Jax Utilities Management, Inc. v. Hancock Bank, A Foreign Corp. ( 2015 )


Menu:
  •                                        IN THE DISTRICT COURT OF APPEAL
    FIRST DISTRICT, STATE OF FLORIDA
    JAX UTILITIES
    MANAGEMENT, INC.,
    Appellant,                       CASE NO. 1D14-664
    v.
    HANCOCK BANK, A FOREIGN
    CORPORATION, and
    PLUMMER CREEK, LLC, A
    FLORIDA CORPORATION,
    Appellees.
    _____________________________/
    Opinion filed June 11, 2015.
    An appeal from the Circuit Court for Duval County.
    Waddell A. Wallace, Judge.
    Diane G. Cassaro, Jacksonville; David S. Wainer, III of Ford, Miller & Wainer,
    P.A., Jacksonville, for Appellant.
    Matthew J. Conigliaro of Carlton Fields Jorden Burt, P.A., Tampa, and Jason A.
    Perkins of Carlton Fields Jorden Burt, P.A., Orlando, for Hancock Bank, a Foreign
    Corporation; Lawrence J. Hamilton, II and Barbara Cocciola of Holland & Knight,
    LLP, Jacksonville, for Plummer Creek, LLC, a Florida Corporation.
    ON MOTION FOR REHEARING OR CLARIFICATION
    LEWIS, C. J.
    We deny Appellant’s Motion for Rehearing or Clarification, but we
    withdraw our previously issued opinion and substitute this opinion in its place.
    Appellant, Jax Utilities Management, Inc. (“Jax”), challenges the trial
    court’s entry of a final summary judgment in favor of Appellee, Hancock Bank,
    arguing that the trial court erred by holding that (1) the statute of limitations set
    forth in section 95.11(5)(b), Florida Statutes (2011), barred Jax’s equitable lien
    claim, and (2) section 713.3471, Florida Statutes (2011), precluded Jax’s common
    law claims of equitable lien and unjust enrichment. For the reasons that follow, we
    affirm.
    BACKGROUND
    On December 29, 2011, Jax brought an action against Appellees based on a
    failed housing development project. In an Amended Complaint, Jax asserted a
    breach of contract claim against Plummer Creek, LLC, (Count I) and equitable lien
    and unjust enrichment claims against Hancock Bank (Counts II and III,
    respectively).   Hancock Bank moved for summary judgment based upon its
    affirmative defenses that section 95.11(5)(b), Florida Statutes, barred Jax’s
    equitable lien claim and section 713.3471, Florida Statutes, precluded both of Jax’s
    common law claims.
    The parties’ summary judgment evidence established in part the following:
    In December 2005, Plummer Creek, as owner, and Jax, as contractor, entered into
    a Standard Form Agreement for the development of the project, which entailed the
    2
    construction of “429 builder lots and amenities.”    In January 2006, Plummer
    Creek, as borrower, and Peoples First Community Bank (“Peoples First”), as
    lender, entered into a Loan Agreement to fund the development.        The Loan
    Agreement was for the principal amount of $15,975,000 and was to be evinced by
    a Note and used “to finance the purchase of land . . . and to construct
    improvements thereon for the engineering, planning and development of 429 single
    family building lots and other improvements that will comprise Plummer Creek
    Subdivision, together with such other improvements necessary or desirable to
    service the Project.” Under the Loan Agreement, Plummer Creek was required to
    make scheduled payments to Peoples First and to submit pay requests. Plummer
    Creek’s failure to make a scheduled payment, a material adverse change in
    Plummer Creek’s financial condition, or any one of the other enumerated events
    constituted a default under the Loan Agreement.       Between 2006 and 2009,
    Plummer Creek performed its obligations under the Loan Agreement.
    On May 28, 2009, however, Plummer Creek’s sole source capital, Stokes
    Land Group, was informed by its investors that they would no longer fund the
    project. On June 1, 2009, Stokes Land Group informed Peoples First that it was no
    longer able to provide capital and make payments on the loan in light of its
    investors’ decision. As such, in June 2009, Peoples First notified Plummer Creek
    3
    that it would cease making further advances under the Loan Agreement. On June
    27, 2009, Plummer Creek missed an interest payment. Although on June 30, 2009,
    Jax submitted two pay applications to Plummer Creek, in the amounts of
    $11,922.98 and $468,680.10, Plummer Creek failed to pay them and failed to
    submit them to Peoples First. In December 2009, pursuant to a Purchase and
    Assumption Agreement with the Federal Deposit Insurance Corporation as receiver
    of Peoples First, Hancock Bank assumed Peoples First’s assets and liabilities,
    including the Note, Mortgage, and Loan Documents relating to the subject
    property. On March 21, 2011, Hancock Bank initiated foreclosure proceedings
    against the project. In September 2011, Hancock Bank obtained a Final Judgment
    of Foreclosure against Plummer Creek in the amount of $18,884,800.38; and in
    January 2012, a Certificate of Sale and Certificate of Title were filed. Based upon
    evidence relating to Construction Acceptance Checklists, Jax claimed that its last
    day on the job was June 20, 2009, while Hancock Bank claimed it was May 14,
    2010. 1
    The trial court entered a Final Summary Judgment in favor of Hancock
    Bank. The trial court concluded that Jax’s equitable lien claim was barred by the
    1
    During the course of the proceedings, the trial court entered a Consent for Final
    Judgment in favor of Jax against Plummer Creek in the amount of $476,523.08 in
    principal, plus interest and costs for a total of $587,737.70, which shall bear
    interest.
