The HC Companies, Inc. v. Myers Industries, Inc. ( 2017 )


Menu:
  •                             COURT OF CHANCERY
    OF THE
    STATE OF DELAWARE
    417 S. State Street
    JOSEPH R. SLIGHTS III                                            Dover, Delaware 19901
    VICE CHANCELLOR                                                Telephone: (302) 739-4397
    Facsimile: (302) 739-6179
    Date Submitted: September 8, 2017
    Date Decided: December 5, 2017
    R. Judson Scaggs, Jr., Esquire                Michael J. Barrie, Esquire
    Ryan D. Stottmann, Esquire                    Stephen M. Ferguson, Esquire
    Morris, Nichols, Arsht & Tunnell LLP          Benesch, Friedlander, Coplan
    1201 North Market Street                           & Aronoff, LLP
    Wilmington, DE 19899                          222 Delaware Avenue, Suite 801
    Wilmington, DE 19801
    Re:    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    Dear Counsel:
    This letter opinion addresses The HC Companies, Inc.’s (“HC”) motion for
    partial summary judgment. For the reasons that follow, the motion is granted.
    HC purchased a lawn and garden business from Myers Industries, Inc. and
    MYE Canada Operations Inc. (together, “Myers”) in February 2015. Among the
    assets acquired were equipment and machinery to manufacture plastic pots, flats,
    trays and other items used to grow and sell plants.1 The condition of that equipment
    1
    HC also acquired other assets and rights from Myers, including leasehold interests in
    manufacturing facilities. Def. Myers Indus. Inc.’s Answer to HC’s Compl. ¶ 8; Aff. of
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 2
    was material to the transaction. Meyers represented and warranted in the Amended
    and Restated Asset Purchase Agreement (the “Purchase Agreement”) that the
    equipment was in “good condition.”2 This representation and warranty, in turn, was
    captured within Meyers’ indemnification obligation as set forth in the Purchase
    Agreement. It was also captured, by extension, within the Escrow Agreement3 that
    memorialized the $8.6 million in funds the parties set aside in escrow to address
    post-closing indemnification claims (the “Escrow Property”).4
    The operative agreements set forth a detailed process by which
    indemnification claims were to be asserted and processed. Relevant here, HC was
    required to submit its indemnification claims to Myers by written notice. Myers, in
    turn, retained the right to object to indemnification claims raised by HC so long as
    it provided a written objection to HC within 10 days of receiving HC’s claim notice.
    Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 1 (“Purchase Agreement”)
    § 2.
    2
    Purchase Agreement § 4.08(c).
    3
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 2 (“Escrow
    Agreement”) § 1.3(c)(i).
    4
    Purchase Agreement § 4.08(c). The precise amount of the Escrow Property is $8,625,000.
    Id. at Art. I (definition of “Escrow Amount”); Escrow Agreement at Recitals (same).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 3
    If Myers failed to provide a timely objection, Myers would be deemed to have
    “irrevocably waived” the right to contest HC’s claim notice.5
    The transaction closed on February 17, 2015. Shortly thereafter, HC sent an
    indemnification claim notice to Myers asserting that Myers had breached the
    Purchase Agreement’s representations and warranties because some of the tangible
    assets it acquired, primarily equipment and machinery, were not in good repair.
    HC’s claim notice demanded almost $8 million of the Escrow Property. Myers
    timely objected on the ground that HC’s claim lacked sufficient detail.
    HC sent a second indemnification claim notice in July 2016, this time seeking
    more than $10 million. Once again, HC claimed that specified pieces of equipment
    and machinery were not in good condition. Myers did not respond to this notice
    until several weeks later, outside the 10-day objection period imposed by the
    agreements. When HC demanded payment because the response was untimely,
    Myers disagreed and refused to authorize the release of the Escrow Property. This
    litigation followed.
    In its motion for partial summary judgment, HC contends that it is entitled to
    the Escrow Property based on the clear terms of the parties’ contracts because
    5
    Escrow Agreement § 1.3(c)(i).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 4
    Myers’ objection to HC’s second claim notice was not timely. Myers counters that
    the first and second claim notices contain the same claim, and thus its objection to
    HC’s first claim notice suffices under the agreements to preserve its rights to contest
    the claim. Myers also raises other defenses based on the terms of the agreements
    and equitable estoppel.
