Crowley Government Services, Inc. v. General Services Administration ( 2021 )


Menu:
  •                               UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    CROWLEY GOVERNMENT SERVICES, INC.,
    Plaintiff,
    Civil Action No. 21-2298 (BAH)
    v.
    Chief Judge Beryl A. Howell
    GENERAL SERVICES ADMINISTRATION, et al.,
    Defendants.
    MEMORANDUM OPINION
    Plaintiff Crowley Government Services, Inc. (“Crowley”) brings this action against the
    General Services Administration and its Administrator (collectively, “GSA”), seeking equitable
    relief to stop GSA’s alleged ongoing practice of interfering with payments due plaintiff pursuant
    to a contract with the U.S. Transportation Command (“USTRANSCOM”), a unit of the
    Department of Defense. Compl. ¶¶ 1–11, ECF No. 1. GSA is not a party to the contract
    underlying this dispute, id. ¶ 40, but in performing its auditing function has adopted and persists
    in applying a different interpretation of plaintiff’s contract than that of the actual contracting
    party USTRANSCOM, id. ¶¶ 40–69, leaving plaintiff in the difficult and expensive circumstance
    of performing under the contract but without getting paid the amounts that both contracting
    parties apparently believe to be owed.
    Plaintiff seeks an order preliminarily enjoining defendants from “auditing invoices
    submitted by Crowley to [USTRANSCOM] under Crowley’s contract with USTRANSCOM”
    and “to the extent GSA has any authority to audit Crowley’s invoices, making audit
    determinations regarding the validity of those invoices that are inconsistent with the Contracting
    Officer’s final and conclusive decisions regarding the interpretation of the contract and
    1
    Crowley’s performance under the contract.” Pl.’s Mot. Prelim. Inj. (“Pl.’s Mot.”) at 1–2, ECF
    No. 9. In response, GSA moves to dismiss the case, pursuant to Federal Rules of Civil
    Procedure 12(b)(1) and 12(b)(6), contending that “this Court lacks jurisdiction over Plaintiff’s
    claims for several independent reasons and the complaint fails to state a valid claim under the
    Administrative Procedure Act.” Defs.’ Mot. Dismiss (“Defs.’ Mot.”) at 1, ECF No. 13. Most
    importantly, GSA argues that the United States Court of Federal Claims (“CFC”)—in which
    plaintiff also has pending a complaint arising from the same events—has exclusive jurisdiction
    pursuant to the Tucker Act, 
    28 U.S.C. § 1491
    . Defs.’ Mot. at 1; see also Defs.’ Mem. Supp.
    Mot. Dismiss & Opp’n Pl.’s Mot. Prelim. Inj. (“Defs.’ Opp’n”) at 7–21, ECF No. 13; Defs.’
    Reply Supp. Mot. Dismiss (“Defs.’ Reply”) at 2–8, ECF No. 19.
    For the reasons discussed below, GSA’s Motion to Dismiss is granted, under Federal
    Rule of Civil Procedure 12(b)(1), and plaintiff’s Motion for Preliminary Injunction must be
    denied as moot. 1
    I.       BACKGROUND
    A.       Factual Background
    Plaintiff is a company that “provides marine solutions, energy, and logistics services in
    domestic and international markets.” Compl. ¶ 12. Unfortunately for plaintiff, as noted, the
    instant dispute arises from a government contract that is apparently differently interpreted by two
    government agencies.
    1
    GSA also moves in the alternative to dismiss for failure to “identify final agency action subject to current
    judicial review,” pursuant to Federal Rule of Civil Procedure 12(b)(6). Defs.’ Mot. at 1. “As the finding that
    subject-matter jurisdiction has not been established requires that the case be fully dismissed, this alternative ground
    for dismissal need not be addressed.” Rosenkrantz v. Inter-Am. Dev. Bank, No. 20-cv-3670 (BAH), 
    2021 WL 1254367
    , at *1 n.1 (D.D.C. Apr. 5, 2021).
    2
    1.      Plaintiff’s Contract with USTRANSCOM
    On November 22, 2016, USTRANSCOM awarded, to plaintiff’s predecessor-in-interest,
    Contract No. HTC711-17-D-R003 (“Contract”), under which plaintiff now “provides various
    logistical, planning, and transportation coordination services to assist USTRANSCOM with
    managing a large and complex network of moving goods and cargo for the Department of
    Defense.” Compl. ¶¶ 19–21.
    Under the Contract, plaintiff receives shipping orders from government shippers
    specifying the origin, destination, and other attributes of desired cargo shipments within the
    continental United States. Compl. ¶¶ 30, 34. In response, plaintiff plans and coordinates the
    transportation of the shipments from end to end—selecting, scheduling, and paying various types
    of subcontractors to perform the actual handling and movement of the cargo. 
    Id.
     ¶¶ 31–32, 35.
    The Contract sets forth certain performance standards for delivery timeframes and allowable
    reasons for deviations from those standards (e.g., inclement weather), 
    id.
     ¶¶ 36–37, as well as
    certain conventions for the computation of shipping timeframes (e.g., the treatment of weekends
    and holidays), 
    id.
     ¶¶ 38–39.
    Since inception of the Contract, plaintiff has provided this shipping service for roughly
    1.2 million shipments. Compl. ¶ 33. Plaintiff does not in the instant case register any grievances
    as to USTRANSCOM’s performance under the Contract, nor does it indicate that the parties to
    the Contract materially disagree as to its essential terms.
    2.      GSA Involvement
    Plaintiff’s complaint arises from allegedly unwanted, extracontractual, and erroneous
    interventions by GSA, in the form of Notices of Overcharge (“NOCs”), after the invoicing phase
    of shipments. Specifically, GSA “audit[s] Crowley’s invoices to USTRANSCOM and assess[es]
    3
    NOCs against Crowley,” Compl. ¶ 42, despite being neither a party to the Contract nor expressly
    contemplated by the Contract to have a role in its administration, 
    id.
     ¶¶ 40–41. Broadly
    speaking, GSA’s disagreements with plaintiff’s invoices include the applicability of allowed
    exceptions to expected delivery timelines, 
    id. ¶ 43
    , the method of counting days when measuring
    actual delivery performance, 
    id.
     ¶¶ 45–46, and issues stemming from alleged errors in
    government paperwork or limitations in government booking systems, 
    id.
     ¶¶ 47–52.
    The Contract, according to plaintiff, contains a “disputes clause” whereby plaintiff may
    “pursue claim[s] for relief” with the appropriate Contracting Officer at USTRANSCOM for such
    matters as the perceived GSA interference with invoicing and payment processes. See Compl.
    ¶ 54. Over the course of 2020, plaintiff made a claim regarding “a sample of” GSA’s NOCs,
    representing the various categories of disputed issues, with the Contracting Officer, resulting in
    the Contracting Officer issuing three Final Decisions that same year, indicating substantive
    agreement with plaintiff on the disputed matters and concluding with respect to each that
    “‘NOCs should not have been issued.’” 
    Id.
     ¶¶ 55–69 (quoting Compl., Ex. C, Contracting
    Officer’s Final Decision Regarding Certified Claim (“December 2020 Final Decision”) ¶ 3, ECF
    No. 1-4). 2 The Contracting Officer observed that although “GSA was provided an opportunity to
    validate its issuance of [NOCs] disputed in this claim,” GSA “declined to provide a meaningful
    or thorough response” and as a result the NOCs “are not factually supportable, and, hence, are
    not valid.” Compl. ¶ 68 (quoting December 2020 Final Decision ¶ 3(a)).
    2
    The claim involved 168 NOCs covering services rendered in April 2018, totaling $119,483.03. December
    2020 Final Decision at 1; 
    id. ¶ 1
    (d). The Contracting Officer agreed that the NOCs were erroneous to the full extent
    of plaintiff’s claim but reduced its determination of the refund due plaintiff by $43,067.50 because it turned out that,
    unbeknownst to both plaintiff and USTRANSCOM, GSA had already partially refunded some of the NOC amounts.
    
