Facchina Construction Litigations ( 2020 )


Menu:
  • IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
    FACCHINA CONSTRUCTION C.A. No. N17C-09-163 PRW CCLD
    LITIGATIONS CONSOLIDATED
    Submitted: July 2, 2020
    Decided: October 29, 2020
    DECISION AFTER TRIAL
    Stephen B. Brauerman, Esquire, Elizabeth A. Powers, Esquire, BAYARD, P.A.,
    Wilmington, Delaware; Robert Mahoney, Esquire, Saleem Mawji, Esquire,
    NORRIS MCLAUGHLIN, P.A., Bridgewater, New Jersey, Attorneys for Plaintiff
    Paul V. Facchina, Sr.
    Kelly A. Green, Esquire, Jennifer M. Rutter, Esquire, SMITH, KATZENSTEIN &
    JENKINS LLP, Wilmington, Delaware; Jeffrey Gans, Esquire, PILLSBURY
    WINTHROP SHAW PITTMAN LLP, Washington, DC, Attorneys for ICA Tech and
    Empresas ICA.
    Joelle E. Polesky, Esquire, STRADLEY RONON STEVENS & YOUNG, LLP,
    Wilmington, Delaware; Timothy E. Heffernan, Esquire, Jonathan R. Wright,
    Esquire, WATT TIEDER HOFFAR & FITZGERALD, L.L.P., McLean, Virginia,
    Attorneys for Plaintiff Facchina Construction Company, Inc.
    I. INTRODUCTION AND PROCEDURAL BACKGROUND
    This consolidated action consists of two lawsuits arising out of the purchase
    of various construction businesses (the “Facchina Companies”), including Facchina
    Construction Company, Inc. (“Facchina Construction Company” or “FCCI’) and
    Facchina Construction of Florida, LLC. On June 28, 2013, Paul V. Facchina, Sr.
    SE
    (“Mr. Facchina” or “Seller Representative”) acting on his own behalf and for entities
    created or owned by him (collectively, the “Sellers”), and ICA Tech Corporation
    (“ICA Tech”) entered into a Purchase and Sale Agreement (“PSA”). ICA Tech’s
    parent, Empresas ICA (“Empresas” and together with ICA Tech, “ICA
    Tech/Empresas”’), was a party to the PSA as a guarantor.
    In mid-September 2017, Mr. Facchina filed suit against ICA Tech and
    Empresas, seeking a declaration that ICA Tech/Empresas owe the Sellers an
    Acceleration Payment of $30,647,509 and that certain escrow funds plus earnings
    thereon should be released to him as part of that payment. Under the PSA, Sellers
    were granted a contingent right to receive future payments from FCCI based on the
    annual financial performance of the Facchina Companies over a three- to five-year
    period (“Earn-Out Payments”). Empresas guaranteed FCCI’s obligations in this
    regard. The right to these Earn-Out Payments by FCCI could be accelerated if ICA
    Tech sold “all or substantially all of the assets” of the [Facchina] Companies, taken
    as a whole as they then currently existed, to an unaffiliated Third Party Purchaser
    and such Third Party Purchaser did not “assume or guaranty” the Sellers’ Earn-Out
    rights.!
    | PSA § 1.8(a), (e), p. 7, 10-11 (JX-27).
    Mr. Facchina alleges the subject June 2013 PSA projected that he would earn
    This figure represents about
    $35-40 million over the ensuing three to five years.
    40% of the consideration Mr. Facchina would receive from the sale.*?_ Additionally,
    ICA Tech would fund a $3.5 million escrow account with Wells Fargo for “payment
    of any outstanding indemnifications claims.”4 Both Mr. Facchina and ICA Tech
    now want those escrow funds. But Wells Fargo will not release them without a court
    judgment or the parties’ consent.’ An additional $2.25 million was withheld “as part
    of the final working capital adjustments from the cash that [Mr. Facchina] received
    at closing” to act as a reserve to indemnify a potential outstanding claim incurred by
    the Facchina Companies.°
    Mr. Facchina alleges that ICA Tech has only paid $4,352,491 of these
    amounts, of which $3.5 million went to escrow and $852,491 went to Mr. Facchina.’
    Mr. Facchina claims he contacted ICA Tech multiple times between 2015 and 2017
    about the status of the Facchina Companies and the Earn-Out Payments but received
    2 Seller Representative’s Compl. (D.I. 1) at 4 1.
    >
    Id. 4
    Id. at 
    992, 28.
    5
    Id. at
    935.
    °
    Id. at
    7 30.
    7
    Id. at
    | 40-41.
    no response.* In turn, Mr. Facchina, as Seller Representative, demanded an
    Acceleration Payment of $30,647,509 by September 5, 2017.2 ICA Tech didn’t
    respond to that request either.'°
    Instead, in October 2017, FCCI filed suit against Mr. Facchina and Facchina
    family members and trusts. FCCI is seeking a money judgment against Sellers in
    the Adjusted Principal Amount of $6,814,303.08 plus costs, pre- and post-judgment
    interest, and attorney’s fees arising from Seller’s indemnification obligations under
    the PSA related to the “Silver Spring Matter” (Count I). FCCI is also seeking a
    money judgment for prevailing party attorney’s fees under PSA § 11.23 (Count II).
    Additionally, FCCI is seeking a declaratory judgment that Sellers are not entitled to
    the $3.5 million held in escrow (the “Escrowed Funds’), which were earmarked as
    security for Sellers’ indemnification obligations for the Silver Spring Matter (Count
    III).
    In late October 2017, ICA Tech/Empresas answered and filed a counterclaim
    in Mr. Facchina’s mid-September suit. And in June 2018, ICA Tech/Empresas
    amended its counterclaim. The amended counterclaim seeks the return of the
    $55 million ICA Tech paid for the Facchina Companies. It says Mr. Facchina
    8
    Id. at
    J 44-45.
    9
    Id. at
    450.
    10 Jd. at 951.
    fraudulently induced ICA Tech to buy the Facchina Companies by making false
    representations that concealed material adverse information about the Facchina
    Companies including the Grove at Grand Bay project (“Grove”). ICA Tech also
    contends that the escrowed $3.5 million plus earnings thereon should be released to
    ICA Tech. Finally, ICA Tech seeks punitive damages against Mr. Facchina
    personally, interest on the $55 million, and reimbursement of its reasonable
    attorney’s fees and costs.
    II. THE TRIAL
    The Court conducted a five-day bench trial and all parties submitted post-trial
    briefing and certain motions. The respective cases were deemed fully submitted for
    decision in July 2020.
    During trial, the Court heard from and considered the testimony of the
    following witnesses:
    Paul V. Facchina, Sr.
    Dolores Laputka, Esquire
    Jennifer Wade Carpenter (by deposition)
    Patrick Wielinski!!
    '!_ Mr. Facchina presented Wielinski as his expert witness on insurance coverage and policies.
    See Del. R. Evid. 702. The Court found Wielinski to be a credible witness. But FCCI objected to
    Wielinski’s testimony, arguing that his opinions do not meet the standards for admissible expert
    testimony under Delaware law because it constitutes improper legal opinion on matters of law
    reserved for this Court. See MG. Bancorporation, Inc. v. LeBeau, 
    737 A.2d 513
    (Del. 1999)
    (adopting the federal Daubert holding and analysis for determining the admissibility of and use of
    expert testimony”). While the Court found Wielinski to be a credible witness and his testimony
    of assistance in certain regards, any testimony the Court considered to have crossed the line into
    -5-
    Leslie A. Nicholson
    Rodrigo Quintana
    Charles McPherson
    Adrian Bastianelli, III, Esquire
    Charles W. Langfitt
    The parties also submitted an extensive number of exhibits, most of which were
    admitted without objection and are cited herein by their designations as joint
    exhibits.
    Ii. FINDINGS OF FACT
    It is difficult at times in the trial of certain actions to fully and cleanly
    segregate findings of fact from conclusions of law. So to the extent any one of the
    Court’s findings of fact here might be more appropriately viewed as a conclusion of
    law, that finding of fact may be considered the Court’s conclusion of law on that
    point.'?
    A. THE PARTIES
    Mr. Facchina is a citizen of the State of Maryland. He is named in these
    actions individually, in his capacity as the Seller Representative under the PSA, and
    improper legal opinion was simply disregarded by the Court during its deliberations. E.g. Penn
    Mut. Life Ins. Co. v. Espinoza, 
    70 F. Supp. 3d 628
    , 635 (D. Del. 2014) (striking rebuttal expert
    testimony that offered improper legal opinion).
    12 See FlowShare, LLC v. GeoResults, Inc., 
    2020 WL 1921019
    , at *2 (Del. Super. Ct. Apr. 2,
    2020) (citing Reserves Dev. LLC v. Crystal Props., LLC, 
    986 A.2d 362
    , 367 (Del. 2009); Osborn
    ex rel. Osborn v. Kemp, 
    991 A.2d 1153
    , 1158 (Del. 2010); Bay City, Inc. v. Williams, 
    2 A.3d 1060
    ,
    1061-62 (Del. 2010)).
    as Trustee for the Paul V. Facchina Revocable Trust organized under the Trust
    Agreement dated November 18, 1993 (“Facchina Revocable Trust”)."°
    FCCI was formed by Mr. Facchina in 1987. FCCI is a corporation organized
    and existing under the laws of the State of Maryland with its principal place of
    business located in La Plata, Maryland.'* FCCI provides a wide range of
    construction services.!°
    ICA Tech is a Florida-based subsidiary of Empresas, a Mexican based
    company.'© Empresas is a Mexican corporation and is a parent of ICA Tech.
    B. RELEVANT PROVISIONS OF THE PSA
    In June 2013, FCCI and ICA Tech entered into the PSA, whereby FCCI was
    sold to ICA Tech. Mr. Facchina was designated as the “Seller Representative” with
    the authority to act on behalf of the Seller.
