Milliken & Company v. Georgia Power Company ( 2020 )


Menu:
  •                           THIRD DIVISION
    DILLARD, P. J.,
    MARKLE, J., and SENIOR APPELLATE JUDGE PHIPPS
    NOTICE: Motions for reconsideration must be
    physically received in our clerk’s office within ten
    days of the date of decision to be deemed timely filed.
    http://www.gaappeals.us/rules
    February 20, 2020
    In the Court of Appeals of Georgia
    A17A1706, A17A2027, A17A2029, A17A2030, A17A2031,
    A18A0516. MILLIKEN & COMPANY v. GEORGIA
    POWER COMPANY (six cases).
    PHIPPS, Senior Appellate Judge.
    This is the second appearance of these companion appeals before this Court.
    In Milliken & Co. v. Ga. Power Co., 
    344 Ga. App. 560
     (811 SE2d 58) (2018)
    (“Milliken I”), we affirmed the trial court’s grant of summary judgment to defendant
    Georgia Power Company as to seven cross-claims filed against it by defendant
    Milliken & Co., the owner of the land where the plane crash that injured or killed
    plaintiffs occurred. The trial court had held that a hold-harmless provision in a 1989
    easement granted to Georgia Power operated as a covenant not to sue rather than an
    indemnity agreement. See 
    id. at 561-562
    . We held that the easement provision was
    void as against public policy under former OCGA § 13-8-2, Georgia’s anti-indemnity
    statute. Id. at 564. The Supreme Court of Georgia granted certiorari and reversed,
    holding that the easement provision was not void because it “did not require
    indemnification” for damages “caused solely by [Milliken’s] negligence[.]” (Footnote
    omitted; emphasis in original.) Milliken & Co. v. Georgia Power Co., 
    306 Ga. 6
    , 13
    (1) (b) (829 SE2d 111) (2019) (“Milliken II”). Our Supreme Court then remanded the
    case to this Court with direction to address Milliken’s original assertions on appeal.
    Id. at 14. Accordingly, we now consider whether the trial court erred in granting
    summary judgment on Milliken’s cross-claims. Because we conclude that the
    easement did create an indemnity obligation in favor of Milliken, we reverse.
    The relevant facts are laid out as follows in the Supreme Court’s opinion in
    Milliken II:
    In 2013, a small business jet crashed into a Georgia Power Company
    transmission pole on Milliken & Company’s property near the
    Thomson-McDuffie Regional Airport in Thomson, Georgia. The two
    pilots were injured and the five passengers died. In the wake of the
    crash, the pilots and the families of the deceased passengers filed a total
    of seven lawsuits against multiple defendants, including Georgia Power
    and Milliken. The complaints in those seven suits alleged that a
    transmission pole located on Milliken’s property was negligently erected
    and maintained within the airport’s protected airspace. The record
    evidence shows that Georgia Power constructed the transmission pole
    2
    on Milliken’s property for the purpose of providing electricity to
    Milliken’s manufacturing-plant expansion, and that the pole was
    constructed pursuant to a 1989 Easement between Georgia Power and
    Milliken. In each of the seven suits, Milliken filed identical cross-claims
    against Georgia Power, alleging that Georgia Power was contractually
    obligated to indemnify Milliken “for all sums that Plaintiffs may recover
    from Milliken” under Paragraph 12 of the 1989 Easement, which
    provides:
    “[Georgia Power] Company, its successors or assigns shall hold
    [Milliken], its successors or assigns harmless from any damages to
    property or persons (including death), or both, which result from
    [Georgia Power] Company’s construction, operation or maintenance of
    its facilities on said easement areas herein granted.”1
    1
    Our Supreme Court also noted that Paragraph 12 of the 1989 Easement
    granted Georgia Power a right of way
    to construct, erect, install, operate, maintain, inspect, reconstruct, repair,
    rebuild, renew and replace thereon a substation and overhead and
