Miami-Dade County v. Florida Power & Light Co. , 2016 Fla. App. LEXIS 5953 ( 2016 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed April 20, 2016.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    Nos. 3D14-1467, 3D14-1466, 3D14-1465, 3D14-1451
    Lower Tribunal Nos. 09-3107, 09-3575
    ________________
    Miami-Dade County, et al.,
    Appellants,
    vs.
    In Re: Florida Power & Light Co., etc., et al.,
    Appellees.
    Appeals from the Florida Department of Environmental Protection.
    Abigail Price-Williams, Miami-Dade County Attorney, and Dennis A.
    Kerbel, Assistant County Attorney; Nabors Giblin & Nickerson, P.A., and William
    C. Garner (Tallahassee); Thomas F. Pepe, City Attorney; Victoria Méndez, City
    Attorney, and John A. Greco, Deputy City Attorney, and Forrest L. Andrews and
    Matthew Haber, Assistant City Attorneys, for appellants.
    Michael S. Tammaro (Juno Beach); Hopping Green & Sams, P.A., and Peter
    C. Cunningham and Brooke E. Lewis (Tallahassee); Holland & Knight, LLP, and
    Rodolfo Sorondo; Franscisco J. Pines; Craig D. Varn, General Counsel, and
    Francine M. Ffolkes, Administrative Law Counsel (Tallahassee), for appellees.
    Wasson & Associates, Chartered, and Roy D. Wasson, for The Friends of
    the Underline, Inc., as amicus curiae.
    Before LAGOA, EMAS and FERNANDEZ, JJ.
    FERNANDEZ, J.
    The City of Miami, Miami-Dade County (“the County”), the Village of
    Pinecrest, and the City of South Miami, et al., supported by amicus curiae, appeal
    the same Final Order on Certification rendered by Florida’s State Siting Board,
    including a Recommended Order and approved Conditions of Certification, which
    permits appellee Florida Power & Light Company (“FPL”) to construct and
    operate two new nuclear generating units and associated facilities at Turkey Point,
    in addition to allowing FPL to install miles of new transmission lines. The parties
    appeal a number of issues, a few of which overlap.1 We reverse and remand
    because the Siting Board failed to apply the City of Miami’s applicable land
    development regulations, the Siting Board erroneously thought it did not have the
    power to require FPL to install the lines underground at FPL’s expense, and the
    Siting Board erred in interpreting the County’s East Everglades Ordinance as a
    zoning regulation, rather than an environmental one. 2
    Factual Background
    1. The Florida Electrical Power Plant Siting Act
    1   The Village of Pinecrest adopts the City of Miami’s positions.
    2 There were many issues that were dealt with below via stipulations and
    agreements. We decline to discuss those issues.
    2
    Sections 403.501-.518, Florida Statutes (2013) are known as the “Florida
    Electrical Power Plant Siting Act” (“PPSA”). The PPSA governs certification of
    new power plants and its associated facilities.      Section 403.502 describes the
    legislative intent, which states:
    The Legislature finds that the present and predicted growth in electric
    power demands in this state requires the development of a procedure for the
    selection and utilization of sites for electrical generating facilities and the
    identification of a state position with respect to each proposed site and its
    associated facilities. The Legislature recognizes that the selection of site and
    the routing of associated facilities, including transmission lines, will have a
    significant impact upon the welfare of the population, the location and
    growth of industry, and the use of the natural resources of the state. The
    Legislature finds that the efficiency of the permit application and review
    process at both the state and local level would be improved with the
    implementation of a process whereby a permit application would be
    centrally coordinated and all permit decisions could be reviewed on the basis
    of the standards and recommendations of the deciding agencies. It is the
    policy of this state that, while recognizing the pressing need for increased
    power generation facilities, the state shall ensure through available and
    reasonable methods that the location and operation of electrical power plants
    will produce minimal adverse effects on human health, the environment, the
    ecology of the land and its wildlife, and the ecology of state waters and their
    aquatic life and will not unduly conflict with the goals established by the
    applicable local comprehensive plans. It is the intent to seek courses of
    action that will fully balance the increasing demands for electrical power
    plant location and operation with the broad interests of the public. Such
    action will be based on these premises:
    (1) To assure the citizens of Florida that operation safeguards are
    technically sufficient for their welfare and protection.
    (2) To effect a reasonable balance between the need for the facility
    and the environmental impact resulting from construction and operation of
    the facility, including air and water quality, fish and wildlife, and the water
    resources and other natural resources of the state.
    3
    (3) To meet the need for electrical energy as established pursuant to s.
    403.519.
    (4) To assure the citizens of Florida that renewable energy sources
    and technologies, as well as conservation measures, are utilized to the extent
    reasonably available.
