All Courts |
Federal Courts |
US Federal District Court Cases |
District Court of Appeal of Florida |
2018-12 |
-
LOGUE, J. The damages sought by P & S Paving, Inc. did not arise from the termination of the subcontract agreement. Accordingly, the remedy sought by P & S was not barred by the termination provision in the subcontract agreement. See *309Bernecker v. Bernecker,
60 So.2d 399 , 406 (Fla. 1952) (Concluding that the law had been erroneously applied where it was determined that "the termination of the contract, even with proper notice, terminated rights already accrued under it at the time of such termination."); Chicago Title Ins. Co. v. Title Consultants, Inc.,472 So.2d 1380 , 1381 (Fla. 2d DCA 1985) ("The termination of a contract in pursuance of a provision therein, even with proper notice, does not terminate the rights already accrued under it at the time of such termination.") (citation omitted). We affirm on all other points.Affirmed.
ANY POST-OPINION MOTION MUST BE FILED WITHIN SEVEN DAYS. A RESPONSE TO THE POST-OPINION MOTION MAY BE FILED WITHIN FIVE DAYS THEREAFTER.
Document Info
Docket Number: No. 3D17-1310
Citation Numbers: 259 So. 3d 308
Judges: Lagoa, Logue, Suarez
Filed Date: 12/5/2018
Precedential Status: Precedential
Modified Date: 10/18/2024