The Cincinnati Insurance Company a/s/a Green Recovery Technologies, LLC v. The Commonwealth Group ( 2024 )


Menu:
  •       IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
    THE CINCINNATI INSURANCE                     )
    COMPANY a/s/o GREEN RECOVERY                 )
    TECHNOLOGIES, LLC,                           )
    Plaintiff,                 )
    v.                                  )
    )
    THE COMMONWEALTH GROUP                       )
    LTD and THE COMMONWEALTH                     )
    GROUP LLC,                                   )
    Defendants.             )   C.A. No.: N19C-06-204 FJJ
    ________________________________             )
    THE COMMONWEALTH GROUP                       )
    LTD and THE COMMONWEALTH                     )
    GROUP LLC,                                   )
    Defendants/Third Party        )
    Plaintiffs,             )
    v.                                 )
    )
    BEAR INDUSTRIES INC.,                        )
    Third Party Defendant.           )
    Date Submitted: December 14, 2023
    Date Decided: January 2, 2024
    OPINION AND ORDER
    Upon Consideration of Third-Party Defendant Bear Industries, Inc.’s
    Motion for Summary Judgment:
    GRANTED.
    Michael I. Silverman, Esquire, Silverman, McDonald & Friedman, Wilmington,
    Delaware, Attorney for Plaintiff.
    Brett Thomas Norton, Esquire, Marks, O’Neill, O’Brien, Doherty & Kelly PC,
    Wilmington, DE, Attorney for Defendant Bear Industries, Inc.
    Kevin J. Connors, Esquire, Marshall, Dennehey, P.C., Wilmington, DE, Attorney
    for Defendant The Commonwealth Group, LTD.
    Jones, J.
    This action arises from the flooding and subsequent damage to a commercial
    property (the “Property”) owned by Green Recovery Technologies, LLC (“Green
    Recovery”) in New Castle, Delaware on June 29, 2017.1 In essence, a tornado
    damaged the Property and caused a power outage. Although power eventually
    returned to the majority of the Property, it was not restored to an air compressor
    which kept a Deluge Sprinkler System (the “Sprinkler System”) closed. This then
    activated the Sprinkler System and flooded the Property, causing significant damage.
    As the subrogor of Green Recovery, Plaintiff Cincinnati Insurance Company
    has filed this action against Defendants/Third-Party Plaintiffs, The Commonwealth
    Group Limited and The Commonwealth Group, LLC (collectively, the
    “Commonwealth”), seeking, among other things, compensatory damages for
    negligence and gross negligence stemming from the Commonwealth’s decision to
    not restore power to the Sprinkler System’s air compressor.2 The Commonwealth
    filed an opposed Motion for Leave to Add Third-Party Defendants, alleging that
    Bear Industries Inc. (“Bear”) was negligent in design and installation of the Sprinkler
    System.3 The Third-Party Complaint against Bear was filed on May 25, 2023.4 In
    its answer to the Third-Party Complaint, Bear conceded that it designed and installed
    the Sprinkler System at the Property in 2014.5
    1
    D.I. 1 ¶¶ 10-12, 18-26; D.I. 46 ¶ 3.
    2
    Id.
    3
    D.I. 39. The Court cites to this motion for procedural purposes only.
    4
    D.I. 46.
    5
    D.I. 52 ¶ 5.
    1
    Nevertheless, Bear filed a Motion for Judgment on the Pleadings pursuant to
    Superior Court Civil Rule 12(c), maintaining that Commonwealth’s third-party
    claim was barred by Delaware’s Statute of Repose found at 10 Del.C. §8127.6 The
    Court initially considered the Motion on August 30, 2023. The Court deferred
    decision on the Motion and allowed Commonwealth to engage in discovery as to
    Bear on the issue of timing of the running of §8127 and whether Bear’s work
    constituted an improvement within the meaning of §8127.            Documents were
    exchanged and the Rule 30(b)(6) deposition of Bear, through Joseph Majewski, Sr.,
    was taken.
    Commonwealth filed a supplemental memorandum in support of its
    opposition to Bear’s Motion pursuant to the statute of repose on December 4, 2023.
    In response, Bear, and the Plaintiff, filed its supplemental memorandum on
    December 8, 2023, each opposing Commonwealth. While the matter started out as
    a motion for judgment on the pleadings, the addition of discovery requires this Court
    to treat the matter as a summary judgment motion. The standard for summary
    judgment is well known. Summary judgment is appropriate when the record “shows
    there is no genuine issue as to any material fact and the moving party is entitled to
    judgment as a matter of law.”7 The moving party bears the burden of establishing
    the nonexistence of material issues of fact.8 The burden then shifts to the nonmoving
    6
    Del. Super. Ct. Civ. R. 12(c).
    7
    Del. Super. Ct. Civ. R. 56(c).
    8
    See Moore v. Sizemore, 
    405 A.2d 679
    , 680 (Del. 1979).
    2
    party to establish the existence of material issues of fact.9 In considering the motion,
    the Court must view the evidence in a light most favorable to the nonmoving party
    and accept the nonmovant’s version of any disputed facts.10
    Bear’s motion rests on §8127, which provides a six-year limitations period on
    actions for damages, indemnification, or contribution for damages resulting from
    personal injuries arising out of any deficiency in the construction of an improvement
    to real property or the design, planning, supervision, or observation of any such
    construction.11 In other words, §8127 is a “true statute of repose. . . . [and] the
    passing of the six-year period deprives the injured party of a legal right to redress.”12
    A statute of repose is not an ordinary statute of limitations.13 An “ordinary
    statute of limitations begins with an injury or the discovery date of an injury.”14 A
    statute of repose, however, can begin to run before the cause of action arises15
    because it begins irrespective of the date of injury.16 Thus, “when the cause of action
    triggers the statute, it is a statute of limitations.” If not, it may be a statute of repose.17
    Here, the repose period set forth in 10 Del. C. §8127 begins to run at the
    earliest of eight designated dates, irrespective of the date of injury.18 Bear submits
    9
    See Id. at 681.
    10
    See Merrill v. Crothall-Am., Inc., 
    606 A.2d 96
    , 99-100 (Del. 1992) (internal citations omitted).
    11
    10 Del. C. §8127(b)(1)-(2) (emphasis supplied).
    12
    City of Dover v. Int’l Tel. and Tel. Corp., 
    514 A.2d 1086
    , 1089 (Del. 1986) (internal citations omitted).
    13
    Cheswold Volunteer Fire Co. v. Lambertson Const. Co., 
    489 A.2d 413
    , 421 (Del. 1984).
    14
    
