FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ ( 2023 )


Menu:
  •        Third District Court of Appeal
    State of Florida
    Opinion filed March 22, 2023.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D22-181
    Lower Tribunal No. 17-22854
    ________________
    Florida Power & Light Company,
    Appellant,
    vs.
    Heydi Velez, et al.,
    Appellees.
    An Appeal from a non-final order from the Circuit Court for Miami-Dade
    County, David C. Miller, Judge.
    Squire Patton Boggs (US), LLP, Alvin B. Davis and Digna B. French;
    Joseph Ianno, Jr. (Juno Beach); Boies, Schiller & Flexner, LLP, Stuart H.
    Singer, Sashi C. Bach, and Pascual Oliu (Ft. Lauderdale), for appellant.
    Armas Bertran Zincone and J. Alfredo Armas; MSP Recovery Law
    Firm, John H. Ruiz and Alexis Fernandez; Acosta Law Firm, Julio C. Acosta
    and Simeon Genadiev; Dorta Law and Gonzalo R. Dorta, for appellees.
    Before FERNANDEZ, C.J., and LINDSEY, and HENDON, JJ.
    FERNANDEZ, C.J.
    Florida Power & Light Company (“FPL”) appeals the trial court’s non-
    final order certifying a class of FPL customers who sued FPL for breach of
    contract and gross negligence after Hurricane Irma. Because the trial court
    correctly determined that plaintiffs satisfied the elements necessary to
    establish class treatment of their claims against FPL under Florida Rule of
    Civil Procedure 1.220(b)(3), we affirm.
    FACTS AND PROCEDURAL BACKGROUND
    In 2005, FPL filed a base rate proceeding before the Public Service
    Commission (“PSC”). The parties reached a Settlement Agreement whereby
    FPL would be allowed to recover storm restoration costs and replenish its
    Storm-Recovery Reserve through the monthly storm surcharge.
    Thereafter, FPL customers were affected by Hurricanes Dennis,
    Katrina, Rita, and Wilma. FPL petitioned the PSC to approve the issuance
    of storm recovery bonds pursuant to section 366.8260, Florida Statutes
    (2005). The bonds would allow FPL to recover over $213 million and $815
    million for 2004 and 2005 storm costs; replenish its storm-recovery reserve
    to a level of approximately $650 million; and recover interest incurred
    through the bond issuance date and bond issuance costs of $23 million. As
    a result of the bonds, FPL customers would have to pay a monthly storm
    2
    surcharge. In return, FPL was to improve and strengthen its facilities for
    future storms, remove decaying utility poles, and remove vegetation that was
    making contact with local power lines.
    During hearings the PSC scheduled on the bond issue, FPL stated the
    storm charge would be used for, among other things, restoring FPL’s
    facilities to their pre-storm condition; repairing and replacing poles that were
    leaning or were braced during the initial restoration stage; replacing lightning
    arrestors; repairing or replacing capacitor banks; and strengthening system
    infrastructure. FPL’s Storm Secure Plan further would adopt the National
    Electric Safety Code (“NESC”) to improve FPL’s system infrastructure to
    withstand extreme wind conditions. The PSC approved the order and the
    issuance of the storm-recovery bonds in the amount up to $708 million.
    Later, in 2012, FPL petitioned for a permanent increase in base rates
    and charges. It requested a base rate increase of $528 million. A Settlement
    Agreement was reached, and the PSC gave FPL a revenue increase of $378
    million effective January 1, 2013.
    In 2016, FPL requested another base rate increase. FPL's request was
    intended to "reduce outages and enable FPL to restore power for customers
    and help local communities recover more quickly when severe weather
    strikes." The PSC authorized a revenue increase of $400 million effective
    3
    January 1, 2017. Also in 2016, FPL filed a petition seeking to implement a
    storm surcharge to recover $318.5 million for Hurricane Matthew restoration
    costs and to replenish its Storm-Recovery Reserve. The PSC granted FPL's
    2017 storm surcharge on each customer’s monthly residential bill, beginning
    on March 1, 2017, which was to last for twelve months.
    On March 15, 2016, FPL filed its petition with the PSC for approval of
    FPL’s Storm Hardening Plan. FPL stated it would comply with NESC
    extreme wind loading (“EWL”) standards by hardening its system so that it
    would withstand winds of 145, 130, and 105 mph in the three different wind
    regions of the state.
