DEAN DESANTIS and LAURA DESANTIS v. LEO A. VECELLIO, JR. ( 2018 )


Menu:
  •        DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA
    FOURTH DISTRICT
    ADDISON CONSTRUCTION CORPORATION, ADDISON
    DEVELOPMENT CORPORATION, and DANNY E. SWANSON,
    Appellants,
    v.
    LEO A. VECELLIO, JR., KATHRYN C. VECELLIO, DEAN DESANTIS,
    LAURA DESANTIS, DEERFIELD BUILDERS SUPPLY COMPANY, INC.,
    BLADE WINDOW AND DOOR COMPANY a/k/a BLADE
    CONSTRUCTION, GULFSTREAM ROOFING, INC., and EAGLE
    WINDOW AND DOOR, LLC,
    Appellees.
    No. 4D16-0618
    DEAN DESANTIS and LAURA DESANTIS,
    Appellants,
    v.
    LEO A. VECELLIO, JR., KATHRYN C. VECELLIO, ADDISON
    CONSTRUCTION CORPORATION, a Florida corporation, ADDISON
    DEVELOPMENT CORPORATION, a Florida corporation, DANNY E.
    SWANSON, DEERFIELD BUILDERS SUPPLY COMPANY, INC., a Florida
    corporation, R.V. ELECTRIC, INC., a Florida corporation, PREFERRED
    AIR CONDITIONING AND MECHANICAL, INC., a Florida corporation,
    L&L ORNAMENTAL ALUMINUM AND IRONWORKS, INC., a Florida
    corporation, PHOENIX ARCHITECTURE, INC., a Florida corporation,
    and ALFRED CILCIUS,
    Appellees.
    No. 4D16-0863
    [March 21, 2018]
    Appeals and cross-appeals from the Circuit Court for the Fifteenth
    Judicial Circuit, Palm Beach County; Gregory M. Keyser, Judge; L.T. Case
    No. 502009CA040005XXXXMB.
    Diane H. Tutt of Conroy Simberg, Hollywood, for Addison Construction
    Corporation, Addison Development Corporation and Danny E. Swanson.
    Thomas A. Valdez and Robert J. Cousins of Quintairos, Prieto, Wood &
    Boyer, P.A., Tampa, and Charles E. Muller II and Brian A. Lebensburger
    of Muller & Lebensburger, P.A., Miami, for Dean DeSantis and Laura
    DeSantis.
    Jack J. Aiello, G. Joseph Curley, Gregor J. Schwinghammer, Jr., and
    Roger Feicht of Gunster, Yoakley & Stewart, P.A., West Palm Beach, for
    Leo A. Vecellio, Jr. and Kathryn C. Vecellio.
    DAMOORGIAN, J.
    The subject of these voluminous appeals, which we have sua sponte
    consolidated for opinion purposes, is a sprawling ocean-front residence
    located in the Town of Palm Beach. According to its purchasers,
    Appellees/Cross-Appellants, Leo and Kathryn Vecellio (“Buyers”), the
    residence was defectively constructed. Based on the foregoing, Buyers
    sued the sellers of the home, Dean and Laura DeSantis (“Sellers”); the
    developer and general contractor who built the home, Addison
    Development Corporation and Addison Construction Corporation
    (individually referred to as “Addison Construction” and “Addison
    Development” and collectively referred to as “Addison”); Addison’s
    principal, Danny Swanson; and a myriad of subcontractors who worked
    on the home. Ultimately, Buyers settled with the majority of the
    subcontractors and recovered over $3 million in damages from Addison,
    Sellers, and Mr. Swanson. Addison, Sellers, and Mr. Swanson each appeal
    their respective judgment(s) and Buyers cross-appeal, primarily
    challenging the amount of damages recovered. Collectively, the parties
    raise more than ten issues for our consideration on appeal. We affirm in
    all respects and write to discuss two discrete issues: 1) the form of the
    judgments and 2) the court’s decision to apply certain subcontractor
    settlements as a setoff to Buyers’ recovery for Sellers’ and Addison’s breach
    of contract.