    See § 403.502, Fla. Stat. (2013). Specifically, section 403.509(3) outlines a
    certification test which the Siting Board, comprised of the Governor and his
    cabinet, must apply when it holds hearings to approve in whole, approve with
    modifications or conditions, or deny a new project. The test requires the submitted
    application to include the following, in pertinent part:
    a) Provide reasonable assurance that operational safeguards are technically
    sufficient for the public welfare and protection.
    b) Comply with applicable nonprocedural requirements of agencies.
    c) Be consistent with applicable local government comprehensive plans and
    land development regulations.
    d) Meet the electrical energy needs of the state in an orderly, reliable, and
    timely fashion.
    e) Effect a reasonable balance between the need for the facility as
    established pursuant to s. 403.519 and the impacts upon air and water
    quality, fish and wildlife, water resources, and other natural resources of
    the state resulting from the construction and operation of the facility.
    f) Minimize through the use of reasonable and available methods, the
    adverse effects on human health, the environment, and the ecology of the
    land and its wildlife and the ecology of state waters and their aquatic life.
    g) Serve and protect the broad interests of the public.
    4
    In addition, the PPSA requires transmission line corridors to adhere to the same
    certification test as the rest of the power plant project. See § 403.509(4)(a).
    2. The East Everglades Ordinance
    The East Everglades is a unique section of land with a biologically diverse
    ecosystem. In 1980, the East Everglades Resources Planning Project issued a
    “Proposed Management Plan for the East Everglades.” In 1981, to implement
    the     Management      Plan,   the   Miami-Dade     County    Board    of     County
    Commissioners designated the East Everglades Area of Critical Environmental
    Concern (“East Everglades”) and adopted regulations to protect the natural
    ecosystem of the East Everglades. These were codified as Chapter 33B, Article
    II, Divisions1-4 of the Miami-Dade County Code (known as “The East
    Everglades Ordinance” or Chapter 33B).
    The East Everglades was designated first, then in 1989 the Park expanded into
    Everglades National Park. The eastern boundary of the East Everglades is the L-
    31N canal, which is also the eastern boundary of Everglades National Park.
    The East Everglades Ordinance’s statement of legislative intent declared:
    It is the purpose of this designation to protect the public health, safety and
    welfare by assuring orderly development of the designated area and minimal
    degradation of those natural ecosystems described in Section 33B-13; by
    requiring that the functional integrity of natural ecosystems as described in
    Section 33B-13 is protected; by assuring the maintenance of the present
    surface and subsurface hydrology within those lands described in Section
    33B-13; by providing for the protection of the ecological form and function
    of the Everglades National Park, its estuarine areas and adjacent wetlands,
    5
    and to maintain the capability of the natural environment to sustain a
    proposed use in the long term.
    See § 33B-11, County Code.
    Specifically,   Section   33B-13(d)-(f)   outlines   environmental   findings
    describing the “[d]angers resulting from uncontrolled development of the area,”
    including:
    (1) Pollution of groundwater supply. Uncontrolled development within
    the area poses a serious threat to the quality of water recharged to the
    Biscayne Aquifer…
    (2) Pollution of surface water to Everglades National Park.
    (3) Reduction of surface water flow to Everglades National Park.
    (4) Reduction of groundwater recharge to Biscayne Aquifer.
    (5) Reduction of flood storage capacity.
    (6) Danger to development from flooding.
    (7) Danger to development from fire.
    (8) Loss of vegetation, pinnacle rock, wildlife.
    The ordinance includes Division 2 titled, “East Everglades Zoning Overlay
    Ordinance.” Division 2 describes which uses are allowed in the East Everglades,
    which uses require a conditional use permit, and which uses are prohibited.
    Although the title includes the word “zoning” in it, section 33B-26 includes
    “environmental performance standards.” These standards are enforced by Miami-
    Dade County’s Division of Environmental Resources Management (“DERM”).
    Division 2 sets the standards for conditional use permits, as well as the standards
    for variances.
    6
    The Ordinance divides the East Everglades into management areas.
    Management Area 2A is the most restrictive area in terms of land uses, filling land,
    excavating land, building roads and clearing native vegetation. See § 33B-25, 33B-
    26.     For example, section 33B-26(c)(1) and (2) state that no roads shall be
    permitted in Management Area 2A.
    3. FPL’s Site Certification Application and Proceedings Below
    FPL submitted a Site Certification Application to the Florida Department of
    Environmental Protection (“DEP”), pursuant to the PPSA. FPL sought approval for
    the Turkey Point Units 6 & 7 Project (“Project”). The Project included new
    electrical transmission lines and associated facilities in western Miami-Dade
    County.
    After FPL filed is Site Certification Application, a lengthy certification
    hearing before the Administrative Law Judge (“ALJ”) followed, at which
    numerous parties participated, including all the appellants. At the hearing, the City
    of Miami presented evidence regarding its land development regulations and why
    FPL was required to comply with those regulations. The City of Miami also
    outlined the problems raised with the placement of FPL’s proposed poles, which
    in some cases were as tall as 105 feet, in the City of Miami’s densely populated
    urban areas. The City of Miami presented evidence that the sea level and storm
    surges would be a problem for the proposed two nuclear reactors. It additionally
    7
    believed that FPL’s proposed water uses for the facilities would harm wetlands,
    ground and surface waters, Biscayne Bay and the Biscayne Bay Aquatic Preserve.
