Verizon Washington, D.C., Inc. v. United States of America , 254 F. Supp. 3d 208 ( 2017 )


Menu:
  •                            UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    VERIZON WASHINGTON, D.C., INC.,                  :
    :
    Plaintiff,                                :       Civil Action No.:     16-1925 (RC)
    :
    v.                                        :       Re Document No.:      12
    :
    UNITED STATES OF AMERICA, et al.,                :
    :
    Defendants.                               :
    MEMORANDUM OPINION
    GRANTING IN PART AND DENYING IN PART FEDERAL DEFENDANTS’ MOTION TO DISMISS
    I. INTRODUCTION
    Plaintiff Verizon Washington, D.C., Inc. (“Verizon”) brings this action against the United
    States, the General Services Administration (“GSA”), and M & M Contractors, Inc. (“M & M”),
    a federal contractor. Verizon alleges it was injured when steam from underground facilities
    owned, maintained, controlled, or repaired by Defendants damaged Verizon’s
    telecommunications equipment. Relying in part on the Federal Tort Claims Act (“FTCA”), 28
    U.S.C. §§ 2671–80, Verizon brings negligence, nuisance, and trespass/interference with
    easement claims against each of the three Defendants.
    The United States and GSA (collectively, “Federal Defendants”) move to dismiss.
    Federal Defendants argue that Verizon’s claims are barred by sovereign immunity and that
    Verizon fails to state a claim upon which relief can be granted. For the reasons set forth below,
    the Court finds that GSA is not a proper defendant under the FTCA and therefore dismisses the
    three counts brought directly against the federal agency. The Court also finds that the
    independent contractor exception to the FTCA bars claims against the United States to the extent
    that the government delegated the relevant duties to M & M. But the Court also concludes that
    the vague allegations in Verizon’s Amended Complaint prevent the Court from determining
    whether Verizon has alleged any claims that fall outside the scope of the contract between the
    government and M & M. Thus, the Court orders Verizon to provide a more definite statement of
    its claims. Finally, the Court rejects Verizon’s argument that the inherently dangerous nature of
    the work at issue means that any duty is nondelegable under District of Columbia law. Federal
    Defendants’ motion to dismiss is thus granted in part and denied in part.
    II. BACKGROUND
    The Court begins with a description of the facts giving rise to Verizon’s claims and then
    turns to the procedural history of this case.
    A. Factual Allegations1
    Verizon alleges that, at all times relevant to this action, the company maintained
    telecommunication equipment near the intersection of 17th Street and F Street in Washington,
    D.C.2 Am. Compl. ¶ 7. The equipment constitutes a part of the company’s telephone service
    distribution system and was lawfully maintained in underground facilities at that location.
    Am. Compl. ¶¶ 7–8. On or about November 6, 2014, steam from steam pipes owned,
    maintained, and controlled by the United States and/or GSA caused damage to Verizon’s facilities.
    Am. Compl. ¶ 8.
    1
    When considering a motion to dismiss for failure to state a claim or for lack of subject
    matter jurisdiction, a court “accepts the allegations of the complaint as true.” Banneker
    Ventures, LLC v. Graham, 
    798 F.3d 1119
    , 1129 (D.C. Cir. 2015).
    2
    The Amended Complaint does not specify the quadrant of the District where the alleged
    damage occurred. See e.g., Am. Compl. ¶ 7–9, 15. This omission is irrelevant to the Court’s
    analysis.
    2
    According to the Amended Complaint, M & M3 is a corporation that conducts business in
    Washington, D.C. Am. Compl. ¶ 6. On or about November 6, 2014, “agents, servants, and/or
    employees of M & M Contractors, Inc. were repairing steam pipes owned, maintained[,] and
    controlled” by the Federal Defendants when they caused damage to Verizon’s underground
    facilities. Am. Compl. ¶ 9. Plaintiff notified GSA of a claim for property damage on or about
    February 17, 2015. Am. Compl. ¶ 10.
    B. The Agreement Between GSA and M & M4
    In support of the motion to dismiss, Federal Defendants present the declarations of Kathy
    White and Greg Westphal. See Decl. of Kathy White (“White Decl.”); ECF No. 12-1, Decl. of
    Greg Westphal (“Westphal Decl.”), ECF No. 12-3. Ms. White is employed by GSA as a
    Contract Specialist assigned to the region covering Washington, D.C. White Decl. ¶ 1.
    In her role as Contract Specialist, Ms. White states that she was responsible for the
    “implementation of the operations and maintenance services contract that was in effect at the
    GSA Steam Distribution System located at Heating, Operation and Transmission District, 13th
    3
    Federal Defendants note that the contracting documents refer to “M&M Welding &
    Fabricators, Inc.,” not “M & M Contractors, Inc.” See Mem. P. & A. Supp. Fed. Defs.’ Mot.
    Dismiss (“Defs.’ Mem.”) at 7 n.1. Verizon acknowledges this discrepancy. See Pl.’s Mem. P. &
    A. Supp. Pl.’s Opp’n Fed. Defs.’ Mot. Dismiss (“Pl.’s Opp’n”) at 1 n.1, ECF No. 13-1
    (“Defendants have disclosed the proper name of the subcontractor to be M & M Welding &
    Fabricators, Inc.”). For consistency with the Amended Complaint, the parties continue to refer to
    M & M Contractors, Inc. See Defs.’ Mem. at 7 n.1; Pl.’s Opp’n at 1 n.1. To avoid confusion,
    the Court will simply refer to “M & M.”
    4
    If necessary to resolve a challenge to subject matter jurisdiction under Rule 12(b)(1), a
    court may “consider the complaint supplemented by undisputed facts evidenced in the record, or
    the complaint supplemented by undisputed facts plus the court’s resolution of disputed facts.”
    Banneker 
    Ventures, 798 F.3d at 1129
    (quoting Herbert v. Nat’l Acad. of Sciences, 
    974 F.2d 192
    ,
    197 (D.C. Cir. 1992)). Here, Verizon does not object to the authenticity or veracity of the
    contract documents. See generally Pl.’s Opp’n. In fact, Verizon relies on facts found in these
    documents in its opposition to the motion to dismiss. See Pl.’s Opp’n at 4–7. Thus, for the
    purpose of resolving the jurisdictional challenge, the Court will rely on facts evidenced by these
    contract documents.
    3
    and C Street SW, Washington, DC, (‘SDS’) on November 6, 2014.” White Decl. ¶ 3. Ms.
    White states that she has provided “the full set of contract documents” governing the relationship