    The core issue is whether Myers timely objected to HC’s second
    indemnification claim notice. In resolving this issue, the Court need only consider
    the Purchase Agreement, the Escrow Agreement and the parties’ written
    correspondence. Because I find that Myers did not timely object to HC’s second
    claim notice, I must conclude that it has waived its right to contest HC’s claim to the
    Escrow Property. Accordingly, HC’s motion for partial summary judgment must be
    GRANTED.
    I. Factual Background
    I have drawn the facts from the admissions in the pleadings, uncontested facts
    presented in the parties’ submissions and those matters of which the Court may take
    judicial notice. Unless otherwise indicated, I have determined that the following
    facts are undisputed.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 5
    A. The Purchase Agreement
    The relevant representations and warranties provision within the Purchase
    Agreement is Section 4.08(c).6 There, Myers represented and warranted that “[a]ll
    Tangible Personal Property that has a replacement value in excess of $50,000 is in
    good condition and in [a] state of good maintenance and repair in all material
    respects.”7 Section 8.02(a) of the Purchase Agreement provides that Myers will
    indemnify HC for “any inaccuracy in or breach of any of the representations or
    warranties of [Myers] contained in this Agreement . . . .”8
    Section 8.05 governs “Indemnification Procedures,” and subsection (c) sets
    forth the process for making “Direct Claims” against an “Indemnifying Party.” 9 A
    “Direct Claim” is any claim by an “Indemnified Party” (i.e., HC) against an
    “Indemnifying Party” (i.e., Myers) “on account of a Loss which does not result from
    a Third Party Claim.”10 Section 8.05(c) requires HC to give written notice to Myers
    6
    Purchase Agreement § 4.08(c).
    7
    Id.
    8
    Id. § 8.02(a).
    9
    Id. § 8.05. Either party, HC or Myers, could make indemnification claims under the
    Purchase Agreement and Escrow Agreement for reasons specified in those agreements.
    Because this decision concerns solely HC’s indemnification rights, however, I do not
    discuss Myers’ indemnification rights.
    10
    Id. § 8.05(c). “‘Losses’ means any Liabilities, losses, damages, fines, interest,
    judgments, awards, settlements, fees, claims, suits, actions, causes of actions, assessments,
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 6
    within 10 days after HC receives a Direct Claim, but provides that failure to give
    prompt notice will not relieve Myers of its indemnification obligations:
    Direct Claims. Any claim by an Indemnified Party on account
    of a Loss which does not result from a Third Party Claim (a “Direct
    Claim”) shall be asserted by the Indemnified Party giving the
    Indemnifying Party prompt written notice thereof (but in any event, no
    later than ten (10) business days after the receipt by such Indemnified
    Party of such Direct Claim). The failure to give such prompt written
    notice shall not, however, relieve the Indemnifying Party of its
    indemnification obligations, except and only to the extent that the
    Indemnifying Party forfeits rights or defenses by reason of such failure.
    Such notice by the Indemnified Party shall describe the Direct Claim in
    reasonable detail, shall include copies of all material written evidence
    thereof and shall indicate the estimated amount, if reasonably
    practicable, of the Loss that has been or may be sustained by the
    Indemnified Party.11
    B. The Escrow Agreement
    According to Section 1.3(c)(i) of the Escrow Agreement, once Myers receives
    an indemnification claim notice from HC, it has 10 business days to send a written
    objection:
    If any Buyer Indemnitee desires to make a claim for indemnification
    pursuant to the Purchase Agreement that is not addressed by a Joint
    Written Instruction pursuant to Section 1.3(a)(i) (an “Indemnification
    Claim”), such Buyer Indemnitee [HC] shall provide written notice of
    penalties, costs or expenses, including reasonable attorneys’ or other professional fees and
    expenses, but excluding any exemplary or punitive damages except in the case of a third-
    party claim.” Id. at Art. I (Definitions).