    It contended that the DEP refused to consider local land development regulations
    or comprehensive plans to the transmission line portions of FPL’s application,
    which it claimed the DEP was statutorily required to consider. Miami-Dade
    County also raised its objections, particularly because the western transmission line
    corridor would run through areas of the East Everglades.3
    At the end of the certification hearing, the ALJ issued its Recommended
    Order approving the project. The ALJ approved FPL’s West Preferred Corridor as
    a back-up western transmission corridor if adequate right-of-way could not be
    obtained in the primary corridor in a timely manner and at a reasonable cost. The
    transmission lines and roads in the West Preferred Corridor would be installed all
    within the current boundaries of both the East Everglades and Everglades National
    Park for approximately 6 miles. The Recommended Order did not consider local
    regulations, stating:
    3 The West Preferred Corridor would run along the west side of the L-31N canal
    for 7.4 miles between S.W. 120th Street and S.W. 8th Street/Tamiami Trail and
    would consist of dual 500-kV transmission lines and a single 230-kV line, along
    with access roads. The transmission lines and roads in the West Preferred Corridor
    would be installed entirely within the current boundaries of both the East
    Everglades and Everglades National Park for approximately 6 miles. The
    remaining 1.4-mile segment would run south along the L-31N canal to S.W. 120th
    Street and falls outside the Everglades National Park boundaries, but remains
    within the East Everglades.
    8
    “[DEP] interprets the [Act], and in particular section 403.509, to mean
    that there are no “applicable” local government comprehensive plans or
    [land development regulations] for the proposed transmission lines...
    In addition, the Recommended Order did not require FPL to underground its lines.
    The parties opposed to the Recommended Order filed numerous exceptions. On
    May 19, 2014, the Siting Board, sitting as the head of the DEP, issued a Final
    Order on Certification (“Order”), in which it adopted the ALJ’s Recommended
    Order.
    Standard of Review
    An administrative agency’s conclusions of law are reviewed de novo.
    Parlato v. Secret Oaks Owners Ass’n, 
    793 So. 2d 1158
    , 1162 (Fla. 1st DCA 2001).
    This is only with respect to statutory interpretation. Florida Statute, section
    120.68(7)(d) states that “[t]he court shall remand a case to the agency for further
    proceedings consistent with the court’s decision or set aside agency action, as
    appropriate when it finds that: …[t]he agency has erroneously interpreted a
    provision of law and a correct interpretation compels a particular action…”
    Deference is given to administrative agencies, however a “court need not
    defer to an agency’s construction if the language of the statute is clear and
    therefore not subject to construction.” Doyle v. Dep’t of Bus. Regulation, 
    794 So. 2d
    686, 690 (Fla. 1st DCA 2001). Here, the statute is clear and unambiguous.
    9
    Thus, we review this case de novo and are not required to give deference to an
    agency’s interpretation.
    The Siting Board Failed to Consider Local Regulations, as required by
    section 403.509(3), Fla. Stat. (2013).
    We first address the City of Miami’s contention that the Siting Board erred
    in not considering local regulations when certifying the transmission line corridors,
    as was required by section 403.509(3)(b), Florida Statute (2013). We agree with
    the City of Miami, as the applicable local regulations should have been applied.
    The PPSA requires that the Siting Board apply the certification test outlined
    in section 403.509(4)(a). Criteria b) and c) state that the applied for project will
    comply with applicable nonprocedural requirements of agencies and be consistent
    with applicable local government comprehensive plans and land development
    regulations, respectively. Section 403.509(4)(a), Fla. Stat. (2013) states that “[a]ny
    transmission line corridor certified by the board...shall meet the criteria of this
    section.”
    In addition, “Nonprocedural requirements of agencies” is defined in section
    403.503(21) as:
    ...any agency’s regulatory requirements established by statute, rule,
    ordinance, zoning ordinance, land development code, or comprehensive plan,
    excluding any provisions prescribing forms, fees, procedures, or time limits for the
    review or processing of information submitted to demonstrate compliance with
    such regulatory requirements.
    10
    Section 403.503(2)‘s definition of “agency” includes local governments. As such,
    section 403.509(3)‘s certification test requires that local comprehensive plans and
    land development regulations be taken into account. The DEP and FPL both agreed
    that this was to be considered at the certification hearing. Therefore, the PPSA
    requires that local comprehensive plans, substantive conditions of zoning
    approvals, and other land development regulations be considered in the
    certification of power plants.
    Here, the conditions of certification in the Final Order did not consider local
    regulations. As the City of Miami contends, the conditions of certification issued
    with the Siting Board’s Final Order are the means by which the Board takes into
    consideration and incorporates local regulations. The ALJ’s Recommended Order
    found that “there are no ‘applicable’ local government” regulations. The record
    that the Siting Board had before it was thus incomplete because the local
    regulations were not considered with respect to the transmission line corridors.