    Id.
    15
    Workers’ Comp. Fund v. Kent Const. Corp., 
    2008 WL 4335873
    , at *3 (Del. Super. Sept. 19, 2008).
    16
    Cheswold, 489 A.2d at 421.
    17
    Workers’ Comp. Fund, 
    2008 WL 4335873
    , at *3; see also Becker v. Hamada, Inc., 
    455 A.2d 353
    , 354-55 (Del.
    1982).
    18
    See generally 10 Del. C. §8127.
    3
    the operative date is when it designed and installed (or, as it puts it, “constructed”)
    the Sprinkler System.19 Discovery reveals that Bear last substantially performed its
    work on the Sprinkler System in September 2016. As September 2016 is more than
    six years removed from the date when the third-party complaint was filed (March
    30, 2023), it is clear that if the work done by Bear was an improvement to real
    property, then the statute of repose applies to Commonwealth’s claims against Bear.
    The battle, then, becomes whether the Sprinkler System is an “improvement”
    as defined in §8127. Bear offers three reasons why it should qualify as such: (i) Bear
    charged Green Recovery for the design and installation of the Sprinkler System; (ii)
    the Sprinkler System was not temporary or removable; and (iii) the Sprinkler System
    protected the Property’s “process room,” which contained equipment to recycle
    animal fats and proteins into reusable commodities, thereby making the Property
    more useful for Green Recovery’s purpose.20
    Commonwealth responds that the installation of this particular sprinkler
    system does not constitute an improvement to the property for purposes of the
    statute. According to Commonwealth, the sprinkler system at issue is a discrete
    interior deluge sprinkler that was installed and could be dismantled by four workers
    in a day. The system at issue is not a building-wide sprinkler system but rather a
    system focused upon a small space within the Green Recovery Technologies
    19
    Mot. ¶ 7.
    20
    Mot. ¶ 7.
    4
    demised premises.              Commonwealth maintains that any subsequent tenant, not
    involved in the very proprietary and secretive work performed by Green Technology
    Recoveries, would have no need for this discrete modification and if not needed it
    could be readily and quickly removed.
    The majority of jurisdictions follow the principle that sprinkler systems are
    “improvements” for repose purposes.21 However these cases involve systems that
    apply to the whole premises and are not discreet to a small portion of the property.
    The question then becomes whether this particular system does in fact constitute
    improvement to real property. This is a question of law.22
    Delaware courts have employed various means to determine whether a
    particular construction is an “improvement” to land. The first case addressing the
    issue, Hiab Cranes & Loaders, Inc. v. Service Unlimited, Inc.,23 looked to the
    definition of improvement in other states and found that two approaches were widely
    employed: (i) a common law fixture analysis, and (ii) a “common sense”
    interpretation defining the term according to common usage.24 On the first approach,
    the Hiab court cited Pennsylvania law for the proposition that “while a fixture is, by
    21
    See, e.g., Travelers Ins. Co. v. Guardian Alarm Co. of Michigan, 
    231 Mich. App. 473
    , 
    586 N.W.2d 760
    , 763 (1998)
    (finding fire alarm system to be “improvement” to real property under repose statute); Red Wing Motel Invs. v. Red
    Wing Fire Dep’t, 
    552 N.W.2d 295
    , 297 (Minn. App. 1996) (treating a sprinkler system for fire protection purposes as
    an “improvement” to real property), review denied (Minn. Oct. 29, 1996); Qualitex, Inc. v. Coventry Realty Corp.,
    