    between GSA and M & M with regard to operations and maintenance services at the SDS.5
    White Decl. ¶ 4; see also White Decl., Ex. A, ECF No. 12-2.6 The relevant contracting
    documents include a series of communications and agreements between GSA and M & M. See,
    e.g., White Decl., Ex. A at 32–186 (“Price Proposal Offer” submitted by M & M to GSA on
    January 10, 2014); White Decl., Ex. A at 1–3 (letter from GSA to M & M dated June 17, 2014,
    accepting M & M’s offer submitted in response to a GSA solicitation for a contract); White
    Decl., Ex. A at 4–8 (“Solicitation, Offer, and Award” issued by GSA on June 25, 2014, awarding
    M & M the relevant contract).
    GSA formally awarded the contract to M & M for a period beginning on July 1, 2014.
    See White Decl. ¶ 5; White Decl., Ex. A at 5. For the purposes of this matter, a particularly
    relevant document is the Price Proposal Offer, especially Section C, which sets forth a detailed
    description of the agreement between GSA and M & M, including numerous specifications. See
    White Decl., Ex. A at 51–64. Section C states that the contractor “shall provide all management,
    labor, supervision, vehicles, equipment, and materials to perform all work as specified herein.”
    White Decl., Ex. A at 52. The agreement also specifies that the contractor “shall coordinate with
    the Government regarding the prioritization of maintenance and repair work, including any
    additional tasks.” White Decl., Ex. A at 52.
    5
    According to Ms. White, the contracting documents have been redacted to remove
    proprietary information, including pricing. See White Decl. ¶ 5 nn.1–6.
    6
    For clarity, the Court’s citations to Exhibit A refer to the page numbers inserted at the
    bottom of each page. These page numbers match the page numbers automatically created by the
    Court’s Electronic Case Filing (“ECF”) system.
    4
    The agreement describes two categories of responsibilities for the contractor. First, under
    the category “Basic Scope of Work (Lump Sum),” the contractor is responsible for “tours,
    inspections, basic operation, preventive maintenance, minor repairs and replacements (≤$1,000),
    and general housekeeping.” White Decl., Ex. A at 52. Second, under the category “Additional
    Tasks As-Needed (Task Order Services),” the contractor is responsible for “additional tasks on a
    task order basis to assist the Government in accomplishing major and emergency repairs and
    replacements . . . (excluding capital improvement projects contracted separately).” White Decl.,
    Ex. A at 52. Under this second category, GSA “will define the desired schedule for each specific
    task order to coordinate the Contractor’s work with” GSA personnel and other contractors.
    White Decl., Ex. A at 58. The agreement also states that “work will be accomplished through
    close coordination with [the Heating Operation and Transmission District], but the Contractor
    shall be required to provide field supervision and quality control functions.” White Decl., Ex. A
    at 57–58.
    Section C states that the contractor “accepts full responsibility for the management and
    supervision of maintenance, minor repairs, inspections, and housekeeping of the [Heating
    Operation and Transmission District] steam distribution system.” White Decl., Ex. A at 53. The
    agreement also requires the contractor to “recognize[] that performance of the work described in
    this solicitation will not convert the acts of the Contractor into acts of the Government, and that
    the Government will not physically supervise the conduct of the Contractor’s day to day
    activities.” White Decl., Ex. A at 53. But the agreement does permit GSA to “inspect the
    Contractor’s performance of work to determine compliance with the solicitation requirements.”
    White Decl., Ex. A at 53. GSA may also “re-prioritize the Contractor’s maintenance and repair
    work when doing so is in the best interest of the Government.” White Decl., Ex. A at 53. The
    5
    agreement requires the contractor to “cooperate with Federal and local officials that enforce”
    mandatory safety requirements. White Decl., Ex. A at 59. Among other terms, Section C also
    requires GSA to provide the contractor “with radios and chargers that are to be supplied to each
    group of employees working in the tunnels” that “are to be used only to communicate with the
    [Federal Protective Service] MegaCenter and for emergencies.” White Decl., Ex. A at 61.
    Section H of the Price Proposal Offer sets forth special contract requirements. See White
    Decl., Ex. A at 76. One of those requirements is that the “Contractor shall provide insurance
    coverage for all risks associated with performing this Contract and its Task Orders.” White
    Decl., Ex. A at 88. The agreement also states that the “Contractor assumes full liability and
    responsibility for all losses and damages to property or injuries to persons occasioned through
    the performance of any services or the use, maintenance and operation of equipment and vehicles
    by the Contractor’s employees and agents.” White Decl., Ex. A at 88. Another special contract
    requirement states that “the Contractor shall defend, indemnify, and hold harmless the
    Government, its officers, agents, and employees” even in cases where “the injury, death, or
    damage may have been caused by negligence of the Government.” White Decl., Ex. A at 91.
    Section J of the Price Proposal Offer includes a range of exhibits and attachments. See
    White Decl., Ex. A at 108–09. One of the exhibits provides general information on the GSA
    facility in question. See White Decl., Ex. A at 110. The exhibit sets forth GSA’s staffing of the
    extensive tunnel facility, which “comprises one manager, three mechanical engineering
    technician (MET) supervisors, and ten mechanical engineering technicians.” White Decl., Ex. A
    at 110. According to the description, “[t]he MET supervisors have been facilitating and assuring
    quality of Steam Distribution Complex maintenance and repairs performed by the current
    6
    maintenance contractor,” presumably meaning the contractor that preceded M & M. See White
    Decl., Ex. A at 110.
    Federal Defendants’ second declarant, Mr. Westphal, is employed by GSA as the
    Manager of the Steam Distribution Branch in Washington, D.C. Westphal Decl. ¶ 1. In general,
    Mr. Westphal states that M & M did, in fact, perform the duties set forth in the agreement
