Friends of Maha'ulepu, Inc. v. Hawai'i Dairy Farms, LLC , 224 F. Supp. 3d 1094 ( 2016 )


Menu:
  • ORDER DENYING: (1) DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT; (2) PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT ON LIABILITY; AND (3) PLAINTIFF’S EX PARTE MOTION FOR LEAVE TO FILE SUPPLEMENTAL DECLARATIONS IN SUPPORT OF REPLY TO MOTION FOR PARTIAL SUMMARY JUDGMENT

    Leslie E. Kobayashi, United States District Judge

    Before the Court are: Defendants Hawaii Dairy Farms, LLC (“Hawaii Dairy”), *1097Ulupono Initiative, LLC (“Ulupono”), and Maha’ulepu Farm LLC’s (“Maha’ulepu,” collectively “Defendants”) Motion for Summary Judgment (“Defendants’ Summary Judgment Motion”), filed on November 25, 2015;1 and Plaintiff Friends of Maha’ule-pu’s (“Friends” or “Plaintiff’) Motion for Partial Summary Judgment on Liability (“Plaintiffs Summary Judgment Motion”), filed on July 1, 2016.2 [Dkt. nos. 41, 107.] On September 1, 2016, Defendants filed their Combined Opposition to (ECF 107) Plaintiffs Motion for Partial Summary Judgment and Reply in Support of (ECF 41) Defendants’ Motion for Summary Judgment [Local Rule 7.9] (“Defendants’ Combined Memorandum”). [Dkt. no. 214.] The same day, Plaintiff filed its reply (“Plaintiffs Reply”).3 [Dkt. no. 218.] Defendant’s Summary Judgment Motion and Plaintiffs Summary Judgment Motion (collectively’ “Summary Judgment Motions”) came on for hearing on September 12, 2016. Also before the Court is Plaintiffs Ex Parte Motion for Leave to File Supplemental Declarations in Support of Reply to Motion for Partial Summary Judgment (ECF No. 107) (“Motion for Leave”), filed on September 1, 2016. [Dkt. nos. 215, 221.4] The Court finds the Motion for Leave suitable for disposition without a hearing pursuant to Rule 7.2(d) of the Local Rules of Practice of the United States District Court for the District of Hawai’i (“Local Rules”). After careful consideration of the motions, memoranda, and the relevant legal authority, Defendants’ Summary Judgment Motion, Plaintiffs Summary Judgment Motion, and the Motion for Leave are all DENIED for the reasons set forth below.

    BACKGROUND

    On June 1, 2015, Plaintiff filed its Complaint. [Dkt. no. 1.] The Complaint seeks declaratory and injunctive relief, as well as civil penalties against Defendants for violations of the Federal Water Pollution Control Act (“Clean Water Act”), 33 U.S.C. § 1251, et seq. [Complaint at ¶ 1.] Specifically, Plaintiff states that it brings the instant suit under 33 U.S.C. § 1365(a)(1)(A). Plaintiff complied with the notice requirements of the Clean Water Act. [Id. ¶ at 10.]

    Plaintiff submits that Hawai’i Dairy has plans for a 699-cow dairy farm in *1098Maha’ulepu, Kaua’i, with the goal of gradually increasing that number to 2,000 cows (“Project Site”). [Id. at ¶ 34.] Plaintiff alleges that Defendants “have engaged and continue to engage in construction and construction support activities,” and have been doing so since early 2014 (possibly as early as January 2014).5 [Id. at ¶¶ 36-37.] On September 9, 2014, Hawaii Dairy submitted a Notice of Intent (“NOI”) to the State of Hawaii, Department of Health (“DOH”), indicating its plan to operate under a National Pollutant Discharge Elimination System (“NPDES”) permit. DOH did not approve the permit. Hawaii Dairy reapplied on May 7, 2015, but the application is still pending. [Id. at ¶¶ 38-39.] Hawaii Dairy therefore does not have an NPDES permit.

