Judson H. Turner, Director, Environmental Protection Division, Georgia Dept of Natural Resources v. Grady County Board of Commissioners ( 2014 )


Menu:
  •                                   WHOLE COURT
    NOTICE: Motions for reconsideration must be
    physically received in our clerk’s office within ten
    days of the date of decision to be deemed timely filed.
    http://www.gaappeals.us/rules/
    July 16, 2014
    In the Court of Appeals of Georgia
    A14A0215. GEORGIA RIVER NETWORK et al. v. TURNER et al.
    A14A0272. GEORGIA RIVER NETWORK et al. v. GRADY
    COUNTY BOARD OF COMMISSIONERS et al.
    A14A0273. TURNER v. GRADY COUNTY BOARD OF
    COMMISSIONERS et al.
    A14A0274. GRADY COUNTY BOARD OF COMMISSIONERS
    et al. v. GEORGIA RIVER NETWORK et al.
    MCFADDEN, Judge.
    These appeals and cross-appeals arise from a petition for administrative hearing
    Georgia River Network and American Rivers (the “River Groups”) filed to challenge
    a buffer variance the Director of the Environmental Protection Division (“EPD”) of
    the Georgia Department of Natural Resources (“DNR”) (the “Director”) issued to the
    Grady County Board of Commissioners (the “County”) under Georgia’s Erosion and
    Sedimentation Act in connection with the County’s plans to construct a 960-acre
    fishing lake. The buffer variance permits the County to encroach upon the 25-foot
    vegetative buffer the Erosion and Sedimentation Act requires adjacent to streams on
    the site. The Administrative Law Judge (“ALJ”), after rejecting two challenges to her
    jurisdiction, reversed the variance, concluding that it failed to account for buffers
    required for wetlands on the site. In parallel proceedings for judicial review, the
    Superior Court of Fulton County (the “Fulton Court”) and the Superior Court of
    Grady County (the “Grady Court”) (collectively, the “Superior Courts”) issued orders
    reversing the ALJ’s decision.
    In Case Nos. A14A0215 and A14A0272, the River Groups appeal from the
    Fulton Court and Grady Court orders, respectively, arguing that the Superior Courts
    erred in finding that the ALJ lacked jurisdiction and in concluding as to the merits
    that the Erosion and Sedimentation Act requires a 25-foot buffer only along the banks
    of state waters with vegetation wrested by normal stream flow or wave action. In Case
    Nos. A14A0273 and A14A0274, the Director and County, respectively, cross-appeal
    the Grady Court order. Although they do not contest the reversal of the ALJ decision,
    they argue that the Grady Court erred by finding “no obvious error” in the ALJ’s
    standing determination.
    2
    We conclude that the River Groups challenged an “order or action” of the
    Director; that the River Groups had standing; and that the Superior Courts erred in
    determining that the buffer requirement applies only to state waters with wrested
    vegetation. We therefore reverse the superior courts’ judgments.
    1.     Statutory background and procedural history.
    This Court conducts a de novo review of claimed errors of law in a superior
    court’s appellate review of an ALJ’s decision. Upper Chattahoochee Riverkeeper v.
    Forsyth County, 
    318 Ga. App. 499
    , 501-502 (734 SE2d 242) (2012).
    We begin with an overview of the statutory background and a discussion of the
    procedural history in these cases. The purpose of the Erosion and Sedimentation Act
    is set out as follows:
    It is found that soil erosion and sediment deposition onto lands and into
    waters within the watersheds of this state are occurring as a result of
    widespread failure to apply proper soil erosion and sedimentation
    control practices in land clearing, soil movement, and construction
    activities and that such erosion and sediment deposition result in
    pollution of state waters and damage to domestic, agricultural,
    recreational, fish and wildlife, and other resource uses. It is therefore
    declared to be the policy of this state and the intent of this chapter to
    strengthen and extend the present erosion and sediment control activities
    and programs of this state and to provide for the establishment and
    3
    implementation of a state-wide comprehensive soil erosion and sediment
    control program to conserve and protect the land, water, air, and other
    resources of this state.
