All Courts |
Federal Courts |
US Federal District Court Cases |
District Court, District of Columbia |
2012-04 |
-
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA ______________________________ ) UNITED STATES OF AMERICA, ) ) Plaintiff, ) ) v. ) Civil Action No. 04-1608 (RWR) ) DRC, INC., ) ) Defendant. ) ______________________________) MEMORANDUM OPINION AND ORDER The government brings suit against defendant DRC, Inc. (also known as Disaster Relief Construction, Inc.) under the False Claims Act (“FCA”),
31 U.S.C. §§ 3729et seq., alleging that DRC submitted false pre-qualification documents and false invoices in connection with a contract awarded to DRC to provide relief assistance in Honduras that was financed by the United States Agency for International Development (“USAID”). DRC filed a motion for partial summary judgment on the false invoices claim. The claim alleges that DRC’s unauthorized subcontracting of work violated the terms of DRC’s contract with Honduras. The parties dispute whether the contract required DRC to seek USAID’s approval for subcontracting and, if so, whether DRC’s invoices were false because they impliedly certified that DRC had complied with that obligation when it had not. There are genuine issues of material fact with respect to elements of the false - 2 - invoices claim with regard to claims for payment submitted from December 2000 to April 2001 and after October 2001. However, the government cannot show that DRC possessed the scienter required to give rise to FCA liability with respect to claims for payment submitted between April 2001 and October 2001. DRC’s motion for partial summary judgment therefore will be granted in part and denied in part. BACKGROUND The contract at the heart of this dispute was financed by USAID in order to help Honduras and other countries rebuild after Hurricane Mitch struck in 1998. USAID collaborated with the Honduran Social Investment Fund (“FHIS”), an agency of the government of Honduras, on a project to construct and reconstruct water, sewer, and sanitation infrastructure in the wake of the hurricane. (Am. Compl. ¶ 10.) DRC participated in a competitive bidding process for a contract to perform the construction work and in connection with its bid submitted numerous pre- qualification documents representing its equipment, inventory, personnel, and financial obligations. (Id. ¶¶ 11-12.) The pre- qualification documents also requested information about the contractor’s plans to subcontract. (Pl.’s Opp’n to Def.’s First Mot. Partial Summ. J. (“Pl.’s Opp’n”), Exs. 4 and 5.) DRC did not identify any subcontractors with which it planned to work and - 3 - represented that the company had no intention of subcontracting. (Id.) On the basis of its pre-qualification score and low bid, DRC obtained a contract for construction projects in Honduras. (Am. Compl. ¶ 13.) The contract took the form of a “host country contract,” an agreement between a foreign country and a third-party contractor, where USAID provides funding but is not itself a party. (Def.’s Reply in Support of Def.’s First Mot. Summ. J. (“Def.’s Reply”), Def.’s Stmt. of Undisputed Facts for Def.’s First Mot. Summ. J. (“Def.’s Stmt. Undisputed Facts”) ¶¶ 10-11.) DRC ultimately submitted twenty eight vouchers for payment under the contract (Compl., Ex. C), each of which the government alleges constitutes a false claim (Am. Compl. ¶¶ 30- 36). I. SUBCONTRACTING OBLIGATIONS IN THE CONTRACT The construction contract between DRC and FHIS was executed on June 21, 2000. (Def.’s Stmt. Undisputed Facts ¶ 26.) The contract contained twelve constituent sections, many of which were written only in Spanish.1 (Id. ¶¶ 4-5.) USAID required the inclusion of two of those sections, Attachment A and Attachment B (“the Mandatory Clauses”), which were rendered both in Spanish and in English. (Id. ¶¶ 6-7.) 1 Renditions in this opinion of provisions written in Spanish rely on the parties’ translations, the accuracy of which has not been contested. - 4 - Multiple provisions in the contract addressed subcontracting. First, Section 28 of the contract provided that “[t]he contractor may not . . . subcontract with third parties without obtaining the advance, written consent of FHIS and USAID.” (Id. ¶ 20; Def.’s First Mot. Summ. J., Ex. 2.) Section 28 further provided that subcontracted work could not exceed 40 percent of the total work budget. (Def.’s Stmt. Undisputed Facts ¶ 21.) The contract listed five instances in which payment could be withheld, including “[f]ailure of the Contractor to make payments due to subcontractors for materials or labor.” (Id. ¶ 157.) Second, both Attachment A, in Section 3(G)(2)(e), and Attachment B, in Section 3(F)(2)(e), state that “[u]nder a fixed- price construction contract of any value, the prime contractor may procure locally produced goods and services under subcontracts.” (Id. ¶¶ 16-17; Def.’s First Mot. Summ. J., Ex. 3.) Third, both Attachments, in Section 2, provide that “the Contract has reserved to USAID certain rights such as . . . the right to approve the terms of this Contract, the Contractor, and any or all . . . subcontracts . . . related to this Contract and the Program/Activity of which it is part.” (Def.’s First Mot. Summ. J., Ex. 3.) Section 2 in Attachment A further states that “[a]ny approval (or failure to disapprove) by USAID shall not bar - 5 - the Contracting Agency or USAID from asserting any right, or relieve the Contractor of any liability which the Contractor might otherwise have to the Contracting Agency or USAID.” (Id.)2 Finally, Attachment A contains Section 14, entitled “Assignment, Subcontract Clauses and Procurements.” Subsection A provides that “USAID’s prior written consent to any assignment of obligations under the Contract, in addition to the consent of the Contracting Agency, is required”; subsection B obligates the contractor to include specified provisions of the Attachment in all subcontracts. (Id.)3 II. DRC’S NEGOTIATIONS CONCERNING SUBCONTRACTING FHIS issued a notice to proceed on June 23, 2000, two days after the contract was executed, giving DRC fifteen days in which to begin work. (Def.’s Stmt. Undisputed Facts ¶ 27.) According to DRC’s Executive Vice President, Sid Vogel, he told FHIS on July 3, 2000 that DRC planned to subcontract and submitted a list of subcontractors for FHIS approval at a meeting with Moises Starkman, the Minister of FHIS, Ramon Cardona, the FHIS director of major infrastructure projects (the “DIM”) who was responsible for administering the contract, and others. (Def.’s First Mot. 2 Section 2 in Attachment B contains the same language, but refers to the “Supplier” rather than the “Contractor.” (Def.’s First Mot. Summ. J., Ex. 3.) 