    Background
    In 2002, Sellers purchased the subject property and then entered into
    Construction and Marketing Agreements with Addison regarding the
    construction and sale of a new custom home. Construction of the home
    began in 2004 and went through late 2006. After receiving a certificate of
    occupancy for the home, Addison Development began marketing the
    property on behalf of the Sellers in early 2007. A few months later, Buyers
    2
    placed an offer on the home thus beginning extensive negotiations between
    the parties. On November 27, 2007, Buyers and Sellers entered into a
    formal agreement (“Purchase Agreement”) regarding the sale of the home.
    Addison joined the Purchase Agreement for the limited purpose of agreeing
    to provide a Warranty. Pursuant to the Purchase Agreement, Buyers had
    until December 17, 2007 to inspect the home and closing was set to take
    place on January 10, 2008.
    During the inspection period, Buyers had air quality, roofing, and
    general inspections performed on their behalf. The air quality inspection
    indicated that there were elevated mold levels in portions of the home.
    Based on the inspection reports, Buyers created a punch-list of items they
    wanted repaired before going forward with the sale. The parties then
    entered into an Addendum to the Purchase Agreement wherein Sellers and
    Addison Development agreed to “repair, replace, or correct all items or
    issues addressed as concerns in the Inspection Reports.” Addison then
    underwent efforts to fix all of the Addendum issues and, while repairs were
    still ongoing, the parties closed on the home. At closing, Addison
    Construction provided Buyers with a Warranty as required by the
    Purchase Agreement. The Warranty provided that Addison Construction
    agreed to repair any work that was proven to be defective within one year
    of the closing date.
    In May of 2008, after Addison was done with its Addendum work,
    Buyers moved into the home. Shortly thereafter, Buyers began to notice
    that that the home still had moisture intrusion issues. Buyers contacted
    Addison in August of 2008 and made a warranty claim. After conducting
    additional testing, Addison discovered the presence of mold and water
    damage along the east wall of the master bedroom. At this point, Addison
    disclosed the fact that the master bedroom suffered water damage during
    2005’s Hurricane Wilma. This admission alarmed Buyers and caused
    them to question the integrity of the home’s overall construction.
    Thereafter, Buyers performed extensive testing throughout the home
    and discovered numerous additional latent defects. Having “lost trust” in
    Addison and Sellers at this point, Buyers sent Addison and the Sellers
    notice that they were in default of their respective obligations under the
    Purchase Agreement, Addendum, and Warranty. A few months later,
    Buyers filed their lawsuit against Addison, Mr. Swanson, Sellers, and
    twelve of the subcontractors who worked on the home.
    Against Addison, the Buyers alleged causes of action for violation of the
    Florida Building Code, breach of contract, negligent failure to disclose,
    fraud, and violation of Florida’s Deceptive and Unfair Trade Practices Act
    3
    (“FDUTPA”). Against Sellers, they alleged causes of action for breach of
    contract, negligent failure to disclose, fraud, violation of FDUTPA, and
    securities fraud. Against the subcontractors whom they were not in privity
    with, Buyers alleged a cause of action for violation of the Florida Building
    Code. Finally, against Mr. Swanson, they alleged causes of action for
    violation of the Florida Building Code, negligent failure to disclose, fraud
    and FDUTPA. Because the Purchase Agreement and Warranty contained
    a jury trial waiver, all claims against Sellers and Addison were set for a
    bench trial. The remaining claims, including the claims against Mr.
    Swanson, were set for a jury trial.
    Before trial, Buyers settled with ten of the subcontractors. The sum
    total of the Buyers’ settlements with the subcontractors was $2,725,000.
    Buyers moved in limine to exclude mention of these settlements. In their
    motion, Buyers represented that the settlements resolved their building
    code claims against Mr. Swanson as well as their building code claims
    relating to: the main entry door of the house, stucco, cast stone, exterior
    balcony and interior railings, steel columns and beams, truss girder
    hanger, concrete defects, exterior wall coverings in the summer kitchen,
    roof trusses, HVAC, electrical, and plumbing. They also argued that
    although “evidence of the settlement discussions and negotiations
    pertaining to these issues may be relevant as evidence of a setoff to any
    damages awarded to [Buyers], . . . evidence relating to setoff is premature
    [and] should be made at the conclusion of the trial outside the jury’s
    presence so as to not confuse or unduly prejudice the jury.” The court
    granted Buyers’ motion without elaboration.
