United States v. Drc, Inc. , 856 F. Supp. 2d 159 ( 2012 )


Menu:
  •                    UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    ______________________________
    )
    UNITED STATES OF AMERICA,      )
    )
    Plaintiff,                )
    )
    v.                        )    Civil Action No. 04-1608 (RWR)
    )
    DRC, INC.,                     )
    )
    Defendant.                )
    ______________________________)
    MEMORANDUM OPINION AND ORDER
    The government brings suit against defendant DRC, Inc. (also
    known as Disaster Relief Construction, Inc.) under the False
    Claims Act (“FCA”), 
    31 U.S.C. §§ 3729
     et seq., alleging that DRC
    submitted false pre-qualification documents and false invoices in
    connection with a contract awarded to DRC to provide relief
    assistance in Honduras that was financed by the United States
    Agency for International Development (“USAID”).   DRC filed a
    motion for partial summary judgment on the false invoices claim.
    The claim alleges that DRC’s unauthorized subcontracting of work
    violated the terms of DRC’s contract with Honduras.   The parties
    dispute whether the contract required DRC to seek USAID’s
    approval for subcontracting and, if so, whether DRC’s invoices
    were false because they impliedly certified that DRC had complied
    with that obligation when it had not.   There are genuine
    issues of material fact with respect to elements of the false
    - 2 -
    invoices claim with regard to claims for payment submitted from
    December 2000 to April 2001 and after October 2001.       However, the
    government cannot show that DRC possessed the scienter required
    to give rise to FCA liability with respect to claims for payment
    submitted between April 2001 and October 2001.       DRC’s motion for
    partial summary judgment therefore will be granted in part and
    denied in part.
    BACKGROUND
    The contract at the heart of this dispute was financed by
    USAID in order to help Honduras and other countries rebuild after
    Hurricane Mitch struck in 1998.     USAID collaborated with the
    Honduran Social Investment Fund (“FHIS”), an agency of the
    government of Honduras, on a project to construct and reconstruct
    water, sewer, and sanitation infrastructure in the wake of the
    hurricane.   (Am. Compl. ¶ 10.)    DRC participated in a competitive
    bidding process for a contract to perform the construction work
    and in connection with its bid submitted numerous pre-
    qualification documents representing its equipment, inventory,
    personnel, and financial obligations.       (Id. ¶¶ 11-12.)    The pre-
    qualification documents also requested information about the
    contractor’s plans to subcontract.        (Pl.’s Opp’n to Def.’s First
    Mot. Partial Summ. J. (“Pl.’s Opp’n”), Exs. 4 and 5.)         DRC did
    not identify any subcontractors with which it planned to work and
    - 3 -
    represented that the company had no intention of subcontracting.
    (Id.)
    On the basis of its pre-qualification score and low bid, DRC
    obtained a contract for construction projects in Honduras.      (Am.
    Compl. ¶ 13.)   The contract took the form of a “host country
    contract,” an agreement between a foreign country and a
    third-party contractor, where USAID provides funding but is not
    itself a party.   (Def.’s Reply in Support of Def.’s First Mot.
    Summ. J. (“Def.’s Reply”), Def.’s Stmt. of Undisputed Facts for
    Def.’s First Mot. Summ. J. (“Def.’s Stmt. Undisputed Facts”)
    ¶¶ 10-11.)   DRC ultimately submitted twenty eight vouchers for
    payment under the contract (Compl., Ex. C), each of which the
    government alleges constitutes a false claim (Am. Compl. ¶¶ 30-
    36).
    I.     SUBCONTRACTING OBLIGATIONS IN THE CONTRACT
    The construction contract between DRC and FHIS was executed
    on June 21, 2000.   (Def.’s Stmt. Undisputed Facts ¶ 26.)     The
    contract contained twelve constituent sections, many of which
    were written only in Spanish.1     (Id. ¶¶ 4-5.)   USAID required the
    inclusion of two of those sections, Attachment A and Attachment B
    (“the Mandatory Clauses”), which were rendered both in Spanish
    and in English.   (Id. ¶¶ 6-7.)
    1
    Renditions in this opinion of provisions written in Spanish
    rely on the parties’ translations, the accuracy of which has not
    been contested.
    - 4 -
    Multiple provisions in the contract addressed
    subcontracting.   First, Section 28 of the contract provided that
    “[t]he contractor may not . . . subcontract with third parties
    without obtaining the advance, written consent of FHIS and
    USAID.”   (Id. ¶ 20; Def.’s First Mot. Summ. J., Ex. 2.)   Section
    28 further provided that subcontracted work could not exceed 40
    percent of the total work budget.   (Def.’s Stmt. Undisputed Facts
    ¶ 21.)    The contract listed five instances in which payment could
    be withheld, including “[f]ailure of the Contractor to make
    payments due to subcontractors for materials or labor.”    (Id.
    ¶ 157.)
    Second, both Attachment A, in Section 3(G)(2)(e), and
    Attachment B, in Section 3(F)(2)(e), state that “[u]nder a fixed-
    price construction contract of any value, the prime contractor
    may procure locally produced goods and services under
    subcontracts.”    (Id. ¶¶ 16-17; Def.’s First Mot. Summ. J., Ex.
    3.)
    Third, both Attachments, in Section 2, provide that “the
    Contract has reserved to USAID certain rights such as . . . the
    right to approve the terms of this Contract, the Contractor, and
    any or all . . . subcontracts . . . related to this Contract and
    the Program/Activity of which it is part.”   (Def.’s First Mot.
    Summ. J., Ex. 3.)   Section 2 in Attachment A further states that
    “[a]ny approval (or failure to disapprove) by USAID shall not bar
    - 5 -
    the Contracting Agency or USAID from asserting any right, or
    relieve the Contractor of any liability which the Contractor
    might otherwise have to the Contracting Agency or USAID.”   (Id.)2
    Finally, Attachment A contains Section 14, entitled
    “Assignment, Subcontract Clauses and Procurements.”   Subsection A
    provides that “USAID’s prior written consent to any assignment of
    obligations under the Contract, in addition to the consent of the
    Contracting Agency, is required”; subsection B obligates the
    contractor to include specified provisions of the Attachment in
    all subcontracts.   (Id.)3
    II.   DRC’S NEGOTIATIONS CONCERNING SUBCONTRACTING
    FHIS issued a notice to proceed on June 23, 2000, two days
    after the contract was executed, giving DRC fifteen days in which
    to begin work.   (Def.’s Stmt. Undisputed Facts ¶ 27.)   According
    to DRC’s Executive Vice President, Sid Vogel, he told FHIS on
    July 3, 2000 that DRC planned to subcontract and submitted a list
    of subcontractors for FHIS approval at a meeting with Moises
    Starkman, the Minister of FHIS, Ramon Cardona, the FHIS director
    of major infrastructure projects (the “DIM”) who was responsible
    for administering the contract, and others.   (Def.’s First Mot.
    2
    Section 2 in Attachment B contains the same language, but
    refers to the “Supplier” rather than the “Contractor.” (Def.’s
    First Mot. Summ. J., Ex. 3.)
    3
    The analogous section 14 in Attachment B is entitled
    simply “Assignment” and contains only the requirement of prior
    written consent for assignment of obligations. (Id.)
    - 6 -
    Partial Summ. J., Ex. 8 (Vogel Dep. 71:20-72:10, 152:18-153:20).)
    Vogel testified that he asked Starkman the next day “what
    [Starkman] want[ed] [Vogel] to do” and Starkman “told [Vogel] to
    go to work,” which Vogel understood to constitute “approval [for
    DRC] to . . . go out there and go to work with these
    subcontractors.”   (Id. 72:11-15.)
    Several months later, on November 7, 2000, Cardona sent a
    letter to DRC stating that FHIS had “been informed” that DRC was
    engaged in subcontracting and reminding DRC that the project “can
    only be contracted up to 40 percent of the project, previous
    authorization from FHIS.”    (Def.’s First Mot. Partial Summ. J.,
    Ex. 9.)   The letter concluded, “[w]e would appreciate that you do
    not effect any subcontractions [sic] without previous
    authorization.”    (Id.)   Cardona sent a copy of the letter to Todd
    Sloan, the head of the USAID section that administered the
    construction contract.     (Def.’s Stmt. Undisputed Facts ¶¶ 32-33.)
    On November 8, 2000, DRC submitted “participation contracts” to
    FHIS in order to receive FHIS’s legal evaluation of whether those
    contracts required formal approval under the construction
    contract.   (Id. ¶ 37.)    In the preceding months, DRC “had
