turn confers jurisdiction, or (2) the claim raises a federal question under
    
    28 U.S.C. § 1331
    . Califano v. Sanders, 
    430 U.S. 99
    , 105-06 (1977). The Court sought
    6
    Defendants moved to dismiss the Complaint and opposed Plaintiffs’ motion for a preliminary
    injunction. Mot. to Dismiss [Dkt. 10]. Plaintiffs opposed. Pls.’ Opp’n to Defs.’ Mot. to Dismiss
    (Opp’n) [Dkt. 26]. Defendants replied. Defs.’ Reply to Opp’n to Mot. to Dismiss (Reply) [Dkt.
    29]. As requested by the Court, both parties further briefed jurisdiction. See Pls.’ Brief
    Regarding Subject-Matter Jurisdiction (Pls.’ Juris. Br.) [Dkt. 32]; Defs.’ Response to Pls.’
    Supplemental Br. on Jurisdiction (Defs.’ Juris. Br.) [Dkt. 34].
    7
    The Court apologizes to the parties for the delay in this Opinion due to illness that prevented
    an earlier decision.
    11
    supplemental briefing on subject-matter jurisdiction, which has clarified its jurisdiction for the
    record.
    The federal-question statute provides that “[t]he district courts shall have original
    jurisdiction of all civil actions arising under the Constitution, laws, or treaties of the United
    States,” 
    28 U.S.C. § 1331
    , and thus it “confer[s] jurisdiction on federal courts to review agency
    action.” Oryszak v. Sullivan, 
    576 F.3d 522
    , 525 (D.C. Cir. 2009) (quoting Califano, 
    430 U.S. at 105
    ); see also Megapulse, Inc. v. Lewis, 
    672 F.2d 959
    , 966 n.30 (D.C. Cir. 1982) (“Even though
    the APA itself technically grants no jurisdiction, power to review any agency action under the
    APA exists under 
    28 U.S.C. § 1331
    .”) (citing Califano, 
    430 U.S. at 97
    ); Robbins v. Reagan, 
    780 F.2d 37
    , 42 (D.C. Cir. 1985) (“Section 1331 vests jurisdiction to review agency action in the
    district court.”). The D.C. Circuit has held that “[i]t is clear that the APA ‘suppl[ies] a generic
    cause of action in favor of persons aggrieved by agency action.’” Trudeau v. FTC, 
    456 F.3d 178
    ,
    188 (D.C. Cir. 2006) (quoting Md. Dep’t of Human Res. v. Dep’t of Health & Human Servs., 
    763 F.2d 1441
    , 1445 n.1 (D.C. Cir. 1985)). Thus, while many APA claims are brought pursuant to a
    separate substantive statute, a court may alternatively have jurisdiction under Section 1331 over
    a claim under the APA, based on allegations that an agency action was arbitrary and capricious
    or that an agency took action without observing procedures required by law. See, e.g., Trudeau,
    
    456 F.3d at 185
     (finding that Section 1331 “is an appropriate source of jurisdiction” for a cause
    of action based on the APA itself, for a “nonstatutory action, independent of the APA,” or for a
    constitutional claim).
    b. Standing
    Section 702 of the APA provides standing to sue to one “‘suffering legal wrong
    because of agency action.’” Abbott Labs. v. Gardner, 
    387 U.S. 136
    , 140 (1967) (quoting 5
    
    12 U.S.C. § 702
    ). Soon after the APA became law, the term “legal wrong” became the subject of
    scrutiny and explication in the courts. In 1955, the United States Circuit Court for the District of
    Columbia Circuit explained that “legal wrong” is a “term of art” which “means such wrong as
    particular statutes and the courts have recognized as constituting grounds for judicial review.”
    Kansas City Power & Light Co. v. McKay, 
    225 F.2d 924
    , 932 (D.C. Cir. 1955) (holding that
    plaintiff power company did not have standing to sue because it would not suffer a “legal wrong”
    as a consequence of a federally-supported power program likely to increase competition). The
    Kansas City Power court cited the APA legislative history to note that the courts have a
    “continuing role . . . in determining . . . who is entitled to judicial review.” 
    Id.
     The D.C. Circuit
    has characterized a “legal wrong” as “the invasion of a legally protected right.” Pennsylvania R.
    Co. v. Dillon, 
    335 F.2d 292
    , 294 (D.C. Cir. 1964).
    Although in some cases a “legally protected right” is one that has been bestowed
    by statute, as in Pennsylvania Railroad, see 
    id. at 295
    , other legally cognizable rights may also
    warrant review. Thus, the D.C. Circuit has recognized a “so-called nonstatutory or common-law
    type of review” under the APA, whereby “[i]f a party can show that he is ‘suffering legal wrong’
    . . . he should have some means of judicial redress.” Scanwell Labs., Inc. v. Shaffer, 
    424 F.2d 859
    , 865 (D.C. Cir. 1970) (quoting S. Doc. No. 248, 79th Cong., 2d Sess. 37-38 38 (1946)).
    Such a legal wrong includes an agency’s basing its “decisions on arbitrary or capricious abuses
    of discretion,” so that “one who makes a prima facie showing alleging such action on the part of
    an agency . . . has standing to sue” under the APA. 
    Id. at 869
    ; see also Whitzell v. Astrue, 
    589 F. Supp. 2d 100
    , 109 (D. Mass. 2008) (“Although [the relevant statute] does not give this Court
    jurisdiction to adjudicate the merits of the complaint, [plaintiff] is correct to seek review from
    this Court because she has nowhere else to turn. . . . In the absence of clear and convincing
    13
    evidence that the congressional intent was to the contrary, courts ought not restrict access to such
    review.” (internal quotation marks and citation omitted)).
    2. Rule 12(b)(6)—Failure to State a Claim
    Under Rule 12(b)(6) of the Federal Rules of Civil Procedure, a complaint must
    contain “sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on
    its face.’” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 570 (2007)). “If as a matter of law ‘it is clear that no relief could be granted under any
    set of facts that could be proved consistent with the allegations,’” then the court must dismiss the
    claim. Neitzke v. Williams, 
    490 U.S. 319
    , 327 (1989) (quoting Hishon v. King & Spalding, 
    467 U.S. 69
    , 73 (1984).
    There are exceptions to the “basic presumption of judicial review to one
    ‘suffering legal wrong because of agency action.’” Abbott Labs., 
    387 U.S. at 140
     (quoting 
    5 U.S.C. § 702
    ). An APA challenge to an agency’s refusal to take enforcement action, as opposed
    to an affirmative final action, is presumptively unreviewable. See Heckler v. Chaney, 
    470 U.S. 821
    , 832-33 (1985). A separate, substantive statute may explicitly preclude judicial review. The
    APA itself also contains statutory exceptions under which judicial review is precluded. Section
    701(a)(2) of the APA excepts from review matters that are “committed to agency discretion by
    law.” 
    5 U.S.C. § 701
    (a)(2). While this exception is “very narrow,” Hi-Tech Furnace Systs., Inc.
    v. FCC, 
    224 F.3d 781
    , 788 (D.C. Cir. 2000), it applies where “a court would have no meaningful
    standard against which to judge the agency’s exercise of discretion.” Heckler, 
    470 U.S. at 830
    .
