Trump Endeavor 12, LLC v. Fernich, Inc., Etc. , 2017 Fla. App. LEXIS 5075 ( 2017 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed April 12, 2017.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    Nos. 3D16-1065 & 3D16-1865
    Lower Tribunal No. 15-13350
    ________________
    Trump Endeavor 12 LLC,
    Appellant,
    vs.
    Fernich, Inc. d/b/a The Paint Spot,
    Appellee.
    Appeals from the Circuit Court for Miami-Dade County, Jorge E. Cueto,
    Judge.
    Bruce S. Rogow and Tara A. Campion (Fort Lauderdale), for appellant.
    Taylor Espino Vega & Touron, Daniel R. Vega and Vanessa A. Van Cleaf,
    for appellee.
    Before EMAS, LOGUE and SCALES, JJ.
    EMAS, J.
    In these consolidated appeals, appellant Trump Endeavor 12, LLC
    (“Trump”) seeks review of two trial court orders:         (1) a final judgment of
    foreclosure of a construction lien by appellee, Fernich, Inc., d/b/a The Paint Spot
    (“Paint Spot”); and (2) a final judgment awarding attorney’s fees and costs to Paint
    Spot.1 We affirm, holding that competent substantial evidence supports the trial
    court’s determination that Paint Spot substantially complied with the statutory lien
    provisions in section 713.06(2), Florida Statutes (2013), and that Trump failed to
    establish it was adversely affected by any omission or error in the Notice to Owner
    (“NTO”).
    BACKGROUND AND PROCEEDINGS BELOW
    On October 21, 2014, Paint Spot recorded a Claim of Lien against the
    Trump National Doral Miami, owned by Trump. When Trump failed to pay
    $32,535.87 owed to Paint Spot for paint and related materials, Paint Spot filed a
    complaint to foreclose its Claim of Lien. Trump asserted that the Claim of Lien
    was invalid because it identified the wrong contractor on the project and because
    Paint Spot failed to comply with the provisions of section 713.06(2)(a).
    The evidence and testimony at trial, taken in a light most favorable to
    upholding the judgment on appeal,2 reveals the following:
    1 As to the final judgment for attorney’s fees, Trump seeks reversal only in the
    event this court reverses the foreclosure final judgment, and does not otherwise
    challenge the merits of that judgment.
    2 Underwater Eng’g Svcs., Inc. v. Utility Bd. of City of Key West, 
    194 So. 3d 437
    2
    The project at the Trump National Doral Miami consisted of two parts:
    renovations to the property’s ten lodges (“the Lodge Project”) and renovations to
    the clubhouse (“the Clubhouse Project”).       Both the Lodge Project and the
    Clubhouse Project share the same property address: 
    4400 N.W. 87
    Avenue, Miami,
    Florida.
    Trump hired a different general contractor for each of the two projects:
    Straticon, LLC for the Lodge Project, and T&G Constructors for the Clubhouse
    Project. Straticon hired M&P Reynolds, Inc. (“M&P”) to furnish paint and labor
    for the Lodge Project, which in turn contracted with Paint Spot to supply paint and
    related materials. Paint Spot negotiated pricing with M&P, which M&P submitted
    to Straticon.3 Trump then approved M&P’s price quotations.4 Trump recorded
    multiple Notices of Commencement (“NOC”) for the Lodge Project, identifying
    Straticon as the general contractor for that project, and later recorded a NOC
    naming T&G as the general contractor for the Clubhouse Project. All the NOCs
    disclosed the same address for both projects:     
    4400 N.W. 87
    Avenue, Miami,
    Florida.
    (Fla. 3d DCA 2016); Hall v. Hall, 
    190 So. 3d 683
    , 684 (Fla. 3d DCA 2016).
    3 According to the trial testimony of Paint Spot’s president (which testimony the
    trial court found credible), Paint Spot dealt directly with M&P only and did not
    know that Straticon and T&G were the project’s general contractors.
    4 Trump directly negotiated pricing with subcontractors, rather than allowing its
    general contractors to do so.