    between GSA and M & M. See Westphal Decl. ¶¶ 5–7. Mr. Westphal states that these duties
    included “all operations and maintenance services” at the steam pipe location where Verizon
    alleges its equipment was damaged. See Westphal Decl. ¶ 5. Mr. Westphal states that “GSA did
    not routinely direct, supervise or exercise control over [M & M’s] day-to-day operations and
    maintenance duties,” nor did GSA “control[] how [M & M] implemented its operations and
    maintenance practices on a daily or any other routine basis.” Westphal Decl. ¶ 8. Finally, Mr.
    Westphal states that “GSA does not routinely direct, control, or supervise the operations and
    maintenance services within the GSA [Steam Distribution System] because an independent
    contractor is responsible for those duties.” Westphal Decl. ¶ 11.
    C. Procedural History
    In September 2016, Verizon brought suit against the United States and GSA in this Court.
    See Compl., ECF No. 1 at 1. Verizon filed an Amended Complaint on October 18, 2016 that
    named M & M Contractors, Inc. as an additional Defendant.7 See Am. Compl. at 1. The United
    States and GSA move to dismiss Verizon’s Amended Complaint. See Fed. Defs.’ Mot. Dismiss
    (“Mot. Dismiss”), ECF No. 12. Specifically, Federal Defendants argue that Verizon’s claims
    cannot be brought against GSA under the FTCA, see Mem. P. & A. Supp. Fed. Defs.’ Mot.
    7
    A summons has been issued as to Defendant M & M Contractors, Inc. See Summons,
    ECF No. 9. At this time, Verizon has not filed an affidavit indicating that M & M Contractors,
    Inc. has been served.
    7
    Dismiss (“Defs.’ Mem.”) at 5, ECF No. 12, that Verizon’s claims against Federal Defendants are
    barred by sovereign immunity, see Defs.’ Mem. at 5–9, and that Verizon fails to state a claim
    upon which relief can be granted, see Defs.’ Mem. at 9. Federal Defendants’ motion is fully
    briefed and ripe for decision. See Pl.’s Mem. P. & A. Supp. Pl.’s Opp’n Fed. Defs.’ Mot.
    Dismiss (“Pl.’s Opp’n”), ECF No. 13-1; Fed. Defs.’ Reply Pl.’s Opp’n Fed. Defs.’ Mot. Dismiss
    (“Defs.’ Reply”), ECF No. 14.
    III. LEGAL STANDARD
    Federal Rule of Civil Procedure 12(b)(1) provides for the dismissal of an action for lack
    of subject matter jurisdiction. See Fed. R. Civ. P. 12(b)(1). Federal courts are courts of limited
    jurisdiction, and the law presumes that “a cause lies outside this limited jurisdiction.” Rasul v.
    Bush, 
    542 U.S. 466
    , 489 (2004) (quoting Kokkonen v. Guardian Life Ins. Co. of Am., 
    511 U.S. 375
    , 377 (1994)); see also Gen. Motors Corp. v. EPA, 
    363 F.3d 442
    , 448 (D.C. Cir. 2004) (“As a
    court of limited jurisdiction, we begin, and end, with an examination of our jurisdiction.”). It is
    the plaintiff’s burden to establish that the court has subject matter jurisdiction. Lujan v. Defs. of
    Wildlife, 
    504 U.S. 555
    , 561 (1992). When considering whether it has jurisdiction, a court must
    accept “the allegations of the complaint as true.” Banneker Ventures, LLC v. Graham, 
    798 F.3d 1119
    , 1129 (D.C. Cir. 2015) (citing Herbert v. Nat’l Acad. of Scis., 
    974 F.2d 192
    , 197 (D.C. Cir.
    1992)). In this context, a court may also “consider the complaint supplemented by undisputed
    facts evidenced in the record, or the complaint supplemented by undisputed facts plus the court’s
    resolution of disputed facts.” 
    Id. (quoting Herbert,
    974 F.2d at 197).
    8
    IV. ANALYSIS
    Federal Defendants argue that sovereign immunity bars the claims Verizon has brought
    against both GSA and the United States. The Court addresses Federal Defendants’ arguments in
    turn.
    Sovereign immunity shields the federal government and its agencies from suit and is
    “jurisdictional in nature.” Am. Road & Transp. Builders Ass’n v. EPA, 
    865 F. Supp. 2d 72
    , 79
    (D.D.C. 2012) (quoting FDIC v. Meyer, 
    510 U.S. 471
    , 475 (1994)) (other citations omitted). The
    government may waive immunity, but such a waiver “must be unequivocally expressed in
    statutory text, and will not be implied.” Lane v. Pena, 
    518 U.S. 187
    , 192 (1996) (citations
    omitted). “If sovereign immunity has not been waived, a claim is subject to dismissal under Rule
    12(b)(1) for lack of subject matter jurisdiction.” Clayton v. District of Columbia, 
    931 F. Supp. 2d
    192, 200 (D.D.C. 2013) (citing 
    Meyer, 510 U.S. at 475
    ). The plaintiff bears the burden “of
    establishing both the court’s statutory jurisdiction and the government’s waiver of its sovereign
    immunity.” Am. Road & Transp. Builders 
    Ass’n, 865 F. Supp. 2d at 80
    (citations omitted).
    Once a court “determines that it lacks subject matter jurisdiction, it can proceed no further.”
    Simpkins v. D.C. Gov’t, 
    108 F.3d 366
    , 371 (D.C. Cir. 1997).
    The FTCA contains a limited waiver of sovereign immunity that allows the United States
    to be sued for the negligent acts or omissions of its employees acting within the scope of their
    employment. See 28 U.S.C. § 1346(b)(1); see also United States v. Orleans, 
    425 U.S. 807
    , 813
    (1976). Specifically, the FTCA waives sovereign immunity based on an “injury . . . caused by
    the negligent or wrongful act or omission of any employee of the Government while acting
    within the scope of his office or employment . . . if a private person[] would be liable to the
    claimant.” 28 U.S.C. § 1346(b)(1).
    9
    A. Claims Against the GSA
    The Court first turns to the counts Verizon brings directly against the GSA. See Am.
    Compl. ¶¶ 28–43 (setting forth Counts IV–VI). Federal Defendants argue that, “[u]nder the clear
    terms of the FTCA, only the United States is a proper defendant to such a suit.” Defs.’ Mem. at
    5. Federal Defendants contend that Verizon has brought “virtually identical claims against both
    the United States and the GSA,” but that the Court lacks subject matter jurisdiction over the
    claims against the GSA. Defs.’ Mem. at 5. Verizon does not respond to this point in its
    opposition to Federal Defendants’ motion to dismiss. See generally Pl.’s Opp’n; see also Defs.’
    Reply at 2 (“Verizon did not even attempt to address these arguments in its opposition . . . .”).
    The only proper defendant in an action brought under the FTCA is the United States. See
    Davis v. United States, 
    196 F. Supp. 3d 106
    , 110 n.2 (D.D.C. 2016) (“[T]he United States is the
    only proper defendant in an action under the FTCA.”); Johnson v. Veterans Affairs Med. Ctr.,
    