    Id. ¶¶ 2
    (e), 3(a).
    4
    The December 2020 Final Decision explained the mechanism by which GSA’s offsets
    were collected. USTRANSCOM employs a third-party payment system, operated by a bank,
    through which GSA “unilaterally applie[s] off-sets to future payments to Crowley” pursuant to
    the NOCs, without coordinating such offsets with USTRANSCOM or the Defense Logistics
    Agency (“DLA”). December 2020 Final Decision ¶ 3(f)(1). When this happens, DLA has
    already paid the bank for the full amount of the invoice, 
    id.,
     but GSA deducts the NOC amount
    from a payment due from the bank to plaintiff, with the proceeds (net of collection expenses)
    ultimately destined for a miscellaneous receipts account with the Treasury, 
    id. ¶ 3
    (f)(2) (citing 
    31 U.S.C. § 3726
    (d), (f)). The Contracting Officer described these funds as “remain[ing] in GSA’s
    possession” and noted that USTRANSCOM lacked authority either to direct GSA to reimburse
    plaintiff or to direct a disbursement from the miscellaneous receipts Treasury account. 
    Id.
    Therefore, according to the Contracting Officer, “recovery of these funds is through the GSA
    Post-Payment Audit dispute process, appealable to the Civilian Board of Contract Appeals
    [(“CBCA”)] or the U.S. Court of Federal Claims.” Id.; see also 
    41 C.F.R. § 102-118.650
    (enumerating the CBCA and the CFC as avenues for review of “a settlement action taken by the
    Administrator of General Services”). USTRANSCOM thus was unable to refund the disputed
    amount to plaintiff despite agreeing that plaintiff was entitled to those funds.
    Plaintiff reports that even after the December 2020 Final Decision, “GSA continues to
    issue NOCs.” Compl. ¶ 70. “In June 2021 alone, Crowley received over 11,000 NOCs” from
    GSA. 
    Id. ¶ 73
    . At the time of filing the complaint, plaintiff had accumulated 50,593 NOCs
    totaling roughly $37 million “[s]ince 2018.” 
    Id. ¶ 72
    . 3 To avoid having offsets imposed on its
    3
    The figures provided by plaintiff suggest that over 20% of the NOCs received since 2018 arrived in the
    single month of June 2021, which would be a roughly eight-fold increase over the average rate of NOC issuance
    over the past several years. It is unclear, however, whether this proportion indicates a durable increase in the
    volume of NOCs in recent months or whether June 2021 was an extreme outlier month for some reason.
    5
    payments from USTRANSCOM, plaintiff must promptly research and dispute each NOC. 
    Id. ¶¶ 71, 74
    . This volume of NOCs, plaintiff alleges, exceeds plaintiff’s capacity to manually
    process, causing plaintiff to “use software to quickly categorize the basis for each of the NOCs”
    and then submit disputes in aggregate fashion, a process that still entails substantial management
    time. 
    Id.
     ¶¶ 76–79. All told, “[t]he enormous resources required to address the NOCs harm
    Crowley’s ability to adequately perform the contract.” 
    Id. ¶ 87
    .
    B.       Procedural Background
    1.       Plaintiff’s Action Before the Court of Federal Claims
    On May 27, 2021, plaintiff filed suit against USTRANSCOM in the United States Court
    of Federal Claims for failure to pay amounts due under the Contract. Compl. ¶ 1, Crowley Gov’t
    Servs., Inc. v. United States, No. 21-cv-1405 (PEC) (Fed. Cl. May 27, 2021), ECF No. 1 (“CFC
    Compl.”). In one count, plaintiff alleged breach of contract and sought money damages totaling
    $117,633.81 because “[t]he contract does not authorize the GSA to issue NOCs” and
    USTRANSCOM failed to provide payment compensating for the improper offsets despite
    agreeing with plaintiff on the amounts due. 
    Id.
     ¶¶ 49–55. 4 In a second count, citing GSA’s
    ongoing issuance of NOCs despite the Contracting Officer’s findings agreeing with plaintiff,
    plaintiff sought a declaratory judgment confirming, inter alia, “the GSA’s lack of authority to
    issue setoffs.” 
    Id.
     ¶¶ 57–60.
    The United States, on behalf of USTRANSCOM, moved on August 9, 2021 to dismiss
    the complaint in the CFC. Def.’s Mot. Dismiss at 1, Crowley, No. 21-cv-1405 (Fed. Cl. Aug. 9,
    4
    As in the recitation of facts above, this amount is “for services performed in April 2018 and the subject of
    the Contracting Officer’s December 30, 2020 final decision.” CFC Compl. ¶ 12. The reason that this value slightly
    differs from the $119,483.03 amount stated in the referenced Final Decision is not apparent, nor does the allegation
    in the CFC Complaint clearly account for the $43,067.50 that the Final Decision indicated had already been
    refunded to plaintiff.
    6
    2021), ECF No. 7 (“CFC Mot. Dismiss”). USTRANSCOM argued that “[a]s currently
    constructed, Crowley’s complaint must be dismissed pursuant to [CFC Rule] 12(b)(6) for failure
    to state a claim upon which relief can be granted.” 
    Id. at 2
    . USTRANSCOM characterized
    plaintiff’s demand for declaratory relief as a “blanket attack on the Transportation Act,”
    providing in relevant part that “[the GSA] Administrator may conduct pre- or post-payment
    audits of transportation bills of any Federal agency,” 
    id.
     at 4–5 (quoting 
    31 U.S.C. § 3726
    (b)),
    which is precisely what GSA did. Furthermore, in the Contract itself plaintiff “expressly agreed
    to ‘support Government agency reviews and audits of all services.’” 
    Id. at 5
    . With respect to the
    breach of contract claim, USTRANSCOM reiterated that the Contract allowed for GSA audits,
    and in any event USTRANSCOM did deposit the full invoiced amounts to the bank and had no
    statutory authority to issue a duplicate payment in response to GSA’s offsets. 
    Id.
     at 7–8.
    Finally, while concluding that “no contractual cause of action exists here,” USTRANSCOM
    reminded that “Crowley is not without recourse,” referring back to the Contracting Officer’s
    explanation, quoted in the complaint itself, of remedies available through the dispute process for
    GSA audits. 
    Id. at 9
    .
    On August 26, 2021, plaintiff filed an amended complaint in its CFC docket, identifying
    both USTRANSCOM and GSA as defendants. First Am. Compl. ¶¶ 16–17, Crowley, No. 21-cv-
    1405 (Fed. Cl. Aug. 26, 2021), ECF No. 8 (“CFC Am. Compl.”). In its first count, the complaint
    reiterated the breach of contract claim against USTRANSCOM for nonpayment, 
    id.
     ¶¶ 90–97,
    including detailed allegations regarding how any inter-agency disputes or perceived limitations
    on USTRANSCOM’s authority to pay are issues to be worked out by USTRANSCOM, not by
    plaintiff, see 
    id.
     ¶¶ 56–67. Plaintiff no longer sought declaratory relief against USTRANSCOM,
    but added a second count arguing, in the alternative, that even if GSA had statutory authority to
    7
    conduct post-payment audits and offsets, its NOCs were unlawful as they were based on an
    “incorrect interpretation of the contract.” 
    Id.
     ¶¶ 99–102. Plaintiff’s alternative count included a
    demand for an additional $11,880,997.99, reflecting additional NOCs which GSA had issued but
    were pending review by the USTRANSCOM Contracting Officer. 
    Id. ¶ 13, 101
    . 5
    On August 30, 2021, CFC denied the motion to dismiss as moot because the complaint
    had by that point been amended, and directed the government to answer or respond by
    September 20, 2021. Order, Crowley, No. 21-cv-1405 (Fed. Cl. Aug. 30, 2021), ECF No. 10.
    The government filed its answer accordingly and to date has not filed a renewed motion to
    dismiss. See Def.’s Answer, Crowley, No. 21-cv-1405 (Fed. Cl. Sept. 20, 2021), ECF No. 12.
    2.       Plaintiff’s Action in this Court
    On August 30, 2021—four days after filing its amended complaint in the CFC—plaintiff
    filed the instant two-count complaint in this Court seeking “declaratory and injunctive relief
    against GSA” (and not against USTRANSCOM) “to stop it from interfering with” the Contract
    between plaintiff and USTRANSCOM. Compl. ¶ 1. In Count I, plaintiff invokes the judicial
    review provisions of the Administrative Procedure Act (“APA”), 
    5 U.S.C. §§ 701
    –706, alleging
    that GSA exceeded, and continues to exceed, its statutory authority by conducting its improper
    audits and issuing erroneous NOCs. Compl. ¶¶ 114, 116, 117. As a result, plaintiff asserts that
    GSA’s actions should be held unlawful and set aside under the APA. See 
    id. ¶ 109
    . In Count II,
    plaintiff alleges in the alternative that “GSA’s actions are ultra vires” warranting judicial review
    and injunctive relief because “no other remedy is available.” 
    Id.
     ¶¶ 128–29. Plaintiff stresses
    5
    This additional sum alleged only against GSA apparently reflects the view that with respect to these
    additional NOCs, GSA had taken an unlawful action by issuing erroneous offsets, but USTRANSCOM had not yet
    breached the contract as those amounts were still in the process of Contracting Officer review. “If payment is
    denied, as anticipated, Crowley will bring a direct action on those decisions, as well, and incorporate the larger
    amount into this case.” CFC Am. Compl ¶ 13.
    8
    that no contractual remedy or money damages are sought against GSA (or USTRANSCOM). 
    Id.
    ¶¶ 99–102. Instead, plaintiff seeks only equitable relief prospectively precluding the GSA from
    conducting audits and issuing NOCs contrary to the interpretations of the Contracting Officer.
    