    3
    Prior to supplying materials to the Lodge Project, Paint Spot’s president,
    Juan Carlos Enriquez, visited the project site for the purpose of obtaining a copy of
    the NOC, so that Paint Spot could use it to prepare its statutory NTO. Enriquez
    made it a habit to obtain the NOC from the owner of the project, rather than the
    general contractor or subcontractor, to ensure that his NTO contained the correct
    information.   When Enriquez asked for the NOC from Trump’s Director of
    Construction, Frank Sanzo, Sanzo mistakenly handed Enriquez the T&G NOC
    instead of the Straticon NOC. At this point, Enriquez was unaware that there was
    a different general contractor for each of the two projects.
    Using this T&G NOC, Paint Spot prepared and timely served its NTO on
    Trump and on T&G by certified mail in November 2013.5 Paint Spot began
    supplying materials to the Lodge Project on November 8, 2013.
    On November 21, 2013, Straticon’s project manager, Jamie Gram, sent an
    email to Claudio Bravo, a Benjamin Moore representative and Paint Spot’s paint
    distributor. In this email, Straticon’s project manager advised Bravo that, after
    reviewing Paint Spot’s NTO, he determined that it had incorrectly been filed under
    the T&G NOC, and that the NTO needed to be corrected and addressed to
    Straticon as the general contractor. Attached to this email was a copy of Paint
    Spot’s NTO.
    5Importantly, the evidence established that Straticon timely received a copy of the
    NTO that had been served on Trump and on T&G.
    4
    Bravo forwarded Straticon’s email to Enriquez and, two days later, Enriquez
    responded that it was being taken care of. However, due to oversight, Enriquez
    never prepared or served a corrected NTO on Straticon.       Nevertheless, there can
    be no doubt that, as of November 21, 2013 (at the latest), Straticon was in
    possession, and had actual knowledge, of the NTO, as it was Straticon’s own
    project manager who reviewed the NTO, discovered the discrepancy, and sent the
    email alerting Benjamin Moore and Paint Spot of the error.
    Notwithstanding the error on the face of the NTO, Straticon knew that Paint
    Spot was suppling materials to the Lodge Project and knew that Paint Spot was
    M&P’s only paint supplier for the project. Paint Spot attended meetings with
    Straticon regarding the Lodge Project, and Paint Spot submitted signed partial
    waivers of lien to M&P as a precondition to receiving payment for the paint
    materials. Straticon would not pay M&P without M&P submitting partial waivers
    from its suppliers.
    Paint Spot continued supplying materials to the Lodge Project through
    September of 2014, at which time M&P stopped working on the project because it
    was not being paid by Straticon.     At the time M&P left the Lodge Project,
    $32,535.87 worth of paint and supplies delivered by Paint Spot, which had not
    been paid for, remained at the Lodge Project. Trump used those materials to finish
    5
    the painting work, but Paint Spot was never paid for those items, resulting in the
    instant action to foreclose the lien.
    After a non-jury trial, the trial court determined, inter alia, that (1) Trump
    and Straticon had actual knowledge of Paint Spot’s NTO; (2) Trump and Straticon
    had actual knowledge that Paint Spot was supplying materials to Straticon (through
    M&P) for the Lodge Project; (3) Trump was estopped from invalidating Paint
    Spot’s NTO because Trump caused Paint Spot to rely to its detriment on the T&G
    NOC; and (4) Paint Spot substantially complied with the statutory requirements of
    section 713.06 and therefore its NTO was valid and its lien enforceable. The trial
    court thereafter entered final judgment in favor of Paint Spot, and subsequently
    entered final judgment awarding attorney’s fees to Paint Spot pursuant to section
    713.29, Florida Statutes (2013). These consolidated appeals followed.
    Trump asserts that strict compliance with 713.06(2)(a) was required of Paint
    Spot, and that the trial court erred in enforcing the lien because Paint Spot failed to
    strictly comply with that provision, despite having knowledge, prior to the
    statutory deadline, that the NTO was defective. Trump contends that neither
    detrimental reliance nor substantial compliance applies here to validate, or permit
    enforcement of, the lien.