    133 F. Supp. 3d 10
    , 16 (D.D.C. 2015) (“FTCA suits ‘must name the United States as
    defendant.’” (quoting Goddard v. D.C. Redevelopment Land Agency, 
    287 F.2d 343
    , 345–46
    (D.C. Cir. 1961))); Daisley v. Riggs Bank, N.A., 
    372 F. Supp. 2d 61
    , 81 (D.D.C. 2005) (“[T]he
    proper defendant is the United States, not Treasury.”). Even if a federal agency may sue and be
    sued in its own name, the FTCA bars direct claims against federal agencies. See 28 U.S.C. §
    2679(a); see also Cox v. Sec’y of Labor, 
    739 F. Supp. 28
    , 29 (D.D.C. 1990) (“The FTCA directs
    that the exclusive remedy for tort claims is an action against the United States rather than against
    the individuals or the particular government agencies.”).
    Here, Verizon’s Amended Complaint brings identical negligence, nuisance, and
    trespass/interference with easement claims against both the United States and GSA. Compare
    Am. Compl. ¶¶ 12–27 (bringing Counts I–III against the United States) with Am. Compl. ¶¶ 28–
    10
    43 (bringing Counts IV–VI against GSA). But the FTCA permits only claims against the United
    States, see 28 U.S.C. § 1346(b)(1), and bars claims brought directly against federal agencies, see
    28 U.S.C. § 2679(a). Consistent with longstanding precedent, the Court finds that Verizon may
    not bring claims pursuant to the FTCA directly against GSA. See, e.g., 
    Davis, 196 F. Supp. 3d at 110
    n.2; 
    Johnson, 133 F. Supp. 3d at 16
    ; 
    Daisley, 372 F. Supp. 2d at 81
    ; 
    Cox, 739 F. Supp. at 29
    .
    Thus, the Court dismisses Counts IV, V, and VI of the Amended Complaint for lack of subject
    matter jurisdiction.
    B. Claims Against the United States
    The Court next turns to the counts Verizon brings against the United States. See Am.
    Compl. ¶¶ 12–27 (setting forth Counts I–III). Federal Defendants argue that these claims are
    barred by the independent contractor exception to the FTCA and that the Court must therefore
    dismiss Verizon’s claims for lack of subject matter jurisdiction. See Defs.’ Mem. at 5–9.
    1. Independent Contractor Exception to the FTCA
    As previously stated, the FTCA’s waiver of sovereign immunity is limited in scope and
    permits the United States to be sued only for the negligent acts or omissions of its employees
    acting within the scope of their employment. See 28 U.S.C. § 1346(b)(1); see also United States
    v. Orleans, 
    425 U.S. 807
    , 813 (1976). The text of the FTCA makes clear that the waiver of
    sovereign immunity applies to an “injury . . . caused by a negligent or wrongful act or omission
    of any employee of the Government while acting within the scope of his office or employment
    . . . if a private person[] would be liable to the claimant.” 28 U.S.C. § 1346(b)(1) (emphasis
    added).
    The FTCA’s definition of “employee of the government” includes “employees of any
    federal agency,” but the definition of “federal agency” explicitly excludes “any contractor with
    11
    the United States.” 28 U.S.C. § 2671. Based on this language, the Supreme Court has
    recognized an “independent contractor exception” to the FTCA. See 
    Orleans, 425 U.S. at 814
    –
    15. Following Orleans, courts “routinely hold that the United States cannot be sued where the
    alleged duty of care has been delegated to an independent contractor.” Hsieh v. Consol. Eng’g
    Servs., Inc., 
    569 F. Supp. 2d 159
    , 176 (D.D.C. 2008) (citing Cannon v. United States, 
    645 F.2d 1128
    , 1133–39 (D.C. Cir. 1981); Cooper v. United States Gov’t, 
    225 F. Supp. 2d 1
    , 4 (D.D.C.
    2002)).
    When considering whether the independent contractor exception to the FTCA applies, a
    court must evaluate the level of control that the United States exercises over the contractor.
    Under this exception, the government can only be liable for a contractor’s acts, if the contractor’s
    “day-to-day operations are supervised by the Federal Government.” 
    Orleans, 425 U.S. at 815
    .
    The Supreme Court has further explained that a “critical element in distinguishing an agency
    from a contractor is the power of the Federal Government ‘to control the detailed physical
    performance of the contractor.’” 
    Id. at 814
    (quoting Logue v. United States, 
    412 U.S. 521
    , 528
    (1973)). The D.C. Circuit has made clear that “the government may ‘fix specific and precise
    conditions to implement federal objectives’ without becoming liable for an independent
    contractor’s negligence.” Macharia v. United States, 
    334 F.3d 61
    , 68–69 (D.C. Cir. 2003)
    (quoting 
    Orleans, 425 U.S. at 816
    ). The United States is also permitted to “reserve the right to
    inspect the contractor’s work and monitor its compliance with federal law without vitiating the
    independent contractor exception.” 
    Hsieh, 569 F. Supp. 2d at 177
    (citing 
    Orleans, 425 U.S. at 815
    ).
    The Court agrees with Federal Defendants that the independent contractor exception
    applies to duties that GSA contracted to M & M and that the Court therefore lacks subject matter
    12
    jurisdiction over claims arising from those duties. Here, the Amended Complaint alleges that
    “steam from and/or off steam pipes owned, maintained and controlled by [Federal Defendants]
    caused damage to Verizon’s underground facilities.” Am. Compl. ¶ 8. The Amended Complaint
    also alleges that, “[o]n or about November 6, 2014, agents, servants, and/or employees of M &
    M Contractors, Inc. were repairing steam pipes . . . and caused damage to Verizon’s underground
    facilities.” Am. Compl. ¶ 9. Thus, the factual allegations in the Amended Complaint rely, at
    least in part, on the actions of M & M and its employees. See Am. Compl. ¶ 9. An employee of
    M & M is not an “employee of the government” for the purposes of the FTCA. See 28 U.S.C. §
    1346(b)(1).
    The contract at issue states that M & M “shall provide all management, labor,
    supervision, vehicles, equipment, and materials to perform all work” described in the agreement.
    White Decl., Ex. A at 52. Among other things, the described tasks include “tours, inspections,
    basic operation, preventive maintenance, minor repairs and replacements (≤$1,000), and general
    housekeeping.” White Decl., Ex. A at 52. Under the agreement, M & M “accepts full
    responsibility for the management and supervision of maintenance, minor repairs, inspections,
    and housekeeping of” the facility and “recognizes that performance of the work described . . .
    will not convert the acts of the Contractor into acts of the Government, and that the Government
    will not physically supervise the conduct of the Contractor’s day to day activities.” White Decl.,
    Ex. A at 53.
    Mr. Westphal also declares that “GSA did not routinely direct, supervise or exercise
    control over [M & M’s] day-to-day operations and maintenance duties,” nor did GSA “control[]
    how [M & M] implemented its operations and maintenance practices on a daily or any other
    routine basis.” Westphal Decl. ¶ 8. In light of M & M’s responsibilities, “GSA does not
    13
    routinely direct, control, or supervise the operations and maintenance services within the GSA
    [Steam Distribution System] because an independent contractor is responsible for those duties.”
    Westphal Decl. ¶ 11.
    To be sure, the agreement calls for close coordination between GSA and M & M and
    gives GSA the right to conduct oversight and inspections. Verizon identifies several such
    provisions in the contract. See Pl.’s Opp’n at 4–5. For instance, the contract requires M & M to
    “coordinate with the Government regarding the prioritization of maintenance and repair work,
    including any additional tasks.” White Decl., Ex. A at 52. It also gives GSA the right to
