  •                                FOURTH DIVISION
    DILLARD, C. J.,
    RAY, P. J., and SELF, J.
    NOTICE: Motions for reconsideration must be
    physically received in our clerk’s office within ten
    days of the date of decision to be deemed timely filed.
    http://www.gaappeals.us/rules
    October 25, 2017
    In the Court of Appeals of Georgia
    A17A1001. FULTON COUNTY, GEORGIA                               v.     SOCO
    CONTRACTING COMPANY, INC.
    RAY, Presiding Judge.
    In 2013, Fulton County (the “County”) and SOCO Construction Company, Inc.
    (“SOCO”) executed a written contract for the construction of a cultural center. The
    contract was approved by the Fulton County Board of Commissioners. As a result of
    several delays, including those caused by change orders, inclement weather, and the
    shutdown of the federal government, the scope of the work and time line was altered.
    SOCO filed the instant complaint against the County for, inter alia, breach of
    contract and bad faith performance of the contract. SOCO also sought attorney fees
    and injunctive relief. Soco and the County filed cross-motions for summary judgment
    on all claims. The trial court granted summary judgment in favor of SOCO and
    against the County.1 In the same order, the trial court also denied the County’s motion
    for reconsideration of its denial of the County’s motion to withdraw admissions.
    We reverse the trial court’s denial of the County’s motion for summary
    judgment on the grounds that any claims arising from unwritten change orders are
    barred under the doctrine of sovereign immunity. Further, we affirm in part and
    reverse in part the trial court’s order denying the County’s motion for reconsideration
    of its motion to withdraw admissions. Finally, we vacate and remand the trial court’s
    ruling on attorney fees.
    To prevail at summary judgment, the moving party must demonstrate
    that there is no genuine issue of material fact and that the undisputed
    facts, viewed in the light most favorable to the nonmoving party,
    warrant judgment as a matter of law. . . . We conduct a de novo review
    a trial court’s grant of summary judgment.
    (Citations and punctuation omitted.) Bright v. Sandstone Hospitality, LLC, 
    327 Ga. App. 157
    , 157-158 (755 SE2d 899) (2014).
    In May 2013, the County and SOCO executed a written contract for the
    construction of the Aviation Community Cultural Center near the Fulton County
    1
    The Association of County Commissioners of Georgia has filed an amicus
    curiae brief in this case.
    2
    Airport. The contract specified that the work should be completed within 287 days
    from the County’s issuance of the notice to proceed or the day the work began,
    whichever came first, with that period to be increased by change order due to changes
    in the scope of work, or upon the occurrence of other delays or events not the fault
    of the contractor. Section 00700-87A of the “General Conditions” portion of the
    contract provides that
    [a] Change Order is a written order to the Contractor signed to show the
    approval and authorization of the County, issued after execution of the
    Contract, authorizing a change in the Work and/or an adjustment in the
    Contract Sum or the Contract Time. Change Orders shall be written
    using forms designated by the County with Contractor providing
    supporting documentation as required by the Construction Manager. The
    Contract Sum and the Contract Time may be changed only by approved
    Change Order pursuant to Fulton County Procedure 800-6. . . . A
    Change Order signed by the Contractor indicates the Contractor’s
    agreement therewith, including the adjustment in either or both of the
    Contract Sum or the Contract Time.
    (Emphasis supplied.) It also provides that “[t]he County, without invalidating the
    Contract, may order changes in the Work within the general scope of the Contract as
    defined herein.”
