Scg America Group Inc. v. Starlight Security Inc. ( 2023 )


Menu:
  •                         UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    SCG AMERICA GROUP, INC.,
    Plaintiff,
    v.                                   Civ. Action No. 20-2877
    (EGS)
    STARLIGHT SECURITY INC.,
    Defendant.
    MEMORANDUM OPINION
    I.       Introduction
    SCG America Group, Inc. (“SCG” or “Plaintiff”) brings this
    action against Starlight Security Inc. (“SSI” or “Defendant”)
    alleging breach of contract and negligence claims following a
    redevelopment project at the consular residence building owned
    by the Embassy of the People’s Republic of China and located in
    the District of Columbia (the “District”). See Am. Compl., ECF
    No. 9 ¶¶ 16, 43-53. 1
    Pending before the Court is SSI’s Motion to Dismiss, ECF
    No. 10. Upon careful consideration of the parties’ submissions,
    1
    When citing electronic filings throughout this Opinion, the
    Court refers to the ECF page numbers, not the page numbers of
    the filed documents.
    1
    the applicable law, and the entire record herein, the Court
    hereby DENIES SSI’s motion.
    II.   Background
    A. Factual
    The People’s Republic of China (“China”) hired SCG as its
    general contractor to complete a redevelopment project at the
    consular residence building in Washington, D.C. (the “Project”).
    See Am. Compl., ECF No. 9 ¶ 16. SCG’s parent company is Shanghai
    Construction Group, a large, prominent construction company in
    China. Id. ¶ 7. The Project is the only construction work SCG
    has ever performed in the District. Id. ¶ 8.
    On December 5, 2016, SCG entered into a contract with SSI,
    a fire alarm subcontractor. Id. ¶¶ 10, 16 (citing Ex. A
    (“Subcontract Agreement”), ECF No. 9-1). Pursuant to this
    contract (the “Subcontract Agreement”), SSI was required to
    furnish and install the fire alarm system at the Project for
    $980,000.00. Id. ¶ 17. The parties agreed that SCG would make
    payments on a progress basis. Id. ¶ 18. The parties also agreed
    that SCG was entitled to withhold certain payments and/or
    collect damages from SSI under certain circumstances. Id. ¶¶ 18-
    22.
    SCG alleges that, during the duration of the Subcontract
    Agreement, SSI repeatedly defaulted on its contractual
    obligations. See id. ¶¶ 23-24, 34-35. In an attempt to resolve
    2
    their disputes and complete the fire alarm installation, the
    parties entered into two additional agreements: the First
    Addendum to Subcontract and the Second Addendum to Subcontract.
    See id. ¶¶ 26, 28 (citing Ex. B (“First Addendum”), ECF No. 9-2;
    Ex. C (“Second Addendum”), ECF No. 9-3). Pursuant to these
    addenda, SCG paid SSI $100,000 in exchange for SSI’s agreement
    to complete its work on the Project. See id. ¶ 27.
    SCG alleges that in December 2019, SSI again stopped work
    on the Project and demanded payment. Id. ¶ 34. SCG then
    determined that SSI “was not capable of completing the
    contracted work” and sent SSI a Notice of Default as well as a
    Notice of Termination of Subcontract Agreement in February 2020.
    Id. ¶ 35 (citing Ex. D (“Notice of Default”), ECF No. 9-4; Ex. E
    (“Notice of Termination of Subcontract Agreement”), ECF No. 9-
    5).
    SCG thereafter engaged a different subcontractor to
    complete the fire alarm installation and to redo a significant
    portion of SSI’s work. Id. ¶¶ 36-38. SCG alleges that it has
    incurred significant additional expenses, including its payments
    to the new subcontractor, the costs of amplifier panels withheld
    by SSI, and other damages. Id. ¶¶ 39-41.