    In addition, the Siting Board applied a “development” exception when it
    should not have it. Section 380.04 (3)(b), Florida Statute (2013), part of “The
    Florida Environmental Land and Water Management Act of 1972” defines
    “development” as:
    Work done by an utility and other persons engaged in the distribution or
    transmission of gas, electricity, or water, for the purpose of inspecting, repairing,
    renewing, or construction on established rights-of-way any sewers, mains, pipes,
    cables, utility tunnels, power lines, towers, poles, tracks or the like…
    11
    The Siting Board incorrectly determined that transmission line corridors were
    excluded from consideration by the definition of “development.” As the City of
    Miami contends, this is incorrect. The “development” exception does not apply to
    the entire corridor. The Siting Board certifies a corridor, not a right-of-way.
    According to the PPSA:
    (11) a “corridor” means the proposed area within which an associated
    linear facility right-of-way is to be located. The width of the corridor
    proposed for certification as an associated facility, at the option of the
    applicant, may be the width of the right-of-way or a wider boundary, not to
    exceed a width of 1 mile. The area within the corridor in which a right-of-
    way may be located may be further restricted by a condition of certification.
    After all property interests required for the right-of-way have been acquired
    by the licensee, the boundaries of the area certified shall narrow to only that
    land within the boundaries of the right-of-way...
    ***
    (27) “Right-of-way” means land necessary for the construction and
    maintenance of a connected associated linear facility, such as a railroad line,
    pipeline, or transmission line as owned by or proposed to be certified by the
    applicant...The right of way shall be located within the certified corridor and
    shall be identified by the applicant subsequent to certification in documents
    filed with the department prior to construction.
    See § 403.503(11) and (27), Fla. Stat. (2013).
    Consequently, the “development” exception cannot be applied to the entire width
    of the corridor. As the record reflects, the corridor is made up of parcels outside of
    established rights-of-way, some of which are privately owned. Thus, the Siting
    Board has no way of knowing if construction will take place within an established
    right-of-way or a private easement. The “development” exception thus cannot
    12
    exempt transmission line corridors from the PPSA’s requirement that local land
    regulations are to be considered.
    In addition, FPL contends that section 380.04 stands for the proposition that
    any work done by a utility company is not development, so land development
    regulations do not apply. We believe this argument to be misplaced and instead
    agree with the City of Miami that construction of a transmission line on land that is
    not established as a right-of-way constitutes “development.” Section 380.04(3)(b)
    states that the “development” exception is limited to work conducted on
    “established rights-of-way.” Courts that have interpreted this section use
    “established” with the word “existing.” See Rinker Materials Corp. v. Town of
    Lake Park, 
    494 So. 2d 1123
    , 1126 (Fla. 1986); St. Johns Cnty. v. Dep’t of Cmty.
    Affairs, 
    836 So. 2d 1034
    , 1037 (Fla. 5th DCA 2002).
    This section uses “established,” a past tense word. The use of the past tense
    in this statute indicates that the “development” exception only applies to existing
    rights-of-way. The Siting Board, in essence, struck the word “established” from
    the statute, which it is not permitted to do. Florida Dept. of Revenue v. Florida
    Mun. Power Agency, 
    789 So. 2d 320
    (Fla. 2001). The right-of-way must be
    established, so there is no exemption from local regulations. And as the City of
    Miami contends, were this Court to accept FPL’s argument on this issue, that an
    13
    established right-of-way is not the same as an existing or pre-existing right-of-way,
    this would make the word “established” meaningless.4
    The Siting Board did not review or consider the City of Miami’s LDR’s, so
    the order on appeal does not incorporate the local regulations of the City of Miami
    into the conditions of certification that control the electrical transmission lines, as
    required by section 403.509(3), Fla. Stat. (2013). Accordingly, because the order
    did not comply with this statute, we reverse on this issue.
    The Siting Board Has the Power to Order Undergrounding of
    Transmission Lines
    We further reverse that portion of the Siting Board’s Order where it
    erroneously determined that it lacked the authority to condition certification of
    FPL’s project on FPL installing the power lines underground, at FPL’s expense. As
    the City of Miami and the City of South Miami contend, the PPSA empowers the
    Siting Board to require FPL to bury these transmission lines.
    Section 403.511 of the PPSA gives the Siting Board the power to make
    certification of FPL’s application subject to the conditions set out in the Final
    Order. The general grant of power in the PPSA to “impose conditions” upon
    certification, other than those listed in the PPSA, gave the Siting Board the power
    to impose the condition of requiring that the power lines be installed underground,
    4      Florida courts have held that a plan to create a right-of-way in the future is
    not a right-of-way. See Clipper Bay Investments, LLC v. State Dep’t of Transp.,
    
    117 So. 3d 7
    (Fla. 1st DCA 2013).