    To the extent that we are reviewing the trial court’s factual determinations,
    our standard of review is whether there is competent, substantial evidence to
    6
    support the judgment. James P. Driscoll, Inc. v. Gould, 
    521 So. 2d 301
    (Fla. 3d
    DCA 1988).    To the extent that we are reviewing the trial court’s application of
    the law to its factual determinations, our standard of review is de novo. Stock
    Bldg. Supply of Fla. Inc. v. Soares Da Costa Constr., 
    76 So. 3d 313
    , 316 (Fla 3d
    DCA 2011).
    ANALYSIS
    The Construction Lien Law
    Chapter 713 of the Florida Statutes, entitled “Construction Lien Law,”
    establishes a statutory framework for establishment and enforcement of
    construction liens by subcontractors, laborers and materialmen.            “[T]he
    fundamental purpose of the Construction Lien Law is to protect those who have
    provided labor and materials for the improvement of real property.”         WMS
    Constr., Inc. v. Palm Springs Mile Assoc., Ltd., 
    762 So. 2d 973
    , 974-75 (Fla. 3d
    DCA 2000). “It is to be construed favorably so as to give laborers and suppliers
    the greatest protection compatible with justice and equity.” 
    Id. at 975.
    “The
    mechanics lien law was enacted to protect the interests of subcontractors and
    materialmen who remain unpaid while the owner pays the contractor directly.”
    Hardrives Co. v. Tri-County Concrete Prods., Inc., 
    489 So. 2d 1211
    , 1212 (Fla. 4th
    DCA 1986).
    7
    For our purposes, the relevant provisions are found in section 713.06,
    Florida Statutes (2013).
    Section 713.06(1) provides:
    A materialman or laborer, either of whom is not in privity with the
    owner, or a subcontractor or sub-subcontractor who complies with the
    provisions of this part and is subject to the limitations thereof, has a
    lien on the real property improved for any money that is owed to him
    or her for labor, services, or materials furnished in accordance with
    his or her contract and with the direct contract and for any unpaid
    finance charges due under the lienor's contract.
    Section 713.06(2)(a) provides:
    All lienors under this section, except laborers, as a prerequisite to
    perfecting a lien under this chapter and recording a claim of lien, must
    serve a notice on the owner setting forth the lienor's name and
    address, a description sufficient for identification of the real property,
    and the nature of the services or materials furnished or to be
    furnished. A sub-subcontractor or a materialman to a subcontractor
    must serve a copy of the notice on the contractor as a prerequisite to
    perfecting a lien under this chapter and recording a claim of lien. A
    materialman to a sub-subcontractor must serve a copy of the notice to
    owner on the contractor as a prerequisite to perfecting a lien under this
    chapter and recording a claim of lien. A materialman to a sub-
    subcontractor shall serve the notice to owner on the subcontractor if
    the materialman knows the name and address of the subcontractor.
    The notice must be served before commencing, or not later than 45
    days after commencing, to furnish his or her labor, services, or
    materials, but, in any event, before the date of the owner's
    disbursement of the final payment after the contractor has furnished
    the affidavit under subparagraph (3)(d)1. The notice must be served
    regardless of the method of payments by the owner, whether proper or
    improper, and does not give to the lienor serving the notice any
    priority over other lienors in the same category; and the failure to
    serve the notice, or to timely serve it, is a complete defense to
    enforcement of a lien by any person. The serving of the notice does
    not dispense with recording the claim of lien. The notice is not a lien,
    8
    cloud, or encumbrance on the real property nor actual or constructive
    notice of any of them.
    (Emphasis added.)
    Section 713.06(2)(b) provides:
    If the owner, in his or her notice of commencement, has designated a
    person in addition to himself or herself to receive a copy of such
    lienor's notice, as provided in s. 713.13(1)(b), the lienor shall serve a
    copy of his or her notice on the person so designated. The failure by
    the lienor to serve such copy, however, does not invalidate an
    otherwise valid lien.
    Finally, under section 713.06(2)(f):
    If a lienor has substantially complied with the provisions of
    paragraphs (a), (b), and (c), errors and omissions do not prevent the
    enforcement of a claim against a person who has not been adversely
    affected by such omission or error. However, a lienor must strictly
    comply with the time requirements of paragraph (a).
    There is no dispute that Paint Spot timely served the NTO on Trump (as
    well as T&G and M&P). There is also no dispute that the NTO was substantially
    in the form provided by section 713.06(2)(c), with one exception: the name of the
    contractor was listed as T&G instead of Straticon.