    B. Procedural
    SCG filed this lawsuit on October 8, 2020, see Compl., ECF
    No. 1; and amended the Complaint later that year on December 29,
    3
    2020, see Am. Compl., ECF No. 9. On January 12, 2021, SSI filed
    this Motion to Dismiss the Amended Complaint. See Def.’s Mot.
    Dismiss Pl.’s Am. Compl. &, in the Alternative, Mot. Summ. J.,
    ECF No. 10; Def. Starlight Security Inc.’s Mem. Supp. Mot.
    Dismiss (“Def.’s Mot.”), ECF No. 10-1. SCG filed its opposition
    brief on January 26, 2021, see Pl.’s Mem. P. & A. Opp’n Def.’s
    Mot. Dismiss Am. Compl. & Summ. J. (“Pl.’s Opp’n”), ECF No. 11;
    and SSI filed its reply brief on February 1, 2021, see Reply
    Supp. Def.’s Mot. Dismiss & Mot. Summ. J. (“Defs.’ Reply”), ECF
    No. 12. SSI’s motion is now ripe and ready for adjudication.
    III. Legal Standard
    A. Rule 12(b)(6) Motion to Dismiss
    A motion to dismiss pursuant to Federal Rule of Civil
    Procedure 12(b)(6) tests the legal sufficiency of a complaint.
    Browning v. Clinton, 
    292 F.3d 235
    , 242 (D.C. Cir. 2002). A
    complaint must contain “a short and plain statement of the claim
    showing that the pleader is entitled to relief, in order to give
    the defendant fair notice of what the . . . claim is and the
    grounds upon which it rests.” Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555 (2007) (citation and internal quotation marks
    omitted).
    Despite this liberal pleading standard, to survive a motion
    to dismiss, a complaint “must contain sufficient factual matter,
    accepted as true, to state a claim to relief that is plausible
    4
    on its face.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009)
    (citation and internal quotation marks omitted). “In determining
    whether a complaint fails to state a claim, [the court] may
    consider only the facts alleged in the complaint, any documents
    either attached to or incorporated in the complaint and matters
    of which [the court] may take judicial notice.” EEOC v. St.
    Francis Xavier Parochial Sch., 
    117 F.3d 621
    , 624 (D.C. Cir.
    1997). A claim is facially plausible when the facts pled in the
    complaint allow the court to “draw the reasonable inference that
    the defendant is liable for the misconduct alleged.” Iqbal, 
    556 U.S. at 678
    . The standard does not amount to a “probability
    requirement,” but it does require more than a “sheer possibility
    that a defendant has acted unlawfully.” 
    Id.
    “[W]hen ruling on a defendant’s motion to dismiss [pursuant
    to Rule 12(b)(6)], a judge must accept as true all of the
    factual allegations contained in the complaint.” Atherton v.
    D.C. Off. of the Mayor, 
    567 F.3d 672
    , 681 (D.C. Cir. 2009)
    (citation and internal quotation marks omitted). In addition,
    the court must give the plaintiff the “benefit of all inferences
    that can be derived from the facts alleged.” Kowal v. MCI
    Commc’ns Corp., 
    16 F.3d 1271
    , 1276 (D.C. Cir. 1994).
    B. Rule 12(b)(3) Motion to Dismiss
    Federal Rule of Civil Procedure 12(b)(3) authorizes a party
    to move to dismiss a case for “improper venue.” Fed. R. Civ. P.
    5
    12(b)(3). “Whether venue is ‘wrong’ or ‘improper’ depends
    exclusively on whether the court in which the case was brought
    satisfies the requirements of federal venue laws.” Atl. Marine
    Constr. Co. v. U.S. Dist. Ct. for W. Dist. of Tex., 
    571 U.S. 49
    ,
    55 (2013). The plaintiff bears the burden of establishing that
    venue is proper. Ananiev v. Wells Fargo Bank, N.A., 
    968 F. Supp. 2d 123
    , 129 (D.D.C. 2013) (citations omitted).
