Sunline Commercial Carriers, Inc. v. Citgo Petroleum Corporation , 206 A.3d 836 ( 2019 )


Menu:
  •            IN THE SUPREME COURT OF THE STATE OF DELAWARE
    SUNLINE COMMERCIAL                     §
    CARRIERS, INC.,                        §     No. 185, 2018
    §
    Plaintiff Below,                 §     Court Below: Superior Court
    Appellant,                       §     of the State of Delaware
    §
    v.                               §     C.A. No. N15C-03-051
    §
    CITGO PETROLEUM                        §
    CORPORATION,                           §
    §
    Defendants Below,                §
    Appellee.                        §
    Submitted: January 9, 2019
    Decided:   March 7, 2019
    Before STRINE, Chief Justice; VALIHURA and VAUGHN, Justices.
    Upon appeal from the Superior Court. REVERSED.
    Michael F. Bonkowski, Esquire, Nicholas J. Brannick, Esquire, Cole Schotz P.C.,
    Wilmington, Delaware; Ross A. Mortillaro, Esquire (Argued), Stinson Leonard
    Street LLP, Dallas, Texas, for Appellant, Sunline Commercial Carriers, Inc.
    Mary F. Dugan, Esquire, Young Conaway Stargatt & Taylor, LLP, Wilmington,
    Delaware; John Zavitsanos, Esquire, Debora Simon Pacholder, Esquire, and Edward
    Goolsby, Esquire (Argued), Ahmad, Zavitsanos, Anaipakos, Alavi & Mensing, P.C.,
    Houston, Texas, for Appellees, Citgo Petroleum Corporation.
    STRINE, Chief Justice:
    This litigation has lasted far longer than the contractual relationship that gave
    rise to it. In early 2013, an oil company, CITGO Petroleum Corp., engaged a
    trucking company, Sunline Commercial Carriers, Inc., to ship its product under what
    the parties call a Master Agreement, which was to be implemented by another
    agreement the parties call the Term Agreement, despite the fact that both contracts
    have the same title: Agreement for Motor Transportation Services.1 The Master
    Agreement was set to expire on December 31, 2014, but could be terminated by
    either party on 60 days’ notice. The Term Agreement “remain[ed] in effect until the
    Master Agreement is expired or terminated” but also contained another sentence
    stating that it was a “1 Year agreement with a start date of April 1, 2013.”2
    The Term Agreement required that CITGO ship a monthly minimum to
    Sunline, or compensate Sunline for failing to do so. But not long into their
    relationship, CITGO breached the agreement by failing to ship the monthly
    minimum, creating what the parties call a “shortfall.” After breaching, CITGO used
    its leverage to obtain concessions that allowed it to make up the shortfall at the end
    of the parties’ contractual relationship. According to Sunline, these concessions
    1
    App. to Opening Br. at A341 (Agreement for Motor Transportation Services (Jan. 9, 2013)); id.
    at A345 (Agreement for Motor Transportation Services (Mar. 23, 2013)). Although both
    agreements have the same name, the parties have given each agreement a name for litigation
    purposes. For the ease of the parties and the reader, we adopt these names.
    2
    Id. at A346.
    were procured based on CITGO’s assurances that it would continue the contractual
    relationship for another year.3
    But on March 31, 2014, CITGO sent Sunline a termination notice, stating
    “CITGO gives Sunline 60 day [sic] notice to cancel Motor Transportation Services
    Agreement. The transportation services, therefore will continue thru the month of
    May, ending on May 31st 2014.”4 Over the next two months, all of the Term
    Agreement’s specific provisions—including price—seemed to govern the parties’
    relationship. During this time, CITGO shipped enough product to Sunline to meet
    its previously accrued shortfalls. But if the Term Agreement’s minimum monthly
    requirement remained in place, CITGO failed meet the minimum and generated
    additional shortfalls. At the end of May, CITGO stopped using Sunline to ship oil.
    Sunline sued and eventually moved for summary judgment, arguing that the
    Term Agreement remained in effect until May 31, 2014; CITGO was therefore still
    liable for the shortfalls generated before the termination notice; and CITGO
    generated shortfalls in April and May. In response, CITGO argued that the Term
    Agreement ended on March 31, 2014, the day CITGO sent its termination notice;
    that only the Master Agreement continued through May 31, 2014; and as a result,
    3
    Id. at A841 (John Flinn affidavit).
    4
    Id. at A576 (email from Jones Khan to John Flinn (March 31, 2014)).
    2
    CITGO had no obligation to meet the Term Agreement’s minimum barrel
    requirements.
    On Sunline’s summary judgment motion, the Superior Court held, as a matter
    of law, that the Term Agreement ended on March 31, 2014.5 But that holding did
    not end the parties’ dispute. Under the Superior Court’s logic, the Term Agreement
    ended on March 31, 2014, and therefore, the Term Agreement’s monthly minimum
    provision had no effect during April and May 2014. Therefore, anything shipped
    after March 31, 2014 went towards satisfying CITGO’s shortfall liability. And
    because CITGO shipped enough oil in April and May to satisfy its previously
    accumulated shortfalls, the Superior Court entered judgment in favor of CITGO.6
    On appeal, Sunline challenges these rulings, arguing that the Superior Court’s
    contractual interpretation is inconsistent with the Term Agreement’s text, and that,
    in the alternative, the Term Agreement is ambiguous and parol evidence must be
    considered.
    In this opinion, we reverse. The Superior Court’s ruling—that the Term
    Agreement expired by its own terms on March 31, 2014—ignores the fact that the
    Term Agreement’s text states that its “terms shall remain in effect until the Master
    5
    Sunline Commercial Carries, Inc. v. CITGO Petroleum Corp. (Sunline Opinion), 
    2017 WL 6618886
    , at *7–8 (Del. Super. Ct. Dec. 27, 2017).
    6
    Sunline Commercial Carries, Inc. v. CITGO Petroleum Corp. (Sunline Order), No. N15C-03-
    051, slip op. at 1–2 (Del. Super. Ct. Mar. 13, 2018) (ORDER).
    3
    Agreement is expired or terminated.”7 As we have previously recognized, we must
    “give each provision and term effect, so as not to render any part of the contract
    mere surplusage.”8 If that contractual provision was given its clear effect, then the
    Term Agreement remained in effect, under CITGO’s own termination
    communication, until May 31, 2014.
    To us, it seems more linguistically likely that the Term Agreement was meant
    to continue in force as long as the Master Agreement did. In the context of the entire
    relationship, the expiration date is more easily read as obligating the parties to try to
    refresh the agreement, and if they failed to do so, then either party could terminate
    the entire relationship—by terminating the Master Agreement—with 60 days’
    notice. CITGO’s argument that a single sentence—that the Term Agreement is a “1
    Year agreement with a start date of April 1, 2013”9—read in isolation from the rest
    of the Term Agreement’s terms terminated the entire agreement on March 31, 2014
    is less textually reasonable.       Nonetheless, the Term Agreement does contain
    conceivably conflicting terms, which cannot be indisputably reconciled on the face
    of the contract, and is therefore ambiguous.10
    7
    App. to Opening Br. at A346.
    8
    Kuhn Constr., Inc. v. Diamond State Port Corp., 
    990 A.2d 393
    , 396–97 (Del. 2010).
    9
    App. to Opening Br. at A346.
    10
    Rhone-Poulenc Basic Chems. Co. v. Am. Motorist Ins. Co., 
    616 A.2d 1192
    , 1196 (Del. 1992)
    (“A contract is not rendered ambiguous simply because the parties do not agree upon its proper
    construction. Rather, a contract is ambiguous only when the provisions in controversy are
    4
    Because we reverse the Superior Court’s finding that the Term Agreement
    expired on March 31, 2014, we must also reverse its holding that the oil shipped in
    April and May satisfied CITGO’s shortfall liability.11 CITGO was to make up the
    shortfalls at the end of the contract.12 But whether the Term Agreement expired on
    March 31, 2014 is not clear on the contract’s face, and parol evidence must be
    considered to determine the parties’ intent.
    The Superior Court, however, failed to consider parol evidence because of its
    earlier finding that the Term Agreement expired, as a matter of law, on March 31,
    2014. The parol evidence makes summary judgment inappropriate as it supports the
    reasonableness of Sunline’s interpretation. For instance, CITGO’s termination
    notice suggests that the parties’ entire contractual relationship—including the Term
    Agreement’s terms—continued until May 31, 2014. In fact, the termination notice
    can be read to suggest that CITGO believed that the Term Agreement remained in
    effect until the Master Agreement expired, and that the termination notice served as
    the 60 days’ notice under the terms of both the Term Agreement and the Master
    Agreement. For these reasons, a genuine dispute of material fact exists, summary
    reasonably or fairly susceptible of different interpretations or may have two or more different
    meanings.”).
    11
    Sunline Order, slip op. at *1–2.
    12
    Although the parties dispute all of the material terms of this alleged oral agreement, see Opening
    Br. at 31–39, both concede that the agreement allowed CITGO to make up the shortfalls at some
    conception of the end of their contractual relationship. See App. to Opening Br. at A306 (Sunline’s
    Motion for Summary Judgment); App. to Answering Br. at B1046 (CITGO’s Answering Brief in
    Response to Sunline’s Motion for Summary Judgment).
    5
    judgment was therefore inappropriate, and Sunline is entitled to prove its claims at
    trial.
    I.
    CITGO sells petroleum.13 Sunline transports petroleum. And in 2012, the
    parties began discussing whether they could reach an agreement for Sunline to
    transport CITGO’s petroleum. Having reached an agreement on the initial terms of
    their relationship, on January 9, 2013, CITGO and Sunline entered into an
    “Agreement for Motor Transportation Services” (the “Master Agreement”).14 The
    Master Agreement expired on December 31, 2014, but either party could terminate
    the agreement on 60 days’ notice.15 Although Sunline would provide petroleum
    transportation services to CITGO under the Master Agreement, that agreement set
    forth only the broad terms of the parties’ relationship, such as the amount of
    insurance Sunline was required to maintain.16 It was silent on key commercial terms,
    including price and quantity.
    13
    These facts are undisputed, supported by the appellate record, and primarily taken from the
    Superior Court’s opinion. See Sunline Opinion, 
    2017 WL 6618886
    , at *1–5.
    14
    App. to Opening Br. at A344 (Agreement for Motor Transportation Services (January 9, 2013)).
    15
    
