MICHAEL HOJNICKI v. JOHN CHILDS AND STEVEN MULLINS ( 2014 )


Menu:
  • IN 'I``HE COURT OF COMMON PLEAS FOR THE STATE OF DELAWARE
    IN AND FOR NEW CASTLE COUNTY
    MICI-IAEL HGJNICKI
    Plaintiff-Below, Appellant,
    C.A. N0.: CPU4-13-O03 805
    v.
    JOHN CHILDS and STEVEN MULLINS,
    ``\q./"\_/‘-\.-/\-z'\q./\-,/\-.J§/\_/\,/
    Defendants-Below, Appellees.
    Submitted: Apn``l 2, 2014
    Decided: Apri125, 2014
    Michael Hojnicki John Childs
    48 Dasher Avenue 622 Black Diamond Road
    Bear, DE 19701 Smyrna, DE 19977
    Pro-Se Plaz``nt:ff
    Steven Mullins
    217 Brickstore Landing Road
    Srnyrna, DE 19977
    Pro-Se Defendants
    DECISION AFTER TRIAL
    RENNIE, J.
    INTRODUCTION
    This matter is before the Court on appeal de novo from an order entered by the Justice of
    the Peace Court on November 26, 2013. The justice of the Peace Court found in favor of
    Defendants John Childs and Steven Mullins (hereinafter "Childs," “Mullins," or collectively,
    "Defendants"), in an action that arose from a contract dispute over work performed by
    Defendants on Plaintiff Michael Hojnicki’s (hereinafter “Hojnicki" or "Plaintiff") Yaniaha wave
    runner. Mr. Hojnicki filed an appeal with this Court on December 20, 2013, pursuant to 10 Del.
    C.§ 9570 et. seq. A trial was held on April 2, 2014, and the Court reserved decision. This is the
    Court’s Opinion in connection with the relief sought by Mr. Hojnicki.
    FACTUAL BACKGROUND
    Mr. Hojnicki purchased a 2007 Yarnaha wave runner from his brother-in-law,
    Christopher Thompson (hereinafter "Thompson") in 2012. Mr. Thompson purchased the wave
    runner new in 2007, and in 2010 the engine fell into disrepair and had to be rebuilt.l
    On June 16, 2012, the wave runner abruptly stopped working while Mr. Hojnicki was
    operating it on the water. According to Mr. Hojnicki, the engine would not start, even though
    the battery was fully charged An acquaintance of Mr. Hojnicki referred him to Defendants as a
    potential option to repair the wave runner. Defendants are not a dealership, but both Mr. Childs
    and Mr. Mullins enjoy working on wave runners and other watercraft owned by their farnilies
    and friends. They are both certified in repair work for Yamaha watercraft engines. On June 19,
    20l2, Mr. Hojnicki dropped off the wave runner to the Defendants for an estimate. Mr. Childs
    testified that after performing spark and compression tests on the motor, at a cost of $320,
    l Mr. Childs testified that he and Mr. Mullins discovered that the engine had been rebuilt because the pistons were
    0.25 millimeters over the size recommended by the manufacturer.
    2
    Defendants determined that cylinder number three was damaged.z Defendants discussed repair
    options with Mr. Hojnicki. Ultirnately, the parties determined that the entire repair would cost
    $3,300: $2,000 for parts and $l,300 for labor. Mr. Hojnicki paid Defendants $2,000 as a cash
    deposit. At that tirne, Defendants informed Mr. Hojnicki that they were neither a dealership nor
    a business, and therefore could offer no warranty on the parts for the wave runner. However,
    both parties testified that Defendants stated that if problems arose as a result of their
    workmanship, that they would not charge Mr. Hojnicki for labor on future repairs
    Following the engine rebuild, Mr. Childs testified that Defendants ran the wave runner
    for eight hours, and performed a compression test on all parts to ensure compliance with the
    manufacturer specifications. Defendants also river tested the motor for approximately two hours.
    Defendants informed Mr. Hojnicki of the proper break-in procedure for the engines On August
    12, 2012, Mr. Hojnicki took the wave runner for a test run in the Rehoboth Bay and Lewes
    Canal, keeping the vehicle at low variable RPMs while maintaining a full throttle. Mr. Hojm``cki
    testified that aHer approximately seven hours of use, the engine stopped working. Mr. Hojnicki
    brought the wave runner back to Defendants, who determined that all of the parts they repaired
    were in working order, but that the engine had a blown crank seal. On August 24, 2012, Mr.
    Hojnicki picked up the wave runner and was told again to fill its tank with the gas/oil
    combination. The total cost to repair the crank seal was $550. Mr. Hojnicki testified that he
    requested and received a receipt for the work performed
    On September 22, 2012, Mr. Hojnicki operated the wave runner in the Rehoboth Bay
    near Love Creek. The watercraft again broke down, and was towed ashore. Mr. Hojnicki called