    In the D.C. Circuit, such a defense is addressed under Rule 12(b)(6) (failure to state a claim) and
    not Rule 12(b)(1) (subject-matter jurisdiction). Sierra Club v. Jackson, 
    648 F.3d 848
    , 854 (D.C.
    Cir. 2011) (“A complaint seeking review of agency action ‘committed to agency discretion by
    14
    law’ has failed to state a claim under the APA, and therefore should be dismissed under Rule
    12(b)(6), not under the jurisdictional provision of Rule 12(b)(1).” (citations omitted)).8
    B. Preliminary Injunction
    “A plaintiff seeking a preliminary injunction must establish that he is likely to
    succeed on the merits, that he is likely to suffer irreparable harm in the absence of preliminary
    relief, that the balance of equities tips in his favor, and that an injunction is in the public
    interest.” Winter v. Nat. Res. Def. Council, Inc., 
    555 U.S. 7
    , 20 (2008). Winter involved a
    challenge to the Navy’s intention to conduct mid-frequency active sonar exercises, involving
    ships, submarines and aircraft, in the waters off Southern California. Plaintiffs sought an
    injunction until the Navy prepared an environmental impact statement due to the presence of
    multiple species of marine mammals in the area. The lower courts that decided Winter before it
    reached the Supreme Court had concluded that a preliminary injunction was warranted. Because
    plaintiffs had demonstrated a strong likelihood of success on the merits of their claim, their
    showing that there was a “possibility” of irreparable harm was sufficient to satisfy the second
    prong. 
    Id. at 20-21
    . The Supreme Court disagreed, emphasizing that “[o]ur frequently reiterated
    standard requires plaintiffs seeking preliminary relief to demonstrate that irreparable injury is
    likely in the absence of an injunction.” 
    Id. at 22
    . The “possibility” of irreparable harm, cited by
    the Ninth Circuit below, was too lenient. 
    Id.
     Further, the Court emphasized the need to consider
    the public interest and the defendant’s interest. 
    Id. at 26-27
    .
    8
    Sierra Club resolved inconsistent precedent as to the applicable Rule. See Sierra Club, 
    648 F.3d at 854
    ; see also Oryszak, 
    576 F.3d at 525-26
    ; Trudeau, 
    456 F.3d 178
    , 183-84; contra Ass’n
    of Irritated Residents v. EPA, 
    494 F.3d 1027
    , 1030 (D.C. Cir. 2007), abrogated by Sierra Club,
    
    648 F.3d 848
    .
    15
    In the past, the D.C. Circuit has generally followed a “sliding scale” approach to
    analyzing the four factors that determine whether to grant a preliminary injunction: “[i]f the
    movant makes an unusually strong showing on one of the factors, then it does not necessarily
    have to make as strong a showing on another factor.” Davis v. Pension Ben. Guar. Corp., 
    571 F.3d 1288
    , 1291-92 (D.C. Cir. 2009). However, in light of Winter, the D.C. Circuit has
    suggested, without deciding, that “Winter could be read to create a more demanding burden,
    although the opinion does not squarely discuss whether the four factors are to be balanced on a
    sliding scale.” 
    Id. at 1292
    . Further, the D.C. Circuit has opined that Winter could be read “to
    suggest if not to hold” that a likelihood of success is an independent, free-standing requirement
    for a preliminary injunction. Sherley v. Sebelius, 
    644 F.3d 388
    , 393 (D.C. Cir. 2011) (citing
    Davis, 
    571 F.3d at 1296
    ).
    While the Fourth Circuit has read Winter to preclude the sliding-scale approach to
    preliminary injunctions, its decision was vacated on other grounds and different Circuits have not
    agreed. See Real Truth About Obama, Inc. v. FEC, 
    575 F.3d 342
    , 347 (4th Cir. 2009), vacated
    on other grounds, 
    559 U.S. 1089
     (2010); see also Alliance for the Wild Rockies v. Cottrell, 
    632 F.3d 1127
    , 1130-35 (9th Cir. 2011); Citigroup Global Mkts., Inc. v. VCG Special Opportunities
    Master Fund Ltd., 
    598 F.3d 30
    , 35-38 (2d Cir. 2010); Hoosier Energy Rural Elec. Coop. v. John
    Hancock Life Ins. Co., 
    582 F.3d 721
    , 725 (7th Cir. 2009)).
    Whatever the viability of the “sliding scale” approach to the factors for a
    preliminary injunction, it has long been held that the four factors are not equal. “Whether a
    sliding-scale analysis still exists or not, courts in our Circuit have held that a failure to show a
    likelihood of success on the merits alone is sufficient to defeat the motion.” Standing Rock Sioux
    Tribe v. U.S. Army Corps of Eng’rs, 
    239 F. Supp. 3d 77
    , 83 (D.D.C. 2017) (denying plaintiffs’
    16
    motion for a preliminary injunction only for failure to show likelihood of success on the merits).
    Without a probability of success, “‘the Plaintiff’s purported injuries, no matter how compelling,
    do not justify preliminary injunctive relief.’” Apotex, Inc. v. Sebelius, 
    700 F. Supp. 2d 138
    , 140
    (D.D.C. 2010) (quoting Am. Bankers Ass’n v. Nat’l Credit Union Admin., 
    38 F. Supp. 2d 114
    ,
    140 (D.D.C. 1999)).
    Beyond likelihood of success, the likelihood of irreparable injury is also a critical
    showing before a preliminary injunction will issue. See Winter, 
    555 U.S. at 22
    . This Court
    concludes that Chaplaincy of Full Gospel Churches v. England is abrogated to the extent it
    adopted a lesser injury threshold than Winter. See 
    454 F.3d 290
    , 297 (D.C. Cir. 2006) (holding
    that a movant must show “at least some injury for a preliminary injunction to issue”). Winter
    emphasizes that the basis for injunctive relief must be demonstrated irreparable harm. See
    Sampson v. Murray, 
    415 U.S. 61
    , 88 (1974); Gomez v. Kelly, 
    237 F. Supp. 3d 13
    , (D.D.C. Feb.
    27, 2017) (adopting the higher standard because the purpose of preliminary relief is “to preserve
    the status quo pending resolution of the underlying litigation”) (internal quotation marks and
    citations omitted).
    III.       ANALYSIS
    A. Motion to Dismiss
    1. Rule 12(b)(1)—Lack of Subject-Matter Jurisdiction
    a. Federal-Question Jurisdiction
    Because the APA does not confer jurisdiction, Defendants argue that the Court
    should dismiss this case for lack of subject-matter jurisdiction. According to this argument,
    Plaintiffs’ claims cannot proceed because they are not based upon a statutory predicate, separate
    from the APA, and because DoDI 6055.05 and other internal guidance that Defendants have
    17
    allegedly violated do not confer legally enforceable duties. Plaintiffs counter that the Court has
    subject-matter jurisdiction because their claims raise a federal question under 
    28 U.S.C. § 1331
    .
    Plaintiffs argue that, even without a separate statutory predicate, the Court has subject-matter
    jurisdiction where the Navy’s action is alleged to be arbitrary and capricious or taken without
    observing procedures required by law.