    3
    Fulton County Policy and Procedure 800-6 (“Procedure 800-6”), titled
    “Procedures for Handling Change Orders,” provides that “except as otherwise
    provided . . . , change orders shall be effected only through a written, bilateral
    agreement (Modification) between the County, acting through its Board of
    Commissioners, and the contractor.” Procedure 800-6 allows for the authorization of
    change orders when needed, inter alia, to correct deficiencies in design or
    construction documents provided by architects or engineers, to remedy concealed
    conditions, abnormal inclement weather, and owner-requested changes within the
    scope of the contract. It further provides that the proper “Change Order Procedure”
    requires the “[a]greement between County and contractor for change [to be] clearly
    defined in a Written Modification,” signed by the Contractor and approved by the
    Board of Commissioners. Section G (2) of Procedure 800-6, captioned “Extraordinary
    Circumstances,” provides that the “County Manager is authorized to approve change
    orders regardless of the amount when due to extraordinary circumstances, work must
    be implemented before the Board of Commissioners can act.” Such extraordinary
    circumstances include a “[l]oss of substantial resources due to delay, including delay
    to critical path schedule.”
    4
    SOCO began work on the cultural center on May 29, 2013. However, SOCO
    did not achieve substantial completion of the project until May 29, 2014, beyond the
    time anticipated in the contract. SOCO contends that the construction of the cultural
    center was delayed due to, inter alia, adverse weather conditions, delays caused by
    the County’s design for the cultural center, the County’s unwillingness to make
    timely decisions on changes, and the impact that the federal government’s shut down
    had on obtaining certain permits. As a result of these issues, the County ordered
    changes to SOCO’s scope of work, and the County’s program manager listed more
    than 30 change orders in its September 5, 2014, change order evaluation log.
    However, SOCO does not provide citations to the record, nor can we find any,
    indicating that the change orders were executed through bilateral, written agreements.
    SOCO admits that the County never issued a change order extending the contract
    time, despite these delays. Further, the County did not release its Certificate of
    Substantial Completion until February 17, 2015, and withheld release of certain
    retainage fees until January 21, 2015.
    SOCO then filed suit against the County for breach of contract and bad faith.
    It also sought attorney fees and injunctive relief. The County answered. On June 30,
    2015, SOCO sent its first Request for Admissions to the County by hand-delivery.
    5
    The County did not respond until on August 3, 2015, 33 days later. Because the
    County’s response to the Requests for Admissions was served to SOCO more than
    30 days after service of the request, the Requests for Admissions were deemed
    admitted pursuant to OCGA § 9-11-36 (a) (2). See Adewumi v. Amelia Grove/Ashland
    Park Homeowners Assoc., Inc., 
    337 Ga. App. 275
    , 277 (2) (787 SE2d 761) (2016).
    On April 26, 2016, the County filed a motion to withdraw the Requests for
    Admissions. The County attached an affidavit of Tommy Walton, a paralegal with the
    Fulton County Attorney’s Office, who averrred that the responses to the Request for
    Admissions were late due to an administrative error. The County also alleged that it
    mistakenly admitted SOCO’s Request for Admission #37 that it was liable for “all
    damages alleged by SOCO in its Complaint.” The trial court denied the motion to
    withdraw. The trial court also denied the County’s petition for interlocutory review,
    and the County filed its motion for reconsideration of the trial court’s denial of the
    motion to withdraw admissions.
    On June 27, 2016, the County moved for summary judgment on the grounds
    that the trial court lacked subject matter jurisdiction because of sovereign immunity.
    In its final order, the trial court, inter alia, denied the motion for reconsideration and
    6
    denied the County’s motion for summary judgment. The County appeals from that
    order.
    1. The County argues that the trial court erred in denying its motion for
    summary judgment because the trial court lacked subject matter jurisdiction due to
    the applicability of sovereign immunity. The County argues that although the State
    has waived sovereign immunity for the breach of any written contract, it did not
    waive immunity for causes of action arising from modifications to the written contract
    that failed to follow the written change order policy outlined in the contract. We
    agree.2
    In Georgia, the doctrine of sovereign immunity has constitutional status and
    may be waived only by an act of the General Assembly or by the Constitution itself.
    Ga. Dept. of Corrections v. Couch, 
    295 Ga. 469
    , 472 (2) (759 SE2d 804) (2014). The
    Georgia Constitution addresses the waiver of the State’s immunity of liability for
    breach of contract as follows:
    (c) The [S]tate’s defense of sovereign immunity is hereby waived as to
    any action ex contractu for the breach of any written contract now
    2
    While we find that the County was entitled to summary judgment on the
    claims relating to modifications to the contract which were not properly executed, we
    note that there were claims presented related to the original contact.