    2 Specifically, Mr. Childs testified that cylinder number three had been previously "blown up."
    3 Mr. Hojnicki testified that under the direction of Defendants, he filled the gas tank of the wave runner with gas and
    16 ounces of oil per every six ounces of gas. Mr. Hojnicki also testified that he kept the watercraft in at least four to
    five feet of water at all times. Mr. Hojnicki testified that he did refuel at the Dewey Marina, but he did not state
    whether he added the 16 ounces of oil for every six gallons of gasoline added during this refuel.
    3
    Defendants, and they requested that Mr. Hojnicki give them an opportunity to inspect the engine
    a final time before Mr. Hojnicki took the wave runner to a deaIership. Plaintiff testified that Mr.
    Childs stated that Defendants would stand behind their work. Mr. Hojnicki took the wave runner
    back to the Defendants for inspection, and Defendants determined that cylinder number three
    was damaged. Defendants testified that their previous repair of the cylinder was proper and that
    they could not definitively determine the cause of the subsequent damage to the cylinder.
    Defendants informed Mr. Hojnicki of the parts he would need to purchase for the repair,
    but Mr. Hojnicki testified that he was unsure about what to do because of the costs associated
    with the repair. Mr. Hojnicki did not agree to further repairs, but instead asked Defendants to
    winterize the wave runner, which they did to prevent the engine block from freezing while in
    storage. Thereafter, Mr. Hojnicki picked up the wave runner from Defendants, and Defendants
    did not hear from him until Mr. Hojnicki filed the Complaint in the Justice of the Peace Court."
    PARTIES’ CONTENTIONS
    Mr. Hojnicki contends that Defendants should be required to pay for necessary repairs to
    his wave runner after the repairs performed by Defendants allegedly failed to fix the engine
    problems. Mr. Hojnicki contends that Defendants’ faulty workmanship is the cause of his wave
    runner’s continuous engine issues, and therefore seeks $3,000 to cover the repairs at a Yarnaha
    dealership.
    Defendants contend that their repair work was properly conducted, and that they did fix
    the wave runner. Defendants allege that user error, for which they were not responsible,
    4 Mr. Hojnicki testified that he ultimately took the wave runner to Deptford Honda Yamaha to have the dealership
    determine the costs of repairs. The dealer determined that the cost to repair the vehicle, and to add a one-year
    warranty would be $2,612, and the cost with a two-year warranty would be $2,981. ln this action, Mr. Hojnicki is
    seeking to recover the cost of repairs to be performed by the dealership.
    4
    contributed to the issues with the engine. Defendants contend that Mr. Hojnicki cannot
    demonstrate that their workmanship was faulty, and therefore, he cannot prove that their work
    caused the engine problems.
    DISCUSSION
    Appeals from matters decided on the merits by the Justice of the Peace Court are
    reviewed de novo.s Mr. Hojnicki is proceeding on a breach of contract theory. In order to
    succeed on a breach of contract claim, Plaintiff must prove the following elements by a
    preponderance of the evidence: (l) the existence of a contract; (2) that Defendants breached an
    obligation imposed by the contract; and (3) that Plaintiff incurred damages as a result of the
    breach.s
    THE PARTIES ENTERE\) INTO A VALID CoNTRACT
    Although no written contract exists in this matter, the testimony of both parties
    demonstrates that there existed a verbal contract to perform repair services Both parties
    acknowledged that Defendants agreed to repair the wave runner so that it could be used on the
    water. In tum, Plaintiff agreed to and did pay Defendants for the repairs. Neither party has
    contested the existence of a contract. Therefore, the Court is satisfied that Plaintiff proved this
    element by a preponderance of the evidence.
    PLAINT!FF FAILED 'ro I’Rovll)l; SUFFIC!ENT EVII)ENCE T0 ESTABL!SH A BREACH oF
    CoNTRAcT BAsEn on DEFENnAN'rs’ ALLEGEI) FAULTY WoRKMANsmP
    5 10 Del. C. § 9571(21) provides for appeals as of right to the Court of Common Pleas from any final judgment of the
    Justice of the Peace Court. The requirements imposed by the statute are mandatory and jurisdictional. See Wz``lliams
    v. Singleton, 
    160 A.2d 376
    , 378 (Del. 1960); Warren Wr``lliams Co. v. Gi'ovannozzz', 
    295 A.2d 587
    , 588 (Del. Super.
    1972); Woods v. Unisex Hair Palace, 