    In considering a motion to dismiss for improper venue, the
    court “accepts the plaintiff’s well-pled factual allegations
    regarding venue as true, draws all reasonable inferences from
    those allegations in the plaintiff’s favor and resolves any
    factual conflicts in the plaintiff’s favor.” McCain v. Bank of
    Am., 
    13 F. Supp. 3d 45
    , 51 (D.D.C. 2014) (citations and internal
    quotation marks omitted), aff’d sub nom. McCain v. Bank of Am.
    N.A., 
    602 F. App’x 836
     (D.C. Cir. 2015). “The Court, however,
    need not accept the plaintiff’s legal conclusions as true, and
    may consider material outside the pleadings, including
    undisputed facts evidenced in the record, to determine whether
    it has jurisdiction in the case.” Ananiev, 
    968 F. Supp. 2d at 129
     (citations and internal quotation marks omitted).
    IV.   Analysis
    A. SCG May Proceed with Its Breach of Contract Claim
    SSI moves to dismiss Count I of the Amended Complaint,
    which alleges breach of contract, because SCG was the general
    6
    contractor for the Project but failed to comply with local
    licensing regulations. See Def.’s Mot., ECF No. 10-1 at 5-13.
    For the reasons that follow, the Court DENIES SSI’s motion as to
    this claim.
    District of Columbia law requires that “individuals or
    businesses engaged in general contracting or construction
    management” obtain “[a] General Contractor/Construction Manager
    License.” 
    D.C. Code Ann. § 47-2851
    .03d(b). To comply, general
    contractors 2 and construction managers 3 must apply to the
    Department of Consumer and Regulatory Affairs to receive a basic
    business license with a general contractor/construction manager
    endorsement. 
    D.C. Mun. Regs. tit. 17, § 3900.1
    . The District
    prohibits “[a] person which is required under law to obtain a
    license issued in the form of an endorsement to engage in a
    business in the District of Columbia” from “engag[ing] in such
    business in the District of Columbia without having first
    2 District regulations define general contractor as “any person
    who, for a fee, is contracted to do construction on real
    property owned, controlled, or leased by another person of
    commercial, industrial, institutional, governmental, residential
    or accessory use buildings or structures. This also includes the
    remodeling, repair, improvement or demolition of these buildings
    or structures.” 
    D.C. Mun. Regs. tit. 17, § 3999
    .
    3 District regulations define construction manager as “any
    person who, for a fee, is contracted to supervise and coordinate
    the work of design professionals and multiple general
    contractors, while allowing the design professionals and general
    contractors to control individual operations and the manner of
    design and construction.” 
    D.C. Mun. Regs. tit. 17, § 3999
    .
    7
    obtained a basic business license and any necessary
    endorsements.” 
    D.C. Code Ann. § 47-2851.02
    (a).
    Here, SSI argues that SCG is subject to the above licensing
    scheme, has failed to comply, and therefore cannot enforce the
    contract at issue. See Def.’s Mot., ECF No. 10-1 at 5-10. SSI
    explains that SCG should have obtained the basic business
    license with a general contractor/construction manager
    endorsement because SCG was the general contractor for the
    Project and the Project was located in the District. See id. at
    8-10. SSI then reviews caselaw from the federal and local courts
    in the District and determines that “courts have consistently
    barred individuals and entities that violated licensing
    requirements from asserting breach of contract and/or quantum
    meruit actions.” Id. at 7 (collecting cases); see also id. at 5-
    7 (collecting and discussing cases). SSI thus concludes that the
    Subcontract Agreement is “void, unenforceable, illegal, and in
    violation of [D.C.] public policy” because SCG did not have the
    appropriate license at any time between execution of the
    original contract and filing of the Amended Complaint. Id. at
    10.