    Following nearly ten weeks of evidence and testimony, the jury entered
    a special verdict wherein it found that neither of the two remaining
    subcontractors (the roofer and window/door installer) violated the Florida
    Building Code. The jury also found that Mr. Swanson did not violate
    FDUTPA but did knowingly made a false statement or intentional omission
    concerning the Hurricane Wilma water damage with the intention that
    Buyers would rely on the statement or omission and which reliance called
    injury to Buyers. Based on its fraud finding, the jury awarded Buyers
    $78,984.30 in damages against Mr. Swanson.
    After the non-jury proceedings, the court entered an extensive order
    making detailed and thorough findings regarding the defects in the home
    and Buyers’ entitlement to damages. The court found that none of the
    parties violated the Florida Building Code, FDUTPA, or committed the tort
    of negligent failure to disclose. Likewise, it found that Sellers did not
    commit securities fraud. It did find, however, that Addison committed
    fraud by failing to disclose, post-closing, information “regarding water
    4
    entry into the Home associated with Hurricane Wilma and leaking through
    or around the center window in the Master Bedroom.” It also found that
    when Addison committed the fraud, it was acting as Sellers’ actual and
    apparent agent and, therefore, also found Sellers liable. Finally, the court
    found that Addison and Sellers breached their respective contractual
    duties under the Purchase Agreement, Addendum, and Warranty.
    With respect to damages, the court found that Buyers were entitled to
    a total of over $3.5 million in damages associated with the repair and loss
    of use of their home. It found that $2,525,684.72 of those damages were
    recoverable against Addison Construction under the Warranty;
    $3,339,654.04 were recoverable against Addison Development and Sellers
    under the Addendum; and $2,365,651.01 were recoverable against Sellers
    under the Purchase Agreement. Many of these damages overlapped.
    Pertaining to its fraud finding, the court found that Buyers would not
    have incurred some of the afore-outlined repair and loss of use damages
    had Addison and Sellers disclosed their water intrusion knowledge earlier
    on. The court found that Buyers incurred $78,984.30 in damages flowing
    from this fraud, which was comprised of Buyers’ inspection fees and the
    cost of replacing the wood floors in the master bedroom. These damages
    also overlapped with the breach of contract damages and the fraud
    damages against Mr. Swanson.
    Post-trial, Mr. Swanson, Sellers and Addison moved for the court to
    apply the subcontractor settlements as setoffs against each of the
    judgments. Looking at the scope of the subcontractor settlements as
    outlined in the individual releases and comparing them with the damages
    requested and recovered by Buyers in their breach of contract claims
    against Addison and Sellers, the court determined that “the pleadings,
    evidence, and argument [do not] demonstrate that [Buyers] either reduced
    their claims for damages at trial or removed claims for damages at trial
    related to the settled scopes of work that will have an impact on the Court’s
    evaluation of whether to award [Addison and Sellers] a set off prior to the
    entry of a Final Judgment.” Therefore, the court granted Addison and
    Sellers a setoff of the subcontractor settlements against the breach of
    contract awards. However, the court reached a different conclusion with
    respect to the fraud awards. It found that the a setoff was not warranted
    because “there were no allegations, evidence or arguments that Mr.
    Swanson[, Addison, and Sellers] could be liable [for] fraud based upon any
    actions of the Settled Defendants.”
    Thereafter, the court entered an Omnibus Final Judgment as to all of
    Buyers’ non-jury claims against Sellers and Addison. In the judgment, the
    5
    court awarded Buyers the following amounts, which accounted for the
    setoffs and prejudgment interest: 1) $518,606.89 against Addison
    Construction under the Warranty; 2) $2,652.284.83 against Addison
    Development and Sellers under the Addendum; 3) $852,920.84 against
    Sellers under the Purchase Agreement; and 4) $120,341.78 against
    Addison and Sellers for Fraud. These appeals follow.
    Analysis
    1) Form of the Judgments
    We begin our analysis by addressing the court’s decision to reduce the
    fraud damages against the parties and the damages under each contract
    to separate judgments. It is undisputed that each of these judgments
    contained overlapping damages. For example, all of the fraud and contract
    judgments encompassed damages associated with replacing the master
    bedroom floor. It is also undisputed that under Florida law, a party is not
    permitted to recover for the same damages more than once. What is
    disputed is whether the potential for double recovery needed to be
    addressed pre-judgment or post-judgment. Addison argues the judgments
    should have indicated they were joint and several on their face. Buyers
    counter that Addison is arguing about a “non-issue” because the “law is
    clear that a party may not collect the same damages twice [and this] is a
    collection issue.” 1 We agree with Buyers.