    Id.
     at A342–44 (“This Agreement shall commence on the Effective Date and shall continue in
    full force and effect until December 31, 2014, unless this Agreement is terminated by either party
    at any time and for any reason, with or without cause, upon sixty (60) days written notice to the
    other party.”).
    16
    See 
    id.
     at A342.
    6
    Two months later, on March 18, 2013, those terms were filled in when Sunline
    and CITGO agreed to the “Agreement for Motor Transportation Service” (the “Term
    Agreement”).17       The Term Agreement incorporated the Master Agreement by
    reference,18 but the Term Agreement controlled any inconsistency between the two
    contracts.19 As noted earlier, the formal name of both the Master Agreement and the
    Term Agreement is confusingly the same: “Agreement for Motor Transportation
    Services.”20
    The Term Agreement required CITGO to provide Sunline with a minimum
    amount of petroleum to transport each month. If CITGO delivered fewer barrels
    than the monthly minimum, then a “shortfall” was created, and CITGO would be
    obligated to pay Sunline about $4.26 per shortfall barrel.21 Otherwise, the price
    CITGO paid Sunline was based on the number of miles Sunline transported the
    petroleum.22 Critical to this dispute, the Term Agreement also provided various
    mechanisms to end the parties’ relationship. Those terms were:23
    17
    See 
    id.
     at A345.
    18
    
    Id.
     at A345 (“The terms and conditions of the Agreement for Motor Transportation Services
    between the parties dated January 9, 2013 (the ‘Master Agreement’) shall apply to this Agreement
    and are incorporated herein by reference.”).
    19
    