    SCG disagrees that the District’s licensing laws apply
    here. Id. at 11. SCG argues that a 2009 executive agreement (the
    “Executive Agreement”) between China and the United States
    governs the Project and allows China “to engage a general
    8
    contractor . . . without regard for local government
    ‘restrictions’ or licensure requirements.” Id. at 11-12 (citing
    Decl. of Hongquan Li (“Li Decl.”), ECF No. 11-1 ¶¶ 3-4; Ex. A,
    Agreement Between the United States of America and China
    (“Executive Agreement”), ECF No. 11-2 ¶ 1.5). SCG reasons that
    the Court must resolve the conflict between the Executive
    Agreement and the District’s licensing laws in favor of the
    Executive Agreement because it is federal law to which state law
    must yield. See id. at 13 (citing Am. Ins. Ass’n v. Garamendi,
    
    539 U.S. 396
    , 425-27 (2003)).
    The Executive Agreement at issue here is the Agreement
    Between the Government of the United States of America and the
    Government of the People’s Republic of China on the Conditions
    of Construction of Diplomatic and Consular Complexes in the
    People’s Republic of China and the United States of America. See
    generally Executive Agreement, ECF No. 11-2. This agreement
    explicitly governs construction projects at the Chinese consular
    building located at 2300 Connecticut Avenue in Washington, D.C.
    Id. ¶¶ 1.5, 1.6. Having “entered into force” on August 20, 2009,
    see id. at 4; it is “to be treated with similar dignity” as any
    treaty, whose “supremacy . . . has been recognized from the
    beginning,” United States v. Pink, 
    315 U.S. 203
    , 223 (1942)
    (citation and internal quotation marks omitted). Accordingly,
    the Executive Agreement “is not and cannot be subject to any
    9
    curtailment or interference on the part of the several states,”
    and “state law must yield when it is inconsistent with or
    impairs the policy or provisions” of the agreement. 
    Id. at 223, 230-31
     (citations and internal quotation marks omitted).
    The Executive Agreement sets forth the two countries’
    responsibilities with respect to construction at the consular
    property. See generally Executive Agreement, ECF No. 11-2. Two
    sections are relevant to this dispute. The first section—on
    Construction Standards and Quality Safety Responsibilities—
    states: “The Construction Party 4 shall be responsible for the
    quality and safety of its project during construction. The Host
    Country 5 shall not require the Construction Party to enter into
    a contract with a local firm to supervise the construction.” Id.
    ¶ 5.3. The second section—on Personnel and Companies—states:
    “The Construction Party shall have the right to select project-
    related personnel and companies of its own choosing and of any
    nationality (including from the Host Country, the Construction
    Party or third countries) to perform all work in connection with
    its project.” Id. ¶ 9.1.
    SSI argues that these provisions do not absolve SCG from
    complying with District licensing laws. See Def.’s Reply, ECF
    No. 12 at 3. SCG interprets these provisions to “clearly mean[]
    4   The Construction Party here is China.
    5   The Host Country here is the United States.
    10
    that the Construction Party need not choose an existing local
    contractor to fulfill the work,” but “does not . . . in any way
    state that the contractor, once chosen and retained, is
    relieve[d] from the express obligation to properly register as a
    general contractor in the District of Columbia.” Id. The Court
    is unpersuaded by this construction. Under the Executive
    Agreement, China is wholly responsible for the quality and
    safety of all its consular construction projects, including the
    Project here. Executive Agreement, ECF No. 11-2 ¶ 5.3. The
    agreement therefore grants China wide latitude over its
    selection of contractors for its consular construction projects,
    specifying that China need not retain a “local firm” to
    supervise construction. Id. Imposing the District’s licensing
    requirements would effectively require China to engage a local
    general contractor and adhere to District safety standards. This
    result directly conflicts with the terms of the Executive
    Agreement.
    SSI’s remaining arguments are similarly unpersuasive.
    First, SCG contends that “the Executive Agreement repeatedly
    establishes that it is subject to the laws of the Host country.”
