Westchester Fire Ins. Co. v. Kesoki Painting , 260 So. 3d 546 ( 2018 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed December 19, 2018.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D16-2523
    Lower Tribunal No. 15-13914
    ________________
    Westchester Fire Insurance Company, LLC,
    Appellant,
    vs.
    Kesoki Painting LLC,
    Appellee.
    An appeal from the Circuit Court for Miami-Dade County, Barbara Areces,
    Judge.
    Eaton & Wolk, PL, and Douglas F. Eaton, for appellant.
    Taylor Espino Vega & Touron, P.A., and Daniel R. Vega and Vanessa A.
    Van Cleaf, for appellee.
    Before SUAREZ, FERNANDEZ, and LUCK, JJ.
    SUAREZ, J.
    Appellant Westchester Fire Insurance Company, LLC (Lee Construction
    Group, Inc.’s surety) appeals from a final judgment, following a jury trial, entered
    in favor of Kesoki Painting, LLC. Because we find that Westchester was not
    entitled to a directed verdict, we affirm.
    BACKGROUND
    This case involves a dispute as to the scope of work required under a
    Subcontract Agreement (the “Agreement”). In March 2014, Lee Construction
    Group, Inc., the Contractor, entered into the Agreement with Kesoki, the
    Subcontractor, to perform painting and waterproofing work for the Miami-Dade
    County Overtown Transit Village. The dispute arises from the work required to
    waterproof windows. Specifically, the work involved cutting window gaskets1 and
    applying a sealant to prevent leaks between the window glass and the frame.
    The controlling specifications did not include instructions to cut the gaskets
    at an angle. However, the County determined that instead of trimming the gaskets
    level with the frame before applying the sealant, it wanted the gaskets cut at a 45
    degree angle. Luis Enriquez, Lee’s president, requested a written directive from
    the project manager after explaining that cutting the gaskets at a 45 degree angle
    deviated from the specifications and would be more time consuming and costly.2
    1 A gasket is a rubber seal inside the perimeter of the window frame that holds the
    glass in place.
    2 Enriquez was also concerned that cutting the gaskets at a 45 degree angle would
    impede the windows’ structural integrity: “Cutting [the gaskets] level I have no
    problem doing so because it is listed in the scope of work and if the glazing starts
    getting loose on those windows in the future than [sic] at least I am covered
    because it was on the scope to do so. The way it's being requested to do so now
    leaves me exposed . . . . The pressures at 22 stories are much higher and at the end
    of the day this will fall on me if I proceed without having this in writing if some
    2
    Based on written instructions from the County, Enriquez directed Kesoki to cut the
    gaskets at 45 degrees. Enriquez acknowledged that complying with the County’s
    instructions to cut the gaskets at an angle as opposed to flush was “a bit more
    work” but suggested that Kesoki wait to submit a change order because the
    additional cost could perhaps be offset by using a less expensive sealant.
    Ultimately, the less expensive sealant was not used, and the anticipated
    savings never materialized. Consequently, Kesoki submitted a change order to
    Enriquez in the amount of $104,599.40 for the extra work associated with cutting
    the gaskets at a 45 degree angle. Enriquez asked Kesoki to reduce the amount,
    which Kesoki did, submitting a reduced change order in the amount of $95,169.40.
    Enriquez signed the revised change order, added an additional fifteen percent
    contractor markup, and submitted it to the County.        The County rejected the
    gasket-cutting change order “for the reason that it is within the scope of the
    construction documents[.]”
    Following the County’s rejection of its change order, Kesoki filed suit
    against Westchester, Lee’s surety, alleging that Kesoki was entitled to recover for
    the extra gasket-cutting work. After the lawsuit was filed, Charles Nyarko, the
    project architect, rejected the change order in writing, finding that the gasket-
    cutting work was a requirement under the Agreement’s specifications.3 The case
    type of failing happens on these windows down the road.”
    3 During cross-examination, however, Nyarko was asked why the specifications
    did not state that the gaskets were to be cut at 45 degrees. He answered, “I didn’t
    3
    proceeded to a jury trial, and the jury returned a $91,904.00 verdict in favor of
    Kesoki.   Westchester sought judgment in accordance with a previously filed
    motion for directed verdict, arguing that (1) Nyarko, the project architect, had the
    final say as to scope of work disputes, and (2) Kesoki could only modify the
    Agreement with respect to the gasket-cutting work with a signed writing from both
    Lee and Kesoki. The trial court denied Westchester’s motion and entered final
    judgment in favor of Kesoki. Westchester timely appealed.
    ANALYSIS
    We review the denial of Westchester’s motion for directed verdict de novo;
    however, we view all record evidence and every inference based on that evidence
    in a light most favorable to Kesoki, the non-moving party. See Maggolc, Inc. v.