    replaced its original subcontracts with ‘participation contracts’
    and argued, based on advice of Honduran legal counsel, that the
    Contract did not require DRC to obtain further approval from FHIS
    concerning these ‘participation contracts’ and [that] the 40
    - 7 -
    percent [subcontracting] limit did not apply.’”   (Def.’s First
    Mot. Partial Summ. J., Def.’s Stmt. of Material Facts (“Def.’s
    Stmt. of Material Facts”) ¶ 34 (citing Ex. 11, Pelaez Dep. at
    115:16-118:11; 27:22-28:7).)   FHIS issued a legal opinion on
    November 11, 2000 that the participation contracts did require
    approval and were subject to the limit.   (Def.’s Stmt. Undisputed
    Facts ¶ 38.)
    After receiving FHIS’s legal opinion, DRC Project Manager
    Francisco Pelaez submitted a memorandum on November 15, 2000
    addressed to Starkman acknowledging the parties’ difference of
    opinion about the status of participation agreements and, given
    FHIS’s legal position, submitting a list of subcontractors for
    the approval of both FHIS and USAID.    (Def.’s Stmt. Undisputed
    Facts ¶¶ 39-40; Def.’s First Mot. Partial Summ. J., Ex. 18.)      The
    memorandum represented that, regardless of the form of agreement
    with local companies, the budgeted amount was below the 40
    percent threshold.   (Id.)   A series of meetings and letter
    exchanges among DRC, FHIS, and USAID followed, lasting several
    months.   (Def.’s Stmt. Undisputed Facts ¶ 42.)   DRC requested
    USAID and FHIS approval for subcontracting again later in
    November, along with revised subcontract forms.   (Id. ¶¶ 61-63.)
    A report by a USAID auditor, Christine Byrne, who visited DRC
    work sites in November noted that at several work sites it
    appeared that DRC had subcontracted the vast majority of the
    - 8 -
    work.        (Def.’s First Mot. Partial Summ. J., Ex. 12.)   From
    December through early March, DRC submitted several requests to
    FHIS requesting approval for subcontractors, copying USAID on the
    letters.        (Def.’s Stmt. Undisputed Facts ¶¶ 65, 66, 68, 69, 71-
    73, 75, 76, 78, 79.)        In January 2001, Sloan wrote to Cardona and
    expressed USAID’s concern about one subcontractor currently
    working for DRC and requested additional information about the
    subcontractor.        (Id. ¶ 75.)   Cardona forwarded USAID’s request to
    DRC.        (Id. ¶ 76.)4
    At various points during these negotiations, USAID officials
    suggested that the portion of overall work that DRC subcontracted
    was not important.         USAID contracting head John McAvoy drafted a
    December 6, 2000 letter, signed by USAID Mission Director Timothy
    Mahoney, in which USAID asked FHIS to increase the permissible
    subcontracting quota from 40 percent to 75 percent.          (Def.’s
    First Mot. Partial Summ. J., Ex. 39; 
    id.,
     Ex. 1 (McAvoy Dep.
    39:9-41:7).)        USAID Deputy Mission Director Joseph Lombardo
    testified that the 40 percent limit was a matter of local law and
    that, from USAID’s perspective, “they could be contracting out 99
    4
    The adequacy of DRC’s response is a disputed point between
    the parties. DRC maintains that it had previously provided the
    requested information and informed FHIS of that fact, while the
    government contends that DRC never provided the information.
    (Def.’s Stmt. of Material Facts ¶ 77; Pl.’s Opp’n to Def.’s Stmt.
    of Material Facts in Supp. of First Mot. Partial Summ. J. ¶ 77.)
    - 9 -
    percent of it and we wouldn’t care.”    (Def.’s First Mot. Partial
    Summ. J., Ex. 68 (Lombardo Dep. 120:16-121:9).5
    FHIS eventually, on March 19, 2001, issued a formal
    resolution approving DRC’s subcontracting, subject to USAID
    review.   (Id. ¶¶ 43-44.)   At a meeting with DRC and FHIS on
    April 6, 2001, Carlos Flores, a USAID technical officer who
    worked under Sloan, represented orally that Flores would be the
    “sole representative of USAID in charge of dealing with matters
    related to the project” and that approval by USAID “is not
    necessary to authorize DRC subcontracting endeavors.”   (Def.’s
    First Mot. Partial Summ. J., Ex. 24 (Memorandum of Francisco
    Pelaez relating minutes of meeting); see also 
    id.,
     Ex. 11 (Pelaez
    Dep. 81:9-82:2); Def.’s Stmt. of Material Facts ¶¶ 46-48.)6
    5
    According to DRC, the inclusion of the 40 percent limit on
    subcontracting rested on a mistaken interpretation of Honduran
    law. The provisions imposing the limit came verbatim from
    Article 88 of the Honduras State Contracting Law, which restricts
    the amount a domestic contractor may subcontract on public
    projects to a maximum of 40 percent. (Def.’s Stmt. Undisputed
    Facts ¶¶ 112-113.) However, Article 123 of the same law requires
    that foreign companies subcontract a minimum of 40 percent of
    work to local companies. (Id. ¶ 115.) The origin of this
    provision is not relevant to the resolution of the instant
    motion. The government’s theory of implied false certification
    is that USAID approval of DRC’s subcontractors was material to
    payment, irrespective of the allowable amount of subcontracting
    under the contract.
    6
    The government does not dispute that Flores made these
    statements to DRC. (Cf. Pl.’s Opp’n to Def.’s Stmt. of Material
    Facts in Supp. of First Mot. Partial Summ. J. at 3, 7.)
    - 10 -
    In June 2001, DRC changed the subcontractors assigned to
    certain project sites and advised FHIS and USAID of the changes.
    (Def.’s Stmt. Undisputed Facts ¶ 90.)    In August 2001, DRC’s new
    project manager, Mario Maciel, sought a formal response from
    Sloan about subcontracting by sending a copy of the March 2001
    FHIS resolution and stating that DRC “assume[d] that [Sloan] had
    no objections to th[e] approval.”   (Def.’s First Mot. Partial
    Summ. J., Ex. 66.)   Sloan’s response is a disputed point between
    the parties.   DRC proffers an undated, unsigned “draft response”
    from Sloan to Maciel, in which Sloan stated that USAID is
    “concerned that DRC, Inc. previously subcontracted work . . .
    without the prior approval of USAID and FHIS,” but that “[i]n
    light of the need to complete the work . . ., [USAID] will raise
    no objection to the approval by FHIS set forth in the FHIS
    Resolution; however, USAID reserves all of its rights with
    respect to the subcontracting of work by DRC, Inc. . . . without
    the prior approval of USAID and FHIS.”   (Def.’s First Mot.
    Partial Summ. J., Ex. 67.)   The government meanwhile proffers a
    letter to Maciel, signed by Sloan and dated October 16, 2001, in
    which Sloan states “subcontracting requires prior written
    approval of FHIS and USAID” and that “USAID (i) cannot
    retroactively approve the subcontracting of work already
    completed under the Group I Contract, (ii) reserves all its
    rights regarding compliance with Section 28 of the Group I
    - 11 -
    Contract.”   (Pl.’s Opp’n, Ex. 15.)      The letter then enumerated
    the information and documents that DRC should submit to secure
    USAID approval in the future.    (Id.)
    During the ongoing discussions about DRC’s subcontracting,
    USAID issued a Letter of Commitment, on December 5, 2000, in
    which it “guarantee[d] payment” to DRC “in accordance with the
    terms and conditions specified in the contract.”      (Def.’s First
    Mot. Partial Summ. J., Ex. 70.)    DRC submitted on December 11,
    2000 its first invoice for work performed (Def.’s Stmt.
    Undisputed Facts ¶ 53), and it certified that “the services
    . . . for which payment is requested have been satisfactorily
    performed (delivered) and the payment requested is in accordance
    with the terms of the contract.”    (Compl., Ex. C2.)7    Each
    subsequent invoice contained an identical certification.         (Id.,
    Exs. C3-C28.)
    III. THE SUIT
    The government filed suit under the False Claims Act in
    September 2004.   The government alleges that DRC made false
    statements in its pre-qualification documents regarding its
    inventory, equipment, and personnel (Am. Compl. ¶¶ 16-23), and
    that it falsely certified performance of work that had actually
    been completed by unauthorized subcontractors (Am. Compl. ¶¶ 24-
    7
    It is undisputed that DRC’s first invoice, submitted
    July 3, 2000, was for mobilization only, and not for work
    performed. (Def.’s Stmt. Undisputed Facts ¶ 52; Compl., Ex. C1.)
    - 12 -
    34).       DRC’s motion to dismiss for failure to state a claim, lack
    of personal jurisdiction, and improper venue, or, alternatively,
    to transfer, was denied.
    In its pending motion for partial summary judgment, DRC
    argues that its invoices were not false because the underlying