    Id. ¶ 107
    ; 
    id. at 18
     (Prayer for Relief).
    Plaintiff moved for a preliminary injunction on September 1, 2021, seeking to enjoin
    GSA from auditing plaintiff’s invoices to USTRANSCOM or, if such audits are authorized,
    issuing decisions and NOCs contrary to the findings of the Contracting Officer’s interpretation of
    the contract. Pl.’s Mot. at 1–2. Following a briefing schedule set by the parties, GSA responded
    on September 15, 2021, with a motion to dismiss combined with an opposition to plaintiff’s
    motion for preliminary injunction. See Defs.’ Mot.; Defs.’ Opp’n. At the Court’s request, see
    Min. Order (Sept. 16, 2021), the parties proposed a revised briefing schedule to complete
    combined briefing on the two pending motions. 6 Briefing completed on October 8, 2021, with
    the filing of plaintiff’s sur-reply. 7
    II.      LEGAL STANDARD
    To survive a motion to dismiss for lack of subject-matter jurisdiction under Federal Rule
    of Civil Procedure 12(b)(1), plaintiffs bear the burden of demonstrating the court’s subject-
    matter jurisdiction over their claims by a preponderance of the evidence. See Lujan v. Defs. of
    Wildlife, 
    504 U.S. 555
    , 561 (1992); Arpaio v. Obama, 
    797 F.3d 11
    , 19 (D.C. Cir. 2015).
    6
    The parties’ original proposed briefing schedule—before GSA filed its motion to dismiss—requested a
    hearing the “[w]eek of September 27,” Joint Proposed Briefing Schedule at 1, ECF No. 11, at least 26 days after
    plaintiff filed its motion for preliminary injunction. Once GSA filed its motion to dismiss, the parties proposed a
    briefing schedule providing for a full month of briefing on the two pending motions, see Joint Proposed Briefing
    Schedule at 1–2, ECF No. 15. Each proposal exhausted the entirety of the 21-day window the Court ordinarily sets
    as an objective for hearings (let alone decisions) on motions for preliminary injunction. See D.D.C. LOCAL CIVIL
    RULE 65.1(d).
    7
    Plaintiff’s sur-reply identified nine topics on which GSA’s reply in support of its motion to dismiss
    allegedly introduced “misrepresentations of fact and law.” Pl.’s Sur-Reply Resp. Defs.’ Reply Supp. Mot. Dismiss
    at 1, ECF No. 21-1. Plaintiff was granted leave to file this sur-reply as it contained information helpful in assessing
    GSA’s reply, but the issues identified in that filing are only addressed as pertinent to the analysis herein.
    9
    “[F]ederal courts are courts of limited subject-matter jurisdiction’ and ‘ha[ve] the power to
    decide only those cases over which Congress grants jurisdiction.’” Bronner ex rel. Am. Stud.
    Ass’n v. Duggan, 
    962 F.3d 596
    , 602 (D.C. Cir. 2020) (second alteration in original) (quoting Al-
    Zahrani v. Rodriguez, 
    669 F.3d 315
    , 317 (D.C. Cir. 2012)); see also Gunn v. Minton, 
    568 U.S. 251
    , 256 (2013) (“‘Federal courts are courts of limited jurisdiction,’ possessing ‘only that power
    authorized by Constitution and statute.’” (quoting Kokkonen v. Guardian Life Ins. Co. of Am.,
    
