Ted's Wiring Service, Ltd. v. Department of Transportation ( 2021 )


Menu:
  •   *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    Electronically Filed
    Supreme Court
    SCWC-XX-XXXXXXX
    27-SEP-2021
    08:57 AM
    Dkt. 36 MO
    SCWC-XX-XXXXXXX
    IN THE SUPREME COURT OF THE STATE OF HAWAII
    TED=S WIRING SERVICE, LTD.,
    Respondent/Plaintiff-Counterclaim Defendant-Appellee,
    vs.
    DEPARTMENT OF TRANSPORTATION, STATE OF HAWAII;
    Petitioner/Defendant-Counterclaimant-Appellant.
    CERTIORARI TO THE INTERMEDIATE COURT OF APPEALS
    (CAAP-XX-XXXXXXX; CIV. NO. 1CC131001910)
    MEMORANDUM OPINION
    (By: Recktenwald, C.J., Nakayama, McKenna, Wilson, and Eddins, JJ.)
    Petitioner/Defendant-Counterclaimant-Appellant
    Department of Transportation, State of Hawaiʻi (DOT) seeks review
    of the Intermediate Court of Appeals’ (ICA) February 4, 2020
    Judgment on Appeal entered pursuant to its December 26, 2019
    Memorandum Opinion.     The ICA vacated the May 20, 2016 Judgment
    of the Circuit Court of the First Circuit (circuit court).
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    This case arises from a contract dispute between DOT
    and Respondent/Plaintiff-Counterclaim Defendant-Appellee Ted’s
    Wiring Service, Ltd. (TWS).      DOT and TWS entered into a contract
    for goods and services, wherein TWS agreed to build a ground
    transportation tracking system for DOT at the Daniel K. Inouye
    International Airport (“the airport”).         After TWS believed it
    had fulfilled its obligations under the contract, DOT notified
    TWS that it was not satisfied with TWS’s performance and
    proposed withholding the remaining balance due to TWS under the
    contract.
    TWS filed an action against DOT in the circuit court
    to recover the remaining balance under the contract and DOT
    filed a counterclaim for damages.        Both parties filed motions
    for summary judgment.     The circuit court ruled in favor of TWS,
    finding that there were no genuine issues of material fact and
    concluding as a matter of law that TWS had completed the
    contract and that DOT accepted the system built by TWS.            The
    circuit court entered a single judgment in favor of TWS and
    against DOT on all claims asserted in the action.
    DOT appealed to the ICA and argued that the circuit
    court erred by (1) concluding that TWS was entitled to summary
    judgment; and (2) disregarding the contract’s non-waiver
    provision, which states that final acceptance by DOT does not
    preclude it from recovering from TWS.        The ICA held that the
    2
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    circuit court erred by granting TWS’s motion for summary
    judgment because genuine issues of material fact exist as to
    whether TWS breached the contract, whether TWS satisfied its
    contractual obligations, and whether DOT accepted TWS’s
    performance.    Because the ICA concluded that there was a genuine
    issue of material fact as to whether DOT accepted TWS’s
    performance, the ICA declined to address the effect of the
    contract’s non-waiver provision.         However, the ICA’s decision
    included a footnote stating that DOT’s appeal did not challenge
    the circuit court’s entry of judgment against it on its
    counterclaim.   The ICA vacated the circuit court’s judgment and
    remanded for further proceedings.
    In its application for writ of certiorari, DOT argues
    that the ICA erred by stating that DOT did not challenge the
    circuit court’s entry of judgment against DOT on its
    counterclaim.    DOT maintains that it is still entitled to pursue
    its counterclaim for damages on remand.         DOT argues that the
    sole issue in this case is whether TWS satisfied or breached the
    contract and that TWS’s claim for the contract balance and DOT’s
    counterclaim for damages are intertwined.         DOT maintains that by
    appealing the circuit court’s judgment in favor of TWS, it
    appealed both the judgment in favor of TWS on its claim and
    against DOT on its counterclaim.