3 The analogous section 14 in Attachment B is entitled simply “Assignment” and contains only the requirement of prior written consent for assignment of obligations. (Id.) - 6 - Partial Summ. J., Ex. 8 (Vogel Dep. 71:20-72:10, 152:18-153:20).) Vogel testified that he asked Starkman the next day “what [Starkman] want[ed] [Vogel] to do” and Starkman “told [Vogel] to go to work,” which Vogel understood to constitute “approval [for DRC] to . . . go out there and go to work with these subcontractors.” (Id. 72:11-15.) Several months later, on November 7, 2000, Cardona sent a letter to DRC stating that FHIS had “been informed” that DRC was engaged in subcontracting and reminding DRC that the project “can only be contracted up to 40 percent of the project, previous authorization from FHIS.” (Def.’s First Mot. Partial Summ. J., Ex. 9.) The letter concluded, “[w]e would appreciate that you do not effect any subcontractions [sic] without previous authorization.” (Id.) Cardona sent a copy of the letter to Todd Sloan, the head of the USAID section that administered the construction contract. (Def.’s Stmt. Undisputed Facts ¶¶ 32-33.) On November 8, 2000, DRC submitted “participation contracts” to FHIS in order to receive FHIS’s legal evaluation of whether those contracts required formal approval under the construction contract. (Id. ¶ 37.) In the preceding months, DRC “had replaced its original subcontracts with ‘participation contracts’ and argued, based on advice of Honduran legal counsel, that the Contract did not require DRC to obtain further approval from FHIS concerning these ‘participation contracts’ and [that] the 40 - 7 - percent [subcontracting] limit did not apply.’” (Def.’s First Mot. Partial Summ. J., Def.’s Stmt. of Material Facts (“Def.’s Stmt. of Material Facts”) ¶ 34 (citing Ex. 11, Pelaez Dep. at 115:16-118:11; 27:22-28:7).) FHIS issued a legal opinion on November 11, 2000 that the participation contracts did require approval and were subject to the limit. (Def.’s Stmt. Undisputed Facts ¶ 38.) After receiving FHIS’s legal opinion, DRC Project Manager Francisco Pelaez submitted a memorandum on November 15, 2000 addressed to Starkman acknowledging the parties’ difference of opinion about the status of participation agreements and, given FHIS’s legal position, submitting a list of subcontractors for the approval of both FHIS and USAID. (Def.’s Stmt. Undisputed Facts ¶¶ 39-40; Def.’s First Mot. Partial Summ. J., Ex. 18.) The memorandum represented that, regardless of the form of agreement with local companies, the budgeted amount was below the 40 percent threshold. (Id.) A series of meetings and letter exchanges among DRC, FHIS, and USAID followed, lasting several months. (Def.’s Stmt. Undisputed Facts ¶ 42.) DRC requested USAID and FHIS approval for subcontracting again later in November, along with revised subcontract forms. (Id. ¶¶ 61-63.) A report by a USAID auditor, Christine Byrne, who visited DRC work sites in November noted that at several work sites it appeared that DRC had subcontracted the vast majority of the - 8 - work. (Def.’s First Mot. Partial Summ. J., Ex. 12.) From December through early March, DRC submitted several requests to FHIS requesting approval for subcontractors, copying USAID on the letters. (Def.’s Stmt. Undisputed Facts ¶¶ 65, 66, 68, 69, 71- 73, 75, 76, 78, 79.) In January 2001, Sloan wrote to Cardona and expressed USAID’s concern about one subcontractor currently working for DRC and requested additional information about the subcontractor. (Id. ¶ 75.) Cardona forwarded USAID’s request to DRC. (Id. ¶ 76.)4 At various points during these negotiations, USAID officials suggested that the portion of overall work that DRC subcontracted was not important. USAID contracting head John McAvoy drafted a December 6, 2000 letter, signed by USAID Mission Director Timothy Mahoney, in which USAID asked FHIS to increase the permissible subcontracting quota from 40 percent to 75 percent. (Def.’s First Mot. Partial Summ. J., Ex. 39;
id.,Ex. 1 (McAvoy Dep. 39:9-41:7).) USAID Deputy Mission Director Joseph Lombardo testified that the 40 percent limit was a matter of local law and that, from USAID’s perspective, “they could be contracting out 99 4 The adequacy of DRC’s response is a disputed point between the parties. DRC maintains that it had previously provided the requested information and informed FHIS of that fact, while the government contends that DRC never provided the information. (Def.’s Stmt. of Material Facts ¶ 77; Pl.’s Opp’n to Def.’s Stmt. of Material Facts in Supp. of First Mot. Partial Summ. J. ¶ 77.) - 9 - percent of it and we wouldn’t care.” (Def.’s First Mot. Partial Summ. J., Ex. 68 (Lombardo Dep. 120:16-121:9).5 FHIS eventually, on March 19, 2001, issued a formal resolution approving DRC’s subcontracting, subject to USAID review. (Id. ¶¶ 43-44.) At a meeting with DRC and FHIS on April 6, 2001, Carlos Flores, a USAID technical officer who worked under Sloan, represented orally that Flores would be the “sole representative of USAID in charge of dealing with matters related to the project” and that approval by USAID “is not necessary to authorize DRC subcontracting endeavors.” (Def.’s First Mot. Partial Summ. J., Ex. 24 (Memorandum of Francisco Pelaez relating minutes of meeting); see also