    511 U.S. 375
    , 377 (1994))). They therefore have a corresponding “independent obligation to
    ensure that they do not exceed the scope of their jurisdiction” and “must raise and decide
    jurisdictional questions that the parties either overlook or elect not to press.” Henderson ex rel.
    Henderson v. Shinseki, 
    562 U.S. 428
    , 434 (2011). Absent subject-matter jurisdiction over a case,
    the court must dismiss it. See Arbaugh v. Y & H Corp., 
    546 U.S. 500
    , 506–07 (2006) (citing
    Kontrick v. Ryan, 
    540 U.S. 443
    , 455 (2004)); FED. R. CIV. P. 12(h)(3).
    When considering a motion to dismiss under Rule 12(b)(1), the court must accept as true
    all uncontroverted material factual allegations in the complaint and “‘construe the complaint
    liberally, granting plaintiff the benefit of all inferences that can be derived from the facts alleged’
    and upon such facts determine jurisdictional questions.” Am. Nat’l Ins. Co. v. FDIC, 
    642 F.3d 1137
    , 1139 (D.C. Cir. 2011) (quoting Thomas v. Principi, 
    394 F.3d 970
    , 972 (D.C. Cir. 2005));
    see also Valambhia v. United Republic of Tanzania, 
    964 F.3d 1135
    , 1139 (D.C. Cir. 2020)
    (“Where . . . the ‘defendant contests only the legal sufficiency of plaintiff’s jurisdictional claims,
    the standard is similar to that of Rule 12(b)(6), under which dismissal is warranted if no plausible
    inferences can be drawn from the facts alleged that, if proven, would provide grounds for
    relief.’” (quoting Schubarth v. Fed. Republic of Germany, 
    891 F.3d 392
    , 398 (D.C. Cir. 2018))).
    The court need not accept inferences drawn by the plaintiff, however, if those inferences are
    10
    unsupported by facts alleged in the complaint or amount merely to legal conclusions. See
    Browning v. Clinton, 
    292 F.3d 235
    , 242 (D.C. Cir. 2002).
    When a jurisdictional challenge “present[s] a dispute over the factual basis of the court’s
    subject matter jurisdiction . . . the court must go beyond the pleadings and resolve” any dispute
    necessary to the disposition of the motion to dismiss. Feldman v. FDIC, 
    879 F.3d 347
    , 351
    (D.C. Cir. 2018) (alterations in original) (quoting Phoenix Consulting v. Republic of Angola, 
    216 F.3d 36
    , 40 (D.C. Cir. 2000)). In such situations, “the . . . court may properly consider
    allegations in the complaint and evidentiary material in the record,” affording the plaintiff “the
    benefit of all reasonable inferences.” Id.; see also Am. Freedom L. Ctr. v. Obama, 
    821 F.3d 44
    ,
    49 (D.C. Cir. 2016) (“In considering a motion to dismiss for lack of subject matter jurisdiction,”
    the court “‘may consider materials outside the pleadings . . . .’” (quoting Jerome Stevens
    Pharms., Inc. v. FDA, 
    402 F.3d 1249
    , 1253 (D.C. Cir. 2005))).
    III.    DISCUSSION
    Plaintiff entered into a contract with USTRANSCOM and performs various services in
    fulfillment of that contract. Plaintiff has not received, and is not receiving, payment from
    USTRANSCOM in the full amount plaintiff—and even USTRANSCOM’s Contracting
    Officer—believes to be due. Plaintiff understandably wishes to be consistently paid in full and
    brings legal actions in multiple courts in pursuit of that result.
    Viewed in that context, the disposition is straightforward: plaintiff has a contract dispute
    with the government exceeding $10,000 in value, and the forum prescribed by statute to hear
    such disputes is the Court of Federal Claims, not this or any other district court. To be sure,
    some details complicate this straightforward analysis, due to the involvement of an agency
    (GSA) not a party to the contract, as well as some questions raised as to precisely which statutes
    11
    govern the auditing of these invoices and the process for challenging the result of such audits. In
    the end, however, none of these issues detract from the essential conclusion that this Court has
    no jurisdiction to hear this dispute and must grant GSA’s motion to dismiss.
    The analysis proceeds in three steps: first, an overview of how sovereign immunity is
    affected by the interaction between the APA and the Tucker Act; second, a discussion of why the
    Tucker Act applies in this case; and finally, a rejection of plaintiff’s alternative argument
    attempting to create jurisdiction by alleging ultra vires conduct.
    A.      Sovereign Immunity
    As an initial matter, the law is well settled that the United States and its agencies are
    immune from suit in federal courts absent a clear, “unequivocally expressed,” waiver of that
    sovereign immunity, such as by an act of Congress. Mowrer v. U.S. Dep’t of Transp., No. 19-
    5321, 
    2021 WL 4343305
    , at *3 (D.C. Cir. Sept. 24, 2021); see also United States v. White
    Mountain Apache Tribe, 
    537 U.S. 465
    , 472 (2003). As relevant here, the APA provides a limited
    waiver of sovereign immunity for claims challenging final agency action and seeking non-
    monetary relief for persons “adversely affected or aggrieved by agency action.” 
    5 U.S.C. § 702
    (“An action . . . seeking relief other than money damages and stating a claim that an agency . . .
    acted or failed to act . . . shall not be dismissed nor relief therein be denied on the ground that it
    is against the United States . . . .”); 
    id.
     § 704. In this case, the question of subject matter
    jurisdiction turns entirely on whether GSA and its Administrator are immune from suit on the
    claims in this Court.
    Meanwhile, the Tucker Act, 
    28 U.S.C. § 1491
    , separately offers another limited waiver of
    sovereign immunity, providing in relevant part that “[t]he United States Court of Federal Claims
    shall have jurisdiction to render judgment upon any claim against the United States founded . . .
    upon any express or implied contract with the United States.” 
    Id.
     § 1491(a)(1). The D.C. Circuit
    12
    has consistently interpreted the Tucker Act as “confer[ring] exclusive jurisdiction over breach of
    contract claims against the United States seeking more than $10,000 in damages on the Court of
    Federal Claims.” Hammer v. United States, 
    989 F.3d 1
    , 2 (D.C. Cir. 2021) (emphasis added)
    (citing 
    28 U.S.C. §§ 1346
    (a), 1491(a)). 8 Where the CFC has jurisdiction over a case, “the court
    shall have the power to remand appropriate matters to any administrative or executive body or
    official with such direction as it may deem proper and just.” 
    Id.
     § 1491(a)(2).
    Although the Tucker Act, by its own terms, never furnishes a waiver of sovereign
    immunity in a district court—and plaintiff does not attempt to invoke this Act here to that end—
    it is relevant to the jurisdictional analysis because of its effect on the APA’s waiver provision.
    The APA’s sovereign immunity waiver does not apply if either: (a) “any other statute that grants
    consent to suit expressly or impliedly forbids the relief which is sought,” 
    5 U.S.C. § 702
    ; or
    (b) some “other adequate remedy in a court” is available, 
    id.
     § 704. The Tucker Act is such a
    statute that allows for suit and “impliedly forbids” the use of the APA immunity waiver to