    According to Plaintiff, because the proposed dairy farm is uncovered, any precipitation will cause “unpermitted stormwater runoff’ that contains pollutants from the construction. [Id. at ¶ 44.] Sources of these pollutants allegedly include “roadways, raceways, concrete troughs, concrete and compacted limestone platforms for troughs, irrigation pipe installation, wells, and other items, machinery and construction materials stored on the [Project] Site, any vehicles driving on and off the [Project] Site, and others.” [Id. at ¶ 45.] The pollutants themselves include “dirt, debris, sewage sludge from land applications, biological materials, rock, sand, or other materials.” [Id. at ¶ 46.] Plaintiffs assert that the alleged construction activity at the Project Site has resulted in stormwater runoff entering navigable waters, including “a series of ancient agricultural ditches,” the Wai’opili Stream and, a short distance thereafter, the Pacific Ocean. [Id. at ¶ 47.] Moreover, Plaintiff contends that the alleged construction has affected the water quality in Wai’opili Stream. [Id. at ¶ 49.]

    Plaintiff brings two claims for relief: (1) unauthorized discharge of construction pollutants into waters of the United States, in violation of 33 U.S.C. § 1311(a) (“Count I”); [id. at ¶¶ 52-57;] and (2) failure to obtain permit coverage for storm water discharges, in violation of 33 U.S.C. § 1342 (“Count II”) [id. at ¶¶ 58-61]. Plaintiff requests: a declaration that Defendants have violated and continue to violate § 1311(a); a declaration that Defendants have violated and continue to violate § 1342; an order enjoining Defendants from any further storm water discharge containing “construction related pollutants” unless authorized by the relevant permit; an order that Defendants must immediately comply with the permit requirements; an order that Defendants must pay $37,500 a day, per violation, for violations of the Clean Water Act, pursuant to 33 U.S.C. §§ 1319(d), 1365(a) and 40 C.F.R. §§ 19.1-19.4; an order that Defendants must remediate any harm caused by their violations; an order that Defendants must pay all of Plaintiffs attorneys’ and expert witness fees, as well as costs, pursuant to 33 U.S.C. § 1365(d); and “any such other relief as the Court may deem just and proper.” [Complaint, Prayer for Relief ¶¶ A-H.]

    *1099DISCUSSION

    I. Preliminary Matters

    A. Motions for Judicial Notice

    1. First Request for Judicial Notice

    On December 2, 2016, Defendants filed a Request for Judicial Notice in Support of Motion for Summary Judgment (“First Request for Judicial Notice”). [Dkt. no. 53.6] Defendants request judicial notice of the Complaint as well as “[t]he pleadings and papers filed in the above-entitled case.”7 [First Request for Judicial Notice at 2.] This district court has stated:

    The court may “take judicial notice of ‘matters of public recordt,]’ ” as long as the facts noticed are not “subject to reasonable dispute.” Intri-Plex Techs., Inc. v. Crest Grp., Inc., 499 F.3d 1048, 1052 (9th Cir. 2007). However, the court may not take judicial notice of a matter of public record in order to consider “the truth of the facts recited therein.” See [Lee v. City of Los Angeles] id. [250 F.3d 668] at 690 [9th Cir. 2001]. The court may only take judicial notice of the existence of the matter. See id. (citing S. Cross Overseas Agencies, Inc. v. Wah Kwong Shipping Grp. Ltd., 181 F.3d 410, 426-27 (3d Cir. 1999)).
    Matters of public record that may be judicially noticed include records and reports of administrative bodies, see Barron v. Reich, 13 F.3d 1370, 1377 (9th Cir. 1994), and documents filed with courts, “both within and without the federal judicial system, if those proceedings have a direct relation to the matters at issue.” United States v. Borneo, Inc., 971 F.2d 244, 248 (9th Cir. 1992). The court may also take judicial notice of records of government agencies. See Dent v. Holder, 627 F.3d 365, 371-72 (9th Cir. 2010) (taking judicial notice of agency records).

    Bartolotti v. Maui Mem’l Med. Ctr., Civil No. 14-00549 SOM/KSC, 2015 WL 4545818, at *3 (D. Hawai'i July 28, 2015). The First Request for Judicial Notice pertains to court documents, and the Court therefore GRANTS the request. The Court, however, notes that it is only taking judicial notice of the documents’ existence.

