Jpay, Inc. v. 10800 Biscayne Holdings, LLC , 2017 Fla. App. LEXIS 8961 ( 2017 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed June 21, 2017.
    Not final until disposition of timely filed motion for rehearing.
    _______________
    No. 3D16-1308
    Lower Tribunal No. 14-32194
    ________________
    JPAY, Inc.,
    Appellant,
    vs.
    10800 Biscayne Holdings, LLC,
    Appellee.
    An appeal from the Circuit Court for Miami-Dade County, Jose M.
    Rodriguez, Judge.
    Law Offices of Jonathan A. Heller, PA and Jonathan A. Heller; Jay M.
    Levy, P.A. and Jay M. Levy, for appellant.
    The Bernstein Law Firm and Michael I. Bernstein and Brian G. Winger, for
    appellee.
    Before SUAREZ, C.J., and LAGOA and LOGUE, JJ.
    SUAREZ, C.J.
    JPAY, Inc. [“JPAY] seeks to reverse a final order granting Appellee’s
    amended motion for summary judgment. We affirm.
    In August 2007, Appellee landlord 10800 Biscayne Holdings [“Biscayne”]
    leased commercial office space to Appellant JPAY. The lease term was set to
    expire on September 14, 2015. JPAY failed to pay its rent, and vacated the
    premises in February 2013 prior to lease expiration. Biscayne sued JPAY for
    breach of the lease and sought damages for a late fee due for the January 2013
    overdue rent, for failing to pay the February 2013 rent, and for continuing damages
    incurred by JPAY’s abandonment of the lease agreement. Biscayne moved for
    partial summary judgment for unpaid rent through January 2014. JPAY moved for
    cross summary judgment claiming that the lease agreement had been terminated
    with Biscayne’s service of a 2013 three-day notice, and that Biscayne had retaken
    the leased premises thereby precluding any further recovery or acceleration of rent
    due under the remaining terms of the lease agreement.
    At the February 12, 2014 hearing, Biscayne stated that it was not seeking
    acceleration of the entire balance due under the lease, only what was due through
    “today.” The trial court (Arzola, J.) acknowledged that the lease had not been
    terminated, Biscayne was not seeking the accelerated amount, granted Biscayne’s
    motion for partial summary judgment as to liability for rent due from February
    2013 through February, 12, 2014, and denied JPAY’s cross-motion for summary
    judgment. In the trial court’s February 18, 2014 Order memorializing that holding
    [“JPAY I”], the court did not state that the rent had been accelerated and entered
    2
    judgment for rent due only through February 12, 2014, the date of the hearing.
    JPAY did not appeal from that order, and satisfied the judgment.
    In October 2014, Biscayne filed a renewed motion for partial summary
    judgment seeking the unpaid rent due for each monthly breach that occurred after
    February 18 Order, beginning on March 1, 2014 through August 31, 2014. JPAY
    moved to strike on grounds that the February 18, 2014 Order was “final” and thus
    the trial court had no jurisdiction to hear any claim for damages accruing after that
    date. The trial court granted JPAY’s motion to strike for lack of jurisdiction,
    agreeing that the February 18, 2014 Order was a final order.
    Biscayne then filed a new complaint [JPAY II] seeking damages for breach
    of the lease for overdue payments starting March 1, 2014 up to and including date
    of filing JPAY II. JPAY moved to dismiss and for final judgment, arguing that
    JPAY I was res judicata. At the hearing on these motions, JPAY asserted that
    Biscayne had requested the judgment for accelerated rent in JPAY I, and was thus
    precluded from seeking additional rents in JPAY II. On December 8, 2015, the
    trial court denied JPAY’s motions.       JPAY then filed a petition for Writ of
    Prohibition in this Court seeking to reverse the December 8 Order, again arguing
    the trial court had no jurisdiction because Biscayne actually sought and got
    accelerated rent in JPAY
    I. This Court denied the petition.
    3
    Biscayne sought final summary judgment for the full amount due under the
    lease for each continuing monthly breach from filing of JPAY II through the lease
    expiration date of September 14, 2015. JPAY answered and also moved for
    summary judgment. At the April 1, 2016 hearing, the trial court entered final
    summary judgment in Biscayne’s favor. JPAY appeals.
    ACCELERATION ISSUE:
    The record is clear that Biscayne did not seek acceleration under the lease in
    JPAY I.     The Complaints in both JPAY I and II contain no language of
    acceleration, and instead set forth clear claim for damages for periods of breach of
    monthly rent due under the lease:
    December 2014 Complaint [JPAY I]:
    25. Plaintiff demands judgment in an amount to be determined at trial
    for rent due from March 1, 2014 through December 31, 2014, plus
    penalties, interest, and attorney's fees and costs pursuant to Paragraph
    22(f) of the Lease Agreement.
    June 2015 Amended Complaint [JPAY II]:
    14. In the First Action, Plaintiff moved for partial summary judgment
    for a determination on Defendant's liability to Plaintiff for breach of
    the Lease, and for rent due and owing up through February 28, 2014,
    as any rent due subsequent thereto had yet to accrue based on Plaintiffs
    re-taking of the Leased Premises for the benefit of Defendant.
    15. The Court in the First Action found that Defendant breached the
    Lease, and on February 18, 2014, entered an order awarding Plaintiff
    damages based on Defendant's breach of the Lease up through
    February 12, 2014 (copy attached as Exhibit D).
    4
    16. Subsequent to the entry of the February 18 Order, Plaintiff
    continued to send Defendant monthly invoices for rent due under the
    Lease.
    17. Plaintiff now seeks rent due under the Lease from March 1,
