Smalley v. Duke Energy Florida, Inc. , 2014 Fla. App. LEXIS 20925 ( 2014 )


Menu:
  •                NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING
    MOTION AND, IF FILED, DETERMINED
    IN THE DISTRICT COURT OF APPEAL
    OF FLORIDA
    SECOND DISTRICT
    JEANNETTE M. SMALLEY, LOREN           )
    LEE WIELAND, STACEE PELTZ, and        )
    KYLE PELTZ, for themselves and on     )
    behalf of a class of all others similarly
    )
    situated,                             )
    )
    Appellants,             )
    )
    v.                                    )              Case No.   2D13-4746
    )
    DUKE ENERGY FLORIDA, INC., a          )
    Florida corporation, formerly FLORIDA )
    POWER CORP., d/b/a PROGRESSIVE )
    ENERGY FLORIDA, INC., and             )
    FLORIDA POWER & LIGHT CO.,            )
    )
    Appellees.              )
    ________________________________ )
    Opinion filed December 31, 2014.
    Appeal from the Circuit Court for Lee
    County; Keith R. Kyle, Judge.
    Frank B. Arenas, Coleman, and
    Alberto E. Lugo-Janer, Windermere,
    for Appellants.
    Stephen H. Grimes, D. Bruce May, Jr.,
    Elizabeth L. Bevington, and Kevin W.
    Cox of Holland & Knight, LLP,
    Tallahassee, for Appellees.
    KELLY, Judge.
    The appellants, customers of Duke Energy Florida, Inc., and Florida
    Power & Light Company (the Utilities), brought suit against the Utilities challenging the
    constitutionality of sections 366.93 and 403.519, Florida Statutes (2012), and seeking a
    refund of monies paid under the statutes. They appeal from the trial court's order
    dismissing the action with prejudice. We affirm.
    In 2006, the Legislature enacted section 366.93, Florida Statutes, and
    amended section 403.519, Florida Statutes,1 with the stated purpose of encouraging
    utility companies to invest in new nuclear power plants. See Ch. 2006-230, § 1, at
    The applicable version of section 403.519(4)(e), Florida Statutes (2012),
    1
    provides in pertinent part:
    After a petition for determination of need for a nuclear or
    integrated gasification combined cycle power plant has been
    granted, the right of a utility to recover any costs incurred
    prior to commercial operation, including, but not limited to,
    costs associated with the siting, design, licensing, or
    construction of the plant and new, expanded, or relocated
    electrical transmission lines or facilities of any size that are
    necessary to serve the nuclear power plant, shall not be
    subject to challenge unless and only to the extent the
    commission finds, based on a preponderance of the
    evidence adduced at a hearing before the commission under
    s. 120.57, that certain costs were imprudently incurred.
    Section 366.93(2), Florida Statutes (2012), retains the same language as
    the 2006 version of the statute and directs the Florida Public Service Commission
    (PSC) to "establish, by rule, alternative cost recovery mechanisms for the recovery of
    costs incurred in the siting, design, licensing, and construction of a nuclear power plant."
    Subsection (1)(a) defines "cost" and states that it "includes, but is not limited to, all
    capital investments, including rate of return, any applicable taxes, and all expenses . . .
    related to or resulting from the siting, licensing, design, construction, or operation of the
    nuclear power plant."
    -2-
    2595-96, Laws of Fla.; Ch. 2006-230, § 44, at 2648-49, Laws of Fla. As contemplated
    by the statutes, the Florida Public Service Commission (PSC) authorized the Utilities to
    begin the construction of a nuclear plant and, in the case of Florida Power & Light
    Company, to modify its existing nuclear plants to increase their generating capacity.
    Normally, a public utility is required to wait until after an electrical power plant is
    constructed and fully operational before it can recover the cost of constructing the new
    plant from its customers. See S. Alliance For Clean Energy v. Graham, 
    113 So. 3d 742
    ,
    745 (Fla. 2013). However, the 2006 legislation allows public utilities to recover
    preconstruction and carrying costs before a nuclear power plant begins to operate.
    Section 366.93(6) provides in pertinent part:
    If the utility elects not to complete or is precluded from
    completing construction of the nuclear power plant, including
    new, expanded, or relocated electrical transmission lines or
    facilities necessary thereto, or of the integrated gasification
    combined cycle power plant, the utility shall be allowed to
    recover all prudent preconstruction and construction costs
    incurred following the commission's issuance of a final order
    granting a determination of need for the nuclear power plant
    and electrical transmission lines and facilities necessary
    thereto or for the integrated gasification combined cycle
    power plant.
    § 366.93(6), Fla. Stat. (2012).
    The appellants sued the Utilities alleging that the 2006 legislation is
    unconstitutional and seeking a refund of the monies paid to the Utilities pursuant to the
    cost recovery statutes. The Utilities moved to dismiss. The trial court dismissed the
    amended complaint, but with leave to amend. The appellants filed a second amended
    complaint and the Utilities again moved to dismiss. After a hearing, the trial court
    -3-
    granted the Utilities' motion and dismissed the second amended complaint with
    prejudice.
    The second amended complaint contained two counts, only one of which
    is at issue in this appeal. In that count the appellants allege that sections 366.93 and
    403.519 are facially unconstitutional under Article I, Section 10 of the Constitution of the
    United States. Specifically, they allege that pursuant to the statutes, the Utilities have
    been charging additional amounts above the amount charged for the electricity they
    have consumed and that this constitutes an unconstitutional impairment of their
    contractual relationship with the Utilities. The complaint alleges that any public purpose
    justifying the impairment is destroyed by the fact that the statutes authorize the Utilities
    to elect not to build, complete, or operate the nuclear power plants yet keep the
    preconstruction costs charged to customers, plus a rate of return.
    The constitutionality of a statute is a question of law we review de novo.
    Fla. Dep't of Revenue v. City of Gainesville, 
    918 So. 2d 250
    , 256 (Fla. 2005). A facial
    constitutional challenge considers only the text of the statute, not its application to a
    particular set of circumstances. Abdool v. Bondi, 
    141 So. 3d 529
    , 538 (Fla. 2014). A
    determination that a statute is facially unconstitutional means that no set of
    circumstances exists under which the statute would be valid. United States v. Salerno,
    