id.,Ex. 11 (Pelaez Dep. 81:9-82:2); Def.’s Stmt. of Material Facts ¶¶ 46-48.)6 5 According to DRC, the inclusion of the 40 percent limit on subcontracting rested on a mistaken interpretation of Honduran law. The provisions imposing the limit came verbatim from Article 88 of the Honduras State Contracting Law, which restricts the amount a domestic contractor may subcontract on public projects to a maximum of 40 percent. (Def.’s Stmt. Undisputed Facts ¶¶ 112-113.) However, Article 123 of the same law requires that foreign companies subcontract a minimum of 40 percent of work to local companies. (Id. ¶ 115.) The origin of this provision is not relevant to the resolution of the instant motion. The government’s theory of implied false certification is that USAID approval of DRC’s subcontractors was material to payment, irrespective of the allowable amount of subcontracting under the contract. 6 The government does not dispute that Flores made these statements to DRC. (Cf. Pl.’s Opp’n to Def.’s Stmt. of Material Facts in Supp. of First Mot. Partial Summ. J. at 3, 7.) - 10 - In June 2001, DRC changed the subcontractors assigned to certain project sites and advised FHIS and USAID of the changes. (Def.’s Stmt. Undisputed Facts ¶ 90.) In August 2001, DRC’s new project manager, Mario Maciel, sought a formal response from Sloan about subcontracting by sending a copy of the March 2001 FHIS resolution and stating that DRC “assume[d] that [Sloan] had no objections to th[e] approval.” (Def.’s First Mot. Partial Summ. J., Ex. 66.) Sloan’s response is a disputed point between the parties. DRC proffers an undated, unsigned “draft response” from Sloan to Maciel, in which Sloan stated that USAID is “concerned that DRC, Inc. previously subcontracted work . . . without the prior approval of USAID and FHIS,” but that “[i]n light of the need to complete the work . . ., [USAID] will raise no objection to the approval by FHIS set forth in the FHIS Resolution; however, USAID reserves all of its rights with respect to the subcontracting of work by DRC, Inc. . . . without the prior approval of USAID and FHIS.” (Def.’s First Mot. Partial Summ. J., Ex. 67.) The government meanwhile proffers a letter to Maciel, signed by Sloan and dated October 16, 2001, in which Sloan states “subcontracting requires prior written approval of FHIS and USAID” and that “USAID (i) cannot retroactively approve the subcontracting of work already completed under the Group I Contract, (ii) reserves all its rights regarding compliance with Section 28 of the Group I - 11 - Contract.” (Pl.’s Opp’n, Ex. 15.) The letter then enumerated the information and documents that DRC should submit to secure USAID approval in the future. (Id.) During the ongoing discussions about DRC’s subcontracting, USAID issued a Letter of Commitment, on December 5, 2000, in which it “guarantee[d] payment” to DRC “in accordance with the terms and conditions specified in the contract.” (Def.’s First Mot. Partial Summ. J., Ex. 70.) DRC submitted on December 11, 2000 its first invoice for work performed (Def.’s Stmt. Undisputed Facts ¶ 53), and it certified that “the services . . . for which payment is requested have been satisfactorily performed (delivered) and the payment requested is in accordance with the terms of the contract.” (Compl., Ex. C2.)7 Each subsequent invoice contained an identical certification. (Id., Exs. C3-C28.) III. THE SUIT The government filed suit under the False Claims Act in September 2004. The government alleges that DRC made false statements in its pre-qualification documents regarding its inventory, equipment, and personnel (Am. Compl. ¶¶ 16-23), and that it falsely certified performance of work that had actually been completed by unauthorized subcontractors (Am. Compl. ¶¶ 24- 7 It is undisputed that DRC’s first invoice, submitted July 3, 2000, was for mobilization only, and not for work performed. (Def.’s Stmt. Undisputed Facts ¶ 52; Compl., Ex. C1.) - 12 - 34). DRC’s motion to dismiss for failure to state a claim, lack of personal jurisdiction, and improper venue, or, alternatively, to transfer, was denied. In its pending motion for partial summary judgment, DRC argues that its invoices were not false because the underlying contract permitted subcontracting, because the FHIS approved the subcontracting and USAID told FHIS and DRC that USAID approval was unnecessary, and because DRC’s invoices did not impliedly certify that no unapproved subcontracting had taken place. DRC also argues that it is entitled to judgment on the false invoices claim because DRC lacked the requisite scienter and because the government did not suffer any actual damages from DRC’s subcontracting. DRC’s motion for partial summary judgment does not address the government’s allegations regarding the pre- qualification process.8 8 In addition to asserting liability on the basis of a false implied certification theory, the government’s opposition also appears to contend that DRC may be liable under a fraudulent inducement theory because DRC would not have been awarded the contract had USAID known of its intent to subcontract extensively. (Pl.’s Opp’n at 9-11.) This argument overlaps with the government’s distinct pre-qualification documents claim -- on which DRC has not moved for summary judgment -- that DRC would not have obtained the contract had it not misrepresented its inventory, personnel, and equipment. DRC does not directly address the fraudulent inducement theory in its motion or in its reply. - 13 - DISCUSSION A party may move for summary judgment on an individual claim or part of a claim. Fed. R. Civ. P. 56(a). Summary judgment may be granted when the pleadings, the discovery and disclosure materials on file, and any affidavits show “that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Id.; see also Moore v. Hartman,
571 F.3d 62, 66 (D.C. Cir. 2009). A court considering a motion for summary judgment must draw all “justifiable inferences” from the evidence in favor of the nonmovant. Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 255 (1986). The nonmovant must either “come forward with specific facts showing that there is a genuine issue for trial[,]” or show that the materials by the movant do not establish the absence of a genuine dispute. Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp.,
475 U.S. 574, 587 (1986) (internal quotation marks and emphasis omitted). The FCA created a cause of action against anyone who “knowingly presents, or causes to be presented, to an officer or employee of the United States Government . . . a false or fraudulent claim for payment or approval[.]”