    7
    existing or hereafter entered into by the [S]tate or its departments and
    agencies. . . .
    (e) Except as specifically provided in this Paragraph, sovereign
    immunity extends to the [S]tate and all of its departments and agencies.
    The sovereign immunity of the [S]tate and its departments and agencies
    can only be waived by an Act of the General Assembly which
    specifically provides that sovereign immunity is thereby waived and the
    extent of such waiver.
    Ga. Const., Art. I, Sec. II, Par. IX (c) and (e). “The sweep of sovereign immunity
    under the Georgia Constitution is broad, [and its] plain and ambiguous text . . . shows
    that only the General Assembly has the authority to waive the State’s sovereign
    immunity.” (Citation omitted.) Olvera v. Univ. Sys. of Ga.’s Bd. of Regents, 
    298 Ga. 425
    , 426 (782 SE2d 436) (2016).
    “[S]overeign immunity is a threshold issue that the trial court [is] required to
    address before reaching the merits of any other argument.” (Footnote omitted.)
    Albertson v. City of Jesup, 
    312 Ga.App. 246
    , 248 (1) (718 SE2d 4) (2011). It is
    axiomatic that “[t]he party seeking to benefit from the waiver of sovereign immunity
    bears the burden of proving such waiver.” (Citations omitted.) Bd. of Regents of the
    Univ. Sys. of Ga. v. Doe, 
    278 Ga.App. 878
    , 881(1) (630 SE2d 85) (2006). “Whether
    8
    sovereign immunity has been waived under the undisputed facts of this case is a
    question of law, and this Court’s review is de novo.” (Citation omitted.) Ga. Dept. of
    Labor v. RTT Assocs., Inc., 
    299 Ga. 78
    , 81 (1) (786 SE2d 840) (2016).
    In the instant case, the County argues that although it did have a written
    contract with SOCO, it did not waive its defense of sovereign immunity as to any
    claims arising from modifications to that contract that did not follow the protocol for
    written change orders as outlined in the contract and in Fulton Procedure 800-6. The
    County cites to RTT Assocs. Inc., supra at 82-83 (2), for the assertion that the limited
    waiver of sovereign immunity for actions ex contractu applies only to written
    agreements, and may not be extended by oral directives or course of conduct. We
    agree.
    In RTT Assocs., Inc., supra, the Department of Labor (“DOL”) executed a
    written contract with software vendor, RTT, that by its terms expired on June 30,
    2012. The written contract also specified that amendments must be made in writing
    and fully executed by both parties. Id. at 78-79. The DOL executed two internal
    project change request documents extending the scope and timeline of the project.
    However, the change requests were not executed by RTT, and no written amendment
    to the contract was executed by either party to extend the expiration of the contract
    9
    or modify other contract terms. Id. at 79. After the DOL refused to compensate RTT
    for work performed after the contract expired, RTT claimed that the contract had been
    extended by certain internal writings of the department and by the parties’ course of
    conduct. Id. at 79. Our Supreme Court held that “even if . . . DOL and RTT waived,
    through their course of conduct, the provision that the contract could be amended
    only in writing and similarly waived or extended the required completion date, this
    conduct could not have waived DOL’s sovereign immunity.” Id. at 82 (2). The Court
    explained that although
    private parties . . . may be able to modify and extend written contracts
    by manifesting their intent to do so even without a written agreement,
    the enforceability of a contract against the [S]tate is governed by the
    Constitution and by statute. . . . General rules of contract law that might
    otherwise support a claim for breach of contract damages between
    private parties, however, will not support a claim against the [S]tate or
    one of its agencies if the contract is not in writing so as to trigger the
    waiver of sovereign immunity.
    (Citations omitted.) Id. at 82 (2).