    3
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    We conclude that by appealing the circuit court’s
    judgment, DOT appealed both the circuit court’s grant of summary
    judgment in favor of TWS on its complaint and against DOT on its
    counterclaim.   Thus, the ICA erred by stating that DOT did not
    challenge the circuit court’s entry of judgment on its
    counterclaim.   Because the ICA concluded that genuine issues of
    material fact exist as to whether the parties modified the
    contract and whether TWS performed under the contract, DOT is
    entitled to pursue its counterclaim for damages on remand.
    Accordingly, we vacate in part the ICA’s
    February 4, 2020 Judgment on Appeal as to DOT’s counterclaim and
    affirm the ICA’s Judgment on Appeal in all other respects.             We
    remand to the circuit court for further proceedings consistent
    with this opinion.
    I.   BACKGROUND
    In June 2000, TWS and DOT entered into a contract for
    goods and services (“the Contract”), wherein TWS agreed to build
    an Automatic Vehicle Identification system (“AVI System”) that
    uses radio frequency technology to help manage commercial ground
    transportation providers at the airport (“the Project”).            DOT
    intended to use the AVI System, which consists of antennas at
    the airport’s entrances and exits, computer hardware, and
    software to track and meter ground transportation providers so
    that DOT could send them accurate monthly bills.
    4
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    The Contract specifically incorporated the request for
    proposals (“the RFP”) issued by DOT, which set forth the
    threshold requirements for the Project.            As relevant here, the
    RFP required the AVI System to “provide an automated record
    keeping and collection system capable of generating invoices and
    reports to the user for confirmation of charges/withdrawals.”
    The Contract required TWS to complete performance by installing
    the AVI System within eight months of the date that DOT issued
    the notice to proceed and then operating and maintaining the
    system for an additional two years after installation.
    DOT issued the notice to proceed on December 15, 2000,
    and the original completion date for the Project was
    August 13, 2003.       However, work on the Project was delayed by
    the September 11, 2001 terrorist attacks, unanticipated
    difficulties in designing the AVI System, and difficulties in
    obtaining DOT’s approval of the Concept of Operations (COP) for
    the Project.1      DOT finally approved the COP on May 19, 2003.
    By letter dated May 27, 2003, TWS proposed changing
    the hardware in the AVI System to a single server because
    1     While the RFP laid out the threshold requirements for the AVI System,
    the COP described in detail how the AVI System would operate and the methods
    it would use. The COP was a document developed by TWS and the Project could
    not begin until DOT approved it.
    In May 2002, DOT rejected TWS’s initial proposed COP because it did not
    meet all of the specifications set forth in the RFP. DOT requested that TWS
    resubmit a proposed COP for approval that included all of the RFP
    specifications and reminded TWS that “any changes and/or adjustments to the
    RFP requires that an [sic] Amendment or Change Order to the Contract.”
    5
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    technology had improved in the years since the Project was first
    proposed and a dual server was no longer necessary.           DOT
    responded to TWS in writing to acknowledge receipt of the single
    server proposal, stating that it “ha[d] no additional input at
    this time[,]” as “the proposed changes ought to meet the
    specifications of your contract,” and DOT would “defer to your
    knowledge and expertise.”      (Emphasis added.)
    By letter dated October 15, 2003, TWS clarified to DOT
    the function of the AVI System software and specified the twelve
    reports the software would generate.        On November 4, 2003, DOT
    notified TWS that it approved of TWS’s description of the twelve
    submitted reports.
    Because of delays, the parties agreed to extend the
    deadline for installation and testing of the AVI System to
    April 30, 2009.    By letter dated June 23, 2009, DOT declared TWS
    to be in default of its obligations under the Contract for
    failure to complete installation and testing by April 30, 2009.
    DOT suspended work on the Project the following day.
    On October 13, 2009, Travelers Casualty and Surety
    Company of America (Travelers), the Contract surety company,
    entered into a Takeover Agreement with DOT to complete the
    Project.   Travelers selected TWS to serve as the completion
    contractor.
    6
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    By February 2010, all of the hardware and software for
    the AVI System was installed.          DOT indicated in a letter to
    Travelers that the AVI System software was “evaluated and found
    to be functional” and that the two-year operations and
    maintenance period, during which TWS would provide support to
    DOT, would commence on February 15, 2010.