    The indemnity provision in § 9.9 of the PSA provides:
    Any settlement or compromise made or caused to be made by the
    Indemnified Person or the Indemnifying Person, as the case may be, of any
    such claim, suit, action or proceeding of the kind referred to in Section 9.8
    shall also be binding upon the Indemnifying Person or the Indemnified
    Person, as the case may be, in the same manner as if a final judgment or decree
    had been entered by a court of competent jurisdiction in the amount of such
    13° Second Am. Joint Pretrial Stipulation and Order (“PTO”) at J 2 (D.I. 144).
    4
    Id. at
    91.
    '5 Trial Tr., Nov. 18, 2019, at 14 (D.I. 145).
    Seller Representative’s Compl. at § 1.
    settlement or compromise; provided, that . . . (11) the Indemnified Person shall
    not compromise or settle any claim, suit, action or proceeding without the
    prior written consent of the Indemnifying Person, which such consent shall
    not be unreasonably withheld."”
    In contrast, § 9.8 is a general catch-all provision for unspecified indemnity
    claims of which Sellers did not already have knowledge:
    The Indemnified Person shall give notice as promptly as is reasonably
    practicable to the Indemnifying Person of the assertion of any claim (or
    the commencement of any suit, action or proceeding) by any
    unaffiliated Person not a party hereto (other than by a Governmental
    Authority with respect to Taxes, which shall be governed by Section
    4.13(e)) in respect of which indemnity may be sought under this
    Agreement...!®
    Section 9.2(e) of the PSA details FCCI’s Silver Spring Matter indemnity
    claims and general provisions. It states that
    Each Seller, jointly and severally, agrees to indemnify, subject to the
    limitations of this Article [X, each of the Purchaser Indemnified Parties
    against, and agrees to hold each of them harmless from, any and all
    Losses incurred or suffered by them relating to or arising out of or in
    connection with any of the following:
    (e) the Silver Spring Matter.!”
    '7 PSA § 9.9, p. 77.
    18 Jd.§ 9.8, p. 76.
    19
    Id. at
    § 9.2(e), p. 73.
    The PSA is “a binding, valid, and enforceable agreement to which the Defendants
    are parties.”*° Each Seller in this Litigation is a “Seller,” as defined in the PSA.7!
    Sellers stipulated that “FCCI is a Purchaser Indemnified Party (as defined in the
    PSA).””?. Therefore, the PSA requires the Sellers to indemnify FCCI for all “Losses
    incurred or suffered by them relating to or arising out of or in connection with...
    the Silver Spring Matter.””?
    Section 11.23 defines “Loss”:
    “Loss” or “Losses” shall mean any and all actual losses,
    liabilities, costs, claims, damages, penalties and expenses (including
    attorneys’ fees and expenses and costs of investigation and litigation).
    In the event any of the foregoing are indemnifiable hereunder, the terms
    “Toss” and “Losses” shall include any and all reasonable attorneys’
    fees and expenses and costs of investigation and litigation incurred by
    the Indemnified Person in enforcing such indemnity.**
    The definition of “Losses” includes the enumerated categories of damages in
    the first sentence, and the second sentence requires award of attorney’s fees and costs
    of investigation where any one of the “Losses” in the first sentence arises.”
    20 FCCI’s Statement of Facts Admitted at Trial (““FCCI’s SOF”) at ¥ 12 (D.I. 156).
    21
    Id. at
    4 13.
    22 Td. at 4 15.
    23 PSA § 9.2(e), p. 73.
    24
    Id. at
    § 11.23, p. 101.
    23 FCCI’s SOF at 19.
    The definition of “Silver Spring Matter” consists of a predicate, three clauses
    specifying events that are expressly included in the definition, and a final section
    listing specific types of “Losses” for which Sellers must indemnify FCCI.° The
    predicate of the “Silver Spring Matter” definition includes, “[a]ll Proceedings and
    Liabilities . .. made, threatened or otherwise asserted or established by Foulger-
    Pratt Contracting, LLC ... against [FCCI]....”:
    [A]ll Proceedings and Liabilities (including any tort, contract, statutory
    other claims) made, threatened or otherwise asserted or established by
    Foulger-Pratt Contracting, LLC, Montgomery County, Maryland or
    any of their respective successors, assigns, representatives, or Affiliates
    or any other Person claiming by, through or on behalf of any of them
    against the Companies, the Acquired Subsidiaries or any Purchaser
    Indemnified Party) [sic] with respect to, relating to or arising out of . .
    27
    The PSA defines “Proceeding” as, “any litigation, action, suit, proceeding,
    charge, claim, complaint, demand, inquiry, investigation, audit, hearing, arbitration
    or Order.”?8 The PSA defines “Liabilities” as “any direct or indirect liability,
    indebtedness, obligation, commitment, expense, claim, deficiency, guaranty or
    endorsement of or by any Person of any time, whether accrued, absolute, contingent,
    matured, unmatured, liquidated, unliquidated, known or unknown.””? FCCI is
    6 Jd. at § 20.
    27 PSA § 11.23, p. 106.
    8
    Id. at
    p. 104.
    29
    Id. at
    p. 101.
    -10-
    
    defined as a “Company” and a “Purchaser Indemnified Party” in the PSA.*°
    The term “Silver Spring Matter” includes the Silver Spring Transit Center
    (“SSTC”) Lawsuit and any “Liabilities” arising from or related to the specified
    1
    events in the following three clauses.*! Clause (i) encompasses non-conforming
    work at the SSTC project (““SSTC Project”):
    (i) allegedly nonconforming concrete or other allegedly nonconforming
    or defective work at the Silver Spring Transit Center including matters
    identified in the KCE Report....
    Clause (ii) encompasses any breach of the subcontract between FCCI and Foulger-
    Pratt:
    (ii) any breach of or failure to perform the subcontract with Foulger-
    Pratt Contracting, LLC or any other contract or arrangement with
    Foulger-Pratt Contracting, LLC, Montgomery County, Maryland or
    any of their respective successors, assigns, representatives or Affiliates
    or any other Person claiming by, through or on behalf of any of them
    related to the Silver Spring Transit Center . . .*?
    Clause (iii) encompasses amounts contemplated by the Retention Agreement, Joint
    Defense Agreement, or similar agreements: “any amounts payable or reimbursable
    under the Retention Agreement or Joint Defense Agreement or any similar
    39 Jd. at p. 1 (identifying the “Companies”);
    id. at p. 104
    (definition of “Purchaser Indemnified
    Parties”); FCCI’s SOF at § 15 (FCCI is a Purchaser Indemnified Party).
    3! PSA § 11.23, p. 106.
    2 Td.
    -l1-
    arrangement... .”33
    The final portion of the definition of the “Silver Spring Matter” is a non-
    exhaustive list of the types of “Proceedings, Liabilities or Losses” specifically
    included in Sellers’ indemnity obligations:
    including in each case, any Proceedings, Liabilities, or Losses related
    to delay of the project, repair or replacement of nonconforming work,
    any indemnification obligations and any legal fees, defense costs,
    consulting or other advisor fees, engineering, evaluation and design or
    investigation costs, liquidated damages, failure to collect on retentions,
    holdbacks or loan amounts or failure to collect any accounts receivable
    related thereto and any amounts owed to subcontractors with respect to,
    relating to, or arising out of any of the matters described in clause (1),
    (ii) or (iii) of this definition.*“
    FCCI suggests that claims arising under PSA 9.2(e) are different than general
    indemnify claims under the other general subsections and that the “Silver Spring
    Cap Amount” should be treated differently than the “General Cap Amount” in
    § 9.5.3° Further, FCCI asserts that the parties intended the Silver Springs claims
    were not to be included in the general provisions and therefore did not require
    additional notice. FCCI also claims that even if it did breach § 9.9, it was not a
    material breach.*°
    33
    Id. 4
    Id.
    35 
    FCCI’s Post-Trial Opening Br. at 6-7 (D.I. 154).
    36 Td.
    -12-
    C. THE ESCROW AGREEMENT
    Pursuant to the PSA, Purchaser entered into an escrow agreement (“Escrow
    Agreement”) around July 2015 with Mr. Facchina, as Seller Representative, and the
    escrow agent, Wells Fargo N.A. Under the PSA, the first $3.5 million of any Earn-
    Out monies was to be placed in an Escrow Account with Wells Fargo, to pay third-
    party claims that might be asserted against the business arising from acts or
    omissions that occurred prior to closing.7’ Section 9.11 of the PSA details the
    Escrow Agreement and states:
    Purchaser shall deposit on behalf of Sellers, to the extent funds are
    available therefor, the amount of $3,500,000 in escrow, to be held and
    disbursed in accordance with the terms of the Silver Spring Indemnity
    Escrow Agreement (the “Escrowed Funds”), from the first dollars of
    the Earn-Out Payments... The Escrowed Funds shall be held as security
    and used for payment of Sellers’ indemnification obligations with
    respect to claims made from time to time by the Purchaser Indemnified
    Parties in respect of the Silver Springs Matter or any other matter as
    provided in this Section 9.11 in accordance with the terms of the Silver
    Spring Indemnity Escrow Agreement.*®
    In August 2015, the Escrow Account was funded—all of the first $3.5 million
    of Earn-Out money having been transferred thereto and available for the Silver
    Spring Claim. That $3.5 million remains with Wells Fargo.*
    37, PTO at F 38.
    38 PSA § 9.11, p. 77.
    39 Trial Tr., Nov. 18, 2019, at 201-02.
    AL
    Section 9.11 of the PSA is clear that Sellers’ indemnification obligations are
    not limited to the Escrowed Funds.*® Rather, Sellers’ indemnification obligations
    are limited to the “Base Purchase Price plus any Earn-Out Payments.”*! And where
    any Losses are caused by “fraud, intentional misrepresentation or any intentional
    breach of [the PSA],” there is no limit on Sellers’ liability.”