    “inspect the Contractor’s performance of work to determine compliance with the solicitation
    requirements.” White Decl., Ex. A at 53. Similarly, GSA is permitted to “re-prioritize the
    Contractor’s maintenance and repair work when doing so is in the best interest of the
    Government.” White Decl., Ex. A at 53. GSA may also set forth specific projects through task
    orders. See White Decl., Ex. A at 52. As Verizon notes, the contract also requires GSA to
    provide radios to all employees for communications with the federal government. See White
    Decl., Ex. A at 61.
    Despite Verizon’s protestations, these facts are not sufficient to override the independent
    contractor exception to the FTCA. The terms of the agreement clearly do not constitute
    supervision of “day-to-day operations . . . by the Federal Government.” 
    Orleans, 425 U.S. at 815
    . Nor does the federal government “control the detailed physical performance of the
    contractor.” 
    Logue, 412 U.S. at 528
    . Instead, the agreement creates a structure that delegates
    routine inspections, maintenance, and repairs to M & M, while retaining GSA’s right to inspect
    its contractor’s activities and to set clear, specific objectives. The federal government is
    permitted to “‘fix specific and precise conditions to implement federal objectives’ without
    14
    becoming liable for an independent contractor’s negligence.” 
    Macharia, 334 F.3d at 68
    –69
    (quoting 
    Orleans, 425 U.S. at 816
    ). Similarly, it may “reserve the right to inspect the
    contractor’s work and monitor its compliance with federal law without vitiating the independent
    contractor exception.” 
    Hsieh, 569 F. Supp. 2d at 177
    (citing 
    Orleans, 425 U.S. at 815
    ). This
    degree of oversight is consistent with the staffing described in the contract, which states that
    “supervisors have been facilitating and assuring quality of Steam Distribution Complex
    maintenance and repairs performed by the . . . contractor” preceding M & M. See White Decl.,
    Ex. A at 110.
    In fact, another court in this District addressed claims arising from the same facilities at
    issue in this case. See 
    Hsieh, 569 F. Supp. 2d at 162
    . The contract and other evidence presented
    in Hsieih are not identical to this case, but the broad facts are similar. See 
    id. at 167–169.
    The
    court concluded that “[e]vidence that GSA employees performed inspections as provided for in the .
    . . Contract . . . does not establish that the Federal Defendants had detailed control or day-to-day
    supervision of [the contractor’s] physical performance.” 
    Id. at 178.
    Similarly, GSA’s requirement
    that the contractor “follow specific procedures,” as well as the fact that GSA “maintained the right to
    inspect that work,” was not sufficient to “render the Federal Defendants liable for those tasks . . . that
    were validly delegated to [the contractor].” 
    Id. The Court
    reaches the same conclusion here. Through its contract, the federal
    government delegated the duty to conduct inspections and routine maintenance and repairs to
    M & M. GSA did not control M & M’s “day-to-day operations,” 
    Orleans, 425 U.S. at 815
    , or
    “control [its] . . . detailed physical performance,” 
    Logue, 412 U.S. at 528
    . Thus, the Court finds
    that the independent contractor exception to the FTCA bars claims arising from the duties
    delegated to M & M in contract. Because the United States has not waived its sovereign
    immunity as to those claims, the Court lacks subject jurisdiction over them.
    15
    2. Potential Allegations Outside the Scope of the Contract
    Verizon notes that the agreement between GSA and M & M did not take effect until July
    1, 2014. Pl.’s Opp’n at 5. In a brief argument that does not cite any legal authority, Verizon
    contends that “[t]he lack of maintenance, inspection, and repair may arise from the ownership,
    maintenance, and control by the Federal Defendants before such contract, placing the duties
    squarely on the Federal Defendants rather than their subcontractor.” Pl.’s Opp’n at 5.
    Federal Defendants’ response is equally brief. Federal Defendants contend that Verizon
    “appears to speculate . . . that the cause of the damage may be related to a lack of maintenance,
    inspection, or repair prior to the . . . maintenance contract with M & M.” Defs.’ Reply at
    5. Federal Defendants argue that Verizon’s position is “directly contradicted by the Amended
    Complaint, which states unequivocally . . . that M & M Contractors’ employees caused damages
    to Verizon’s underground on or about November 6, 2014.” Defs.’ Reply at 5.
    The parties’ different perspectives appear to be rooted in Verizon’s vague allegations
    with regard to the cause of the purported damage. To be sure, the Amended Complaint alleges
    that repairs conducted by M & M on or about November 6, 2014 “caused damage to Verizon’s
    underground facilities.” Am. Compl. ¶ 9. But Verizon also alleges, more generally, that “steam
    from and/or off steam pipes owned, maintained and controlled by [Federal Defendants’] caused
    damage” on or about that date. Am. Compl. ¶ 8. In the context of its negligence claim against
    the United States, Verizon alleges that the United States acted negligently through its “failure to
    exercise due care to prevent steam leaks, failure to exercise due care to prevent its pipes from
    causing secondary steam, failure to properly notify Verizon of the potential of harm, failure to
    properly instruct and supervise agent, servants and/or employees . . . and other negligence.” Am.
    Compl. ¶ 14. These more general allegations are not expressly limited to the time period covered
    16
    by the contract at issue here. Similarly, the vague nature of the allegations makes it impossible
    for the Court to determine whether the alleged acts were delegated to M & M or any other
    contractor.
    To clarify issues raised here, the Court will order Verizon to provide a more definite
    statement of its claims pursuant to Federal Rule of Civil Procedure 12(e). Under Rule 12(e) a
    “party may move for a more definite statement of a pleading . . . which is so vague or ambiguous
    that the party cannot reasonably prepare a response.” Fed. R. Civ. P. 12(e). Although Rule 12(e)
    refers to a motion made by a party, other courts in this jurisdiction have construed motions to
    dismiss as motions for a more definite statement in appropriate circumstances. See, e.g., Koch v.
    White, No. 12-1934, 
    2014 WL 1273427
    , at *1 (D.D.C. Mar. 31, 2014); Bouknight v. District of
    Columbia, 
    538 F. Supp. 2d 44
    , 49 (D.D.C. 2008); Powers-Bunce v. District of Columbia, 479 F.
    Supp. 2d 146, 158–59 (D.D.C. 2007); see also 5C Charles A. Wright & Arthur R.
    Miller, Federal Practice & Procedure § 1376 (3d ed. 2017) (“If the pleading is impermissibly
    vague, the court may act under Rule 12(b)(6) or Rule 12(e), whichever is appropriate, without
    regard to how the motion is denominated.”).
    To be sure, courts are “reluctant to compel a more definite statement pursuant to Rule
    12(e)” and “will generally deny a motion for a more definite statement where the information
    sought may be obtained in discovery.” Feldman v. CIA, 
    797 F. Supp. 2d 29
    , 42 (D.D.C. 2011)
    (quoting Hilska v. Jones, 
    217 F.R.D. 16
    , 21 (D.D.C. 2003)). But that reluctance is not
    absolute. For example, the Supreme Court has explained that requiring a more definite statement
    may be appropriate where qualified immunity is at issue. See Crawford-El v. Britton, 
    523 U.S. 574
    , 597–98 (1998). In that context, a court “must exercise its discretion so that officials are not
    subjected to unnecessary and burdensome discovery or trial proceedings.” Id.; see also Powers-
    17
    