    Unlike the written contract in RTT Assocs., Inc., supra, the written contract in
    the instant case provides a procedure for obtaining a written Change Order to amend
    the contract, and that procedure provides a method by which parties can bypass the
    10
    necessity for a written Change Order in the event “extraordinary circumstances”
    warrant it. The trial court in its motion denying the County’s motion for summary
    judgment found that the parties complied with Fulton County Procedure 800-6 G (2)
    because the changed work ordered by County administrators were necessary to avoid
    delay to the “critical path schedule of the work[,]” and thus constituted “extraordinary
    circumstances” which invoked an exception to the written change order requirement
    under Fulton Procedure 800-6 G (2), as incorporated into the parties’ contract.
    However, Fulton Procedure 800-6 G (2), captioned “Extraordinary
    Circumstances[,]” provides a specific procedure that must be followed in order to
    bypass the contractual requirement that any changes be made by a written Change
    Order. Specifically, Fulton Procedure 800-6 G (2) provides that “[t]he County
    Manager is authorized to approve change orders regardless of the amount when due
    to extraordinary circumstances, work must be implemented before the Board of
    Commissioners can act.” These extraordinary circumstances include, inter alia, when
    immediate action must be taken to protect the County’s interest due to a threat of
    “[l]oss of substantial resources due to delay, including delay to critical path
    schedule.” Fulton Procedure 800-6G (2) (d) provides that “[a]t a minimum, the
    following procedures must be observed” in the event of such an extraordinary
    11
    circumstance: (1) the contractor must execute a “written contract Modification” that
    describes the scope of the work and its cost; (2) the department head shall obtain
    approval of the purchasing agent; and (3) the work may proceed upon approval of the
    County Manager, which includes a sign-off sheet, and the County Manager shall
    place the change order on the Board of Commissioners’ agenda.
    In the instant case, SOCO argues that the County ordered more than 30
    modifications to the existing budget and timeline under the Contract. However,
    SOCO does not allege that they followed the procedure outlined under the
    “Extraordinary Circumstances” provision in Fulton Procedure 800-6 G (2) (d). SOCO
    does not allege, and provides no citations to the record, that it provided a written
    contract modification describing the scope of the work or its cost, that the purchasing
    agent approved the changes, or that the County Manager approved the changes or the
    sign-off sheet before work commenced. Indeed, SOCO relies heavily on the
    contentions deemed admitted as a matter of law when the County failed to respond
    timely to its request for admissions. However, as our Supreme Court noted in RTT
    Assocs. Inc., supra, sovereign immunity cannot be waived by the County’s actions
    outside of the written contract, and this “rule would apply to any admissions made by
    [the County] that the contract had been extended, when the evidence shows any
    12
    agreements to extend did not meet the written contract requirement set forth in the
    applicable statute and constitutional provision relating to the waiver of sovereign
    immunity.” Id. at 87 (3).
    The constitutional provision “expressly reserving the power to waive sovereign
    immunity to the legislature does not allow for exceptions to be created by the courts.”
    (Citation and punctuation omitted.) Id. Accordingly, this Court cannot create an
    exception to the rules regarding waiver of sovereign immunity based upon any
    reliance that SOCO may have placed on the County’s request for changes, upon the
    parties’ course of conduct, or upon facts deemed admitted pursuant to OCGA § 9-11-
    36 (2). Accordingly, we reverse the trial court’s denial of the County’s summary
    judgment on all of SOCO’s claims arising from modifications of the May 2013
    contract. Although “this result may seem harsh, parties are presumed to know the law,
    and are required ‘at their peril’ to ascertain the authority of a public officer with
    whom they are dealing.” (Citation omitted.) Id. Further, the “fundamental purpose of
    sovereign immunity is the protection of [S]tate funds[, and] it follows that one of the
    purposes of the Constitution’s requirement that contracts must be in writing in order
    to invoke the [S]tate’s waiver of sovereign immunity is to protect the [S]tate from
    13
    exposure to unanticipated damages.” (Citation and punctuation omitted.) Id. at 87-88
    (3).
