DePrince v. Starboard Cruise Services, Inc. ( 2015 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed April 08, 2015.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D14-1570
    Lower Tribunal No. 13-16523
    ________________
    Thomas DePrince,
    Appellant,
    vs.
    Starboard Cruise Services, Inc.,
    Appellee.
    An Appeal from the Circuit Court for Miami-Dade County, Darrin P.
    Gayles, Judge.
    Cohen Ruiz P.A., and Mario M. Ruiz, for appellant.
    Isicoff, Ragatz & Koenigsberg, and Eric D. Isicoff and Carolina A. Latour,
    for appellee.
    Before ROTHENBERG, LAGOA, and FERNANDEZ, JJ.
    ROTHENBERG, J.
    Thomas DePrince (“DePrince”) appeals the trial court’s order granting
    summary judgment in favor of Starboard Cruise Services, Inc. (“Starboard”) on
    DePrince’s claims against Starboard for breach of contract, specific performance,
    and conversion. Because we find that disputed issues of material fact remain to be
    resolved on all three counts of DePrince’s complaint, we reverse and remand for
    further proceedings.
    Historical Hollywood starlet Mae West once said, “I never worry about
    diets. The only carrots that interest me are the number of carats in a diamond.”
    Thus, it appears quite likely that Ms. West would have been interested in the
    diamond in this case: a twenty carat diamond that Starboard offered to DePrince
    for a very low sum. As it turns out, the “too good to be true” price of the diamond
    was just that, and the price conveyed to DePrince was a mistake. Now DePrince
    wants his twenty carat diamond; Starboard wants out of its sales contract; and
    Starboard’s supplier, who allegedly misquoted the price of the diamond upon
    which Starboard and DePrince relied, has not even been added as a party to the
    lawsuit. In short, this is truly a gem of a case.
    FACTUAL BACKGROUND
    DePrince embarked on a cruise from Miami in February 2013. During that
    cruise, DePrince visited an onboard jewelry shop that is wholly owned and
    operated by Starboard. When DePrince expressed some interest in a large loose
    2
    diamond1 and specified to the sales manager of the store, Mihai Rusan (“Rusan”),
    that the stone should be between 15 and 20 carats, Rusan, who had never dealt
    with a diamond of such magnitude, sent an email inquiry to Starboard’s corporate
    office in Miami (“the Miami Office”).
    Starboard maintains a consignment agreement with a supplier, Sophia Fiori
    (“Fiori”),2 that allows Starboard to obtain gemstones and jewelry for sale in its
    onboard stores.      The consignment agreement between Starboard and Fiori
    specifies, in relevant part:
    3. Title to the Consigned Merchandise shall at all times remain with
    Consignor until the time of its sale to customers of Consignee,
    whereupon the Consigned Merchandise shall be deemed to have been
    purchased from Consignor by Consignee.[3]
    Upon receiving the email inquiry from Rusan, the Miami Office relayed the
    information to Fiori to determine whether Fiori could fill such an order should
    DePrince decide to purchase a diamond. Fiori responded to the Miami Office via
    email, informing Starboard that there were two diamonds of that size available.
    Fiori’s email described the diamonds precisely as follows:
    1. EMERALD CUT 20.64 carats D VVS2 GIA VG Price $235,000
    1 A “loose diamond” refers only to the gemstone itself, rather than a gemstone that
    is a component of a larger piece of jewelry.
    2 Fiori is the business name for the corporation Elba Jewelry, Inc. DePrince refers
    to the supplier of the diamond as Elba Jewelry throughout his brief, but we will
    refer to it as “Fiori” in this opinion.
    3 “Consigned Merchandise” refers to the jewelry items ordered by Starboard; the
    “Consignor” refers to Fiori; and the “Consignee” refers to Starboard.
    3
    2. EMERALD CUT 20.73 carats E VVS2 GIA EX EX FNT Price $245,000
    The Miami Office relayed this information to Rusan via email exactly as Fiori had
    typed it. Rusan notified DePrince of the availability of the size of the diamond he
    was interested in purchasing and the pricing information contained in the email,
    telling him that the purchase prices for the diamonds were $235,000 and $245,000
    respectively.