    Id.
     (“To the extent of any inconsistent or conflicting terms between this Agreement and the
    Master Agreement, this Agreement shall govern and control.”).
    20
    See 
    id.
     at A341, 345.
    21
    
    Id.
     at A346.
    22
    
    Id.
     The pricing scale increased the cost of transportation as the mileage increased. For instance,
    if Sunline transported the oil 200 miles, Sunline would be paid $5.34 per barrel. But if Sunline
    transported the oil 300 miles, it would be paid $7.37 per barrel.
    23
    We have attempted to replicate the formatting of the actual agreement.
    7
    Both parties, CITGO and Sunline, agree that the following
    terms shall remain in effect until the Master Agreement is
    expired or terminated.
    Term of Agreement                 1 Year agreement with a start
    date of April 1, 2013. Both
    parties agree to review terms
    60 days prior to expiration
    date and review pricing and
    volumes. If both parties agree
    on terms and volumes, this
    Agreement will be renewed
    with the agreed upon start date
    and term of agreement.
    ...
    Termination                       Termination of the Agreement
    by either party must be given
    at least 60 days prior to the
    expiration of the Agreement in
    writing.24
    Things went smoothly until, in June 2013, CITGO failed to deliver the
    minimum monthly volume of petroleum to Sunline. Although the Term Agreement
    required CITGO to deliver at least 240,000 barrels to Sunline in June, CITGO
    delivered only 142,405 barrels, generating a 97,595-barrel shortfall.25
    When Sunline invoiced CITGO for the June shortfall, CITGO asked if Sunline
    would “add” the shortfalls to “the end of the contract.”26 During the negotiations
    24
    
    Id.
     at A345–46.
    25
    Sunline Opinion, 
    2017 WL 6618886
     at *1.
    26
    App. to Opening Br. at A434 (email from Jones Khan to John Flinn (Aug. 13, 2013)).
    8
    about the June shortfalls, CITGO continued to accrue shortfalls in July, August, and
    September, and the parties continued to discuss how to handle them. In late
    September 2013, Sunline sent CITGO an invoice for the June, July, and August
    shortfalls, requesting 30% of the amount due immediately and moving 70% “to the
    end of the contract.”27 Although CITGO acknowledged receipt of the invoice, by
    November 15, 2013 CITGO had still not paid any of the shortfall amount due to
    Sunline.28
    In December 2013, Sunline sent another invoice to CITGO, requesting 20%
    of the shortfall for June, July, August, and September. According to Sunline’s
    president, Sunline agreed to push out some of CITGO’s payments because it wanted
    CITGO to renew the contract.29 CITGO paid 20% of the then outstanding shortfalls
    on December 26, 2013; the remaining shortfalls were to be satisfied at “the end of
    the Contract.”30
    CITGO nevertheless continued to generate shortfalls in December of 2013
    and February of 2014. When Sunline began to discuss these shortfalls with CITGO,
    27
    
    Id.
     at A520 (email from John Flinn to Jones Khan (Sept. 26, 2013)).
    28
    Opening Br. at 10.
    29
    App. to Opening Br. at A840–42 (Affidavit of John Flinn (May 15, 2017)) (“On December 10,
    2013, after the call with Michael Barrett and Jones Khan, I sent an e-mail to several Sunline
    employees informing them of my understanding of the call. Specifically, my understanding was
    that in exchange for allowing CITGO to pay 20% of its shortfall obligation now, with the
    remaining 80% pushed to a later date, CITGO would renew the Contract for another year, until
    May 2015.”).
    30
    
    Id.
     at A842.
    9
    Sunline allegedly agreed that CITGO could pay 20% of the December shortfall now
    and 80% at the end of the contract, but Sunline required CITGO to pay the February
    shortfall in full.31 CITGO also generated a shortfall in March 2014, and Sunline
    required CITGO to pay it in full too.32 Ultimately, CITGO paid Sunline for 20% of
    the December shortfall and all of the February and March shortfalls.33
    Shortcutting the parties’ ongoing negotiations over the shortfalls, on March
    31, 2014, CITGO sent Sunline a 60-day cancellation notice, stating that “CITGO
    Petroleum Corporation gives Sunline Commercial Carriers Inc. 60 day [sic] notice
    to cancel Motor Transportation Services Agreement. The transportation services,
    therefore will continue thru the month of May, ending on May 31 st 2014.”34
    Although both contracts are titled “Agreement for Motor Transportation Services,”
    the termination notice canceled the “Motor Transportation Services Agreement.”
    Logically, this slight change appears to just be a way of referring to both the Term
    Agreement and the Master Agreement, and the next sentence’s reference to the
    “transportation services” makes it reasonable to read the notice as applying to both
    of the contracts that were involved in the performance of these services. Therefore,
    at best for CITGO, its notice is unclear as to whether it was terminating both
    31
    Id.; Opening Br. at 10–11.
    32
    App. to Opening Br. at A843.
    33
    Opening Br. at 10–12.
    34
    App. to Opening Br. at A576 (email from Jones Khan to John Flinn (March 31, 2014)).
    10
    agreements or just one (and if just one which one). The termination notice also gave
    60 days’ notice, the time frame for terminating both the Term Agreement35 and the
    Master Agreement.36
    At this point, CITGO had accumulated a 337,969 barrel shortfall. 37 CITGO
    continued to ship oil through Sunline during both April and May, shipping 211,163
    and 147,782 barrels, respectively, during those two months, over 20,000 barrels
    more than the previously accumulated shortfall.38 And CITGO paid Sunline for the
    April and May volumes based on the Term Agreement’s pricing formula. At the end
    of May, CITGO stopped using Sunline to transport petroleum.
    On August 11, 2014, Sunline sent CITGO a breach of contract notice, stating
    that “[i]n June, July, August, September and December 2013, as well as February,
    March, April and May 2014, Citgo failed to purchase the agreed minimum number
    of barrels, and has failed to fully compensate Sunline for the cumulative outstanding
    shortfall, thereby breaching the Contract.”39 Sunline provided CITGO with the
    35
    
    Id.
     at A348 (“Termination of the Agreement by either party must be given at least 60 days prior
    to the expiration of the Agreement in writing.”)
    36
    