    In September 2017, Hurricane Irma sideswiped Florida. Named class
    members Heydi Velez, Miriam Perez, Guillermo Patino-Hidalgo, Enrique
    Arguelles, Mercedes Sastre, Ruben N. Mendiola, Carlos M. Colina, Shalom
    Navarro, and Jose Zarruk (collectively, “plaintiffs”) were FPL customers
    whose power went out for an extended period after Hurricane Irma. As
    customers, they entered into a contract with FPL, the Tariff, for electrical
    services that set out the parties’ obligations. In the Tariff, FPL agreed to use
    “reasonable diligence at all times to provide continuous service and storm
    recovery activities.”
    4
    During Hurricane Irma, the very highest sustained wind recorded by
    the National Weather Service was 115 mph in Marco Island where the storm
    first made land fall. The highest gust recorded was 142 mph near Naples
    Airport. Although Irma did not approach any county east of Lake
    Okeechobee, over 75% of FPL customers in South Florida lost power for
    close to a week. In the western half of South Florida, over 90% of FPL
    customers lost power for over a week.
    On February 1, 2018, plaintiffs brought a class action lawsuit against
    FPL. They alleged one count for breach of contract seeking compensatory
    damages for FPL’s failure to comply with its contractual obligations to use
    reasonable diligence at all times to provide continuous service in accordance
    with FPL’s Tariff and industry standards. Plaintiffs alleged that each of the
    individual plaintiffs entered into a uniform contractual agreement with FPL
    for services (the Tariff), for which plaintiffs paid a monthly fee. They alleged
    each plaintiff was individually charged a surcharge for storm restoration and
    hardening activities, pursuant to section 366.8260, Florida Statutes (2017).
    Plaintiffs suffered consequential damages such as loss of food and incurred
    expenses, loss of income, loss of sleep, intense discomfort, and more.
    The Tariff specifically stated that FPL “will use reasonable diligence at
    all times to provide continuous service at the agreed nominal voltage” and
    5
    storm recovery activities. Plaintiffs claim that FPL failed to use reasonable
    diligence by failing to meet NESC standards and its own standards, and that
    as a result of FPL’s breaches, Florida residents suffered unnecessary and
    prolonged power outages from Hurricane Irma that sideswiped South
    Florida.
    In Count II for gross negligence, plaintiffs claimed FPL “acted with
    reckless, willful, and wanton disregard for plaintiffs in the gross negligent
    maintenance and management of its system infrastructure, storm
    organization, restoration plan, and outright failure to restore, replace, and
    better the distribution system and hazards posed by vegetation and trees
    close to power lines.” They alleged FPL became aware of this need after
    previous storms hit Florida and undertook a duty to strengthen its distribution
    system in anticipation of the next hurricane. Plaintiffs further alleged that FPL
    was grossly negligent in performing various actions such as in replacing
    outdated grids, decaying utility poles, and hardening its power grid after the
    prior storm; failing to clear vegetation from the vicinity of distribution facilities
    and equipment; failing to clear vegetation from all feeder circuits serving top
    critical infrastructures prior to the peak of hurricane season; and failing to
    replace defective equipment, including but limited to, company power poles,
    power lines, and transformers.
    6
    Thereafter, FPL moved to dismiss the action, which the trial court
    denied. FPL then petitioned this Court for a writ of prohibition to require the
    parties to take their dispute before the PSC. This Court denied the writ in
    Florida Power and Light Company v. Velez, 
    257 So. 3d 1176
     (Fla. 3d DCA
    2018). Thus, the matter returned to the trial court.
    Plaintiffs then proceeded with class discovery. Pursuant to a discovery
    settlement agreement the parties entered, FPL produced data regarding its
    hurricane readiness and performance delivery reports to the PSC. FPL also
    produced data relating to power outage assessments, diagnoses, causes,
    and repairs during and after Hurricane Irma.
    On October 18, 2021, plaintiffs filed their Motion for Entry of Class
    Certification Order. The plaintiffs moved to certify the following class:
    All persons and business owners who reside and are otherwise
    citizens of the state of Florida that entered into contractual
    agreement with FPL for electrical services, were charged a storm
    charge, experienced a power outage after Hurricane Irma, and
    suffered consequential damages, directly and proximately,
    because of FPL’s breach of contract and/or gross negligence.