    557 A.2d 850
    , 852 (R.I. 1989) (recognizing sprinkler system as an “improvement to real property”); Kallas Millwork
    Corp. v. Square D Co., 
    66 Wis. 2d 382
    , 
    225 N.W.2d 454
     (1975) (concluding that a high-pressure water system
    designed for fire protection constituted “an improvement to real property” as that phrase is used in statute of repose).
    22
    Hiab Cranes & Loaders, Inc. v. Serv. Unlimited, Inc., No. CIV.A. 82C–FE–98, 
    1983 WL 875126
    , letter op. at 3
    (Del. Ch. Aug. 16, 1983).
    23
    
    Id.
    24
    Id. at 3-4.
    5
    definition, an improvement to real property, the converse is not true; an improvement
    to real property[,] in the ordinary sense of the term, need not be a fixture.”25 Of the
    second approach, the Hiab court cited with approval Brown v. Jersey Central Power
    & Light Co.,26 which contrasted permanent parts of the mechanical systems
    necessary to the normal function of a building from those “chattels brought into a
    structure after it is architecturally and mechanically suitable for occupancy for the
    purpose intended, … e.g., furniture, production machinery, appliances, etc.” – the
    former being improvements, the latter not.27 The Hiab court went on to find that a
    building’s furnace was an improvement covered by the statute.28
    In Davis v. Catalytic, Inc.,29 the Superior Court analyzed the Hiab decision’s
    use of a “common sense” approach and found that, under that approach, a “slurry
    cooler” was an improvement to a real property and its builder was entitled to
    protection under 10 Del.C. §8127.30 The “slurry cooler” was a sizable free-standing
    structure bolted to the concrete floor and affixed to the adjacent pieces of the
    production process.31 In Standard Chlorine of Delaware, Inc. v. Dover Steel Co.,32
    the Court held that a liquid storage tank “attached to the realty through a system of
    pipes, valves, manifolds, wires, scaffolds, catwalks and a foundation” was an
    25
    Id. at 4 (citing Keeler v. Com., Dep’t of Transp., 56 Pa. Cmwlth. 236, 
    424 A.2d 614
    , 616 (1981)).
    26
    