    D. THE SILVER SPRING TRANSIT CENTER LITIGATION
    On September 3, 2008, Montgomery County, Maryland (“MontCo”) entered
    into a contract (“Prime Contract”) with Foulger-Pratt Contracting, LLC for the
    construction of the Silver Spring Transit Center in Montgomery County, Maryland.*
    The SSTC Project was intended to be turned over to the Washington Metropolitan
    Area Transit Authority (“WMATA”) to operate upon completion.“4 On December
    5, 2008, Foulger-Pratt entered a subcontract (“Subcontract”) with FCCI to serve as
    the concrete subcontractor on the SSTC Project. In March 2018, Travelers
    40 PSA § 9.11, p. 78 (“[T]he Escrowed Funds shall not be a limitation on Sellers’ indemnification
    obligations with respect to any indemnification matter, including the Silver Spring Matter. . .”).
    41 Td. at § 9.5(b), p. 75 (“The Sellers’ aggregate liability under this Agreement for indemnification
    shall not exceed the Base Purchase Price plus any Earn-Out Payments earned hereunder.”); FCCI’s
    SOF at 21.
    42, PSA § 9.5(c), p. 75; FCCI’s SOF ¥ 21.
    43 FCCI’s SOF at $5.
    “
    Id. 4
    Id. at 
    4 6.
    -14-
    provided a performance bond on behalf of FCCI to ensure its performance on the
    SSTC Project. That bond remained in full force and effect for the entire contract
    period.*® In approximately 2011, a dispute arose concerning alleged construction
    defects at the SSTC Project involving observed cracking of concrete and on the
    major structural decks.*” In January 2012, FCCI and Foulger-Pratt entered into a
    Standstill and Joint Defense Agreement (“JDA”) regarding the SSTC Project,
    including MontCo’s allegations that certain portions of the work were defective
    and/or did not conform with the Prime Contract requirements.*® Travelers paid
    FCCI’s $5 million portion of the MontCo/Foulger-Pratt settlement on FCCI’s behalf
    to settle the SSTC lawsuit, including Foulger-Pratt’s claims against FCCI and its
    bond.*? Travelers paid FCCI’s portion of the WMATA settlement on FCCI’s behalf
    to settle the SSTC lawsuit.°? Also, during the SSTC lawsuit, Travelers paid FCCI’s
    lawyers and FCCI’s consultant.*!
    46
    Id. at
    47.
    47
    Id. at
    8.
    48°
    Id. at
    4. 9.
    49 ECCI Post-Trial Opening Br. at 17; FCCI’s SOF at { 55-64.
    °° FCCI’s SOF at § 57.
    1
    Id. at
    9] 74, 81.
    -15-
    FCCI is seeking indemnity from Sellers for “any and all Losses incurred or
    suffered [by FCCI] relating to or arising out of or in connection with . . . the Silver
    Spring Matter.”°? At PSA § 11.23 the “Silver Spring Matter” definition has
    categories of “Liabilities or Losses” that are indemnifiable thereunder:
    including in each case, any Proceedings, Liabilities or Losses relating
    to delay of the project... any indemnification obligations and any legal
    fees .. . consulting or other advisor fees .. . and any amounts owed to
    subcontractors with respect to, relating to, or arising out of any of the
    matters described in clause (i), (ii), or (iii) of this definition.*
    That same definition’s clause (i) encompasses non-conforming or defective work at
    the SSTC project; while clause (ii) encompasses any breach of the subcontract
    between FCCI and Foulger-Pratt; and, clause (iil) encompasses amounts
    contemplated by the Retention Agreement, Joint Defense Agreement or similar
    agreements.’
    FCCI argues that Sellers refuse to indemnify it for “Losses” incurred in the
    SSTC lawsuit that include: (i) payments Travelers made on FCCI’s behalf to settle
    the SSTC lawsuit and legal fees and consulting fees related to the SSTC lawsuit; and
    °2 FCCI’s Post-Trial Reply Br. at 3 (D.I. 165).
    3 PSA § 9.2(e), p. 73; PSA § 11.23, p. 106.
    4 PSA § 11.23, p. 106.
    -16-
    (ii) uncovered retainage and unrecovered claims for delays and pour strip work on
    the SSTC Project.°>
    ICA Tech asserts that after Travelers paid over $5.5 million in May 2017 to
    settle the liabilities faced under the bond issued to FCCI with respect to the Silver
    Spring Matter, Travelers demanded that ICA Tech obtain the $3.5 million that had
    been escrowed by Sellers to protect ICA Tech from liabilities related to the Silver
    Spring Matter.°° ICA Tech says that because it was prohibited from obtaining the
    escrowed funds it was forced to settlement its overall liabilities to Travelers for $80
    (rather than 76.5) million.>”’
    As a party to the Escrow Agreement, on June 30, 2017, ICA Tech caused the
    Silver Spring Claim Statement to be sent to the Escrow Agent, Mr. Facchina, and
    Mr. Facchina’s counsel demanding payment of $9,259,949.01 in “Losses” that FCCI
    sustained related to the Silver Spring Matter, and release of the Escrowed Funds as
    partial payment therefor.°* The Silver Spring Claim Statement described FCCI’s
    “Losses” as follows:
    [C]ertain actual losses, liabilities, costs, claims, damages and expenses
    (including certain attorneys’ fees and expenses) that Facchina [FCCI]
    33 FCCI’s SOF at 4 41(a)-(c).
    °6 ICA Tech/Empresas’s Post-Trial Opening Br. at 18-19 (D.I. 157).
    7
    Id. at
    19.
    8 FCCI’s SOF at 9 91.
    -|7-
    has incurred (including those that Facchina’s bonding company,
    Travelers Casualty and Surety Company of America asserts that it has
    incurred on Facchina’s behalf) in connection with the Silver Spring
    Matter . . .>?
    The Silver Spring Claim Statement specified the categories of damages for which
    indemnity was demanded.® Further demand for indemnity was made by FCC]
    through its bonding company, Travelers.°! On July 11, 2017, Travelers sent a letter
    on behalf of FCCI demanding payment in the amount of $9,259,949.01 for “certain
    actual losses, liabilities, costs, claims, damages and expenses (including certain
    attorneys’ fees and expenses) that [FCCI] and Travelers have incurred in connection
    with the Silver Spring Matter.” The July 11, 2017 Travelers letter identified the
    same eight categories of “Losses” under the PSA as in the Silver Spring Claim
    Statement.” Finally, FCCI’s Complaint sought indemnification.“
    Travelers paid FCCI’s portion of the MontCo/Foulger-Pratt and WMATA
    settlements that FCCI asserted as claims for retainage, delay, and pour strips in the
    °° -JX-241 (Silver Spring Claim Statement) at 3.
    60 Jd. at 3-4.
    61 FCCI’s SOF at § 92-93.
    62 JX-243 (Travelers Demand Letter) at 2; FCCI’s SOF at 4 93.
    63 JX-243 at 2-3; JX-241 at 3; Trial Tr., Nov. 21, 2019, at 118-212; FCCI’s SOF at ff 91, 93.
    64 FCCI’s SOF at 4 98.
    -18-
    SSTC lawsuit.” In response to the Silver Spring Claim Statement, Mr. Facchina
    sent an Objection Notice dated July 26, 2017 challenging FCCI’s rights to indemnity
    and release of the Escrowed Funds.°® Mr. Facchina admits that he objected to the
    Silver Spring Claim Statement. Mr. Facchina also refused to pay Travelers in
    response to Travelers’ July 11, 2017 letter.°’
    Charles McPherson, FCCI’s CEO, confirmed that FCCI never received
    payment for its affirmative claims in the SSTC lawsuit. Adrian Bastianelli, Esquire,
    of Peckar & Abramson (“Peckar”), FCCI’s lawyer during the SSTC lawsuit, testified
    that Travelers paid his legal bills and those of David Anderson, FCCI’s consultant
    in the SSTC lawsuit.© Charles Langfitt of Travelers testified that Travelers
    advanced funds on FCCI’s behalf for the MontCo/Foulger-Pratt and WMATA
    settlements, Peckar’s legal fees, and David Anderson’s consulting fees.© And,
    Langfitt told the Court, Travelers has received no reimbursement for any of those.””
    65 Seller Representative’s Compl. at $6; JX-239 (Travelers’ wire transfer for $5,000,000 for
    MontCo/Foulger-Pratt settlement); see also FCCI’s SOF at 4 50, 57.
    66 JX-246 (Mr. Facchina’s July 26, 2017 Letter); FCCI’s SOF at { 96.
    67 See JX-247 (Mr. Facchina’s July 27, 2017 Letter); FCCI’s SOF at J 97.
    68 Trial Tr., Nov. 20, 2019, at 18.
    6 Trial Tr., Nov. 21, 2019, at 106-30; JX-229 (Travelers $583,333.34 Wire Transfer to
    WMATA); see also FCCI’s SOF at 950.
    7 Trial Tr., Nov. 21, 2019, at 131-32.
    -19-
    E. THE CONCRETE WORK AT THE GROVE
    Facchina Construction of Florida, LLC (“FCF”) was created by Mr. Facchina
    in October of 2007 to continue his general contracting business in Florida after he
    7l Mr. Facchina is an expert
    had suspended operations by Facchina-McGaughan.
    with respect to concrete and has a sophisticated understanding of the construction
    issues on the projects undertaken by the Facchina Companies.” Mr. Facchina
    testified that concrete packages for construction in Florida could typically be
    3 Mr. Facchina also
    procured in a range from five to eight different packages.’
    testified that parceling out concrete work to various subcontractors is a common
    practice. He explained that Facchina-McGaughan had procured anywhere from five
    to eight different concrete packages for its condominium tower projects.”* He also
    testified that it previously “broke up” the concrete packages for each of the three
    Brickell condominiums in various ways.’”> Mr. Facchina testified that in Maryland,
    7 JX-27 (PSA Exhibit G -- Form of Shop Lease (9320 W&W Industrial Road) - Schedule 2.5(a)
    Financial Statements Facchina Group of Companies) at p. 292; Trial Tr., Nov. 18, 2019, at 21-22,
    28.
    72 Trial Tr., Nov. 20, 2019, at 52-53.
    3 Trial Tr., Nov. 18, 2019, at 35.
    4
    Id. at
    41.