31 U.S.C. § 3729(a)(1) (2000).9 “[T]he elements of section 3729(a)(1) are 9 Congress amended the FCA in the Fraud Enforcement and Recovery Act of 2009 (“FERA”), altering slightly the language in the presentment provision. The amendment of the presentment - 14 - (1) the defendant submitted a claim to the government, (2) the claim was false, and (3) the defendant knew the claim was false.” United States ex rel. Harris v. Bernad,
275 F. Supp. 2d 1, 6 (D.D.C. 2003). “Any request for payment is properly considered a claim for purposes of the FCA.” United States ex rel. Siewick v. Jamieson Sci. & Eng’g, Inc.,
214 F.3d 1372, 1375-76 (D.C. Cir. 2000); see also
31 U.S.C. § 3729(c) (defining claim broadly to include “any request or demand, whether under a contract or otherwise, for money or property which is made to a contractor, grantee, or other recipient if the United States Government provides any portion of the money or property which is requested or demanded.”) A claim may be “legally false” if it represents falsely that the party submitting the claim has complied with an applicable federal statute or regulation, or with a contractual term. United States v. Sci. Applications Int’l Corp.,
626 F.3d 1257, 1266 (D.C. Cir. 2010) (“SAIC”). Such a “false certification” can be inferred from silence if “certification was a prerequisite to the government action sought.” Siewick,
214 F.3d at 1376. “To establish FCA liability under an implied certification theory, provision took “effect on the date of enactment of this Act and shall apply to conduct on or after the date of enactment[.]” Pub. L. No. 111-21, § 4,
123 Stat. 1617, 1625 (2009). Since the alleged conduct here occurred before 2009, the provision as amended in 2009 does not apply here, and references in this opinion to § 3729(a)(1) are to the pre-amendment version. - 15 - the plaintiff must prove by a preponderance of the evidence that compliance with the legal requirement in question is material to the government’s decision to pay.” SAIC,
626 F.3d at 1271. The materiality of a contractual requirement may be evident from “[t]he existence of express contractual language specifically linking compliance to eligibility for payment.”
Id. at 1269. But a contractual requirement can also be considered material in the absence of express language if “both parties to the contract understood that payment was conditional on compliance with the requirement at issue.” Id.; see also United States v. TDC Mgmt. Corp., Inc.,
288 F.3d 421, 426 (D.C. Cir. 2002) (noting that withholding “‘information critical to the decision to pay’” is a false claim (quoting Ab-Tech Constr., Inc. v. United States,
31 Fed. Cl. 429, 434 (Fed. Cl. 1994))). Interpreting the plain language of a contract is a question of law, not a question of fact. See LTV Corp. v. Gulf States Steel, Inc. of Ala.,
969 F.3d 1050, 1055 (D.C. Cir. 1992). The FCA also imposes a scienter requirement, requiring that a defendant present a false claim knowingly, which entails having “actual knowledge of the information[,]” acting “in deliberate ignorance of the truth or falsity of the information[,]” or acting “in reckless disregard of the truth or falsity of the information.”
31 U.S.C. § 3729(b). “Strict enforcement of the FCA’s scienter requirement will . . . help to ensure that - 16 - ordinary breaches of contract are not converted into FCA liability.” SAIC,
626 F.3d at 1271. If parties to a contract merely disagreed about how to interpret ambiguous contract language, the government cannot satisfy the requirement to show that the defendant presented claims knowingly. United States ex rel. K&R Ltd. P’ship v. Mass. Housing Finance Agency,
530 F.3d 980, 984 (D.C. Cir. 2008). Liability under an implied certification theory therefore is limited to cases where “the contractor knew, or recklessly disregarded a risk, that its certification of compliance was false.” Shaw v. AAA Eng’g & Drafting, Inc.,
213 F.3d 519, 533 (10th Cir. 2000). “Establishing knowledge under this provision [section 3729(a)(1)] on the basis of implied certification requires the plaintiff to prove that the defendant knows (1) that it violated a contractual obligation, and (2) that its compliance with that obligation was material to the government’s decision to pay.” SAIC,
626 F.3d at 1271. Claims for payment submitted under a contract procured by fraud also may be actionable. See United States ex rel. Bettis v. Odebrecht Contractors of Cal., Inc.,
393 F.3d 1321, 1326 (D.C. Cir. 2005). Congress intended that “‘each and every claim submitted under a contract . . . or other agreement which was originally obtained by means of false statements or other corrupt or fraudulent conduct . . . constitutes a false claim” under - 17 - § 3729(a). Id. (quoting S. Rep. No. 99-345, at 9 (1986), reprinted in 1986 U.S.C.C.A.N. 5266, 5274). In United States ex rel. Schwedt v. Planning Research Corp.,
59 F.3d 196, 197 (D.C. Cir. 1995), the D.C. Circuit considered an FCA action against a defendant who contracted to design software for the government. The court noted that a § 3729(a)(1) claim could rest on allegations that the defendant “made an initial misrepresentation about its capability to perform the contract in order to induce the government to enter into the contract[,] and . . . this original misrepresentation tainted every subsequent claim made in relation to the contract[.]” Id. at 199.10 A defendant who submits a false claim “is liable for civil penalties regardless of whether the government shows that the submission of that claim caused the government damages.” SAIC,
626 F.3d at 1277. The defendant may also be liable for “3 times the amount of damages which the Government sustains because of the act of [the defendant].”
Id. at 1277-78(quoting
31 U.S.C. § 3729(a)). Damages may arise even where the defendant completes satisfactorily the work required under the contract, if the defendant’s violation of the contract provisions deprived the 10 Thus, the government may seek to hold DRC liable for each claim for payment on the government’s fraudulent inducement theory -- the theory about which DRC did not seek summary judgment -- wholly independent of the government’s allegations that all of DRC’s claims for payment falsely implied that DRC complied with the requirement to obtain prior written approval for subcontracting. - 18 - government of receiving the work under the conditions it required. In SAIC, the defendant contended that its alleged violation of conflict-of-interest provisions did not give rise to damages because the defendant completed the required work. The D.C. Circuit rejected the argument since it was reasonable to conclude that “no matter how technically proficient SAIC’s performance, the value of that performance [to the government]. . . was compromised by the appearance of bias created by the company’s failure to live up to its contractual conflict of interest obligations.”