    contract permitted subcontracting, because the FHIS approved the
    subcontracting and USAID told FHIS and DRC that USAID approval
    was unnecessary, and because DRC’s invoices did not impliedly
    certify that no unapproved subcontracting had taken place.      DRC
    also argues that it is entitled to judgment on the false invoices
    claim because DRC lacked the requisite scienter and because the
    government did not suffer any actual damages from DRC’s
    subcontracting.      DRC’s motion for partial summary judgment does
    not address the government’s allegations regarding the pre-
    qualification process.8
    8
    In addition to asserting liability on the basis of a false
    implied certification theory, the government’s opposition also
    appears to contend that DRC may be liable under a fraudulent
    inducement theory because DRC would not have been awarded the
    contract had USAID known of its intent to subcontract
    extensively. (Pl.’s Opp’n at 9-11.) This argument overlaps with
    the government’s distinct pre-qualification documents claim -- on
    which DRC has not moved for summary judgment -- that DRC would
    not have obtained the contract had it not misrepresented its
    inventory, personnel, and equipment. DRC does not directly
    address the fraudulent inducement theory in its motion or in its
    reply.
    - 13 -
    DISCUSSION
    A party may move for summary judgment on an individual claim
    or part of a claim.     Fed. R. Civ. P. 56(a).   Summary judgment may
    be granted when the pleadings, the discovery and disclosure
    materials on file, and any affidavits show “that there is no
    genuine dispute as to any material fact and the movant is
    entitled to judgment as a matter of law.”    Id.; see also Moore v.
    Hartman, 
    571 F.3d 62
    , 66 (D.C. Cir. 2009).       A court considering a
    motion for summary judgment must draw all “justifiable
    inferences” from the evidence in favor of the nonmovant.
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 255 (1986).       The
    nonmovant must either “come forward with specific facts showing
    that there is a genuine issue for trial[,]” or show that the
    materials by the movant do not establish the absence of a genuine
    dispute.   Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio
    Corp., 
    475 U.S. 574
    , 587 (1986) (internal quotation marks and
    emphasis omitted).
    The FCA created a cause of action against anyone who
    “knowingly presents, or causes to be presented, to an officer or
    employee of the United States Government . . . a false or
    fraudulent claim for payment or approval[.]”      
    31 U.S.C. § 3729
    (a)(1) (2000).9    “[T]he elements of section 3729(a)(1) are
    9
    Congress amended the FCA in the Fraud Enforcement and
    Recovery Act of 2009 (“FERA”), altering slightly the language in
    the presentment provision. The amendment of the presentment
    - 14 -
    (1) the defendant submitted a claim to the government, (2) the
    claim was false, and (3) the defendant knew the claim was false.”
    United States ex rel. Harris v. Bernad, 
    275 F. Supp. 2d 1
    , 6
    (D.D.C. 2003).   “Any request for payment is properly considered a
    claim for purposes of the FCA.”   United States ex rel. Siewick v.
    Jamieson Sci. & Eng’g, Inc., 
    214 F.3d 1372
    , 1375-76 (D.C. Cir.
    2000); see also 
    31 U.S.C. § 3729
    (c) (defining claim broadly to
    include “any request or demand, whether under a contract or
    otherwise, for money or property which is made to a contractor,
    grantee, or other recipient if the United States Government
    provides any portion of the money or property which is requested
    or demanded.”)
    A claim may be “legally false” if it represents falsely that
    the party submitting the claim has complied with an applicable
    federal statute or regulation, or with a contractual term.
    United States v. Sci. Applications Int’l Corp., 
    626 F.3d 1257
    ,
    1266 (D.C. Cir. 2010) (“SAIC”).    Such a “false certification” can
    be inferred from silence if “certification was a prerequisite to
    the government action sought.”    Siewick, 
    214 F.3d at 1376
    .   “To
    establish FCA liability under an implied certification theory,
    provision took “effect on the date of enactment of this Act and
    shall apply to conduct on or after the date of enactment[.]”
    Pub. L. No. 111-21, § 4, 
    123 Stat. 1617
    , 1625 (2009). Since the
    alleged conduct here occurred before 2009, the provision as
    amended in 2009 does not apply here, and references in this
    opinion to § 3729(a)(1) are to the pre-amendment version.
    - 15 -
    the plaintiff must prove by a preponderance of the evidence that
    compliance with the legal requirement in question is material to
    the government’s decision to pay.”       SAIC, 
    626 F.3d at 1271
    .   The
    materiality of a contractual requirement may be evident from
    “[t]he existence of express contractual language specifically
    linking compliance to eligibility for payment.”      
    Id. at 1269
    .
    But a contractual requirement can also be considered material in
    the absence of express language if “both parties to the contract
    understood that payment was conditional on compliance with the
    requirement at issue.”    Id.; see also United States v. TDC Mgmt.
    Corp., Inc., 
    288 F.3d 421
    , 426 (D.C. Cir. 2002) (noting that
    withholding “‘information critical to the decision to pay’” is a
    false claim (quoting Ab-Tech Constr., Inc. v. United States, 
    31 Fed. Cl. 429
    , 434 (Fed. Cl. 1994))).      Interpreting the plain
    language of a contract is a question of law, not a question of
    fact.    See LTV Corp. v. Gulf States Steel, Inc. of Ala., 
    969 F.3d 1050
    , 1055 (D.C. Cir. 1992).
    The FCA also imposes a scienter requirement, requiring that
    a defendant present a false claim knowingly, which entails having
    “actual knowledge of the information[,]” acting “in deliberate
    ignorance of the truth or falsity of the information[,]” or
    acting “in reckless disregard of the truth or falsity of the
    information.”    
    31 U.S.C. § 3729
    (b).    “Strict enforcement of the
    FCA’s scienter requirement will . . . help to ensure that
    - 16 -
    ordinary breaches of contract are not converted into FCA
    liability.”    SAIC, 
    626 F.3d at 1271
    .   If parties to a contract
    merely disagreed about how to interpret ambiguous contract
    language, the government cannot satisfy the requirement to show
    that the defendant presented claims knowingly.    United States ex
    rel. K&R Ltd. P’ship v. Mass. Housing Finance Agency, 
    530 F.3d 980
    , 984 (D.C. Cir. 2008).    Liability under an implied
    certification theory therefore is limited to cases where “the
    contractor knew, or recklessly disregarded a risk, that its
    certification of compliance was false.”    Shaw v. AAA Eng’g &
    Drafting, Inc., 
    213 F.3d 519
    , 533 (10th Cir. 2000).
    “Establishing knowledge under this provision [section 3729(a)(1)]
    on the basis of implied certification requires the plaintiff to
    prove that the defendant knows (1) that it violated a contractual
    obligation, and (2) that its compliance with that obligation was
    material to the government’s decision to pay.”    SAIC, 
    626 F.3d at 1271
    .
    Claims for payment submitted under a contract procured by
    fraud also may be actionable.    See United States ex rel. Bettis
    v. Odebrecht Contractors of Cal., Inc., 
    393 F.3d 1321
    , 1326 (D.C.
    Cir. 2005).    Congress intended that “‘each and every claim
    submitted under a contract . . . or other agreement which was
    originally obtained by means of false statements or other corrupt
    or fraudulent conduct . . . constitutes a false claim” under
    - 17 -
    § 3729(a).    Id. (quoting S. Rep. No. 99-345, at 9 (1986),
    reprinted in 1986 U.S.C.C.A.N. 5266, 5274).    In United States ex
    rel. Schwedt v. Planning Research Corp., 
    59 F.3d 196
    , 197 (D.C.
    Cir. 1995), the D.C. Circuit considered an FCA action against a
    defendant who contracted to design software for the government.
    The court noted that a § 3729(a)(1) claim could rest on
    allegations that the defendant “made an initial misrepresentation
    about its capability to perform the contract in order to induce
    the government to enter into the contract[,] and . . . this
    original misrepresentation tainted every subsequent claim made in
    relation to the contract[.]”   Id. at 199.10
    A defendant who submits a false claim “is liable for civil
    penalties regardless of whether the government shows that the
    submission of that claim caused the government damages.”      SAIC,
    
