CITY OF DUNWOODY v. DISCOVERY PRACTICE MANAGEMENT, INC. Et Al. ( 2016 )


Menu:
  •                               SECOND DIVISION
    BARNES, P. J.,
    BOGGS and RICKMAN, JJ.
    NOTICE: Motions for reconsideration must be
    physically received in our clerk’s office within ten
    days of the date of decision to be deemed timely filed.
    http://www.gaappeals.us/rules
    July 14, 2016
    In the Court of Appeals of Georgia
    A16A0058. CITY OF DUNWOODY v. DISCOVERY PRACTICE RI-002
    MANAGEMENT, INC. et al.
    RICKMAN, Judge.
    This court granted a discretionary appeal application by the City of Dunwoody
    (the “City”) from the judgment of the DeKalb County Superior Court reversing the
    decision of the City of Dunwoody Zoning Board of Appeals (the “ZBA”) in a dispute
    regarding whether the proposed use of property controlled by Discovery Practice
    Management, Inc., d/b/a Center For Discovery and DV Dunwoody, LLC (hereinafter
    collectively “Discovery”) fit within the existing zoning classification of the district
    where the property is located. The ZBA determined that the City’s earlier
    classification of Discovery’s proposed use of the property as a family personal care
    home was erroneous. But the superior court reversed the ZBA’s determination, and
    thus, reinstated the classification. The City appeals from this superior court order,
    contending that the superior court erred by: (1) denying its motion to dismiss a
    renewed petition for certiorari Discovery had filed pursuant to OCGA §§ 5-4-3 and
    9-2-61 (a); and (2) reversing the ZBA’s decision. For the followings reasons, we
    affirm the judgment.
    1. The City contends that the renewal provisions of OCGA § 9-2-61 (a) did not
    entitle Discovery to dismiss a timely filed petition for writ of certiorari, then renew
    the petition after the expiration of the applicable limitation period.
    Pursuant to OCGA § 9-2-61 (a), a case commenced within the
    applicable limitation period may be dismissed and recommenced within
    six months even if the limitation period has expired. The privilege of
    dismissal and renewal under OCGA § 9-2-61 does not apply to a case
    dismissed on the merits or to a case which was void when dismissed, but
    it does apply if the dismissed case was merely voidable. A suit is also
    void and incapable of renewal under OCGA § 9-2-61 (a) if there has
    been a judicial determination that dismissal is authorized . . . It is settled
    that the renewal provisions of OCGA § 9-2-61 apply to certiorari cases
    brought pursuant to OCGA § 5-4-1 et seq.
    (Citations and punctuation omitted.) Buckler v. DeKalb County, 
    290 Ga. App. 190
    ,
    191 (1) (659 SE2d 398) (2008).
    2
    Discovery filed its first petition for writ of certiorari in the superior court on
    July 10, 2014, within the 30-day limitation period of OCGA § 5-4-6 (a). Pursuant to
    OCGA § 5-4-6 (b), the petition and writ were required to be personally served upon
    the ZBA, as respondent-in-certiorari.1 The parties did not dispute that service of the
    petition and writ were perfected on the City (the opposing party or “defendant-in-
    certiorari”). However, the City disputed service on the ZBA, and in September 2014,
    Discovery voluntarily dismissed the action. At the time of dismissal, no judicial
    determination had been entered on the petition.
    In October 2014, Discovery re-filed the petition for writ of certiorari, citing
    OCGA §§ 5-4-32 and 9-2-61 (a). Subsequently, the City filed a motion to dismiss the
    1
    See Gornto v. City of Brunswick, 
    119 Ga. App. 673
     (168 SE2d 323) (1969)
    (construing statute requiring service on respondent-in-certiorari to mean personal
    service).
    2
    OCGA § 5-4-3 provides
    When either party in any case in any inferior judicatory or before any
    person exercising judicial powers is dissatisfied with the decision or
    judgment in the case, the party may apply for and obtain a writ of
    certiorari by petition to the superior court for the county in which the
    case was tried, in which petition he shall plainly and distinctly set forth
    the errors complained of. On the filing of the petition in the office of the
    clerk of the superior court, with the sanction of the appropriate judge
    endorsed thereon, together with the bond or affidavit, as provided in
    3
    re-filed petition on the basis that it was void ab initio because the original petition and
    writ were never properly served on ZBA pursuant to OCGA § 5-4-6 (b) before the
    action was dismissed and that, therefore, the dismissed action was void and not
    subject to renewal under OCGA § 9-2-61 (a). Discovery filed a response to the
    motion to dismiss, arguing that the City failed to meet its burden of showing improper
    service of the original petition and writ because, inter alia, personal service was not
    required for renewal, and that even assuming personal service was required,
    Discovery had shown good cause to excuse such service.