    The Court agrees with Plaintiffs that their allegations establish federal-question
    jurisdiction under Section 1331, even absent allegations of a non-APA statutory violation. See
    Heckler, 
    470 U.S. at 825
     (before holding that there is a presumption against reviewability under
    the APA of an agency’s refusal to act, noting as an initial matter that the district court had
    subject-matter jurisdiction pursuant to Section 1331); Trudeau, 
    456 F.3d at 185
     (finding that the
    federal-question statute “is an appropriate source of jurisdiction” for a cause of action based in
    the APA itself, for a “nonstatutory action, independent of the APA,” or for a constitutional
    claim).
    Defendants cite Steenholdt v. FAA, which suggests a different conclusion: “If no
    ‘judicially manageable standard’ exists by which to judge the agency’s action, meaningful
    judicial review is impossible and the courts are without jurisdiction to review that action.” 
    314 F.3d 633
    , 638 (D.C. Cir. 2003). Steenholdt, however, has been abrogated, insofar as it holds this
    question to be jurisdictional. See Sierra Club, 
    648 F.3d at 854
    . The Court need not belabor the
    point: Plaintiffs’ allegations establish subject-matter jurisdiction pursuant to the federal-question
    statute.
    b.        Standing
    A plaintiff must also establish a “legal wrong” in order to bring a claim under the
    APA for a non-statutory violation. 
    5 U.S.C. § 702
     (“A person suffering legal wrong because of
    18
    agency action, or adversely affected or aggrieved by agency action within the meaning of a
    relevant statute, is entitled to judicial review thereof.”). Defendants argue that Plaintiffs fail to
    establish that “the interest [they] seek to vindicate falls within a statute’s zone of interest.”
    Defs.’ Juris. Br. at 2. The “zone of interests” test, however, is relevant to claims by plaintiffs
    who were “adversely affected or aggrieved by agency action within the meaning of a relevant
    statute.” 
    5 U.S.C. § 702
     (emphasis added); see, e.g., Lujan v. Nat’l Wildlife Fed’n, 
    497 U.S. 871
    (1990); Nat’l Fed’n of Fed. Emps. v. Cheney, 
    883 F.2d 1038
     (D.C. Cir. 1989). Courts have
    found a “legal wrong” sufficient to establish standing under the APA where “the courts have
    recognized” other grounds for judicial review. Kansas City Power, 
    225 F.2d at 932
    ; see also
    Scanwell Labs., 
    424 F.2d at 865
     (recognizing a “nonstatutory or common-law type of review”
    under the APA for a party who has suffered a “legal wrong”).
    The allegations of the Complaint make a prima facie showing of such a legal
    wrong: Plaintiffs allege that DoD orders or effectively forces them to live and work in areas
    contaminated with harmful substances, and they charge that doing so results from arbitrary and
    capricious decision-making and also violates DoDI 6055.05 and other policies binding on Navy.
    For purposes of establishing a right to review, these allegations are sufficient to establish
    prudential standing.
    c. Mootness
    Defendants also argue that Counts Two and Three in Plaintiffs’ Complaint are
    moot due to intervening events since the Complaint was filed on April 11, 2017. Count Two
    alleges that DoD violated the APA by unreasonably delaying the completion of its risk
    assessment and the implementation of controls to address environmental hazards; Count Three
    seeks a writ of mandamus requiring completion of the investigation, risk assessment and
    19
    implementation. Defendants argue that these allegations are no longer “live” because DoD has
    completed its assessment and appropriate implementations, as described in the Final Report and
    expert declarations. Defendants add that when they filed the Final Report under seal on May 19,
    2017, and subsequently published it online, the delay of which Plaintiffs complained was fully
    remedied.
    A defendant moving for dismissal pursuant to Federal Rule of Civil Procedure
    12(b)(1) for lack of subject-matter jurisdiction may argue that the claim in question is moot,
    which means that “‘the issues presented are no longer ‘live’ or the parties lack a legally
    cognizable interest in the outcome.’” City of Erie v. Pap’s A.M., 
    529 U.S. 277
    , 287 (2000)
    (quoting County of Los Angeles v. Davis, 
    440 U.S. 625
    , 631 (1979)). “[A]n actual controversy
    must be extant at all stages of review, not merely at the time the complaint is filed.” Arizonans
    for Official English v. Arizona, 
    520 U.S. 43
    , 68 n.22 (1997); see also 21st Century Telesis Joint
    Venture v. FCC, 
    318 F.3d 192
    , 198 (D.C. Cir. 2003). The party asserting mootness carries a
    “heavy burden,” Honeywell Int’l, Inc. v. NRC, 
    628 F.3d 568
    , 576 (D.C. Cir. 2010), and must
    show that events have occurred which prevent the court from granting the relief sought. See
    Burlington N. R. Co. v. Surface Transp. Bd., 
    75 F.3d 685
    , 688 (D.C. Cir. 1988). A court may
    dismiss a claim as moot if intervening events “have completely and irrevocably eradicated the
    effects of the alleged violation.” County of Los Angeles, 
    440 U.S. at 631
    .
    Defendants argue that Counts Two and Three are moot because the relief sought
    therein—completion of an investigation and risk assessment and implementation of appropriate
    remediation and controls—is final. DoD highlights the facts that the Final Report was completed
    on March 3, 2017, and submitted for internal security review; it was provided to the Court on
    May 19, 2017 under seal, and subsequently released to the public. The Final Report details the
    20
    process that DoD and its experts undertook, over almost two years, to investigate the alleged
    environmental hazards, including multiple rounds of sampling and analysis. See Final Report at
    3-7 (detailing the investigations, reports, and remedial measures taken); see also Final Report
    App’x A, Public Health Review Actions-to-Date (Feb. 2017) [Dkt. 14-1]. DoD emphasizes its
    mitigation efforts, subsequent follow-up testing, and conclusions, as detailed in the Final Report;
    steps it took to implement appropriate controls, see generally App’x F Status Report, and other
    materials, such as expert declarations, that demonstrate completion of the implementation phase.
    Plaintiffs argue that Counts Two and Three are not moot because the
    investigation, risk management process, and other activities on which DoD relies do not satisfy
    the processes set forth in DoDI 6055.05, and are thus incomplete and unreasonably delayed. See
    Opp’n at 8-9. Specifically, Plaintiffs allege that DoD has not yet “completed” three final
    “stages” required by DoDI 6055.05: “Step 3: developing controls and making risk decisions;
    Step 4: implementing controls; and Step 5: supervising and evaluating the results.” Opp’n at 9.
    In response, Defendants argue that these remaining stages are only broad categories of
    requirements that are inherently discretionary. Defendants contend that they have already
    conducted the analyses they believe to be sufficient, and that the Final Report establishes the
    adequacy of the remediation that has been implemented. They also argue that no additional
    “controls” need be developed or implemented because no further “unacceptable risks were
    found.” Reply at 4. According to DoD, the results of its investigation and analysis have already
    been documented in the Final Report, and DoD has supplied additional expert declarations in this
    litigation to support its determinations that further mitigation is not necessary to protect those
    who live and work at Camp Justice from an unacceptable risk of environmental harm. See Mot.
    to Dismiss, Exs. 1-5 (expert declarations) [Dkts. 10-1 - 10-5].