    2. The County argues that the trial court erred in denying its motion to
    withdraw admissions and in denying its motion for reconsideration of that denial. The
    County argues that the trial court misapplied OCGA § 9-11-36 (b) and that the trial
    court should not have deemed certain requests for admissions admitted, as they are
    based on inappropriate legal conclusions. For the following reasons, we affirm in part
    and reverse in part.3
    Under Georgia law,
    [a] party’s failure to timely respond to requests for admission
    conclusively establishes as a matter of law each of the matters addressed
    in the requests. This is true even if the requested admissions require
    opinions or conclusions of law, so long as the legal conclusions relate
    to the facts of the case. The language in OCGA § 9-11-36 (a) is clear,
    unambiguous, and unequivocal and means just what it says. One must
    comply strictly and literally with the terms of the statute upon the peril
    of having his response construed to be an admission. Thus, matters
    deemed admitted under this statute become solemn admissions in judicio
    and are conclusive as a matter of law on the matters stated and cannot
    3
    As found in Division 1 herein, we have concluded that the admissions do not
    act as a waiver on sovereign immunity for claims related to the alleged modifications.
    Our analysis herein relates to admissions related to the original written contract.
    14
    be contradicted by other evidence unless the admissions are withdrawn
    or amended on formal motion.
    (Citation omitted.) Adewumi, supra at 277 (2).
    The trial court is vested with broad discretion to permit withdrawal, and “the
    trial court’s ruling on this issue may be reversed only upon a showing of abuse of
    discretion.” (Citation omitted.) Parham v. Weldon, 
    333 Ga. App. 744
    , 746 (1) (776
    SE2d 826) (2015).
    (a) The County argues that the trial court abused its discretion by “grossly
    misapplying” OCGA § 9-11-36 (b)’s two-part test.
    There is a two-pronged test to be employed when considering a motion to
    withdraw admissions. A court may grant a motion to withdraw when “[1] the
    presentation of the merits of the action will be subserved thereby and [2] the party
    who obtained the admission fails to satisfy the court that withdrawal or amendment
    will prejudice him in maintaining his action or defense on the merits.” OCGA § 9-11-
    36 (b). Accord Parham, supra at 746 (1). “If the movant satisfies the court on the first
    prong, the burden is on the respondent to satisfy the second prong. Both prongs must
    be established, pursuant to the standard provided in OCGA § 9-11-36 (b).” (Citation
    and punctuation omitted.) Marlowe v. Lott, 
    212 Ga. App. 679
    , 681 (2) (442 SE2d
    15
    487) (1994). “If the movant fails to make the required showing to satisfy the first
    prong of the test, then the trial court is authorized to deny the motion to withdraw the
    admissions.” (Citations omitted.) Turner v. Mize, 
    280 Ga. App. 256
    , 257 (1) (633
    SE2d 641) (2006).
    To prove that the presentation of the merits in this case would be subserved by
    the withdrawal, the County needed to establish that
    the admitted requests either could have been refuted on trial of the issues
    by admissible evidence having a modicum of credibility or that the
    admitted requests were incredible on their face; and that the denials
    being tendered to the court with the motion to withdraw had not been
    offered solely for the purposes of delay.
    (Citations omitted.) Fox Run Properties, LLC v. Murray, 
    288 Ga. App. 568
    , 570-571
    (1) (654 SE2d 676) (2007). “The first prong of the test is not perfunctorily satisfied[,]
    and the desire to have a trial, standing alone, is not sufficient to satisfy the test.”
    (Citation and punctuation omitted.) Turner, supra at 257 (1).
    In support of its motion to withdraw admissions, the County relied upon the
    affidavit of Freddie Robinson. The trial court’s order found that the County did not
    meet its initial burden of showing that presentations of the merits of the action would
    be subserved by withdrawal of the admissions. Specifically, the trial court found that
    16
    the affidavit of County construction manager Freddie Robinson
    proffered by the County in support of its motion to withdraw its
    admissions was insufficient to support their withdrawal, in part, because
    it lacked even a modicum of credibility. It contained facially
    contradictory statements, material misstatements on basic elements of
    the contract, miscounting of performance days, and other statements that
    contradict documents in the record and the County’s own answers to
    Interrogatories.
