Center for Biological Diversity v. U.S. Army Corps of Engineers ( 2021 )


Menu:
  •                                UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    CENTER FOR BIOLOGICAL DIVERSITY,
    et al.,
    Plaintiffs,
    v.
    Civil Action No. 20-103 (RDM)
    U.S. ARMY CORPS OF ENGINEERS, et al.,
    Defendants,
    and
    FG LA LLC,
    Defendant-Intervenor.
    MEMORANDUM OPINION
    Sometimes, in the midst of a legal challenge to an agency action, the agency itself
    develops doubts about its action (or the process that led to it) and voluntarily suspends its rule to
    allow for further consideration. The question then becomes what should happen to the pending
    lawsuit.
    In this case, the U.S. Army Corps of Engineers’ (“the Corps”) issued a permit allowing
    FG LA LLC (“FG”) to construct a large plastics manufacturing plant in St. James, Louisiana.
    Plaintiffs brought suit under the Administrative Procedure Act (“APA”) challenging the Corps’
    issuance of the permit, and FG intervened in defense of the Corps’ action. Ctr. for Biological
    Diversity v. U.S. Army Corps of Eng’rs, No. 20-cv-103, 
    2020 WL 5642287
    , at *1 (D.D.C. Sept.
    22, 2020). Shortly after the Court granted in part and denied in part Plaintiffs’ Motion to Admit
    Extra-Record Evidence, Dkt. 61, Plaintiffs moved for summary judgment, Dkt. 62. The day
    before the Corps and FG were to file their oppositions and cross-motions, however, the Corps
    filed a motion seeking to stay the briefing schedule, Dkt. 67. The Corps explained that it had
    “come to [its] attention that an element of the permit warrants additional evaluation” and that a
    motion for voluntary remand would be forthcoming. Id. at 2, 5. Plaintiffs did not oppose the
    stay, Dkt. 68, and the Court accordingly granted the motion. Minute Order, November 5, 2020.
    On November 10, 2020, the Corps notified FG that the agency was suspending the permit
    at issue in this litigation to allow reevaluation of “the alternatives analysis under the Clean Water
    Act [(“CWA”)] and other aspects of the permit decision if appropriate.” Dkt. 69-1 at 2. Other
    than actions necessary for “a controlled wind-down of permitted activities to stabilize the site . . .
    or activities that do not require Corps authorization under” the relevant CWA provision, progress
    at the construction site has ceased during the suspension. Dkt. 71 at 6. Then, on December 2,
    2020, the Corps moved for a voluntary remand without vacatur and to dismiss the complaint.
    Dkt. 71.
    All parties agree that the Court should remand the matter without vacatur, which the
    Court will do. But the parties dispute whether the Court should retain jurisdiction while the
    matter is on remand or, rather, should dismiss the complaint. In the view of the Corps and FG,
    the Corps’ suspension of the permit means that the agency will need to take some further action,
    reinstating, modifying, or revoking the permit; this further action will involve a new and
    different administrative record; as a result, the Corps’ prior issuance of a permit no longer
    constitutes final agency action for purposes of the APA; and that the Court should, accordingly,
    dismiss the action. If the Corps subsequently reinstates the permit or issues a modified permit to
    which Plaintiffs object, Plaintiffs can, in the view of the Corps and FG, simply bring a new
    action; there is no reason, however, to retain jurisdiction pending the agency’s further decision.
    2
    Plaintiffs disagree. In their view, it is not uncommon for courts to retain jurisdiction over APA
    challenges while on remand, and that is what the Court should do here.
    Although a close question, the Court agrees with the Corps and FG that dismissal is the
    most prudent course. When a challenge to an agency proceeding is on remand, the Court has
    discretion to retain jurisdiction over the case or to dismiss the action without prejudice. Cobell v.
    Norton, 
    240 F.3d 1081
    , 1108–09 (D.C. Cir. 2001) (citing cases in which courts have decided to
    retain jurisdiction during remands and referring to such relief as within “a district court’s
    equitable powers” (internal quotation marks omitted)); Baystate Med. Ctr. v. Leavitt, 
    587 F. Supp. 2d 37
    , 41 (D.D.C. 2008). For the following reasons, the Court will decline to retain
    jurisdiction over the present dispute.
    First, any post-remand proceedings in this case will necessarily focus on the action the
    Corps takes on remand. As the Corps explains, its
