MAURO LEDER AND PATRICIA LEDER v. IMBURGIA CONSTRUCTION SERVICES, INC. ( 2021 )


Menu:
  •       Third District Court of Appeal
    State of Florida
    Opinion filed July 28, 2021.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D21-218
    Lower Tribunal Nos. 20-43 CC, 20-203 AP
    ________________
    Mauro Leder and Patricia Leder,
    Appellants,
    vs.
    Imburgia Construction Services, Inc.,
    Appellee.
    An Appeal from the County Court for Miami-Dade County, Myriam
    Lehr, Judge.
    Gary B. Goldman, for appellants.
    A. Platon Alexandrakis, for appellee.
    Before LOGUE, SCALES, and HENDON, JJ.
    HENDON, J.
    The plaintiffs below, Mauro Leder and Patricia Leder (collectively,
    “Owners”), appeal from a county court order granting Imburgia Construction
    Services, Inc.’s (“Contractor”) motion to dismiss the Owners’ amended
    complaint. For the reasons that follow, we reverse the order under review
    and remand with directions.
    The Owners and the Contractor entered into a written construction
    contract for renovations to the Owners’ home. The contract executed by
    the parties provides for arbitration as the method for binding dispute
    resolution. However, prior to arbitration, the parties are required to submit
    any claim, which includes disputes related to the contract, to the Initial
    Decision Maker, who the parties agreed would be the Miami Shores Village
    Building Department Official. A claim must be initiated within twenty-one
    days of the occurrence of the event giving rise to the claim.             Pending
    resolution of a claim, the Contractor is required to proceed diligently with
    the performance of the contract, and the Owners are required to make
    payments in accordance with the contract. The initial decision by the Initial
    Decision Maker is a condition precedent to mediation, and mediation is a
    condition precedent to arbitration. The parties’ contract reflects that the
    parties’ right to proceed to binding dispute resolution—arbitration—is
    waived if a certain condition precedent to arbitration is not followed.
    In January 2020, the Owners initiated an action against the
    2
    Contractor, and thereafter, filed an amended complaint, seeking monetary
    damages. In the amended complaint, the Owners asserted that on June
    25, 2019, the Contractor presented a fifth change order for structural work,
    which the Owners refused to execute, questioning both the necessity and
    the price. The Owners alleged that the Contractor then abandoned the job
    and failed to file a claim with the Initial Decision Maker, thereby waiving any
    right to proceed under the contract’s dispute resolution procedures. The
    Owners further alleged that the Contractor left unpaid subcontractor bills,
    and the amounts paid by the Owners exceeded the value of the work
    performed by the Contractor.
    The Contractor moved to dismiss the amended complaint, without
    specifically seeking to compel arbitration. The Contractor argued that the
    contract stipulates for arbitration, but the Owners filed the lawsuit in
    contravention of the contract, thereby failing to adhere to the dispute
    resolution provisions.    Despite not specifically seeking arbitration, the
    Contractor cited to section 682.181(1) of the Florida Statutes, which
    provides that “[a] court of this state having jurisdiction over the controversy
    and the parties may enforce an agreement to arbitrate.”           Further, the
    Contractor set forth the factors a court is to consider when ruling on a
    motion to compel arbitration—(1) whether a valid agreement to arbitrate
    3
    exists; (2) whether an arbitrable issue exists; and (3) whether the right to
    arbitration was waived, and asserted that “there is a valid written
    agreement with arbitrable issues and the Defendant has not waived its right
    to arbitrate.”
    Following a hearing, the trial court granted the Contractor’s motion to
    dismiss the amended complaint.       In its order, the trial court stated as
    follows:
    THIS COURT finds that the parties entered into a contract with
    a valid Binding Dispute Resolution Clause, wherein both parties
    agreed and elected to resolve disputes through Arbitration.
    Plaintiff failed to comply with any of the Dispute Resolution
    provisions. The Court further finds that Plaintiff’s claim arises
    out of the parties’ agreement and therefore Plaintiff’s Amended
    Complaint is improper, and its argument of waiver has no merit
    since Defendant has not asserted any claims for damages.