    626 F.3d at 1277
    .   The defendant may also be liable for “3 times
    the amount of damages which the Government sustains because of
    the act of [the defendant].”   
    Id. at 1277-78
     (quoting 
    31 U.S.C. § 3729
    (a)).   Damages may arise even where the defendant completes
    satisfactorily the work required under the contract, if the
    defendant’s violation of the contract provisions deprived the
    10
    Thus, the government may seek to hold DRC liable for each
    claim for payment on the government’s fraudulent inducement
    theory -- the theory about which DRC did not seek summary
    judgment -- wholly independent of the government’s allegations
    that all of DRC’s claims for payment falsely implied that DRC
    complied with the requirement to obtain prior written approval
    for subcontracting.
    - 18 -
    government of receiving the work under the conditions it
    required.   In SAIC, the defendant contended that its alleged
    violation of conflict-of-interest provisions did not give rise to
    damages because the defendant completed the required work.   The
    D.C. Circuit rejected the argument since it was reasonable to
    conclude that “no matter how technically proficient SAIC’s
    performance, the value of that performance [to the
    government]. . . was compromised by the appearance of bias
    created by the company’s failure to live up to its contractual
    conflict of interest obligations.”     
    Id. at 1278
    .11
    I.   PRESENTMENT
    DRC argues in its reply in support of its motion for partial
    summary judgment that the government cannot prove its FCA claim
    because the government was not a party to the contract between
    11
    In view of this case law, DRC’s argument that the
    government suffered no damages, because the construction work for
    Honduras was satisfactorily performed under the contract, is
    without merit. The D.C. Circuit has held that in cases “where
    the defendant fraudulently sought payments for participating in
    programs designed to benefit third-parties rather than the
    government itself, the government can easily establish that it
    received nothing of value from the defendant and that all
    payments made are therefore recoverable as damages.” SAIC, 
    626 F.3d at 1279
    . The government argues that USAID’s funding of the
    contract was a humanitarian project, implemented in part to
    promote foreign policy objectives, and that it was willing to pay
    more for adherence to contractual requirements. (Pl.’s Opp’n at
    33.) The construction contract produced tangible benefit for
    Honduras, not for the government. The degree to which alleged
    misrepresentations in the pre-qualification documents vitiated
    the value to the government of the contract awarded to DRC would
    be relevant to calculating damages.
    - 19 -
    DRC and FHIS.   (Def.’s Reply at 7-8.)   However, DRC cites no
    authority for the proposition that liability under the FCA
    depends on the existence of a contract between the claimant and
    the government; what matters is whether DRC submitted to the
    government a claim for payment.     Because FHIS may readily be
    characterized as a grantee of the United States, satisfying the
    FCA’s presentment requirement entails showing either that “the
    Government provides the funds to the grantee upon presentment of
    a claim [by the defendant] to the Government” or that “after the
    grantee presents the claim, the Government provides the funds
    directly to the claimant[.]”   United States ex rel. Totten v.
    Bombardier Corp., 
    380 F.3d 488
    , 493 (D.C. Cir. 2004) (emphasis
    omitted).   USAID disbursed funds directly to DRC upon receipt of
    invoices that included certifications from both DRC and FHIS.
    (See Compl., Ex. C.; see also Def.’s First Mot. Partial Summ. J.,
    Ex. 3 (Attachment A, Section 13, Alternative II (A)(1))
    (“Payments under this Contract shall be made in U.S. Dollars
    financed with funds made available by USAID.    Such payments will
    be made to the Contractor directly by USAID[.]”).)    This
    financing arrangement satisfies the requirement that DRC
    submitted claims for payment to the government.
    II.   IMPLIED FALSE CERTIFICATION
    DRC does not contest that it subcontracted work without
    obtaining written prior approval from USAID.    The claims for
    - 20 -
    payment DRC made under the contract may be considered “false”
    therefore if the contract (1) required DRC to secure USAID’s
    prior approval for subcontracting, (2) that requirement was
    material, and (3) DRC withheld information about its non-
    compliance with that requirement.   The government must also prove
    that DRC knew that it violated the requirement and knew that its
    compliance with the requirement was material to the government’s
    decision to pay.   SAIC, 
    626 F.3d at 1271
    .
    A.   Contractual obligations
    If FCA liability is to be premised on an implied false
    certification of compliance with contractual term, the term must
    be clear and unambiguous because FCA liability is not triggered
    where parties “simply disagree about how to interpret ambiguous
    contract language.”    Mass. Housing Finance Agency, 
    530 F.3d at 984
    ; see also United States v. Kellogg Brown & Root Srvcs., Inc.,
    