Id. at 1278.11 I. PRESENTMENT DRC argues in its reply in support of its motion for partial summary judgment that the government cannot prove its FCA claim because the government was not a party to the contract between 11 In view of this case law, DRC’s argument that the government suffered no damages, because the construction work for Honduras was satisfactorily performed under the contract, is without merit. The D.C. Circuit has held that in cases “where the defendant fraudulently sought payments for participating in programs designed to benefit third-parties rather than the government itself, the government can easily establish that it received nothing of value from the defendant and that all payments made are therefore recoverable as damages.” SAIC,
626 F.3d at 1279. The government argues that USAID’s funding of the contract was a humanitarian project, implemented in part to promote foreign policy objectives, and that it was willing to pay more for adherence to contractual requirements. (Pl.’s Opp’n at 33.) The construction contract produced tangible benefit for Honduras, not for the government. The degree to which alleged misrepresentations in the pre-qualification documents vitiated the value to the government of the contract awarded to DRC would be relevant to calculating damages. - 19 - DRC and FHIS. (Def.’s Reply at 7-8.) However, DRC cites no authority for the proposition that liability under the FCA depends on the existence of a contract between the claimant and the government; what matters is whether DRC submitted to the government a claim for payment. Because FHIS may readily be characterized as a grantee of the United States, satisfying the FCA’s presentment requirement entails showing either that “the Government provides the funds to the grantee upon presentment of a claim [by the defendant] to the Government” or that “after the grantee presents the claim, the Government provides the funds directly to the claimant[.]” United States ex rel. Totten v. Bombardier Corp.,
380 F.3d 488, 493 (D.C. Cir. 2004) (emphasis omitted). USAID disbursed funds directly to DRC upon receipt of invoices that included certifications from both DRC and FHIS. (See Compl., Ex. C.; see also Def.’s First Mot. Partial Summ. J., Ex. 3 (Attachment A, Section 13, Alternative II (A)(1)) (“Payments under this Contract shall be made in U.S. Dollars financed with funds made available by USAID. Such payments will be made to the Contractor directly by USAID[.]”).) This financing arrangement satisfies the requirement that DRC submitted claims for payment to the government. II. IMPLIED FALSE CERTIFICATION DRC does not contest that it subcontracted work without obtaining written prior approval from USAID. The claims for - 20 - payment DRC made under the contract may be considered “false” therefore if the contract (1) required DRC to secure USAID’s prior approval for subcontracting, (2) that requirement was material, and (3) DRC withheld information about its non- compliance with that requirement. The government must also prove that DRC knew that it violated the requirement and knew that its compliance with the requirement was material to the government’s decision to pay. SAIC,
626 F.3d at 1271. A. Contractual obligations If FCA liability is to be premised on an implied false certification of compliance with contractual term, the term must be clear and unambiguous because FCA liability is not triggered where parties “simply disagree about how to interpret ambiguous contract language.” Mass. Housing Finance Agency,
530 F.3d at 984; see also United States v. Kellogg Brown & Root Srvcs., Inc.,
800 F. Supp. 2d 143, 156 (D.D.C. 2011) (emphasizing that a contractor “should not face the severe penalties of the FCA for merely tangential violations”). DRC argues that the contract gave it “unconditional authorization to subcontract to local subcontractors” because the Mandatory Clauses provided that “[u]nder a fixed-price construction contract of any value, the prime contractor may procure locally produced goods and services under subcontracts.” (Def.’s Mem. of P. & A. in Support of First - 21 - Mot. Partial Summ. J. (“Def.’s Mem.”) at 4-5.)12 DRC maintains this contention despite the fact that the contract clearly provided that “[t]he contractor may not . . . subcontract with third parties without obtaining the advance, written consent of FHIS and USAID” (Def.’s First Mot. Partial Summ. J., Ex. 2, Section 28). The Mandatory Clauses provide, in Section 15, that, in the event the terms of the contract conflict with provisions of the Mandatory Clauses, the Mandatory Clauses control. (See Def.’s First Mot. Partial Summ. J., Ex. 3 (“[F]or matters which are addressed in both the text of such Contract and this Attachment, the provisions of this Attachment will constitute additional requirements for the Contract and, in the event of ambiguity or conflict between any provision in the text of the Contract and any provision(s) set forth in this Attachment, the provisions in this Attachment will control.”) Relying on this provision, DRC argues that the Mandatory Clauses’ general dictate that “the prime contractor may procure locally produced goods and services under subcontracts” (id.), without mention of any necessary approval, trumps the approval requirement found in the text of the contract. (Def.’s Mem. at 6.) DRC’s interpretation of the contract is not tenable. The term of the Mandatory Clauses allowing DRC to subcontract for 12 The government concedes that the contract was a fixed- price contract. (Pl.’s Opp’n to Def.’s Stmt. of Material Facts ¶ 18.) - 22 - local services does not conflict with Section 28. The two provisions are complementary, and the Mandatory Clauses may be harmonized with other, more specific provisions. Although nothing in the Mandatory Clauses’ express reservation to USAID of “the right to approve . . . subcontracts” (Def.’s First Mot. Partial Summ. J., Ex. 3, Section 2) makes clear that DRC would be required to make a formal submission to USAID for approval before subcontracting, the specific contract language in Section 28 explicitly does require prior written approval from USAID. The Mandatory Clauses’ general grant of permission to use subcontracts simply does not provoke “ambiguity or conflict” regarding whether approval is necessary, because it is easily read alongside the more specific provisions describing the circumstances under which subcontracting may occur. In sum, the contract did not provide unconditional authority for DRC to subcontract, but rather permitted subcontracting subject to the approval of FHIS and USAID.13 13 The government argues that Section 14 of the Mandatory Clauses clearly required that DRC secure prior approval from USAID for subcontracting. Section 14 provides that “USAID’s prior written consent to any assignment of obligations under the Contract, in addition to the consent of the Contracting Agency, is required.” (Def.’s First Mot. Summ. J., Ex. 3 (emphasis added).) An “assignment” of contract obligations, however, as DRC points out, is a practice that is distinct from subcontracting work under the contract. (Def.’s Reply at 6.) An assignment transfers completely a right or obligation under the contract to a third party, whereas when a party subcontracts with a third party for the performance of some work, the party retains all obligations under the contract. This point is confirmed by a - 23 - B. Materiality and scienter DRC’s invoices can be considered false under an implied false certification theory only if they represent falsely that DRC complied with a contractual term that is material to payment. SAIC,
626 F.3d at 1269. USAID pre-approval of subcontractors could not be considered material per se, because no contractual provision expressly linked pre-approval to DRC’s eligibility for payment.