    163 N.J. Super. 179
    , 
    394 A.2d 397
    , 405-06 (1978).
    27
    
    Id.
    28
    Hiab, No. CIV.A. 82C–FE–98, 
    1983 WL 875126
    , at 5.
    29
    No. 82C-AU-39, 
    1985 WL 189329
     (Del. Super. Ct. Dec. 11, 1985).
    30
    Id. at *5.
    31
    Id.
    32
    No. C.A. 87C-DE-194-1-CV, 
    1988 WL 32044
    , at *2 (Del. Super. Ct. March 31, 1988).
    6
    improvement to property. In Windley v. Potts Welding & Boiler Repair, Co., the
    Court found a preheater that was “central to the plant’s function” to be an
    improvement.33
    In Woessner v. Air Liquid, Inc.,34 the Third Circuit found that a motor control
    center at a carbon dioxide recovery plant was an improvement to a real property
    within the meaning of the statute.
    City of Dover v. Int'l Tel. & Tel. Corp.35 is the only Delaware Supreme Court
    case addressing what an improvement is. The Court stated that a “utility pole can
    be considered a ‘structure’ within the meaning of the statute.               Since it is
    unquestionably affixed to land, it can be considered an ‘improvement’ covered by
    statute.”36 However, the Court in Davis went on to say:
    City of Dover argues that the term
    “improvement” includes only structures that actually
    enhance the value of the property and/or make the
    property more useful. However, the statutory definition
    of “improvement” clearly does not require such value
    enhancement.37 Therefore, “structures” covered by the
    statute need not meet a “value added” test to be
    “improvements,” even though such a test may prove
    useful in determining the parameters of the statute.38
    The instant sprinkler system was a deluge sprinkler system which was installed at a
    total cost of $105,000. The system included its own fire pump, controller, six-inch
    33
    
    888 F.Supp. 610
    , 613 (D. Del. 1995).
    34
    
    242 F.3d 469
     (3rd Cir. 2001).
    35
    
    514 A.2d 1086
     (Del. 1986).
    36
    
    Id.
     At 1090.
    37
    10 Del.C. §8127(a)(2).
    38
    Id.
    7
    valves and six-inch piping, drain lines and was attached to both the plumbing and
    electrical systems.39 To remove this system would require two men, two days and
    at a cost of over $9,000.40 If a fixture analysis is applied to these facts, this Court
    concludes that the deluge sprinkler system would constitute an improvement within
    the meaning of §8127.
    If a “commonsense” approach analysis is utilized, this Court believes that the
    same result would follow. The deluge sprinkler system clearly enhanced the
    property’s capital value, involved the expenditure of labor and money, and was
    designed to make the property more useful or valuable as distinguished from
    ordinary repairs. This sprinkler system like the situations in Davis, Standard
    Chlorine, Welding and Woessner involved a change to the property that added value
    to the property for the purposes of its intended use by the occupant of that property.41
    When viewed in this light there is no question that the system was central to the user
    of the property and enhanced the value of the property not only to the entire
    marketplace but also to the user of the improvement.42
    Commonwealth added Bear to this litigation in May 2023, nearly seven years
    after Bear substantially completed its work on the property.                                         Given the
    uncompromising nature of the statute of repose, it must now suffer the
    39
    See Exhibit A to Plaintiff’s Supplemental Memorandum of Law in Opposition to Defendant’s Motion for
    Judgment on the Pleadings.
    40
    Id at Exhibit B.
    41
    See Adair v. Koppers Co., Inc., 
    741 F.2d 111
     (6th Cir. 1984); Phillips v. Langston Corp., 
    59 F.Supp.2d 696
     (E.D.
    Mich. 1999); Sette v. Benham, Blair & Affiliates, 
    70 Ohio App. 3
    .d 651, 
    591 N.E.2d 871
     (1991); Mullis v. S. Co.
    Servs., 
    250 Ga. 90
    , 
    296 S.E.2d 579
     (1982).
    42
    
    Id.
    8
    consequences: dismissal of its claim against Bear. Accordingly, Bear’s motion as to
    the Statute of Repose is GRANTED and summary judgment is entered in favor of
    Bear.
    IT IS SO ORDERED.
    /s/ Francis J. Jones, Jr.
    Francis J. Jones, Jr., Judge
    cc:     File & ServeXpress
    9
    

Document Info

Docket Number: N19C-06-204 FJJ

Judges: Jones J.

Filed Date: 1/2/2024

Precedential Status: Precedential

Modified Date: 1/3/2024