    OCGA § 12-7-2. The Erosion and Sedimentation Act provides that land-disturbing
    activities must conform with “best management practices.” OCGA § 12-7-6 (b). One
    of these practices is set forth in OCGA § 12-7-6 (b) (15), which states that “[t]here
    is established a 25[-]foot buffer along the banks of all state waters, as measured
    horizontally from the point where vegetation has been wrested by normal stream flow
    or wave action” unless one of six exceptions applies, including “[w]here the director
    determines to allow a variance that is at least as protective of natural resources and
    the environment.” No land-disturbing activities may be conducted within a buffer
    “except as otherwise provided by this paragraph.” OCGA § 12-7-6 (b) (15) (B). “State
    waters” include
    any and all rivers, streams, creeks, branches, lakes, reservoirs, ponds,
    drainage systems, springs, wells, and other bodies of surface or
    subsurface water, natural or artificial, lying within or forming a part of
    the boundaries of the state, which are not entirely confined and retained
    completely upon the property of a single individual, partnership, or
    corporation.
    OCGA § 12-7-3 (16).
    4
    On May 28, 2010, the U. S. Army Corps of Engineers issued a permit to the
    County pursuant to Section 404 of the Federal Clean Water Act, authorizing
    construction of a 960-acre fishing lake. The permit allows the County to impound
    Tired Creek, a tributary of the Upper Ochlockonee River, by constructing a 3,000-
    foot long, 65-foot tall, and 450-foot wide dam. The construction of the dam and lake
    will destroy at least 129 acres of wetlands and over nine miles of streams.
    The County also needed a buffer variance to proceed with its project. On April
    30, 2012, the County submitted a revised application to the EPD for a buffer variance
    to permit the disturbance and loss of stream buffers at the site. In comments to the
    EPD, the River Groups maintained that the County’s application was deficient
    because it did not address impacts to buffers along wetlands on the site. The River
    Groups asserted that wetlands are “state waters” protected by buffers and that impacts
    to wetlands on the site would require a buffer variance and appropriate mitigation. On
    July 6, 2012, the Director granted the County’s application for a variance. The EPD’s
    Nonpoint Source Program Manager thereafter sent a letter to the River Groups in
    which he agreed that wetlands are state waters but asserted that “[w]etlands are
    features that usually do not require a buffer due to the lack of ‘wrested vegetation.’
    Therefore, those impacts are not included in the buffer variance request.”
    5
    The River Groups then filed a petition for hearing in the Office of State
    Administrative Hearings against the Director seeking to invalidate the County’s
    buffer variance on the ground that it failed to account for and authorize impacts to
    wetlands. The County was permitted to intervene. The Director filed a motion to
    dismiss, later adopted by the County, asserting that the River Groups failed to identify
    an “order or action” they were challenging within the meaning of OCGA § 12-2-2 (c)
    (2) (A). The County filed a motion to dismiss, asserting that River Groups lacked
    standing under OCGA § 12-2-2 (c) (2) (A) because they were not aggrieved or
    adversely affected by the variance. The River Groups and the County filed cross-
    motions for summary determination. In his response to the River Groups’ motion for
    summary determination, the Director argued that the River Groups were not
    aggrieved or adversely affected by the variance.
    The ALJ entered an order denying the motions to dismiss; granting the River
    Groups’ motion for summary determination; and reversing the buffer variance. The
    ALJ concluded that “applying the plain and unambiguous meaning of the statute, a
    buffer is required for all state waters, including wetlands.” The Director filed a
    petition for judicial review in the Fulton Court, and the County filed a petition for
    6
    judicial review in the Grady Court. The County was permitted to intervene in the
    Fulton Court, and the Director was permitted to submit briefs in the Grady Court.
    The Fulton Court reversed the ALJ’s decision, concluding that the River
    Groups failed to challenge an “order or action” of the Director; the River Groups
    lacked standing; and the Director’s application of the Erosion and Sedimentation Act
    was consistent with its plain terms. The Grady Court subsequently entered an order
    reaching the same conclusions and reversing the ALJ’s decision, except that it found
    “no obvious error” in the ALJ’s conclusion as to standing. We granted the River
    Groups’ applications for discretionary appeal from the Superior Courts’ orders, and
    these appeals and cross-appeals followed.
    2. Jurisdiction.
    We first address the River Groups’ enumerations of error pertaining to the
    ALJ’s subject matter jurisdiction because if subject matter jurisdiction was lacking,
    neither the ALJ nor the Superior Courts were authorized to enter a judgment on the
    merits. See First Christ Holiness Church v. Owens Temple First Christ Holiness
    Church, 
    282 Ga. 883
    , 885 (655 SE2d 605) (2008).
    (a) “Order or action.”
    7
    The River Groups contend that the Superior Courts erred in concluding that the
    ALJ lacked jurisdiction over their petition because the petition challenged the
    Director’s alleged failure to act, not an “order or action” of the Director. We conclude
    that the Superior Courts erred in reversing the ALJ on this issue.