    DePrince told Rusan that he was interested, but that he would like to take
    some time to think about the purchase. That night, DePrince spoke with his life
    partner, Vernon Crawford, a certified gemologist who was on the cruise with
    DePrince, and also DePrince’s sister, Carolyn DePrince, who holds the highest
    available degree in gemology.        Both advised DePrince against making the
    purchase, telling him that the sale price was too good to be true and that the price
    for a diamond that large should be at least $2 million.
    DePrince, however, ignored their advice and opted to complete the
    transaction. DePrince returned to Starboard’s onboard jewelry store and placed a
    special mail purchase order for the 20.64 carat diamond the next day. Rusan
    prepared and signed a one-page sales agreement that listed the total price for the
    diamond at $235,000 plus a $25 shipping charge. DePrince made an initial down
    payment of $125,000 on the spot and paid the balance ($110,025) the next day.
    The parties agreed to have the diamond shipped to the Gemological Institute of
    4
    America laboratory in New York so that a neutral gemologist could verify that the
    diamond that was shipped was the same one specified in the sales agreement.
    Soon after the sale was completed, Starboard learned that Fiori’s $235,000
    price quote in the email was the per carat price for the diamond rather than the
    total price for the diamond ($4,850,400), and thus, Starboard had inadvertently
    contracted to sell the diamond to DePrince for less than 1/20th of the diamond’s
    actual value.    Five days after the sales agreement was executed, Starboard
    contacted DePrince via telephone to explain the situation, stating that the price on
    the sales agreement was “seriously in error” due to the mix-up in the email.
    Starboard offered discounted future cruise rates to DePrince to compensate him for
    the inconvenience, but DePrince demanded that the sale be completed as specified
    in the sales agreement. Starboard unilaterally reversed the charges on DePrince’s
    credit card to refund him all the money he had paid and then repudiated the sales
    agreement, informing DePrince that it would not be shipping the diamond as they
    had originally agreed. These communications were memorialized in an email
    Starboard sent to DePrince after the phone call. The record does not disclose how
    Starboard dealt with the cancellation of the sale with regard to Fiori.
    Thereafter, DePrince filed a complaint against Starboard alleging counts for
    specific performance, breach of contract, and conversion. Starboard answered and
    pleaded the affirmative defense of unilateral mistake, among others, claiming that
    5
    Rusan had misquoted DePrince the total price of the diamond rather than the per
    carat price and that DePrince had known about the error the whole time due to his
    extensive experience with jewelry.           Starboard also counterclaimed for a
    declaratory judgment that the sales agreement was unenforceable and for rescission
    of the contract.
    Starboard moved for summary judgment on the ground that there had clearly
    been a unilateral mistake in the pricing, and, after hearing argument on that issue,
    the trial court granted summary judgment against DePrince on all his claims.
    Specifically, the trial court ruled at the summary judgment hearing:
    I don’t find that the plaintiff has established that there were any
    actionable damages and I don’t find that there was a valid and
    enforceable contract for either the breach of contract or the conversion
    count. Particularly as to conversion, I don’t find that the plaintiff or
    the defendant ever – there’s no record evidence that the plaintiff
    possessed the diamond, as opposed to remaining in the possession of
    the vendor. I find, quite frankly, that it may be unconscionable to
    enforce this particular contract.
    This appeal followed.
    ANALYSIS
    “[A] party moving for summary judgment must show conclusively the
    absence of any genuine issue of material fact and the court must draw every
    possible inference in favor of the party against whom a summary judgment is
    sought.” Moore v. Morris, 
    475 So. 2d 666
    , 668 (Fla. 1985). Summary judgment is
    only appropriate when an examination of the facts in the light most favorable to the
    6
    non-movant demonstrates that the movant is entitled to judgment as a matter of
    law. Fla. R. Civ. P. 1.510(c); Volusia Cnty. v. Aberdeen at Ormond Beach, L.P.,
    
    760 So. 2d 126
    , 130 (Fla. 2000).