    4
    one-year statute of limitations set forth in section 95.11(5)(b), Florida Statutes,
    regardless of which party’s position about Jax’s last day on the job was correct. In
    doing so, the trial court rejected Jax’s argument that the statute of limitations did
    not begin to run until the equitable lien claim accrued upon the initiation of the
    foreclosure proceeding. The trial court further concluded that Jax’s equitable lien
    and unjust enrichment claims were precluded by section 713.3471, Florida
    Statutes, and reasoned that the Legislature clearly intended to alter the common
    law and that the statute is so repugnant to Jax’s common law claims that they
    cannot coexist. This appeal followed.
    ANALYSIS
    Summary judgment is proper only when there is no genuine issue of material
    fact and the moving party is entitled to a judgment as a matter of law. Haynes v.
    Universal Prop. & Cas. Ins. Co., 
    120 So. 3d 651
    , 653 (Fla. 1st DCA 2013). An
    order granting a motion for summary judgment is reviewed de novo. 
    Id.
     Similarly,
    a trial court’s interpretation of a statute is reviewed de novo. M.D.C. v. B.N.M.J.,
    
    117 So. 3d 489
    , 490 (Fla. 1st DCA 2013).
    5
    Construction of Section 95.11(5)(b)
    Jax first argues that the statute of limitations set forth in section 95.11(5)(b),
    Florida Statutes, began to run not from the last furnishing of labor, services, or
    material, but from the initiation of the foreclosure proceeding. We disagree.
    “Except as provided in subsection (2) [fraud and products liability] and in s.
    95.051 [tolling] and elsewhere in these statutes, the time within which an action
    shall be begun under any statute of limitations runs from the time the cause of
    action accrues.” § 95.031, Fla. Stat. (2011). “A cause of action accrues when the
    last element constituting the cause of action occurs.” § 95.031(1), Fla. Stat. “An
    action to enforce an equitable lien arising from the furnishing of labor, services, or
    material for the improvement of real property” must be commenced within one
    year. § 95.11(5)(b), Fla. Stat. (2011).
    By its plain language, section 95.11(5)(b) requires that a claim for equitable
    lien be brought within one year of the last furnishing of labor, services, or material
    for the improvement of real property. Roehner v. Atl. Coast Dev. Corp., 
    356 So. 2d 1296
    , 1297 (Fla. 4th DCA 1978) (“This is an appeal from a denial of a motion
    to dismiss a complaint to enforce an equitable lien, said complaint filed in excess
    of one year after the last furnishing of labor, services or material. We reverse upon
    the authority of s 95.11(5)(b) (Fla.Stat.1975) which unequivocally requires such a
    6
    suit to be filed within one year after the last furnishing of labor, services or
    material for the improvement of real property.”); see also Westburne Supply, Inc.
    v. Cmty. Villas Partners, Ltd., 
    508 So. 2d 431
    , 434-35 (Fla. 1st DCA 1987)
    (finding that the one-year statute of limitations on the appellant’s equitable lien
    claim began running on the day the last materials were supplied for the
    construction of an apartment complex, and noting that “an equitable lien arises at
    the time of the transaction from which it springs”); Haney v. Holmes, 
    364 So. 2d 81
    , 82 (Fla. 2d DCA 1978) (explaining that if section 95.11(5)(b) were the
    applicable provision, it would have barred the appellant’s claim for foreclosure of
    an equitable lien where the complaint alleged that the last work on the real
    property was performed on or about February 27, 1975, and the complaint was
    filed on September 3, 1976).