    The trial court determined that the requisite personal service pursuant to OCGA
    § 5-4-6 was not perfected upon the ZBA,3 but that the lack of personal service as to
    ZBA did not render the petition void and, thus, a bar to renewal. For the reasons
    explained below, we hold that lack of service on ZBA, the respondent, did not make
    the original action void.
    Code Section 5-4-5, it shall be the duty of the clerk to issue a writ of
    certiorari, directed to the tribunal or person whose decision or judgment
    is the subject matter of complaint, requiring the tribunal or person to
    certify and send up all the proceedings in the case to the superior court,
    as directed in the writ of certiorari.
    3
    Discovery did not file a cross-appeal as to this determination.
    4
    [T]he failure to deliver, within the time required by the statute, the
    petition and writ to the officer whose decision is under review . . . is a
    mere irregularity which can be cured either by a waiver by the officer
    himself, evidenced by the filing of his answer, or by an extension of
    time by the judge of the superior court.
    Bass v. Milledgeville, 
    121 Ga. 151
    , 153 (
    48 SE 919
    ) (1904); see Hudson v. Watkins,
    
    225 Ga. App. 455
    , 456 (1) (484 SE2d 24) (1997). Accordingly, failure to comply with
    service requirements regarding the officer whose decision is under review “will not
    render the proceeding void,” Bass, 121 Ga. at 153, but instead, voidable. Given that
    a case is capable of renewal under OCGA § 9-2-61 (a) if when the case was dismissed
    it was merely voidable, OCGA § 9-2-61 (a) applies in the instant case, and the
    superior court properly denied the City’s motion to dismiss Discovery’s renewed
    petition.
    The City argues that pursuant to Fisher, 
    212 Ga. App. 635
     (442 SE2d 762)
    (1994), Discovery’s failure to comply with service requirements of OCGA § 5-4-6
    rendered the original petition void unless notice was given to the ZBA pursuant to
    OCGA § 5-4-3 (by the clerk of court), and that because no notice pursuant to OCGA
    § 5-4-3 was given in the instant case, the petition was void. We disagree. In Fisher,
    service of the original petition was not perfected upon the tribunal whose decision
    5
    was under review, and this Court held that the petition, although properly dismissed
    for lack of service under OCGA § 5-4-6 (b), could be renewed pursuant to OCGA §
    9-2-61. Fisher, 212 Ga. App. at 636-637. Although this Court acknowledged that the
    tribunal had received notice of the petition pursuant to a procedure authorized by
    statute (OCGA § 5-4-3), this Court did not hold that such notification was a
    prerequisite to renewal. Id. Nothing in Fisher contradicts the Bass rule. Therefore, the
    trial court properly denied the City’s motion to dismiss Discovery’s renewed
    petition.4
    2. The City contends that the superior court erred by, among other things,
    reversing the ZBA’s decision by ruling that neighbors were not entitled to notice of
    the city planner’s classification decision and by ruling that the ZBA wrongly
    construed the city zoning ordinance to require notice.
    The record shows the following. Discovery sought to open a six bed home for
    the treatment of adolescents with eating disorders. In January 2014, the City of
    Dunwoody planner/director of sustainability (“city planner”) issued a letter
    4
    To the extent that the trial court misconstrued the holding in Fisher, we will
    affirm its ruling if it is right for any reason. Reed v. Reed, 
    295 Ga. 574
    , 578 (2) (761
    SE2d 326) (2014) (“We may affirm the judgment of a lower court so long as it is right
    for any reason.”) (citation and punctuation omitted).
    6
    (“confirmation”) to Discovery, classifying Discovery’s stated proposed use for the
    subject property as a family personal care home, and informing Discovery that such
    was a permitted “use by right” in the single-family residential zoning district in which
    the property was located.5 In April 2014, some nearby residents who had found out
    (in March 2014 ) about the use to which the property (an existing home ) was going
    to be put, filed an application for administrative appeal with the ZBA. The ZBA voted
    to accept the appeal and held hearings on the matter. The neighbors challenged the
    classification of the land use as a personal care home, arguing that the city planner
    was not informed of material facts when she made the classification decision and that
    Discovery’s intended use for the property was as a medical treatment facility, which
    was not a permitted use.