    Bunce, 479 F. Supp. 2d at 158
    (explaining that “courts have inherent authority to order a more
    definite statement” in this context). Like qualified immunity, the independent contractor
    exception is a threshold bar that must be considered at the outset of litigation. Here, it would be
    inappropriate to subject the Federal Defendants to further proceedings if all of Verizon’s claims
    arise from acts delegated to M & M. 
    See supra
    Part IV.B.1. Requiring Verizon to clarify its
    vague Amended Complaint and provide a more definite statement of its claims will permit the
    Court to make that determination.
    Thus, at this time, the Court dismisses Counts I, II, and III, only to the extent that the
    claims arise from the duties delegated to M & M in the contract before the Court. Once Verizon
    has provided a more definite statement of its allegations, Federal Defendants may renew their
    motions to dismiss, if necessary.
    3. Nondelegable Duties for Inherently Dangerous Activities
    Verizon argues that the independent contractor exemption to the FTCA is irrelevant
    because the duty to maintain and repair the steam distribution facility “is a nondelegable duty
    based on the ultrahazardous nature of the work.” Pl.’s Opp’n at 6. Verizon relies on a series of
    citations to District of Columbia law to support this position. See Pl.’s Opp’n at 6–7.
    Under District of Columbia law, the “general rule is that an individual or corporation is
    not liable for injuries resulting from the work of an independent contractor.” W.M. Schlosser Co.
    v. Maryland Drywall Co., 
    673 A.2d 647
    , 651 (D.C. 1996) (quoting Washington Metro. Area
    Transit Auth. v. L’Enfant Plaza Prop., Inc., 
    448 A.2d 864
    (D.C. 1982)). But this general rule
    does not apply where the work “is inherently dangerous.” 
    Id. (quoting Levy
    v. Currier, 
    587 A.2d 205
    , 209 (D.C. 1991)). Instead, where work is inherently dangerous, “the contractee should not
    be allowed to escape liability and is obligated to contemplate and guard against such dangers.”
    18
    