    The trial court granted summary judgment against DePrince on his breach of
    contract action due to its finding that there had been a unilateral mistake of fact
    sufficient to rescind the otherwise-enforceable contract, enforcement of the
    contract would be “unconscionable,” and DePrince had not alleged any actionable
    damages. On DePrince’s claim for specific performance, the trial court found that
    the diamond was not unique and was therefore not the proper subject of the remedy
    of specific performance. And as to DePrince’s conversion claim, the trial court
    granted summary judgment in Starboard’s favor based on its finding that Starboard
    never had possession of the diamond.
    We do not agree with the trial court that there are no genuine issues of
    material fact such that Starboard is entitled to judgment as a matter of law on any
    of these claims. Thus, Starboard was not entitled to summary judgment.
    I.    Contract Formation and Enforcement
    On appeal, Starboard has raised two defenses to the sales agreement’s
    formation and enforcement. First and primarily, Starboard claims that a unilateral
    mistake of law prevents the contract from being formed.         Second, Starboard
    summarily raised an unconscionability defense in its briefing and then pressed that
    7
    point more extensively at oral argument. For the reasons that follow, neither of
    these arguments entitle Starboard to summary judgment on DePrince’s breach of
    contract claim. Moreover, the trial court seemed to make a sua sponte finding that
    DePrince had not alleged any actionable damages to support his breach of contract
    claim. That ruling was also in error. We explain each of these theories at length
    because there appears to be a great deal of misunderstanding in each of these areas.
    A. Unilateral Mistake
    There are three potentially viable tests to determine whether a contract may
    be rescinded based on a unilateral mistake of fact: (1) A four-prong test requiring
    the highest burden of proof for the party seeking to avoid the contract; (2) a two-
    prong test requiring the lowest burden of proof for the party seeking to avoid the
    contract; and (3) a 3-prong disjunctive test that provides several more-flexible
    methods of establishing a unilateral mistake.
    This Court’s most recent decisions on this topic clearly articulated and
    reaffirmed the viability of the four-prong test to establish a unilateral mistake,
    Rachid v. Perez, 
    26 So. 3d 70
    , 72 (Fla. 3d DCA 2010), and this panel—along with
    the trial court—is of course bound by that decision, see State v. Washington, 
    114 So. 3d 182
    , 188-89 (Fla. 3d DCA 2012) (“This panel is not free to disregard, or
    recede from, [a prior decision from this Court]; only this Court, sitting en banc,
    may recede from an earlier opinion.”). However, it matters not which test is
    8
    applied at this stage of the proceedings because we find that the trial court’s
    summary judgment order cannot be upheld due to a unilateral mistake of fact under
    any of these three formulations. Thus, the trial court’s order granting summary
    judgment cannot be upheld based on a unilateral mistake of fact. We analyze each
    of these three tests in turn to clarify what appears to be a confusing area of the law
    with inconsistent application among Florida’s district courts of appeal.
    1. This Court’s Four-Prong Test for Unilateral Mistakes of Fact
    This Court has held that in order to rescind an otherwise-valid contract4
    based on a unilateral mistake, the party seeking to avoid the contract must show:
    (1) [T]he mistake was induced by the party seeking to benefit from the
    mistake, (2) there is no negligence or want of due care on the part of
    the party seeking a return to the status quo, (3) denial of release from
    the agreement would be inequitable, and (4) the position of the
    opposing party has not so changed that granting the relief would be
    unjust.
    Rachid, 
    26 So. 3d at 72
     (quoting Lechuga v. Flanigan’s Enters., Inc., 
    533 So. 2d 856
    , 857 (Fla. 3d DCA 1988)); Ali R. Ghahramani, M.D., P.A. v. Pablo A.
    Guzman, M.D., P.A., 
    768 So. 2d 535
    , 537 n.1 (Fla. 4th DCA 2000). Examining
    the facts as alleged and supported by DePrince, Starboard did not conclusively
    demonstrate either of the first two prongs of this analysis.5
    4 Starboard pled several other affirmative defenses to the sales agreement,
    however, only a unilateral mistake and unconscionability have been raised on
    appeal. For purposes of this analysis, we assume without deciding that the sales
    agreement is valid and enforceable in all other respects.