    Roberson, 
    116 So. 3d 556
    , 558 (Fla. 3d DCA 2013). We also review the trial
    court’s interpretation of the Agreement de novo. Sunhouse Const., Inc. v. Amwest
    Sur. Ins. Co., 
    841 So. 2d 496
    , 498 (Fla. 3d DCA 2003).
    Westchester first argues that it was entitled to a directed verdict because the
    Agreement gives the project architect the final say over disputes that arise between
    Lee and Kesoki regarding the scope of work, and the project architect determined
    that the 45 degree cut was required by the specifications. The relevant dispute-
    resolution provision provides as follows:
    intend it to be cut at 45 degrees. That’s why it wasn’t written.”
    4
    2.5 If a dispute arises between the Contractor and the
    Subcontractor regarding the Scope of Work, or in the
    interpretation of the Contract Documents, and the parties
    hereto do not promptly resolve that dispute, the decision
    of the [Architect] shall be final.
    We agree that this provision would require the parties to be bound by the
    project architect’s determination as to the required scope of work in the event of a
    dispute between Lee, the Contractor, and Kesoki, the Subcontractor. See James A.
    Cummings, Inc. v. Young, 
    589 So. 2d 950
    , 954 (Fla. 3d DCA 1991) (“When
    parties to a contract agree by its express terms to be bound to the determination
    made by an architect, that agreement is binding upon the parties.”). But we reject
    Westchester’s argument because unlike in Cummings, where “[s]everal disputes
    arose” between the general contractor and subcontractor, the evidence in this case,
    viewed in a light most favorable to Kesoki, establishes that there was no dispute
    between Lee and Kesoki regarding the scope of the gasket-cutting work.
    Before the work started, Lee’s president, Enriquez, repeatedly acknowledged
    that cutting the gaskets at a 45 degree angle would be more work. Enriquez
    explained to the project manager that the work was outside of the specifications
    and would be more time consuming and costly. Further, he suggested that Kesoki
    hold off on submitting a change order in case the cost of the extra work could be
    offset by other savings. After the work had been completed, Enriquez accepted
    and signed Kesoki’s revised change order. At trial, Enriquez testified that when he
    submitted the change order, both he and Kesoki believed that the gasket-cutting
    5
    work was extra work. Based on our review of the record, we conclude that there
    was simply no dispute between Lee and Kesoki, so there was nothing for the
    architect to resolve.
    Westchester also argues that it was entitled to a directed verdict because
    Kesoki failed to establish that it modified the Agreement. Westchester relies on
    the following provision:
    15.2 This Agreement represents the entire agreement and
    understanding between Contractor and Sub Contractor
    and supersedes all prior negotiations, representations or
    agreements, either oral or written. This Agreement may
    be amended only by an instrument in writing signed by
    Contractor and Sub Contractor.
    We reject this argument because the Agreement also contains a provision that
    allows Lee to make additions to the Work without invalidating the Agreement:
    10.7 CHANGES IN THE WORK The Contractor may
    direct the Subcontractor, in writing, without invalidating
    this Agreement, to make revisions, modifications and
    additions to the Work. The Contract Sum and the
    Contract Time would be adjusted accordingly. The
    Subcontractor, prior to the commencement of such
    added, changed or revised Work, shall submit promptly
    to the Contractor written copies of any claim for
    adjustment to the Contract Sum and Contract Time for
    such revised Work in a manner consistent with this
    Agreement and the Contract Documents.
    Here, Lee did what the Agreement provided for by directing Kesoki, in writing, to
    undertake the additional work of cutting the gaskets at a 45 degree angle. No
    6
    modification of the Agreement was necessary because the Agreement itself already
    allowed Lee to make such changes to the work.4
    Because we find that there was no dispute between Lee and Kesoki for the
    architect to resolve regarding the scope of work and the Agreement allowed Lee to
    make additions to the work, we conclude that Westchester was not entitled to a
    directed verdict, and we affirm the decision below.5
    Affirmed.
    ANY POST-OPINION MOTION MUST BE FILED WITHIN SEVEN
    DAYS. A RESPONSE TO THE POST-OPINION MOTION MAY BE
    FILED WITHIN FIVE DAYS THEREAFTER.
    4 Moreover, the next section, 10.8, provides a means through which Kesoki could
    submit a claim for additional cost.
    5 Although the Agreement’s “pay after paid” clause was briefly mentioned during
    oral argument, neither party raised any arguments with respect to this clause in
    their briefs. We therefore decline to address any issues concerning the clause here.
    7
    

Document Info

Docket Number: 16-2523

Citation Numbers: 260 So. 3d 546

Filed Date: 12/19/2018

Precedential Status: Precedential

Modified Date: 12/19/2018