    11
    Id. § 8.05(c).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 7
    such Indemnification Claim to Sellers [Myers] and the Escrow Agent
    (“Claim Notice”), specifying in reasonable detail (to the extent known)
    the nature and dollar amount (estimated, as necessary and to the extent
    feasible) of the Indemnification Claim. Upon receipt of an
    Indemnification Claim, any Seller may contest the Indemnification
    Claim(s) specified in the Claim Notice (or any portion thereof) by
    giving the Escrow Agent, the applicable Buyer Indemnitee (to the
    extent necessary contact information for such Buyer Indemnitee is
    provided in the Claim Notice) and Buyer written notice of such
    contest (the “Objection Notice”) on or before 5:00 p.m., Dallas,
    Texas time, on the tenth (10th) Business Day after receipt by the
    Sellers of such Claim Notice (such period, the “Dispute Period”),
    which Objection Notice shall include a statement of the reason or basis
    of such contest and shall state the amount, if any, of any such Claim
    that is not in dispute (any disputed Claim shall hereinafter be referred
    to as a “Disputed Claim”).12
    Section 1.3(c)(i) goes on to state that if Myers does not object within 10 days, then
    Myers is deemed to have “irrevocably waived the right to contest” HC’s claim:
    If the Escrow Agent has not received an Objection Notice prior to
    the expiration of the applicable Dispute Period, the Sellers shall
    have irrevocably waived the right to contest the distribution of that
    portion of the Escrow Property specified by the corresponding
    Claim Notice and the Escrow Agent shall pay to the Buyer Indemnitee
    specified in the corresponding Claim Notice the amount set forth in the
    Claim Notice on or before the fifth (5th) Business Day after the
    expiration of the Dispute Period.13
    12
    Escrow Agreement § 1.3(c)(i) (emphasis supplied).
    13
    Id. (emphasis supplied).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 8
    C. The Indemnification Claims
    On April 13, 2015, just two months after the transaction closed, HC sent a
    Claim Notice to Myers (the “First Claim Notice”) asserting that Myers had breached
    Section 4.08(c) of the Purchase Agreement because the equipment and other assets
    listed in the notice were not in “good condition.”14 The First Claim Notice identified
    almost $8 million of losses and expressly invoked the procedures set forth in Section
    8.05(c) of the Purchase Agreement.15 Myers sent out its objection on April 24, 2015,
    in which it stated its position that HC’s First Claim Notice lacked sufficient detail.16
    HC responded by notifying the escrow agent of the dispute on May 28, 2015, and
    instructing the agent not to release the Escrow Property to either party until they
    resolved their dispute and submitted either a “Joint Written Instruction or Final
    Decree.”17
    14
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 3 (“First Claim
    Notice”).
    15
    Id. at 2 (“In total, Buyer has identified $7,916,539 in Losses for which Sellers have
    agreed to indemnify Buyer pursuant to Section 8.02(a) of the Purchase Agreement.”).
    16
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 4 at 2 (“For each
    and every purported ‘deficiency’ and ‘additional deficiency’ referred to in your Letter, you
    failed to describe it in any detail, let alone ‘reasonable detail.’”) (emphasis in original).
    17
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 5 at 1 (“Until [HC]
    and [Myers] are able to resolve the Direct Claims referenced in the Notice, [HC] hereby
    expressly requests that the Escrow Agent retain the full amount of the Escrow Property . . .
    until receipt of a Joint Written Instruction or a Final Decree . . . , in each case, directing
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 9
    After Myers objected, the parties utilized the indemnification procedure as a
    dispute resolution mechanism of sorts. HC hired experts to inspect the equipment
    with an eye toward addressing Myers’ objections regarding the lack of specificity in
    the First Claim Notice.18 HC then sent Myers a letter in December 2015, in which
    it included a settlement demand along with a detailed breakdown of each alleged
    defective asset and the experts’ opinions regarding why the asset was not in “good
    condition” as warranted.19 The parties were unable to reach an agreement.
    HC sent a second claim notice on July 15, 2016, and Myers received it on
    July 18, 2016 (the “Second Claim Notice”).20 In the Second Claim Notice, HC
    identified a number of assets it alleged were not in “good condition” as warranted in
    Section 4.08 of the Purchase Agreement, and provided detailed charts that listed for
    each asset the amount of the alleged loss and an explanation of the deficiency.21 This
    any disposition thereof. [HC] reserves all of its rights and remedies against [Myers].
    Nothing contained in this notice shall preclude [HC] from providing a subsequent notice
    of any indemnification claim . . . .”).