    5 DePrince has not argued on appeal that the third or fourth prong has not been
    9
    First, Starboard presented no evidence that DePrince induced it into making
    the pricing mistake. The primary focus of Starboard’s argument, both at the
    summary judgment hearing and in its brief, was that DePrince must have known of
    the mistake in pricing due to his background as a former antiques and jewelry
    dealer and the advice he received from his gemologist partner and his sister.
    DePrince, however, denied that he knew there had been a pricing mistake in his
    affidavit, which is sufficient at the summary judgment phase of the proceedings to
    create a genuine issue of material fact. More importantly, we note that even if
    DePrince had known that the price he was quoted to purchase the diamond was in
    error, knowledge of an error is markedly different than inducement of that error.
    See, e.g., Gemini Investors III, L.P. v. Nunez, 
    78 So. 3d 94
    , 97 (Fla. 3d DCA
    2012) (explaining that fraudulent inducement requires that the party seeking to
    enforce the contract “(1) made a statement concerning a material fact, (2) knowing
    that the statement was false, (3) with intent that the [mistaken party] act on the
    false statement; and (4) the [mistaken party was] damaged as a result of [its]
    reasonable reliance on the false statement”).6 Because Starboard presented no
    satisfied. He seems to agree that the transaction appears inequitable and that he
    has not changed his position in reliance on the purchase.
    6 We do not hold that the burden to establish inducement for purposes of the first
    prong of a unilateral mistake defense is the same as proving the elements for a
    fraudulent inducement defense, but merely use fraudulent inducement by way of
    example to demonstrate that inducement requires some type of action, not mere
    knowledge. In fact, the burden of proof cannot be the same because such a
    requirement would render the unilateral mistake of fact defense completely
    10
    evidence that the pricing mistake was induced by DePrince, the trial court clearly
    erred by granting summary judgment in Starboard’s favor under the four-prong
    test.
    Second, there is a factual dispute regarding the second prong of the
    unilateral mistake standard: that the party seeking to avoid the contract (Starboard)
    was not inexcusably negligent or failed to act with due care. DePrince avers in
    both his complaint and affidavit that Starboard did not act with due care when it
    sold him the diamond. Starboard claims it simply provided DePrince with the
    quote provided to it by Fiori, and that it did not act negligently. Thus, whether
    Starboard made a reasonable and understandable mistake or acted negligently in its
    handling of the sale is a disputed issue of fact, and, because questions involving
    reasonableness and negligence determinations are highly factual inquiries upon
    which reasonable people could disagree, they are rarely appropriately resolved on
    summary judgment. Spadafora v. Carlo, 
    569 So. 2d 1329
    , 1331 (Fla. 2d DCA
    1990). This case is no exception.
    2. The Two-Prong Test for Unilateral Mistakes of Fact
    obsolete by requiring a party seeking to avoid a contract on that basis to prove
    fraudulent inducement, which is itself sufficient to render a contract voidable by
    the aggrieved party. Mazzoni Farms, Inc. v. E.I. DuPont De Nemours & Co., 
    761 So. 2d 306
    , 313 (Fla. 2000) (“It is axiomatic that fraudulent inducement renders a
    contract voidable . . . .”).
    11
    Although we have determined that Starboard has not satisfied its burden of
    meeting the four-prong test adopted by this Court to set aside a contract for
    unilateral mistake for purposes of summary judgment, Starboard contends that the
    two-prong test for pleading and proving a unilateral mistake is the test that should
    be applied.    Starboard’s argument is not wholly without merit, and in fact,
    numerous Florida cases have relied on the two-prong standard. Most recently, in
    Garvin v. Tidwell, the Fourth District Court of Appeal stated “that a trial court may
    rescind an agreement based on unilateral mistake if ‘(1) the mistake did not result
    from an inexcusable lack of due care, and (2) defendant’s position did not so
    change in reliance that it would be unconscionable to set aside the agreement.’”
    
    126 So. 3d 1224
    , 1228 (Fla. 4th DCA 2012) (quoting Stamato v. Stamato, 
    818 So. 2d 662
    , 664 (Fla. 4th DCA 2002)); see also Fla. Ins. Guar. Ass’n v. Love, 
    732 So. 2d 456
    , 457 (Fla. 2d DCA 1999) (applying the same two-prong test); U.S. Alliance
    Corp. v. Tobon, 
    715 So. 2d 1122
    , 1123 (Fla. 3d DCA 1998) (same); BMW of N.