    Here, Jax claims that its last day on the job was June 20, 2009, while
    Hancock Bank claims it was May 14, 2010. In either case, section 95.11(5)(b)’s
    one-year statute of limitations, which runs from the last furnishing of labor,
    services, or material for the improvement of real property, had long expired by the
    time Jax initially filed its complaint in December 2011. Therefore, the trial court
    correctly determined that regardless of whether Jax’s last day of work on the
    project was on June 20, 2009, as Jax argued, or on May 14, 2010, as Hancock
    7
    Bank contended, Jax filed its December 29, 2011, lawsuit too late as it did not
    bring suit within the one-year period provided by section 95.11(5)(b). As such,
    like the trial court, we reject Jax’s argument that the statute of limitations period
    ran from when Hancock Bank initiated foreclosure proceedings.
    Construction of Section 713.3471
    Turning now to Jax’s second argument, Jax contends that the trial court
    misapplied section 713.3471, Florida Statutes, to preclude common law relief
    under the facts of this case. Hancock Bank, on the other hand, argues that the trial
    court correctly applied section 713.3471 to preclude Jax’s common law claims of
    equitable lien and unjust enrichment because the statute expressly precludes such
    claims and is so repugnant to the existence of common law remedies that the two
    cannot coexist. However, both parties agree that this is an issue of first impression
    for a Florida appellate court. For the reasons that follow, we agree with Hancock
    Bank.
    Section 713.3471, Florida Statutes (2011), was enacted in 1992, is part of
    the Construction Lien Law, and is titled “Lender responsibilities with construction
    loans.” Section 713.3471(2) defines a lender’s responsibilities to a contractor for
    construction work where the lender decides to stop making advances prior to the
    8
    distribution of all the construction loan funds.       Subsection (2)(a) sets forth a
    lender’s duties and provides for no liability if those duties are satisfied:
    (2)(a) Within 5 business days after a lender makes a final
    determination, prior to the distribution of all funds available under a
    construction loan, that the lender will cease further advances pursuant
    to the loan, the lender shall serve written notice of that decision on the
    contractor and on any other lienor who has given the lender notice.
    The lender shall not be liable to the contractor based upon the decision
    of the lender to cease further advances if the lender gives the
    contractor notice of such decision in accordance with this subsection
    and the decision is otherwise permitted under the loan documents.
    § 713.3471(2)(a), Fla. Stat. Subsections (2)(b) and (2)(c) define a lender’s liability
    where it fails to provide the requisite notice:
    (b) The failure to give notice to the contractor under paragraph (a)
    renders the lender liable to the contractor to the extent of the actual
    value of the materials and direct labor costs furnished by the
    contractor plus 15 percent for overhead, profit, and all other costs
    from the date on which notice of the lender’s decision should have
    been served on the contractor and the date on which notice of the
    lender’s decision is served on the contractor. The lender and the
    contractor may agree in writing to any other reasonable method for
    determining the value of the labor, services, and materials furnished
    by the contractor.
    (c) The liability of the lender shall in no event be greater than the
    amount of undisbursed funds at the time the notice should have been
    given unless the failure to give notice was done for the purpose of
    defrauding the contractor. The lender is not liable to the contractor for
    consequential or punitive damages for failure to give timely notice
    under this subsection. The contractor shall have a separate cause of
    action against the lender for damages sustained as the result of the
    lender’s failure to give timely notice under this subsection. Such
    separate cause of action may not be used to hinder or delay any
    9
    foreclosure action filed by the lender, may not be the basis of any
    claim for an equitable lien or for equitable subordination of the
    mortgage lien, and may not be asserted as an offset or a defense in the
    foreclosure case.
    § 713.3471(2)(b)-(c), Fla. Stat.
    To discern legislative intent, courts first look to the plain language of a
    statute, whereby “[t]he plain and ordinary meaning of the words of a statute must
    control.”   Marrero v. State, 
    71 So. 3d 881
    , 886-87 (Fla. 2011).               Section
    713.3471(2) governs construction loan lenders who, prior to the distribution of all
    funds available under a loan, make a final determination that they will cease
    further advances. Such lenders must give timely notice to the contractor and any
    other lienor who has given the lender notice. If the lender complies with this
    notification duty (and its decision is permitted under the loan documents), it has no
    liability to the contractor or lienor. § 713.3471(2)(a), Fla. Stat.
    If the lender fails to comply with this notification duty, it is liable to the
    contractor through a statutory cause of action, but the damages are calculated as
    prescribed by the statute, unless the noncompliance was intended to defraud the
    contractor. § 713.3471(2)(b)-(c), Fla. Stat. Furthermore, where the lender fails to
    comply with the notice requirement, the statutory claim may not interfere with any
    foreclosure action and “may not be the basis of any claim for an equitable lien or
    for equitable subordination of the mortgage lien . . . .” § 713.3471(2)(c), Fla. Stat.