    Def.’s Reply, ECF No. 12 at 2-3 (citing Executive Agreement, ECF
    No. 11-2 ¶¶ 2.1, 3.2, 3.6, 4.1, 4.2, 5.3). This summary is
    misleading. The Executive Agreement makes clear that China must
    comply with federal and local regulations for its consular
    11
    construction projects but only in certain instances. See, e.g.,
    Executive Agreement, ECF No. 11-2 ¶¶ 4.1 (planning, design
    review, and permits), 5.1 (inspections of equipment and lines at
    utility interface points), 6.1 (use of temporary sites), 6.3
    (obtaining easements), 10.8 (storage, use, and disposal of
    hazardous materials), 12.4 (vehicle registration), 13.2 (local
    work hour restrictions). For example, China must comply with
    federal and local law in its installation and use of
    telecommunications equipment, id. ¶ 3.6; but at the same time,
    the agreement gives China complete discretion over its selection
    of utility and service providers, id. ¶ 3.5. The Executive
    Agreement does not contain any clear language requiring that
    China comply with federal or state licensing for general
    contractors, and the Court will not insert its own restriction.
    SSI also argues that another federal law—the Foreign
    Missions Act, 
    22 U.S.C. § 4301
     et seq.—applies here and requires
    China to comply with the District’s licensing laws in its
    consular construction projects. See Def.’s Mot., ECF No. 10-1 at
    11-12; Def.’s Reply, ECF No. 12 at 5. The Foreign Missions Act
    “‘was designed to provide the Secretary of State with the
    leverage necessary to remove unreasonable restraints and costs
    on United States missions abroad’ by giving the federal
    government a voice in local regulation of services provided to
    foreign missions within this country.” Sturdza v. Gov’t of
    12
    United Arab Emirates, No. CV 98-2051 (CKK), 
    1999 WL 35643442
    , at
    *4 (D.D.C. Dec. 22, 1999) (quoting Embassy of the People’s
    Repub. of Benin v. Dist. of Columbia Bd. of Zoning & Adjustment,
    
    534 A.2d 310
    , 314 (D.C. 1987)), aff’d in part, rev’d in part and
    question certified sub nom. Sturdza v. United Arab Emirates, 
    281 F.3d 1287
     (D.C. Cir. 2002), certified question answered, 
    11 A.3d 251
     (D.C. 2011). As relevant here, the Act provides that “[t]he
    Secretary [of State] shall require foreign missions to comply
    substantially with District of Columbia building and related
    codes in a manner determined by the Secretary to be not
    inconsistent with the international obligations of the United
    States.” 
    22 U.S.C. § 4306
    (g). However, it contains no provision
    regarding contractor licensing requirements. As the Sturdza
    court explained, the District’s building codes and licensing
    requirements “are separate and distinct.” Sturdza, 
    1999 WL 35643442
    , at *4. The Foreign Missions Act is thus inapplicable
    here.
    Third, SSI contends that the licensing laws must apply to
    SCG because the D.C. Code applies to other government
    construction projects. Def.’s Reply, ECF No. 12 at 4 (citing
    
    D.C. Mun. Regs. tit. 17, § 1735
    ); 
    id.
     at 6 (citing 
    D.C. Mun. Regs. tit. 17, § 3907.1
    ); cf. id. at 4 (discussing SCG’s
    registration and later correction of its registration). This
    argument ignores supremacy principles, which dictate that “state
    13
    law must yield when it is inconsistent with or impairs the
    policy or provisions” of federal law, including executive
    agreements. Pink, 
    315 U.S. at 230-31
    . SSI’s citation to Sturdza
    is equally unpersuasive. See Def.’s Reply, ECF No. 12 at 5. In
    that case, the district court ruled that an unlicensed architect
    could not bring her contract or quantum meruit claims against
    the United Arab Emirates for her work on the country’s embassy
    because she failed to comply with the District’s licensing
    requirements. Sturdza, 
    1999 WL 35643442
    , at *4. That dispute did
    not involve any executive agreement—and certainly not the
    Executive Agreement here. See generally 
    id.