    3
    Id. at
    42.
    -20-
    Northern Virginia, and Washington, D.C., FCCI regularly “broke up” concrete
    packages.’°
    McPherson testified that, as a matter of operational policy, FCF would not
    break up the concrete work under its general contracts, as had been done by
    Facchina-McGaughan.’’ The record shows that FCF consistently followed this
    policy of assigning the concrete work to a single subcontractor until the Grove
    project.”
    Sometime in early 2012, Jesus Vazquez approached Mr. Facchina for
    permission to pursue construction of the Grove, a proposed new condominium
    project.” The Grove project was more complex because its geometry was so
    unconventional.®° The twisting concrete floors of the condo towers were supported
    by a “big steel structure in the core of the building that was very unusual.”*! As
    such, this was Mr. Facchina’s companies’ first time working on a project with this
    76
    Id. at
    54-55.
    7 Trial Tr., Nov. 20, 2019, at 69-70.
    78 JX-299 (Schedule 2.12(b)) at 8, 31 (Phase J), 33 (Phase II); JX-307 (Agreement Between Coral
    Gables and FCF) at 5; JX-27 at 542.
    19 Trial Tr., Nov. 18, 2019, at 29.
    80 Trial Tr., Nov. 20, 2019, at 69-70 (“Q. And do you know that the Grove at Grand Bay has that
    somewhat unique twisting aspect to it? A. It’s got a geometry feature to it. That’s all.”).
    81 Trial Tr., Nov. 20, 2019, at 80.
    Fi «
    twisting geometry.®? Mr. Facchina’s approval to take on Grove had been given on
    the express condition that the concrete work would not be broken up.®’ Indeed, both
    Mr. Facchina and McPherson expressly instructed Vazquez not to break up the
    concrete portion of the contract work on the Grove project.**
    FCF and Terra entered into a contract on January 24, 2013, under which FCF
    t.25. Mr. Facchina’s consent was
    agreed to build the Grove under a GMP contrac
    required for Vazquez to execute this contract.*° Mr. Facchina reviewed the estimates
    and made many comments about the structure.®’ The steel and concrete portions of
    the structure were with Mr. Facchina’s area of expertise. Mr. Facchina approved
    the GMP Amendment, in part, because it included “a conditional bond,” which gave
    him “great comfort.”®?
    82 Trial Tr., Nov. 19, 2019, at 21.
    83 Trial Tr. Nov. 19, 2019, at 9; Trial Tr. Nov. 20, 2019, at 71. Mr. Facchina’s sworn deposition
    testimony echoed this fact; he testified that, regarding the concrete work for the Grove, he told
    Vazquez “you buy one package, one package, not multiple, one . . . to perform the concrete portion
    of the contract.” Mr. Facchina Dep., Oct. 5, 2018, at 63.
    84 Trial Tr., Nov. 20, 2019, at 68.
    85 JX-15 (Terra and FCF Agreement).
    86 Trial Tr., Nov. 20, 2019, at 81.
    87 JX-100 (Emails Between Charles McPherson and Les Nicholson March 4, 2016) at 3.
    88 Trial Tr., Nov. 20, 2019, at 79-80.
    89 Trial Tr., Nov. 18, 2019, at 32; JX-302 (Facchina Construction of Florida Guaranteed
    Maximum Price for the Grove) at 138-41.
    -22-
    The description of the concrete packages in the GMP amendment matches the
    breakdown in JX-17 (GMP spreadsheet), in terms of the work to be done and the
    “Final Bought Prices” for each package.” The prices in the Capform, C+C, and
    Titon subcontracts in the record exactly match the “Final Bought Prices” shown in
    t.2! When Mr. Facchina reviewed and
    the GMP amendment to the Grove contrac
    approved the GMP amendment, ICA Tech/Empresas allege that he knew, at least by
    then, that the concrete portion of the work had been awarded to separate contractors
    because at the Facchina Companies, the word “Bought” meant awarded to a separate
    contractor, i.e., the package is procured.”
    Mr. Facchina testified that he was generally aware that there were forty to fifty
    different subcontractors working at the Grove, but that he was not familiar with the
    details regarding the subcontractors or subcontracts.”? Mr. Facchina testified that he
    was unaware of the number of concrete packages awarded by Vazquez and did not
    participate in procuring them.”* After the closing, around mid-2015, Mr. Facchina
    90 -JX-302 at 4-5.
    9! JX-119 (Subcontract Agreement for Concrete Formwork at the Grove) at 4; JX-23
    (Subcontract Agreement for Concrete Pump: Place and Finish Work at the Grove) at 4; JX-28
    (Subcontract Agreement between FCCI and Titon) at 31, 127; JX-302 at 4.
    2 Trial Tr., Nov. 18, 2019, at 38.
    3 Td. at 43.
    4
    Id. at
    56.
    -23-
    heard for the first time that Vazquez retained more than one concrete subcontractor
    for the Grove, but he did not know the extent to which the concrete packages were
    separated.”°
    In reviewing the Grove concrete subcontracts during the pendency of this
    litigation, Mr. Facchina found that the FCF procurement team followed his initial
    advice by procuring fewer concrete packages.”° Mr. Facchina explained at trial that
    the procurement team did a “masterful” job for awarding only three concrete
    subcontracts, which was fewer than there had been awarded in previous FCF and
    Facchina-McGaughan projects that were comparable to the Grove.”’
    In connection with the potential purchase of the Facchina Companies, ICA
    Tech/Empresas_ conducted exhaustive due diligence that occurred over
    8 During the due diligence process with ICA
    approximately two years.
    Tech/Empresas, Mr. Facchina witnessed ICA Tech/Empresas representatives visit
    FCCI’s home office in La Plata, Maryland.”’ He also directed McPherson to provide
    9
    Id. at
    58-59.
    % Jd. at 50-51, 54; Trial Tr., Nov. 19, 2019, at 164-65.
    7 Trial Tr., Nov. 18, 2019, at 50-51, 54; Trial Tr., Nov. 19, 2019, 164-65.
    % Trial Tr., Nov. 20, 2019, at 133-34; Trial Tr., Nov. 21, 2019, at 189.
    °° Trial Tr., Nov. 18, 2019, at 95-96.
    -24-
    any and all information to them.'°° McPherson (who was Sellers’ due diligence point
    person) testified that there were several layers of ICA Tech/Empresas due diligence,
    including business, legal, and accounting.'°’ He testified that any requested
    ? and that nothing was held
    information was provided to ICA Tech/Empresas'®
    back.!%
    As part of the due diligence process and during the approximately sixteen
    months from January of 2013 until closing on the purchase in April of 2014, sellers
    uploaded voluminous document electronically into a data room that were available
    to be viewed by the buyers and their representatives.’ Rodrigo Quintana (“R.
    Quintana”), ICA Tech/Empresas’ former general counsel and its current Chief
    Financial Officer, testified that at least twenty people working on ICA
    Tech/Empresas’s behalf had access to the data room.' He explained that ICA
    Tech/Empresas had legal, accounting, business, and outside specialists conducting
    100 Td. at 95-96, 100.
    101 Trial Tr., Nov. 20, 2019, at 134.
    102 7g
    103 Td. at 136, 188.
    104 PTO at 9 43.
    105 Trial Tr., Nov. 21, 2019 at 173.
    -25-
    its due diligence.'!°° McPherson, who supervised the data room, directed his team to
    place the required documents into the data room.'®’ He also directed his team to
    place all information required into the contract schedules attached to the PSA.'°°
    Jennifer Wade Carpenter, a member of McPherson’s team and former FCCI
    employee, testified via deposition that she was charged with gathering FCCI’s
    contracts, preparing the contract schedules to the PSA, and uploading documents,
    both from FCF and FCCI, into the data room.’ The Grove subcontracts for
    Capform, C&C and Titon, were placed in the data room in July 2013, nearly nine
    months before closing.'!°
    All concrete subcontractors were identified in the PSA’s contract schedules.'!!
    Quintana admitted that he does not know whether anyone on behalf of ICA
    Tech/Empresas even looked for the concrete subcontracts in the data room.!!?
    106 Yq at 157.
    107 Trial Tr., Nov. 20, 2019, at 136.
    108 Td. at 137-38.
    109 Trial Deposition of Jennifer Wade Carpenter (“Carpenter Dep.”), Oct. 30, 2019, at 24-25, 38-
    39 (DI. 143).
    110 JX.279 (Screenshot of Database C&C folder); JX-281 (Screenshot of Database Capform
    folder); JX-297 (Screenshot of Database Titon folder).
    11 JX-299 (Schedule 2.12(b) Material Contracts) at 36, 61, 62; Trial Tr., Nov. 21, 2019, at 203.
    12 Trial Tr., Nov. 21, 2019, at 174-75.
    -26-
    Quintana admitted that he does not know whether anyone even asked questions
    about the Grove contract even though the operations of FCF were “very important”
    to ICA Tech/Empresas.! Mr. Facchina had no role in preparing or reviewing any
    of the contract schedules attached to the PSA.'!* And he never directed anyone to
    withhold any information from the data room or Ito eave any information out of the
    PSA’s schedules.!"°
    After ICA Tech’s purchase of the Facchina Companies, Mr. Facchina was
    named Chairman of FCCI’s Board of Directors.''® The board’s members were Mr.
    Facchina, Alonso Quintana, and Ruben Lopez.'!’ As Mr. Facchina understood it,
    Alonso Quintana was ICA Tech’s Chief Executive Officer and Ruben Lopez was its
    Chief Operating Officer.!'® FCCI’s officers were McPherson, Chief Executive
    Officer, Paul Kravic, Chief Financial Officer, and Jesus Vazquez, Chief Operating
    3 Trial Tr., Nov. 18, 2019, at 98-99; Trial Tr., Nov. 21, 2019, at 192-93; Carpenter Dep. at 31,
    Oct. 30, 2019, at 46.