    The ZBA sustained the appeal, determining that the “staff decision to classify
    this as a personal care home was in error . . . [o]r incorrect.” Discovery thereafter
    appealed ZBA’s decision to the superior court, which ruled that, among other things,
    the neighbors’ appeal to the ZBA was untimely and the ZBA erred as a matter of law
    5
    At the time, the City of Dunwoody did not have a community development
    director, and the city planner issued the letter pursuant to authority previously
    delegated to her to act as community development director.
    7
    by accepting the appeal and reading into the ordinance a notice requirement that
    otherwise did not exist.
    “We review the construction of a zoning ordinance under a de novo standard.”
    (Citations omitted.) Burton v. Glynn County, 
    297 Ga. 544
    , 546 (1) (776 SE2d 179)
    (2015). The scope of review of the superior court is “limited to all errors of law and
    determination as to whether the judgment or ruling below was sustained by
    substantial evidence.” OCGA § 5-4-12 (b). “[T]he substantial-evidence standard is
    effectively the same as the any-evidence standard.” (Citation and punctuation
    omitted.) City of Atlanta Govt. v. Smith, 
    228 Ga. App. 864
    , 865 (1) (493 SE2d 51)
    (1997).
    Pursuant to Section 27-458 of the Dunwoody Zoning Ordinance in effect at the
    time of the appeal to the ZBA, the neighbors – assuming they had standing6 – had 30
    days from the date of the city planner’s decision to appeal the decision, and the
    ordinance did not require that notice of the decision be given to neighboring property
    6
    Section 27-457 of the Dunwoody Zoning Ordinance authorized “any person
    aggrieved by . . . any final order, requirement, or decision of an administrative
    official, based on or made in the enforcement of the this zoning ordinance” to appeal
    the administrative decision.
    8
    owners by mail, by signage, or by publication in a newspaper.7 And in the instant
    case, the neighbors filed their appeal 98 days after the date of the decision. At the
    ZBA hearings, the neighbors argued that they were unaware of the confirmation
    within 30 days of its issuance, and that unless the ordinance was construed as
    impliedly requiring that notice be given to them, the appeal provisions of the zoning
    ordinance violated due process. The ZBA accepted the appeal, thus, impliedly reading
    a notice provision into the ordinance.
    “The construction of a zoning ordinance is a question of law for
    the courts. Zoning ordinances are to be strictly construed in favor of the
    property owner. Since statutes or ordinances which restrict an owner’s
    right to freely use his property for any lawful purpose are in derogation
    of the common law, they must be strictly construed and never extended
    beyond their plain and explicit terms.”
    Haralson County v. Taylor Junkyard of Bremen, Inc., 
    291 Ga. 321
    , 323-324 (729
    SE2d 357) (2012); Cherokee County v. Martin, 
    253 Ga. App. 395
    , 396 (1) (559 SE2d
    138) (2002). In construing a zoning ordinance, “the cardinal rule is to ascertain and
    7
    The ordinance was amended in January 2015, which date was after the ZBA’s
    decision. The amended ordinance contained a provision that authorized the ZBA to
    waive the 30-day deadline and allow an appeal to be filed within 30 days of actual or
    constructive notice of the decision. Additionally, the amended ordinance required that
    notice of the decision be given to adjacent property owners.
    9
    give effect to the intention of the lawmaking body.” (Punctuation and footnote
    omitted.) Northside Corp. v. City of Atlanta, 
    275 Ga. App. 30
    , 31 (1) (619 SE2d 691)
    (2005).
    Here, “the language of the ordinance is plain and unambiguous, and does not
    lead to contradictory, absurd, or wholly impracticable results, [and] it is the sole
    evidence of legislative intent and must be construed according to its terms.”
    (Punctuation and footnote omitted.) Northside Corp., 275 Ga. App. at 32 (2). The
    ordinance explicitly provided that use of property as a family personal care home was
    permitted as of right in the residential zoning district where the property was located.
    And it is undisputed that the plain language of the ordinance did not require that
    neighboring property owners be given notice of a city official’s decision that a
    homeowner’s stated proposed use for his/her property was permitted under the
    existing zoning classification as a matter of right.