    Am., Inc. v. Krathen, 
    471 So. 2d 585
    , 588 (Fla. 4th DCA 1985) (same).
    The two elements in the two-prong test are in substance nearly identical to
    two of the four prongs relied upon by this Court. Indeed, the four-prong test
    largely restates the two-prong test and adds the elements that “the mistake was
    induced by the party seeking to benefit from the mistake [and] . . . denial of release
    from the agreement would be inequitable.” Rachid, 
    26 So. 3d at 72
     (quoting
    12
    Lechuga, 
    533 So. 2d at 857
    ). Interestingly, both the courts espousing the four-
    prong test and the courts applying the two-prong test all seem to rely on the
    Florida Supreme Court’s decision in Maryland Casualty Co. v. Krasnek, 
    174 So. 2d 541
     (Fla. 1965), to support their variant formulations of the standard. Compare
    Lechuga, 
    533 So. 2d at
    857 (citing Krasnek after articulating a four-prong test for
    unilateral mistake) with Krathen, 
    471 So. 2d at
    588 (citing Krasnek to support its
    two-prong test). Although Krasnek clearly states the two-prong test, the additional
    prongs of the four-prong test can be inferred from the opinion as well. Krasnek,
    
    174 So. 2d at 543-44
    .
    Most importantly in this case, however, is the fact that both the two- and the
    four-prong tests require that the party seeking to invoke a unilateral mistake of fact
    as an affirmative defense establish that he was not unduly negligent in forming the
    contract.   As explained above, a genuine question of fact remains regarding
    whether Starboard was negligent in this case, thereby precluding summary
    judgment under the two-prong standard as well.
    3. Florida’s Jury Instruction for Unilateral Mistakes of Fact
    Lastly, although neither party initially argued for the application of the third
    test to establish unilateral mistake, Florida’s new jury instruction, which was
    adopted in June 2013, In re Standard Jury Instructions—Contract and Bus. Cases,
    13
    
    116 So. 3d 284
    , 324 (Fla. 2013), pertaining to unilateral mistake states the test in
    yet another substantially different way:
    To establish [the defense of unilateral mistake], (defendant)
    must prove all of the following:
    1. (Defendant) was mistaken about (insert description of
    mistake) at the time the parties made the contract;
    2. [The effect of the mistake is such that enforcement of the
    contract would be unconscionable]
    [or]
    [ (Claimant) had reason to know of the mistake or
    [he][she][it] caused the mistake.]
    and
    3. (Defendant) did not bear the risk of mistake. A party
    bears the risk of a mistake when
    [the parties’ agreement assigned the risk to [him][her][it]]
    [or]
    [[he][she][it] was aware, at the time the contract was made,
    that [he][she] [it] had only limited knowledge about the facts
    relating to the mistake but decided to proceed with the contract].
    Fla. Std. Jury Instr. (Civ.) 416.26 (first alteration added).
    This instruction is nearly identical to the formulation of the unilateral
    mistake defense found in the Restatement (Second) of Contracts. See Restatement
    (Second) of Contracts §§ 153, 154 (1979). However, this particular three-prong
    test has not been adopted or cited by any Florida decision to date. “Standard jury
    instructions are not binding precedent,” although they can be quite persuasive and
    instructive “[i]n the absence of a definitive case.” BellSouth Telecomm., Inc. v.
    Meeks, 
    863 So. 2d 287
    , 292 (Fla. 2003). In this instance, however, because there
    are definitive cases in this jurisdiction, we are bound by those cases. And in those
    14
    cases, this Court clearly applied the four-prong test. See Rachid, 
    26 So. 3d at 72
    ;
    Lechuga, 
    533 So. 2d at 857
    .