    Id.
     at A343 (“This Agreement shall commence on the Effective Date and shall continue in full
    force and effect until December 31, 2014, unless this Agreement is terminated by either party at
    any time and for any reason, with or without cause, upon sixty (60) days prior written notice to the
    other party.”).
    37
    Sunline Opinion, 
    2017 WL 6618886
    , at *1.
    38
    App. to Opening Br. at A885 (Updated Sunline Shortfall Spreadsheet).
    39
    
    Id.
     at A612–13 (Letter from Sunline’s counsel to Citgo (Aug. 11, 2014)).
    11
    required 30 days to cure the breach by compensating Sunline for the shortfalls,40 but
    CITGO failed to cure.
    Sunline then sued CITGO in the Superior Court on March 6, 2015 claiming
    breach of contract. CITGO answered and counter-claimed, requesting an accounting
    and alleging (i) breach of contract; (ii) breach of the implied covenant of good faith
    and fair dealing; and (iii) unjust enrichment.41        The Superior Court dismissed
    CITGO’s request for an accounting, but not its other claims.42 After the completion
    of discovery, the parties filed cross-motions for summary judgment.43 CITGO
    eventually abandoned its counterclaims against Sunline,44 leaving only the cross-
    motions for summary judgment on the breach of contract claim.45
    In moving for summary judgment, Sunline argued that, during the last two
    months of the parties’ relationship, the Term Agreement’s terms remained in force.
    As such, CITGO was obligated to ship 240,000 barrels per month, and therefore
    CITGO generated shortfalls in April and May.46 Although CITGO paid for the
    40
    
    Id.
    41
    
    Id.
     at A116–19 (Defendant Citgo Petroleum Corporation’s Answer with Affirmative Defenses
    and Counterclaims (Apr. 28, 2015)).
    42
    Opening Br. at 1.
    43
    
    Id.
     at 1–2.
    44
    Sunline Opinion, 
    2017 WL 6618886
     at *4 (“On November 30, 2017, the Defendant abandoned
    its counterclaims against Plaintiff.”).
    45
    