    800 F. Supp. 2d 143
    , 156 (D.D.C. 2011) (emphasizing that a
    contractor “should not face the severe penalties of the FCA for
    merely tangential violations”).   DRC argues that the contract
    gave it “unconditional authorization to subcontract to local
    subcontractors” because the Mandatory Clauses provided that
    “[u]nder a fixed-price construction contract of any value, the
    prime contractor may procure locally produced goods and services
    under subcontracts.”   (Def.’s Mem. of P. & A. in Support of First
    - 21 -
    Mot. Partial Summ. J. (“Def.’s Mem.”) at 4-5.)12   DRC maintains
    this contention despite the fact that the contract clearly
    provided that “[t]he contractor may not . . . subcontract with
    third parties without obtaining the advance, written consent of
    FHIS and USAID” (Def.’s First Mot. Partial Summ. J., Ex. 2,
    Section 28).   The Mandatory Clauses provide, in Section 15, that,
    in the event the terms of the contract conflict with provisions
    of the Mandatory Clauses, the Mandatory Clauses control.    (See
    Def.’s First Mot. Partial Summ. J., Ex. 3 (“[F]or matters which
    are addressed in both the text of such Contract and this
    Attachment, the provisions of this Attachment will constitute
    additional requirements for the Contract and, in the event of
    ambiguity or conflict between any provision in the text of the
    Contract and any provision(s) set forth in this Attachment, the
    provisions in this Attachment will control.”)   Relying on this
    provision, DRC argues that the Mandatory Clauses’ general dictate
    that “the prime contractor may procure locally produced goods and
    services under subcontracts” (id.), without mention of any
    necessary approval, trumps the approval requirement found in the
    text of the contract.   (Def.’s Mem. at 6.)
    DRC’s interpretation of the contract is not tenable.     The
    term of the Mandatory Clauses allowing DRC to subcontract for
    12
    The government concedes that the contract was a fixed-
    price contract. (Pl.’s Opp’n to Def.’s Stmt. of Material Facts
    ¶ 18.)
    - 22 -
    local services does not conflict with Section 28.   The two
    provisions are complementary, and the Mandatory Clauses may be
    harmonized with other, more specific provisions.    Although
    nothing in the Mandatory Clauses’ express reservation to USAID of
    “the right to approve . . . subcontracts” (Def.’s First Mot.
    Partial Summ. J., Ex. 3, Section 2) makes clear that DRC would be
    required to make a formal submission to USAID for approval before
    subcontracting, the specific contract language in Section 28
    explicitly does require prior written approval from USAID.     The
    Mandatory Clauses’ general grant of permission to use
    subcontracts simply does not provoke “ambiguity or conflict”
    regarding whether approval is necessary, because it is easily
    read alongside the more specific provisions describing the
    circumstances under which subcontracting may occur.   In sum, the
    contract did not provide unconditional authority for DRC to
    subcontract, but rather permitted subcontracting subject to the
    approval of FHIS and USAID.13
    13
    The government argues that Section 14 of the Mandatory
    Clauses clearly required that DRC secure prior approval from
    USAID for subcontracting. Section 14 provides that “USAID’s
    prior written consent to any assignment of obligations under the
    Contract, in addition to the consent of the Contracting Agency,
    is required.” (Def.’s First Mot. Summ. J., Ex. 3 (emphasis
    added).) An “assignment” of contract obligations, however, as
    DRC points out, is a practice that is distinct from
    subcontracting work under the contract. (Def.’s Reply at 6.) An
    assignment transfers completely a right or obligation under the
    contract to a third party, whereas when a party subcontracts with
    a third party for the performance of some work, the party retains
    all obligations under the contract. This point is confirmed by a
    - 23 -
    B.    Materiality and scienter
    DRC’s invoices can be considered false under an implied
    false certification theory only if they represent falsely that
    DRC complied with a contractual term that is material to payment.
    SAIC, 
    626 F.3d at 1269
    .   USAID pre-approval of subcontractors
    could not be considered material per se, because no contractual
    provision expressly linked pre-approval to DRC’s eligibility for
    payment.   
    Id.
       The contract enumerated five instances in which
    comparison of the versions of Section 14 found in both
    Attachments. In Attachment A, the section is entitled
    “Assignment, Subcontract Clauses and Procurements,” and it
    includes three subsections corresponding with each practice.
    Subsection A, addressing assignment, contains the prior written
    approval requirement. Subsection B, addressing subcontracts,
    simply obligates the contractor to include specified provisions
    of the Attachment in all subcontracts. (Def.’s First Mot. Summ.
    J., Ex. 3.) In Attachment B, the analogous Section 14 is
    entitled only “Assignment” and contains the requirement of prior
    written consent for assignment of obligations. Although the
    structure of these provisions confirms that the prior written
    consent requirement specified in the Mandatory Clauses relates to
    a contractor’s assignment of obligations, not to subcontracting,
    Section 28 imposes a prior written consent requirement with
    regard to subcontracting.
    In addition, the government’s briefing contends that Section
    3(C)(3)(b) of the Mandatory Clauses, requiring that “[a]t least
    half of the supervisors and other Key personnel specified in the
    Contract schedule working at the Program/Activity site(s) must be
    citizens or permanent legal residents of the United States”
    (Def.’s First Mot. Summ. J., Ex. 3), is relevant to assessing
    DRC’s liability for false invoices. (Pl.’s Opp’n at 6.) The
    government’s complaint alleges liability because DRC “incorrectly
    certified that DRC performed the work required by the contract”
    (Am. Compl. ¶ 24) and “neither requested, nor received, prior
    written approval from USAID or FHIS to authorize any of these
    subcontracts” (id. ¶ 29). Section 3(C)(3)(b) bears only
    tangentially on subcontracting and imposes no requirement of any
    prior authorization.
    - 24 -
    payment could be withheld, and did not include failure to obtain
    prior approval for subcontracting among them.    (Def.’s Stmt.
    Undisputed Facts ¶ 157.)   In the absence of an express link to
    payment eligibility, the materiality of USAID approval must rest
    on record evidence that “both parties to the contract understood
    that payment was conditional on compliance with the requirement
    at issue.”   SAIC, 
    626 F.3d at 1269
    .    The materiality inquiry into
    the parties’ understanding of the importance of specified terms
    overlaps with the FCA’s scienter requirement that a defendant
    have submitted false claims knowingly.     Articulating the scienter
    standard, the D.C. Circuit stated that the government must “prove
    that the defendant knows that it (1) “violated a contractual
    obligation, and (2) that its compliance with that obligation was
    material to the government’s decision to pay,” SAIC, 
    626 F.3d at 1271
    .14   Where materiality is established by reference to the
    14
    In its opening brief, DRC relied on a scienter standard
    provided by Allison Engine Co., Inc. v. United States ex rel.
    Sanders, 
    553 U.S. 662
     (2008) (requiring a FCA plaintiff to prove
    that the defendant intended that the false record or statement be
    material to the Government’s decision to pay or approve the false
    claim). (Def.’s Mem. at 34.) Allison Engine addressed scienter
    in the context of 
    31 U.S.C.A. § 3729
    (a)(2) (imposing civil
    liability on any person who “knowingly makes, uses, or causes to
    be made or used, a false record or statement to get a false or
    fraudulent claim paid or approved by the Government”), but as DRC
    noted, the government’s implied certification claim arises under
    § 3729(a)(1). (Def.’s Reply at 3-5). The D.C. Circuit’s holding
    in SAIC articulates the appropriate scienter standard in this
    context. SAIC was decided after the government submitted its
    opposition, but before DRC replied. Although DRC cited SAIC for
    other purposes in its reply, it did not address SAIC’s holding
    regarding scienter.
    - 25 -
    parties’ own understanding, evidence that a defendant
    “underst[ands] that payment [is] conditional on compliance with
    the requirement at issue,” id. at 1269, may also reflect the
    defendant’s knowledge that its violation of the requirement is
    “material to the government’s decision to pay,” id. at 1271.
    Because the FCA does not proscribe fraudulent activity in general
    but rather prohibits the knowing submission of false claims, the
    requisite knowledge must be proven to exist not at just any time
    in the course of the parties’ interactions but at the point at
    which a defendant submits its claims for payment.   See, e.g.,
    United States ex rel. Hockett v. Columbia/HCA Healthcare Corp.,
    