    litigate a contract claim. See Perry Capital LLC v. Mnuchin, 
    864 F.3d 591
    , 618–19 (D.C. Cir.
    2017).
    In short, plaintiff’s APA claim against defendants cannot go forward if the claim is
    deemed to be covered by the Tucker Act.
    B.       The Tucker Act Covers Plaintiff’s APA Claim
    Neither party disputes the basic contention that the Tucker Act excises a particular type
    of claim from district courts’ jurisdiction and situates it solely in the CFC. See Defs.’ Opp’n at 9
    (“contract-based claims in excess of $10,000 against the federal government”); Pl.’s Opp’n
    8
    In contrast, “[t]he district courts and the Court of Federal Claims generally share jurisdiction over Little
    Tucker Act claims, i.e., those not exceeding $10,000.” Palacios v. Spencer, 
    906 F.3d 124
    , 127 n.2 (D.C. Cir. 2018)
    (citing 
    28 U.S.C. § 1346
    (a)(2)).
    13
    Defs.’ Mot. Dismiss and Reply Supp. Mot. Prelim. Inj. (“Pl.’s Opp’n”) at 3–4, ECF No. 17
    (similar). Furthermore, the parties agree that at least one specific type of claim falls under the
    aegis of the Tucker Act and therefore into CFC jurisdiction: namely, a breach of contract claim
    by plaintiff against USTRANSCOM seeking money damages for past underpayments. Indeed,
    plaintiff brought this very claim in its original and amended complaints at the CFC. See CFC
    Compl. ¶¶ 53–55; CFC Am. Compl. ¶¶ 90–97. For its part, while the government, in its motion
    to dismiss plaintiff’s original complaint at the CFC, argued on the merits that as a matter of law,
    USTRANSCOM was not in breach, see CFC Mot. Dismiss 7–9, it notably did not raise a
    jurisdictional objection, nor did it challenge the premise that the Tucker Act conferred
    jurisdiction over that claim on the CFC.
    Where the parties diverge is with respect to the extent to which “the source of the rights”
    on which the claims are founded, and “the type of relief sought (or appropriate),” A & S Council
    Oil Co. v. Lader, 
    56 F.3d 234
    , 240 (D.C. Cir. 1995) (citation omitted), should be examined to
    determine if the Tucker Act applies to a claim that is not, on its face, expressed as a breach of
    contract claim seeking money damages. In plaintiff’s view, for the Tucker Act to preclude
    jurisdiction in this Court, GSA must “show that the Court of Federal Claims would have
    jurisdiction over the complaint.” Pl.’s Opp’n at 4 (emphasis added). Plaintiff then explains why
    its complaint, as pleaded, could not be brought at the CFC. Count I alleges, against GSA, that
    GSA lacks authority under the statute and by the terms of the Contract to perform audits and
    issue NOCs at all, or at least that GSA lacks authority to issue NOCs that contravene the
    interpretations and decisions of the Contracting Officer at USTRANSCOM. See Compl. ¶¶ 109–
    26. Instead of seeking damages, plaintiff seeks equitable relief to stop GSA from proceeding
    similarly in the future. Compl. at 18 (Prayer for Relief). Plaintiff cannot “seek a contractual
    14
    remedy against GSA in the Court of Federal Claims under the Tucker Act because GSA is not a
    party to the contract.” Pl.’s Opp’n at 6. As a result, in plaintiff’s view, the Tucker Act does not
    deprive this Court of jurisdiction. Id. at 5.
    Plaintiff reasons that the Court should “generally limit [its inquiry] to the four corners of
    the complaint” when assessing whether the Tucker Act precludes the exercise of jurisdiction.
    Pl.’s Opp’n at 10 (alteration in original) (quoting Smalls v. United States, 
    471 F.3d 186
    , 190
    (D.C. Cir. 2006)). Describing the complaint as not “explicitly or ‘in essence’ seek[ing] more
    than $10,000 in monetary relief,” plaintiff maintains that this Circuit’s “bright line approach” to
    defining the scope of the Tucker Act should cause the instant complaint to escape the Act’s
    reach. 
    Id.
     (quoting Smalls, 
    471 F.3d at
    189–90). As to what it means for a complaint to “in
    essence” seek monetary relief, plaintiff recites a standard invoked in several binding Circuit
    cases: “[a] complaint is not in essence one for monetary damages if the only remedy requested is
    non-monetary relief that has considerable value independent of any future potential for monetary
    relief.” 
    Id.
     (internal quotation marks omitted) (quoting Smalls, 
    471 F.3d at 190
    ); see also Tootle
    v. Sec’y of Navy, 
    446 F.3d 167
    , 176 (D.C. Cir. 2006); Kidwell v. Dep’t of Army, Bd. for Corr. of
    Mil. Recs., 
    56 F.3d 279
    , 284 (D.C. Cir. 1995).
    Plaintiff may be correct that this claim, as framed and pleaded in this complaint, against
    this defendant, seeking this remedy, does not fit nicely into the criteria for CFC jurisdiction
    under the Tucker Act. There is no contract between plaintiff and GSA, and thus there is nothing
    for GSA to “breach.” Furthermore, plaintiff seeks no money damages at all (let alone a sum
    above $10,000). 9 Plaintiff asserts that even if, for the sake of argument, compensation were its
    9
    Plaintiff entertains, at least in the hypothetical, the possibility that the claim against GSA as written could
    be cognizable in the CFC if its requests for equitable relief were characterized as seeking money damages. See Pl.’s
    Opp’n at 15–21. Even in that scenario where CFC has jurisdiction, plaintiff insists, the CFC’s jurisdiction would
    not be exclusive because “[the claim against GSA] is not founded upon a contract.” Id. at 15.
    15
    “ultimate goal,” and even if success in its quest for equitable relief at this Court “would
    ultimately result in the transfer of funds from the government to the plaintiff,” that result is still
    not dispositive of the jurisdictional question. Pl.’s Opp’n at 10–11. In support, plaintiff argues
    that the requested equitable relief aims to arrest harms going beyond merely the partial
    nonpayment of its invoices, such as “time and resources spent investigating and challenging
    invalid audit conclusions,” “degrading [its] performance” on the Contract by “[k]eeping
    personnel from normal contract performance,” and exposure to “two dispute resolution
    processes.” Id. at 12–13.
    GSA, on the other hand, argues that the Tucker Act does apply by viewing the situation
    more holistically: “the claims in Plaintiff’s complaint derive from or arise from the contract
    between Crowley and USTRANSCOM or, otherwise stated, Plaintiff’s claim is contractual in
    origin.” Defs.’ Reply at 3 (emphasis added). GSA also views the requested relief in
    consequentialist terms: “the underlying implication of the relief in the complaint seeks the
    protection of a right to money that is secured by contract.” Id. Emphasizing that the genesis of
    any right plaintiff may have to payment is the Contract, GSA suggests that any detriment to
    plaintiff from GSA’s actions is, if actionable at all, only meaningful in the context of those
    payment rights derived from contract. See Defs.’ Opp’n at 11–12. Even though in this
    complaint plaintiff nominally seeks only declaratory and injunctive relief, GSA argues that such
    claims, too, “originate under and are governed by the [Contract], in which NOCs were issued and