Id.The contract enumerated five instances in which comparison of the versions of Section 14 found in both Attachments. In Attachment A, the section is entitled “Assignment, Subcontract Clauses and Procurements,” and it includes three subsections corresponding with each practice. Subsection A, addressing assignment, contains the prior written approval requirement. Subsection B, addressing subcontracts, simply obligates the contractor to include specified provisions of the Attachment in all subcontracts. (Def.’s First Mot. Summ. J., Ex. 3.) In Attachment B, the analogous Section 14 is entitled only “Assignment” and contains the requirement of prior written consent for assignment of obligations. Although the structure of these provisions confirms that the prior written consent requirement specified in the Mandatory Clauses relates to a contractor’s assignment of obligations, not to subcontracting, Section 28 imposes a prior written consent requirement with regard to subcontracting. In addition, the government’s briefing contends that Section 3(C)(3)(b) of the Mandatory Clauses, requiring that “[a]t least half of the supervisors and other Key personnel specified in the Contract schedule working at the Program/Activity site(s) must be citizens or permanent legal residents of the United States” (Def.’s First Mot. Summ. J., Ex. 3), is relevant to assessing DRC’s liability for false invoices. (Pl.’s Opp’n at 6.) The government’s complaint alleges liability because DRC “incorrectly certified that DRC performed the work required by the contract” (Am. Compl. ¶ 24) and “neither requested, nor received, prior written approval from USAID or FHIS to authorize any of these subcontracts” (id. ¶ 29). Section 3(C)(3)(b) bears only tangentially on subcontracting and imposes no requirement of any prior authorization. - 24 - payment could be withheld, and did not include failure to obtain prior approval for subcontracting among them. (Def.’s Stmt. Undisputed Facts ¶ 157.) In the absence of an express link to payment eligibility, the materiality of USAID approval must rest on record evidence that “both parties to the contract understood that payment was conditional on compliance with the requirement at issue.” SAIC,
626 F.3d at 1269. The materiality inquiry into the parties’ understanding of the importance of specified terms overlaps with the FCA’s scienter requirement that a defendant have submitted false claims knowingly. Articulating the scienter standard, the D.C. Circuit stated that the government must “prove that the defendant knows that it (1) “violated a contractual obligation, and (2) that its compliance with that obligation was material to the government’s decision to pay,” SAIC,
626 F.3d at 1271.14 Where materiality is established by reference to the 14 In its opening brief, DRC relied on a scienter standard provided by Allison Engine Co., Inc. v. United States ex rel. Sanders,
553 U.S. 662(2008) (requiring a FCA plaintiff to prove that the defendant intended that the false record or statement be material to the Government’s decision to pay or approve the false claim). (Def.’s Mem. at 34.) Allison Engine addressed scienter in the context of
31 U.S.C.A. § 3729(a)(2) (imposing civil liability on any person who “knowingly makes, uses, or causes to be made or used, a false record or statement to get a false or fraudulent claim paid or approved by the Government”), but as DRC noted, the government’s implied certification claim arises under § 3729(a)(1). (Def.’s Reply at 3-5). The D.C. Circuit’s holding in SAIC articulates the appropriate scienter standard in this context. SAIC was decided after the government submitted its opposition, but before DRC replied. Although DRC cited SAIC for other purposes in its reply, it did not address SAIC’s holding regarding scienter. - 25 - parties’ own understanding, evidence that a defendant “underst[ands] that payment [is] conditional on compliance with the requirement at issue,” id. at 1269, may also reflect the defendant’s knowledge that its violation of the requirement is “material to the government’s decision to pay,” id. at 1271. Because the FCA does not proscribe fraudulent activity in general but rather prohibits the knowing submission of false claims, the requisite knowledge must be proven to exist not at just any time in the course of the parties’ interactions but at the point at which a defendant submits its claims for payment. See, e.g., United States ex rel. Hockett v. Columbia/HCA Healthcare Corp.,
498 F. Supp. 2d 25, 57 (D.D.C. 2007) (emphasizing that the FCA “goes after claims that are false, not claims that are submitted while fraud is afoot”); Harrison v. Westinghouse Savannah River Co.,
176 F.3d 776, 785 (4th Cir. 1999) (“The statute attaches liability, not to the underlying fraudulent activity or to the government’s wrongful payment, but to the claim for payment.”) (internal quotations marks omitted). Accordingly, even if the government establishes that USAID’s prior approval for subcontracting was material, it must also prove that DRC knew that it was in violation of that requirement when it submitted its claims for payment. Although only DRC and FHIS were “parties to the contract” at issue here, as is discussed above, the financing arrangement - 26 - suffices to expose DRC to liability if the “government’s decision to pay,” SAIC,
626 F.3d at 1271, depended on DRC’s false implied certification of compliance with its obligation to seek prior authorization for subcontractors. To survive summary judgment, the government must provide evidence that USAID, rather than FHIS, considered DRC’s securing of USAID approval sufficiently important and that DRC knew it had violated the pre-approval requirement and that the requirement was material to payment. The extensive record demonstrates that there are triable issues regarding these facts. The government contends that DRC’s understanding that USAID’s approval was important can be inferred from DRC’s actions during the pre-qualification stage. DRC’s Executive Vice President signed numerous documents during the pre-qualification stage of the public competition for the host country contract, including “every page of what became attachment A [of the Mandatory Clauses],” representing that DRC did not intend to subcontract. (Pl.’s Opp’n at 10-11.) The government argues that prompt execution of subcontracts following award of the host country contract demonstrates DRC’s pre-existing intent to subcontract on a large scale and in violation of the terms of the host country contract. (Id.) DRC maintains that, because FHIS required DRC to begin work only weeks after the execution of the contract, DRC was “forced . . . to abandon its original approach - 27 - and to subcontract a portion of each project.” (Def.’s Mem. at 7.) The government proffers evidence suggesting that DRC intended to subcontract even before the bid. (See Pl.’s Opp’n 11-12 n.1 (quoting deposition testimony of Robert Isakson, DRC’s Founder and Managing Director that DRC was “talking to a couple of subcontractors before the bid”).) Fraudulent intent may be inferred in circumstances where a defendant rapidly repudiates promises after a contract is awarded, Bettis,