    498 F. Supp. 2d 25
    , 57 (D.D.C. 2007) (emphasizing that the FCA
    “goes after claims that are false, not claims that are submitted
    while fraud is afoot”); Harrison v. Westinghouse Savannah River
    Co., 
    176 F.3d 776
    , 785 (4th Cir. 1999) (“The statute attaches
    liability, not to the underlying fraudulent activity or to the
    government’s wrongful payment, but to the claim for payment.”)
    (internal quotations marks omitted).   Accordingly, even if the
    government establishes that USAID’s prior approval for
    subcontracting was material, it must also prove that DRC knew
    that it was in violation of that requirement when it submitted
    its claims for payment.
    Although only DRC and FHIS were “parties to the contract” at
    issue here, as is discussed above, the financing arrangement
    - 26 -
    suffices to expose DRC to liability if the “government’s decision
    to pay,” SAIC, 
    626 F.3d at 1271
    , depended on DRC’s false implied
    certification of compliance with its obligation to seek prior
    authorization for subcontractors.     To survive summary judgment,
    the government must provide evidence that USAID, rather than
    FHIS, considered DRC’s securing of USAID approval sufficiently
    important and that DRC knew it had violated the pre-approval
    requirement and that the requirement was material to payment.
    The extensive record demonstrates that there are triable issues
    regarding these facts.
    The government contends that DRC’s understanding that
    USAID’s approval was important can be inferred from DRC’s actions
    during the pre-qualification stage.       DRC’s Executive Vice
    President signed numerous documents during the pre-qualification
    stage of the public competition for the host country contract,
    including “every page of what became attachment A [of the
    Mandatory Clauses],” representing that DRC did not intend to
    subcontract.   (Pl.’s Opp’n at 10-11.)     The government argues that
    prompt execution of subcontracts following award of the host
    country contract demonstrates DRC’s pre-existing intent to
    subcontract on a large scale and in violation of the terms of the
    host country contract.   (Id.)    DRC maintains that, because FHIS
    required DRC to begin work only weeks after the execution of the
    contract, DRC was “forced . . . to abandon its original approach
    - 27 -
    and to subcontract a portion of each project.”   (Def.’s Mem. at
    7.)   The government proffers evidence suggesting that DRC
    intended to subcontract even before the bid.    (See Pl.’s Opp’n
    11-12 n.1 (quoting deposition testimony of Robert Isakson, DRC’s
    Founder and Managing Director that DRC was “talking to a couple
    of subcontractors before the bid”).)   Fraudulent intent may be
    inferred in circumstances where a defendant rapidly repudiates
    promises after a contract is awarded, Bettis, 
    393 F.3d at 1330
    ,
    and such inconsistency might demonstrate the parties’
    understanding that the promise was important to the decision to
    award the contract.   The pre-qualification documents did not
    require DRC to promise or certify that it would not subcontract,
    and the government does not point to any notification to DRC
    during the pre-qualification stage that USAID approval would be
    required in the event it did subcontract.   Nonetheless, the
    parties agreed to a contract bearing an explicit prior approval
    requirement.   USAID insisted on adding language appearing in
    Section 2 of both Attachments reserving its right to approve all
    subcontracts, and to assert that right against DRC despite any
    failure by USAID to disapprove a subcontract.    Drawing
    justifiable inferences from the evidence in favor of the non-
    movant, a reasonable jury might find that the pre-qualification
    documents inquired about subcontracting, DRC hid its intent to
    subcontract, the contract contained multiple provisions
    - 28 -
    addressing and requiring subcontracting pre-approval, and the
    parties considered subcontracting procedures important to
    contract award and payment.15
    The government also argues that DRC’s replacement of its
    original subcontracts with “participation agreements” DRC hoped
    would avoid the prior approval requirement also tends to show
    DRC’s perception that prior approval for subcontracting was an
    important contractual obligation.16      DRC maintains that it
    attempted to use participation agreements on the advice of its
    Honduran counsel, and that it promptly submitted the agreements
    15
    Evidence that USAID regulations require that program
    funding not be paid to subcontractors who have not been
    pre-authorized by USAID (Pl.’s Opp’n, Ex. 2 (Agency Directive
    E305.5.7a (requiring inclusion of clause reserving USAID’s right
    to approve subcontractors))) is relevant to assessing the
    government’s perception of the importance of including those
    terms in the contract. DRC contests the importance of this
    evidence, arguing that the regulations are not binding and that
    the government cannot rely on them to maintain an implied false
    certification action “for failure to comply with federal
    regulations.” (Def.’s Reply at 16.) DRC, however, conflates the
    source of the obligation on which an implied certification theory
    depends with the relevant evidence to which a court may look to
    determine whether the government considered the obligation
    material. The agency directives are not proffered as a binding
    requirement with which DRC allegedly falsely certified its
    compliance. Rather, the government’s theory is that DRC failed
    to comply with a contractual term, and the agency directives are
    relevant to determining the importance of the term to one of the
    parties.
    16
    In its reply, DRC moved to strike under Rule 56(c)(2) the
    government’s Exhibit 10, which contained interview notes by a
    USAID agent representing statements from former DRC employees and
    USAID employees concerning DRC’s alleged efforts to conceal
    subcontracting. The government did not respond to the motion and
    this opinion does not rely on Exhibit 10.
    - 29 -
    to FHIS in order to determine their status under the contract and
    did so before submitting any work invoices under the contract.
    (Def.’s Mem. at 8.)    Assessing the credibility and implications
    of DRC’s representations is not an appropriate task on summary
    judgment.   The evidence is sufficient to raise a jury question
    whether DRC’s pursuit of participation agreements in lieu of
    subcontracts tends to prove that DRC understood the procedures
    surrounding subcontracting, including the prior approval
    requirement, to be material to payment.
    In addition to establishing a triable issue whether the pre-
    approval requirement was material to payment, the record reflects
    a triable issue whether DRC possessed the requisite knowledge of
    materiality when it submitted its claims for payment.   The
    government’s awareness of a defendant’s activities is relevant to
    determining a defendant’s knowledge that its claims for payment
    are impliedly false.   “The fact that the government knew of [a
    contractor’s] mistakes and limitations, and that [the contractor]
    was open with the government about them, suggests that while [the
    contractor] might have been groping for solutions, it was not
    cheating the government in the effort.”   Wang ex rel. United
    States v. FMC Corp., 
    975 F.2d 1412
    , 1421 (9th Cir. 1992).
    Although there is some evidence favoring DRC’s position that it
    was forthcoming with its subcontracting plans, there is also
    evidence that supports the opposite conclusion.   On the one hand,
    - 30 -
    DRC initiated communication with FHIS regarding subcontracting as
    early as July 3, 2000, less than two weeks after the execution of
    the host country contract on June 21, 2000.     Early openness about
    subcontracting would tend to support DRC’s argument that it was
    forthcoming with its plans and engaged in good faith negotiations
    to meet its contractual obligations.     And, according to Vogel,
    Starkman told Vogel the day after the July 3, 2000 meeting that