    Id. at 651
    n.10. Verizon contends that maintenance of the steam pipes is inherently dangerous
    and that Federal Defendants “should not be permitted to escape liability for the damage their
    steam pipes caused to [Verizon’s] telecommunication facilities.” Pl.’s Opp’n at 7.
    Verizon’s argument is misplaced. In fact, the D.C. Circuit has expressly rejected this line
    of reasoning. In Clark v. United States, the D.C. Circuit stated that the federal government does
    not “have a nondelegable duty under District of Columbia law.” Clark v. United States, 
    52 F.3d 1122
    , 
    1995 WL 225702
    , at *1 (D.C. Cir. 1995) (per curiam) (unpublished table decision). The
    court explained that “[t]he nondelegable duty doctrine is inapplicable to cases arising under the
    Federal Tort Claims Act because federal law does not permit the application to the United States
    of a generalized state-defined duty.” 
    Id. The court
    relied on the Fourth Circuit case Berkman v.
    United States, 
    957 F.2d 108
    (4th Cir. 1992). See 
    id. In Berkman,
    the Fourth Circuit rejected the plaintiff’s reliance on the rule—articulated in
    Virginia law—that a landowner cannot delegate to a contractor the duty to maintain its premises
    in a reasonably safe manner. See 
    Berkman, 957 F.2d at 111
    –13. The court concluded that, “[b]y
    expressly waiving immunity for the tortious conduct of its employees, and only its employees,
    the FTCA requires a more focused approach that requires the courts to determine the relationship
    to the United States of the actor whose negligence might be imputed to the government under
    state law.” 
    Id. at 113;
    see also Clark, 
    52 F.3d 1122
    , 
    1995 WL 225702
    , at *1 (quoting this
    language). To be sure, Berkman recognized that one other circuit had reached a different
    conclusion. See 
    Berkman, 957 F.2d at 113
    (noting disagreement with the Eleventh Circuit’s
    decision in Dickerson, Inc. v. United States, 
    875 F.2d 1577
    (11th Cir. 1989)). But the D.C.
    Circuit came down firmly on the side of Berkman and the Fourth Circuit. See Clark, 
    52 F.3d 1122
    , 
    1995 WL 225702
    , at *1.
    19
    Other circuits have also endorsed the rule set forth in Berkman. See, e.g., Berrien v.
    United States, 
    711 F.3d 654
    , 658 (6th Cir. 2013) (“[S]tate-law concepts of nondelegable duty
    cannot be applied in the FTCA context to undermine the contractor exception.”); Alinsky v.
    United States, 
    415 F.3d 639
    , 645 (7th Cir. 2005) (“State common law principles cannot
    overcome [the FTCA].”); Roditis v. United States, 
    122 F.3d 108
    , 111 (2d Cir. 1997) (“Thus, any
    state law nondelegable duty cannot, on its own, override the United States’ sovereign immunity
    from suits for injuries caused by its independent contractors.”); Norman v. United States, 
    111 F.3d 356
    , 358 (3d Cir. 1997) (“We believe the Fourth Circuit [in Berkman] offers the better
    reasoned analysis and we accept it as our own.”). And courts in this District have also rejected
    the application of nondelegable duties under state law to FTCA claims. See e.g., Jennings v.
    United States, 
    530 F. Supp. 40
    , 45 n.6 (D.D.C. 1981) (noting in dicta that “a ‘nondelegability’
    theory also fails” because it “rests on a theory of absolute or strict liability, a theory foreclosed
    under the FTCA”); Hockman v. United States, 
    741 F. Supp. 5
    , 8 (D.D.C. 1990) (“[T]he law is
    well-settled that the government cannot be held strictly or absolutely liable under the FTCA for
    ultrahazardous activity.”). But see Hale v. United States, No. 13-1390, 
    2015 WL 7760161
    , at
    *6 n.3 (D.D.C. Dec. 2, 2015) (noting that “district courts in other jurisdictions have rejected
    FTCA claims based on common law premises liability theories,” but refusing to dismiss a FTCA
    claim where “the District of Columbia has adopted a negligence standard for premises liability”).
    Consistent with the D.C. Circuit’s decision in Clark and the weight of authority in other
    circuits, this Court finds that the United States does not have a nondelegable duty under District
    of Columbia law for inherently dangerous activities. The Supreme Court has explained that
    Congress defined the scope of the independent contractor exception in statute, instead of relying
    on existing state common law. See 
    Logue, 412 U.S. at 527
    . This Court cannot broaden
    20
    Congress’s waiver of the government’s sovereign immunity through the invocation of state
    common law principles. Cf. FAA v. Cooper, 
    566 U.S. 284
    , 290 (2012) (explaining that waivers
    of sovereign immunity must be strictly construed); Haase v. Sessions, 
    893 F.2d 370
    , 373 (D.C.
    Cir. 1990) (“[W]aivers of sovereign immunity. . . must be narrowly construed.”). Verizon’s
    reliance on the District of Columbia law of nondelegable duties for inherently dangerous
    activities must be rejected. See Clark, 
    52 F.3d 1122
    , 
    1995 WL 225702
    , at *1; see also 
    Alinsky, 415 F.3d at 645
    ; 
    Berkman, 957 F.2d at 113
    .
    *               *               *
    The Court finds that the independent contractor exception to the FTCA bars claims
    arising from the duties delegated to M & M by contract. But the Court also concludes that the
    vague allegations in Verizon’s Amended Complaint prevent the Court from determining whether
    Verizon has alleged any claims that fall outside the scope of the contract between the
    government and M & M. Thus, the Court orders Verizon to provide a more definite statement of
    its claims.
    The independent contractor exception to the FTCA implicates the Court’s subject matter
    jurisdiction, see 28 U.S.C. § 1346(b)(1), and the Court cannot reach the merits of Verizon’s case
    against the United States without assuring itself that it has subject matter jurisdiction. See Steel
    Co. v. Citizens for a Better Env’t, 
    523 U.S. 83
    , 84 (1998) (rejecting the principle of hypothetical
    jurisdiction); see also 
    Hsieh, 569 F. Supp. 2d at 179
    –80. The Court, therefore, does not reach
    Federal Defendants’ arguments under Rule 12(b)(6) that Verizon has failed to state a claim upon
    which relief can be granted at this time. Cf. Simpkins v. D.C. Gov’t, 
    108 F.3d 366
    , 371 (D.C.
    Cir. 1997) (“[T]he rule is strict that once a court determines that it lacks subject matter
    jurisdiction, it can proceed no further.”). Defendants may renew these arguments, and any other
    21
    bases for dismissal, after Verizon provides a more definite statement of its allegations, if
    necessary.
    Finally, the Court notes again that Verizon has not indicated that it has served
    M & M. Nor has counsel for M & M appeared before this Court. Therefore, the Court does not
    address Verizon’s claims against M & M at this time.
    V. CONCLUSION
    For the foregoing reasons, Federal Defendants’ Motion to Dismiss (ECF No. 12) is
    GRANTED IN PART AND DENIED IN PART. An order consistent with this Memorandum
    Opinion is separately and contemporaneously issued.
    Dated: June 8, 2017                                                 RUDOLPH CONTRERAS
    United States District Judge
    22
    