    The Restatement of Judgments is instructive to this issue. Section 49
    of the Second Restatement provides that:
    A judgment against one person liable for a loss does not
    terminate a claim that the injured party may have against
    another person who may be liable therefor.
    Restatement (Second) of Judgments § 49 (Am. Law Inst. 1982). The author
    of the restatement explained the rational for this rule as follows:
    When a person suffers injury as the result of the concurrent
    or consecutive acts of two or more persons, he has a claim
    against each of them. . . . Accordingly, a judgment for or
    against one obligor does not result in merger or bar of the
    claim that the injured party may have against another obligor.
    . . . The rule that there are separate claims against each
    1  Sellers made their own argument against multiple judgments in their brief
    but abandoned the argument and sided with Buyers’ position at oral argument.
    6
    obligor applies whether the obligation results from a tort, a
    breach of contract, or other obligation.
    ...
    Under rules originating in an early period of legal
    development, however, rendition of judgment against one of
    several obligors sometimes had the effect of extinguishing a
    claim against another. Some of these rules were based on the
    notion that a “joint” obligation could be enforced only through
    a single action. . . . Other rules having like effect were
    expressed in terms of requiring an “election of remedies.”
    Both types of rules were often justified as a means of
    preventing double recovery for the loss involved. These rules
    are now obsolete. Double recovery is foreclosed by the rule
    that only one satisfaction may be obtained for a loss that is
    the subject of two or more judgments.
    Restatement (Second) of Judgments § 49 cmt. a (Am. Law Inst. 1982).
    The “rule” of satisfaction as a preventive to double recovery is set forth
    in section 50 of the Restatement as follows:
    When a judgment has been rendered against one of several
    persons each of whom is liable for a loss claimed in the action
    on which the judgment is based:
    (1) A satisfaction or release of the judgment, or covenant
    not to execute upon it, or other agreement terminating
    in whole or in part the judgment debtor’s obligation,
    does not discharge the liability of any of the other
    persons liable for the loss, except:
    a. To the extent that the agreement may so provide; and
    b. To the extent required by the law of suretyship.
    (2) Any consideration received by the judgment creditor in
    payment of the judgment debtor’s obligation discharges,
    to the extent of the amount of value received, the
    liability to the judgment creditor of all other persons
    liable for the loss.
    Restatement (Second) of Judgments § 50 (Am. Law Inst. 1982).
    7
    The basis of the foregoing principles is rooted in fairness: if a party is
    unable to collect on a judgment, it should not be precluded from seeking
    other consistent but separate manners of recovery against equally liable
    persons. See Heller v. Held, 
    817 So. 2d 1023
    , 1027 (Fla. 4th DCA 2002)
    (attorney who held a charging lien and judgment against client in a case
    which settled after attorney withdrew was not precluded from seeking
    recovery from settling defendants whose actions thwarted attorney’s
    enforcement of lien against settlement proceeds). Alternatively, if in
    satisfying a judgment, a party recovers damages encompassed by another
    outstanding judgment, it should not be entitled to double recovery. 
    Id.
    Based on the foregoing, Buyers properly obtained multiple judgments
    against different parties for overlapping damages. Buyers may not,
    however, satisfy each judgment entirely. Rather, Mr. Swanson, Addison,
    and Sellers may use satisfaction of any of the overlapping items of
    compensation in the various judgments as bar to payment of the
    remaining judgments. But, as argued by Buyers, this is a post-judgment
    collections issue.
    2) The Setoff Ruling
    Addison, Mr. Swanson, and Buyers each take issue with the court’s
    setoff determinations. Addison and Mr. Swanson maintain that the court
    should have extended the subcontractor settlement setoff to the fraud
    judgments entered against Addison and Mr. Swanson. In their cross-
    appeals, Buyers argue that the court erred in applying the entirety of the
    $2.75 million subcontractor settlements as a setoff to the damage awards
    against Addison and Sellers under the Purchase Agreement, Addendum
    and Warranty. Buyers assert several grounds for this argument, the main
    ground being that the damages encompassed by the subcontractor
    settlements did not overlap with the contract based damages awarded
    against Addison and Sellers. We hold that the trial court properly applied
    the subcontractor settlements as a setoff against all of the breach of
    contract awards and properly denied a setoff with respect to the fraud
    awards.