393 F.3d at 1330, and such inconsistency might demonstrate the parties’ understanding that the promise was important to the decision to award the contract. The pre-qualification documents did not require DRC to promise or certify that it would not subcontract, and the government does not point to any notification to DRC during the pre-qualification stage that USAID approval would be required in the event it did subcontract. Nonetheless, the parties agreed to a contract bearing an explicit prior approval requirement. USAID insisted on adding language appearing in Section 2 of both Attachments reserving its right to approve all subcontracts, and to assert that right against DRC despite any failure by USAID to disapprove a subcontract. Drawing justifiable inferences from the evidence in favor of the non- movant, a reasonable jury might find that the pre-qualification documents inquired about subcontracting, DRC hid its intent to subcontract, the contract contained multiple provisions - 28 - addressing and requiring subcontracting pre-approval, and the parties considered subcontracting procedures important to contract award and payment.15 The government also argues that DRC’s replacement of its original subcontracts with “participation agreements” DRC hoped would avoid the prior approval requirement also tends to show DRC’s perception that prior approval for subcontracting was an important contractual obligation.16 DRC maintains that it attempted to use participation agreements on the advice of its Honduran counsel, and that it promptly submitted the agreements 15 Evidence that USAID regulations require that program funding not be paid to subcontractors who have not been pre-authorized by USAID (Pl.’s Opp’n, Ex. 2 (Agency Directive E305.5.7a (requiring inclusion of clause reserving USAID’s right to approve subcontractors))) is relevant to assessing the government’s perception of the importance of including those terms in the contract. DRC contests the importance of this evidence, arguing that the regulations are not binding and that the government cannot rely on them to maintain an implied false certification action “for failure to comply with federal regulations.” (Def.’s Reply at 16.) DRC, however, conflates the source of the obligation on which an implied certification theory depends with the relevant evidence to which a court may look to determine whether the government considered the obligation material. The agency directives are not proffered as a binding requirement with which DRC allegedly falsely certified its compliance. Rather, the government’s theory is that DRC failed to comply with a contractual term, and the agency directives are relevant to determining the importance of the term to one of the parties. 16 In its reply, DRC moved to strike under Rule 56(c)(2) the government’s Exhibit 10, which contained interview notes by a USAID agent representing statements from former DRC employees and USAID employees concerning DRC’s alleged efforts to conceal subcontracting. The government did not respond to the motion and this opinion does not rely on Exhibit 10. - 29 - to FHIS in order to determine their status under the contract and did so before submitting any work invoices under the contract. (Def.’s Mem. at 8.) Assessing the credibility and implications of DRC’s representations is not an appropriate task on summary judgment. The evidence is sufficient to raise a jury question whether DRC’s pursuit of participation agreements in lieu of subcontracts tends to prove that DRC understood the procedures surrounding subcontracting, including the prior approval requirement, to be material to payment. In addition to establishing a triable issue whether the pre- approval requirement was material to payment, the record reflects a triable issue whether DRC possessed the requisite knowledge of materiality when it submitted its claims for payment. The government’s awareness of a defendant’s activities is relevant to determining a defendant’s knowledge that its claims for payment are impliedly false. “The fact that the government knew of [a contractor’s] mistakes and limitations, and that [the contractor] was open with the government about them, suggests that while [the contractor] might have been groping for solutions, it was not cheating the government in the effort.” Wang ex rel. United States v. FMC Corp.,
975 F.2d 1412, 1421 (9th Cir. 1992). Although there is some evidence favoring DRC’s position that it was forthcoming with its subcontracting plans, there is also evidence that supports the opposite conclusion. On the one hand, - 30 - DRC initiated communication with FHIS regarding subcontracting as early as July 3, 2000, less than two weeks after the execution of the host country contract on June 21, 2000. Early openness about subcontracting would tend to support DRC’s argument that it was forthcoming with its plans and engaged in good faith negotiations to meet its contractual obligations. And, according to Vogel, Starkman told Vogel the day after the July 3, 2000 meeting that DRC should “go to work,” which Vogel testified he understood to constitute “approval [for DRC] to . . . go out there and go to work with these subcontractors.” (Vogel Dep. 72:11-15.) On the other hand, Section 28 of the contract required prior written consent of both FHIS and USAID. Whatever a jury might find concerning what Vogel believed Starkman’s consent to mean, DRC offers no evidence that DRC sought USAID approval of subcontractors in July 2000, or at any point over the following three months. The course of the discussions concerning DRC’s subcontracting, which began in November 2000, also could lead a jury to draw different conclusions. In December 2000, in the midst of those negotiations, USAID issued a letter of commitment guaranteeing payment to DRC under the contract and DRC submitted its first work invoice. (Def.’s Stmt. Undisputed Facts ¶¶ 53, 108.) USAID paid this invoice and twenty one others submitted between December 11, 2000 and March 4, 2002. (Id. ¶ 98.) That - 31 - the government committed to paying and indeed paid DRC even after it knew that DRC had subcontracted without approval could be found to support DRC’s argument that it did not know the pre- approval requirement was important to payment. DRC argues