Document Info

Docket Number: Civil Action No. 2016-1925

Citation Numbers: 254 F. Supp. 3d 208, 2017 U.S. Dist. LEXIS 87731

Judges: Judge Rudolph Contreras

Filed Date: 6/8/2017

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (28)

Cooper v. United States Government & General Services ... , 225 F. Supp. 2d 1 ( 2002 )

Feldman v. Central Intelligence Agency , 797 F. Supp. 2d 29 ( 2011 )

Hockman v. United States , 741 F. Supp. 5 ( 1990 )

Bouknight v. District of Columbia , 538 F. Supp. 2d 44 ( 2008 )

Charles R. Goddard v. District of Columbia Redevelopment ... , 287 F.2d 343 ( 1961 )

Edward Haase v. William B. Sessions, Director, F.B.I , 893 F.2d 370 ( 1990 )

Kokkonen v. Guardian Life Insurance Co. of America , 114 S. Ct. 1673 ( 1994 )

Victor Herbert v. National Academy of Sciences , 974 F.2d 192 ( 1992 )

Steel Co. v. Citizens for a Better Environment , 118 S. Ct. 1003 ( 1998 )

United States v. Orleans , 96 S. Ct. 1971 ( 1976 )

Daisley v. Riggs Bank, N.A. , 372 F. Supp. 2d 61 ( 2005 )

Logue v. United States , 93 S. Ct. 2215 ( 1973 )

Cox v. Secretary of Labor , 739 F. Supp. 28 ( 1990 )

Rasul v. Bush , 124 S. Ct. 2686 ( 2004 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Diana L. Alinsky, Individually and as Personal ... , 415 F.3d 639 ( 2005 )

Jennings v. United States , 530 F. Supp. 40 ( 1981 )

Athanasios Roditis and Cathy Roditis v. United States , 122 F.3d 108 ( 1997 )

Cuthbert O. Simpkins v. District of Columbia Government , 108 F.3d 366 ( 1997 )

General Motors Corp. v. Environmental Protection Agency , 363 F.3d 442 ( 2004 )

View All Authorities »