    “Whether the trial court awarded a proper set-off is a pure question of
    law reviewed de novo, and ‘no deference is given to the judgment of the
    lower courts.’” Cornerstone SMR, Inc. v. Bank of Am., N.A., 
    163 So. 3d 565
    ,
    568 (Fla. 4th DCA 2015) (quoting D’Angelo v. Fitzmaurice, 
    863 So. 2d 311
    ,
    314 (Fla. 2003)). Setoffs for collateral recoveries are available pursuant to
    sections 768.041(2) and 46.015(2) of the Florida Statutes, (2015). Both
    sections contain nearly identical language, however, section 46.015 is
    located in the civil practice and procedure title of the Florida Statutes and
    8
    section 768.041 is located in the torts title. Because the instant case was
    founded in contract and not in tort, the court found that section 46.015(2)
    was the controlling statute. To that end, section 46.015(2) provides that
    if a defendant demonstrates that a plaintiff has released “any person in
    partial satisfaction of the damages sued for, the court shall set off this
    amount from the amount of any judgment to which the plaintiff would be
    otherwise entitled at the time of rendering judgment.” § 46.015(2), Fla.
    Stat. (2015).
    The purpose of the setoff statutes is to prevent a windfall to a plaintiff
    by way of double recovery. See Cornerstone, 163 So. 3d at 569 (“The set-
    off provision in section 768.041(2) ‘was designed to prevent duplicate or
    overlapping compensation for identical damages.’” (quoting Gordon v.
    Marvin M. Rosenberg, D.D.S., P.A., 
    654 So. 2d 643
    , 644 (Fla. 4th DCA
    1995)). Thus, any “settlement recovery sought to be set off must be ‘in
    partial satisfaction for the damages sued for.’” Escadote I Corp. v. Ocean
    Three Ltd. P’ship, 
    211 So. 3d 1059
    , 1062 (Fla. 3d DCA 2016) (quoting §
    768.041(2), Fla. Stat. (2010)). Accordingly, “[i]f the settlement funds are
    applicable to a claim asserted only against the settling co-defendant, the
    non-settling co-defendants are not eligible for a set-off in the amount of
    the settlement.” Id. In the same vein, “[w]hen a settlement recovery is
    allocated between claims with different and distinctive damage elements,
    set-off should only be allowed to co-defendants jointly and severally liable
    for the same claims.” Id. at 1063 (emphasis provided).
    The necessity of same damages sued for as a prerequisite for a setoff is
    illustrated by Escadote I Corp. There, the owner of a condo unit sued the
    developer, contractor and condo association, alleging several causes of
    action based on the presence of mold in the condo unit. 
    211 So. 3d 1060
    −61. Against the condo association, the owner alleged a statutory
    claim for failure to maintain which also included a demand for attorney’s
    fees under the applicable statute. Id. at 1061. The owner did not make
    any claim of attorney’s fees against either the contractor or developer. Id.
    at 1063−64. Before the jury returned its verdict, the owner settled its
    claim against the association for $375,000. Id. at 1061. The settlement
    agreement delineated that $500 of the settlement was attributable to
    damages and the remaining sum was intended to reimburse the owner for
    its attorney’s fees. Id. The jury found the developer and contractor jointly
    and severally liable for over $2 million in damages. Id. Thereafter, the
    developer and contractor successfully moved to apply the entirety of the
    owner’s settlement with the condo association as a setoff against the
    damages awarded against them. Id. at 1062. The appellate court reversed,
    holding that because the owner did not make any claim for attorney’s fees
    against either the developer or contractor, the portion of the condo
    9
    association settlement which was specifically apportioned for attorney’s
    fees could not be applied as a setoff against the damages awarded against
    the contractor and developer. Id. at 1063−65.