    4 Trial Tr., Nov. 18, 2019, at 99.
    115 Trial Tr., Nov. 18, 2019, at 100; Trial Tr., Nov. 20, 2019, at 137-38; Trial Tr., Nov. 21, 2019,
    at 188.
    16 Tyial Tr., Nov. 18, 2019, at 105.
    117 1X-52 (FCCI Board of Directors Meeting Minutes June 20, 2014); Trial Tr., Nov. 18, 2019, at
    106.
    "8 JX-52: Trial Tr., Nov. 18, 2019 at 107.
    -27-
    Officer.'!9 An executive committee was then formed to oversee day-to-day
    company operations.!”° The executive committee was composed of McPherson,
    Vazquez, Antonio Sordo and Rafael Rodriguez.'”! Antonio Sordo and Rafael
    Rodriguez were both officers of ICA Tech/Empresas. Mr. Facchina was not a
    member of the executive committee.'?? R. Quintana acknowledged that it was the
    executive committee that ran all FCCI operations post-closing and provided strategic
    advice.!?8
    McPherson testified that after the sale, FCCI and ICA Tech/Empresas began
    to face a multitude of financial challenges and operational difficulties, only some of
    which related to the Grove.!*4
    During 2015, the project architect began to identify defects with the concrete
    work that resulted in FCF not being paid on a monthly basis. This caused serious
    cash flow problems for FCF. The defects were not being corrected by the concrete
    subcontractors because of disputes among them and with FCF as to who was
    119 JX- 52; Trial Tr., Nov. 18, 2019 at 108-09.
    120 JX-52: Trial Tr., Nov. 18, 2019, at 105; Trial Tr., Nov. 21, 2019, at 155.
    121. Trial Tr., Nov. 18, 2019, at 110.
    122 Iq: Trial Tr., Nov. 20, 2019, at 147-48; Trial Tr., Nov. 21, 2019, at 179-80.
    123 Trial Tr., Nov. 21, 2019 at 155.
    124 Trial Tr., Nov. 20, 2019 at 172-76, 215-16.
    -28-
    responsible. FCF incurred substantial expenses bringing in additional labor and
    contractors to correct the defects. There were claims that breaking up the work
    among the various subcontractors had resulted in gaps between the scope of work
    for the various subcontractors and the overall scope of FCF’s responsibility.
    Ultimately, both Capform and C&C were placed in default by FCF.'”
    According to McPherson, the multitude of financial challenges and
    operational difficulties related to the Grove only manifested themselves as the Grove
    progressed.'* The Grove had a gross profit of $1,697,160 as of December 31,
    2014.!27 On April 9, 2015, McPherson and FCCI’s Chief Financial Officer, Kravic,
    sent a letter to Deloitte identifying, among other things, certain issues and concerns
    facing the Grove.!”8 The letter does not mention any problems caused by or relating
    to having three concrete subcontractors at the Grove.!”?
    McPherson acknowledged that the letter does identify a 46-day delay in
    construction caused by the Grove’s steel subcontractor, SteelFab. McPherson
    125 Trial Tr., Nov. 21, 2019, at 30-35; JX-81 (Capform Incorporated Default SDI Claim, December
    31, 2015) and JX-82 (C&C Concrete Pumping Default SDI Claim, December 31, 2015).
    126 Trial Tr., Nov. 20, 2019, at 144.
    127 JX-65 (FCCI Board of Directors Meeting May 15, 2015) at 85; Trial Tr., Nov. 18, 2019, at
    115.
    128 JX-65 at 96; Trial Tr., Nov. 18, 2019, at 117.
    129 JX-65 at 96; Trial Tr., Nov. 18, 2019, at 117.
    -29-
    admitted that because of that that delay other subcontractors asserted claims against
    FCF.!3° FCF paid SteelFab $1,000,000 in order to resolve that dispute.!?!
    In addition, in a letter dated April 9, 2015, Deloitte raised concerns regarding
    FCCI’s lack of internal controls. Deloitte wrote, ““We have identified, and included
    in Appendix B, certain matters involving the Company’s internal control over
    financial reporting that we consider to be a significant deficiency under standards
    established by the American Institute of Certified Public Accountants.”!?? These
    deficiencies included lack of journal entry documentation (account reconciliations
    and estimates) and information technology controls. McPherson and Les Nicholson,
    FCCI’s former in-house counsel and ICA Tech/Empresas’ paid consultant in this
    matter, both testified that in or about August, 2015, a new project executive, the
    fourth such person, who is the individual tasked with overseeing an entire project,
    was assigned to the Grove.!**
    McPherson admitted that after the closing, he had made a poor financial deal
    130 JX-65 at 96; Trial Tr., Nov. 20, 2019, at 149-50.
    131 JX-79 (FCCI Consolidated Financial Statements as of December 31, 2015”) at 38; Trial Tr.,
    Nov. 20, 2019, at 151-52; see also JX-113 (Emails Between Charles McPherson, Les Nicholson,
    and Jesus Vazquez, March 18, 2016).
    132 JX-65 at 89; Trial Tr., Nov. 18, 2019, at 118-19.
    133 JX-75 (FCCI Board of Directors Meeting, December 11, 2015) at 6; Trial Tr., Nov. 18, 2019,
    at 120-23; Trial Tr., Nov. 20, 2019, at 158-59 (McPherson: “That’s a lot. And it’s not good.”);
    Trial Tr., Nov. 21, 2019, at 56.
    -30-
    with Terra based on incorrect information he received from FCF regarding the
    Grove’s schedule.'34
    As of November 30, 2015, FCCI’s financial statements, as presented at a
    December 11, 2015 FCCI board meeting, anticipated a profit in excess of $3 million
    for the Grove.!3> Those same financial statements reveal that FCCI anticipated a
    $6,889,000 cash recovery for back charges from contractor default insurance for
    C&C, Capform, and Steelfab.'°° After the December 11, 2015 board meeting, it is
    undisputed no other board meetings occurred for approximately nine months.'
    The December 31, 2015 financial statements identify disputes between FCCI
    and Steelfab, GM&P, C&C and Capform.'*? GM&P, like Steelfab, was not a Grove
    concrete subcontractor.!3? McPherson confirmed that on December 31, 2015, FCF
    submitted a subcontractor default insurance (“SDI”) claim related to Capform.'*°
    The amount of that claim was $5,456,678 and related to poor workmanship,
    134 JX-75 at 6; Trial Tr., Nov. 20, 2019, at 159-63.
    135 JX-75 at 10; Trial Tr., Nov. 18, 2019, at 125-26.
    136 JX-75 at 11; Trial Tr., Nov. 18, 2019, at 126-27.
    137 JX-165; JX- 166 (“FCCI Board of Directors Meeting, September 26, 2016”); Trial Tr., Nov.
    18, 2019, at 140-41.
    138 JX-79 at 38-39; Trial Tr., Nov. 18, 2019, at 130-31.
    139 Trial Tr., Nov. 18, 2019, at 131.
    140 JX-81; Trial Tr., Nov. 20, 2019, at 164-65.
    -3]-
    not work coordination.!*! “The work that was rejected, included, but was not limited
    to, defective concrete finishes, work outside of acceptable tolerances, incorrect form
    layout and defective window wall and shower pan depressions.”'*?. McPherson also
    confirmed that on December 31, 2015, FCF submitted a subcontractor default
    insurance (“SDI”) claim related to C&C.'*
    The amount of that claim was $863,000 and, again, related to poor
    workmanship, not work coordination.'‘* The workmanship issues included
    “defective window wall depressions, incorrect balcony edge thicknesses, improper
    vibration/finishing/consolidation and defective shower pan depressions.”!*
    Nicholson testified that he prepared the aforesaid insurance claims on FCCI’s
    behalf.!46
    On March 4, 2016, McPherson wrote an email to ICA Tech’s Rodrigo
    Quintana identifying “serious cash issues” facing FCCI.'*7 When shown this email,
    141 YX-81 at 11.
    142 TX- 81 at 7.
    43 JX-82: Trial Tr., Nov. 20, 2019, at 165.
    144 JX-82 at 8.
    145 X-82 at 6.
    146 Trial Tr., Nov. 21, 2019, at 54.
    147 JX-100 at 5.
    -32-
    McPherson testified that these significant cash flow issues were caused by a
    $5 million loss on a National Park Service job, a $4,352,491 earnout payment, and
    a $6 million investment that was supposed to be reimbursed to FCCI from ICA Tech
    but never was.'*8
    It is undisputed that the June 30, 2016 unaudited internally generated FCCI
    financial documents indicate an anticipated loss of approximately $3,750,000 at
    completion of the $135 million Grove.'*? ICA Tech/Empresas did not prove that
    this alleged loss was a result of the awarding of the concrete subcontracts.
    When shown the above financial documents, McPherson acknowledged that
    they also indicate an approximate $55 million company-wide decrease in revenues
    between the years 2015 and 2016.'°° McPherson testified that between the years
    2015 and 2016 site work was down fifty-three percent and heavy construction was
    down thirty-nine percent.'!
    Nicholson testified that FCCI did not prepare audited financial statements for
    the year 2016.'*? On August 12, 2016, more than two years after closing, McPherson
    148 Trial Tr., Nov. 20, 2019, at 173-77.
    149 JX-139 (FCCI Internal Financial Reports, June 2016); Trial Tr., Nov. 18, 2019, at 135-37.
    150 JX-139 at 4; Trial Tr., Nov. 18, 2019, at 137-38; Trial Tr., Nov. 20, 2019, at 172.
    3! Trial Tr., Nov. 20, 2019, at 173.
    132 Trial Tr., Nov. 21, 2019, at 61.
    -33-
    wrote an e-mail explaining issues with the Grove at Grand Bay to Dolores Laputka,
    Esquire, Mr. Facchina’s counsel, and copied, among others, Mr. Facchina.!”
    When shown this email, McPherson testified that the largest issue facing
    FCCI post-purchase was that the Grove schedule could not be maintained.’