    14
    at   FPL’s   expense.    See   §     403.511(1),   Fla.   Stat.;   §   403.511(2)(b)(2).
    Undergrounding of the transmission lines is a condition upon certification
    encompassed by the Siting Board’s ability to impose “site specific criteria,
    standards, or limitations” on FPL’s project. As such, the Siting Board had the
    power to require it, contrary to the Siting Board’s conclusion that it had no such
    power.5 Accordingly, reversal is required on this point.
    FPL contends that Florida Power Corp. v. Seminole County, 
    579 So. 2d 105
    ,
    108 (Fla. 1991) stands for the proposition that requiring undergrounding of the
    transmission lines is outside of the Siting Board’s jurisdiction. We disagree with
    FPL’s interpretation of this case.
    In Seminole, Seminole County and the City of Lake Mary were trying to
    mandate Florida Power Corporation (FPC) to convert overhead lines to
    underground lines on a stretch of road in question. 
    Id. at 106.
    The City and County
    5 In its Final Order of Certification, the Siting Board adopted the ALJ’s conclusion
    that “as a matter of law. . . the PPSA preempts a local government’s authority to
    regulate transmission lines that extend through several local government
    jurisdictions.” A fair reading of the Final Order of Certification, in context, leads
    us to conclude that the Siting Board determined it did not have the authority to
    require undergrounding of transmission lines as a condition of certification. As we
    explain in this opinion, we conclude that the Siting Board does have such
    authority, although we express no opinion on the merits of the issue. We recognize
    that the Final Order of Certification contains a discussion of the ALJ’s factual
    findings regarding the increased cost and effectiveness of such a proposition. Our
    holding in this regard should not be interpreted as requiring that additional
    hearings be held or additional evidence taken, only that the Siting Board is within
    its authority to consider such an issue and should exercise that authority as it
    deems appropriate.
    15
    decided to widen Lake Mary Boulevard. The City enacted ordinances requiring
    FPC to relocate its power lines underground and stating that FPC bear the cost of
    undergrounding. The County's ordinance did not specify who would pay the cost of
    placing the power lines underground, but the County stated that it would not do so.
    
    Id. FPC sued
    the City and the County for a declaratory judgment and injunctive
    relief, admitting it was obligated under section 337.403(1), Florida Statutes (1989),
    to relocate the lines overhead within the new right of way at its expense. 
    Id. However, FPC
    contended that it would cost an additional $1,250,000 to place the
    lines underground, and it would place the lines underground only if the City and
    the County would bear the additional cost. Following trial, the circuit judge upheld
    the validity of the ordinances. 
    Id. On appeal,
    FPC asserted that the ordinance invaded the exclusive authority
    of the Public Service Commission (PSC) to regulate rates and service. 
    Id. FPC argued
    that if the ordinances were upheld, similar ordinances would follow and
    that the cost of converting all of FPC's lines to underground lines would exceed
    $2.5 billion. Both the City and the County relied on section 337.403(1), Florida
    Statutes (1989), which the circuit judge cited as authority for his ruling. 
    Id. The Supreme
    Court of Florida ruled in favor of FPC. 
    Id. The Court
    stated
    that section 366.04(1), Florida Statutes (1989), expressly confers jurisdiction on
    16
    the Public Service Commission to “regulate and supervise each public utility with
    respect to its rates and service.” 
    Id. The Court
    stated that the Public Service
    Commission has broad powers in the exercise of its “exclusive and superior”
    jurisdiction, including:
    [the] power to prescribe fair and reasonable rates and charges,
    classifications, standards of quality and measurements, and service rules and
    regulations to be observed by each public utility; to require repairs,
    improvements, additions, and extensions to the plant and equipment of any
    public utility when reasonably necessary to promote the convenience and
    welfare of the public and secure adequate service or facilities for those
    reasonably entitled thereto; ... and to prescribe all rules and regulations
    reasonably necessary and appropriate for the administration and enforcement
    of this chapter.§ 366.05(1), Fla. Stat. (1989).
    
    Id. at 106-07.
    The Court reasoned that if FPC has to expend large sums of money
    in converting its overhead power lines to underground, these expenditures will
    necessarily be reflected in the rates of its customers. The Court did not believe that
    the statute granted the County the authority to regulate public utilities and that such
    authority rested exclusively with the Public Service Commission. 
    Id. at 107.
    The Court went on to state that “if there was any doubt that the legislature
    did not intend that cities and counties could dictate the decision of whether public
    utilities should convert their overhead systems to underground, this was laid to rest
    by the enactment of section 366.04(7)(a), Florida Statutes (1989),” which provides
    in pertinent part that:
    By July 1, 1990, the commission shall make a determination as to the
    cost-effectiveness of requiring the installation of underground electric utility
    17
    distribution and transmission facilities for all new construction, and for the
    conversion of overhead distribution and transmission facilities to
    underground distribution and transmission facilities when such facilities are
    replaced or relocated.... Upon a finding by the commission that the
    installation of underground distribution and transmission facilities is cost-
    effective, the commission shall require electric utilities, where feasible, to
    install such facilities.
