Gwinnett County v. McManus ( 2014 )


Menu:
  • FINAL COPY
    
    294 Ga. 702
    S13A1878. GWINNETT COUNTY v. MCMANUS et al.
    BLACKWELL, Justice.
    In this equity case, Gwinnett County appeals from an interlocutory
    injunction against the County and in favor of Gerard and Jewell McManus.
    Pending further proceedings in this case, the injunction prohibits the County
    from using “artificial means” to increase the water and sediment that runs off a
    parcel of real property owned by the County and onto an adjacent parcel owned
    by the McManuses. The County contends that the trial court abused its
    discretion when it entered the injunction, but we see no error and affirm.
    Viewed in the light most favorable to the findings of the trial court, the
    record shows that the County is constructing a roadway upon its parcel, a
    construction project that commenced in 2009. The County claims a public
    drainage easement across the rear of the McManus property, and it built a
    temporary sediment pond on the County property to drain water and sediment
    from the construction project and to divert that water and sediment into the
    drainage easement. But soon after the pond was built, heavy rains caused the
    water and sediment runoff to exceed the bounds of the easement, depositing
    sediment throughout the McManus property and causing significant damage. In
    2010, the McManuses sued the County, and they sought an interlocutory
    injunction to keep their property from further damage during the pendency of
    the suit. The next year, the County built a permanent detention pond on its
    property, which would, the County claimed, ensure that the runoff into the
    easement would not exceed the runoff that predated the construction project.
    Although disputed by the County, there is some evidence that shows that, even
    after the construction of the permanent detention pond, the runoff was not
    contained entirely within the easement, that the runoff overran the bounds of the
    easement “every time it rains,” and that portions of the McManus property
    “nowhere near” the easement — such as the front yard of the McManus home
    — continued to flood occasionally as a result of the road construction project.
    Upon this record, the trial court found that the County had exceeded the bounds
    of the easement and continued to divert water and sediment by artificial means
    onto other portions of the McManus property. As with the other pertinent
    findings of the trial court, this finding has some support in the evidentiary
    record, and we cannot say it is clearly erroneous. See OCGA § 9-11-52 (a) (“In
    ruling on interlocutory injunctions . . . [f]indings shall not be set aside unless
    2
    clearly erroneous, and due regard shall be given to the opportunity of the trial
    court to judge the credibility of the witnesses.”). See also Menzies v. Hall, 
    281 Ga. 223
    , 225 (2) (637 SE2d 415) (2006). From these findings, the trial court
    entered its interlocutory injunction, ordering the County to cease “causing
    increased water flow, sedimentation, and runoff onto the [McManus property]”
    by artificial means and directing the County to undertake 26 interim remedial
    measures to halt the excessive runoff pending further proceedings.
    The County appears to primarily object to the injunction on the ground
    that it effectively prohibits the County from letting water and sediment run off
    even through the public drainage easement that runs across the rear of the
    McManus property.1 But we do not understand the injunction to do so. The
    1
    Similarly, the County claims that the trial court abused its discretion because —
    according to the County — the permanent detention pond that it constructed had been
    functioning properly and because implementation of the action items required by the order
    would be prohibitively expensive and would essentially provide the M cManuses with final
    and not merely temporary relief. But, as noted previously, whether the permanent detention
    pond had satisfactorily contained the runoff within the confines of the County’s easement
    was disputed at the hearing, and evidence presented by the McManuses supports the trial
    court’s conclusion that the permanent detention pond did not, in fact, fix the problem.
    Although it is true that, when granting an injunction, a court should not impose “any greater
    restriction (burden) than is necessary to protect plaintiff from the injury of which he
    complains[,]” 
    Menzies, 281 Ga. at 225
    (2) (citation and punctuation omitted), the County
    presented no evidence at the hearing about the cost of implementing any solutions to the
    problem, about any viable alternatives to the solution set forth in the order, or about whether,
    as it now claims, compliance with the order would make meaningless the results of any trial
    3
    injunction explicitly acknowledges the existence of the easement and orders the
    County merely to stop “increased” runoff, a term that most reasonably is