    On February 15, 2012,2 DOT notified Travelers that it
    was not satisfied with the functionality of the software because
    of errors that occurred when DOT ran the billing report.                DOT
    stated that it would not deem the Project to be complete until
    the software issue was resolved.
    By letter dated March 27, 2012, DOT wrote to Travelers
    to “acknowledge[] the completion of the two-year operations and
    maintenance period as of February 29, 2012.”             However, DOT
    stated that it was still not satisfied with the functionality of
    the AVI System software, claiming that it did not satisfy the
    RFP because it did not provide accurate reports.              Because DOT
    did not believe that TWS could satisfactorily resolve the
    software issues, DOT stated that it was “willing to accept the
    installed system ‘as is’ and consider the Takeover Agreement
    completed[.]”      DOT stated that it would withhold the outstanding
    balance due under the Takeover Agreement and use those funds to
    2     Because the two-year operations and maintenance period required by the
    Contract commenced on February 15, 2010, the operations and maintenance
    period was scheduled to conclude on February 14, 2012.
    7
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    “correct the issues with the current software on its own accord
    with another software consultant.”
    A.     Circuit Court Proceedings3
    On July 9, 2013, TWS filed an action against DOT in
    the circuit court seeking to recover the remaining balance under
    the Contract.      On July 31, 2013, DOT filed a counterclaim
    against TWS for damages for lost revenue and expenses incurred
    by DOT because the Project was not completed on time and the AVI
    System software failed to function as expected.4
    On June 2, 2015, TWS filed a motion for summary
    judgment on all claims asserted in its complaint and on all
    counterclaims asserted by DOT.
    On September 11, 2015, DOT filed a motion for partial
    summary judgment on all claims asserted in TWS’s complaint and
    on all of DOT’s counterclaims for damages, except lost revenue
    and additional security costs.
    The circuit court heard TWS’s motion for summary
    judgment on September 9, 2015, and heard DOT’s motion for
    partial summary judgment on October 7, 2015.
    3      The Honorable Jeannette H. Castagnetti presided.
    4     In its discovery responses, DOT divided its damages into four
    categories: (1) additional expense to hire an outside contractor to supervise
    completion of the Project; (2) additional security costs incurred because DOT
    was unable to reduce security as planned, once the AVI System was
    implemented; (3) the entire Contract amount; and (4) lost revenue because the
    AVI System was not completed and operating by the original project completion
    date.
    8
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    During the October 7, 2015 hearing, the circuit court
    ruled that TWS was entitled to summary judgment on its claim for
    the outstanding balance due under the Contract because there
    were no genuine issues of material fact.            The circuit court
    concluded that TWS “completed the contract as extended and
    modified by DOT and [TWS]” and “[TWS] performed under the
    contract to the DOT’s satisfaction, as agreed and modified by
    the parties.”      The circuit court further concluded that DOT
    accepted the AVI System.
    As to DOT’s counterclaims, the circuit court orally
    ruled that TWS was entitled to summary judgment based on the
    circuit court’s conclusion that TWS did not breach the Contract.5
    Finally, the circuit court concluded that because “[TWS] is
    entitled to judgment as a matter of law on its claim for
    retainage and amounts owing as well as the counterclaim asserted
    by the [DOT], and the [DOT] would not, therefore, be entitled to
    partial summary judgment as the [DOT] has moved for.”               (Emphasis
    added.)
    5     The circuit court also stated its conclusion that even if TWS had
    breached, DOT did not have a valid claim for damages because (a) DOT did not
    assert a claim for breach of contract based on any untimely performance;
    (b) if DOT had asserted such a claim, it would not be valid because DOT
    agreed to multiple extensions of the time of performance; (c) DOT did not
    incur additional expenses to supervise completion of the Project based on
    TWS’s conduct, but because DOT was understaffed; (d) DOT’s claim for lost
    revenue lacked any legal basis because TWS was not obliged to provide DOT
    with revenue from the AVI System; and (e) DOT’s claim for recovery of the
    entire Contract price failed as a matter of law.
    9
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    On November 12, 2015, the circuit court entered orders
    granting TWS’s motion for summary judgment and denying DOT’s
    motion for partial summary judgment.         The circuit court awarded
    TWS the outstanding balance due under the Contract.