    Even if jury instruction 416.26 was the law in Florida, Starboard should not
    have prevailed on its summary judgment motion. That is because even if DePrince
    had been aware of the mistake and enforcement of the contract would be
    unconscionable—either or both of which would satisfy the second prong of the
    analysis—the third prong requires that the party seeking to assert the unilateral
    mistake defense show that it did not bear the risk of the mistake. Fla. Std. Jury
    Instr. (Civ.) 416.26. A party can be found to bear the risk of its mistake if the
    contract expressly assigns that risk to the party or if that party is aware at the time
    of the contract’s formation that it had only limited knowledge about the facts
    relating to the mistake but decided to proceed with the contract anyway. The
    contract in this case does not assign the risk to either party, and factual questions
    certainly remain as to whether Starboard should have known at the time it formed
    the contract that it had insufficient information to facilitate such an expensive
    transaction. Indeed, Rusan himself stated in his deposition that he had never dealt
    with a diamond this large.      Because this factual question remains, summary
    judgment would also have been inappropriate under the new jury instruction.
    To reiterate our position on unilateral mistakes of fact, this Court currently
    adheres to the four-prong test as stated in Rachid and Lechuga. There are at least
    15
    two other tests—the two-prong test found primarily in other districts’ case law and
    the three-prong test found in standard jury instruction 416.26—in Florida
    jurisprudence. The existence of three different tests has caused a great deal of
    confusion in the case law and to litigants and trial courts. However, under any of
    these three tests, Starboard should not have prevailed on summary judgment based
    on its unilateral mistake of fact defense.
    B. Unconscionability as an element of Unilateral Mistake
    Starboard also contends on appeal, and the trial court seemed to find, that
    the contract was unenforceable because the agreement was unconscionable. The
    independent affirmative defense of unconscionability requires that the party
    seeking to avoid enforcement of the contract prove both procedural and substantive
    unconscionability. Kohl v. Bay Colony Club Condo., Inc., 
    398 So. 2d 865
    , 867
    (Fla. 4th DCA 1981). The procedural aspect of an unconscionability defense
    focuses on the parties to the contract and the circumstances surrounding the
    formation of the contract. In essence, procedural unconscionability requires proof
    that one party had such an extreme advantage with respect to bargaining power,
    experience, or some other important characteristic that the other party to the
    contract was not given a “meaningful choice” to refuse the contract terms. 
    Id. at 868
     (quoting Bennett v. Behring Corp., 
    466 F. Supp. 689
    , 696 (S.D. Fla. 1979)).
    Before finding that a contract is a product of procedural unconscionability, the
    16
    court must examine all the details surrounding the formation of the contract—an
    incredibly factually intensive inquiry.        Gainesville Health Care Ctr., Inc. v.
    Weston, 
    857 So. 2d 278
    , 284 (Fla. 1st DCA 2003).
    Conversely, the substantive aspect of an unconscionability defense focuses
    on the terms of the contract itself.      To find that a contract is substantively
    unconscionable, a court must find that the terms are “so outrageously unfair as to
    shock the judicial conscience.” 
    Id. at 285
     (quotation marks omitted). Resolving an
    unconscionability defense obviously requires a great deal of fact-finding regarding
    many aspects of the contract formation process; it should not be the subject of a
    trial court’s gut feeling or whim, and it is rarely appropriately determined on
    summary judgment.
    In this case, Starboard never asserted a full-fledged unconscionability
    defense in its motion for summary judgment.7 Rather, Starboard seems to assert
    “unconscionability” as an element or factor—it is unclear which—in establishing
    its unilateral mistake defense.     The only portions of Starboard’s summary
    judgment motion and answer brief that discuss unconscionability cite Florida
    Cranes, Inc. v. Florida East Coast Properties, Inc. for the proposition that “equity
    can correct a unilateral mistake where said mistake is committed by an employee
    of the appellant, and constitutes a simple but honest mistake which could lead to an
    7 Starboard did assert unconscionability as an affirmative defense in its answer, and
    it is certainly entitled to litigate that defense on remand if it so chooses.
    17
    unconscionable result.” 
    324 So. 2d 721
    , 722 (Fla. 3d DCA 1976). The use of the
    word “unconscionable” in the Florida Cranes decision is not in reference to the
    independent unconscionability defense explained above, however, but is merely a
    portion of the unilateral mistake analysis. Indeed, the word “unconscionable” is
    also used in the Florida Supreme Court’s decision in Krasnek, but only to explain
    that a trial court cannot grant relief based on a unilateral mistake if the party
    seeking to enforce the contract has changed its position in reliance on the contract.