that USAID did not respond to its multiple requests to approve its subcontractors, and instead simply facilitated negotiations between DRC and FHIS, including encouraging FHIS to raise the 40% limit on subcontracting, precluding a finding that DRC knew prior USAID approval was important to payment. The undisputed fact that on April 6, 2001, USAID technical officer Flores told DRC orally that USAID pre-approval was not necessary lends further support for this position. (Id. ¶¶ 46-47.) However, a reasonable jury might conclude from other evidence regarding the negotiations that DRC did possess the requisite scienter. In January 2001, a USAID official responded to a subcontracting request, via FHIS, by requesting additional information from DRC. (Id. ¶¶ 75-76.) FHIS’s letter to DRC informing DRC of USAID’s request urged DRC to “send[] the requested information as soon as possible in order to obtain the approval from USAID for the subcontracts.” (Def.’s First Mot. Partial Summ. J., Ex. 48.) This tends to show that DRC was on notice of the importance of USAID pre-approval. USAID’s general non-responsiveness to DRC’s requests could weigh against finding that DRC knew that, by not securing prior written authorization - 32 - from USAID, it was in violation of a contractual obligation that was sufficiently important to the government. But courts must “eschew making credibility determinations or weighing the evidence” in deciding summary judgment motions. Czekalski v. Peters,
475 F.3d 360, 363 (D.C. Cir. 2007). In determining how USAID’s responses or lack of responses might affect DRC’s scienter, a reasonable jury might also consider the impact of the delay of several months between DRC’s beginning work under the contract and USAID’s learning of the subcontracting issues. The government argued that this delay forced USAID into the position of not being able to insist on compliance with contractual requirements. According to the government, USAID failed to assert its right to require prior written approval because it did not want to interrupt assistance to Honduras. The government, for example, has presented evidence that USAID officials considered suspending the contract, but decided against it “given the amount of work that was already in progress.” (Pl.’s Opp’n, Ex. 12 (Lombardo Dep. 77-78).) See United States ex rel. Harrison v. Westinghouse Savannah River Co.,
352 F.3d 908, 917 (4th Cir. 2003) (noting that a contractual obligation may qualify as material even though the government continues to fund the contract after learning of wrongdoing by a contractor because “to avoid further costs the government might want . . . to continue the project rather than terminate the contract and start over”). - 33 - Although the government presented no evidence that DRC was privy to these internal discussions, a reasonable jury might conclude that DRC was aware of the urgency of disaster relief and that it knew that the prior approval provision was important to payment, even though under the circumstances USAID did not strictly enforce it. In light of the above evidence regarding scienter, the record establishes a triable issue for all but one period -- the distinct period of time from April 2001 to October 2001. In April 2001, Flores told DRC that USAID would not require DRC to seek prior approval from USAID for subcontracting. The government does not dispute the fact of Flores’ representation and does not proffer any evidence tending to qualify or contradict Flores’ remarks. The government’s general argument that USAID was forced into a position of not being able to insist on compliance with contractual requirements does not suffice to explain how DRC could have known pre-approval was important at all, much less critical to payment, after a USAID official explicitly told DRC that USAID’s approval was not necessary. Presented with the undisputed fact of Flores’ remarks, no reasonable jury could find DRC possessed the requisite scienter that claims submitted after Flores’ remarks -- at least until October 2001 -- were false. - 34 - The government has, however, proffered evidence sufficient to revive its case with respect to claims for payment following October 2001. In response to DRC’s August 2001 request for a “formal response” from USAID regarding subcontracting approval, the government says Sloan informed DRC in October 2001 that prior authorization was required and that USAID could not retroactively approve the subcontractors. Sloan’s letter set out the eight kinds of information that USAID would need in order to approve subcontractors in the future. (Pl.’s Opp’n, Ex. 15.) The inconsistency between Sloan’s representation and Flores’ oral representation a few months earlier is relevant to assessing whether the pre-approval requirement was understood by DRC to be of sufficient importance to the government even after Sloan affirmed the requirement. Nevertheless, viewing the evidence in the light most favorable to the nonmoving party, a reasonable jury could find, based on Sloan’s affirmation that USAID considered its prior written approval important, that DRC knew it was violating that obligation by failing to secure approval going forward. CONCLUSION AND ORDER The contract underlying this dispute required USAID approval for DRC subcontracting. The record is insufficient to support DRC’s entitlement to judgment as a matter of law with respect to claims submitted from December 2000 to April 2001 and from - 35 - October 2001 through March 2002. With respect to claims submitted following Flores’ representation on April 2, 2001 and before Sloan’s alleged communication to DRC on or about October 16, 2001, however, the government has failed to create a triable issue that DRC knew that compliance with the contract’s pre-approval requirement was material to payment. Therefore, it is hereby ORDERED that DRC’s first motion [43] for partial summary judgment be, and hereby is, GRANTED IN PART AND DENIED IN PART. Judgment is granted to DRC on the government’s claim of implied false certifications on DRC’s invoices submitted between April 2, 2001 and October 16, 2001. The motion is otherwise denied. It is further ORDERED that the parties meet and confer and file a joint status report by May 23, 2012 reflecting their progress in concluding discovery and proposing three mutually agreeable dates for a continued post-discovery status conference. SIGNED this 21st day of April, 2012. /s/ RICHARD W. ROBERTS United States District Judge
Document Info
Docket Number: Civil Action No. 2004-1608
Citation Numbers: 856 F. Supp. 2d 159, 2012 WL 1379833, 2012 U.S. Dist. LEXIS 55561
Judges: Judge Richard W. Roberts
Filed Date: 4/21/2012
Precedential Status: Precedential
Modified Date: 10/19/2024