    In comparison, in Centex-Rooney Construction Co., v. Martin County.,
    
    706 So. 2d 20
    , 29 (Fla. 4th DCA 1997), we held that a county’s pretrial
    settlements with the architect and mason who worked on the construction
    of a courthouse were correctly applied as a setoff to the county’s recovery
    against the construction manager because the “County’s claimed damages
    [recovered against the construction manager] were not separate and
    distinct from the damages compensated by its settlements.”
    Although the same-damages-sued-for prerequisite seems simple
    enough in theory, because settlement agreements are often so broadly
    worded, in practice it is not always easy to determine whether damages
    paid as part of a settlement overlap with damages awarded against a
    remaining co-defendant. To that end, the law provides that if settlement
    proceeds are “not apportioned between (a) claims for which co-defendants
    are jointly and severally liable with the settling co-defendant, and (b)
    claims which were only asserted against the settling co-defendant, the
    entire amount of the undifferentiated recovery is allowable as a set-off.”
    Escadote I Corp., 211 So. 3d at 1063. See also Cornerstone, 163 So. 3d at
    569 (“Where a settlement is undifferentiated and general, the aggregate of
    the amount of the settlement should be set off against the judgment.”).
    This is the case even where some of the settlement amount may have been
    for different damages and the settlement amount exceeded the damages it
    setoff. See Cornerstone, 163 So. 3d at 569.
    For example, in Cornerstone, a company sued its former bookkeeper for
    conversion after it learned that over the course of four years, the
    bookkeeper deposited $478,490 worth of checks made out the company in
    her own account at Bank of America. Id. at 566−67. The company also
    sued Bank of America for its role in allowing the bookkeeper to deposit the
    stolen checks in her account. Id. at 566. Prior to trial, the company settled
    with the bookkeeper for $285,625. Id. at 571. It was then awarded
    $146,743.23 in damages against Bank of America, a number which was
    far lower than the company’s actual damages because the statute of
    limitations barred recovery against the bank for about two-thirds of the
    embezzled checks. Id. at 567. Bank of America moved to apply the
    company’s settlement with the bookkeeper as a setoff against its liability.
    Id. The company, in turn, argued that setoff was not appropriate because
    the settlement with the bookkeeper covered damages not encompassed by
    the award against Bank of America due to the operation of the statute of
    limitations. Id. Attempting its best to do equity, the court pro-rated the
    10
    settlement with the bookkeeper based on the percentage of checks cashed
    after the statute of limitations bar and applied the pro-rated number as a
    setoff. Id. at 568.
    On appeal, we reversed the trial court’s pro-rated setoff and held that
    the entire bookkeeper settlement amount should have been applied as a
    setoff against the Bank of America award. Id. at 569. The basis of our
    decision was that the company’s settlement agreement with the
    bookkeeper “did not allocate the damages between claims.” Id. Although
    we recognized that the settlement probably encompassed damages which
    the company could not recover against Bank of America due to the statute
    of limitations and, therefore, may have provided a windfall to the Bank, we
    reasoned that it was the company’s “own failure to allocate the settlement
    agreement which has produced this result.” Id. at 570. We concluded
    that without an allocation, it was simply “impossible to know whether [the
    company] would be receiving a duplicate payment” and therefore, the trial
    court was required to offset the damage award against the bank by the
    total amount of the bookkeeper settlement. Id. In doing so, we also
    rejected the company’s attempt to explain the scope of its settlement
    agreement with the bookkeeper based on authority establishing that
    courts are required to “‘ignore a private unilateral apportionment of
    settlement proceeds among plaintiffs, when the settlement agreement itself
    fails to apportion the proceeds among the plaintiffs.’” Id. at 569 (quoting
    Dionese v. City of W. Palm Beach, 
    500 So. 2d 1347
    , 1348 (Fla. 1987)).
    In the instant case, the court underwent a thorough analysis utilizing
    the foregoing principles when arriving at its setoff determination.