    offsets are applied because that contract is the source of plaintiff’s alleged right to payment and
    any other relief.” Id. at 14. Thus, GSA urges the Court to reject plaintiff’s “attempt to plead
    around” the Tucker Act “jurisdictional problem,” id. at 12, invoking the rule against plaintiffs
    “bypass[ing] Tucker Act jurisdiction by converting complaints which ‘at their essence’ seek
    16
    money damages from the government into complaints requesting injunctive relief or declaratory
    actions,” id. at 12–13 (quoting Kidwell, 
    56 F.3d at 284
    ).
    1.      The Kidwell Test Is Controlling
    The D.C. Circuit’s opinion in Kidwell v. Department of Army, Board for Correction of
    Military Records, 
    56 F.3d 279
    , is instructive—and cited by both parties. In Kidwell, a veteran
    filed an APA claim in the district court seeking a change in his military files to indicate that his
    discharge was “medical” in nature. 
    Id. at 281
    . “Although Kidwell did not explicitly request
    monetary relief in his complaint, the government claimed that a district court order” requiring
    recharacterization of his discharge “would entitle Kidwell to retroactive disability benefits that
    could exceed $50,000.” 
    Id. at 283
    . In the government’s view, this gave exclusive jurisdiction
    over the suit to the CFC under the Tucker Act. 
    Id.
     On appeal from the district court’s grant of
    dismissal for lack of jurisdiction, the Circuit recognized that although the complaint did not
    expressly seek monetary relief, “[t]he plain language of a complaint . . . does not necessarily
    settle the question of Tucker Act jurisdiction.” 
    Id.
     at 283–84. The court observed that when a
    plaintiff seeks to evade the Tucker Act by creatively avoiding pleading a request for money
    damages, “this forum shopping circumvents a primary purpose of the Act—to ensure that a
    central judicial body adjudicates most claims against the United States Treasury.” 
    Id. at 284
    .
    The court confirmed that a claim falls under the Tucker Act if it “explicitly or ‘in
    essence’ seeks more than $10,000 in monetary relief.” 
    Id.
     It cautioned, however, that merely
    “hint[ing] at some interest in a monetary reward” or the fact that “success on the merits may
    obligate the United States to pay” does not, alone, mean a plaintiff “in essence” seeks monetary
    relief. 
    Id.
     The critical test, according to the Circuit, is whether the “complaint only requests
    non-monetary relief that has ‘considerable value’ independent of any future potential for
    17
    monetary relief—that is, as long as the sole remedy requested is declaratory or injunctive relief
    that is not ‘negligible in comparison’ with the potential monetary recovery.” 
    Id.
     (citations
    omitted). If so, the complaint may proceed in district court. 
    Id.
     As to the Kidwell case itself, the
    Circuit recognized that while “monetary benefits . . . may flow from Kidwell’s victory,” the
    relief would also confer non-monetary benefits by “lift[ing] some of the shame associated with
    failing to receive an honorable discharge.” 
    Id. at 285
    . The court viewed the equitable relief as
    “not ‘negligible in comparison’” to eventual monetary benefits and held that the district court did
    have jurisdiction to hear the complaint. 
    Id. at 286
    . 10
    The Kidwell test favors GSA here. Although the parties differ on the precise effects of an
    order granting plaintiff’s requested equitable relief against GSA, it is difficult to see how the
    requested “[j]udgment declaring that GSA is not authorized to audit the contract” and “that
    GSA’s NOCs violate the finality of the Contracting Officer’s final decisions,” Compl. at 18
    (Prayer for Relief), would not effect the release of the offsets assessed by GSA to date and
    prevent more such offsets from issuing. Indeed, GSA posits that such an order would have that
    result. See Defs.’ Opp’n at 14 (“Plaintiff wants to . . . seek reimbursement of the monies already
    offset.”). Ironically, plaintiff strenuously argues that this is not the result sought in this action
    and that “[e]ven if granting Crowley’s requested relief would prevent GSA from offsetting
    further funds, this would not demonstrate that Count I is contractual.” Pl.’s Opp’n at 20–21.
    Instead, plaintiff insists that it “seeks to enjoin GSA’s statutory violations that subject it to
    irreparable harm—including the resources necessary to address GSA’s myriad unlawful audits.”
    Id. at 21.
    10
    Although Kidwell reversed the decision below dismissing for lack of jurisdiction, the district court had also
    made an alternative grant of summary judgment for the government, which the Circuit affirmed. 56 F.3d at 287.
    18
    Plaintiff faults GSA for not reciting and faithfully applying Kidwell’s “considerable
    value” test. Pl.’s Opp’n at 13. Applying that test, however, does not help plaintiff’s cause. In
    plaintiff’s framing, the primary harm that would be addressed by the relief requested in this
    Court is the accrual of expense associated with “investigating and challenging” the audits, “an
    expense which [as of September 24, 2021] exceeds $187,000 and cannot be recovered.” Pl.’s
    Opp’n at 12–13. While that expense is not insignificant and indeed would not be compensated
    by any money damage award either here or at the CFC, these “investigat[ions] and challeng[es]”
    concern “more than fifty thousand individual Notices of Overcharges . . . totaling approximately
    $37 million and counting.” Pl.’s Mem. Supp. Mot. Prelim. Inj. (“Pl.’s Mem.”) at 1, ECF
    No. 9-1. That is the real amount at stake here, and plaintiff’s own figures show that it dwarfs the
    harm ostensibly motivating this complaint by a factor of roughly 200-to-1. 11 Under these facts,
    the relief sought here is indeed “negligible in comparison” to the uncollected contractual
    proceeds at issue.
    2.       Other Case Law
    Aside from Kidwell, the parties invoke dueling suites of Circuit precedent in their
    attempts to divine the dividing line between permissible and impermissible district court
    equitable claims in light of the Tucker Act’s jurisdictional restrictions. 12 None changes the
    conclusions reached above.
    Plaintiff cites Megapulse, Inc. v. Lewis, 
    672 F.2d 959
     (D.C. Cir. 1982), in which the
    Circuit held that district court jurisdiction could lie for a claim against the government for
    11
    These two figures appear in papers filed 23 days apart and as such may not perfectly correspond to each
    other. That said, the magnitude of the difference between the value of the equitable relief and the potential contract
    relief is sufficiently great that any minor temporal misalignment is of minimal, if any, significance.
    12
    The briefs are replete with citations to decisions from other Judges on this Court, but since binding Circuit
    authorities provide sufficient guidance, those district court cases will not be discussed here.
    19
    “alleged governmental infringement of property rights and violation of the Trade Secrets Act,”
    