    McPherson testified that he learned of the improper schedule in late 2015 or early
    2016.'>
    Nicholson testified that FCF was responsible for the project schedule.'*
    McPherson testified that the second largest issue facing FCCI post-purchase was the
    lack of civil work in Maryland, which had nothing at all to do with the Grove.'*’
    McPherson testified that third largest issue facing FCCI post-purchase was its
    excessive amount of overhead, which was caused by the increase in the number of
    individuals FCCI had to retain in order to transition from a private company to a
    public one.!*8 McPherson testified that the Grove may have turned out to be a bad
    153 JX-145 (Email Between Charles McPherson and Dolores Laputka, August 12, 2016); Trial Tr.,
    Nov. 18, 2019, at 149-50; 152-56.
    154 Trial Tr., Nov. 20, 2019, at 144; see also JX-113 at 1.
    '5. Trial Tr., Nov. 20, 2019, at 157.
    196 Trial Tr., Nov. 21, 2019, at 53.
    157 Trial Tr., Nov. 20, 2019, at 145.
    158 Trial Tr., Nov. 20, 2019, at 146, 155-56.
    _34-
    business decision, but that is all.!°? At trial, McPherson also confirmed his
    deposition testimony where he unequivocally stated that there was no fraud.'°°
    Additionally, in mid-2015, Empresas defaulted on a more than a billion-dollar
    bond.'*! Shortly after this massive default, Travelers refused to issue surety bonds
    to FCCI.'® Charles Langfitt, Travelers’ corporate representative, testified that
    Travelers issued a credit freeze because of ICA Tech/Empresas’s downgrade on
    Moody’s credit rating system.'® Lack of surety support is a death knell for a
    construction company because without it one cannot work on larger, bonded
    projects.'©! And, McPherson testified, surety work was FCCI’s “bread and butter.”!©
    At trial, Nicholson agreed: “The loss of Travelers as its surety company going
    forward posed a serious threat to FCCI’s ability to remain in business unless a
    replacement surety company could be promptly obtained.”!® After the Empresas
    159 Td. at 144-45.
    160 Td.
    16 7d. at 131-32.
    162 Trial Tr., Nov. 21, 2019, at 44.
    163 Td. at 92.
    164 Trial Tr., Nov. 18, 2019, at 133-34; Trial Tr., Nov. 20, 2019, at 169-70.
    165 Trial Tr., Nov. 20, 2019, at 170.
    166 Trial Tr., Nov. 21, 2019, at 44.
    -35-
    billion-dollar bond default, Mr. Facchina learned that there were “massive” changes
    made at ICA Tech/Empresas’s senior level.'®’ And it wasn’t until five to six months
    after Travelers refused to provide surety support, that FCCI found a surety willing
    to provide it with bonding support, Berkshire Hathaway Specialty Insurance
    Group.!®
    IV. GENERAL LEGAL PRINCIPLES
    Though the Court sits without a jury, it has applied the same principles of law
    in its deliberations and consideration of each individual claim and counterclaim that
    it would have more formally instructed a jury to follow. The Court may highlight
    here some of those that are most applicable to this particular case. But the fact that
    some particular point or concept may be mentioned here should not be regarded as
    any indication that the Court did not—during its deliberations—consider all legal
    principles applicable to this case and the parties claims and counterclaims.
    In reaching its verdict the Court has examined the joint exhibits submitted
    and considered the testimony of all witnesses, both direct and cross. The Court has
    also considered the applicable Delaware case law that has defined the legal precepts
    applicable here. The Court has applied the Delaware Rules of Evidence to the
    167 JX-130 (Emails Between FCCI Executives and Staff, June 16, 2016) at 2; Trial Tr., Nov. 18,
    2019, at 148-49.
    168 JX-102 (Emails Between FCCI and Berkshire Hathaway, March 12, 2016).
    -36-
    testimony and exhibits and only used for its deliberation that which would be
    allowed under those rules—consistent with the Court’s knowledge of those rules and
    the specific rulings that may have been made and articulated both pre-trial, during
    the trial proceedings, and post-trial. And, of course, the Court has considered each
    party’s respective arguments on the weight to be accorded the testimony and
    evidence.
    The Court then reviewed and applied the very instructions that it would give
    a jury in these circumstances.!©
    In this particular case, FCCI carries the burden of proof by a preponderance'”°
    of the evidence on Counts I, II and III of its Complaint; Mr. Facchina on Counts I,
    V, and VI of his Complaint;'7! and ICA Tech/Empresas on Counterclaims I and II.
    V. FINDINGS AND VERDICT
    At trial there were three central contentions to be resolved: (1) whether there
    was fraud in the form of concealment of risks concerning the Grove at Grand Bay
    169 See, e.g., Super. Ct. Civil Pattern Jury Instr. 4.1 (Burden of Proof by a Preponderance of the
    Evidence);
    id. at 4.2
    (Evidence Equally Balanced); id at 23.1 (Evidence—Direct or
    Circumstantial);
    id. at 23.9
    (Credibility of Witnesses—Weighing Conflicting Testimony);
    id. at 23.10
    (Expert Testimony).
    110 See e.g., Reynolds v. Reynolds, 
    237 A.2d 708
    , 711 (Del. 1967) (defining preponderance of the
    evidence); Oberly v. Howard Hughes Medical Inst., 
    472 A.2d 366
    , 390 (Del. Ch. 1984) (same).
    '71 Counts I-IV of Seller Representative’s Complaint were voluntarily dismissed on August 30,
    2019. See Order Denying All Motions for Summary Judgment, Dismissing Certain Claims, and
    Striking Certain Affirmative Defenses.
    -37-
    condominium project in Miami; (2) whether indemnification was required under the
    terms of the PSA, including entitlement to $3.5 million held in escrow; and
    (3) whether acceleration of an earn-out payment was due under the terms of the PSA.
    A. THE COURT FINDS FOR MR. FACCHINA ON THE FRAUD COUNTERCLAIMS.
    The Court first addresses the primary issue of whether the representations and
    warranties made by Mr. Facchina as Seller Representative under PSA Sections 2.6
    and 2.29 were intentionally false and misleading, thereby entitling the Purchaser to
    recover for fraud under PSA Section 9.5(c). Under Delaware law, a claim of
    common law or legal fraud requires the plaintiff to prove each of the following: “(1)
    the defendant falsely represented or omitted facts that the defendant had a duty to
    disclose; (2) the defendant knew or believed that the representation was false or
    made the representation with a reckless indifference to the truth; (3) the defendant
    intended to induce the plaintiff to act or refrain from acting; (4) the plaintiff acted in
    justifiable reliance on the representation; and (5) the plaintiff was injured by its
    reliance.”!”
    To recover on a claim of equitable fraud, the plaintiff must satisfy all the
    elements of common-law fraud with the exception that plaintiff need not
    demonstrate that the misstatement or omission was made knowingly or recklessly.
    172 ABRY Partners V, L.P. v. F&W Acquisition LLC, 
    891 A.2d 1032
    , 1050 (Del. Ch. 2006)
    (citation omitted).
    -38-
    So, to succeed on that claim, the plaintiff must prove each of the following: (1) the
    defendant falsely represented or omitted facts that the defendant had a duty to
    disclose; (2) the defendant intended to induce the plaintiff to act or refrain from
    acting; (3) the plaintiff acted in justifiable reliance on the representation; and (4) the
    plaintiff was injured by its reliance.'”
    One is equally culpable of fraud when he by omission fails to reveal that which
    it is his duty to disclose in order to prevent statements actually made from being
    misleading.'”*
    ICA Tech/Empresas alleges: that “breaking up” the Grove concrete work
    created enormous risks to FCCI; and, that Vazquez deliberately disobeyed an
    instruction given by Mr. Facchina not to “break up” the concrete. ICA
    Tech/Empresas claims that the aforesaid information was known by Mr. Facchina
    before closing and concealed from ICA Tech/Empresas.'” ICA Tech/Empresas
    must prove by a preponderance of the evidence that: (1) Mr. Facchina made a false
    representation; (2) Mr. Facchina knew the representation was untrue or made the
    statement with reckless indifference to the truth; (3) Mr. Facchina intended for ICA
    13, Zirn vy. VLI Corp., 
    681 A.2d 1050
    , 1061 (Del. 1996).
    174 See Lock v. Schreppler, 
    426 A.2d 856
    , 860-61 (Del. Super. Ct. 1981) (concealment of material
    facts); Leech v. Husbands, 
    152 A. 729
    , 731-32 (Del. Super. Ct. 1930) (same).
    175 PTO at Iq 6-7.
    -39-
    Tech/Empresas to rely on the representation; (4) ICA Tech/Empresas justifiably
    relied on the representation; and (5) ICA Tech/Empresas suffered causally related
    6 Resolution of this claim depends, in part, on the Court’s assessment of
    damages.
    the credibility of Mr. Facchina and McPherson as witnesses, evaluation of the
    documentary evidence, and derivation of reasonable inferences from the direct and
    circumstantial evidence.
    The Court finds no credible evidence that Mr. Facchina knew before the
    closing that Vasquez had awarded the Grove concrete packages to more than one
    subcontractor. Mr. Facchina and McPherson only learned that Vazquez had awarded
    concrete packages to more than one subcontractor after the closing of the sale of the
    Facchina Companies to ICA Tech, which occurred on April 14, 2014.!77
    McPherson, the post-sale CEO and President of FCCI, credibly testified that both he
    and Mr. Facchina learned this information “well after” the sale.'”
    In fact, there is no evidence that Vazquez did not follow Mr. Facchina’s
    instructions regarding the concrete work at the Grove. As for his conversation with
    McPherson and Vazquez about the Grove, Mr. Facchina testified that he advised
    Vazquez and McPherson to “make it easy” on themselves by purchasing concrete
    '%6 Vichi v. Koninklijke Philips Elecs., N.V., 
    85 A.3d 725
    , 807 (Del. Ch. 2014).
    '17 See Trial Tr., Nov. 18, 2019, at 58-59.