    (Emphasis supplied.) The trial court further found that the County failed to credibly
    refute specific admitted requests.4
    The County argues in its brief that its supporting affidavit had a sufficient
    modicum of credibility. However, the trial court, after examining the affidavit in
    detail, found the issue not to be one of degree of credibility, but rather, of the utter
    absence of it. Robinson’s affidavit directly contradicted the County’s responses to
    various interrogatories. When asked in Interrogatory 5 why it issued no change orders
    and why payment was withheld from SOCO, the County answered that “SOCO has
    refused to amicably negotiate proposed field changes to a final reconciled amount.”
    4
    In its motion for reconsideration of the trial court’s denial of the County’s
    motion to withdraw admissions, the County filed the affidavit of Felicia Strong-
    Whittaker. However, Strong-Whitaker’s affidavit was not filed until after the trial
    court denied the County’s motion to withdraw the admissions. The trial court
    similarly found Strong-Whittaker’s affidavit to be lacking in credibility.
    17
    In his affidavit, however, Robinson attributes the refusal to issue change orders to
    several different reasons, including: SOCO’s improper management and failure to
    protect the site during bad weather; superintendent burnout; and poor SOCO staffing.
    Further, Robinson miscounted performance days to calculate the completion date of
    the project, and his affidavit contradicts evidence in the record without explanation.
    Robinson averred that the project was only 50 percent complete on March 31, 2014,
    but reports by his superiors show that the project was 65 percent complete two weeks
    before that date and 80 percent complete two weeks after it. “Based on these
    inconsistencies, the trial court was . . . authorized to find that [Robinson] lacked
    credibility and that the admissions were not false.” (Footnote omitted.) Fox Run
    Properties, LLC, supra at 571 (1) (trial court did not err in denying motion to
    withdraw admissions when supporting affidavit was deemed unreliable because it
    contradicted interrogatories and contained inconsistent statements).
    “Under these circumstances, we cannot conclude that the trial court abused its
    discretion in concluding that [the County] did not present credible evidence to refute
    the admissions.” (Citations omitted.) Id. Compare Bailey v. Chase Third Century
    Leasing Co., Inc., 
    211 Ga. App. 60
    , 61-62 (1) (438 SE2d 172) (1993) (trial court
    abused its discretion by denying a motion to withdraw admissions in the face of a
    18
    sworn affidavit and other admissible evidence that cast doubt on the veracity of the
    admissions).
    Because the trial court did not err in concluding that the County had not
    satisfied its burden in the first prong of this test, we need not address the second
    prong. Turner, supra at 257 (1).
    (b) The County next argues that the trial court should have withdrawn
    Admissions Nos. 23, 36 and 37 on the grounds that they are based on inappropriate
    legal conclusions.
    (i) We find no error as to Requests for Admissions Nos. 23 and 36. Request for
    Admission No. 23 asks the County to admit that SOCO “fully performed its
    obligations under the contract[.]” Request for Admission No. 36 asks the County to
    admit that “Fulton County acted with bad faith intentionally, with malice, and with
    intent to do harm to SOCO in the County’s administration of the Contract.” Requests
    for admissions requiring opinions or conclusions of law are specifically permitted,
    as long as the legal conclusions relate to the facts of the case. G. H. Bass & Co. v.
    Fulton County Bd. of Tax Assessors, 
    268 Ga. 327
    , 329 (1) (486 SE2d 810) (1997).
    See also State Dept. of Corrections v. Developers Surety & Indemity Co., 
    291 Ga. 741
    (763 SE2d 868) (2016) (affirmed on cert. by State Dept. of Corrections v. Developers
    19
    Surety & Indemnity Co., 
    324 Ga. App. 371
     (750 SE2d 697) (2013) (matters deemed
    admitted by the Georgia Department of Corrections as a matter of law established that
    it materially breached its contract with a government contractor for re-roofing certain
    buildings). Requests are not objectionable because they seek admission of the
    ultimate issue in the case but are only objectionable if they seek admission of purely
    abstract principles unrelated to the facts of the case. G. H. Bass & Co., supra at 328
    (1). A determination of whether the County acted with bad faith is not such an
    abstract proposition of law.