     The Court therefore
    cannot borrow the Sturdza court’s reasoning.
    In sum, the Court concludes that the Executive Agreement
    grants China the discretion to retain a general contractor of
    its choice without regard to local licensing laws. Because the
    Executive Agreement constitutes federal law and prevails over
    state law, SCG may pursue its breach of contract claim despite
    having been unlicensed during the Project. Accordingly, the
    Court DENIES SSI’s Motion to Dismiss Count I of the Amended
    Complaint. 6
    6 The Court need not address SCG’s remaining contract defenses
    because SSI raises only the licensing issue in its Motion to
    Dismiss. Cf. Benton v. Laborers’ Joint Training Fund, 
    121 F. Supp. 3d 41
    , 51 (D.D.C. 2015) (“[I]t is a well-settled
    prudential doctrine that courts generally will not entertain new
    arguments first raised in a reply brief.” (citations and
    14
    B. SCG May Maintain Its Negligence Claim
    SSI next moves to dismiss Count II of the Amended
    Complaint, which alleges negligence, for two reasons. See Def.’s
    Mot., ECF No. 10-1 at 13-15. First, it argues that SCG has not
    adequately pleaded the existence of a duty to bring a negligence
    claim. See id. at 13-14. Second, SSI argues that the economic
    loss doctrine bars this claim. See id. at 14-15. For the reasons
    below, the Court DENIES SSI’s motion as to this claim.
    1. SCG Has Adequately Alleged That SSI Owed a Duty
    SSI first argues that the Court should dismiss the
    negligence claim because it “does not owe SCG an independent
    duty under the law of the District of Columbia.” Id. at 13.
    Under District of Columbia law, “for a plaintiff to recover in
    tort for conduct that also constitutes a breach of contract,
    ‘the tort must exist in its own right independent of the
    contract, and any duty upon which the tort is based must flow
    from considerations other than the contractual relationship.’”
    Attias v. CareFirst, Inc., 
    365 F. Supp. 3d 1
    , 18 (D.D.C. 2019)
    (quoting Choharis v. State Farm Fire & Cas. Co., 
    961 A.2d 1080
    ,
    1089 (D.C. 2008)), on reconsideration in part, 518 F. Supp. 3d
    internal quotation marks omitted)). Additionally, the Court will
    not address SSI’s argument, made in passing, that the Court
    should grant summary judgment because SSI has not presented any
    other arguments showing that it is entitled to judgment as a
    matter of law. See Fed. R. Civ. P. 56(a); see also Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 250 (1986).
    15
    43 (D.D.C. 2021). Here, SCG alleges that SSI owed a duty “to
    perform its work on the [P]roject in a skillful, careful,
    diligent, and workmanlike manner.” Am. Compl., ECF No. 9 ¶ 51.
    SSI contends that this is “a near textbook example of an
    unsupported legal conclusion” because SCG does not state “where
    this legal duty is derived from under [D.C.] law.” Def.’s Mot.,
    ECF No. 10-1 at 14. SSI thus concludes that its only legal duty
    to SCG arises from the contract and the parties’ contractual
    relationship. See 
    id.
    In its opposition briefing, SCG argues that SSI “owed . . .
    a duty to perform its work in a workmanlike manner.” Pl.’s
    Opp’n, ECF No. 11 at 26. Citing authority from the District of
    Columbia Court of Appeals (“D.C. Court of Appeals”), SCG
    explains that this duty “exists independently from the terms of
    the Subcontract Agreement.” 
    Id.
     (citing Ehrenhaft v. Malcolm
    Price, Inc., 
    483 A.2d 1192
    , 1200 (D.C. 1984)). SSI does not
    address this caselaw in its reply briefing. See Def.’s Reply,
    ECF No. 12 at 5-7.