    Id.
     (“On November 30, 2017, the Defendant abandoned its counterclaims against Plaintiff,
    therefore making Plaintiff’s Motion for Summary Judgment regarding Defendant’s counterclaims
    moot. This is the Court’s decision on the parties’ remaining cross-motions for summary
    judgment.”).
    46
    CITGO sent 211,163 and 147,782 barrels to Sunline in April and May, respectively. App. to
    Opening Br. at A885.
    12
    volume it sent through Sunline in April and May, it did not pay Sunline’s claimed
    April and May shortfalls and failed to pay the remaining 80% of the June, July,
    August, September, and December shortfalls, which would remain outstanding if
    CITGO was obligated to ship 240,000 barrels to Sunline in April and May.
    In response, CITGO argued that the Term Agreement—by its own terms—
    expired on March 31, 2014, and only the Master Agreement continued in force
    through May 31, 2014. Thus, CITGO argued that it did not accumulate shortfalls in
    April and May, and satisfied the previously accumulated shortfalls during those
    months.
    In its opinion denying Sunline’s motion for summary judgment (and
    effectively granting CITGO summary judgment),47 the Superior Court reviewed the
    Term Agreement’s text, determined that it was “not so ambiguous to require
    resorting to extrinsic evidence,” and concluded that the Term Agreement expired on
    March 31, 2014.48 In its analysis, the Superior Court focused on the one-year term
    clause, and did not discuss the clause that kept the Term Agreement’s terms in effect
    until the Master Agreement expired:
    [T]he Court finds Plaintiff and Defendant had a one-year
    agreement from April 1, 2013 to March 31, 2014 for
    Plaintiff to provide transportation services for a
    guaranteed minimum amount of petroleum products
    which Defendant was obligated to provide. However, if
    47
    See Sunline Opinion, 
    2017 WL 6618886
     at *9.
    48
    Id. at *6.
    13
    there was no agreement to modify the Term Agreement
    before March 31, 2014, the Term Agreement by its own
    terms expired. Therefore, the Court finds that as of March
    31, 2014, CITGO had no obligation to supply petroleum
    products to Plaintiff nor did Plaintiff have any obligation
    to provide transportation for those products. The Court
    finds the Plaintiff’s 60–day notice argument from the
    “Termination” provision of the Term Agreement is simply
    unprevailing. Once the one-year term ended, so did any
    obligation under the Term Agreement. In this case, neither
    party “terminated” the Term Agreement, it simply ended
    by its own terms.49
    Based on finding that the Term Agreement unambiguously ended on March 31,
    2014, the Superior Court then concluded that “the 60 days’ notice provided by
    CITGO . . . only related to its continued relationship under the Master Agreement,”
    and because the Master Agreement did not provide pricing terms, CITGO “was
    under no obligation to meet monthly minimum barrel requirements in April or May
    of 2014 pursuant to that document.”50
    But that did not end the Superior Court’s inquiry. The Superior Court went
    on to find that “[b]ecause CITGO continually failed to meet minimum barrel
    requirements set forth in the Term Agreement[,] [i]t appears this caused the parties
    to orally agree to a continuation of the relationship for an additional two months.”51
    The terms of this apparent oral agreement also needed to be determined, but the
    49
    Id. at *7.
    50
    Id.
    51
    Id. at *8 (emphasis added).
    14
    Superior Court rejected Sunline’s argument that the Term Agreement’s shortfall
    requirements continued as part of the alleged oral agreement:
    The only legal basis for Plaintiff arguing that Defendant
    had a continuing obligation in April and May of 2014 to
    continue to meet the minimum requirements was its
    interpretation of the Term Agreement and the 60–day
    notice language in the “Termination” provision. As
    mentioned previously, Plaintiff asserted that since the 60–
    day notice was not given until March 31, 2014, the
    minimum obligation set forth in the Term Agreement
    continued into April and May. Unfortunately for Plaintiff,
    that interpretation of the Term Agreement has been
    rejected by the Court. Since the Court has held the end of
    the Term Agreement to be March 31, 2014, all that
    remains is an undisputed agreement between the parties
    that during the months of April and May of 2014, CITGO
    would make up the shortage during these months either by
    providing petroleum products for Plaintiff to transport or
    monetarily making up the difference.52
    According to the Superior Court, this was a sufficient basis to enter summary
    judgment because “ample correspondence between the parties . . . demonstrate[s] a
    willingness and a mutual assent to move the 2013 shortages to the end of the Term
    Agreement.”53 Thus, after the Superior Court’s summary judgment ruling, the only
    remaining determination was “limited to the extent of the shortages and what
    monetary payments have been made to compensate Plaintiff for them.”54
    52
    Id. (emphasis added).
    53
    Id.
    54
    Id.
    15
    Both parties filed post-decision motions requesting clarification of the
    Superior Court’s ruling.55 After a hearing, the Superior Court issued an order,
    finding that (i) CITGO was not obligated to deliver minimum monthly volume to
    Sunline for April and May; (ii) CITGO supplied Sunline with barrels in excess of
    the existing shortfall in April and May; and thus (iii) CITGO “made up” its shortfalls
    in April and May, “resolv[ing] the outstanding issues left from the Court’s [summary
    judgment] decision.”56 Based on that analysis, the Superior Court issued a final
    judgment in favor of CITGO on Sunline’s claims, and Sunline timely appealed.
    II.
    “We review the Superior Court’s grant of summary judgment de novo.”57 A
    grant of summary judgment is appropriate only when “there is no genuine issue as
    to any material fact and the moving party is entitled to judgment as a matter of
    law.”58 Questions of contract interpretation are also reviewed de novo.59
    III.
    The key issue the parties dispute is when the Term Agreement ended. If, as
    the Superior Court found, there is no material dispute of fact that the Term
    Agreement ended on March 31, 2014, then the April and May oil shipments satisfied
    55
    Sunline Order, slip op. at *1–2; Opening Br. at 3.
    56
    Sunline Order, slip op. at *1–2.
    57
    GMG Capital Invs., LLC v. Athenian Venture Partners I, L.P., 
    36 A.3d 776
    , 779 (Del. 2012).
    58
    AeroGlobal Capital Mgmt., LLC v. Cirrus Indus., Inc., 
    871 A.2d 428
    , 443 (Del. 2005) (quoting
    Del. Super. Ct. Civ. R. 56).
    59
    GMG Capital Invs., 
    36 A.3d at 779
    .
    16
    CITGO’s previous shortfall liability. But if there is a triable question of fact as to
    whether the Term Agreement expired on May 31, 2014, as Sunline argues, then
    summary judgment was inappropriately entered, and Sunline is entitled to a trial. If
    Sunline is correct, then CITGO continued to accumulate shortfalls in April and May
    and failed to satisfy its previous shortfall liability.
    On appeal, Sunline first challenges the Superior Court’s interpretation of the
    Term Agreement, arguing that the Superior Court misinterpreted the Term
    Agreement by finding that it unambiguously terminated on March 31, 2014. We
    agree and reverse. The Term Agreement is ambiguous, and the parties are entitled
    to a trial where they can attempt to prove, using parol evidence, their interpretation
    of the contract.60
    Sunline’s second issue on appeal—that the Superior Court erred by finding
    that Sunline and CITGO had an undisputed agreement that permitted CITGO to
    make up the shortfalls in April and May 2014—is bound up in Sunline’s first issue
    on appeal. The parties agreed that CITGO would make up the shortfalls at the end
    of the contract. Therefore, if the Term Agreement ended on March 31, 2014, as the
    Superior Court found, then any oil shipped during April and May would satisfy
    60
    GMG Capital Invs., LLC v. Athenian Venture Partners I, L.P., 
    36 A.3d 776
    , 783 (“But, where
    reasonable minds could differ as to the contract’s meaning, a factual dispute results and the fact-
    finder must consider admissible extrinsic evidence.”); see also 
    id.
     at 783 n.27 (“When, in contrast,
    contractual texts are deemed ambiguous, the resolution of the ambiguity becomes a trial issue for
    the jury.”) (quoting Lawrence M. Solan, Pernicious Ambiguity in Contracts and Statutes, 79 CHI.-
    KENT L. REV. 859, 862 (2004)).
    17
    CITGO’s shortfall liability. But the Term Agreement is ambiguous and might not
    have expired on March 31, 2014. Thus, the Superior Court also erred by holding
    that any oil shipped during April and May satisfied CITGO’s shortfall liability and
    parol evidence must be considered to determine when the Term Agreement ended.
    A.
    To determine what contractual parties intended, Delaware courts start with the
    text.61 “When the contract is clear and unambiguous, we will give effect to the plain-
    meaning of the contract’s terms and provisions,” without resort to extrinsic
    evidence.62 To aid in the interpretation of the text’s meaning, “Delaware adheres to
    the ‘objective’ theory of contracts, i.e. a contract’s construction should be that which
    would be understood by an objective, reasonable third party.”63 The contract must
    also be read as a whole, giving meaning to each term and avoiding an interpretation
    61
    See Twin City Fire Ins. Co. v. Delaware Racing Ass’n, 
    840 A.2d 624
    , 628 (Del. 2003) (“The
    [contract] analysis starts with the language.”).
    62
    Osborn ex rel. Osborn v. Kemp, 
    991 A.2d 1153
    , 1159–60 (Del. 2010).
    63
    
    Id.
     (quoting NBC Universal v. Paxson Commc’ns, 
    2005 WL 1038997
    , at *5 (Del.Ch. Apr. 29,
    2005)).
    18
    that would render any term “mere surplusage.”64 But general terms of the contract
    must yield to more specific terms.65
    If, after applying these canons of contract interpretation, the contract is
    nonetheless “reasonably susceptible [to] two or more interpretations or may have
    two or more different meanings,”66 then the contract is ambiguous and courts must
    resort to extrinsic evidence to determine the parties’ contractual intent.67 Here, the
    contract’s terms contradict each other, are susceptible to two meanings, and are thus
    ambiguous.68
    64
    Osborn, 
    991 A.2d at
    1159–60 (quoting Kuhn Construction, Inc. v. Diamond State Port Corp.,
    