    underground electric transmission, distribution and communication
    lines, with necessary or convenient towers, frames, poles, wires,
    manholes,     conduits,     transformers,     switches,     breakers     and
    communication equipment, with the necessary wires, fixtures,
    appliances, protective wires and devices, buildings, sewers, drains,
    fences and other facilities in connection therewith . . . . including the
    right . . . to clear, grade, fill excavate, ditch and drain said substation
    tract[.]
    3
    Georgia Power moved for summary judgment on the cross-claims. The
    trial court granted summary judgment to Georgia Power in all seven
    actions, reasoning that Paragraph 12 of the 1989 Easement operates as
    a covenant not to sue, rather than as an indemnity agreement, because
    it “nowhere contains the word ‘indemnity’” and “it is not so
    comprehensive regarding protection from liability.”
    Milliken II, 306 Ga. at 6-7.2
    On appeal, Milliken asserts that the trial court erred when it granted Georgia
    Power summary judgment on the cross-claims because Paragraph 12 indemnifies
    Milliken against all “damages,” including plaintiffs’ claims, resulting from Georgia
    Id. at 8 (1) (a).
    2
    Our Case Nos. A17A1706, A17A2027, A17A2029, A17A2030, and
    A17A2031, which were addressed in the Supreme Court’s Case No. S18G0876, arise
    from the trial court’s entry of judgment in favor of Georgia Power on Milliken’s
    cross-claims in five plaintiffs’ actions. See Milliken II, 306 Ga. at 7, n. 1. Our Case
    No. A17A2028 was also remanded by the Supreme Court, see id., but was withdrawn
    from this Court on June 27, 2019. In Case No. S18G1107, granted as to our Case No.
    A18A0516 (a summary affirmance under our Rule 36), the Supreme Court vacated
    and remanded “for further proceedings consistent with” its opinion. Id. at 14-15. We
    note further that Georgia Power has not moved this Court, either on the original
    appeals or on remand from the Supreme Court, to supplement the record concerning
    an apparent defense verdict in Milliken’s favor in one of the plaintiffs’ cases, which
    might have mooted our Case No. A17A2030. See id. at 14, n.7. We therefore take no
    action on the question.
    4
    Power’s negligent construction, operation, or maintenance of the transmission pole
    on Milliken’s property. We agree.
    “The construction of a contract is a question of law for the court.” OCGA §
    13-2-1. In construing a contract so as implement the intentions of the parties, a court
    is first required “to look to the plain meaning of the words of the contract[.]” (Citation
    and punctuation omitted.) Argo v. G-Tec Svcs., 
    338 Ga. App. 608
    , 609 (1) (791 SE2d
    193) (2016).
    [I]t is a cardinal rule of contract construction that a court should, if
    possible, construe a contract so as not to render any of its provisions
    meaningless and in a manner that gives effect to all of the contractual
    terms. “Words generally bear their usual and common signification; but
    technical words, words of art, or words used in a particular trade or
    business will be construed, generally, to be used in reference to this
    peculiar meaning.” OCGA § 13-2-2 (2). Furthermore, courts must favor
    a construction that upholds the contract in whole and in every part, and
    look at the whole contract in construing any part. OCGA § 13-2-2 (4).
    Courts should not render any language in a contract as superfluous, and
    any construction that renders portions of the contract language
    meaningless should be avoided.
    (Citations and punctuation omitted.) Id. at 609-610 (1).
    5
    Specifically, “[i]n a contract of indemnity the indemnitor, for a consideration,
    promises to indemnify and save harmless the indemnitee against liability of the
    indemnitee to a third person, or against loss resulting from such liability.” (Footnote
    and punctuation omitted.) Old Republic Nat’l Title Ins. Co. v. Darryl J. Panella, LLC,
    