    understood in context to refer to the increase in water and sediment runoff that
    repeatedly has exceeded the bounds of the easement. And nowhere in the order
    did the trial court say that the County was prohibited altogether from using the
    easement or that it must stop all runoff onto the McManus property. Nor does
    the record contain any evidence that completion of the 26 interim remedial
    measures would absolutely prevent the County from using the easement. In fact,
    these remedial measures seem to have been intended to prevent the County from
    artificially diverting water onto the McManus property beyond the bounds of the
    easement, inasmuch as several of the provisions for such measures specifically
    concern portions of the McManus property that the court had found to be
    outside the bounds of the easement, and several provisions reference the
    existence of the easement itself, including one that requires the County to
    modify the drainage ponds to “meet the confines of the twenty-foot wide
    because of the cost and permanence of the trial court’s “temporary” solution. As a result,
    there are no findings by the trial court on these issues for us to review. Compare Columbia
    County v. Doolittle, 
    270 Ga. 490
    , 493 (3) (512 SE2d 236) (1999) (finding that injunctive
    relief was overbroad where evidence presented at trial showed that compliance with proposed
    relief was impossible).
    4
    drainage easement in a defined area inside the [McManus property].” To the
    extent that the County wishes to present evidence that satisfying the provisions
    for interim remedial measures effectively would require the County to abandon
    the use of the easement, the County still could do so. After all, the injunction
    provides that it is effective only “until the conclusion of trial of this case or until
    further order of the Court,” and even if it did not so provide, the County
    nevertheless would be entitled to petition the trial court to clarify or modify the
    injunction, as with any other interlocutory injunction. See Opatut v. Guest Pond
    Club, 
    254 Ga. 258
    , 259 (5) (327 SE2d 487) (1985).2
    Similarly, while the County claims that the injunction limits its use of the
    public drainage easement “to a certain volume of water,” nowhere in the order
    is any “certain volume” limit imposed. Although the order restrains the County
    from “causing increased water flow, sedimentation, and runoff onto the
    [McManus property] by way of waterflow caused by artificial means,” this
    restriction does not impose a specific volume restriction, and the trial court
    2
    Indeed, the record shows that the County filed a motion to clarify the order, as well
    as to suspend the order pending this appeal. And while the County claims that the trial court
    denied its motion to clarify the order, the record shows only that the trial court granted the
    County’s motion to suspend.
    5
    specifically declined to “distinguish between the flow of water and the quantity,
    or rate, of water” permitted by the easement. Instead, the trial court found that
    the County had a right to use a 20-foot easement across the rear of the McManus
    property, but that the County had exceeded the scope of the easement by
    increasing the runoff by artificial means to the point that it flowed beyond the
    bounds of the easement and across other portions of the McManus property. The
    County did not present any evidence that it could increase the volume of water
    that flowed across the easement through a pipe or some other improvement that
    would keep the increased flow contained within the easement, and as noted
    previously, the record supports the findings of the trial court that the increased
    runoff from the County property repeatedly exceeded the scope of the easement.
    “[I]t was within the discretion of the trial court to determine whether and how
    to require” the County to keep the runoff within the bounds of the easement
    pending further proceedings, and “the trial court did not clearly err when it
    determined that an adequate cure for the run-off problem required . . .
    implementation of [the interim remedial measures contained in the order].”
    
    Menzies, 281 Ga. at 225
    -226 (1)-(2).
    6
    Having reviewed the record and the arguments of the parties, we see no
    abuse of the substantial discretion of the trial court to award interlocutory
    injunctive relief to keep the McManuses from further harm pending the
    resolution of this lawsuit. Accordingly, we affirm the judgment below.
    Judgment affirmed. All the Justices concur.
    Decided March 3, 2014.
    Equity. Gwinnett Superior Court. Before Judge Hamil.
    Michael V. Stephens II, Michael P. Ludwiczak, for appellant.
    Anderson, Tate & Carr, Robert M. Reeves, Marian C. Adeimy, for
    appellees.
    7
    

Document Info

Docket Number: S13A1878

Judges: Blackwell

Filed Date: 3/3/2014

Precedential Status: Precedential

Modified Date: 11/7/2024