    The Erosion and Sedimentation Act provides that “[a]ll hearings on and review
    of contested matters, orders, or permits issued by or filed against the director . . . shall
    be provided and conducted in accordance with subsection (c) of Code Section 12-2-
    2.” OCGA § 12-7-16. In turn, OCGA § 12-2-2 (c) (2) (A) provides in relevant part:
    Any person who is aggrieved or adversely affected by any order or
    action of the director shall, upon petition to the director within 30 days
    after the issuance of such order or the taking of such action, have a right
    to a hearing before an administrative law judge.
    As the ALJ concluded, the River Groups’ petition challenged a specific action,
    the Director’s issuance of a variance. The petition asserts that the variance is invalid
    and in violation of the Erosion and Sedimentation Act because the Director allowed
    the County to submit an application that failed to address alleged wetland buffers at
    the site and subsequently issued a variance failing to account for those buffers. At
    bottom, the River Groups are challenging the validity of the variance on the theory
    that both the application and the Director’s consideration of it were incomplete. The
    8
    River Groups’ challenge to the variance is akin to the permit challenges in other
    environmental cases we have entertained that were likewise based in whole or in part
    on the regulating authority’s alleged incomplete consideration or regulation of a
    proposed project. See Longleaf Energy Assoc., LLC v. Friends of the Chattahoochee,
    
    298 Ga. App. 753
    , 756-760 (2) (681 SE2d 203) (2009) (considering and rejecting
    claim that EPD permit for construction of coal-fired electric plant was invalid because
    it failed to limit carbon dioxide gas emissions); Coastal Marshlands Protection
    Committee v. Center for a Sustainable Coast, 
    286 Ga. App. 518
    , 521-529 (2) (649
    SE2d 619) (2007), aff’d 
    284 Ga. 736
    (670 SE2d 429) (2008) (considering and
    rejecting petitioners’ claim that permit authorizing construction of marina and dock
    facilities over coastal marshlands was invalid because it failed to regulate permittee’s
    adjoining upland development).
    The Superior Courts reasoned that the River Groups were challenging the
    Director’s inaction because the Director had no duty under the Erosion and
    Sedimentation Act to consider impacts to buffers at the site of the project if the
    application did not request permission to encroach on them or to require the County
    to address additional buffers in its application. The River Groups’ petition cited to
    and relied upon the regulation setting forth the buffer variance process, which, in fact,
    9
    contemplates that a variance application will address all of the buffer impacts
    associated with a proposed project.1 Further, the County conceded before the ALJ that
    during the buffer variance application process, the Director required it to revise its
    application to increase the number of linear feet of streams and associated buffers that
    would be impacted by the project. While the parties may dispute whether the buffer
    provision in the Erosion and Sedimentation Act and the variance regulation apply to
    wetlands, those issues relate to the merits of the River Groups’ petition. Meritorious
    or not, the petition invoked the ALJ’s jurisdiction to review the “orders or actions”
    of the Director.
    (b) Standing.
    The River Groups argue that the Fulton Court erred in concluding that the
    River Groups lacked standing because their members are not aggrieved or adversely
    affected within the meaning of OCGA § 12-2-2 (c) (2) (A). Conversely, the Director
    1
    For example, the regulation states that a variance application must include a
    “[s]ite map that includes locations of all state waters, wetlands, floodplain boundaries
    and other natural features, as determined by field survey,” a “[d]escription of the
    project, with details of the buffer disturbance, including estimated length of time for
    the disturbance and justification for why the disturbance is necessary,” and
    “[c]alculation of the total area and length of the buffer disturbance.” Ga. Comp. R.
    & Regs. r. 391-3-7-.05 (3) (a), (d), (e). Further, in reviewing a variance application,
    the Director must consider, inter alia, the “[l]ocation and extent of buffer intrusion.”
    Ga. Comp. R. & Regs. r. 391-3-7-.05 (5) (c).
    10
    and the County argue that the Grady Court erred in failing to reverse the ALJ’s
    conclusion that the River Groups had standing.
    OCGA § 12-2-2 (c) (3) (A) explains that “[p]ersons are ‘aggrieved or adversely
    affected,’ [for purposes of OCGA § 12-2-2 (c) (2) (A)] . . . where the challenged
    action has caused or will cause them injury in fact and where the injury is to an
    interest within the zone of interests to be protected or regulated by the statutes that
    the director is empowered to administer and enforce.”