    18
    See Def. Myers Indus. Inc.’s Answering Br. in Opp’n to Pl.’s Mot. for Partial Summ. J.
    (“Myers’ Answering Br.”), Ex. 7.
    19
    Id.
    20
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 6 (“Second Claim
    Notice”); Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 8 (stating
    that Myers’ received the Second Claim Notice via FedEx on July 18, 2016).
    21
    Second Claim Notice, Ex. A–B.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 10
    notice also included the experts’ opinions on defects and damages.22 In total, HC
    claimed over $10 million in losses, well in excess of the $8.6 million in escrow. 23
    Myers did not deliver its written objection until August 12, 2016.24 On August 17,
    2016, HC advised the escrow agent that HC had not received a timely objection from
    Myers and stated its position that Myers, therefore, had “irrevocably waived the right
    to contest the distribution of the full amount of the Escrow Property . . . .” 25
    D. Procedural History
    On August 17, 2016, HC filed its Verified Complaint in this Court for breach
    of contract seeking, inter alia, the full amount of Escrow Property based on the
    claims raised in its Second Claim Notice. On May 25, 2017, HC filed a motion for
    partial summary judgment in which it argues that Myers has waived its right to
    contest the Second Claim Notice, and the release of the Escrow Property, because
    22
    Id.
    23
    Id. at 2 (“[HC] has identified $10,144,445 in Losses related to the Deficiencies for which
    [Myers] ha[s] agreed to indemnify [HC] pursuant to Section 8.02(a) of the Purchase
    Agreement.”).
    24
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 7. Myers 10-day
    objection period expired no later than August 1, 2016. Aff. of Jason Reed in Support of
    HC’s Mot. for Partial Summ. J., Ex. 8.
    25
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 8.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 11
    its objection to the Second Claim Notice was not timely. Myers opposes the motion.
    This is the Court’s decision.
    II. Analysis
    As noted, the core issue raised by the motion is whether Myers timely objected
    to HC’s Second Claim Notice. In order to decide that issue, the Court must first
    determine whether the claim contained in the Second Claim Notice is the same as
    the claim contained in the First Claim Notice. If the claims are different, then the
    Escrow Agreement required Myers to send a written objection within 10 days of
    receiving the Second Claim Notice, which Myers did not do. If the claims are the
    same, then Myers’ original objection to the First Claim Notice, timely provided,
    would perfect its objection and require HC to prove its breach of warranty claim on
    the merits. For reasons discussed below, I find that the two claim notices clearly and
    unambiguously contain different claims. Thus, Myers’ objection to the Second
    Claim Notice was untimely, it has waived its objections and HC is entitled to the
    Escrow Property.
    A. Standard Of Review
    Under Court of Chancery Rule 56(c), summary judgment is appropriate where
    “there is no issue as to any material fact and . . . the moving party is entitled to
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 12
    judgment as a matter of law.”26 This Court has often observed that “[w]hen the issue
    before the Court involves the interpretation of a contract, summary judgment is
    appropriate only if the contract in question is unambiguous.”27
    Delaware “is more contractarian than . . . many other states.”28 With this in
    mind, our courts have recognized that “[p]arties have a right to enter into good and
    bad contracts, the law enforces both.”29 “The presumption that the parties are bound
    by the language of the agreement they negotiated applies with even greater force
    when the parties are sophisticated entities that have engaged in arms-length
    negotiations.”30
    After carefully reviewing the operative provisions of the contracts at issue
    here, I am satisfied they are clear and unambiguous.31 Thus, the Court’s task is to
    construe and enforce the contracts as written.
    26
    Ct. Ch. R. 56(c).
    27
    United Rentals, Inc. v. RAM Hldgs., 
    937 A.2d 810
    , 830 (Del. Ch. 2007).
    28
    GRT, Inc. v. Marathon GTF Tech., Ltd., 
    2011 WL 2682898
    , at *12 (Del. Ch. July 11,
    2011).
    29
    Nemec v. Shrader, 
    991 A.2d 1120
    , 1125 (Del. 2010).
    30
    W. Willow-Bay Ct., LLC v. Robino-Bay Ct. Plaza, LLC, 
    2007 WL 3317551
    , at *9 (Del.
    Ch. Nov. 2, 2007).