    
    Id. at 108.
    The Court stated, “Permitting cities or counties to unilaterally mandate
    the conversion of overhead lines to underground would clearly run contrary to the
    legislative intent that the Public Service Commission have regulatory authority
    over this subject.” 
    Id. We find
    the Seminole case to be distinguishable because the Court said
    nothing in that case regarding whether undergrounding may be required as a
    condition of certification in the licensing of a transmission line corridor. In
    addition, the Supreme Court’s determination regarding the Public Service
    Commission was based on statutory language that the Legislature has since deleted
    from this section. The Seminole holding was made in the context of rate-making
    with regard to the power vested in the Public Service Commission and not in the
    context of any of the Siting Board’s powers. The Siting Board’s power in no way
    infringes on the PSC’s authority with regard to rate-making, and there is no
    conflict with the PSC’s role. The Seminole case is simply inapplicable to the case
    before us.
    The Siting Board Erred in Interpreting the County’s East Everglades Ordinance
    as a Zoning Ordinance Rather than as an Environmental Regulation
    18
    Turning now to Miami-Dade County’s contention that the Siting Board erred
    in interpreting the County’s East Everglades Ordinance, we believe that the
    substance and legislative history of the ordinance demonstrate that the ultimate
    purpose of the East Everglades Ordinance is to protect the environment in the
    Everglades.6 Thus, we agree with the County that the East Everglades Ordinance is
    primarily an environmental regulation.
    In coming to this decision, we note that it appears that the Siting Board
    decided that Chapter 33B is a zoning regulation because one of its divisions is
    titled “East Everglades Zoning Overlay Ordinance.” In its Order, the Siting Board
    stated “MDC has adopted the East Everglades regulations as part of its Zoning
    Code, it cannot now be allowed to unilaterally change the nature or expand the
    scope of those regulations to suit its purposes in this proceeding.” This statement
    was incorrect.
    The County’s Zoning Code is codified as Chapter 33 of the Miami-Dade
    County Code. As previously discussed, the East Everglades Ordinance is codified
    as Chapter 33B. It is a separate chapter titled “Areas of Critical Environmental
    Concern.” Although it appears adjacent to the zoning code, it is not part of it. As
    the County points out in support of its position, Chapter 28 of its Code addresses
    6 At oral argument, FPL’s counsel conceded that the purpose of chapter 33B was to
    “protect the natural resources and environmental values” in the East Everglades
    area.
    19
    “Subdivisions,” while chapter 28A addresses “Seaport Security and Operations.”
    Chapter 8 is titled, “Building Code,” while chapter 8A is the code of “Business
    Regulations.” Just like these adjacent chapters make it clear that they are not
    related to each other, chapter 33B is not related to chapter 33. These two chapters
    are distinct, and Chapter 33B is not an appendix to chapter 33.
    The County contends that the character of a law is determined by its purpose
    and operation, not its titles or headings. The United States Supreme Court held in
    United States v. Constantine, 
    296 U.S. 287
    , 294 (1935) that courts “must ascribe to
    [a regulation] the character disclosed by its purpose and operation, regardless of
    name.” The subchapter heading cannot substitute for the operative text of the
    statute.” Florida Dept. of Revenue v. Piccadilly Cafeterias, Inc., 
    554 U.S. 33
    , 47
    (2008). In addition, the County Code specifies that section headings are not to be
    considered as part of the regulation: “The catchlines of the several sections of this
    Code printed in boldface type are intended as mere catchwords to indicate the
    contents of the section and shall not be deemed or taken to be titles of such
    sections, nor as any part of the section, nor, unless expressly so provided, shall
    they be so deemed when any of such sections, including the catchlines, are
    amended or reenacted.” See § 1-3, County Code. Furthermore, the title or section
    heading does not determine its meaning. See Whitman v. American Trucking
    Assocs., 
    531 U.S. 457
    , 482-83 (2001). Thus, the Siting Board’s determination that
    20
    Chapter 33B is a zoning regulation was erroneous because it focused on the title of
    the chapter as opposed to its environmental character.
    In addition, the text of Chapter 33B indicates that it is an environmental
    regulation. Section 33B-13, Division 1, outlines the “environmental findings”
    which focuses on the protection of water flow, water quality and quantity, and
    native wildlife in the East Everglades. Division 2 states its purpose is to protect and
    preserve the environmental values of the East Everglades. As previously discussed,
    the “Zoning Overlay” division lists “environmental performance standards” and
    regulates issues such as fill, excavation, and roads and their environmental
    impacts.” See § 33B-26(c)(1). The Ordinance is how the County implemented the
    East Everglades Resources Planning Project’s “Proposed Management Plan for the
    East Everglades.” The Management Plan’s main concern was the area’s freshwater
    resources, its wildlife and its vegetation, and the impact of future development on
    those resources,” in addition to “the long term health of the water supply.”