    We look to U. S. Supreme Court precedent concerning Article III standing for
    guidance in analyzing the River Groups’ standing under OCGA § 12-2-2 (c) (2) (A)
    and (c) (3) (A). See Center for a Sustainable Coast v. Turner, 
    324 Ga. App. 762
    , 764
    (751 SE2d 555) (2013). The U. S. Supreme Court has explained that
    to satisfy Article III’s standing requirements, a plaintiff must show (1)
    it has suffered an injury in fact that is (a) concrete and particularized and
    (b) actual or imminent, not conjectural or hypothetical; (2) the injury is
    fairly traceable to the challenged action of the defendant; and (3) it is
    likely, as opposed to merely speculative, that the injury will be redressed
    by a favorable decision. An association has standing to bring suit on
    behalf of its members when its members would otherwise have standing
    to sue in their own right, the interests at stake are germane to the
    organization’s purpose, and neither the claim asserted nor the relief
    11
    requested requires the participation of individual members in the
    lawsuit.
    (Citations and punctuation omitted.) Friends of the Earth v. Laidlaw Environmental
    Svcs. (TOC), 
    528 U.S. 167
    , 180-181 (II) (A) (120 SCt 693, 145 LE2d 610) (2000).
    “Environmental plaintiffs adequately allege injury in fact when they aver that they use
    the affected area and are persons for whom the aesthetic and recreational values of
    the area will be lessened by the challenged activity.” (Citation and punctuation
    omitted.) 
    Turner, supra
    , 
    324 Ga. App. 765
    . The issues in dispute here are whether the
    River Groups can show that their members’ alleged injuries are fairly traceable to the
    buffer variance and redressable in this action.
    In his response to the River Groups’ motion for summary determination, the
    Director requested that the ALJ make a determination on the issue of standing in
    accordance with OCGA § 12-2-2 (c) (3) (A) , which states:
    In the event the director asserts in response to the petition before the
    administrative law judge that the petitioner is not aggrieved or adversely
    affected, the administrative law judge shall take evidence and hear
    arguments on this issue and thereafter make a ruling on this issue before
    continuing with the hearing. The burden of going forward with evidence
    on this issue shall rest with the petitioner.
    12
    The statute contemplates an evidentiary hearing on the issue of standing. See Smart
    Growth – Forsyth County v. Couch, Docket No. OSAH-BNR-ES-0707202-60-
    Howells, Order on Standing, March 2, 2007, 
    2007 WL 828306
    , at *2 (ALJ conducted
    hearing on standing and heard testimony from petitioners’ witnesses).2 During oral
    argument on the parties’ motions, the Director’s counsel, rather than requesting that
    an evidentiary hearing take place, stated that because the Director had invoked OCGA
    § 12-2-2 (c) (3) (A), the River Groups were required to come forward with evidence
    to establish causation in support of their motion for summary determination. The
    Director’s counsel argued that the River Groups failed to do so. The River Groups,
    however, already had presented evidence relevant to standing, as they attached
    several affidavits to their petition, including affidavits from two individuals who are
    members of both organizations and live in close proximity to the proposed lake.
    Neither the Director nor the County disputed the veracity of these affidavits. Thus,
    2
    We disagree with the Director to the extent he argues that a petitioner must
    establish standing at such a hearing with “undisputed credible evidence.” See Board
    of Regents &c. v. Oglesby, 
    264 Ga. App. 602
    , 605 (1) (591 SE2d 417) (2003) (when
    trial court makes determinations of fact when ruling on motion to dismiss on
    jurisdictional grounds, “[i]ts evaluation rests on where the preponderance of evidence
    lies, not necessarily on whether the issue may be decided as a matter of law.”)
    (citations and punctuation omitted).
    13
    the issue before the ALJ was whether those affidavits are legally sufficient to
    establish the individuals’ standing.3 We conclude that they are.
    One of the affiants stated that she has enjoyed walking along Tired Creek and
    its tributaries, has canoed on the Ochlockonee River downstream from the proposed
    lake, and hopes to continue these activities. She believes that as a result of the buffer
    variance, the waters downstream will be less desirable for viewing, recreation, and
    other uses. The other affiant stated that she enjoys walking along the waters
    downstream from the site and is afraid that the destruction of the buffers will
    negatively impact the water quality downstream. She is also concerned the variance
    will negatively impact migratory birds and destroy trails animals use when seeking
    food and water. The affiants stated that their use and enjoyment of waters on the site
    and downstream has been and will continue to be significantly and negatively
    affected by the variance.