    The trial court held a three-day evidentiary hearing on class
    certification and other issues in December 2021. Plaintiffs argued that the
    trial court should focus not on who would prevail on the issues raised related
    to the breach of contract or gross negligence counts, but rather whether the
    requirements of rule 1.220 were met. Plaintiffs contended that based on
    7
    FPL’s own structured data, FPL could identify exactly which customer lost
    power, at what address, when they lost power, and the reason why they lost
    power. At the end of the hearing on the third day, the trial court granted
    plaintiffs’ motion and certified the class. Thereafter, the trial court entered its
    detailed, twenty-four page “Order Granting Plaintiffs’ Motion for Class
    Certification.” FPL then appealed.
    DISCUSSION
    “A trial court’s order certifying a class is a non-final appealable order
    that is reviewed for an abuse of discretion.” Miami Auto. Retail, Inc. v.
    Baldwin, 
    97 So. 3d 846
    , 851 (Fla. 3d DCA 2012). This is because “‘the
    determination that a case meets the requirements of a class action is a
    factual finding,’ which falls within a trial court’s discretion.” Sosa v. Safeway
    Premium Fin. Co., 
    73 So. 3d 91
    , 103 (Fla. 2011). “[T]he appellate court must
    fully recognize the superior vantage point of the trial judge and should apply
    the ‘reasonableness’ test to determine whether the trial judge abused his
    discretion. If reasonable men could differ as to the propriety of the action
    taken by the trial court, then the action is not unreasonable and there can be
    no finding of an abuse of discretion.” Canakaris v. Canakaris, 
    382 So. 2d 1197
    , 1203 (Fla. 1980). “A trial court should resolve doubts with regard to
    8
    certification in favor of certification, especially in the early stages of litigation.”
    Sosa, 
    73 So. 3d at 105
    .
    FPL contends that plaintiffs did not meet their burden under Florida
    Rule of Civil Procedure 1.220(b)(3) because individual issues predominate
    in this case, and a class action is not manageable or superior to other forms
    of resolving this controversy. We find no merit in this argument.
    Parties seeking class certification have the burden of pleading and
    proving each element of Florida Rule of Civil Procedure 1.220(a) and one of
    the three requirements of Florida Rule of Civil Procedure 1.220(b). Terry L.
    Braun, P.A. v. Campbell, 
    827 So. 2d 261
    , 265 (Fla. 5th DCA 2002). Under
    Rule 1.220(a), the four prerequisites for class certification are numerosity,
    commonality, typicality, and adequate representation. Broin v. Philip Morris
    Cos., 
    641 So. 2d 888
     (Fla. 3d DCA 1994). FPL makes the general statement
    that plaintiffs have not satisfied the elements of Rule 1.220(a). However, it
    does not address this argument in its briefs. We have carefully reviewed the
    record and find no abuse of discretion in the trial court's determination that
    the class established the four elements under Rule 1.220(a). Love v. General
    Dev. Corp., 
    555 So. 2d 397
     (Fla. 3d DCA 1989).
    In addition to establishing numerosity, commonality, typicality, and
    adequacy of representation, plaintiffs must also demonstrate that the action
    9
    meets the criteria under at least one basis for class certification under Rule
    1.220(b). Here, plaintiffs sought class certification under rule 1.220(b)(3).
    This rule states:
    (b) Claims and Defenses Maintainable: A claim or defense may
    be maintained on behalf of a class if the court concludes that the
    prerequisites of subdivision (a) are satisfied, and that
    …
    (3) … the questions of law or fact common to the claim or defense
    of the representative party and the claim or defense of each
    member of the class predominate over any question of law or
    fact affecting only individual members of the class, and class
    representation is superior to other available methods for the fair
    and efficient adjudication of the controversy. …
    Thus, predominance and superiority must be shown. Freedom Life Ins. Co.
    of Am. v. Wallant, 
    891 So. 2d 1109
    , 1118 (Fla. 4th DCA 2004) (“For class
    certification to be appropriate under Rule 1.220(b)(3), ‘the issues in the class
    action that are subject to generalized proof, and thus applicable to the class
    as whole, must predominate over those issues that are subject only to
    individualized proof.’”).