    id. at 969
    , where the intellectual property at issue was disclosed to the government during
    performance of various contracts, 
    id. at 964
    . See Pl.’s Mem. at 13–14. The Circuit rejected the
    idea that “any case requiring some reference to or incorporation of a contract is necessarily on
    the contract and therefore directly within the Tucker Act.” Megapulse, 672 F.2d at 967–68. The
    court particularly noted that the infringement claims were not an attempt to enforce a contract
    and, to the extent the case was contract related at all, it was only because the government
    attempted to use the contract as a defense by showing it provided for lawful possession of the
    property. Id. at 969. While articulating some limits on the Tucker Act, Megapulse does not help
    plaintiff. Here, even though plaintiff tries to frame GSA’s audits as an independent wrong and
    violation of statute, the audits have no significance outside the context of collection on the
    contract and no other exogenous harm (such as improper disclosures of trade secrets) is alleged.
    Plaintiff’s other D.C. Circuit cases are similarly unhelpful. See Pl.’s Opp’n at 10–14;
    Pl.’s Mem. at 12–16. In Tootle v. Secretary of the Navy, 
    446 F.3d 167
    , the Circuit held that the
    district court had jurisdiction to hear a claim “materially indistinguishable from” that in Kidwell,
    
    id. at 174
    , observing that a medical determination finding making a servicemember eligible for
    retirement (even if possibly eventually accompanied by some retroactive monetary benefit)
    “itself has non-negligible value, especially for an ill serviceman,” 
    id. at 175
    . See also Smalls,
    