    To establish standing, the River Groups must show that the injuries described
    by the members are “fairly traceable to the challenged action of the defendant, and
    3
    Since the parties acquiesced in the ALJ deciding the issue of standing based
    on the member affidavits, we conclude that any error in failing to hold an evidentiary
    hearing was waived. See Davis v. Phoebe Putney Health Systems, 
    280 Ga. App. 505
    ,
    506 (1) (634 SE2d 452) (2006).
    14
    not the result of the independent action of some third party not before the court.”
    (Citation omitted.) Bennett v. Spear, 
    520 U.S. 154
    , 167 (III) (A) (117 SCt 1154, 137
    LE2d 281) (1997). Here, it is undisputed that the buffers required by the Erosion and
    Sedimentation Act at the site could not be disturbed and the lake project could not go
    forward without both the Section 404 permit and the buffer variance. As such, even
    if the Section 404 permit is also a cause of the damage to and loss of alleged wetland
    buffers, the loss is nonetheless fairly traceable to the buffer variance. See Mattaponi
    Indian Tribe v. Commonwealth, Dept. of Environmental Quality, 
    261 Va. 366
    , 375-
    378 (541 SE2d 920) (2001) (petitioners had standing to challenge state permit
    authorizing reservoir for public water supply although project also would require
    federal Section 404 permit; state permit protected separate interests and could cause
    injury). In concluding that the River Groups failed to establish that the buffer
    variance, rather than the Section 404 permit, caused their members’ injuries, the
    Fulton Court relied on OCGA § 12-7-6 (b) (15) (C) (i), which requires that the Board
    of Natural Resources adopt rules with specific criteria for the grant or denial of a
    variance and states that the
    rules shall provide, at a minimum, that the director shall consider
    granting a variance in the following circumstances: (i) Where a
    15
    proposed land-disturbing activity within the buffer would require the
    landowner to acquire a [Section 404] permit, . . . and the Corps of
    Engineers has approved a mitigation plan to be implemented as a
    condition of such a permit.
    The applicable regulation allows a variance in this circumstance. Ga. Comp. R. &
    Regs. r. 391-3-7-.05 (2) (h). While the statute and regulation establish that a variance
    may be available when a Section 404 permit has been issued and is subject to a
    mitigation plan, a variance is not a foregone conclusion. Rather, a detailed application
    is still required, and the Director must consider various factors in deciding whether
    to grant it. See Ga. Comp. R. & Regs. r. 391-3-7-.05 (3)-(5).
    We also disagree with the Fulton Court’s conclusion that the permanent loss
    of wetland buffers due to flooding would be inconsequential since the wetlands they
    protect will be destroyed by flooding. It is undisputed that the County was required
    to apply for a buffer variance in connection with the inundation and permanent loss
    of streams and their buffers at the lake site. That the County was required to do so is
    evidence that permanent buffer loss in connection with a project like the County’s
    implicates the interests protected by the Erosion and Sedimentation Act.
    Finally, we reject the County’s argument that the River Groups cannot establish
    redressability. The County’s reliance on our decision in 
    Turner, supra
    , is unavailing.
    16
    In that case, an environmental group challenged a consent order the Director entered
    into with a property owner after discovering that the property owner had constructed
    a bulkhead in a salt water marsh area without first requesting a buffer 
    variance. 324 Ga. App. at 762-763
    . We held that the environmental group could not establish that
    the relief requested would redress its injuries. 
    Id. at 768.
    We reasoned that if the ALJ
    issued an order invalidating the consent order, the bulkhead would remain in place.
    
    Id. We also
    concluded that the ALJ could not require the Director to order removal
    of the bulkhead because such a requirement would amount to improper interference
    with an agency’s exercise of its discretionary enforcement authority. 
    Id. The relief
    requested here, reversal or invalidation of the variance, does not implicate the
    Director’s enforcement authority. Further, an ALJ possesses authority to reverse the
    Director’s decision on a variance application if the decision does not comport with
    the requirements of the Erosion and Sedimentation Act and the variance regulation.
    See The Sembler Company v. Environmental Protection Div., Dept. of Natural
    Resources, Docket No. OSAH-DNR-ES-02-04135060-SEP, Final Decision, March
    18, 2002, 
    2002 WL 34125519
    (reversing denial of buffer variance application).