    reevaluation of the [p]ermit will result in a new administrative record and a new
    final agency action superseding the agency action challenged here. While the
    [p]ermit is suspended and until the Corps undertakes new agency action, none
    of the activities that the [p]ermit authorized may proceed, with the exception of
    limited work necessary to safely wind down FG’s previously undertaken
    activities.
    Dkt. 71 at 2. That reevaluation, moreover, will involve questions that go to the core of the
    agency’s decision to issue the permit that it did; the Corps now acknowledges that its
    Memorandum of Record “may have been insufficient to support eliminating five alternative sites
    . . . from its alternatives analysis” and that, on remand, it will need to decide “whether it
    correctly determined that there are no practicable alternatives to FG’s proposed project that
    would have less adverse impacts, as well as other issues the Corps may deem appropriate.” Id. at
    7. Were the Corps to decide on remand that an alternative site is appropriate, for example, that
    would fundamentally alter the challenge, if any, that Plaintiffs might bring. But, in any event,
    3
    because the Corps contemplates taking a new, final agency action, it seems likely that Plaintiffs
    would need to file a supplemental complaint challenging that action, and it seems likely that the
    Corps would need to file a new administrative record. In short, even were this Court to retain
    jurisdiction, the case would likely need to start from scratch with a new final agency action, a
    new complaint, and a new administrative record. Although portions of the old and new case
    might well overlap, the initiation of a new proceeding would avoid confusion regarding the
    issues properly before the Court.
    Second, courts most often retain jurisdiction over proceedings while on remand in “cases
    alleging unreasonable delay of agency action or failure to comply with a statutory deadline,” in
    “cases involving a history of agency noncompliance with court orders or resistance to fulfillment
    of legal duties,” Baystate, 
    587 F. Supp. 2d at 41
    , and in cases in which the court has issued
    specific instructions to guide the agency on remand, Matson Navigation Co. v. U.S. Dep’t of
    Transp., No. 18-cv-2751, 
    2020 WL 4816460
    , at *2 (D.D.C. Aug. 19, 2020). Likewise, where a
    remand is only for the purposes of clarifying an issue in the administrative record, a court might
    reasonably remand the action without vacatur to permit supplementation or clarification of the
    record or to permit the agency to clarify reasoning that was not pellucid. In such circumstances,
    the remand serves to facilitate judicial review, and it is often appropriate for the court to retain
    jurisdiction. But none of these reasons for retaining jurisdiction is present here: Plaintiffs would
    have little ground to object if the Corps were to take an excessive amount of time in resolving the
    remand, since the permit has been suspended pending further agency action; this Court has yet to
    enter any order that might require agency compliance; and the proposed remand is not for the
    purpose of facilitating judicial review.
    4
    More generally, Plaintiffs have failed to identify any purpose that would be served if the
    Court were to retain jurisdiction during the remand. Their request that the Court require the
    Corps to transmit all relevant decision documents to Plaintiffs within 24 hours of final action,
    Dkt. 73 at 4, is both unnecessary and unsupported. The Corps has represented that it will
    “provide a copy of its final decision on reevaluation of the [p]ermit and any supporting
    memorandum for the record to Plaintiffs . . . within three business days after giving notice of that
    decision to” FG, Dkt. 76 at 6, and Plaintiffs have failed to explain why they need more
    expeditious notice and have failed to identify any rule or precedent supporting their request.
    The Court will, accordingly, remand the matter without vacatur for further action
    consistent with the Corps’ representations before this Court and will dismiss the action in light of
    the suspension and remand.
    A separate order will issue.
    /s/ Randolph D. Moss
    RANDOLPH D. MOSS
    United States District Judge
    Date: January 1, 2021
    5
    

Document Info

Docket Number: Civil Action No. 2020-0103

Judges: Judge Randolph D. Moss

Filed Date: 1/1/2021

Precedential Status: Precedential

Modified Date: 1/1/2021