    21
    Plaintiffs’ argument does not overcome the fact that the actions sought in their
    Complaint have been undertaken and, to the extent demanded, completed. When a plaintiff has
    received the relief sought but considers the outcome wrong, a charge of unreasonable delay is no
    longer live and review lies in the APA’s protection against arbitrary and capricious action. See
    Bldg & Constr. Trades Dep’t, AFL-CIO v. Solis, 
    600 F. Supp. 2d 25
     (D.D.C. 2009). The instant
    Complaint alleges unreasonable delay as to both the risk assessment and the implementation of
    controls; it seeks a writ of mandamus to require these actions. Compl. ¶¶ 135, 139. However,
    the Final Report constitutes the Navy’s final act as to the risk assessment and implementation of
    what it considers appropriate measures to address potential hazards. Given this development,
    Plaintiffs’ arguments now relate to the adequacy of these actions, not to delay.
    Plaintiffs resist this conclusion by citing two D.C. Circuit cases on unreasonable
    delay, both of which found that the claims at issue were not moot. See Kifafi v. Hilton Hotels
    Ret. Plan, 
    701 F.3d 718
     (D.C. Cir. 2012); True the Vote, Inc. v. Internal Revenue Serv., 
    831 F.3d 551
     (D.C. Cir. 2016). Neither case supports Plaintiffs’ argument here because both involved the
    voluntary cessation of the challenged conduct, not the fulfillment of a plaintiff’s demands for
    relief. In a case of voluntary cessation, the defendant is still “free to return to its old ways” and
    cannot be said to have “irrevocably eradicated the effects of the alleged violation.” True the
    Vote, 831 F.3d at 561 (internal quotation marks and citations omitted). In contrast, the “alleged
    violation” here was unreasonable delay in analyzing the risk and implementing controls. There
    is no longer any danger that DoD will continue to delay its risk assessment and related
    implementation, because these activities have been completed, whether or not to Plaintiffs’
    satisfaction.
    22
    Plaintiffs further argue that Defendants’ actions are incomplete because they have
    not implemented all recommendations from the Final Report, “such as the implementation of an
    operations and management program for asbestos-containing materials.” Opp’n at 11. Citing
    True the Vote, Plaintiffs argue that even if these claims are “nearly moot,” they are still subject to
    review. Opp’n at 11 (citing True the Vote, 831 F.3d at 561). Defendants counter that all
    necessary steps to mitigate the alleged health risks (such as changes to heating, ventilation, and
    air conditioning) have been taken, and that any remaining recommendations are discretionary. In
    light of the record evidence, DoD has resolved the allegations of delay advanced by Plaintiffs,
    that is, delay in completing a risk assessment and delay in implementing “controls to address
    environmental contamination and other unhealthy conditions.” Compl. ¶ 135. Plaintiffs’
    ongoing allegations relate to the adequacy of DoD’s investigation and remediation measures, not
    to unreasonable delay. The Motion to Dismiss will be granted as to Counts Two and Three and
    those claims will be dismissed as moot.
    2. Rule 12(b)(6)—Failure to State a Claim
    Count One alleges that the decision that Camp Justice is safe and habitable, and
    the requirement that Plaintiffs live and work in allegedly contaminated areas, are based on an
    inadequate investigation and implementation of mitigating controls and are therefore arbitrary
    and capricious and an abuse of the Navy’s discretion in violation of Section 706(2).
    a. Actions “Committed to Agency Discretion by Law”
    Defendants argue that the challenged actions are “committed to agency discretion
    by law” and are therefore unreviewable by the Court, even under the APA. See 
    5 U.S.C. § 701
    (a)(2). Plaintiffs respond that Defendants failed to raise this defense in their Motion to
    Dismiss and that the Court should not consider it now. Plaintiffs are correct that the question of
    23
    agency discretion is an affirmative defense that does not go to the Court’s jurisdiction, but they
    do not cite any authority for the suggestion that Defendants’ failure to raise the issue in their
    Motion to Dismiss precludes the Court from determining whether the claims are reviewable and
    as to which Plaintiffs have had a full opportunity to object. Indeed, under Federal Rule of Civil
    Procedure 12(h)(1), failure to state a claim upon which relief can be granted is not a defense that
    can be waived if a party fails to include it in a responsive pleading or other papers filed with the
    Court. See Fed. R. Civ. P. 12(h), (b)(2)-(5) (providing that a party waives the defenses of lack of
    personal jurisdiction, improper venue, insufficient process, and insufficient service of process by
    failing to make them by motion, but that failure to state a claim may be raised by a motion under
    Rule 12(c)). Moreover, although the question is not jurisdictional, it is a “threshold” question:
    the Court cannot review an action that is outside the Court’s authority to review. See Heckler,
    
    470 U.S. at 829
     (discussing the “‘threshold question’ of whether the agency’s action was at all
    reviewable” (quoting Citizens to Pres. Overton Park v. Volpe, 
    401 U.S. 402
    , 410 (1971))).
    Defendants characterize the administrative action at issue as the Navy’s refusal to
    take action—a category of administrative action that is presumptively unreviewable. See
    Heckler, 
    470 U.S. at 831
    . DoD further argues that its actions were “[o]perational military
    decisions” that “fall very much within this ‘presumptively unreviewable’ category.” Defs.’ Juris.
    Br. at 8. Without further elaboration, the Court cannot agree with this characterization of the
    nature of the claims at issue. Plaintiffs challenge the adequacy of DoD’s investigation and
    remediation efforts, not its decision to exercise enforcement discretion. Because Count Three
    does not complain of a refusal to act, its allegations are not presumptively unreviewable.
    As to the argument that the Navy engaged in “operational military decisions” that
    are presumptively unreviewable, DoD provides no legal or factual analysis to establish that the
    24
    healthy maintenance of Camp Justice falls within an “operational military” category. Plaintiffs
    are appointed counsel and DoD employees who are required, by virtue of their appointments, to
    live and work at times on an operating base. Only Major Seeger is in the military forces.
    Certainly, the Navy retains discretion to manage NSGB, but DoD does not connect its
    operational mission to Camp Justice or to Plaintiffs’ allegations of serious environmental
    hazards, which, at this point, the Court assumes are true. See Twombly, 
    550 U.S. at 572
    .
    Defendants also argue that the challenged actions are “committed to agency
    discretion” by law because there are no judicially manageable standards by which to judge them.
    This argument is based on Heckler, which held that a claim is unreviewable if “no judicially
    manageable standards are available for judging how and when an agency should exercise its
    discretion.” Heckler, 
    470 U.S. at 830
    . In these circumstances, the argument amounts to stuff
    and nonsense. The “arbitrary and capricious” standard of the APA is well established. Further,
    judicially manageable standards are not limited to statutory terms but also “may be found in
    formal and informal policy statements and regulations” because “[i]t is well settled that an
    agency, even one that enjoys broad discretion, must adhere to voluntarily adopted, binding
    policies that limit its discretion.” Padula v. Webster, 
    822 F.2d 97
    , 100 (D.C. Cir. 1987) (citing
    Vitarelli v. Seaton, 
    359 U.S. 535
    , 539 (1959); Service v. Dulles, 
    345 U.S. 363
    , 372 (1957)).
    In determining whether administrative policies or internal statements establish
    judicially manageable standards, courts look to whether statements “[impose] rights or
    obligations on the respective parties” and whether an agency intended to transform a
    pronouncement into a binding norm. 
    Id.