    The trial court’s dismissal of the amended complaint left the Owners
    without a remedy for the Contractor’s alleged wrongdoings. The Owners’
    timely appeal followed.
    “[W]hether a party has waived the right to arbitrate is a question of
    fact, reviewed on appeal for competent, substantial evidence to support the
    lower’s court’s findings.” Green Tree Servicing, LLC v. McLeod, 
    15 So. 3d 682
    , 686 (Fla. 2d DCA 2009). However, “the standard of review applicable
    to the trial court’s construction of the arbitration provision, and to its
    4
    application of the law to the facts found, is de novo.” 
    Id. at 686-87
    .
    The Owners contend that the arbitration provision in the contract is
    unenforceable as it was waived. We agree.
    Although a dispute arose between the parties, neither party initiated a
    claim with the Initial Decision Maker.      Under the contract, a condition
    precedent to mediation is filing a claim with the Initial Decision Maker, and
    a condition precedent to arbitration is demanding mediation of the Initial
    Decision Maker’s decision.     In this case, either party had the ability to
    initiate a claim with the Initial Decision Maker because the dispute relating
    to the fifth change order affected both parties and was related to the
    construction contract. However, neither party elected to do so.
    As recognized by the Contractor in its motion to dismiss the amended
    complaint, “[i]n determining whether a dispute is subject to arbitration,
    courts consider at least three issues: (1) whether a valid written agreement
    to arbitrate exists: (2) whether an arbitrable issue exists; and (3) whether
    the right to arbitration was waived.” Green Tree, 
    15 So. 3d at 686
     (quoting
    Stacy David, Inc. v. Consuegra, 
    845 So. 2d 303
    , 306 (Fla. 2d DCA 2003)).
    In the instant case, there is no dispute that there was a valid written
    agreement to arbitrate and that there was an arbitrable issue. The parties,
    however, disagree as to whether the Contractor waived its contractual right
    5
    to arbitrate.
    “[T]he question of whether there has been waiver in the arbitration
    agreement context should be analyzed in much the same way as in any
    other contractual context. The essential question is whether, under the
    totality of the circumstances, the defaulting party has acted inconsistently
    with the arbitration right.” Green Tree, 
    15 So. 3d at 687
     (quoting Nat’l
    Found. for Cancer Rsch. v. A.G. Edwards & Sons, Inc., 
    821 F.2d 772
    , 774
    (D.C. Cir. 1987)). Waiver of an arbitration clause “may be predicated on
    both pre- and post-suit actions in tandem.” Bland v. Green Acres Grp.,
    L.L.C., 
    12 So. 3d 822
     (Fla. 4th DCA 2009). The “prosecution or defense of
    a lawsuit on issues subject to arbitration may constitute a waiver.” Green
    Tree, 
    15 So. 3d at 687
     (quoting Seville Condo. #1, Inc. v. Clearwater Dev.
    Corp., 
    340 So. 2d 1243
    , 1245 (Fla. 2d DCA 1976)). Moreover, “a party
    may waive his or her right to arbitration by filing a lawsuit without seeking
    arbitration; by filing an answer to a pleading seeking relief without raising
    the right to arbitration; and by moving for summary judgment.” Green Tree,
    
    15 So. 3d at 687
     (internal citations omitted).
    In the instant case, the Contractor waived its right to arbitrate based
    on its pre-litigation action and the language in the parties’ contract. As
    stated above, prior to binding arbitration, there are other steps that the
    6
    parties to the contract must take to preserve its contractual right to
    arbitrate—submitting a claim to the Initial Decision Maker, and thereafter,
    pursuing mediation. Neither party utilized this procedure to resolve their
    dispute relating to the fifth change order, including taking the first step—
    initiating a claim with the Initial Decision Maker. As such, we conclude that
    the parties waived their right to arbitrate under the terms of their contract.
    Therefore, we reverse the order granting the Contractor’s motion to dismiss
    the amended complaint and, on remand, the trial court is instructed to order
    the Contractor to file an answer to the Owners’ amended complaint.
    Reversed and remanded with instructions.
    7