    
    174 So. 2d at 543
     (holding that a trial court cannot order rescission based on
    unilateral mistake unless “the respondent’s position had not been so changed in
    reliance on the contract that it would be unconscionable to order rescission”
    (emphasis added)).
    To the extent that Starboard relies on unconscionability as an independent
    affirmative defense to the contract—not as part of the unilateral mistake analysis—
    that defense was not properly before the trial court on summary judgment, and the
    trial court did not and could not make the requisite findings to warrant rescission
    on that basis. Indeed, the word “unconscionable,” or any variation thereof, only
    appears one time in the hearing transcript—when the trial court found that it would
    be unconscionable to enforce the contract. And to the extent that Starboard relies
    on “unconscionability” as a way to establish its unilateral mistake defense, the
    “unconscionability” it has demonstrated is merely a necessary component to the
    18
    four-prong (or two-prong) test to establish a unilateral mistake of fact, not a
    sufficient basis for relief in and of itself. Thus, the trial court erred in granting
    relief based on “unconscionability.”
    C. Damages
    Finally, the trial court found that DePrince had not alleged any actionable
    damages as a result of the breach of contract. The trial court’s ruling on this point
    reflects a fundamental misunderstanding of the nature of contractual damages. It is
    well-established in Florida, and in virtually every state, that the measure of a
    buyer’s damages for a breach of contract when the seller refuses to deliver a
    product as agreed can include the difference between the market price of that
    product and the price of the product as specified in the repudiated contract. §
    672.713, Fla. Stat. (2013); A & P Bakery Supply & Equip. Co. v. Hawatmeh, 
    388 So. 2d 1071
    , 1072 (Fla. 3d DCA 1980); U.C.C. § 2-713 (2002); see also Buschman
    v. Clark, 
    583 So. 2d 799
    , 799 (Fla. 1st DCA 1991) (applying the same rule to real
    estate).   This damage calculation serves to vindicate the buyer’s expectation
    interest by placing him in the same position in which he would have been had the
    contract been executed as agreed.
    The trial court’s finding appears to be based on the notion that DePrince had
    not taken any action or incurred any additional expenses in reliance on the sales
    agreement, and thus, DePrince would have incurred no damages whatsoever had
    19
    the contract never been made. However, this is only one method of calculating a
    plaintiff’s damages for breach of contract.8     As explained in the Restatement
    (Second) of Contracts § 344 (1981), there are three remedies a plaintiff may elect
    to vindicate his rights for a breach of contract depending on the circumstances:
    (a) his “expectation interest,” which is his interest in having the benefit of
    his bargain by being put in as good a position as he would have been in had the
    contract been performed,
    (b) his “reliance interest,” which is his interest in being reimbursed for loss
    caused by reliance on the contract by being put in as good a position as he would
    have been in had the contract not been made, or
    (c) his “restitution interest,” which is his interest in having restored to him
    any benefit that he has conferred on the other party.
    A plaintiff that has alleged any of these types of damages has alleged
    actionable damages under the law. Here, DePrince clearly seeks to vindicate his
    expectation interest in the contract by recovering the difference between the
    market value of the contract and the price he agreed to pay—an amount that likely
    exceeds $2 million according to all the testimony below. Thus, the trial court erred
    in finding that DePrince had not alleged “actionable damages” and accordingly
    erred in granting summary judgment on that basis.
    II.   Specific Performance
    DePrince pled specific performance as a wholly separate cause of action
    from his breach of contract claim. Specific performance is an equitable remedy
    8This detrimental reliance is also one of the elements to rescind a contract based
    on unilateral mistake as explained above.
    20
    that may be invoked in a breach of contract action under certain circumstances.