    DRC should “go to work,” which Vogel testified he understood to
    constitute “approval [for DRC] to . . . go out there and go to
    work with these subcontractors.”    (Vogel Dep. 72:11-15.)     On the
    other hand, Section 28 of the contract required prior written
    consent of both FHIS and USAID.     Whatever a jury might find
    concerning what Vogel believed Starkman’s consent to mean, DRC
    offers no evidence that DRC sought USAID approval of
    subcontractors in July 2000, or at any point over the following
    three months.
    The course of the discussions concerning DRC’s
    subcontracting, which began in November 2000, also could lead a
    jury to draw different conclusions.      In December 2000, in the
    midst of those negotiations, USAID issued a letter of commitment
    guaranteeing payment to DRC under the contract and DRC submitted
    its first work invoice.    (Def.’s Stmt. Undisputed Facts ¶¶ 53,
    108.)    USAID paid this invoice and twenty one others submitted
    between December 11, 2000 and March 4, 2002.     (Id. ¶ 98.)     That
    - 31 -
    the government committed to paying and indeed paid DRC even after
    it knew that DRC had subcontracted without approval could be
    found to support DRC’s argument that it did not know the pre-
    approval requirement was important to payment.    DRC argues that
    USAID did not respond to its multiple requests to approve its
    subcontractors, and instead simply facilitated negotiations
    between DRC and FHIS, including encouraging FHIS to raise the 40%
    limit on subcontracting, precluding a finding that DRC knew prior
    USAID approval was important to payment.    The undisputed fact
    that on April 6, 2001, USAID technical officer Flores told DRC
    orally that USAID pre-approval was not necessary lends further
    support for this position.   (Id. ¶¶ 46-47.)
    However, a reasonable jury might conclude from other
    evidence regarding the negotiations that DRC did possess the
    requisite scienter.   In January 2001, a USAID official responded
    to a subcontracting request, via FHIS, by requesting additional
    information from DRC.   (Id. ¶¶ 75-76.)    FHIS’s letter to DRC
    informing DRC of USAID’s request urged DRC to “send[] the
    requested information as soon as possible in order to obtain the
    approval from USAID for the subcontracts.”     (Def.’s First Mot.
    Partial Summ. J., Ex. 48.)   This tends to show that DRC was on
    notice of the importance of USAID pre-approval.    USAID’s general
    non-responsiveness to DRC’s requests could weigh against finding
    that DRC knew that, by not securing prior written authorization
    - 32 -
    from USAID, it was in violation of a contractual obligation that
    was sufficiently important to the government.    But courts must
    “eschew making credibility determinations or weighing the
    evidence” in deciding summary judgment motions.    Czekalski v.
    Peters, 
    475 F.3d 360
    , 363 (D.C. Cir. 2007).     In determining how
    USAID’s responses or lack of responses might affect DRC’s
    scienter, a reasonable jury might also consider the impact of the
    delay of several months between DRC’s beginning work under the
    contract and USAID’s learning of the subcontracting issues.    The
    government argued that this delay forced USAID into the position
    of not being able to insist on compliance with contractual
    requirements.   According to the government, USAID failed to
    assert its right to require prior written approval because it did
    not want to interrupt assistance to Honduras.    The government,
    for example, has presented evidence that USAID officials
    considered suspending the contract, but decided against it “given
    the amount of work that was already in progress.”    (Pl.’s Opp’n,
    Ex. 12 (Lombardo Dep. 77-78).)   See United States ex rel.
    Harrison v. Westinghouse Savannah River Co., 
    352 F.3d 908
    , 917
    (4th Cir. 2003) (noting that a contractual obligation may qualify
    as material even though the government continues to fund the
    contract after learning of wrongdoing by a contractor because “to
    avoid further costs the government might want . . . to continue
    the project rather than terminate the contract and start over”).
    - 33 -
    Although the government presented no evidence that DRC was privy
    to these internal discussions, a reasonable jury might conclude
    that DRC was aware of the urgency of disaster relief and that it
    knew that the prior approval provision was important to payment,
    even though under the circumstances USAID did not strictly
    enforce it.
    In light of the above evidence regarding scienter, the
    record establishes a triable issue for all but one period -- the
    distinct period of time from April 2001 to October 2001.    In
    April 2001, Flores told DRC that USAID would not require DRC to
    seek prior approval from USAID for subcontracting.   The
    government does not dispute the fact of Flores’ representation
    and does not proffer any evidence tending to qualify or
    contradict Flores’ remarks.   The government’s general argument
    that USAID was forced into a position of not being able to insist
    on compliance with contractual requirements does not suffice to
    explain how DRC could have known pre-approval was important at
    all, much less critical to payment, after a USAID official
    explicitly told DRC that USAID’s approval was not necessary.
    Presented with the undisputed fact of Flores’ remarks, no
    reasonable jury could find DRC possessed the requisite scienter
    that claims submitted after Flores’ remarks -- at least until
    October 2001 -- were false.
    - 34 -
    The government has, however, proffered evidence sufficient
    to revive its case with respect to claims for payment following
    October 2001.   In response to DRC’s August 2001 request for a
    “formal response” from USAID regarding subcontracting approval,
    the government says Sloan informed DRC in October 2001 that prior
    authorization was required and that USAID could not retroactively
    approve the subcontractors.   Sloan’s letter set out the eight
    kinds of information that USAID would need in order to approve
    subcontractors in the future.    (Pl.’s Opp’n, Ex. 15.)   The
    inconsistency between Sloan’s representation and Flores’ oral
    representation a few months earlier is relevant to assessing
    whether the pre-approval requirement was understood by DRC to be
    of sufficient importance to the government even after Sloan
    affirmed the requirement.   Nevertheless, viewing the evidence in
    the light most favorable to the nonmoving party, a reasonable
    jury could find, based on Sloan’s affirmation that USAID
    considered its prior written approval important, that DRC knew it
    was violating that obligation by failing to secure approval going
    forward.
    CONCLUSION AND ORDER
    The contract underlying this dispute required USAID approval
    for DRC subcontracting.   The record is insufficient to support
    DRC’s entitlement to judgment as a matter of law with respect to
    claims submitted from December 2000 to April 2001 and from
    - 35 -
    October 2001 through March 2002.   With respect to claims
    submitted following Flores’ representation on April 2, 2001 and
    before Sloan’s alleged communication to DRC on or about
    October 16, 2001, however, the government has failed to create a
    triable issue that DRC knew that compliance with the contract’s
    pre-approval requirement was material to payment.   Therefore, it
    is hereby
    ORDERED that DRC’s first motion [43] for partial summary
    judgment be, and hereby is, GRANTED IN PART AND DENIED IN PART.
    Judgment is granted to DRC on the government’s claim of implied
    false certifications on DRC’s invoices submitted between April 2,
    2001 and October 16, 2001.   The motion is otherwise denied.   It
    is further
    ORDERED that the parties meet and confer and file a joint
    status report by May 23, 2012 reflecting their progress in
    concluding discovery and proposing three mutually agreeable dates
    for a continued post-discovery status conference.
    SIGNED this 21st day of April, 2012.
    /s/
    RICHARD W. ROBERTS
    United States District Judge
    