    Specifically, it looked at the scope of each subcontractor settlement and
    compared it to the damages Mr. Swanson, Addison and Sellers were “sued
    for.” The court began by examining the controlling complaint, wherein
    Buyers alleged a singular cause of action against each of the settled
    subcontractors for violation of the Florida Building Code. Within that
    count, Buyers alleged that because of the various subcontractors’ defective
    workmanship, Buyers “suffered both direct and special damages,
    including, without limitation, consequential loss of use of the Residence,
    diminution in value, carrying costs, relocation expenses, expert testing
    and consulting expenses, legal expenses, property damage, repair costs,
    replacement material and supply expenses, security and staff expenses,
    moving and storage expenses, taxes, interest and insurance expenses,
    permit and inspection expenses, and other consequential damages.” In
    their breach of contract(s) count against Sellers and Addison, Buyers
    alleged that they suffered the exact damages. In the fraud counts,
    however, the Buyers alleged that the damages they suffered were those
    flowing from Mr. Swanson, Addison, and the Seller’s intentional failure to
    11
    disclose and cover up of construction defects which caused water intrusion
    in the home.
    Based on the allegations of the complaint, the court found that a setoff
    against the fraud judgments was not warranted because “there were no
    allegations, evidence or arguments that Mr. Swanson[, Addison, and
    Sellers] could be liable [for] fraud based upon any actions of the Settled
    Defendants.” The court’s finding in this respect was sound. As discussed
    in greater detail above, the settlements with the settled subcontractors
    were for damages caused by their respective scopes of work on the home.
    Alternatively, the damages “sued for” under the fraud counts were those
    flowing from Mr. Swanson’s, Addison’s, and the Seller’s intentional failure
    to disclose water damage. These are not the same. 2
    Turning to the contract based damages, the court found that the
    damages “sued for” under the contracts and the damages “sued for” under
    the count against the subcontractors were identical. Buyers argue that
    this determination was erroneous because the scope of damages they
    sought against the subcontractors should be dictated by what they could
    have actually recovered against the subcontractors, not what they claimed
    in their complaint. The law suggests otherwise. The plain language of
    section 46.015(2) establishes that when determining whether to apply a
    settlement as a setoff, the court must determine if the settlement was
    made “in partial satisfaction of the damages sued for.” § 46.015(2), Fla.
    Stat. Accordingly, when making a setoff decision, it does not matter what
    the party was actually entitled to recover, “[i]nstead, what matters is [what
    the plaintiff] sued for.” Blasland, Bouck & Lee, Inc. v. City of N. Miami, 
    283 F. 3d 1286
    , 1296 (11th Cir. 2002) (interpreting section 46.015(2)). Here,
    although Buyers may not have been entitled to recover all damages
    requested in their complaint against each of the settled subcontractors,
    the fact remains that those are the damages they “sued for.”
    2  This is not to say that Buyers may actually satisfy both the fraud and the
    breach of contract judgments as they contain duplicate items of compensation.
    See Fla. Temps. Inc. v. Shannon Props., Inc., 
    645 So. 2d 102
    , 104 (Fla. 2d DCA
    1994) (holding that because a plaintiff was not entitled to recover “damages for
    fraud that duplicate damages awarded for breach of the contract,” the court was
    required to enter a judgment “clarifying whether any award for breach of contract
    duplicates an award for fraud” in order to prevent the plaintiff from recovering
    both). However, it remains that under these circumstances, a setoff was not the
    proper mechanism to prevent double recovery. Rather, as discussed in our
    analysis on the form of judgment issue, Mr. Swanson, Addison, and Sellers may
    use satisfaction of any of the overlapping items of compensation in the breach
    judgments as a bar to payment of the fraud judgments.
    12
    Next, the court looked to each of the settlement agreements to
    determine their respective scopes. The court noted that each of the
    settlement agreements and releases between Buyers and the settled
    subcontractors provided that Buyers “agreed not to seek recovery against
    Mr. Swanson and [Addison] for damages allegedly caused by each Settled
    Defendant’s respective scope of work.” None of the settlement agreements
    differentiated the damages being settled for and all contained broad
    releases of the settled subcontractors which were not limited to releases
    for damages related to violation of the Florida Building Code. Based on
    the foregoing, the court concluded that neither “the pleadings, evidence
    and argument demonstrate that [Buyers] either reduced their [contract
    based] claims for damages at trial or removed claims for damages at trial
    related to the settled scopes of work that will have an impact on the Court’s
    evaluation of whether to award the Defendants a set off prior to the entry
    of Final Judgment.”