    The Court is persuaded that SCG has adequately pleaded the
    existence of a duty. SSI is correct that “[t]he failure to
    perform a contractual obligation typically does not give rise to
    a cause of action in tort.” Attias, 365 F. Supp. 3d at 18
    (quoting Jones v. Hartford Life & Accident Ins. Co., 
    443 F. Supp. 2d 3
    , 5 (D.D.C. 2006)). However, District of Columbia law
    16
    has long “‘extended the tort liability for misfeasance to
    virtually every type of contract where defective performance may
    injure the promisee,’” thereby permitting a plaintiff who
    alleges a breach of contract to maintain a tort claim. See
    Ehrenhaft, 
    483 A.2d at 1200
     (quoting W. Prosser, Law of Torts §
    92, at 617 (4th ed. 1971)). Following this principle, the D.C.
    Court of Appeals has permitted negligence claims against
    contractors to proceed where plaintiffs allege a failure to
    perform work properly. See id. (collecting cases). Here, SCG
    alleges that SSI “(i) failed to complete its work on the Project
    in a timely manner and (ii) produced deficient and defective
    work on the Project, requiring a substitute contractor to repair
    and redo a substantial portion of the work SSI was obligated to
    complete.” Am. Compl., ECF No. 9 ¶ 52. Stated differently, SCG’s
    negligence claim is based on SSI’s alleged failure to perform
    work properly. This allegation is sufficient to bring a
    negligence claim under District of Columbia law.
    2. The Economic Loss Doctrine is Inapplicable
    SSI also argues that SCG’s negligence claim is barred by
    the economic loss doctrine. See Def.’s Mot., ECF No. 10-11 at
    14-15. Under District of Columbia law, this doctrine “bars
    recovery of purely economic losses in negligence, subject to
    only one limited exception where a special relationship exists.”
    Aguilar v. RP MRP Wash. Harbour, LLC, 
    98 A.3d 979
    , 986 (D.C.
    17
    2014). A special relationship exists where the defendant had an
    obligation to care for the plaintiff’s economic well-being or an
    obligation that implicated the plaintiff’s economic
    expectancies. Whitt v. Am. Prop. Constr., P.C., 
    157 A.3d 196
    ,
    205 (D.C. 2017) (quoting Aguilar, 
    98 A.3d at 985
    ).
    Here, the parties agree, as they must, that SCG seeks
    recovery of purely economic losses for its negligence claim. See
    Def.’s Mot., ECF No. 10-1 at 15; Am. Compl., ECF No. 9 ¶ 53.
    They dispute whether SCG has alleged a special relationship. SSI
    contends that SCG alleges that “the only relationship whatsoever
    between the parties is the December 2016 alleged agreement.”
    Def.’s Mot., ECF No. 10-1 at 15 (citing Am. Compl., ECF No. 9 ¶
    51 (“SSI was engaged to furnish and install a fire alarm system
    for the Project.”)). SCG rejects this interpretation of the
    Amended Complaint, see Pl.’s Opp’n, ECF No. 11 at 26-27;
    explaining that the relationship between contractor and
    subcontractor is a “paradigm” special relationship because SSI
    “had an obligation . . . that implicated SCG’s economic
    interests,” 
    id.
     at 27 (citing Whitt, 
    157 A.3d at 206
    ). SCG
    further argues that the parties were in a special relationship
    because they were in privity of contract. 
    Id.
     at 26 (citing
    Aguilar, 
    98 A.3d at 985
    ; Commonwealth Land Title Ins. Co. v. KCI
    Techs., Inc., 
    922 F.3d 459
    , 468 (D.C. Cir. 2019)).