Document Info

Docket Number: Civil Action No. 2004-1608

Citation Numbers: 856 F. Supp. 2d 159, 2012 WL 1379833, 2012 U.S. Dist. LEXIS 55561

Judges: Judge Richard W. Roberts

Filed Date: 4/21/2012

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (18)

United States Ex Rel. Hockett v. Columbia/HCA Healthcare ... , 498 F. Supp. 2d 25 ( 2007 )

United States Ex Rel. Bettis v. Odebrecht Contractors of ... , 393 F.3d 1321 ( 2005 )

Edwin P. Harrison, and United States of America, Party in ... , 176 F.3d 776 ( 1999 )

United States of America Ex Rel., Mervyn A. Schwedt v. ... , 59 F.3d 196 ( 1995 )

Moore v. Hartman , 571 F.3d 62 ( 2009 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

US Ex Rel. Harris v. Bernad , 275 F. Supp. 2d 1 ( 2003 )

United States Ex Rel. Totten v. Bombardier Corp. , 380 F.3d 488 ( 2004 )

United States Ex Rel. Siewick v. Jamieson Science & ... , 214 F.3d 1372 ( 2000 )

us-ex-rel-edwin-p-harrison-v-westinghouse-savannah-river-company-united , 352 F.3d 908 ( 2003 )

Allison Engine Co. v. United States Ex Rel. Sanders , 128 S. Ct. 2123 ( 2008 )

Chen-Cheng Wang, AKA C.C. Wang, an Individual and Ex Rel. ... , 975 F.2d 1412 ( 1992 )

United States v. TDC Management Corp. , 288 F.3d 421 ( 2002 )

United States v. Science Applications International Corp. , 626 F.3d 1257 ( 2010 )

Czekalski, Loni v. Peters, Mary , 475 F.3d 360 ( 2007 )

United States v. Kellogg Brown & Root Services, Inc. , 800 F. Supp. 2d 143 ( 2011 )

United States Ex Rel. K & R Limited Partnership v. ... , 530 F.3d 980 ( 2008 )

Shaw v. AAA Engineering & Drafting, Inc. , 213 F.3d 519 ( 2000 )

View All Authorities »