    And while the notice was not directly served by Paint Spot upon Straticon,
    the evidence at trial established that: Straticon actually received the NTO in a
    timely manner; Straticon was on actual notice that Paint Spot was supplying
    materials to the Lodge Project under an order given by M&P; and that Straticon
    and Trump knew from the NTO that Trump was required to obtain lien waivers
    9
    from Paint Spot in order to avoid paying twice for materials provided by Paint
    Spot.
    Detrimental Reliance
    Further, although “mechanic’s lien statutes are to be strictly construed . . .
    good faith reasonable substantial compliance has been recognized as effective in
    cases where material acts or omissions by the owner have caused circumstances of
    detrimental reliance.” Roof Structures, Inc. v. Picou, 
    544 So. 2d 1138
    (Fla. 4th
    DCA 1989). It is clear that until November 21, Paint Spot did in fact rely, to its
    detriment, upon the wrong NOC it received from Trump. But on that date, when
    Paint Spot received the email from Bravo regarding this error, Paint Spot was no
    longer relying to its detriment on the incorrect information supplied by Trump.
    Instead, Paint Spot failed to take steps to remedy this defect after being placed on
    notice of the defect.     Therefore, Trump is correct in its contention that the
    detrimental reliance doctrine does not apply in this case. Compare Picou, 
    544 So. 2d
    at 1139 (holding lien valid despite subcontractor naming wrong contractor in
    NTO because the owner failed to file a NOC identifying the correct contractor, and
    this material omission caused the subcontractor to detrimentally rely upon
    erroneous building department records.) See also, Suchman v. Nat’l Hauling, Inc.,
    
    549 So. 2d 200
    (Fla. 3d DCA 1989) (holding NTO was valid, despite failure to
    10
    deliver a copy of the NTO to the general contractor, because owner failed to file a
    NOC identifying that general contractor).
    Substantial Compliance
    Nevertheless, the absence of detrimental reliance by Paint Spot does not end
    our analysis. A plain reading of the applicable statute evidences that if Paint Spot
    has “substantially complied” with section 713.06(2)(a),6 (b)7 and (c), “errors and
    omissions do not prevent the enforcement of a claim against a person who has not
    been adversely affected by such omission or error.” § 713.06(2)(f), Fla. Stat.
    (2013).
    Subsection (a) requires the lienor to, within 45 days after commencing to
    furnish labor, services, or materials, serve the NTO “on the owner setting forth the
    lienor’s name and address, a description sufficient for identification of the real
    6  Section 713.06(2)(f) deems “substantial compliance” sufficient, with one
    exception: “a lienor must strictly comply with the time requirements” of subsection
    (2)(a), which mandates that the NTO be served within forty-five days after
    commencing to furnish labor, services or materials. Trump contends that Paint
    Spot failed to strictly comply with this time requirement because it did not serve
    Straticon within forty-five days of commencement. However, subsection (2)(f)
    speaks to strict compliance with the time requirements, not with the service
    requirement. This time requirement was met when Paint Spot served its NTO on
    Trump within 45 days of commencement.                 We further hold that there was
    substantial compliance with the service requirement; although Paint Spot did not
    serve Straticon, it is undisputed that Straticon actually received and reviewed the
    NTO within the requisite 45-day period. See 
    Suchman, 549 So. 2d at 202
    , note 5
    (holding that actual notice is sufficient to satisfy the requirements of the statute).
    7 Paint Spot’s compliance with subsection (b) is not in dispute, and thus a
    discussion of that subsection’s application to this case is unnecessary.
    11
    property, and the nature of the services or materials furnished or to be furnished.”
    It also requires the lienor, if a subcontractor or materialman, to serve the NTO on
    the contractor within that same 45-day time period. Paint Spot complied with
    these requirements, but served it on T&G instead of Straticon.      As to subsection
    (c), Paint Spot’s NTO was in compliance with the form requirements, again with
    the exception of designating the incorrect name of the contractor. Thus, we must
    assess whether the trial court properly determined that Paint Spot’s NTO
    “substantially complied” with subsections (a) and (c) and, if so, whether Trump
    established it was adversely affected by the error.