    481 U.S. 739
    , 745 (1987); City of 
    Gainesville, 918 So. 2d at 256
    . "If any state of facts,
    known or to be assumed, justify the law, the court's power of inquiry ends." State v.
    Bales, 
    343 So. 2d 9
    , 11 (Fla. 1977) (citing United States v. Carolene Prods. Co., 
    304 U.S. 144
    , 154 (1938)). A facial challenge fails when a statute has a "plainly legitimate
    -4-
    sweep." Wash. State Grange v. Wash. State Republican Party, 
    552 U.S. 442
    , 449
    (2008) (citation omitted).
    While the appellants argue that the challenged statutes are facially
    unconstitutional, they have utterly failed in their burden to demonstrate that no
    circumstances exist under which the statutes would be valid. Rather, the crux of the
    appellants' challenge focuses only on one particular circumstance contemplated by the
    statute—the recovery of costs of construction where a utility "elects" not to build the
    plant. The appellants contend that the "statutes authorize each Defendant to elect not
    to build, complete or operate the nuclear power plants and thereby defeat any public
    purpose or public use." They have not alleged nor argued that in the event a utility is
    precluded from completing a power plant due to factors beyond its control, the public
    purpose for the legislation, which is to encourage investment in new nuclear power
    plants, is defeated. As noted by the Florida Supreme Court, transferring the risk for
    proposed nuclear projects to encourage utilities to invest in new facilities is a "policy
    consideration best addressed by the Legislature," and not the courts. Graham, 
    113 So. 3d
    at 753. Because the appellants have not met their burden of demonstrating that the
    statute is unconstitutional in all its possible applications, we affirm.
    Affirmed.
    ALTENBERND and SILBERMAN, JJ., Concur.
    -5-
    

Document Info

Docket Number: 2D13-4746

Citation Numbers: 154 So. 3d 439, 2014 Fla. App. LEXIS 20925

Judges: Kelly, Altenbernd, Silberman

Filed Date: 12/31/2014

Precedential Status: Precedential

Modified Date: 10/19/2024