    2010 WL 779992
    , *2 (Del. Mar. 8, 2010)); see also RESTATEMENT (SECOND) OF CONTRACTS § 203
    (“In the interpretation of a promise or agreement or a term thereof, the following standards of
    preference are generally applicable: (a) an interpretation which gives a reasonable, lawful, and
    effective meaning to all the terms is preferred to an interpretation which leaves a part unreasonable,
    unlawful, or of no effect.”); id. cmt. b (“Since an agreement is interpreted as a whole, it is assumed
    in the first instance that no part of it is superfluous.”).
    65
    DCV Holdings, Inc. v. ConAgra, Inc., 
    889 A.2d 954
    , 961 (Del. 2005) (“Specific language in a
    contract controls over general language, and where specific and general provisions conflict, the
    specific provision ordinarily qualifies the meaning of the general one.”); see also RESTATEMENT
    (SECOND) OF CONTRACTS § 236(c) (“Where there is an inconsistency between general provisions
    and specific provisions, the specific provisions ordinarily qualify the meaning of the general
    provisions.”).
    66
    Kaiser Alum. Corp. v. Matheson, 
    681 A.2d 392
    , 395 (Del.1996).
    67
    SI Mgmt. L.P. v. Wininger, 
    707 A.2d 37
    , 43 (Del. 1998) (“[I]f there existed an ambiguous
    provision in a negotiated bilateral agreement, extrinsic evidence should be considered if it would
    tend to help the court interpret such a provision.”).
    68
    CITGO asserts that whether the contract is ambiguous is not properly before this Court because
    Sunline did not argue that the contract was ambiguous below. Answering Br. at 24. But whether
    a contract is unambiguous is a question of law; this Court cannot find an ambiguous contract
    unambiguous because each party interprets the contract differently to find it unambiguous. Indeed,
    in many contract disputes, both parties argue for different interpretations, but claim that the
    contract is unambiguous. See Motorola, Inc. v. Amkor Techs., Inc., 
    849 A.2d 931
    , 937–38 (Del.
    2004) (finding a contract ambiguous despite the fact that both parties argued that it was
    unambiguous).
    19
    The Term Agreement first states that “the following terms shall remain in
    effect until the Master Agreement is expired or terminated.”69 Because the Master
    Agreement terminated on May 31, 2014,70 this clause suggests that the Term
    Agreement expired on May 31, 2014. But the Term Agreement’s very next clause
    states that the Agreement is a “1 Year agreement with a start date of April 1, 2013,”
    necessarily implying that the Term Agreement expires on March 31, 2014, one year
    after the start date.71 So which governs, which controls? Both terms are clear in
    isolation; neither is more general or specific than the other; and reading one to
    control would cause the other to be a mere surplusage. In isolation, they create an
    ambiguity.
    But we must read the contract as a whole. Unfortunately, the rest of the Term
    Agreement does not definitively resolve this contradiction. After specifying a one-
    year term, the Term Agreement goes on to say that “[b]oth parties agree to review
    terms 60 days prior to expiration date and review pricing and volumes. If both
    parties agree on terms and volumes, this Agreement will be renewed with the agreed
    upon start date and term of agreement.”72
    69
    App. to Opening Br. at A346.
    70
    Because the Master Agreement expired on December 31, 2014 but could be terminated upon 60
    days’ notice, the parties do not dispute that the Master Agreement terminated on May 31, 2014.
    71
    App. to Opening Br. at A346.
    72
    
    Id.
    20
    To our minds, this language suggests that the one-year term is more of a nudge
    for the parties to reevaluate their relationship. That is, the 60-day provision suggests
    that the parties will review pricing terms 60 days before the Term Agreement’s one-
    year anniversary. But if this pricing review breaks down, then based on the first
    clause—which keeps the Term Agreement’s terms in effect so long as the Master
    Agreement was in effect—the parties can terminate the complete relationship upon
    60 days’ notice.
    This reading of the Term Agreement is supplemented by another part of the
    Term Agreement, which states that “[t]ermination of the Agreement by either party
    must be given at least 60 days prior to the expiration of the Agreement in writing.”73
    That clause suggests that 60 days’ notice is required to terminate and aligns the Term
    Agreement’s termination notice—60 days—with the Master Agreement’s
    termination provision, which also allows for the Master Agreement to be terminated
    on 60 days’ notice.74 Put another way, if the parties cannot reach a mutually
    beneficial pricing agreement after the Term Agreement’s first year of operation, then
    the Term Agreement is placed on “life support.” The Term Agreement still remains
    in effect until the Master Agreement expires or is terminated, but the parties are on
    73
    
    Id.
     at A348.
    74
    
    Id.
     at A342–44.
    21
    notice that they no longer have a mutually beneficial agreement and can thus
    terminate the entire arrangement by terminating the Master Agreement.
    Not only is this interpretation supported by the text, but it makes commercial
    sense too. Arranging for the capacity to haul thousands of barrels of petroleum, as
    Sunline had to do, requires a substantial investment in shipping capacity, which
    would subject it to losses if the contract ended abruptly. Likewise, CITGO had to
    get its product to market, and an abrupt termination by Sunline could injure it for
    obvious reasons.        Because both parties invested substantial time, assets, and
    logistical capacity in creating a mutually beneficial relationship, this reading, in
    which the Term Agreement and Master Agreement both end simultaneously after 60
    days’ notice, allows each party time to reallocate resources or find alternative
    arrangements in an orderly fashion. Therefore, the mix of practical and textual
    support also supports the reasonableness of Sunline’s interpretation.
    CITGO argues that although the Term Agreement must “remain in effect until
    the Master Agreement is expired or terminated,”75 that clause, along with the rest of
    the Term Agreement, nevertheless expires on March 31, 2014.76 To us, CITGO’s
    argument relies on one clause read in isolation and seems strained. But we cannot
    rule it out as a possible reading of the Term Agreement’s text because we must give
    75
    