    17
    For these reasons, we reject the Director’s and County’s arguments that the
    Grady Court erred by failing to reject the ALJ’s determination that the River Group’s
    had standing.
    2. Buffer requirement.
    Finally, the River Groups contend that the Superior Courts erred in concluding
    that under the plain statutory language, buffers exist only along the banks of state
    waters4 where vegetation has been wrested by normal stream flow or wave action. We
    agree.
    As this case involves a matter of statutory construction, we must “look
    diligently for the intention of the General Assembly and . . . follow the literal
    language of the statute unless it produces contradiction, absurdity, or such an
    inconvenience as to insure that the legislature meant something else.” Judicial
    Council of Georgia v. Brown & Gallo, 
    288 Ga. 294
    , 296-297 (702 SE2d 894) (2010)
    (citation and punctuation omitted). See also OCGA § 1-3-1 (a). With these principles
    in mind, we conclude that the Superior Courts erred by determining that the 25-foot
    4
    The parties do not dispute that wetlands fall within the definition of “state
    waters” in the Erosion and Sedimentation Act. Various professional organizations and
    trade groups, however, have submitted an amicus brief arguing that wetlands are not
    “state waters.” This issue has not been fully litigated, and we need not and do not
    reach it here.
    18
    buffer requirement of the Erosion and Sedimentation Act does not apply unless the
    state waters at issue have banks with wrested vegetation.
    19
    As detailed above, OCGA § 12-7-6 (b) (15) (A), which is set out in the
    margin,5 establishes “a 25[-] foot buffer along the banks of all state waters.” “State
    5
    “There is established a 25[-]foot buffer along the banks of all state waters, as
    measured horizontally from the point where vegetation has been wrested by normal
    stream flow or wave action, except:
    (i) As provided by paragraph (16) of this subsection;
    (ii) Where the director determines to allow a variance that is at least as
    protective of natural resources and the environment;
    (iii) Where otherwise allowed by the director pursuant to Code Section
    12-2-8;
    (iv) Where a drainage structure or a roadway drainage structure must be
    constructed, provided that adequate erosion control measures are
    incorporated in the project plans and specifications and are
    implemented;
    (v) Along any ephemeral stream. As used in this division, the term
    “ephemeral stream” means a stream:
    (I) That under normal circumstances has water flowing
    only during and for a short duration after precipitation
    events;
    (II) That has the channel located above the ground-water
    table year round;
    (III) For which ground water is not a source of water; and
    (IV) For which runoff from precipitation is the primary
    source of water flow; or
    20
    waters” is a defined term, and the definition is broad. “State waters” includes
    any and all rivers, streams, creeks, branches, lakes, reservoirs, ponds,
    drainage systems, springs, wells, and other bodies of surface or
    subsurface water, natural or artificial, lying within or forming a part of
    the boundaries of the state, which are not entirely confined and retained
    completely upon the property of a single individual, partnership, or
    corporation.
    OCGA § 12-7-3 (16). That broad definition of “state waters” is narrowed, for
    purposes of the applicability of the 25-foot buffer requirement in OCGA § 12-7-6 (b)
    (15) (A), by six statutory exceptions not applicable here; the requirement otherwise
    applies to “all state waters.” One of these exceptions is for a category of waters to
    which the General Assembly deemed a buffer inappropriate (ephemeral streams).
    OCGA § 12–6 (b) (15) (A) (v). Two others give the Director limited discretion to
    grant variances. OCGA § 12-7-6 (b) (15) (A) (ii), (iii). In a subordinate clause, the
    (vi) Where shoreline stabilization is installed; provided, however, that
    this exception shall be limited to the construction of bulkheads and sea
    walls only to the extent required to prevent the erosion of the shoreline.
    This exception shall be limited to Lake Oconee and Lake Sinclair and
    shall be limited to the duration of such construction.
    Unless exempted under division (v) of this subparagraph, buffers of at least 25 feet
    established pursuant to Part 6 of Article 5 of Chapter 5 of this title shall remain in
    force unless a variance is granted by the director as provided in this paragraph.
    21
    statute goes on to direct that the buffer is to be “measured horizontally from the point
    where vegetation has been wrested by normal stream flow or wave action.” The
    question before us is whether that direction entails a seventh exception.
    We hold that it does not. It merely specifies the location of the buffer –
    alongside the “bank” or the “margin of the watercourse,” Webster’s New
    International Dictionary (1954) – and a method for measuring it. To treat that
    language as a seventh exception, as the Superior Courts did, would be to hold that no
    buffer is required along the banks of streams, rivers, and lakes that have rocky or
    sandy shores where lines of wrested vegetation cannot be found. This interpretation
    would hold that buffer protection is afforded in fits and starts, should the line of
    wrested vegetation not be continuous, an absurdity not intended by the legislature.