    31
    Myers did not argue in its brief on the motion that the contracts are ambiguous. At oral
    argument, however, Myers’ counsel made an off-handed comment that the contracts might
    be subject to two reasonable interpretations. Tr. of Oral Argument 43:3–8. It is unclear
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 13
    B. Myers Failed To Object On Time
    As noted, Myers argues that the First Claim Notice and the Second Claim
    Notice cover the same claim, and thus its objection to the First Claim Notice is
    sufficient for the Second Claim Notice. I disagree. Although many of the assets
    listed in the two notices overlap, the Second Claim Notice identified seventy new
    Losses as subjects of the claim.32 It also provided substantially more detail regarding
    the deficiencies of all the listed assets, along with supporting expert opinions, as the
    bases of HC’s claim that the assets were not in “good condition” as warranted.33 In
    many instances, the stated Losses for the individual assets that are listed in both of
    HC’s two Claim Notices differ in amount. For example, the Loss claimed for
    machine G9 is $27,000 in the First Claim Notice, but is revised to $27,542 for a
    from this comment whether Myers intended to argue that the agreements are ambiguous.
    Assuming Myers does seek to press a belated ambiguity argument, I reject it both as
    untimely and unsustainable. As explained below, the operative provisions are subject to
    only one reasonable construction. See Rhone-Poulenc Basic Chem. Co. v. Am. Motorists
    Ins. Co., 
    616 A.2d 1192
    , 1196 (Del. 1992) (“A contract is not rendered ambiguous simply
    because the parties do not agree upon its proper construction. Rather, a contract is
    ambiguous only when the provisions in controversy are reasonably or fairly susceptible of
    different interpretations or may have two or more different meanings.”); Comet Sys., Inc.
    S’holders’ Agent v. MIVA, Inc., 
    980 A.2d 1024
    , 1030 (Del. Ch. Oct. 22, 2008) (“The
    determination of whether a contract is ambiguous is a question for the court to resolve as a
    matter of law.”) (citations omitted) (internal quotation marks omitted).
    32
    Second Claim Notice, Ex. A.
    33
    Compare First Claim Notice at Ex. A–B, with Second Claim Notice at Ex. A–B.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 14
    “software” defect and $17,100 for “clamp end seals/screw” in the Second Claim
    Notice.34 The Loss for machine 103 is $8,000 in the First Claim Notice, but is
    revised to $10,611 for a “color head” repair.35
    No analytical or perceptual paradigm exists where one could read the First
    Claim Notice and the Second Claim Notice and then credibly declare that they are
    the “same notices.” Myers’ attempt to do just that—to argue that the notices are the
    same and, therefore, that its objection to the First Claim Notice carried over to the
    Second Claim Notice—is simply not credible. The differences are manifest on the
    face of the notices and they are substantive. I am satisfied, therefore, that HC’s
    delivery of the Second Claims Notice triggered Myers’ obligation timely to object
    to that notice under Section 1.3(c)(i) of the Escrow Agreement.36 It did not do so.
    Myers’ construction of the agreements as allowing its first and only timely
    objection to HC’s indemnification claim to freeze the Escrow Property as to all
    future claims finds no support in the language of the contracts and, indeed, runs
    34
    Compare First Claim Notice, Ex. A, with Second Claim Notice, Ex. A–B.
    35
    Compare First Claim Notice, Ex. A, with Second Claim Notice, Ex. A–B. As noted,
    there are upwards of 70 such examples where the Losses stated in the Second Claim Notice
    differ from those set forth in the First Claim Notice.
    36
    While “Direct Claims” are tied to “Losses,” Myers’ response obligation is tied to its
    receipt of an “Indemnification Claim” from HC. Purchase Agreement § 8.05(c); Escrow
    Agreement § 1.3(c)(i).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 15
    directly contrary to the clear terms of the Escrow Agreement. Section 1.3(c)(i)
    provides that Myers was obligated timely to “contest [the] Indemnification
    Claim(s)” and further provides that if it did not do so, it lost the right to “contest the
    distribution of that portion of the Escrow Property specified in the corresponding
    Claim Notice.”37 This language unambiguously requires that Myers object to claims
    as made and makes clear that objections raised will be tied to “the corresponding
    Claim Notice.” The language also reveals that the parties anticipated HC might
    make more than one claim. Thus, Myers’ first objection (the only timely objection)
    was tied to the “corresponding” First Claim Notice and did not carry over to the
    Second Claim Notice.38
    37
    Escrow Agreement § 1.3(c)(i) (emphasis supplied).