     (citing American Bus Ass’n v. U.S., 
    627 F.2d 525
    , 529
    (D.C. Cir. 1980); Doe v. Hampton, 
    566 F.2d 265
    , 281-82 (D.C. Cir. 1977)); see also Steenholdt,
    
    314 F.3d at 638
     (“In determining whether agency statements create such a standard, the Court
    25
    inquires whether the statements create binding norms by imposing rights or obligations on the
    respective parties.”). Such intent is “ascertained by an examination of the provision’s language,
    its context, and any available extrinsic evidence.” Doe v. Hampton, 
    566 F.2d at 281
    . Plaintiffs
    allege, and DoD denies, that Defendants failed to follow internal policies and procedures that
    have the force and effect of binding norms. Specifically, Plaintiffs cite DoDI 6055.05, which
    articulates, as a risk management principle, that Commanders “[a]ccept no unnecessary risks” in
    the context of occupational and environmental health; DoDI 6055.05 also requires the Navy and
    the Convening Authority to investigate the nature and extent of health hazards, develop controls
    and make risk decisions, and, in Plaintiffs’ summary, “determine which risks are acceptable and
    unacceptable by balancing operational benefits against the potential for adverse health effects
    (i.e., severity and likelihood of occurrence).” Compl. ¶ 123. Plaintiffs emphasize that DoDI
    6055.05 specifies the categories of actions that military commanders should take to assess risks,
    implement controls, and monitor implementation.
    Plaintiffs additionally rely on other directives, underlying documents, and
    “applicable regulatory standards” that they argue set forth factors that DoD should have taken
    into account in making its DoDI-mandated determination, including:
       DoD Directive (DoDD) 4715.1E, which Plaintiffs characterize
    as requiring DoD to implement an Environment, Safety, and
    Occupational Health management system, see Compl. ¶¶ 66,
    123(a);
       DoDI 6055.01, which governs DoD’s safety and occupational
    health program, see Compl. ¶ 66;
       EPA standards that Plaintiffs allege Defendants acknowledge
    apply (for example, by using those standards in the Final
    Report), see, e.g., Opp’n at 7-8 n.2;
       Instructions from the Chief of Naval Operations (OPNAVIST)
    that govern safety and occupational health and require that,
    26
    among other things, identified hazards must be promptly abated,
    see Compl. ¶¶67-69;
       Navy guidance, including the Navy’s Industrial Hygiene Field
    Operations Manual, see id. ¶ 70-71, and the Navy Policy on the
    Use of Background Chemical Levels, see id. ¶¶ 72, 85, 92.
    These policies and procedures, Plaintiffs contend, establish DoD’s intent to bind its personnel to
    certain steps to address environmental hazards that were not followed at NSGB.
    Defendants argue that these directions “very clearly commit the protection of
    DoD personnel” to the Navy’s discretion. Defs.’ Juris. Br. at 6. In support, DoD cites a handful
    of DoDD and DoDI provisions, but these are insufficient, on a motion to dismiss, to demonstrate
    that none of the Directives, Instructions, or other documents cited by Plaintiffs “create[s] binding
    norms by imposing rights or obligations on the respective parties.” Steenholdt, 
    314 F.3d at 638
    .
    Indeed, while the materials cited by Defendants allow for discretion in aspects of system
    implementation and in the authority of commanders to make health-related risk/benefit
    determinations, none suggests that the Navy has full discretion to ignore them. On its face,
    DoDI 6055.05 appears to require that the Navy and Convening Authority take certain steps to
    assess risks, weigh them, establish controls, and consult other materials to make risk assessments
    and mitigate harms as necessary. See Doe v. Hampton, 
    566 F.2d at 281
     (providing that the
    language of a document can provide evidence of intent that the document binds agency action).
    Certainly, there are discretionary aspects to these requirements, and it may be that DoD’s various
    investigations, reports, and mitigation activities satisfied the requirements that do apply—but
    those questions cannot be resolved on a motion to dismiss, where the Court must accept all of
    Plaintiffs’ allegations as true. See Twombly, 
    550 U.S. at 572
    .
    27
    b.        Final Agency Action
    Finally, Defendants argue that Plaintiffs have failed to challenge a “final agency
    action” by which APA review might be available. Count One challenges DoD’s assignment of
    Plaintiffs to sleep in Cuzcos at Camp Justice during work trips, as well as the determination that
    the Camp Justice facilities are safe and habitable. Compl. ¶ 131. Defendants argue that Count
    One should be dismissed for failure to state a claim under Rule 12(b)(6), because Plaintiffs’
    allegations do not identify a final action by Defendants and therefore fail to state an APA claim.
    Final agency action is clearly required before judicial review. See 
    5 U.S.C. § 704
    (“Agency action made reviewable by statute and final agency action for which there is no other
    adequate remedy in a court are subject to judicial review.”). “The District Court’s authority to
    review the conduct of an administrative agency is limited to cases challenging ‘final agency
    action.’” Reliable Automatic Sprinkler Co., Inc. v. CPSC, 
    324 F.3d 726
    , 731 (D.C. Cir. 2003).
    The APA defines an “agency action” as “the whole or a part of an agency rule, order, license,
    sanction, relief, or the equivalent or denial thereof.” 
    5 U.S.C. § 551
    (13). “This list is
    expansive,” and is “‘meant to cover comprehensively every manner in which an agency may
    exercise its power.’” Fund for Animals, Inc. v. U.S. Bureau of Land Mgmt., 
    460 F.3d 13
    , 19
    (D.C. Cir. 2006) (quoting Whitman v. Am. Trucking Ass’ns, Inc., 
    531 U.S. 457
    , 478 (2001)).
    To be deemed final, an agency action “must ‘mark the consummation of the
    agency’s decisionmaking process,’ i.e., it is not ‘merely tentative or interlocutory.’ . . . Second,
    ‘the action must be one by which rights or obligations have been determined, or from which
    legal consequences will flow.’” Safari Club Int’l v. Jewell, 
    842 F.3d 1280
    , 1289 (D.C. Cir.
    2016) (quoting Bennett v. Spear, 
    520 U.S. 154
    , 177-78 (1997)). This is a “pragmatic” and
    “flexible” inquiry. Safari Club, 842 F.3d at 1289 (quoting Nat’l Ass’n of Home Builders v. U.S.
    28
    Army Corps of Eng’rs, 
    417 F.3d 1272
    , 1279 (D.C. Cir. 2005)). The possibility that a decision
    may later be revised based on new information does not render “an otherwise definitive decision
    nonfinal.” Safari Club, 842 F.3d at 1289 (quoting U.S. Army Corps of Eng’rs v. Hawkes Co.,
    
    136 S. Ct. 1807
    , 1814 (2016)).
    The first question raised by Defendants’ argument is what action or actions
    Plaintiffs actually challenge in their lawsuit. Count One of the Complaint describes the actions
    at issue as “[t]he Navy’s decision that Camp Justice is safe and habitable, and Defendants’
    decision that Plaintiffs and other personnel must live and work in contaminated areas at Camp
    Justice.” Compl. ¶ 131. In brief, Plaintiffs characterize their complaint as a challenge to DoD’s
    “flawed and incomplete risk management process and the resulting orders to live and work at
    Camp Justice.” Opp’n at 8. Plaintiffs also reference “DoD’s repeated orders assigning Plaintiffs
    to live and work at Camp Justice,” and suggest that these orders provide evidence that DoD
    “determined that Camp Justice was safe and habitable and that personnel should continue to live
    and work there.” Id. at 13. Finally, Plaintiffs describe the “agency actions” in question as
    “DoD’s repeated, health-threatening orders that the Plaintiffs live and work in contaminated
    areas of Camp Justice, DoD’s failure to protect the Plaintiffs from environmental hazards, and
    DoD’s determination that Camp Justice is safe and habitable.” Opp’n at 14. For purposes of
    determining whether Plaintiffs have challenged “final agency actions,” the Court interprets these
    passages collectively as a challenge to two categories of agency action: (1) DoD’s assignment of
    Plaintiffs to live and work in contaminated areas at Camp Justice during work trips, and (2)
    DoD’s “determination” that Camp Justice safe and habitable.