    Plaintiffs must first establish that common questions of law and fact
    predominate over individual, plaintiff-specific issues. Fla. R. Civ. P.
    1.220(b)(3); Sosa, 
    73 So. 3d at 111
    . “Florida courts have held that common
    questions of fact predominate when the defendant acts toward the class
    members in a similar or common way.” Sosa, 
    73 So. 3d at 111
    . “The
    methodology employed by a trial court in determining whether class claims
    10
    predominate over individual claims involves a proof-based inquiry.” 
    Id. at 112
    . Thus, a class representative establishes predominance if “the class
    representative can prove his individual case and, by so doing, necessarily
    prove the cases for each of the other class members.” InPhyNet Contr.
    Servs. v. Soria, 
    33 So. 3d 766
    , 771 (Fla. 4th DCA 2010).
    Here, Rule 1.220(b)(3) certification was proper because even where
    some individualized issues of proof exist in a case, where an issue raised by
    a common contract provision predominates, “the better reasoned approach
    is to maintain the suit as a class action and, if required after further
    development of the issues, permit the lower court to create subclasses.”
    Paladino v. Am. Dental Plan, Inc., 
    697 So. 2d 897
    , 899 (Fla. 1st DCA 1997).
    Further, “[N]umerous courts have recognized that the presence of
    individualized damages issues does not prevent a finding that the common
    issues in the case predominate.” Allapattah Servs., Inc. v. Exxon Corp., 
    333 F.3d 1248
    , 1261 (11th Cir. 2003).
    The record supports the trial court’s conclusion that plaintiffs
    established that common questions of law and fact predominate over
    individual plaintiff issues. FPL’s Tariff is a form document, and FPL admitted
    it applies to all plaintiffs and class members. As previously discussed, FPL
    drafted the Tariff, and it was presented to its customers on a take it or leave
    11
    it basis. Plaintiffs and class members had no bargaining power in the drafting
    of the Tariff. The Tariff    also incorporates FPL’s “Service Standard” as
    previously discussed and incorporated the latest edition of the NESC. The
    Tariff further provides for the storm charge that plaintiffs referenced in their
    amended complaint. Plaintiffs claim that due to FPL’s breach of the Tariff,
    plaintiffs and class members experienced consequential damages.
    Predominance exists where common questions can be answered by
    use of computerized software systems. Roper v. Consurve, Inc., 
    578 F.2d 1106
    , 1113 (5th Cir. 1978) (“While it may be necessary to make individual
    fact determinations with respect to charges, if that question is reached, these
    will depend on objective criteria that can be organized by a computer,
    perhaps with some clerical assistance.”). As the trial court noted in its order,
    “It is well-settled in data-driven cases like this one, even if there are potential
    individualized determinations, that ‘the necessity of making individualized
    factual determinations does not defeat class certification if those
    determinations are susceptive to generalized proof like [business] records.’
    Minns v. Advanced Clinical Employment Staffing LLC, 
    2015 WL 3491505
    , at
    *8 (N.D. Cal. 2015) …”.
    The evidence showed that FPL uses “cause codes” among other data
    related to customer power outage, which the trial court noted would provide
    12
    the court with “a reasonable methodology for generalized proof of class-wide
    impact.” Thus, FPL’s conduct in determining the cause of power loss for each
    client is the same. In addition, the standard Tariff is the same one given to
    all customers. Thus, the evidence used to prove one of the named plaintiffs’
    breach of contract claims is the same evidence that will be used to prove the
    rest of the class members’ breach of contract claims. Accordingly, plaintiffs
    can use FPL’s data to prove FPL’s liability for the entire class. Regarding this
    predominance factor, the trial court further noted:
    FPL deploys “patrollers” and “forensic patrollers” in order to
    determine outage causes and restore power. FPL uses multiple
    data systems to track that information, makes outage information
    and restoration projections available to customers in real-time,
    draws conclusions from its data-rich systems, and reports outage
    causes (and makes its data available) to Florida’s Public Service
    Commission. It stands to reason that FPL has identified the
    cause of an outage where it has been able to turn the power back
    on. FPL, though, has now dedicated the bulk of its presentation
    to undermining the accuracy of its own records. The Court is
    unmoved by those efforts.