    Id.
     at A346.
    76
    Answering Br. at 18–33.
    22
    credit to each clause in the contract.77             And although Sunline’s reading is a
    reasonable one, it still is in arguable tension with the one-year term language. The
    Term Agreement is therefore ambiguous on its face, and parol evidence must be
    considered to determine the parties’ intent.78
    B.
    Because the Superior Court found that the Term Agreement unambiguously
    terminated on March 31, 2014, it also held that CITGO satisfied its shortfall liability
    by making up the shortfalls during April and May.79 We also reverse that finding.
    Both parties concede that CITGO was to make up the shortfalls at the end of
    their contractual relationship.80 But CITGO says the shortfalls were to be made up
    after the Term Agreement was terminated (on March 31, 2014, in its view), while
    the Master Agreement was still in effect (until May 31, 2014 under its interpretation).
    By contrast, Sunline says that shortfalls were to be made up after both the Term
    Agreement and the Master Agreement were terminated (on May 31, 2014). Whether
    CITGO could make up its shortfall liability in April and May then depends on when
    77
    Osborn ex rel. Osborn v. Kemp, 
    991 A.2d 1153
    , 1159–60 (Del. 2010).
    78
    Salamone v. Gorman, 
    106 A.3d 354
    , 374 (Del. 2014) (“The standard for interpreting ambiguous
    contracts is well settled: ‘If the contract is ambiguous, a court will apply the parol evidence rule
    and consider all admissible evidence relating to the objective circumstances surrounding the
    creation of the contract.’”) (quoting In re Mobilactive Media, LLC, 
    2013 WL 297950
    , at *15 (Del.
    Ch. Jan. 25, 2013)).
    79
    See Sunline Order, slip op. at *1–2.
    80
    App. to Opening Br. at A306 (Sunline’s Motion for Summary Judgment) (“In December 2013,
    the Parties ultimately resolved that CITGO would pay 20% immediately with 80% being made up,
    in barrels or cash, at a later date at ‘the end of the Contract.’”); App. to Answering Br. at B1046
    (CITGO’s Answering Brief in Response to Sunline’s Motion for Summary Judgment).
    23
    the Term Agreement terminated. Because the Superior Court found that, as a matter
    of law, the Term Agreement terminated on March 31, 2014, it naturally concluded
    that the oil shipped during April and May satisfied CITGO’s shortfall liability under
    that expired contract. But the Term Agreement is ambiguous, and therefore parol
    evidence must be considered to determine when it terminated. The Superior Court,
    however, never considered parol evidence.
    Summary judgment for CITGO might have been appropriate if all the parol
    evidence pointed in one direction and conclusively resolved the ambiguity in
    CITGO’s favor, as a matter of law. That is, if the parol evidence left “no genuine
    issue as to any material fact,” then this Court may still affirm the Superior Court. 81
    But parol evidence in the record supports Sunline’s interpretation that the Term
    Agreement and the Master Agreement expire together, and creates an issue of fact
    to be resolved at trial.
    First, CITGO’s internal understanding of the Term Agreement’s terms, while
    it was in place, supports Sunline’s textual argument that 60 days’ notice was required
    to terminate it. For instance, an internal CITGO presentation emphasized that
    CITGO must provide a “cancellation notice 60 days prior [to the termination of the
    81
    Del. Super. Ct. Civ. R. 56.
    24
    Term Agreement] or agreement renews another year.”82 Likewise, internal CITGO
    email correspondence suggested that they thought 60 days’ notice was required to
    terminate the contract.83 This parol evidence suggests that before CITGO ever tried
    to terminate the Term Agreement, its internal understanding was that 60 days’ notice
    was required.
    But the most obvious piece of evidence suggesting that the Term Agreement
    and the Master Agreement expire together is the termination notice CITGO provided
    to Sunline on March 31, 2014, the day the Term Agreement was set to expire under
    CITGO’s interpretation.         CITGO’s termination notice informed Sunline that
    “CITGO Petroleum Corporation gives Sunline Commercial Carriers Inc. 60 day [sic]
    notice to cancel Motor Transportation Services Agreement.”84 This first clause is
    inherently ambiguous. For starters, neither the Master Agreement nor the Term
    Agreement is entitled the “Motor Transportation Services Agreement.” In fact, both
    the Master Agreement and the Term Agreement are entitled the “Agreement for
    Motor Transportation Services,”85 a reality that by itself tends to support Sunline’s
    argument that the Term Agreement was to remain in effect until the entire
    contractual relationship under that common name expired. Parties are unlikely to
    82
    App. to Opening Br. at A451 (CPC Endorsement of Sunline Trucking Amendment to Master
    Transportation Services Agreement (Oct. 2013)) (emphasis added).
    83
    
    Id.
     at A380 (Email from Becky Murchison to Jones Khan (July 25, 2013)) (“To terminate at the
    expiration of the contract we need to give 60 days [sic] notice.”).
    84
    
    Id.
     at A576 (email from Jones Khan to John Flinn (March 31, 2014)).
    85
    
    Id.
     at A341, 345.
    25
    give two agreements the same name unless they intend for them to be substantially
    related to and dependent on one another.
    To this point, CITGO’s use of a proxy for the formal name of both the Term
    Agreement and the Master Agreement in the termination notice can be reasonably
    read as meaning that the termination notice applied to the parties’ entire contractual
    relationship and therefore both contracts would terminate in 60 days on May 31,
    2014. It may be that CITGO meant the termination notice to apply to only one of
    the agreements, that both have the same name, and that the missing “s” that would
    make “agreement” plural was intentional. But, if so, the notice is at best ambiguous
    because it does not specify which agreement it was terminating.
    And importantly, the termination notice’s next sentence states that, “[t]he
    transportation services[ ] therefore will continue thru the month of May, ending on
    May 31st 2014.”86 This not only seems to imply that CITGO is terminating the
    parties’ entire contractual relationship as of May 31, 2014, but can also be read as
    acknowledging the primacy of the first sentence in the Term Agreement, which
    states that the Term Agreement “remains in effect until the Master Agreement is
    expired or terminated.”87
    86
    