    See Judicial Council of 
    Georgia, supra
    , 288 Ga. at 296-297.
    The wrested vegetation measurement language was added to the statute in
    1994. Formerly, the statute had provided that the buffer was “measured from the
    stream banks.” In 1994, the General Assembly amended that language to provide that
    the buffer was measured “from the point where vegetation has been wrested.” The
    1994 version of the statute listed three exceptions to the buffer requirement. Had the
    General Assembly intended to except state waters without wrested vegetation from
    22
    the buffer requirement, it would have said so expressly in the list of exceptions, not
    by implication in a subordinate clause that addresses measurements.
    The statute is internally inconsistent. As the dissent says, it does not set out an
    alternative to its provision that buffers are to be measured from wrested vegetation.
    On the other hand it sets out explicitly the six exceptions to the rule establishing a
    buffer along the banks of all state waters – each narrower than the purported
    exception for state waters without wrested vegetation. It is our duty to resolve that
    inconsistency so as to give effect to the intent of the General Assembly and to avoid
    absurd results.
    Here the General Assembly stated its intent: “to strengthen and extend the
    present erosion and sediment control activities and programs of this state” and “to
    protect the land, water, air, and other resources of this state.” OCGA § 12-7-2. See
    also Mark McCarty et al., Peach Sheets: Conservation and Natural Resources, 12 Ga.
    St. U. L. Rev. 39, 47 (1995) (reporting on another change made to the Erosion and
    Sedimentation Act the year after the “wrested vegetation” language was adopted:
    “The Senate committee substitute made a blanket change of terms from ‘streams’ to
    ‘waters,’ and this change was ultimately adopted in the Act. Environmental lobbyists
    and the EPD encouraged this change to broaden the scope of regulation to waters that
    23
    do not flow, such as lakes and marshlands.”) (footnotes omitted). The Superior Courts
    erred in construing the statute in a manner contrary to the General Assembly’s stated
    intent.
    Judgments reversed. Barnes, P. J., Doyle, P. J., and Boggs, J., concur;
    Andrews, P. J., Ray and Branch, JJ., dissent.
    24
    A14A0215. GEORGIA RIVER NETWORK et al. v. TURNER et al.
    A14A0272. GEORGIA RIVER NETWORK et al. v. GRADY COUNTY
    BOARD OF COMMISSIONERS et al.
    A14A0273. TURNER v. GRADY                   COUNTY        BOARD       OF
    COMMISSIONERS et al.
    A14A0274. GRADY COUNTY BOARD OF COMMISSIONERS et al.
    v. GEORGIA RIVER NETWORK et al.
    ANDREWS, Presiding Judge, concurring in part and dissenting in part.
    I concur fully in Division 1 of the majority’s opinion. I respectfully
    dissent from Division 2, however. The majority’s interpretation of OCGA
    § 12-7-6 (b) (15) (A) (the “buffer provision”) rewrites that statutory
    provision, and its assertion that doing so is necessary to effectuate the
    General Assembly’s intent and to avoid an unreasonable result is
    conclusory and speculative.
    In cases involving questions of statutory interpretation, we are guided
    by the following principles:
    It is elementary that in all interpretations of statutes, the courts
    shall look diligently for the intention of the General Assembly.
    In so doing, the ordinary signification shall be applied to all
    words. Where the language of a statute is plain and susceptible
    to only one natural and reasonable construction, courts must
    construe the statute accordingly. . . . Moreover, Georgia law
    provides that the express mention of one thing in an act or
    statute implies the exclusion of all other things.
    (Footnotes and punctuation omitted.) Chase v. State, 
    285 Ga. 693
    , 695 (2)
    (681 SE2d 116) (2009).
    In relevant part, OCGA § 12-7-6 (b) (15) (A) states that “[t]here is
    established a 25-foot buffer along the banks of all state waters, as measured
    horizontally from the point where vegetation has been wrested by normal
    stream flow or wave action, except” when one of six exceptions applies.