    2009 WL 3152878
    , *l (Del. Com. Pl. Aug. 26, 2009).
    5 VLIW Tech., LLC v. Hewlett-Packarcf, Co., 
    840 A.2d 606
    , 612 (Del. 2003).
    5
    Pursuant to the verbal contract, Defendants agreed to repair the wave runner and return it
    to Mr. Hojnicki in working condition. The testimony at trial demonstrates that Defendants
    repaired the wave runner, ran it for close to the manufact11rer’s recommended time to ensure that
    it was in proper working order, and then retumed it to Mr. Hojnicki. The testimony at trial
    further revealed that Mr. Hojnicki ran the wave runner for close to 10 hours after it was returned
    to him. There is no evidence in the record that the cause of the first breakdown (blown crank
    seal) after Defendants’ initial repair was related to work performed by Defendants, and therefore,
    Mr. Hojnicki has failed to prove that Defendants employed faulty workmanship with respect to
    the first repair.
    After Defendants completed the crank seal repair, Mr. Hojnicki again took the wave
    runner out on the water, where it subsequently stopped working. The only evidence Mr.
    Hojnicki produced at trial demonstrates that the engine failed again, but did not offer any
    explanation as to the cause of the breakdown. This lack of evidence does not prove that
    Defendants’ workmanship was a cause of the breakdown. Mr. Hojnicki’s evidence supported his
    contention that the engine needed to be repaired, but he did not bring an expert witness or present
    other evidence to prove that the Defendants’ faulty workmanship was the cause of the engine
    failures.
    Conversely, Defendants provided the Court with expert testimony as to the possible
    causes of the engine problems. At trial, Defendants’ expert, David Wayne Castagna (hereinafter
    "Castagna") testified about the possible causes of damage to the wave runner and why faulty
    workmanship based on the described malfunction could not be a contributing factor. Mr.
    Castagna testified that the problems exhibited by Mr. Hojnicki’s wave runner are consistent with
    the flipping over of the wave runner and subsequent improper righting of the watercraft, which
    causes water to get into the engine, and result in engine failure. Mr. Castagna also testified that
    sediment entry into the engine, caused by operating the wave runner in shallow waters, causes
    engine problems. Mr. Castagna testified that although he did not personally inspect Mr.
    Hojnicki’s wave runner, the Defendants’ workmanship could not be the cause of the subsequent
    engine failures He specifically testified that if the wave runner’s engine was put together
    improperly, the engine would have failed during the first few hours of use. Instead, testimony at
    trial demonstrates that the engine stopped working only after numerous hours of use.
    Mr. Hojnicki has the burden to prove, by a preponderance of the evidence, that
    Defendants breached the contract, and that the subsequent damage to the wave runner was a
    result of the Defendants’ faulty workmanship Mr. Hojnicki provided the Court with evidence
    sufficient to inform the Court that the wave runner broke down two times after Defendants’
    initial repair, but he offered no evidence, either through expert testimony -or through documents,
    that demonstrates that the cause of the breakdowns was the faulty workmanship of the
    Defendants, Indeed, the wave runner functioned properly each time Defendants retumed it to
    Mr. Hojnicki. The wave runner only experienced problems after Mr. Hojnicki had operated it on
    the water outside the supervision of Defendants. Mr. Hojnicki cannot support his argument that
    the workmanship was faulty by using only his opinions and by requiring the Court to assume
    facts not in the record. Without evidence of fault by the Defendants, the Court is left to speculate
    about what caused the wave runner to stall. "l``hus, Mr. Hojnicki failed to prove that the
    Defendants breached their contract by employing faulty workmanship in their repair of the wave
    runner.
    Accordingly, the Court finds in favor of Defendants on the breach of contract claim for
    repair costs for Plaintiff’s wave runner.
    CONCLUSION
    For the foregoing reasons, the Court finds in favor of Defendants .lohn Childs and Steven
    Mullins. Each party shall bear his own costs.
    IT IS SO ORDERED.
    The Hono able Sheldon K. Rennie,
    Judge
    

Document Info

Docket Number: CPU4-13-003805

Judges: Rennie J.

Filed Date: 4/25/2014

Precedential Status: Precedential

Modified Date: 10/30/2014