    18
    The Court concludes that SCG has adequately alleged that
    the parties were in a special relationship. Admittedly, “there
    is limited legal authority in the District of Columbia
    addressing the factual circumstances that may give rise to a
    ‘special relationship.’” Heidi Aviation, LLC v. Jetcraft Corp.,
    
    573 F. Supp. 3d 182
    , 199 (D.D.C. 2021) (reviewing relevant
    cases). The existing caselaw, however, suggests that a special
    relationship exists where there is contractual privity or some
    other close nexus between the parties. Aguilar, 
    98 A.3d at
    985
    n.3 (citation omitted). Here, SCG has alleged that it was in
    privity of contract with SSI. Pl.’s Opp’n, ECF No. 11 at 27; Am.
    Compl., ECF No. 9 ¶ 16. This contract clearly implicated SCG’s
    economic expectancies. See Am. Compl., ECF No. 9 ¶¶ 34-41. The
    Court is persuaded that this is sufficient to plead a special
    relationship. Cf., e.g., Vantage Commodities Fin. Servs. I, LLC
    v. Willis Ltd., 
    531 F. Supp. 3d 153
    , 177–79 (D.D.C. 2021) (no
    “special relationship” because “[t]here was no ‘contractual
    privity or its equivalent’” between the parties); McDowell v.
    CGI Fed. Inc., No. CV 15-1157, 
    2017 WL 2392423
    , at *4–5 (D.D.C.
    June 1, 2017) (plaintiff did not adequately allege a “special
    relationship” because plaintiff did “not argue that she was in
    contractual privity, or its equivalent” with defendant).
    Because SCG has pleaded a special relationship between the
    parties, the economic loss doctrine does not apply. The Court
    19
    therefore DENIES SSI’s Motion to Dismiss Count II of the Amended
    Complaint.
    C. Venue is Proper in the District of Columbia
    Finally, SSI moves to dismiss this case for improper venue.
    Def.’s Mot., ECF No. 10-1 at 15-17. For the following reasons,
    the Court concludes that venue is proper in the District.
    Pursuant to 
    28 U.S.C. § 1391
    (b), a lawsuit “may be brought
    in” a judicial district (1) where “any defendant resides, if all
    defendants are residents of the State in which the district is
    located”; (2) where “a substantial part of the events or
    omissions giving rise to the claim occurred”; or (3) if there is
    no judicial district where the case may be brought as provided
    by the first two categories, where “any defendant is subject to
    the court’s personal jurisdiction.” 
    28 U.S.C. § 1391
    (b). “When
    venue is challenged, the court must determine whether the case
    falls within one of the three categories set out in § 1391(b).”
    Atl. Marine Constr. Co., 
    571 U.S. at 56
    .
    Here, SCG alleges that venue is proper in this judicial
    district because (1) “a substantial part of the events or
    omissions giving rise to the claim occurred” here, Am. Compl.,
    ECF No. 9 ¶ 14 (citing 
    28 U.S.C. § 1391
    (b)(2)); and (2) the
    District is “the exclusive venue for any dispute between the
    parties” under the Subcontract Agreement, id. ¶ 15. SSI argues
    that, “to the extent that the Court finds that the Project is
    20
    somehow exempt from [D.C.] regulations, that finding would
    remove any substantial nexus between this forum and the
    Project.” Def.’s Mot., ECF No. 10-1 at 17. This argument is
    unpersuasive. The Project was located in the District. Am.
    Compl., ECF No. 9 ¶ 16. The construction and contractual
    activity at issue all occurred in the District. Id. ¶¶ 16-42.
    The Court’s conclusion that the District’s licensing laws do not
    apply to SCG’s work on the Project does not change the fact that
    “a substantial part of the events or omissions giving rise to
    the claim occurred” in the District. 
    28 U.S.C. § 1391
    (b)(2).
    Venue is proper; accordingly, the Court DENIES SSI’s Motion to
    Dismiss for improper venue.
    V.   Conclusion
    For the foregoing reasons, the Court DENIES SSI’s Motion to
    Dismiss. See ECF No. 10.
    An appropriate Order accompanies this Memorandum Opinion.
    SO ORDERED.
    Signed:   Emmet G. Sullivan
    United States District Judge
    March 15, 2023
    21