    319 Ga. App. 274
    , 277 (734 SE2d 523) (2012). In order to create a binding contract
    for indemnity, the indemnitor need only express the intent to protect the indemnitee
    against a loss; the contract “is not required to contain the magic word ‘indemnify.’”
    (Footnote omitted.) Id.; see also Black’s Law Dictionary, 848 (10th ed. 2014)
    (defining “indemnify” as “to reimburse for a loss suffered because of a third party’s
    or one’s own act or default; hold harmless”) (emphasis supplied); Liberty Mutual Ins.
    Co. v. Alsco Const., 
    144 Ga. App. 307
    , 311 (240 SE2d 899) (1977) (agreement to
    hold “harmless and free of liability for injury to or death of any person and for loss
    of or damage to” equipment was, “[u]nder clear and unequivocal standards,”
    “sufficient to require indemnification”).
    We cannot agree with the trial court’s conclusion that Paragraph 12 amounts
    to a covenant not to sue. The paragraph’s reference to personal injuries, including
    death, would be rendered mere surplusage under that reading because Georgia Power
    could never have standing to assert a claim for wrongful death. See Tolbert v. Maner,
    6
    
    271 Ga. 207
    , 208 (518 SE2d 423) (1999) (because OCGA § 51-4-2 is in derogation
    of the common law, only those persons specified in the statute may maintain a
    wrongful death action); Argo, 338 Ga. App. at 609 (1) (“any construction that renders
    portions of the contract language meaningless should be be avoided”) (citations
    omitted).
    Paragraph 12 refers not to claims or suits, but rather to “damages . . . resulting
    from” Georgia Power’s activities on the easement, and seeks to “hold [Milliken]
    harmless” as to “damages to property or persons (including death), or both, which
    result from [Georgia Power’s] construction, operation or maintenance of its facilities
    on said easement areas herein granted.” It is also beyond dispute that the claims
    asserted by plaintiffs, whatever their ultimate merit, arise from “damages” or injury
    to them, “including death,” resulting from Georgia Power’s “construction, operation
    or maintenance” of the transmission pole, located “on said easement area,” into which
    the plane crashed. See Liberty Mutual, 144 Ga. App. at 311 (2); Rankin v. Smith, 
    113 Ga. App. 204
    , 205-207 (147 SE2d 649) (1966) (a party’s agreement “to hold harmless
    and release” other parties “from any and all liability and obligations resulting from”
    the parties’ status as stockholders or officers was “in the nature of an indemnity
    contract”) (emphasis supplied).
    7
    Nor is this a case in which Milliken will be indemnified from its own
    negligence, which Georgia law will not authorize in the absence of an explicit
    undertaking by the indemnitor. Viad Corp. v. U. S. Steel Corp., 
    343 Ga. App. 609
    ,
    614-615 (1) (808 SE2d 58) (2017) (“[W]e will not interpret ‘contractual indemnities
    [to] extend to losses caused by an indemnitee’s own negligence unless the contract
    expressly states that the negligence of the indemnitee is covered’”), quoting Ryder
    Integrated Logistics v. BellSouth Telecommunications, 
    281 Ga. 736
    , 737-738 (642
    SE2d 695) (2007). Rather, as Milliken acknowledged below, and as our Supreme
    Court explained,3 Milliken cannot be owed indemnity unless Georgia Power is also
    found to have been negligent. See Benson Paint Co. v. Williams Const. Co., 
    128 Ga. App. 47
    , 50 (2) (195 SE2d 671) (1973) (if two defendants’ negligence “combined to
    cause the plaintiff’s injuries,” then a provision granting indemnity by one to the other
    would be enforceable “under the express terms of the contract”).
    For all these reasons, we conclude that Paragraph 12 of the 1989 Easement
    plainly includes Georgia Power’s promise to indemnify Milliken from any personal
    3
    Milliken II, 306 Ga. at 12, n. 5 (“indemnification could potentially apply in
    certain instances where the combined negligence of Georgia Power and Milliken . .
    . results in damages. But none of these scenarios would implicate [OCGA § 13-8-2’s]
    prohibition on indemnification for an indemnitee’s ‘sole negligence’”).
    8
    injury, death, or other “damages” arising from the claims of third parties, such as
    plaintiffs, “result[ing] from” Georgia Power’s activities on the easement. The trial
    court therefore erred when it granted Georgia Power summary judgment on
    Milliken’s cross-claims for indemnity.
    Judgments reversed. Dillard, P. J., and Markle, J., concur.
    9
    

Document Info

Docket Number: A18A0516

Filed Date: 3/5/2020

Precedential Status: Precedential

Modified Date: 3/5/2020