    38
    Myers argues that under HC’s construction of the Agreements, HC could serially send
    the same claim notice and pounce on the Escrow Property the moment Myers failed to
    respond in time to any one of the repeated notices. But that is not what occurred here. As
    demonstrated above, the two Indemnification Claims stated in their respective notices are
    clearly different. According to Myers, HC’s First Claim Notice lacked detail. HC provided
    that detail and then asserted substantially more Losses in its Second Claim Notice. Myers’
    argument, under these circumstances, that it may simply stand on its original objection
    (that the claim lacked detail) flies in the face of the bargained-for give and take required
    by the parties’ agreements. Moreover, the extreme scenario that Myers envisions would
    be addressed (and prevented) either by the express terms of the contract (e.g., the
    “corresponding” language in Section 1.3(c)(i) of the Escrow Agreement) or the implied
    covenant of good faith and fair dealing. See, e.g., Nemec v. Shrader, 
    991 A.2d 1120
    , 1126
    (Del. 2010) (“[The courts] will [] imply contract terms when the party asserting the implied
    covenant proves that the other party has acted arbitrarily or unreasonably, thereby
    frustrating the fruits of the bargain that the asserting party reasonably expected.”).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 16
    Section 1.3(c)(i) of the Escrow Agreement requires Myers to object to HC’s
    claim notices in writing within 10 days after it receives the notice.39 Myers received
    HC’s Second Claim Notice no later than July 18, 2016, but Myers did not object
    until August 12, 2016—several days outside of the 10-day window. Thus, the
    objection was untimely and, absent some other viable legal defense to HC’s
    indemnification claim, Myers has “irrevocably waived the right to contest the
    distribution of that portion of the Escrow Property specified by the [Second] Claim
    Notice.”40
    C. HC’s Claim Is Not Barred By Estoppel
    Myers sees that other viable legal defense in the law of estoppel. Specifically,
    Myers argues that HC is estopped from arguing that Myers waived any objection to
    the Second Claim Notice because HC instructed the escrow agent on two occasions
    not to release any of the Escrow Property until the parties’ dispute was resolved by
    “Joint Written Instruction or Final Decree.”41 Specifically, HC’s instruction to the
    escrow agent appeared in a letter dated May 28, 2015, following Myers’ objection
    39
    Escrow Agreement § 1.3(c)(i).
    40
    Id.
    41
    E.g., Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 5 at 1.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 17
    to the First Claim Notice, and again in the Second Claim Notice.42 According to
    Myers, by affirmatively stating to the escrow agent that the indemnification dispute
    was “subject to final resolution only through Joint Written Instruction or Final
    Decree,” HC acknowledged that the Escrow Property was subject to a “Disputed
    Claim” and thereby relieved Myers of its obligation to object.43
    Myers bears the burden of proving equitable estoppel by demonstrating that
    it: “(i) lacked knowledge or the means of obtaining knowledge of the truth of the
    facts in question; (ii) reasonably relied on the conduct of the party against whom
    estoppel is claimed; and (iii) suffered a prejudicial change of position as a result of
    [its] reliance.”44 Myers estoppel defense fails as a matter of law because the
    undisputed evidence in the summary judgment record reveals that Myers cannot
    demonstrate reasonable, detrimental reliance.
    42
    Second Claim Notice at 2.
    43
    Myers’ Answering Br. at 21. According to the Escrow Agreement, an “Indemnification
    Claim” is treated as a “Disputed Claim” only when Myers sends a “written notice of []
    contest” (i.e., an objection notice) to HC and the escrow agent within the 10-day window
    following HC’s claim. Escrow Agreement § 1.3(c)(i).