    29
    i. Did DoD’s Assignment of Plaintiffs to Allegedly Contaminated
    Accommodations Constitute Final Agency Action?
    The Complaint alleges that “[e]ach time military commissions hearings are
    scheduled at Camp Justice, the legal teams and support personnel request travel arrangements
    from the Convening Authority and receive orders from the Convening Authority assigning them
    to specific housing.” Compl. ¶ 26. At the hearing on their motion for a preliminary injunction,
    Plaintiffs acknowledged that only Major Seeger, as an Army officer, is required without
    exception to stay in the allegedly contaminated Camp Justice housing; the non-military Plaintiffs
    may stay in preferable hard housing such as the townhouses or nearby hotel rooms, subject to
    availability which has usually been arranged. See PI Tr. at 44-46.9
    Plaintiffs complain further that their support staff, such as legal assistants who
    accompany them to NSGB for detainee hearings, are inconvenienced and endangered by the
    housing assignments, which impedes Plaintiffs’ work by limiting or interfering with their ability
    9
    DoD counsel proffered, without contradiction, that Plaintiff Michael Schwartz stayed on-base
    for a total of 29 days in 2016, always staying at the Navy Lodge or NSGB housing; from
    January-July 2017 he stayed at the Navy Lodge for seven days and in Cuzcos for four days. PI
    Tr. at 44. Plaintiffs Cheryl Bormann and Edwin Perry have traveled to NSGB numerous times
    since 2014 and 2015, respectively, and both have always stayed in “hard housing”: Ms.
    Bormann stayed at either the Navy Lodge or NSGB “hard housing” during her four days on-base
    in 2014, 46 days in 2015, 40 days in 2016, and 22 days in January-July of 2017, and as of July
    2017 she had received “hard housing” assignments for her remaining work trips in 2017; Mr.
    Perry stayed in the Navy Lodge or NSGB “hard housing” for a total of 21 days in 2015, 56 days
    in 2016, and 21 days in January-July 2017, and also had hard housing reservations for the
    remainder of his 2017 trips as of July 2017. Id. at 44. As an Army officer, Major Seeger stayed
    in Cuzcos for a total of 18 days in 2015, 63 days in 2016, and 23 days in January-July 2017, with
    no option of requesting hard housing even if available. Id. at 46. Defendants do not challenge
    Mr. Schwartz’s, Ms. Bormann’s, or Mr. Perry’s standing on the grounds that they have stayed in
    “hard housing” for all or the vast majority of their time on-base. Because Plaintiffs’ allegations
    are based on the potential harm of both living and working in allegedly contaminated housing,
    and because the operative housing policy does not guarantee “hard housing” to Plaintiffs and
    apparently prioritizes their right to preferable housing below the needs of other visitors to NSGB,
    the Court does not find any impediments to these Plaintiffs’ standing on such grounds.
    30
    to bring support staff. See Compl. ¶ 29. Plaintiffs also complain that the work they are assigned
    requires them to spend the majority of their working hours on base in allegedly contaminated
    areas because the SCIF and designated defense workspaces convenient to the SCIF have been
    built in hazardous containerized housing. See Compl. ¶ 30.
    Defendants respond that Plaintiffs do not cite “any specific regulation, policy, or
    decision” that requires them to live and work in the allegedly contaminated areas, so that “there
    is no final agency action, nor is there an administrative record on which such an action could
    have been based.” Mot. to Dismiss at 17. In support, Defendants cite Fraternal Order of Police
    v. Gates, which held that a challenge to the Navy’s exposure of trainees to pepper spray failed to
    state a claim, because those plaintiffs had been “less than clear as to which agency action is at
    issue” and had failed to “connect the [challenged] training to the language of the DoD and Navy
    documents” cited in their complaint. 
    602 F. Supp. 2d 104
    , 107-08 (D.D.C. 2009).
    Defendants’ reliance on Fraternal Order is unpersuasive. The Fraternal Order
    court found that the right to relief was “speculative,” Twombly, 
    550 U.S. at 555
    , because the
    plaintiffs had not identified the precise agency actions challenged, leaving the Court to “guess.”
    Fraternal Order, 
    602 F. Supp. 2d at 108
    . Here, however, there is no need to guess which actions
    Plaintiffs challenge or what law and policies upon which they rely. Defendants are mistaken
    when they argue that Plaintiffs fail to point to any decision that requires Plaintiffs to stay at
    Camp Justice. Plaintiffs’ pleadings, which the Court accepts as accurate in this procedural
    posture, clearly allege that there is a procedure in place whereby attorneys and other visiting
    personnel submit housing requests for upcoming work trips, and that the Convening Authority
    orders them to specific housing. Further, the nature of their work as attorneys requires them to
    31
    work in the SCIF where relevant documents are available and classified briefs can be prepared
    but which is allegedly contaminated.
    It is well established that “a completed universe” of orders can establish a final
    agency action subject to APA review: less central to the analysis than the format of the orders is
    whether “the scope of the controversy has been reduced to manageable proportions, and its
    factual components fleshed out, by concrete action that harms or threatens to harm the
    complainant.” Lujan, 
    497 U.S. at 873
    . Particularly when viewed within the “pragmatic” and
    “flexible” framework of the inquiry into “final agency action” and the acceptance given to a
    plaintiff’s fact allegations, the Complaint adequately alleges final agency action. Nat’l Ass’n of
    Home Builders, 417 F.3d at 1279. The orders are a “consummation of the agency’s
    decisionmaking process,” imposing on Plaintiffs the requirement that they work, and possibly
    stay, in the facilities of which they complain. Safari Club, 842 F.3d at 1289. That decision in
    turn places Plaintiffs’ health at risk, according to their pleadings. The housing orders and
    necessary work areas are clearly connected to the alleged policy violations, and the Court
    concludes that Plaintiffs have alleged final agency action sufficient to state a claim.
    ii. Did DoD’s Determination that Camp Justice Is Safe and
    Habitable Constitute Final Agency Action?
    Plaintiffs allege that DoD’s “determination that Camp Justice is sufficiently safe
    and habitable to live and work there” is final agency action, because “there is no indication that
    Defendants will alter their position regarding the environmental contamination at Camp Justice.”
