STEPHEN HESS v. PMG-S2 SUNNY ISLES, LLC ( 2022 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed November 10, 2022.
    ________________
    No. 3D20-630
    Lower Tribunal No. 18-37446
    ________________
    Stephen Hess, et al.,
    Appellants,
    vs.
    PMG-S2 Sunny Isles, LLC,
    Appellee.
    An Appeal from the Circuit Court for Miami-Dade County, William
    Thomas, Judge.
    Quintana Law Firm, and J. Luis Quintana; Schlesinger Law Group, and
    Michael J. Schlesinger; Shutts & Bowen LLP, and Julissa Rodriguez, for
    appellants.
    Kluger, Kaplan, Silverman, Katzen & Levine, P.L., Josh M. Rubens and
    Philippe Lieberman; Samson Appellate Law, and Daniel M. Samson, for
    appellee.
    Before FERNANDEZ, C.J., and SCALES and GORDO, JJ.
    GORDO, J.
    ON MOTION FOR REHEARING
    We deny PMG-S2 Sunny Isles, LLC’s motion for clarification, rehearing
    and rehearing en banc, but withdraw our previous opinion, and substitute the
    following opinion in its stead.
    INTRODUCTION
    Stephen Hess, Clearwater Beach Company, LLC, Muse 1901, LLC,
    Muse 2101, LLC and Muse 2201, LLC appeal a final judgment in favor of
    PMG-S2 Sunny Isles, LLC.          We have jurisdiction. Fla. R. App. P.
    9.030(c)(1)(A). We affirm the trial court’s order awarding summary judgment
    in PMG’s favor in all regards. We find, however, the trial court erred in not
    allowing the Muse entities to amend their pleadings regarding calculation of
    the return of the deposits and therefore remand with instructions to allow
    amendment.
    FACTUAL AND PROCEDURAL BACKGROUND
    In 2014, Stephen Hess visited Muse, a condominium located in Miami-
    Dade being developed by PMG, where he reviewed promotional materials
    and floor plans for prospective units. Hess, and his company Clearwater,
    subsequently entered into purchase agreements with PMG for the purchase
    and sale of three pre-construction condominium units at Muse. Hess paid
    PMG $6.1 million in deposits for the units.
    2
    The terms of the agreements barred assignment and amendment
    without the consent of PMG and a signed written instrument.             Per the
    agreements, if Hess and Clearwater defaulted, PMG was entitled to
    terminate the agreements and apply a specific damages clause to calculate
    PMG’s damages. Four subsequent amendments to the agreements were
    made, and three were sent to Hess and Clearwater. In the first, PMG agreed
    Hess could assign its interest in the agreements to an affiliated domestic
    corporate entity. The second detailed modifications regarding an institutional
    mortgagee. The third only affected future purchasers and was not sent to
    Hess or Clearwater and the fourth detailed changes to the property
    management agreement and reflected the unit’s final square footage.
    Neither Hess nor Clearwater sent any written notice to rescind the
    agreements due to these amendments.
    In May 2018, Hess and Clearwater assigned their “rights, title, interests
    and obligations” under the agreements to Muse 1901, Muse 2101 and Muse
    2201 (the “Muse entities”). 1 Notice of the assignments were sent to PMG.
    Closing was scheduled for May 31, 2018, but the Muse entities failed to
    timely close. In late June, PMG furnished the Muse entities with formal
    written notice of default and terminated the agreements.
    1
    All three Muse entities are wholly owned by Hess.
    3
    In November 2018, Hess and Clearwater filed a complaint against
    PMG for recission pursuant to sections 718.202 and 718.506, Florida
    Statutes, breach of contract and declaratory judgment challenging the
    enforceability of the default damages clause in the agreements. Following a
    motion by PMG, the trial court dismissed the declaratory judgment action
    without prejudice as the issue was not ripe because the units had not been
    resold. 2 Hess and Clearwater then filed an amended complaint, including
    the Muse entities as co-plaintiffs and reasserting the claims for recission and
    breach of contract only. After initial discovery was conducted, both Hess and
    PMG filed motions for summary judgment.
    2
    In granting the motion to dismiss the trial court stated:
    THE COURT: What about the fact that it’s
    premature? We’re not even there yet. And why
    should I, in this instance, give you an advisory
    opinion of how I think it should go assuming that
    you’re not fully compensated pursuant to the
    contract?
    ...
    Why don’t we make that determination if we
    determine that there is a breach? In other words, we
    can litigate the case based upon the other three
    allegations in the complaint. If the Court finds that
    there is a breach, then we can litigate the issue of
    whether or not when the breach occurred and
    what damages you are entitled to.
    (emphasis added).
    4
    In March 2020, rather than proceeding to trial, the trial court heard
    argument in support of the cross-motions and granted PMG’s motion for
    summary judgment finding Hess and Clearwater lacked standing and the
    remaining claims were unsupported.          Hess and the Muse entities
    subsequently filed a motion for reconsideration of the entry of summary
    judgment and requested to amend their complaint to reassert their previous
    claim regarding the calculation of the deposits because they learned the
    issue had recently ripened as PMG resold at least one of the units. The trial
    court subsequently denied the motion for rehearing and motion to amend,
    entering final judgment in PMG’s favor. This appeal followed.