    (ii) The County argues that the trial court should have withdrawn Request for
    Admission No. 37. We agree.
    Request for Admission No. 37 asks the County to admit that “Fulton County
    is liable to SOCO for each of the damages pleaded and prayed for in its Complaint.”
    The damages prayed for in the Complaint included, inter alia, “pre-judgment interest
    of at least $25,866.22” on funds that SOCO claims the County unlawfully withheld,
    “damages in excess of $406,732.53” resulting from the “County’s refusal to
    administer change orders and compensate SOCO for acceleration of the work”;
    “damages in excess of $25,000.00” for the County’s interference with SOCO’s
    subcontractors; “327,756.99 for unabsorbable extended home office expense,” and
    20
    “$638,876.50 due to profit on federal work lost as a result of Fulton County’s
    wrongful withholding or retainage and intentional delay of project closeout and the
    resultant loss of bonding capacity[.]”
    The trial court should have withdrawn Request for Admission No. 37 because
    some of the damages sought in the complaint arose from causes of action related to
    the unwritten change orders on which the County is entitled to sovereign immunity,
    as noted in Division 1. Further, other damages, such as SOCO’s lost profits claim, are
    outside the County’s realm of knowledge. “While admissions resulting from a party’s
    failure to respond to requests for admission are . . . generally considered conclusive
    until withdrawn . . . , a party obviously has not the capacity to admit something which
    is patently outside the realm of his knowledge.” (Citations omitted.) Cole v. Smith,
    
    182 Ga. App. 59
    , 63 (3) (354 SE2d 835) (1987). Accord K-Mart Corp. v. Hackett,
    
    237 Ga. App. 127
    , 133 (4) (514 SE2d 884) (1999) (trial court did not abuse its
    discretion in allowing admission that defendant injured each plaintiff in the amount
    of $2,500,000.00 because the answer was outside the knowledge of the defendant).
    4. The County argues that the trial court erred in awarding attorney fees as part
    of the summary judgment order. For the following reasons, we vacate and remand the
    trial court’s award of attorney fees.
    21
    The trial court’s summary judgment order found that the County was liable for
    “reasonable attorneys’ fees and litigation costs as SOCO has incurred since this
    lawsuit was filed on May 8, 2015[,]” and directed SOCO to submit a statement of
    such costs to the Court and to Fulton County within 21 days from the order, and gave
    the County 10 days in which to make specific objections to SOCO’s statement of fees.
    In Division 1, supra, we reverse the trial court’s denial of the County’s motion for
    summary judgment on SOCO’s causes of action arising from the modifications to the
    original contract made without written change orders. However, the trial court’s order
    does not specify under which statute it awarded attorney fees or on which conduct it
    based the award of attorney fees. Accordingly, we cannot determine whether the trial
    court’s award was based upon claims from which we have concluded the County is
    protected under the doctrine of sovereign immunity or which statute the trial court
    relied upon in awarding attorney fees. See Aaron v. Ga. Farm Bureau Mut. Ins. Co.,
    
    297 Ga. App. 403
    , 408 (c) (677 SE2d 419) (2009) (since appellant “cannot succeed
    on his breach of contract . . . claims, he likewise cannot succeed on a claim for
    attorney fees”) (footnote omitted). Therefore, we vacate the trial court’s grant of
    attorney fees to SOCO and remand to the trial court for further consideration in light
    of this opinion. See Cohen v. Nudelman, 
    269 Ga. App. 517
    , 523 (5) (604 SE2d 580)
    22
    (2004) (vacating an award of attorney fees and remanding to the trial court when the
    record is unclear on which statutory basis the trial court relied to grant the award of
    fees).
    Judgment affirmed in part, reversed in part, vacated in part, and case
    remanded. Dillard, C. J., and Self, J., concur.
    23
    