    44
    Nevins v. Bryan, 
    885 A.2d 233
    , 249 (Del. Ch. 2005) (citing Wilson v. Am. Ins. Co., 
    209 A.2d 902
    , 904 (Del. 1965); Waggoner v. Laster, 
    581 A.2d 1127
    , 1136 (Del. 1990)); see
    also VonFeldt v. Stifel Fin. Corp., 
    714 A.2d 79
    , 87 (Del. 1998) (“To make out a claim of
    equitable estoppel, plaintiff must show that he was induced to rely detrimentally on
    defendant’s conduct.”).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 18
    The analysis must begin with a complete picture of precisely what HC said in
    its directions to the escrow agent. Myers has cherry picked what it likes in the
    correspondence but there is more. Following the language Myers relies upon, HC
    stated in both the May 28 letter and the Second Claim Notice that it “reserves all of
    its rights and remedies against [Myers]. Nothing contained in this notice shall
    preclude [HC] from providing a subsequent notice of any additional indemnification
    claim under any section of the Purchase Agreement . . . .”45 The Second Claim
    Notice does not contain the words “Disputed Claim,” but does state clearly that HC
    was seeking in that notice “payment of the full value of the Escrow Property.”46
    Myers could not have reasonably relied on HC’s correspondence to the escrow
    agent in deciding not to send an objection to the Second Claim Notice because HC
    made it clear that it “reserve[d] its right” to raise “additional indemnification
    claim[s]” against the Escrow Property in “subsequent notice[s].”             When HC
    delivered its Second Claim Notice, it did just that. Moreover, Myers’ conduct
    reveals that it did not rely on HC’s letters in deciding not to send a written objection;
    45
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 5 at 1; Second
    Claim Notice at 2.
    46
    Second Claim Notice at 2.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 19
    it sent a written objection to the Second Claim Notice on August 12, 2016—after the
    10-day window closed.47 In the absence of reasonable reliance, Myers’ estoppel
    argument fails.48
    D. Myers’ Untimeliness Argument Is Itself Untimely
    Myers disputes that HC’s Second Claim Notice was valid in the first place
    because HC sent the notice more than 10 days after it received notice of the alleged
    equipment defects that gave rise to its claim. According to Myers, this means the
    47
    Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J., Ex. 7. Myers also
    points to HC’s December 2015 settlement overture as yet another statement by HC upon
    which Myers relied to justify its failure to object to the Second Claim Notice. While HC
    did provide additional detail in its settlement letter, it said nothing that would lead Myers
    reasonably to believe that a second indemnification claim would not be forthcoming or that
    an objection to that claim would not be necessary. See Myers’ Answering Br. at 21, 23;
    Myers’ Answering Br., Ex. 7.
    48
    See Nevins, 
    885 A.2d at 249
    . Myers’ estoppel argument likely fails on the first prong as
    well. Myers cannot say that it “lack[ed] knowledge or the means to obtain knowledge of
    the truth of the facts in question”—the fact in question being that HC may bring a second
    claim—after it received HC’s May 28 letter and the Second Claim Notice in which (in both
    instances) HC reserved the right to bring additional claims. 
    Id.
     Myers was also aware of
    its obligation to object to HC’s claim notice under the Escrow Agreement, as it was a party
    to the contract, had timely objected to the First Claim Notice and had belatedly objected to
    the Second Claim Notice. Aff. of Jason Reed in Support of HC’s Mot. for Partial Summ. J.,
    Ex. 5.
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 20
    Second Claim Notice was untimely under Section 8.05(c) of the Purchase
    Agreement.49
    Myers’ timing defense to the Second Claim Notice may have carried the day
    if only Myers had timely raised it.50 Unfortunately for Myers, any delay by HC
    under Section 8.05(c) of the Purchase Agreement (assuming there was a delay) did
    not relieve Myers of its obligation to send a written objection. Section 8.05(c)
    provides that “the failure to give such prompt written notice shall not, however,
    relieve the Indemnifying Party [Myers] of its indemnification obligations,
    except and only to the extent that the Indemnifying Party forfeits rights or defenses
    by reason of such failure.”51 Myers has not shown that it forfeited any rights or
    defenses as a result of HC’s delay in submitting the Second Claim Notice, and I can
    think of no right or defense that Myers would have lost if it had made a timely
    49
    Purchase Agreement § 8.05(c) (providing that Direct Claims “shall be asserted by [HC]
    giving [Myers] prompt written notice thereof (but in no event, no later than (10) business
    days after the receipt of [HC] of such Direct Claim)”).