    In Symons Corp. v. Tartan-Lavers Delray Beach, Inc., 
    456 So. 2d 1254
    (Fla.
    4th DCA 1984), Symons Corp., a subcontractor, mistakenly listed an incorrect
    name as the owner of the property. Instead of Tartan-Lavers Delray Beach, Inc.,
    the NTO identified the owner as Lavers Delray Racquet Club. The Fourth District
    acknowledged that the names were different, but pointed out that “if the owner, or
    others, were not misled, prejudiced or injured by the claimed defect in the Notice,
    especially in the case of an honest mistake, the lien is not vitiated by such defect.”
    
    Id. at 1259.
    The Fourth District held that the lien was valid, and that the owner
    could not have been misled by this error because the owner responded to the claim
    of lien by bonding off the lien against the property.
    12
    In the instant case, Trump and Straticon had actual, express and timely
    notice that: Paint Spot mistakenly named the wrong contractor in its NTO; M&P
    (whose name was properly listed in the NTO) was Straticon’s own subcontractor
    for the Lodge Project; Paint Spot was supplying materials to the Lodge Project
    under M&P; and Paint Spot intended to lien the property if payment was not timely
    made.
    Further, the evidence established that Straticon treated Paint Spot as a
    potential lienor for the duration of the Lodge Project. For example, Paint Spot
    attended meetings with Straticon on the Lodge Project, and Straticon received
    partial lien waivers from M&P, which included partial lien waivers from Paint
    Spot for materials provided for the Lodge Project. Several partial payments were
    made to Paint Spot for materials supplied for the Lodge Project. Straticon even
    attempted to assist Paint Spot in obtaining payment from Trump for the remaining
    Paint Spot materials left at the Lodge Project, which materials were later used to
    complete M&P’s work.
    We addressed a similar error in Centex-Winston Corp. v. Crown Paint, Inc.,
    
    294 So. 2d 694
    (Fla. 3d DCA 1974). In that case, instead of the actual contractor
    (Arcus Dry Wall) being identified in the notice to owner, Crown Paint listed the
    contractor as “Sen Tex-Winston Corp.” (i.e., the owner and developer of the
    project, though incorrectly spelled). Notwithstanding this error, we affirmed the
    13
    final judgment and held that the lien was properly found valid, because Centex-
    Winston “failed to make a sufficient showing that it was adversely affected by the
    error on the notice to owner.” 
    Id. at 695.
    Here too, Trump has failed to carry its
    burden of demonstrating that it was adversely affected by Paint Spot’s erroneous
    listing of T&G as the contractor. Notably, there is no evidence that, as a result of
    this error, Trump paid T&G for the paint supplies, and was thus at risk of paying
    twice for the same materials. Rather, the evidence at trial established that the
    painting subcontractor (who replaced M&P when it left the job) used Paint Spot’s
    materials to finish the Lodge Project, and that Paint Spot was not fully paid for
    those materials. At trial, Jamie Gram (Straticon’s project manager) admitted the
    reason for not paying Paint Spot the amounts due:
    [T]he decision not to pay [Paint Spot] had nothing to do with a
    defective Notice to Owner . . . . They weren’t paid because Mr. Trump
    had already paid M&P a decent amount of money of the contract . . .
    and there was still a lot of work that needed to be completed, so we
    used the money, M&P’s remaining balance, plus additional funds to
    pay to get the work done.
    “The purpose of the [NTO] is to protect an owner from the possibility of
    paying over to his contractor sums which ought to go to a subcontractor who
    remains unpaid.” Stock Bldg. 
    Supply, 76 So. 3d at 319
    (quoting Bishop v. James
    A. Knowles, Inc., 
    292 So. 2d 415
    , 417 (Fla. 2d DCA 1974)).
    CONCLUSION
    14
    Accordingly, we hold that the trial court correctly determined that Paint Spot
    substantially complied with the provisions of section 713.06(2)(a), (b), and (c), and
    that Paint Spot strictly complied with the time requirements of subsection (2)(a).
    We further hold that that Trump failed to establish that it was adversely affected by
    the error contained in the NTO. We also affirm the final judgment awarding
    attorney’s fees.
    Affirmed.
    15