    The East Everglades Ordinance is administered mainly by DERM, not the
    County’s zoning department. Moreover, the land use components that are included
    in the ordinance are designed to address environmental impacts, such as water
    pollution, reduction in the supply of water to the Everglades, reduction of
    groundwater recharge to the Biscayne Aquifer, and reduction of flood storage
    capacity. See § 33B-13(d), 33B-25, 33B-28. All of these factors together leads us
    21
    to the conclusion that the ALJ erred in determining that 33B was a zoning
    regulation, and the Siting Board erred in accepting the ALJ’s findings.
    Consequently, because the East Everglades Ordinance is an applicable, non-
    procedural environmental requirement of the County, very similar to Chapter 24 of
    the County Code, which is the County’s environmental regulatory code, FPL
    cannot install the transmission lines and roads proposed in its project without
    requesting a variance.   7   Chapter 33B expressly prohibits roads, does not permit
    transmission lines anywhere in the East Everglades, and greatly restricts the
    amount of wetland filing in the area. FPL never requested these variances. There is
    no evidence in the record that notice was given that these variances would be
    considered. The East Everglades Ordinance required public notice and an
    7 Chapter 24 of the Miami-Dade County Code is titled “Environmental Protection,
    Biscayne Bay and Environs Designated Aquatic Park and Conservation Area, The
    Biscayne Bay Environmental Enhancement Trust Fund, and the Environmentally
    Endangered Lands Program. Section 24-2, “Declaration of Legislative Intent”
    states:
    The Board further finds it necessary to maintain within Miami-Dade County a
    freshwater wetlands management program for the purposes of providing adequate
    water levels, flood control, water conservation, protection of water quality and
    recharge to the Biscayne Aquifer, and prevention of saltwater intrusion; for the
    maintenance of the biological integrity of freshwater wetlands in Miami-Dade
    County; for the protection of the interrelated natural functions between Miami-
    Dade County's wetlands and the natural systems in Everglades National Park; for
    managing freshwater wetland resources in accordance with environmental
    standards and management criteria as recommended by the Miami-Dade County
    Comprehensive Development Master Plan and Chapter 33B of the Code of Miami-
    Dade County, Florida, as amended from time to time; and providing for
    cooperation with federal, State, and local agencies and authorities.
    22
    opportunity to be heard for any conditional uses or variances being approved. See
    § 33B-27(b)(2). Because FPL cannot construct the transmission lines and roads on
    the west side of the L-31N canal without these variances, FPL’s proposed West
    Preferred Corridor project could not have been approved.
    The PPSA requires applicants to request any “variance, exemption,
    exception, or other relief” that would be required to comply with the applicable,
    non-procedural regulations of agencies such as the County, that are parties to the
    certification proceeding. The only way for the applicant to not have to comply
    with this requirement is if the agency has failed to provide notice in the site
    certification proceeding that the regulations are applicable. See § 403.507(3)(a),
    Fla. Stat.
    Here, the County filed an Agency Report on the West Preferred Corridor
    that outlined all the requirements of Chapter 33B, including Section 33B-28, as
    County regulations that apply to FPL’s project in question. The Agency Report
    stated that roads and fill pads would be prohibited in certain areas under Chapter
    33B. The County’s Report also stated:
    The portion of the project proposed in the East Everglades Area of
    Critical Environmental Concern shall be relocated outside the Easter
    Everglades or not be constructed unless the project is modified to meet all
    requirements of County Code Chapter 24 and 33B including but not limited
    to the Section 33B-28 and provided the portions of the corridor are built with
    road less construction techniques and without fill pads for the transmission
    lines. Furthermore, additional modification of project design in this area
    would be required to avoid all permanent impacts to rare, threatened and
    23
    endangered species by techniques such as undergrounding, and FPL shall be
    responsible for the cost associated with undergrounding transmission lines.
    Because FPL did not apply for the necessary variances from Chapter 33B, it
    was a violation of due process for the Siting Board to grant them. A court must set
    aside any agency action if a notice does not adequately identify the matters that the
    agency will consider. Florida Optometric Ass’n v. Dep’t of Prof’l Reg., Bd. Of
    Opticianry, 
    567 So. 2d 928
    , 934 (Fla. 1st DCA 1990). With regard to public notice,
    “notice must adequately inform as to what changes are proposed, and the actual
    change must conform substantially to the proposed changes in the notice.”
    Williams v. City of N. Miami, 
    213 So. 2d 5
    , 7 (Fla. 3d DCA 1968).
    In addition, even if the variances had been requested and considered, FPL
    presented no competent substantial evidence that the project could satisfy the
    environmental performance standards requirements of Chapter 33B. Variances
    must satisfy the same standards as conditional uses. See § 33B-31. Here, the West
    Preferred Corridor cannot satisfy the East Everglades Ordinance’s variance
    standards because the corridor would adversely impact the environment and the
    ecology of the land and its wildlife.