    78 Trial Tr., Nov. 20, 2019, at 142.
    -40-
    packages in “chunks”, i.e., the fewer packages, the better.'” As Mr. Facchina
    explained, the fewer concrete packages purchased simply meant that the general
    contractor, FCF in this case, had fewer concrete contractors to manage and
    coordinate.'8° McPherson testified that it was his understanding that the above
    advice was an instruction.’®!
    Vazquez, the former President of FCF, and the individual who procured the
    concrete subcontractors for the Grove, did not testify at trial despite the fact that:
    (a) he previously submitted an Affidavit on behalf of ICA Tech/Empresas in
    response to Mr. Facchina’s Motion for Partial Summary Judgment Regarding Fraud;
    (b) he was the third person involved in the conversation regarding plans for concrete
    subcontracting at the Grove and the only one with personal knowledge of his
    understanding of Mr. Facchina’s comments; and (c) he is the individual best-situated
    to explain his intention to comport with Mr. Facchina’s advice. Yet, ICA
    Tech/Empresas chose not to call Vazquez. So there is no evidence of record as to
    how Vazquez interpreted the aforesaid conversation or sought to follow the
    recommendations. Indeed, given the other record evidence the inference properly
    drawn is that Vazquez would confirm Mr. Facchina’s testimony that his statements
    '19 Trial Tr., Nov. 18, 2019, at 34-36, 58.
    180 Trial Tr., Nov. 19, 2019, at 28-29.
    181 Trial Tr., Nov. 20, 2019, 68-69.
    -4]-
    were recommendations or advice and that Vazquez believed that he followed Mr.
    Facchina’s recommendations or advice.
    Of greater import, however, is that the evidence does not show that the Grove
    concrete subcontracts were “broken up” in a manner to cause concern. For instance,
    the most complicated work and the work Mr. Facchina would have found most
    concerning resided with a single concrete subcontractor, Titon. Mr. Facchina
    testified as follows: “My expectation in Grove is that that they would make their life
    easier on them, take the easy way out, make it simpler, one-stop shop. That was my
    expectation. And they did exactly that and exceeded my expectation.”!*?
    ICA Tech/Empresas has not demonstrated that Mr. Facchina misrepresented
    or did not disclose information with the intent to induce it to purchase FCCI. Again,
    it is undisputed that sometime after the closing of the sale of the Facchina Companies
    to ICA Tech, which occurred on April 14, 2014, Mr. Facchina and McPherson
    learned that Vazquez awarded concrete packages for the Grove to more than one
    subcontractor.'*? Rodrigo Quintana, ICA Tech/Empresas’s former general counsel
    and its current Chief Financial Officer, admitted that ICA Tech/Empresas was
    particularly interested in FCF’s vertical construction experience with residential
    182 Tyial Tr., Nov. 19, 2019, at 16-17.
    183 Trial Tr., Nov. 18, 2019, at 58-59; Trial Tr., Nov. 20, 2019, at 142.
    -42-
    condominiums.!** Quintana testified that ICA Tech/Empresas personnel specifically
    visited various construction sites, including those in Florida, visited FCF’s offices
    in Miami, Florida, and reviewed the Grove contract.!*
    As for information particular to the Grove, Mr. Facchina never withheld any
    information from the purchasers regarding it.'8° It is undisputed that Mr. Facchina
    did not have access to the data room and had no role in preparing the contract
    schedules attached to the PSA, which identify the Grove subcontractors and
    contracts.!87? The only evidence of any construction concern raised by Mr. Facchina
    about the Grove is contained in an email sent to Vazquez more than two months
    8 That concern, which involved thermal contraction and
    before the closing.'®
    expansion, was addressed by DeSimone, the architect and engineer of record, and
    considered resolved in February 2014, more than two months before closing.'®
    184 Trial Tr., Nov. 21, 2019, at 176.
    185 Trial Tr., Nov. 20, 2019, at 134-35; Trial Tr., Nov. 21, 2019, at 175-76.
    186 Trial Tr., Nov. 18, 2019, at 100.
    187 Tq, at 98-99, 100; Trial Tr., Nov. 20, 2019, at 137-138; Trial Tr., Nov. 21, 2019, at 188, 192-
    93; Carpenter Dep. at 31, 46.
    188 JX_37 (Emails Between Mr. Facchina and Jesus Vazquez, February 3, 2014); Trial Tr., Nov.
    18, 2019, at 102-04.
    189 Trial Tr., Nov. 18, 2019, at 102-104.
    -43-
    In summary, the Court finds: first, there is no evidence that Mr. Facchina knew
    before closing how Vazquez had awarded the Grove concrete packages; second,
    there is no evidence that Vazquez broke up those packages in any way inconsistent
    with Mr. Facchina’s expectations; and, third, there is no evidence that Vazquez
    broke up those packages in any way materially detrimental to the Grove as a whole.
    Moreover, ICA Tech/Empresas has failed to prove its actual reliance on any false
    statement or any omissions made by Mr. Facchina. The trial evidence convincingly
    demonstates that ICA Tech/Empresas had complete access to FCCI’s information
    and personnel.!® There is also no evidence that ICA Tech/Empresas suffered any
    losses on the Grove proximately caused by the fraud it alleges here.
    B. THE COURT FINDS FOR MR. FACCHINA ON THE INDEMNIFICATION CLAIMS.
    The Court next addresses whether the Sellers are in breach of the PSA as a
    result of their refusal to indemnify FCCJ. Under Delaware law, to prevail on a
    breach-of-contract count, a plaintiff must show: “(1) a contractual obligation; (2) a
    breach of that obligation; and (3) resulting damages.”!?! The Court determines the
    parties’ rights and obligations from the clear, unambiguous terms of the PSA. Under
    Delaware law, “[w]hen the contract is clear and unambiguous, [Delaware courts]
    190 Trial Tr., Nov. 21, 2019, at 173.
    19! Cornell Glasgow, LLC v. LaGrange Props., LLC, 
    2012 WL 6840625
    , at *14 (Del. Super. Ct.
    2012) (citing H-M Wexford LLC v. Encorp, Inc., 
    832 A.2d 129
    , 144 (Del. Ch. 2003)).
    -44-
    give effect to the plain meaning of the contract’s terms and provisions.”'”? Delaware
    courts “‘adhere[] to the objective theory of contracts.””'”? The objective theory of
    contracts “requires a court to interpret a particular contractual term to mean ‘what a
    reasonable person in the position of the parties would have thought it meant.’”!”4
    Delaware courts “‘will read the contract as a whole and [] will give each provision
    and term effect[.]”!?°
    Now “[t]he parties’ disagreement as to the meaning of the contract does not
    render it ambiguous.”!”© Rather, “a contract is ambiguous only when the provisions
    in controversy are reasonably or fairly susceptible to different reasonable
    interpretations.”!?’ In contrast, a contract is unambiguous “where the court can
    determine the meaning of a contract ‘without any other guide than a knowledge of
    192 Osborn ex rel. Osborn v. Kemp, 
    991 A.2d 1153
    , 1159-60 (Del. 2010).
    193, Vinton v. Grayson, 
    189 A.3d 695
    , 704 (Del. Super. Ct. 2018) (quoting 
    Osborn, 991 A.2d at 1159
    ).
    194 Tq. at 704 (quoting Lorillard Tobacco Co. v. Am. Legacy Found, 
    903 A.2d 728
    , 740 (Del.
    2006)).
    195 Td. (quoting Kuhn Const., Inc. v. Diamond State Port Corp., 
    990 A.2d 393
    , 396-97 (Del.
    2010)).
    196 Catawba Assoc.-Christiana LLC v. Jayaraman, 
    2016 WL 4502306
    , at *6 (Del. Super. Ct. Aug.
    26, 2016); see also Rhone-Poulenc Basic Chem. Co. v. Am. Motorists Ins. Co., 
    616 A.2d 1192
    ,
    1196 (Del. 1992) (“A contract is not rendered ambiguous simply because the parties do not agree
    upon its proper construction.”).
    197 Axis Reinsurance Co. v. HLTH Corp., 
    993 A.2d 1057
    , 1062 (Del. 2010).
    -45-
    the simple facts on which, from the nature of language in general, its meaning
    depends.’”!8
    Sellers have never suggested that any provision of the PSA is ambiguous. And
    the Court’s own examination of the controlling PSA provisions reveal no ambiguity.
    So the Court may determine the parties’ rights and obligations without relying on
    extrinsic evidence or anything more than the plain, ordinary meaning of the PSA’s
    words.!??
    Section 9.9 of the PSA states the following:
    9.9 Settlement or Compromise. Any settlement or compromise made
    or caused to be made by the Indemnified Person or the Indemnifying
    Person, as the case may be, of any such claim, suit, action or proceeding
    of the kind referred to in Section 9.8 shall also be binding upon the
    Indemnifying Person or the Indemnified Person, as the case may be, in
    the same manner as if a final judgment or decree had been entered by a
    court of competent jurisdiction in the amount of such settlement or
    compromise; provided, that . . . (ii) the Indemnified Person shall not
    compromise or settle any claim, suit, action or proceeding without the
    prior written consent of the Indemnifying Person, which consent shall
    not be unreasonably withheld.”
    1988 
    Rhone-Poulenc, 616 A.2d at 1196
    (quoting Holland v. Hannan, 
    456 A.2d 807
    , 815 (D.C. App.
    Ct. 1983)).
    199 Alta Berkeley VIC.V. v. Omneon, Inc., 
    41 A.3d 381
    , 385 (Del. 2012).
    200 PSA § 9.9 (emphasis added).
    -46-
    Section 9.8 of the PSA addresses the obligation to notify an “Indemnifying Person”
    of a third-party claim.2°! “[T]Jhe kind referred to in Section 9.8” includes
    indemnification sought pursuant to Sections 9.2, 9.3 or 9.4. Section 9.2 of the PSA
    further provides that “Each Seller, jointly and severally, agrees to indemnify . . .
    each of the Purchaser Indemnified Parties against, and agrees to hold each of them
    harmless from, any and all Losses incurred or suffered by them relating to or arising
    out of .. . the Silver Spring Matter.”°* Section 9.2 is also explicitly subject to the
    limitations of Article Ix.?"