    Buyers also disagree with this conclusion, arguing that the court
    should have interpreted the settlement agreements consistent with the
    narrowness of the facts of the case and not the broadness of their
    language. In support of their position, Buyers point to testimony offered
    at the hearing on their motion for reconsideration of the court’s setoff
    determination. There, Buyers’ engineering expert testified that none of the
    evidence of damage to the home presented at trial was encompassed by
    the subcontractor settlements. However, this post-settlement attempt to
    differentiate the damages settled-for has no legal effect. As we explained
    in Cornerstone, a court may not apportion settlement proceeds based on
    the representation of one of the settling parties when the agreement itself
    does not do the same. 163 So. 3d at 569−70. See also Nauman v. Eason,
    
    572 So. 2d 982
    , 983−85 (Fla. 1st DCA 1990) (holding that it was error for
    trial court to apportion settlement agreement among plaintiffs where
    settlement was silent on the subject).
    Lastly, Buyers assert that the end result was unfair, emphatically
    arguing that Addison and Sellers ultimately received a setoff for damages
    not recovered in the damage awards against Addison and Sellers. They
    point to their settlement with a pool subcontractor as an example. There
    is no dispute that Buyers did not present any evidence of pool damage
    during either trial and there is also no disputing that the court did not
    delineate any damages specific to a pool in its final judgment. Although it
    seems likely that Addison and Sellers received a setoff for pool damages
    that were not awarded, because the settlement agreement with the pool
    contractor does not differentiate the settled damages, arriving at the
    conclusion proffered by Buyers still requires a degree of speculation—the
    court would have to assume that any damages caused by the pool
    13
    subcontractor were to the pool. But, what if the pool contractor caused
    damage to the surrounding landscaping features during their work on the
    pool? What if during settlement talks Buyers claimed that they should be
    reimbursed for their loss of use of the pool while it was being repaired?
    Buyers sued the subcontractors, Sellers, and Addison for a wide range of
    damages and as a result, paver damage, landscaping lighting damage, and
    loss of use were all elements of compensation awarded against Addison
    and Sellers. Without differentiation in the settlement agreement, there is
    simply no way to know if there was any overlap.
    Further exemplifying the need for allocation of damages in a settlement
    agreement to prevent duplicate recovery are Buyers’ settlements with the
    stucco, cast-stone, and the painting and caulking subcontractors. Buyers
    claim that they did not introduce any evidence of settled damages caused
    by these subcontractors, but as the court outlined in its final omnibus
    order, Buyers’ evidence showed that “the construction elements that may
    (or in specific instances may not) have contributed to the water intrusion
    include, but are not necessarily limited to, improper or no waterproofing,
    painting, calking, stucco, and cast stone installation.”           Without
    differentiation, it seems more than likely that the settlement agreements
    with stucco, cast-stone, and painting and caulking subcontractors (just as
    an example) encompassed damages awarded against Addison and Sellers
    under the Purchase Agreement, Addendum, and Warranty.
    In sum, because the subcontractor settlement agreements failed to
    differentiate the damages settled for, it is simply “impossible to know
    whether [Buyers] would be receiving a duplicate payment” for their breach
    of contract based claims. Cornerstone, 163 So. 3d at 569−70. If Buyers
    wanted to prevent this problem, they should have allocated the damages
    encompassed in each subcontractor settlement. Buyers made a strategic
    and understandable decision not to do so, and this is the end result. We
    acknowledge that this may seem harsh, but it is the only pragmatic result.
    If courts were required to delve into the scope of undifferentiated
    settlement agreements for the purposes of making a setoff determination,
    then post-judgment proceedings would turn into a second trial. Principles
    of judicial economy prohibit this result. Accordingly, under the direction
    of Cornerstone, the trial court was required to offset the breach of contract
    damages awarded against Addison and Sellers by the total amount of the
    subcontractor settlements. Id.
    Conclusion
    Although this was an extremely complicated and lengthy case, the
    record, especially the trial court’s many orders, reflect that the court spent
    14
    a great deal of time considering and carefully analyzing each of the issues
    raised on appeal and, in doing so, ensured that the parties had a fair trial
    based on the evidence. Under the circumstances, we affirm in all respects.
    Affirmed.
    WARNER and MAY, JJ., concur.
    *         *         *
    Not final until disposition of timely filed motion for rehearing.
    15