    Section 33B-28 states that a conditional use permit may be granted only if
    the applicant demonstrates that:
    (a) The conditional use is consistent with the purposes, goals, objectives and
    standards of the East Everglades Management Plan;…
    24
    The proposed use, singly or cumulatively, will not have any of the
    following irreversible effects on the ecological integrity of the East
    Everglades:
    (1) Harmful obstruction or undesirable alteration of the natural flow of
    water within the area of work.
    (2) Harmful or increased erosion, or adverse environmental impact
    resulting from changes in water quality or quantity.
    (3) Adverse impact upon wetland flora and fauna within adjacent parcels.
    (4) Adverse impact upon wetland flora and fauna within those portions of
    the subject property not proposed for development under the
    application…
    Under these restrictions, FPL’s application cannot be approved under the facts
    before us. For example, filling land and constructing structures in the proposed
    area would affect sheet flow and the hydrological resources of the area. FPL’s
    application proposed filling is up to 137 acres of the 296-acre right-of-way. Filling
    wetlands in this area would create barriers to water flow. The effect on the area’s
    hydrology would destroy the plant species that supplies the base for the food chain
    in the ecosystem and will adversely affect the endangered birds that nest and feed
    on the west side of the L-31N canal. In addition, these adverse impacts would also
    affect the County’s water supply.
    The roads that FPL would need to build for the construction of the project
    would affect the sheet flow in the area. Roads would have to be elevated in some
    areas so that vehicles could avoid the high water levels in this part of the East
    Everglades. The Siting Board permitted FPL to construct roads using culverts,
    which is a drain or channel crossing under a roadway. Section 33B-26 maintains
    25
    that a variance is needed to install elevated roads or culverts. FPL alleged that it
    could build a road with enough culverts to mitigate disrupting sheet flow west of
    the L-31N canal.
    The record on appeal indicates that FPL’s hydrology expert admitted that
    FPL had not conducted any analysis of the actual flow of water from one side of
    the transmission lines to the other. In addition, FPL’s experts did not enter the Park
    when they conducted their field visits. The structure pads and roads would change
    the local hydrology and ecology of the subject area. These changes would have an
    irreversible ecological effect on the Everglades that would result from “[h]armful
    obstruction or undesirable alteration of the natural flow of water.” § 33B-28(e)(1).
    In sum, the evidence was insufficient to support a variance to allow roads and
    culverts in Management Area 2A.
    With regard to FPL’s project’s impact to endangered birds, the Siting Board
    stated that “there will be no adverse impacts on avian species.” However, the
    record supports the opposite – that the endangered avian species would be greatly
    impacted. Filling wetlands in the manner proposed by FPL’s project, for example,
    would irreversibly affect endangered species in the subject area. The East
    Everglades wetlands are home to a number of federally-listed endangered species.
    Two of these species, the wood stork and the snail kite, nest and forage for food
    very close to or in the West Preferred Corridor. Filling wetlands in the area would
    26
    destroy the foraging habitat of these birds. The FPL’s proposed roads and structure
    pads have side slopes not suitable for producing food sources. The fill would
    change the microclimate in the area, rendering the area less suitable for apple
    snails, which snail kites feed almost exclusively on and other food sources for the
    wood stork. In addition, snail kites nest in woody vegetation, and FPL removes
    woody vegetation under power lines. FPL submitted no competent substantial
    evidence that the approved conditions of certification would adequately address the
    risk to these endangered birds.
    There is also risk that the birds will collide with the transmission poles and
    lines proposed by FPL, particularly young birds that have not yet learned how to
    avoid obstacles. There is no competent substantial evidence that the proposed
    facilities will comply with the County’s East Everglades Ordinance. The
    conditions in the Order do not address the loss of foraging or the potential loss of
    protected birds. Furthermore, the Order approves mitigation techniques such as
    perch discouragers and flight diverters so birds can identify and avoid poles and
    wires. This finding was not supported by competent substantial evidence because it
    fails to satisfy the variance criteria that the proposed use not have an “irreversible
    effect[] on the ecological integrity of the East Everglades” that would result from
    “adverse impact upon wetland flora and fauna”. 33B-28(e)(3),(4). The mitigation
    27
    technique presumes that some of the species are going to die. And that simply is
    not the standard under chapter 33B.
    Conclusion
    We therefore reverse the Final Order and remand to the Siting Board for
    further review consistent with local developmental regulations, comprehensive
    plans and the applicable environmental regulations, as discussed in this opinion.
    Reversed and remanded.
    28
    

Document Info

Docket Number: 14-1467 & 14-1466 & 14-1465 & 14-1451

Citation Numbers: 208 So. 3d 111, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20080, 2016 Fla. App. LEXIS 5953

Judges: Lagoa, Emas, Fernandez

Filed Date: 4/20/2016

Precedential Status: Precedential

Modified Date: 10/19/2024