RAYMOND ERB v. CHUBB NATIONAL INSURANCE COMPANY, etc. ( 2022 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed December 14, 2022.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D20-1694
    Lower Tribunal No. 18-31014
    ________________
    Raymond Erb,
    Appellant,
    vs.
    Chubb National Insurance Company, etc.,
    Appellee.
    An Appeal from a non-final order from the Circuit Court for Miami-Dade
    County, Mark Blumstein, Judge.
    Perry & Neblett, P.A., and David Avellar Neblett, James M. Mahaffey,
    III and John A. Wynn, for appellant.
    Brown Sims, P.C., and Marlin K. Green and Cody L. Frank, for
    appellee.
    Before EMAS, GORDO and BOKOR, JJ.
    BOKOR, J.
    Raymond Erb appeals a final order compelling arbitration with his
    insurer pursuant to an arbitration clause contained in the insurance contract.
    He alleges that the trial court erred by enforcing the arbitration provision
    despite the insurer failing to timely demand arbitration within the time
    specified by contract. Because requiring arbitration in this context conflicts
    with the intent of the parties, as expressed through the plain language of the
    agreement, we reverse. 1
    Generally, a party may demand arbitration where: (1) a valid written
    agreement to arbitrate exists, (2) an arbitrable issue exists, and (3) the right
    to arbitration has not been waived. Jackson v. Shakespeare Found., Inc.,
    
    108 So. 3d 587
    , 593 (Fla. 2013). As the former two factors are not in dispute
    on this appeal, we address only Erb’s argument that the insurer waived its
    right to arbitrate by failing to timely invoke the arbitration provision.
    The agreement here provides that “[t]he request for arbitration must
    be filed within one (1) year of the date of loss or damage.” (emphasis added).
    Chubb concedes that it did not request arbitration within one year of the
    underlying accident.      However, Chubb also argues that because the
    1
    We review de novo an order interpreting a contract provision. See, e.g.,
    Castro v. Mercantil Commercebank, N.A., 
    305 So. 3d 623
    , 625 (Fla. 3d DCA
    2020); see also Grove Isle Ass'n, Inc. v. Grove Isle Assocs., LLLP, 
    137 So. 3d 1081
    , 1089 (Fla. 3d DCA 2014) (reviewing motion to dismiss under de
    novo standard of review).
    2
    agreement provides that “[a]ny controversy or claim . . . arising out of or
    related to this policy . . . shall be referred to and settled by arbitration,” the
    agreement does not expressly allow any form of dispute resolution other than
    arbitration, so Chubb’s failure to comply with the time limitation had no
    impact on arbitrability.
    In Abel Homes at Naranja Villas, LLC v. Hernandez, 
    960 So. 2d 891
    (Fla. 3d DCA 2007), this court evaluated an arbitration provision allowing the
    developer, Abel Homes, to elect arbitration within 20 days of receiving notice
    of a claim, but providing that a purchaser could then proceed with other legal
    processes if the developer did not elect to arbitrate. 
    Id. at 893
    . Under that
    contractual provision, we held that “the Developer waived its right to
    arbitration by failing to timely serve a demand for arbitration within the
    twenty-day time limit specified in the Agreements.” 
    Id. at 894
    .
    Because arbitration provisions are contractual in nature and governed
    by principles of contract interpretation, “the determination of whether an
    arbitration clause requires arbitration of a particular dispute necessarily rests
    on the intent of the parties,” and “[a] natural corollary of this rule is that no
    party may be forced to submit a dispute to arbitration that the party did not
    intend and agree to arbitrate.” Seifert v. U.S. Home Corp., 
    750 So. 2d 633
    ,
    636 (Fla. 1999) (quotations and citations omitted). The intent of the parties
    3
    to a contract is primarily discerned from the plain meaning of the contractual
    language, considered in context. See, e.g., Gulliver Schs., Inc. v. Snay, 
    137 So. 3d 1045
    , 1047 (Fla. 3d DCA 2014). “Where contractual provisions are
    clear and unambiguous, the court must give those terms their plain and
    ordinary meaning.”     Abel Homes, 
    960 So. 2d at 894
    .            Further, when
    construing a contract with two possibly conflicting provisions, we endeavor
    to reconcile the provisions and give a “reasonable, lawful and effective
    meaning” to all terms. See Nabbie v. Orlando Outlet Owner, LLC, 
    237 So. 3d 463
    , 466 (Fla. 5th DCA 2018) (internal quotations and citations omitted);
    see also City of Homestead v. Johnson, 
    760 So. 2d 80
    , 84 (Fla. 2000) (“[W]e
    rely upon the rule of construction requiring courts to read provisions of a
    contract harmoniously in order to give effect to all portions thereof.”).
    Here, the trial court’s interpretation fails to harmonize the two
    sentences of the same contractual provision. The better reading, indeed,
    the only reading that gives effect to both relevant portions, requires
    arbitration of any conflict between the parties, but only if invoked by the
    insurer within one year from the date of loss. Accordingly, based on the
    failure to invoke arbitration within such time as required by contract, the trial
    court erred in compelling arbitration.
    Reversed.
    4