    On May 20, 2016, the circuit court entered final
    judgment in favor of TWS and against DOT.
    B.   ICA Proceedings
    DOT appealed the circuit court’s judgment to the ICA.
    As relevant here, DOT argued on appeal that the circuit court
    erred by (1) concluding, as a matter of law, that (a) the COP
    changed the Contract specifications; and (b) that DOT accepted
    the AVI System; and (2) disregarding the Contract’s non-waiver
    provision, which states that final acceptance by DOT does not
    preclude it from recovering from TWS.         DOT requested that the
    ICA reverse the circuit court’s judgment in favor of TWS, enter
    judgment in favor of DOT “as requested in [DOT]’s motion for
    partial summary judgment,” and remand for a trial on DOT’s
    damages.
    The ICA entered a memorandum opinion (MO) in which it
    concluded that the circuit court erred by granting summary
    judgment in favor of TWS because there were genuine issues of
    material fact regarding whether the COP modified the Contract
    specifications and whether DOT finally accepted the AVI System
    under the terms of the Contract.         Because there was a genuine
    10
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    issue of material fact about whether DOT accepted the AVI
    System, the ICA declined to address the effect of the Contract’s
    non-waiver provision.     The ICA did not address the question of
    whether TWS was entitled to summary judgment as to DOT’s
    counterclaim, stating in footnote 6 of its MO: “TWS also argued
    that it was entitled to judgment as to DOT’s counterclaim for
    damages under the contract.       DOT has not challenged the Circuit
    Court’s entry of judgment against it on its counterclaim on
    appeal.”   (Emphasis added.)
    Accordingly, the ICA vacated the circuit court’s
    May 20, 2016 Judgment in favor of TWS and against DOT and
    remanded for further proceedings “not inconsistent” with its MO.
    The ICA entered its Judgment on Appeal on February 4, 2020.
    II.    DISCUSSION
    In its application for writ of certiorari, DOT argues
    that the ICA erred by stating in footnote 6 of its MO that “DOT
    has not challenged the Circuit Court’s entry of judgment against
    it on its counterclaim on appeal.”        DOT contends that by
    appealing the circuit court’s judgment in favor of TWS and
    against DOT, it appealed all claims asserted in the action —
    which encompassed both the award of the remaining balance of the
    Contract in favor of TWS and DOT’s counterclaim for damages.
    According to DOT, the sole issue in this case is whether TWS
    performed under the Contract and the parties’ competing claims
    11
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    regarding whether the Contract was modified and whether DOT
    accepted the AVI System are inextricably intertwined.               DOT
    contends that footnote 6 contradicts the ICA’s conclusion that
    TWS was not entitled to summary judgment because there were
    genuine issues of material fact as to which party defaulted on
    the Contract.      Accordingly, DOT maintains that it is still
    entitled to pursue its counterclaim for damages against TWS on
    remand.
    Conclusions of law are reviewed de novo under the
    right/wrong standard of review.          Maria v. Freitas, 
    73 Haw. 266
    ,
    270, 
    832 P.2d 259
    , 262 (1992).          In this case, the ICA concluded
    as a matter of law that the circuit court erred by granting
    summary judgment in favor of TWS and against DOT because genuine
    issues of material fact exist.          The ICA also concluded that DOT
    failed to challenge on appeal the circuit court’s entry of
    judgment against it on its counterclaim for damages.6              For the
    following reasons, we agree with DOT that footnote 6 is wrong.
    The ICA erred by concluding that DOT appealed only the entry of
    judgment in favor of TWS on its claim and did not appeal the
    circuit court’s judgment on its counterclaim.
    6     We note that the ICA cited no basis for its conclusion in footnote 6
    that “DOT has not challenged the Circuit Court’s entry of judgment against it
    on its counterclaim on appeal.”
    12
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    First, the circuit court issued a single judgment in
    favor of TWS and against DOT “on all claims asserted in the
    action.”7     Pursuant to Hawaiʻi Rules of Appellate Procedure Rule
    3(c)(2) (2019), “[t]he notice of appeal shall designate the
    judgment, order, or part thereof and the court . . . appealed
    from[]” and “[a] copy of the judgment or order shall be attached
    as an exhibit.”       (Emphasis added.)      In this case, DOT filed a
    Notice of Appeal “from the [circuit court]’s JUDGMENT filed May
    20, 2016” and attached a copy of the judgment as Exhibit 1.