    Opp’n at 15; see also Compl. ¶ 8 (“Defendants’ decision to require Plaintiffs and other personnel
    to live and work [at Camp Justice] should be set aside as arbitrary and capricious.”). Plaintiffs
    allege that DoD’s repeated orders assigning Plaintiffs to live and work at Camp Justice are
    evidence of a final decision. Opp’n at 12. Plaintiffs also allege that Defendants “fail[ed] to
    32
    properly complete the risk management process required by DoD Instruction 6055.05 . . . and to
    determine whether the operational benefits of requiring personnel to live and work there
    outweigh the risk to those individuals’ health.” Id. DoD’s limited response argues that DoDI
    6055.05 and other “[i]nternal guidelines” are “insufficient to connect agency action to specific
    regulatory authorization or to raise a right to relief above the speculative level.” Reply at 7
    (citing Fraternal Order, 
    602 F. Supp. 2d at 107-08
    ).10
    Plaintiffs argue that the decision that Camp Justice is safe and habitable is
    “concrete” and “reviewable” because the orders and assignments to live and work in allegedly
    contaminated housing and work space “operate as a de facto risk management decision” that
    violates DoDI 6055.05. Opp’n at 13. As the Court found above, Navy undertook a
    “decisionmaking process” which “consummate[ed]” in the issuance of the Final Report. Bennett,
    520 U.S. at 178.
    What is less clear is whether any of the allegedly flawed investigation, risk
    assessment, mitigation, and Final Report constitute final agency action. Such a study does not fit
    the statutory definition of agency action, that is, “the whole or a part of an agency rule, order,
    license, sanction, relief, or the equivalent or denial thereof.” 
    5 U.S.C. § 551
    (13). Even if the
    Final Report were “definitive,” it is the resulting order, not the preceding study that has a “‘direct
    and immediate . . . effect on the day to day business’ of the party challenging the agency action.”
    Reliable Automatic Sprinkler, 
    324 F.3d at 731
     (quoting FTC v. Standard Oil Co. of Cal., 449
    10
    Defendants also cite Schweiker v. Hansen, 
    450 U.S. 785
     (1981), for the proposition that
    internal guidelines “do not create an actionable duty for an agency.” Reply at 7. While an
    accurate point, reference to Schweiker is curious because that case did not analyze any APA
    questions, much less whether agency action is final, and there is no shortage of Supreme Court
    and D.C. Circuit cases more squarely considering the question. Plaintiffs allege that the Navy at
    NSGB was required to abide by the various directives and instructions they cite, and Defendants
    do not overcome those allegations.
    
    33 U.S. 232
    , 239 (1980)). Applied here, it is Navy’s orders, whether explicit or functional, that are
    the means through which it “may exercise its power.” Whitman, 
    531 U.S. at 478
    . As the D.C.
    Circuit noted in Fund for Animals, “[m]uch of what an agency does is in anticipation of agency
    action. Agencies prepare proposals, conduct studies, . . . and engage in a wide variety of
    activities that comprise the common business of managing government programs.” 
    460 F.3d at 19-20
    . In the context of potential harms to Plaintiffs, the determination that the areas in question
    are safe and habitable is such an anticipatory step, while the housing orders and necessary
    location of work assignments are the final actions on which Plaintiffs’ claim is based.
    B. Preliminary Injunction
    First, the Motion for a Preliminary Injunction will be denied as moot as to Counts
    Two and Three, because those claims do not survive DoD’s Motion to Dismiss.
    Second, as Winter recently emphasized, a preliminary injunction is “an
    extraordinary remedy that may only be awarded upon a clear showing that the plaintiff is entitled
    to such relief.” Winter, 
    555 U.S. at 22
    . Since Winter was decided, the D.C. Circuit has twice
    declined to abandon the sliding-scale approach. See Sherley, 
    644 F.3d at 393
     (“We need not
    wade into this circuit split today.”); Davis v. Pension Ben. Guar. Corp., 
    571 F.3d 1288
    , 1292
    (D.C. Cir. 2009) (“We need not decide whether a stricter standard applies.”). Recognizing the
    Circuit’s silence, this Court nonetheless concludes that Winter makes clear that a plaintiff must
    make, at the least, a strong showing on likelihood of success on the merits and irreparable harm,
    or he cannot obtain preliminary injunctive relief.
    1. Likelihood of Success on the Merits
    Plaintiffs argue that they have demonstrated a likelihood of success on the merits
    because “[t]here is simply no reasonable or rational justification for requiring Plaintiffs and
    34
    others to live and work in dangerous, contaminated areas, particularly where, as here,
    uncontaminated alternatives exist,” which renders the Navy’s orders arbitrary and capricious.
    Mot. PI at 11 (citing 
    5 U.S.C. § 706
    (2)(A)). Plaintiffs cite DoDD 4715.1E, which charges DoD
    components with ensuring compliance with applicable “laws, regulations, and DoD policies,”
    and which Plaintiffs take to include environmental safety and occupational health laws and
    policies, such as EPA standards for environmental health and safety. Mot. PI at 12. Plaintiffs
    contend that the Navy violated these policies by failing to address “data gaps”; conducting
    insufficient “additional environmental sampling”; failing to address moisture and microbial
    growth; and inadequately mitigating risks posed by formaldehyde and benzo(a)pyrene identified
    in sampling. More generally, Plaintiffs allege that the investigation itself was inadequate. Their
    summary allegation is that the Navy’s orders that Plaintiffs “continue to live and work in
    contaminated areas at Camp Justice . . . materially deviate from the Navy’s own regulations,
    policies, and guidance (as well as recommendations from its own consultants).” 
    Id. at 12
    .
    DoD’s response emphasizes the process and reasoning behind its determination
    that the facilities at Camp Justice are habitable without undue risk:
    NMCPHC’s Final PHR Report concluded that there is no evidence
    that the old runway at Camp Justice was contaminated from prior
    use, no evidence that Camp Justice personnel are exposed to
    carcinogens or toxic substances above the acceptable risk ranges
    established by the EPA, OSHA, and other regulatory agencies, and
    no evidence that any verifiable cancer cases are linked to
    environmental or occupational exposure at Camp Justice. [The
    Report’s] findings and recommendations are well-founded, and it
    would not be the Court’s place to second-guess the NMCPHC’s
    expert analysis.
    Mot. to Dismiss at 20 (citing Lee Mem’l Health Sys. v. Burwell, 
    206 F. Supp. 3d 307
    , 321
    (D.D.C. 2016)).
    35
    Plaintiffs raise particular concern regarding the February 2016 Navy Preliminary
    Assessment, which the Navy characterizes in the Final Report as a “preliminary public health
    screening risk assessment.” Final Report at 6. Plaintiffs charge that Navy had concluded in
    February 2016 that “formaldehyde and benzo(a)pyrene found in the samples exceeded the
    screening levels [NMCPHC] had established for a 9-month active duty military worker.” Mot.
    PI at 13; see also Final Report at 6-8. The Court recognizes that formaldehyde is of particular
    concern to Plaintiffs. Indeed, based on the prominent placement of discussions of formaldehyde
    levels and remediation, this appears to be an issue of great concern in the Final Report as well.11
    However, the Final Report provides significant detail, beyond the February 2016 Navy
    Preliminary Assessment, that undercuts Plaintiffs’ likelihood of success.
    The Final Report states that “[t]he results of the preliminary public health
    screening risk assessment [i.e., the February 2016 Navy Preliminary Assessment] indicated that
    mercury and formaldehyde concentrations in indoor air, and arsenic and benzo(a)pyrene
    concentrations in soil were of potential concern and warranted further evaluation at specific
    locations in Camp Justice,” although the mercury and formaldehyde levels measured in indoor
    air were within the acceptable OSHA range.12 Final Report at 6. As Defendants’ counsel
    explained at oral argument, the concentrations at that time warranted further evaluation because
    they exceeded EPA screening standards set forth in the Comprehensive Environmental
    Response, Compensation, and Liability Act (CERCLA, commonly known as the Superfund), 42
    11
    Because formaldehyde is the most serious potential hazard of which Plaintiffs complain, the
    Court’s analysis on the Motion for a Preliminary Injunction focuses on formaldehyde exposure.