    We reject the City’s argument that “to maintain the constitutionality of the
    appeals provision of the Zoning Ordinance . . . the courts must imply a notice
    requirement, otherwise the Ordinance simply ignores foundational due process
    constraints” by not affording notice to those who may appeal the zoning decision.
    Procedural due process includes the right to notice and an opportunity to be heard.
    10
    See Glass Systems, Inc. v. Ga. Power Co., 
    288 Ga. 85
    , 87 (1) (703 SE2d 605) (2010).
    “The principles of due process extend to every proceeding judicial or administrative
    or executive in its nature at which a party may be deprived of life, liberty, or
    property.” (Citation and punctuation omitted.) Cobb County School Dist. v. Barker,
    
    271 Ga. 35
    , 37 (2) (518 SE2d 126) (1999). Due process rights were not triggered in
    the instant case.
    The ordinance explicitly required that public notice (i. e., by placing a yard sign
    in a conspicuous location on the property, or by publication in a newspaper) and/or
    notice by mail be given prior to any zoning or land use amendment, or prior to the
    issuance of special land use permits, variances, special exceptions, or administrative
    permits. See, e.g., Atlantic Refining Co. v. Spears, 
    214 Ga. 126
    , 127 (103 SE2d 547)
    (1958) (“Where proper notice is given and an actual hearing is had, the rezoning of
    property does not violate the due process laws of the Constitution.”). Here, the city
    planner’s confirmation did not change the existing zoning of the district where the
    property at issue was located; it did not authorize a non-permitted use of land or any
    variance or exception from permitted uses; nor did it deprive the complainants of life,
    liberty, or property. The City cites no authority, and we found none, holding that due
    process required that neighboring property owners be given notice aside from that
    11
    provided in the ordinance of a homeowner’s permitted use of his/her property as of
    right. As the city planner testified at one of the ZBA hearings in this matter, “a use
    by right [was] not something that requires notification,” and “if at any time, the
    proposed use exceeds their threshold of a personal care home, then those activities
    on the lot are not deemed allowable by the letter or by the ordinance. Indeed, in the
    event of use outside the existing zoning classification, the neighbors and City would
    not be without a remedy. See generally Burton, 297 Ga. at 544-548 (1) (trial court
    properly granted county’s counterclaim for declaratory judgment where homeowners
    were violating a zoning ordinance by using their property for large-scale gatherings,
    which use fell outside the scope of the single-family residential use for which the
    district was zoned); Hall v. Trubey, 
    269 Ga. 197
    -200 (1) (498 SE2d 258) (1998)
    (despite issuance of building permits, where property owner had not received zoning
    variance to construct residential units on property zoned strictly for commercial use,
    adjacent property owner’s action for injunction was not barred by laches even though
    formal lawsuit was not filed until several months after construction project began);
    Maloof v. Gwinnett County, 
    231 Ga. 164
    -166 (200 SE2d 749) (1973) (trial court
    properly granted interlocutory injunction sought by county and nearby property
    12
    owners who sought to abate homeowners’ use of their property as a commercial dog
    kennel in a zoning district of the county in which such use was not permitted).
    By accepting the appeal, the ZBA impermissibly read a notice requirement into
    the ordinance, where there was not one and where the language of the ordinance
    evidenced no intent that any special notice be given for the use permitted as a matter
    of right in this case. The ZBA erroneously construed the ordinance despite its plain
    language and the superior court, in accordance with its obligation to construe Section
    27-458 of the Dunwoody Zoning Ordinance as a matter of law, see Northside Corp.,
    275 Ga. App. at 31 (1), correctly ruled so.
    “Municipal ordinances are entitled to a presumption of validity, and will be
    sustained unless clearly invalid.” (Citation and punctuation omitted.) Buckler v.
    DeKalb County Bd. of Commrs., 
    299 Ga. App. 465
    , 467 (2) (683 SE2d 22) (2009).
    In the instant case, the appeals provisions of the zoning ordinance were not clearly
    invalid, and the superior court’s reversal of the ZBA’s contrary interpretation is
    correct and must be affirmed.
    3. Given our conclusion that the ZBA erred by accepting the appeal, we need
    not reach the remaining enumerated errors.
    Judgment affirmed. Barnes, P. J., and Boggs, J., concur.