    See Rybovich Boat Works, Inc. v. Atkins, 
    585 So. 2d 270
    , 272 (Fla. 1991) (“[T]he
    remedy of specific performance is not a matter of right.” (emphasis added));
    Linkous v. Linkous, 
    941 So. 2d 530
    , 530 (Fla. 1st DCA 2006) (“Specific
    performance is an appropriate remedy only when there is no adequate remedy at
    law.” (emphasis added)); Frank Silvestri, Inc. v. Hilltop Devs., Inc., 
    418 So. 2d 1201
    , 1203 (Fla. 5th DCA 1982) (explaining that in a breach of contract for the
    sale of real property, the seller can elect either the remedy of specific performance
    or retain the property and sue for damages for breach of contract). “It is a well-
    established legal principle that a court of equity will grant specific performance of
    a contract involving personal property when the property is of a unique character
    and value, such as an antique, and there is no adequate remedy at law.” Mangus v.
    Porter, 
    276 So. 2d 250
    , 251 n.1 (Fla. 3d DCA 1973) (citing Graham v. Herlong, 
    39 So. 111
    , 111 (Fla. 1905)); see also § 672.716(1), Fla. Stat. (2013) (“Specific
    performance may be decreed where the goods are unique or in other proper
    circumstances.”).
    The trial court granted summary judgment in Starboard’s favor on
    DePrince’s claim for specific performance based on its determination that the
    diamond at issue is not unique. This ruling, however, is in conflict with the facts
    DePrince alleged and averred in his action. In fact, the only evidence submitted on
    21
    this issue was an affidavit submitted by DePrince’s expert gemologist averring that
    the gem was unique based on a variety of characteristics and a specific laser
    number assigned only to that gem. Thus, whether the diamond in this case is
    unique is a factual issue not properly resolved on summary judgment.
    III.   The Conversion Action
    DePrince’s conversion action—unlike his breach of contract and specific
    performance actions—is a claim sounding in tort rather than in contract. Ginsberg
    v. Lennar Fla. Holdings, Inc., 
    645 So. 2d 490
    , 495 (Fla. 3d DCA 1994).9
    The essence of the tort of conversion is the exercise of wrongful
    dominion or control over property to the detriment of the rights of the
    actual owner. Thus, conversion may occur where a person wrongfully
    refuses to relinquish property to which another has the right of
    possession. The tort may be established despite evidence that the
    defendant took or retained property based upon the mistaken belief
    that he had a right to possession, since malice is not an essential
    element of the action.
    Seymour v. Adams, 
    638 So. 2d 1044
    , 1046-47 (Fla. 5th DCA 1994) (citations
    omitted). An essential element of any conversion claim is that the defendant must
    have taken possession of the item the plaintiff has the right to possess.
    The trial court made a factual finding that Starboard never had possession of
    the diamond, and therefore, DePrince had not established a necessary element of
    his conversion claim. DePrince, however, maintained that Starboard did in fact
    9 Whether DePrince’s conversion claim is properly brought when it overlaps with
    the contract claims is not before us, and we therefore offer no opinion on that issue.
    22
    have possession of the diamond by way of its consignment agreement with Fiori.
    The relevant portion of the consignment agreement states: “Title to the [diamond]
    shall at all times remain with [Fiori] until the time of its sale to customers of
    [Starboard], whereupon the [diamond] shall be deemed to have been purchased
    from [Fiori] by [Starboard].”      No evidence was introduced other than the
    consignment agreement, and thus, there is no evidence in the record to refute
    Starboard’s constructive possession of the diamond.        Summary judgment in
    Starboard’s favor was therefore improperly granted.
    CONCLUSION
    The trial court erred by granting summary judgment on all three of
    DePrince’s claims. There remain genuine issues of material fact to be resolved,
    and Starboard has not demonstrated that it is entitled to judgment as a matter of
    law.
    We also note that, for some inexplicable reason, Fiori has not been made a
    party to this suit. It is difficult to imagine how DePrince’s and Starboard’s rights
    and obligations can be completely established and redressed without Fiori’s
    involvement, particularly if specific performance is found to be a proper remedy.
    Importantly, both parties in their briefs have at times suggested that Fiori is the
    party who was actually negligent by way of its price quote, which omitted a “per
    carat” designation. Fiori can undoubtedly shed light on who, if anyone, should
    23
    shoulder the blame of the price mistake, as well as explain industry standards and
    its pattern of dealings with Starboard.
    We therefore conclude that while some may claim that diamonds are
    forever, the same cannot be said of the trial court’s summary judgment order.
    Reversed and remanded.
    24