    Plaintiffs have raised other issues of concern but none satisfies the standards for a preliminary
    injunction.
    12
    OSHA sets Permissible Exposure Limits, or PELs, which are enforceable regulatory standards
    for determining allowable exposures in U.S. workplaces. See Gillooly Decl. at 12.
    
    36 U.S.C. § 9601
     et seq. See PI Tr. at 38-39. Contrary to Plaintiffs’ contention that DoD has
    “conceded” that “EPA CERCLA risk guidance must be used,” PI Tr. at 26, Defendants argue
    that CERCLA guidelines do not impose requirements on an overseas base such as NSGB, but
    were only “borrow[ed]” for use as a benchmark during the investigation prior to the Final
    Report. 
    Id. at 38-39
    .
    The Final Report concluded that “[c]umulative cancer risks were within the
    [EPA] acceptable risk range of 1E-06 to 1E04 (i.e., 1 in 1,000,000 to 1 in 10,000)” for “Adult
    Resident/Workers Inside Camp Justice.” Final Report at 41. The Final Report stated that, after
    “engineering controls” including HVAC modifications, formaldehyde levels in “almost all
    modular buildings” decreased by an average of 63 percent. 
    Id. at 8
    . It also reported that the
    “concentrations of formaldehyde detected in indoor air at Camp Justice were within the range of
    concentrations considered ‘Low’ to ‘Mid’ by the CDC for typical concentrations observed in
    manufactured homes” in the United States. 
    Id. at 42
    . The Final Report recommended new
    procedures to document modifications and monitor the functionality of HVAC systems going
    forward, and suggested that the Navy “consider sampling formaldehyde annually during the
    summer to verify and demonstrate that engineering controls are effective at keeping
    formaldehyde levels at their current reduced levels.” 
    Id. at 13
    . Although Plaintiffs’ expert, Dr.
    Killen, expressed his concern regarding identified toxins and possible exposure pathways, see
    Killen Report at 1, Navy experts reviewed the same data and concluded that the detected
    formaldehyde levels, and historical use and effects of the area, did not indicate an unacceptable
    risk. See, e.g., Gillooly Decl. at 7-11 (discussing the iterative process of repeated formaldehyde
    sampling and mitigation efforts).
    37
    Plaintiffs further challenge DoD’s conclusions because its samples came from
    only 16 of the 100 Cuzco sleeping spaces, and because they did not test and re-test all of them.
    See, e.g., Killen Report at 10 (“[I]n a serious deviation from appropriate testing protocol and
    methodology, not all CUZCOSs appear to have been sampled, even though formaldehyde was
    detected in all locations that were sampled.”). Dr. Killen does not explain in sufficient detail to
    counter the Final Report why it is methodologically unsound to sample some but not all of a
    collection of nearly identical structures situated in close proximity. Notably, the subsequent
    HVAC modifications, shown in later sampling to have been effective in reducing formaldehyde
    exposure, was implemented in all of the Cuzcos used for sleeping.
    Plaintiffs’ motion does not sufficiently demonstrate that DoD’s conclusion was an
    unreasonable risk assessment or that DoD wholly disregarded the broad guidelines set forth in
    DoDI 6055.05 and the other relevant policies. The investigation into potential hazards was
    apparently considered with competing needs. DoD considered factors such as housing demand,
    convenience to the ELC, and other reasons to assign legal team members to live and work in the
    contested housing.
    Plaintiffs’ motion does not show a likelihood of success on the merits. DoD
    appears to have examined the relevant data and articulated “‘a rational connection between the
    facts found and the choice made.’” Americans for Safe Access v. DEA, 
    706 F.3d 438
    , 449 (D.C.
    Cir. 2013) (quoting MD Pharm. Inc. v. DEA, 
    133 F.3d 8
    , 16 (D.C. Cir. 1998)). The Court
    concludes that Plaintiffs have not shown that they are likely to succeed on the merits, such that
    the extraordinary remedy of a preliminary injunction is warranted.
    38
    2. Irreparable Injury
    The Court finds that Plaintiffs also have failed to demonstrate irreparable injury.
    Such harm must be “certain, great, actual, and imminent.” Mylan Labs. Ltd. v. FDA, 
    910 F. Supp. 2d 299
    , 313 (D.D.C. 2012) (citing Wis. Gas Co. v. FERC, 
    758 F.2d 669
    , 674 (D.C. Cir.
    1985)). While the alleged harm—risk of cancer—is no doubt “great,” the record does not show
    that it is currently “certain,” “actual,” or “imminent.” DoD has made important upgrades,
    including HVAC modifications in modular buildings and additional actions in the Cuzco living
    quarters. See App’x F Status Report at 21-22. The fact that these upgrades have been made, and
    have been shown to mitigate potential harms, lessens the likelihood of irreparable harm.
    3. Balance of Equities and Public Interest
    Plaintiffs contend that the equities and the public interest favor granting their
    requested injunction. These two factors merge when relief is sought against the government.
    United States Ass’n of Reptile Keepers, Inc. v. Jewell, 
    103 F. Supp. 3d 133
    , 163 (D.D.C. 2015)
    (citing Nken v. Holder, 
    556 U.S. 418
    , 435 (2009)). Plaintiffs cite the “significant risk due to the
    exposures summarized herein” and the “readily available” alternative facilities at NSGB. Mot.
    PI at 20. They also cite the public interest in the proper functioning of the Military
    Commissions. Id. at 21. Through declarations from persons with relevant experience and
    knowledge, the Navy responds that the Military Commissions have specific housing and
    workspace requirements, due to the specialized security requirements for its cases, and that there
    are no other facilities at NSGB that would meet those requirements. See Mot. to Dismiss, Exs.
    2-4 (declarations of Wendy A. Kelly; Capt. David Culpepper, USN; and Sandra Greenwell). The
    Navy argues that if it were required to house all lawyers for detainees in hard housing and
    39
    provide new work facilities, the operations of the base would be affected for its personnel and its
    mission.
    “In each case, courts ‘must balance the competing claims of injury and must
    consider the effect on each party of the granting or withholding of the requested relief.’” Winter,
    
    555 U.S. at 24
     (quoting Amoco Prod. Co. v. Vill. of Gambell, Alaska, 
    480 U.S. 531
    , 542 (1987)).
    The parties present their arguments in abbreviated form and without sufficient detail for the
    Court to perform the balancing of interests as required before an injunction can be issued.
    Plaintiffs have therefore failed to demonstrate that the current balance of equities and the public
    interest favor issuance of an injunction.
    CONCLUSION
    For the reasons discussed above, Plaintiffs’ motion for a preliminary injunction
    will be denied. Defendants’ motion to dismiss will be granted as to Counts Two and Three and
    denied as to Count One. A memorializing Order accompanies this Memorandum Opinion.
    Date: March 30, 2018
    /s/
    ROSEMARY M. COLLYER
    United States District Judge
    40