    50
    If HC failed to provide timely notice of an indemnification claim, then Myers could
    have included that failure as a “reason or basis” for contesting HC’s claim, as envisioned
    by the Escrow Agreement. Escrow Agreement § 1.3(c)(i) (providing that Myers’ objection
    notice “shall include a statement of the reason or basis” for Myers objection).
    51
    Id. (emphasis supplied).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 21
    objection. In fact, a timely objection would have preserved Myers’ rights and
    defenses, including its defense that HC’s Second Claim Notice was untimely.
    Myers does claim that it was prejudiced by HC’s delay because it could not
    make a prompt inspection of the allegedly defective assets listed in the Second Claim
    Notice.52 Assuming that is true, that does not amount to a “forfeit[ure]” of rights
    and defenses captured by the exception in Section 8.05(c).53 The only reasonable
    construction of Section 8.05(c) is that HC’s delay in sending a claim notice must be
    the cause of Myers forfeiting rights and defenses.54 But Myers forfeited its defenses
    only as a result of its delay in objecting to HC’s claim. As stated, Myers could have
    used HC’s delay as part of its defense in arguing that HC was not entitled to
    indemnification, along with any other arguments it might muster in defense of the
    claim on the merits. According to the plain language of the Purchase Agreement
    52
    As an aside, I note that Myers’ argument that the Second Claims Notice did not provide
    it with adequate, timely notice of the claimed loss is inconsistent with its argument that the
    First and Second Claim Notices are the same notices. See Myers’ Answering Br. at 19–20
    (defending on the basis that HC was “resubmitting notice of the same claim”); id. at 26–27
    (“HC’s delay between alleged discovery and notice to Myers has prevented Myers from
    defending against HC’s substantive deficiency claims.”).
    53
    Purchase Agreement § 8.05(c).
    54
    Id. (“[T]he failure to give such prompt written notice shall not, however, relieve the
    Indemnifying Party [Myers] of its indemnification obligations, except and only to the
    extent that the Indemnifying Party forfeits rights or defenses by reason of such failure.”)
    (emphasis supplied).
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 22
    and the Escrow Agreement, however, Myers is not entitled to raise its defenses
    unless it objects on time.55 Myers did not object on time, and thus it cannot challenge
    HC’s Second Claim Notice.56
    III. Conclusion
    For the reasons discussed above, HC is entitled to the Escrow Property. This
    may seem like a harsh result, but it is the result dictated by what these two
    sophisticated parties bargained for.57 To reiterate, Delaware courts enforce bad deals
    the same as good deals.58 The Court cannot rewrite the contracts, and it cannot
    ignore the plain terms of the contracts. HC’s motion for partial summary judgment
    55
    It appears that the parties structured the indemnification claim procedure in a way that
    resembles a short statute of limitations period. See id.; Escrow Agreement § 1.3(c)(i). The
    limitations period is the 10-day window following HC’s claim notice. If Myers objects
    within that window, it can then raise any and all defenses it possesses. But if Myers’ fails
    to object within the window, it is time-barred from raising any defenses. This scheme
    reflects an intent to have post-closing indemnification claims addressed promptly and
    efficiently so that the Escrow Property, a percentage of the funds Myers paid to HC as
    consideration, will either be paid out to the seller as contemplated to round out the purchase
    price, or to the buyer, if needed, to cover indemnifiable losses, all within the 18 months
    post-closing allowed for indemnification claims. See Purchase Agreement § 8.01
    (providing that indemnification claims survive for only 18 months after closing).
    56
    Specifically, the Court’s ruling pertains to HC’s claim for the Escrow Property. The
    Court expresses no opinion as to whether Myers’ failure to object on time affects its rights
    to defend HC claims for amounts in excess of the Escrow Property.
    57
    See W. Willow-Bay Ct., 
    2007 WL 3317551
    , at *9.
    58
    Nemec, 
    991 A.2d at 1125
    .
    The HC Companies, Inc. v. Myers Industries, Inc.
    C.A. No. 12671-VCS
    December 5, 2017
    Page 23
    is GRANTED. HC shall submit an implementing order on notice to Myers within
    ten (10) days.
    IT IS SO ORDERED.
    Very truly yours,
    /s/ Joseph R. Slights III