    471 F.3d 186
     (similar). In Vietnam Veterans of America v. Secretary of the Navy, 
    843 F.2d 528
    (D.C. Cir. 1988), the court expressly noted that at that time the Circuit had not “settle[d] the
    issue of splitting equitable and monetary claims, in either Tucker Act context”—precisely what
    plaintiff is now doing—and did not need to address it then either. 
    Id. at 535
    . Esch v. Yeutter,
    
    876 F.2d 976
     (D.C. Cir. 1989) involved rights arising from participation in a grant program and
    20
    not on “an agreement negotiated by the parties,” 
    id.
     at 978 n.13 (citation omitted). In Alaska
    Airlines, Inc. v. Johnson, 
    8 F.3d 791
     (Fed. Cir. 1993), the monetary claim did not exceed
    $10,000, so there was no question of district court jurisdiction under the Little Tucker Act, see
    
    id. at 794, 797
    . These cases are only useful to plaintiff to support the proposition that the
    possibility (or even certainty) of monetary relief arising as a result of a successful claim does not
    per se preclude the district court from hearing a related equitable claim. Yet, that is a different
    question from the key question here: whether the specific dispute here is “in essence” a contract
    claim.
    GSA’s appeals to authority are more apposite. See Defs.’ Opp’n at 12–15. Most notably,
    in Spectrum Leasing Corp. v. United States, 
    764 F.2d 891
     (D.C. Cir 1985), a contractor
    providing software and hardware services to GSA (who, unlike here, was a party to the contract)
    challenged GSA’s withholding of payments on certain hardware invoices on account of
    liquidated damages assessed against the plaintiff due to failures to fulfill software-related
    obligations, 
    id. at 892
    . The contractor sued in district court not for money damages per se, but
    for violations of the Debt Collection Act of 1982, a statute that “provides a set of procedures and
    safeguards designed to assure due process protections to delinquent government debtors.” 
    Id.
     at
    892 n.1. The Circuit held that “the contract provides the ultimate source of [plaintiff’s] rights”
    and as such the claim was subject to the jurisdictional provisions of the Tucker Act. 
    Id. at 895
    . 13
    As GSA explains, this case is analogous. See Defs.’ Opp’n at 14. Plaintiff’s alleged rights to
    certain monies “originate under and are governed by the [C]ontract.” 
    Id.
     As in Spectrum
    Leasing, plaintiffs allege government noncompliance with other statutory strictures relevant to
    13
    At the time, the Court of Federal Claims was named the “United States Claims Court.” See Federal Courts
    Administration Act of 1992, Pub. L. No. 102-572, § 902(a), 
    106 Stat. 4506
    , 4516 (changing name to Court of
    Federal Claims).
    21
    contract and payment administration. The result is a claim that “at [its] essence seek[s] to
    recover money from the government”—one that can be brought only under the Tucker Act and
    not under the APA. 
    Id.
    *    *    *
    All told, plaintiff’s situation is understandably difficult and frustrating, but the
    fundamental grievance underlying plaintiff’s cases before both the CFC and this Court is that it
    furnishes transportation-related services to the government pursuant to the Contract and does not
    get paid the full amount it believes it is due. But for that issue, neither complaint would exist,
    and leads inexorably to the conclusion that the dispute “arises from” a contract—the Contract—
    with the government. In these two companion cases, plaintiff articulately deconstructs its
    grievance into two constituent parts: (1) funds reflecting the full invoice totals are not delivered
    to plaintiff, a matter plaintiff pursues as a breach of contract action at the CFC; and (2) GSA’s
    allegedly erroneous and unlawful invoice audits cause not only the diversion of funds properly
    destined for plaintiff but also undue administrative hassle and expense incurred in disputing the
    results of those audits. In one sense, plaintiff is correct that two potentially problematic actions
    (or inactions) are occurring here, and distinct actors take those two actions: aberrant auditing on
    the one hand, and nonpayment on the other. As a practical matter, however, GSA’s audits are
    merely part of the mechanism (albeit a very important part) by which the nonpayments arise, and
    neither issue would exist were it not for certain rights to payment promised in the Contract.
    Simply put, it strains credulity to insist that “[t]he actual terms of the contract and
    Crowley’s right to payment are irrelevant” to “the narrow issue of GSA’s auditing of Crowley’s
    invoices beyond GSA’s authority . . . in a manner that directly contradicts the final decisions of
    the Contracting Officer.” Pl.’s Mem. at 12–13. The Court declines plaintiff’s invitation to
    22
    compartmentalize these matters in such an unintuitive fashion. Under controlling Circuit
    precedent, the declaratory and injunctive relief claims advanced by plaintiff here fall under the
    umbrella of the Tucker Act. As such, the APA’s sovereign immunity waiver does not apply, and
    the Court lacks jurisdiction to entertain this claim.
    C.       Plaintiff’s Ultra Vires Claim Fails
    Plaintiff argues that even if, as the Court has found, the APA’s sovereign immunity
    waiver is inapplicable due to the claim falling within the Tucker Act, “this Court may also
    provide relief due to GSA’s ultra vires actions.” Pl.’s Mem. at 23; Pl.’s Opp’n at 23. This side-
    door attempt to invoke the district court’s jurisdiction can be easily dispatched.
    To be sure, under the “so-called Larson–Dugan exception to the general rule” of
    sovereign immunity absent a waiver, “‘suits for specific relief against officers of the sovereign’
    allegedly acting ‘beyond statutory authority or unconstitutionally’ are not barred.” Pollack v.
    Hogan, 
    703 F.3d 117
    , 119–20 (D.C. Cir. 2012) (per curiam) (quoting Larson v. Domestic &
    Foreign Com. Corp., 
    337 U.S. 682
    , 689, 693 (1949); and citing Dugan v. Rank, 
    372 U.S. 609
    ,
    621–22 (1963)). 14 “The exception is based on the principle that such ultra vires action by a
    federal officer ‘is beyond the officer’s powers and is, therefore, not the conduct of the
    sovereign.’” Id. at 120 (quoting Larson, 
    337 U.S. at 690
    ). Put another way, “courts will
    ‘ordinarily presume that Congress intends the executive to obey its statutory commands and,
    accordingly, that it expects the courts to grant relief when an executive agency violates such a
    command.’” Chamber of Com. of U.S. v. Reich, 
    74 F.3d 1322
    , 1328 (D.C. Cir. 1996) (quoting
    Bowen v. Mich. Acad. of Fam. Physicians, 
    476 U.S. 667
    , 681 (1986)).
    14
    The Larson–Dugan exception only holds for named officers and thus plaintiff’s ultra vires theory could at
    most sustain jurisdiction against the GSA Administrator, not GSA itself.
    23
    This type of exception, like plaintiff’s argument, carries significant normative appeal, as
    seemingly an important source of assurance that executive agencies and officers are not “above
    the law.” That said, plaintiff provides no case law examples of courts allowing, or even
    considering, ultra vires theories of statutory violations as a way to escape the jurisdictional
    strictures imposed by the Tucker Act—and the Court has found none. 15 As such, allowing
    jurisdiction on this theory appears to be unprecedented, and this case will not open this door.
    Perhaps not surprisingly, this theory does not tend to arise in this context. For one thing,
    the Tucker Act is not fundamentally a limitation on reviewability of government actions; rather,
    it is a jurisdiction-steering provision. Requiring review to be sought first at the CFC (with
    appeal to an Article III court available) is quite different in character from precluding judicial
    review altogether. Furthermore, this theory admits of no limiting principle and likely would
    create a gaping exception that would risk swallowing the Tucker Act jurisdictional rule. Given
    the number and complexity of statutes governing interactions between agencies and contractors,
    nearly any government contract dispute might also incidentally implicate some statutory
    provision and create a basis for jurisdiction at a district court alongside the CFC. Such a result
    would plainly frustrate the Tucker Act’s objective of “ensur[ing] that a central judicial body
    adjudicates most claims against the United States Treasury.” Kidwell, 56 F.3d at 284.
    15
    The CFC and the Federal Circuit have occasionally confronted a related issue: whether ultra vires actions
    by a federal official can be the basis for a Tucker Act takings claim brought in the CFC. See, e.g., Del-Rio Drilling
    Programs, Inc. v. United States, 
    146 F.3d 1358
    , 1362–63 (Fed. Cir. 1998). The general rule appears to be that
    where the official is definitively acting outside the scope of his or her duties, a Tucker Act claim will not lie. See 
    id.
    This does not mean, however, that an unlawful act is necessarily an “ultra vires” act outside the reach of the Tucker
    Act. “In holding that ultra vires conduct cannot give rise to a Fifth Amendment taking, the courts have drawn an
    important distinction between conduct that is ‘unauthorized’ and conduct that is authorized but nonetheless
    unlawful. Merely because a government agent’s conduct is unlawful does not mean that it is unauthorized; a
    government official may act within his authority even if his conduct is later determined to have been contrary to
    law.” 
    Id. at 1362
    . Analogizing to plaintiff’s ultra vires argument, the type of GSA audit conduct alleged in the
    complaint seems to be in the category of potentially erroneous conduct that is nevertheless within the general scope
    of authority of GSA officials.
    24
    *   *    *
    Plaintiff’s allegations, taken as true, weave a rather Kafkaesque tale. Regardless of the
    correct substantive answer about the meaning of the Contract and how the ensuing invoices
    should be calculated—matters on which this Court cannot and does not opine due to its
    jurisdictional ruling today—the apparent inability of the government to agree with itself and to
    implement a consistent decision on interpretation of the Contract is hardly a model of efficiency.
    The government has expressly represented here that “Plaintiff does indeed not lack an adequate
    remedy in another Court”—the Court of Federal Claims—and has in essence laid out a blueprint
    for how this matter can receive a fulsome hearing there. See Defs.’ Opp’n at 15–18. Plaintiff’s
    case before that tribunal appears poised to continue even as this case here ends today. Hopefully,
    the government will maintain a litigation position there consistent with its representations here,
    allowing the parties to this Contract to achieve a common understanding of their commercial
    terms rather than remaining stuck in an infinite loop of audits, disputes, and payments held in
    limbo.
    IV.      CONCLUSION
    For the foregoing reasons, this Court lacks jurisdiction to hear plaintiff’s action,
    jurisdiction for which is conferred exclusively by statute to the Court of Federal Claims.
    Accordingly, defendants’ motion to dismiss for lack of jurisdiction is GRANTED and plaintiff’s
    motion for preliminary injunction must be DENIED AS MOOT.
    An order consistent with this Memorandum Opinion will be entered contemporaneously.
    Date: October 22, 2021
    __________________________
    BERYL A. HOWELL
    Chief Judge
    25
    

Document Info

Docket Number: Civil Action No. 2021-2298

Judges: Chief Judge Beryl A. Howell

Filed Date: 10/22/2021

Precedential Status: Precedential

Modified Date: 10/23/2021

Authorities (25)

alaska-airlines-inc-american-airlines-inc-continental-airlines , 8 F.3d 791 ( 1993 )

Bowen v. Michigan Academy of Family Physicians , 106 S. Ct. 2133 ( 1986 )

Gunn v. Minton , 133 S. Ct. 1059 ( 2013 )

No. 97-5055 , 146 F.3d 1358 ( 1998 )

Kokkonen v. Guardian Life Insurance Co. of America , 114 S. Ct. 1673 ( 1994 )

Phoenix Consulting, Inc. v. Republic of Angola , 216 F.3d 36 ( 2000 )

Larson v. Domestic and Foreign Commerce Corp. , 69 S. Ct. 1457 ( 1949 )

Tootle v. Secretary of the Navy , 446 F.3d 167 ( 2006 )

Dugan v. Rank , 83 S. Ct. 999 ( 1963 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Smalls, Eugene C. v. United States , 471 F.3d 186 ( 2006 )

Henderson v. Shinseki , 131 S. Ct. 1197 ( 2011 )

Patrick Esch v. Clayton K. Yeutter, Secretary, U.S. ... , 876 F.2d 976 ( 1989 )

Kontrick v. Ryan , 124 S. Ct. 906 ( 2004 )

Jerome Stevens Pharmaceuticals, Inc. v. Food & Drug ... , 402 F.3d 1249 ( 2005 )

Thomas, Oscar v. Principi, Anthony , 394 F.3d 970 ( 2005 )

American Nat. Ins. Co. v. FDIC , 642 F.3d 1137 ( 2011 )

Vietnam Veterans of America v. Secretary of the Navy, (Two ... , 843 F.2d 528 ( 1988 )

Dolly Kyle Browning and Direct Outstanding Creations ... , 292 F.3d 235 ( 2002 )

Spectrum Leasing Corporation v. United States of America , 764 F.2d 891 ( 1985 )

View All Authorities »