    10
    In effect, section 713.3471(2) provides benefits and burdens to lenders and
    contractors. Prior to the statute’s enactment in 1992, case law prohibited lenders
    from misleading contractors about advances, but did not impose an obligation to
    notify contractors of a decision to cease making advances. See Giffen Indus. of
    Jacksonville, Inc. v. Se. Assocs., Inc., 
    357 So. 2d 217
     (Fla. 1st DCA 1978); J. G.
    Plumbing Serv., Inc. v. Coastal Mortg. Co., 
    329 So. 2d 393
     (Fla. 2d DCA 1976).
    Section 713.3471(2) changed the common law by imposing on lenders an
    affirmative duty to notify, thereby protecting contractors from continuing work on
    projects without notice that further funds will not be advanced. See Whitehead v.
    Tyndall Federal Credit Union, 
    46 So. 3d 1033
    , 1035-36 (Fla. 1st DCA 2010) (“The
    obvious purpose of [section 713.3471(2)] is to prevent exactly what occurred here:
    the unjust termination of payments to a contractor who continues work, without
    any notice from the lender that payments will be terminated.”).           Section
    713.3471(2) constitutes comprehensive regulation in this narrow area.
    While courts generally presume that the common law remains in effect when
    a statute is enacted in derogation of the common law, this presumption is
    inapplicable where the statute expressly says otherwise or “is so repugnant to the
    common law that the two cannot coexist.” Major League Baseball v. Morsani, 
    790 So. 2d 1071
    , 1077-78 (Fla. 2001).        Section 713.3471 does both.      Section
    11
    713.3471(2) expressly immunizes lenders who provide notice, prescribes the
    damages where notice is not provided, and states that the cause of action cannot
    become the basis for an equitable lien claim. Moreover, a common law claim
    would conflict with the statute. If a lender complies with the statute, it has no
    liability.   If the lender fails to comply, a contractor may seek damages as
    prescribed by the statute.
    Notably, section 713.3471 lacks a provision expressly preserving common
    law remedies. The Legislature routinely includes such provisions where it does not
    intend to displace the common law, and the omission of such a provision reinforces
    the conclusion that section 713.3471 displaces the common law remedies. See,
    e.g., § 83.808(1), Fla. Stat. (2012) (“Nothing in ss. 83.801-83.809 shall be
    construed as in any manner impairing or affecting the right of parties to create liens
    by special contract or agreement nor shall it in any manner impair or affect any
    other lien arising at common law . . . .”); § 403.191(1), Fla. Stat. (2011) (“Nothing
    contained herein shall be construed to abridge or alter rights of action or remedies
    in equity under the common law . . . .”); § 403.760(5)(e), Fla. Stat. (2011)
    (“Nothing in this section shall affect or modify in any way the obligations or
    liability of any person under any other provisions of state or federal law, including
    common law . . . .”); § 494.002, Fla. Stat. (2011) (“Sections 494.001-494.0077 do
    12
    not limit any statutory or common-law right of any person to bring any action in
    any court for any act involved in the mortgage loan business or the right of the
    state to punish any person for any violation of any law.”); § 517.241(2), Fla. Stat.
    (2011) (“Nothing in this chapter limits any statutory or common-law right of a
    person to bring an action in a court for an act involved in the sale of securities or
    investments, or the right of the state to punish any person for a violation of a
    law.”); § 607.0833, Fla. Stat. (2011) (“Nothing in this section shall be deemed to
    deny, limit, or restrict the powers of guaranty or warranty of any corporation at
    common law or under any statute.”).
    Here, Peoples First was a construction loan lender that decided to cease
    further advances before all the loan funds had been distributed. Though the record
    does not indicate that Peoples First ever served notice on Jax pursuant to section
    713.3471(2), Jax elected not to bring a statutory claim and instead sued Hancock
    Bank (as successor-in-interest to Peoples First) for equitable lien and unjust
    enrichment. However, we find that section 713.3471(2) precluded Jax’s common
    law claims and the trial court properly entered summary judgment in Hancock
    Bank’s favor on this issue because the plain language of section 713.3471(2)
    evinces a legislative intent to displace the common law remedies and the statute is
    so repugnant to common law remedies that the two cannot coexist.
    13
    CONCLUSION
    Accordingly, the trial court correctly held that the statute of limitations set
    forth in section 95.11(5)(b), Florida Statutes, barred Jax’s equitable lien claim and
    section 713.3471, Florida Statutes, precluded Jax’s common law claims of
    equitable lien and unjust enrichment.
    Therefore, we AFFIRM the trial court’s Final Summary Judgment.
    MARSTILLER and OSTERHAUS, JJ., CONCUR.
    14