    The wrested vegetation phrase, set off by commas between “state waters”
    and “except,” is a participial phrase that modifies the term “buffer.” The
    wrested vegetation phrase directs that the 25-foot buffer along the banks
    of state waters is “measured horizontally from the point where vegetation
    2
    has been wrested by normal stream flow or wave action.” OCGA § 12-7-6
    (b) (15) (A). Applying its ordinary meaning, “wrest” means “[t]o extract by
    or as if by force, twisting, or persistent effort.” The American Heritage
    Dictionary of the English Language at 2060 (3d ed. 1992). When normal
    stream flow or wave action is absent or lacks sufficient force to wrest the
    vegetation along the banks of state waters, the E&S Act provides no means
    of measuring a buffer. I would hold that the most natural and reasonable
    construction of the buffer provision is that under such circumstances, no
    buffer exists. This interpretation is reinforced by the buffer provision’s
    description of buffers as located along the “banks” of state waters. When
    used in reference to a body of water, “bank” most commonly means “the
    rising ground bordering a lake, river, or sea,” Merriam Webster’s Collegiate
    Dictionary at 96 (11th ed. 2008) or “[t]he slope of land adjoining a body of
    water, especially adjoining a river, lake, or channel.” The American
    Heritage 
    Dictionary, supra, at 145
    .      Even if they are not in and of
    themselves determinative of the buffer provision’s meaning, these
    definitions are evidence that the General Assembly contemplated that
    buffers would exist along those bodies of water, such as rivers and lakes,
    3
    that are characterized by water movement sufficient to create a line of
    wrested vegetation.
    The majority agrees that wrested vegetation phrase sets forth the
    method for measuring the buffer yet concludes that a buffer exists adjacent
    to all state waters even when there is no line of wrested vegetation from
    which it may be measured. In reaching this conclusion, the majority is
    impliedly holding that other means of measuring a buffer may be used if
    wrested vegetation is absent. But if the General Assembly had intended
    that other methods of measuring a buffer could apply or that the EPD
    should develop them, it would have said so. The express mention of one
    method of measuring the buffer implies the exclusion of other methods
    under the principle of expressio unius est exclusio alterius. See Morton v.
    Bell, 
    264 Ga. 832
    , 833 (452 SE2d 103) (1995). The majority, too, relies on
    this principle of statutory construction, stating that the Superior Courts’
    interpretation of the buffer provision violates the principle by adding a new,
    seventh exception to the circumstances in which a buffer is required. I find
    this conclusion unpersuasive. A determination that state waters that do not
    have banks with wrested vegetation do not fall within the scope of the
    4
    buffer requirement in the first place is not tantamount to creating a new
    statutory exception.
    The majority rewrites the buffer provision because it concludes that
    doing so is necessary to effectuate the intent of the General Assembly and
    to avoid unreasonable results. The majority states that under the Superior
    Courts’ interpretation of the buffer provision, no buffer would be required
    “along the banks of streams, rivers, and lakes that have rocky or sandy
    shores where lines of wrested vegetation cannot be found” and that an
    absurd result would ensue if, therefore, buffer protection applied in “fits
    and starts.” The majority does not explain, however, why it would be
    unreasonable for the General Assembly to conclude that a vegetative buffer
    is not necessary where there is no vegetation along the water banks to begin
    with. Nor does the majority hazard an explanation as to why the General
    Assembly could not have reasonably concluded that a buffer should not be
    required where, as may occur with wetlands, there is a continuous growth
    of vegetation from the upland into the waters.
    The scope of the buffer provision may not be as wide as the River
    Groups and the majority believe it should be, but it is nonetheless broadly
    5
    drawn to apply to the banks of any “state waters,” so long as the criteria of
    the wrested vegetation phrase are satisfied.       The majority offers no
    compelling reason for concluding that the General Assembly could not have
    determined that a buffer along the banks of state waters with wrested
    vegetation together with the numerous other best management practices set
    forth in OCGA § 12-7-6 (b) would effectuate the purposes of the statute.
    While there are no doubt policy arguments in favor of a broader buffer
    provision, it is not our place to second-guess the General Assembly’s
    judgment in this regard or to rewrite the buffer provision to achieve what
    we believe is a more desirable level of environmental protection. See Allen
    v. Wright, 
    282 Ga. 9
    , 12 (1) (644 SE2d 814) (2007) (“[U]nder our system
    of separation of powers this Court does not have the authority to rewrite
    statutes.”) (citation and punctuation omitted).
    I am authorized to state that Judge Ray and Judge Branch join in this
    dissent.
    6
    

Document Info

Docket Number: A14A0273

Filed Date: 7/31/2014

Precedential Status: Precedential

Modified Date: 10/30/2014