    Thus, DOT appealed the entire judgment, and its appeal
    necessarily encompassed both the circuit court’s grant of
    summary judgment in favor of TWS on its complaint and against
    DOT on its counterclaim.
    Second, DOT’s appeal in no way indicated that it was
    abandoning its counterclaim for damages.            Instead, in its
    opening and reply briefs, DOT maintained its position that it
    was TWS who breached the Contract.           DOT disputed TWS’s claims
    that (1) the parties modified the Contract; (2) TWS performed
    under the Contract, as modified; and (3) DOT issued a final
    acceptance.      Thus, DOT’s arguments that TWS breached the
    Contract and that DOT was entitled to damages were the same
    7     Not only did the circuit court enter a single judgment, it also treated
    TWS’s complaint and DOT’s counterclaim as a single issue by addressing their
    cross-motions for summary judgment in one oral ruling and stating that “a lot
    of the issues in both motions . . . just overlap.”
    13
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    arguments made by DOT for why TWS was not entitled to the
    remaining balance under the Contract.        It follows that if there
    were genuine issues of material fact as to which party breached
    the Contract, DOT is entitled to pursue its claim for damages on
    remand.
    Third, DOT specifically challenged on appeal the
    circuit court’s failure “to give effect to the non-waiver
    provision of the contract,” which is only relevant to DOT’s
    counterclaim for damages.      DOT argued to the ICA that the non-
    waiver provision entitled DOT to seek damages from TWS, even if
    the circuit court found that TWS did not breach the Contract.
    In addition, the relief that DOT requested on appeal was for the
    ICA to reverse the circuit court’s judgment in favor of TWS,
    enter judgment in favor of DOT “as requested in [DOT]’s motion
    for partial summary judgment,” and remand for a trial on DOT’s
    damages.   (Emphasis added.)
    Thus, DOT’s appeal of the circuit court’s judgment
    encompassed both the entry of judgment in favor of TWS for the
    remaining balance under the Contract and DOT’s counterclaim for
    damages.   To the extent that the ICA concluded that DOT
    failed to challenge on appeal the circuit court’s entry of
    judgment against DOT on its counterclaim, the ICA erred.            The
    14
    *** NOT FOR PUBLICATION IN WEST’S HAWAII REPORTS AND PACIFIC REPORTER ***
    ICA vacated the circuit court’s judgment8 because it concluded
    that genuine issues of material fact exist as to whether DOT
    agreed to modify the Contract specifications and whether DOT
    accepted the AVI System.         For that reason, DOT is entitled to
    pursue its counterclaim for damages against TWS on remand.
    III.   CONCLUSION
    Accordingly, we vacate in part the ICA’s
    February 4, 2020 Judgment on Appeal as to DOT’s counterclaim and
    affirm the ICA’s Judgment on Appeal in all other respects.                We
    remand to the circuit court for further proceedings consistent
    with this opinion.
    DATED:    Honolulu, Hawaiʻi, September 27, 2021.
    John H. Price and                           /s/ Mark E. Recktenwald
    William J. Wynhoff
    for petitioner                              /s/ Paula A. Nakayama
    Department of Transportation,
    /s/ Sabrina S. McKenna
    State of Hawaiʻi
    /s/ Michael D. Wilson
    Keith Y. Yamada,
    Kelly G. LaPorte,                           /s/ Todd W. Eddins
    Christopher T. Goodin,
    and Trisha H.S.T. Akagi
    for respondent Ted’s
    Wiring Service, Ltd.
    8     To “vacate” a judgment is to “nullify or cancel; make void; invalidate”
    it. Black’s Law Dictionary 1862 (11th ed. 2019). Thus, because the ICA
    vacated the circuit court’s judgment which disposed of DOT’s counterclaim for
    damages, the judgment is void and DOT’s counterclaim necessarily survives.
    15
    

Document Info

Docket Number: SCWC-16-0000473

Filed Date: 9/27/2021

Precedential Status: Precedential

Modified Date: 9/27/2021