    Id.
     at A576 (email from Jones Khan to John Flinn (March 31, 2014)).
    87
    
    Id.
     at A346.
    26
    Alternatively, this last clause can also be reasonably read as an offer to extend
    the Term Agreement through May 31, 2014; an offer that Sunline accepted by
    performance.88 The Term Agreement allows for such an extension.89 And because
    the Master Agreement does not provide price terms for transportation services, the
    extension of those price terms would be necessary if the transportation services were
    to continue for another two months. Indeed, the Term Agreement’s pricing terms
    continued to govern the parties’ relationship in April and May, suggesting an
    extension of the Term Agreement. On a cold summary judgment record, it also must
    be deemed uncoincidental that CITGO sent this notice extending the parties’
    relationship to May 31, 2014 on March 31, 2014, the last day of the Term
    Agreement’s existence under its interpretation. That timing suggests that even if
    CITGO believed that the Term Agreement was set to expire at day’s end on March
    31, 2014, it intended to extend the entire relationship—including the Term
    Agreement—until May 31, 2014.
    Other parol evidence supports Sunline’s contention that CITGO intended for
    both the Term Agreement and Master Agreement to end simultaneously on May 31,
    2014. For example, contemporaneous correspondence suggests CITGO initially
    88
    See RESTATEMENT (SECOND) OF CONTRACTS § 32 (“In case of doubt an offer is interpreted as
    inviting the offeree to accept either by promising to perform what the offer requests or by rendering
    the performance, as the offeree chooses.”).
    89
    See App. to Opening Br. at A346 (Agreement for Motor Transportation Services (Mar. 23,
    2013)).
    27
    believed that it was subject to a monthly minimum volume requirement in April and
    May. For instance, in early April, Sunline sent CITGO a spreadsheet listing
    minimum amounts for April and May. Although CITGO challenged other aspects
    of the spreadsheet, CITGO was silent as to the minimum delivery amounts for both
    April and May.90 Not only did CITGO not acknowledge the minimum delivery
    requirement, but two days after it sent the termination notice, CITGO characterized
    its March 31, 2014 termination notice in an email to Sunline’s president as
    “essentially an offer to extend the agreement for one more month to May 31,
    2014.”91 Such an extension would inherently apply to all of the Term Agreement’s
    terms, including the minimum volume requirements.
    Not only does CITGO’s termination notice suggest that Sunline’s
    interpretation is a reasonable one, but CITGO’s behavior adds further credibility to
    Sunline’s interpretation.        First, even after CITGO sent its termination letter,
    CITGO’s interactions with Sunline suggest that they thought the Term Agreement
    remained in effect, as suggested by Sunline’s preferred reading. For instance, in a
    90
    Id. at A872–73 (email from John Flinn to Jones Khan (Apr. 9, 2014)) (CITGO acknowledging
    shortfall volumes for April and May but disputing the amount owed for December shortfalls)
    91
    Id. at A728 (Email from Gene Riccetti to John Flinn et al (Apr. 2, 2014)). In suggesting that the
    agreement only extended for one month, CITGO acknowledged that both parties had already
    agreed to extend the Term Agreement until April 30, 2014. Id. (“[T]he only agreement on a
    potential new term was extending the agreement one additional month to the end of April 2014.”).
    28
    meeting with Sunline, CITGO allegedly acknowledged accruing a shortfall in April
    and that it would likely accrue one in May too.92
    And the volume of oil CITGO shipped to Sunline during April and May can
    be viewed as suggesting that CITGO believed the Term Agreement’s monthly
    minimum requirements remained in effect during April and May. On March 31,
    2014, the end of the Term Agreement according to CITGO, CITGO’s shortfall stood
    at 337,969 barrels. The Superior Court found that the parties’ contemplated CITGO
    making up its shortfall requirement—337,969 barrels—during April and May.93 But
    CITGO actually sent 358,945 barrels to Sunline during the two-month extension.94
    One reasonable inference to be drawn from CITGO sending Sunline petroleum in
    excess of its previously accumulated shortfalls, then, is that the Term Agreement
    was extended, and CITGO was attempting to send as much petroleum to Sunline as
    possible to minimize its April and May shortfalls, suggesting that CITGO
    understood that the Term Agreement remained in effect until the Master Agreement
    was terminated on May 31, 2014.95
    92
    Id. at A1549 (Deposition of John Flinn 166:1–16 (Sept. 21, 2016)) (“Q: As for minimums, what
    was caused about the minimums? A: He [CITGO’s Jones Khan] told me we needed a billing for
    April because they didn’t meet their minimums and we sent that then out a few days later. WE
    talked about how many he had purchased for May. Q: What – what did he say? Did he say that
    – did he use the word minimums. A: My recollection is yes.”).
    93
    Sunline Opinion, 
    2017 WL 6618886
     at *7–9; App. to Opening Br. at A432.
    94
    App. to Opening Br. at A885.
    95
    See Senior Housing Capital, LLC v. SHP Senior Housing Fund, LLC, 
    2013 WL 1955012
    , at *31
    (Del. Ch. May 13, 2013) (“The parties’ course of performance under a contract is a powerful
    indication of what the correct interpretation of that contract is.”).
    29
    IV.
    In sum, both the text of the relevant contracts and the parol evidence suggest
    that Sunline’s interpretation is a potentially viable one, and that it is entitled to a trial
    to determine whether its interpretation or CITGO’s ultimately prevails. Because the
    Superior Court (and this Court) cannot weigh evidence at the summary judgment
    stage,96 a jury must evaluate this parol evidence to determine the parties’ intent.97
    The Superior Court’s judgment is hereby reversed and remanded for
    proceedings consistent with this opinion.
    96
    See Cont’l Oil Co. v. Pauley Petroleum, Inc., 
    251 A.2d 824
    , 826 (Del. 1969) (“The function of
    a judge in passing on a motion for summary judgment is not to weigh evidence and to accept that
    which seems to him to have the greater weight.”).
    97
    See GMG Capital Invs., LLC v. Athenian Venture Partners I, L.P., 
    36 A.3d 776
    , 783 (Del. 2012).
    30