    LEGAL ANALYSIS
    We review the entry of summary judgment de novo. See Volusia Cnty.
    v. Aberdeen at Ormand Beach, L.P., 
    760 So. 2d 126
    , 130 (Fla. 2000).3 We
    review for abuse of discretion a trial court’s denial of leave to amend a
    pleading. See Jain v. Buchanan Ingersoll & Rooney PC, 
    322 So. 3d 1201
    ,
    1204 (Fla. 3d DCA 2021), reh’g denied (July 27, 2021). We affirm without
    further discussion the trial court’s ruling that PMG was properly entitled to
    3
    “Where the trial court has adjudicated the summary judgment motion prior
    to the new rule’s May 1, 2021, effective date (as the trial court did in this
    case), we apply the pre-amendment rule in our review on appeal.” De Los
    Angeles v. Winn-Dixie Stores, Inc., 
    326 So. 3d 811
    , 813 (Fla. 3d DCA 2021).
    5
    summary judgment as a matter of law on the issues raised. We reverse,
    however, as the Muse entities should have been allowed to amend their
    pleadings.
    Florida Rule of Civil Procedure 1.190(a) requires courts to allow
    amendment of pleadings which “shall be given freely when justice so
    requires.” This Court has considered some exceptions to this rule, such as
    abuse of the privilege to amend, futility of the proposed amendment and
    prejudice to the opposing party. See Grove Isle Ass’n, Inc. v. Grove Isle
    Assocs., LLLP, 
    137 So. 3d 1081
    , 1090 (Fla. 3d DCA 2014) (“A trial court
    should give leave to amend a deficient complaint unless . . . the complaint
    shows on its face that there is a deficiency which cannot be cured by
    amendment.” (quoting Unitech Corp. v. Atl. Nat’l Bank of Miami, 
    472 So. 2d 817
    , 818 (Fla. 3d DCA 1985))); Annex Indus. Park, LLC v. City of Hialeah,
    
    218 So. 3d 452
    , 453 (Fla. 3d DCA 2017) (“‘Leave to amend should not be
    denied unless the privilege has been abused or the complaint is clearly not
    amendable.’” (quoting Osborne v. Delta Maint. and Welding, Inc., 
    365 So. 2d 425
    , 427 (Fla. 2d DCA 1978))); Carib Ocean Shipping, Inc. v. Armas, 
    854 So. 2d 234
    , 236 (Fla. 3d DCA 2003) (noting “amendments may be denied
    when there is a sufficient showing of prejudice to the opposing party”); Vella
    v. Salaues, 
    290 So. 3d 946
    , 949 (Fla. 3d DCA 2019) (“‘[W]hile the policy in
    6
    Florida is to liberally allow amendments to pleadings where justice so
    requires, a trial judge in the exercise of sound discretion may deny further
    amendments [where the same materially varies from the relief initially
    sought, or] where a case has progressed to a point that the liberality
    ordinarily to be indulged has diminished.’” (quoting Alvarez v. DeAguirre, 
    395 So. 2d 213
    , 216 (Fla. 3d DCA 1981))).
    Importantly, in Jain we found the trial court did not abuse its discretion
    in denying a plaintiff’s motion to amend her pleadings after summary
    judgment was entered in the defendant’s favor where the plaintiff conceded
    “in her brief that she only sought leave to amend because she saw the
    ‘handwriting on the wall’” and the “proposed amendment would advance new
    issues that contradict her prior unsuccessful theories.” Jain, 322 So. 3d at
    1206. This Court determined “[a] party who opposes summary judgment will
    not be permitted to alter the position of his or her previous pleadings,
    admissions, affidavits, depositions or testimony in order to defeat a summary
    judgment.” Id.
    Here, the Muse entities moved to amend their pleadings after the entry
    of summary judgment, but the purpose of their amendment was not to
    advance a new issue or otherwise undermine the trial court’s summary
    judgment liability determination. Rather, the amendment sought to have the
    7
    deposits distributed consistent with the terms of the default provision
    following the trial court’s determination the purchase agreements were not
    rescinded. The Muse entities’ motion to amend was consistent with the trial
    court’s position at the hearing on the motion to dismiss, which stated that
    entitlement to the deposits should be litigated after the issue of breach was
    determined. 4
    Under the specific facts of this case, where an initial complaint seeking
    a judicial determination of the disposition of the deposits was filed, the trial
    court dismissed the count as premature as the application of the default
    provisions were uncertain and events transpired during the pendency of the
    action adding Hess’s wholly owned Muse entities as parties and rendering
    the default provisions ripe for enforcement, we conclude it was error not to
    allow amendment by the Muse entities.
    Affirmed in part, reversed in part, and remanded with instructions.
    4
    We note at oral argument Counsel for PMG contended all $6.1 million of
    Hess’s deposits were necessarily forfeited because any arguments
    regarding their return would be barred under the doctrine of res judicata. We
    express no opinion as to this res judicata argument as it was not before us
    and to do so would be advisory. The interests of justice, however, are
    necessarily implicated here where a party argued all terms of a purchase
    agreement are enforceable, but now seeks to evade the impact of some
    provisions and obtain a windfall. Given that “any doubts should be resolved
    in favor of the amendment,” the Muse entities should have been granted
    leave to amend their complaint. Overnight Success Const., Inc. v. Pavarini
    Const. Co., Inc., 
    955 So. 2d 658
    , 659 (Fla. 3d DCA 2007).
    8