    Under the plain language of the PSA, the Indemnifying Person’s consent is a
    condition precedent to FCCI being indemnified for any settlement or claim. Indeed,
    if the parties had wanted a violation of Section 9.9 to have an effect other than relief
    from indemnity obligations, they could have written Section 9.9 differently, but they
    did not. For example, Section 9.8 states “that the failure of the Indemnified Person
    to give notice [of a claim in which indemnity may be sought] shall not relieve the
    Indemnifying Person of its obligation under this Article IX except to the extent (if
    any) that the Indemnifying Person shall have been actually prejudiced thereby.”?"
    201
    Id. at
    § 9.8.
    202 Td. at § 9.2.
    203 Tq. at § 9.2.
    204 Td. at § 9.8.
    -47-
    Mr. Facchina—the Indemnifying Person—testified that he did not provide
    prior written consent or even oral consent to the SSTC lawsuit settlement nor was
    he asked for his consent to any of the settlement agreements.” After reviewing
    some invoices, Bastianelli recalled that he and Mr. Facchina only had two brief
    telephone conversations approximately two weeks before the MontCo/Foulger-Pratt
    settlement.2°° Although Mr. Facchina was copied on a handful of informational
    emails regarding settlement negotiations, it is undisputed that Mr. Facchina never
    once replied to these e-mails with his consent or opinion. Nor was he ever requested
    to do so.?%7
    What’s more, Bastianelli testified that he did not copy Mr. Facchina on several
    emails closer in time to the WMATA and MontCo/Foulger-Pratt final settlement
    discussions. Bastianelli testified that he did not negotiate the settlement with Mr.
    Facchina.2°? And Bastianelli did not seek Mr. Facchina’s consent to those
    settlements because Mr. Facchina was not a decision maker.” Bastianelli testified
    that the two decision makers were Langfitt of Travelers and Don Asselin of
    205 Tyial Tr., Nov. 18, 2019, at 181-183.
    206 Trial Tr., Nov. 20, 2019, at 47-48.
    207 Trial Tr., Nov. 18, 2019, at 181-183; JX-230; Tr. Trial Tr. Nov. 20, 2019, at 55.
    208 Td. at 62.
    209 Trial Tr., Nov. 20, 2019, at 60, 67; JX-232.
    -48-
    Zurich.2!° And, Bastianelli testified that the individuals with decision making
    authority on behalf of FCCI were McPherson and Timothy Heffernan, Traveler’s
    counsel and FCCI’s counsel in the present matter.?!!
    It is undisputed that FCCI executed the settlement agreements, FCCI was the
    named party in the SSTC lawsuit, and FCCI is seeking indemnification from Sellers
    based on the terms and conditions of the PSA. It is also undisputed that Mr. Facchina
    did not consent to withdraw or release any of the aforementioned SSTC-related
    claims nor was he asked for his consent.?!”
    Therefore, the existence of the condition precedent to any indemnification
    obligation was not proven at trial by a preponderance of the evidence. And so, the
    Court rules in favor of Mr. Facchina on this claim brought by FCCI.
    C. THE COURT FINDS FOR ICA TECH/EMPRESAS ON THE CLAIMS CONCERNING
    ACCELERATION OF THE EARN-OUT PAYMENT UNDER THE PSA.
    Lastly, this Court addresses the claims concerning acceleration of the earn-
    out payment under the PSA. At issue is these claims is whether the actions of ICA
    Tech and/or FCCI constituted a sale of all or substantially all of the assets of the
    210 Td. at 56.
    211 Tq at 61.
    212 Trial Tr., Nov. 18, 2019, at 198.
    -49-
    Facchina Companies, taken as a whole, to a Third-Party Purchaser, as defined in
    Section 1.8(e) of the PSA.
    1. Mr. Facchina’s Breach-of-Contract Claim
    Mr. Facchina alleges that ICA Tech breached the terms of the PSA in way that
    triggers Seller’s contingent right to an acceleration payment under Section 1.8 (e).
    PSA § 1.8(e)(i) requires Seller to demonstrate a sale to a Third-Party Purchaser of:
    [A]ll or substantially all of the assets of the Companies, taken as a
    whole, or a business unit that includes all or substantially all of the
    business of the Companies, taken as a whole, in each case as they then
    currently exist (a “Sale Transaction”) . . .?!°
    The PSA language detailing the obligation to make the Acceleration Payment
    provides that after the predicate to Mr. Facchina’s right to an Acceleration Payment
    is met, “Facchina Construction shall ... make a payment to the Seller Representative
    on behalf of Sellers in the amount of the Acceleration Payment.”?!4
    Section 11.21 of the PSA does require Empresas, as parent guarantor, to
    guarantee Facchina Construction’s obligation to make payments under the PSA.*?°
    But Empresas’s guarantee obligation does not arise until FCCI is first found liable
    213 PSA §1.8(e)(i).
    214
    Id. at
    § 1.8 (e)(i), p. 19.
    215 Td. at § 11.21, p. 96.
    -50-
    to make a payment.?!® Mr. Facchina did not show (1) that an Acceleration Payment
    is due; (2) that FCCI failed to make the required payment; or (3) that FCCI’s failure
    to make any such payment is a breach of the PSA.
    The fact is that Mr. Facchina has never asked Facchina Construction
    Company to make an Acceleration Payment because he does not allege that the
    Facchina Companies did anything to harm him.?!”
    Mr. Facchina disavowed having any claim against FCCI for an acceleration
    payment, and there is no basis for any claim by against Empresas under its guarantee.
    Accordingly, Empresas has no corresponding obligation to ensure a payment is
    made.
    216 Td.
    217 Mr. Facchina, himself, has always been consistent on this point:
    Q. Did Facchina Construction Company breach the PSA?
    A. My complaints are not with Facchina Construction Company. They are
    with ICA.
    Q. So if Facchina Construction Company isn’t in breach, what you were just
    referring to is ICA?
    A.  That’s what I’m referring to, because my deal is with ICA, not Facchina
    Construction.
    Q. I’mjust clarifying to make sure that here in this affirmative defense you’re
    not suggesting that Facchina Construction Company is in breach of the
    PSA.
    A. No, I’m not.
    Mr. Facchina Dep. at p. 12 (intervening objections omitted).
    -5]-
    Mr. Facchina has also failed to prove by a preponderance of the evidence that
    that a triggering “Sale Transaction”—.e. a sale to a third-party purchaser of “all or
    substantially all” of the Company’s assets—occurred. And his cited cases do not
    truly assist him in shouldering this burden.
    In Gimbel v. Signal Companies, Inc., the trial court interpreted a statute and
    found the subject stock sale did not constitute a sale of “all or substantially all” of
    the company’s assets.?!8 Of particular note, the Gimbel court had an opportunity to
    closely examine expert testimony and valuations of the alleged assets in making its
    determination. Here, however, Sellers fail to supply even the basic evidence that
    would allow this Court to make a determination in its favor.?!?
    Likewise, the application of Hollinger Inc. v. Hollinger Int’l, Inc. 1s limited to
    the same statute in at issue in Gimbel—8 Del. C. § 271—and again the court
    ultimately found the sale did ot constitute “all or substantially all” of the company’s
    assets.”2° Despite the “contextual approach” advocated by Sellers, the Hollinger
    court made it clear such approach will not permit a finding that “all or substantially
    all” of a company’s assets were sold unless the plaintiff meets the minimum
    218 
    316 A.2d 599
    , 606-08 (Del. Ch. 1974) (holding that a sale of less than 50% of the assets is not
    “all or substantially all’).
    19 Compare id. at 607-608.
    220 
    858 A.2d 342
    , 385 (Del. Ch. 2004).
    -52-
    requirement of showing that at least half of the assets were sold.”7). Mr. Facchina
    has not satisfied this minimum requirement.
    2. Breach of the Implied Covenant of Good Faith and Fair Dealing
    Under Delaware law, in order to recover for breach of the implied covenant
    of good faith and fair dealing, the Seller must prove that ICA Tech acted arbitrarily
    or unreasonably—effectively preventing Plaintiff from receiving the benefit of the
    bargain. “A party does not act in bad faith by relying on contract provisions for
    which that party bargained where doing so simply limits advantages to another
    99222
    party.
    Mr. Facchina has not proven by a preponderance of the evidence that ICA
    Tech acted arbitrarily or unreasonably. ICA Tech has no obligation to the Sellers
    regarding the Acceleration Payment. And because FCCI never became obligated to
    make the Aceleration Payment, Empresas was never obligated to make any such
    payment.
    221 Td. at 386.
    222 Nemec v. Shrader, 
    991 A.2d 1120
    , 1128 (Del. 2010).
    -53-
    VI. VERDICT AND JUDGMENT
    A. ON FCCI’S COMPLAINT:
    - Count I — Breach of Contract: For Mr. Facchina
    - Count II — Attorneys’ Fees: For Mr. Facchina
    - Count III — Declaratory Judgment: For Mr. Facchina
    B. ON MR. FACCHINA’S COMPLAINT:
    - Count J — Breach of Contract against ICA Tech: For ICA Tech
    - Count V — Breach of Implied Covenant of Good Faith and Fair Dealing
    against ICA Tech and Empresas: For ICA Tech and Empresas
    - Count VI — Enforcement of Guaranty against Empresas
    as the Parental Guarantor: For Empresas
    C. ON ICA TECH/EMPRESAS’S AMENDED ANSWER AND COUNTERCLAIM:
    - Count I— Declaratory Judgment: For Mr. Facchina
    - Count II — Fraud: For Mr. Facchina
    The parties shall confer and, within 15 days, submit to the Court a proposed
    form of Order of Final Judgment consistent with these findings and verdicts.
    Paul R. Wallace, Judge
    IT IS SO ORDERED.
    Original to Prothonotary
    cc: All counsel via File & Serve
    -54-