    FPL’s “very business model includes gathering and distilling
    information from a variety of sources in order to [determine the
    cause of outages].” . . . And, in general, “courts do not look
    favorably upon the argument that records a defendant treats as
    accurate for business purposes are not accurate enough to
    define a class.” (citations omitted). The Court finds that the
    evidence supports Plaintiffs’ theory and methodology for utilizing
    FPL’s business records and data systems for determining liability
    on a class-wide basis.
    13
    Similarly, regarding the gross negligence claim, the court found that
    “these issues are common to Plaintiffs and all putative class members and
    will be resolved by common proof that does not vary from customer to
    customer based on FPL’s course of conduct to utilize the same data systems
    and methodologies for all 5.6 million customers.” The court specifically found
    from the information presented to it by FPL that FPL “blurred” the difference
    between how it collected data on customer outages on a “blue-sky day” (non-
    hurricane days) as opposed to how it collected data on customer outages
    during a hurricane. On a “blue-sky” day, the “cause code” pertaining to a
    power outage for a customer was the actual cause for a customer’s power
    outage. However, FPL trained its employees to select the “cause code” of
    “hurricane” as the actual cause of a customer’s power outage following a
    hurricane like Hurricane Irma. Thus, the trial court found that whether FPL
    adopted or did not adopt these procedures/training instructions evidenced a
    conscious disregard of an imminent or “clear and present danger.” The court
    stated that “a jury could find that FPL’s conscious decision to categorically
    subject information about outages following a storm to a different standard
    than information about outages on a blue-sky day, and inherently invites
    breaches of the type that are alleged above to be grossly negligent.” The
    court noted that a jury could also find that FPL understood the risks
    14
    associated with its manner of documenting “causes” of customer power
    outages after a storm, and its integration or lack of integration with other FPL
    databases and that because FPL was aware, its common course of
    conducted evinced a conscious disregard of an imminent or “clear and
    present danger.” Thus, the court correctly determined that common
    questions of law and fact predominated over individual questions in this
    case.
    In addition, contrary to FPL’s position, the superiority requirement of
    Rule 1.220(b)(3) was also met in this case. Under Rule 1.220(b)(3), the court
    examines whether class representation is superior to other available
    methods for the fair and efficient adjudication of the controversy. “Three
    factors for courts to consider when deciding whether a class action is the
    superior method of adjudicating a controversy are (1) whether a class action
    would provide the class members with the only economically viable remedy;
    (2) whether there is a likelihood that the individual claims are large enough
    to justify the expense of separate litigation; and (3) whether a class action
    cause of action is manageable.” Sosa, 
    73 So. 3d at 116
    .
    Here, the trial court was correct in concluding that class representation
    was superior to other methods of adjudication. The court accurately noted
    that there were potentially millions of prospective class members and that
    15
    their small, individual economic claims were not large enough to justify each
    individual plaintiff filing a separate action. Thus, the court found a class
    action would be the “most economically feasible remedy given the potential
    individual damage recovery for each class member.” In addition, a class
    action recovery system in this case would be a more manageable and
    efficient use of judicial resources than if each plaintiff was required to file
    their own individual claim against FPL. The trial court stated in its order that
    MSP Recovery LLC’s (class action plaintiff trial counsel) chief information
    officer testified in his deposition that through MSP Recovery, LLC, plaintiffs
    would have the ability to assess FPL’s data regarding this class action. The
    chief information officer reviewed the documents produced by FPL and
    testified that FPL’s data contain outage tickets and other information used to
    calculate metrics and pinpoint the cause of a customer’s power outage.
    Consequently, the trial court was correct in determining that plaintiffs
    presented evidence that a class action was superior to other available
    methods for resolving this controversy.
    CONCLUSION
    The trial court correctly concluded that in this case, common questions
    of law and fact predominate over individual questions, and that class
    16
    representation is superior to other methods of adjudication. Accordingly,
    finding no abuse of discretion in the trial court’s decision to certify the class
    under Rule 1.220(b)(3), we affirm the trial court’s “Order Granting Plaintiffs’
    Motion for Class Certification.”
    Affirmed.
    17