    2014 through May 31, 2015, as well as attorney's fees and costs due
    under the Lease.
    The language of acceleration is not used, and the substance of the claims clearly
    indicate breach of monthly installments of rent due.
    On breach by a lessee, a lessor has the choice of three alternative courses of
    action: 1) the lessor may treat the lease as terminated and retake possession for his
    own account, thus terminating any further liability on the part of the lessee; or 2)
    the lessor may retake possession of the premises for the account of the lessee,
    holding the lessee liable for the difference between rental stipulated to be paid
    under the lease agreement and what, in good faith, the lessor is able to recover
    from a reletting; or 3) the lessor may stand by and do nothing, holding the lessee
    liable for the rent due as it matures, which means all remaining rent due if there is
    an acceleration clause and the lessor chooses to exercise the right to accelerate.
    Coast Fed. Sav. & Loan Ass'n v. DeLoach, 
    362 So. 2d 982
    , 984 (Fla. 2d DCA
    1978).
    JPAY argues (for the third time in these proceedings) that once the Appellee
    Biscayne retook the premises pursuant to the three-day notice, the lease was
    effectively terminated (the first option stated above).       Thus, JPAY argues,
    5
    accelerated rent was then due. At the hearing before Judge Arzola, Biscayne
    provided evidence and argument that it had retaken possession of the vacated
    premises on the lessee’s behalf, was able to re-let a portion of it, made good-faith
    effort to re-let the remaining premises without success, and did not seek the
    accelerated rent due under the lease.1 Under the case law, Biscayne is not entitled
    to terminate the lease and also accelerate the rent:
    By retaking possession either for his own account or for the account
    of the lessee, a lessor loses the right to recover the full amount of
    remaining rental due on the basis of an acceleration clause. The two
    positions are inconsistent. (citations omitted) If the lessor retakes
    possession for the account of the lessee, two results follow. First, the
    lessor acquires a duty to exercise good faith in attempting to relet the
    premises, and second, any rentals received by the lessor as a result of
    the reletting must be deducted from the balance of rent due from the
    lessee.
    Coast Fed., 
    362 So. 2d at 984
    . Biscayne re-took the vacated premises, made good
    faith efforts to re-let on JPAY’s behalf, and deducted what it got from a partial
    sublet from JPAY’s unpaid rents due up to the date of the JPAY I final judgment.
    Its actions belie an intent to accelerate.
    1 JPAY argued that it was an issue of fact whether Biscayne re-took the premises
    for its own account or for JPAY’s – but the court asked why would Biscayne be
    billing JPAY if it re-took for its own use:
    But what evidence have you shown me that they’ve taken this for their
    possession: They have specifically indicated that what they’ve done
    is attempted to re-let unsuccessfully, they’ve accepted rent from the
    subtenant, which, as a result, lessens your client’s liability, and they
    have not utilized this for any purpose other than to re-let. They have
    not used it for storage, they’ve not used it to throw office parties . . .
    6
    RES JUDICATA ISSUE
    JPAY I is not res judicata as to JPAY II. Under the doctrine of res judicata,
    a final judgment or decree on the merits by a court of competent jurisdiction
    constitutes an absolute bar to a subsequent suit on the same cause of action and is
    conclusive of all issues which were raised or could have been raised in the action.
    Wise v. Tucker, 
    399 So. 2d 500
     (Fla. 4th DCA 1981). To apply the doctrine there
    must be (1) identity in the thing sued for, (2) identity of the causes of action, (3)
    identity of the persons and parties to the action, and (4) identity of the person for or
    against whom the claim is made. See Pumo v. Pumo, 
    405 So. 2d 224
    , 226 (Fla. 3d
    DCA 1981). In this case, the parties are the same, the same landlord is suing the
    same lessee, but the identity of the thing sued for is different: JPAY II seeks
    damages for a completely different set of monthly rents that had yet to accrue at
    the time the judgment in JPAY I was rendered. Those damages were not included
    in JPAY I judgment. See Gilbert v. Florida Power & Light Co., 
    981 So. 2d 609
    ,
    614 (Fla. 4th DCA 2008) (holding that under the rule against splitting a cause of
    action, a new claim for damages is not barred if the underlying cause of action had
    not accrued at the time of filing the previous lawsuit); see also Greene v. Boyette,
    
    587 So. 2d 629
    , 630 (Fla. 1st DCA 1991) (holding that a suit for one installment
    payment does not preclude suit for a later installment).2
    7
    The record clearly establishes that Biscayne was not seeking accelerated rent
    in JPAY I, and that Order did not grant accelerated rent. Although JPAY I is a
    Final Judgment, it is not res judicata as to JPAY II; the JPAY I Order only
    adjudicated outstanding rent due that had accrued from Appellant’s failure to pay
    monthly rent installments under the lease from March 2014 through the entry of
    the JPAY I order; there was no award for the entire amount of future rents. We
    therefore affirm the trial court’s order granting Biscayne’s amended motion for
    summary judgment.
    Affirmed.
    2 JPAY’s estoppel argument fits under this same analysis and we reject it for those
    reasons.
    8
    

Document Info

Docket Number: 3D16-1308

Citation Numbers: 225 So. 3d 876, 2017 Fla. App. LEXIS 8961, 2017 WL 2664679

Judges: Suarez, Lagoa, Logue

Filed Date: 6/21/2017

Precedential Status: Precedential

Modified Date: 10/19/2024