    2. Second Motion for Judicial Notice

    On September 1, 2016, Defendants filed a Request for Judicial Notice in Support of (214) Defendants’ Opposition to (EOF 107) Plaintiffs Motion for Partial Summary Judgment (“Second Request for Judicial Notice”). [Dkt. no. 216.] Defendants request judicial notice of: (1) the DOH Clean Water Branch’s (“Clean Water Branch”) “Waiopili Ditch Sanitary Survey, Kauai Part I,” published March 2016 (“DOH Sanitary Survey”); [Second Request for Judicial Notice, Exh. A;] (2) the Clean Water Branch’s instructions on “Forms to be used in E-Permitting Portal for the National Pollution Discharge Elimination System (NPDES) Program” (“NPDES Forms”); [id. Exh. B;] and (3) a letter from then-Acting Director of the United States Environmental Protection Agency (“EPA”) James F. Pendergast to ‘Water Division Directors, Regions 1-10,” dated February 5, 1998 (“2/5/1998 Pendergast Letter”) [id. Exh. C]. For the same reasons and on the same limited basis the Court granted the First Request for Judicial Notice, the Court GRANTS the Second Request for Judicial Notice.

    *1100B. Evidentiary Objections

    On September 1, 2016, Defendants filed Evidentiary Objections to Portions of Declarations of (ECF 110) David J. Erickson, (ECF 111) Bridget Hammerquist, (EOF 113) Eileen Kechloian, (ECF 114) Llewelyn “Billy” Kaoheulauli’i,8 and (ECF 115) Alan E. Faye, Jr. in Support of Plaintiffs Motion for Partial Summary Judgment (107) (“Evidentiary Objections”). [Dkt. no. 220.] Bridget Hammerquist (“Hammerquist”), Eileen Kechloian (“Kechloian”), Billy Kaohelauli’i (“Kaohelauli’i”), and Alan E. Faye, Jr. (“Faye”) are all members of Friends of Maha’ulepu. See Decl. of Bridget Hammerquist (“Hammerquist Decl.”), filed 7/1/16 (dkt. no. 111), at ¶ 7 (“I now serve as President, and am co-founder of, Friends of Maha’ulepu, Inc.”); Decl. of Eileen Kechloian (“Kechloian Decl.”), filed 7/1/16 (dkt. no. 113), at ¶ 4 (“I am director and co-founder of Friends of Maha’ulepu, Inc.”); Decl. of Llewelyn “Billy” Kaohelauli’I (“Kaohelauli’I Decl.”), filed 7/1/16 (dkt. no. 114), at ¶ 5 (“As Friends of Maha’ulepu shares my interest in protecting and preserving the natural resources of Maha’ulepu, I became a member of Friends in about October 2014.”); Decl. of Alan E. Fayé Jr. (“Fayé Decl.”), filed 7/1/16 (dkt. no. 115), at ¶ 8 (“I became a member of Friends in June 2015”).9

    Fed. R. Civ. P. 56(c)(4) states, in relevant part, “[a]n affidavit or declaration used to support or oppose a motion must be made on personal knowledge, set out facts that would be admissible in evidence, and show that the affiant or declarant is competent to testify on the matters stated.” At the hearing, Plaintiff represented that all of the aforementioned declarations were offered for the purpose of establishing Plaintiffs standing. The declarations are appropriate for this purpose. If offered for any other purpose, however, the Court agrees with many of Defendants’ objections. The Court makes the following determinations:

    — -with respect to the Hammerquest Declaration, the Court sustains the objections to paragraphs 6 and 14-19, and overrules the objection as to paragraphs 7;

    — with respect to the Kechloian Declaration, the Court sustains the objections to paragraphs 5, 11-14, and 16;

    — with respect to the Kaohelauli’i Declaration, the Court sustains the objections to paragraphs 9, 11, 14, and 27-28; and

    — with respect to the Fayé Declaration, the Court sustains the objection to paragraph 12, and overrules all other objections.

    Plaintiff also challenges the expert testimony of David J. Erickson (“Erickson”). See Decl. of David J. Erickson (“Erickson Decl.”), filed 7/1/16 (dkt. no. 110).10 Specifically, Defendants argue that Erickson’s expertise is hydrogeology and subsurface waters, and that it is not relevant to issues related to surface water and the *1101Clean Water Act. [Evidentiary Objections at 2.] In addition, Defendants assert that Erickson has no experience in Hawai’i, and also challenge the methods that Erickson used at an inspection of the Project Site. [Id. at 3-5.] Expert testimony is governed by Fed. R. Evid. 702, which states, in relevant part:

    A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if:
    (a) the expert’s scientific, technical, or other specialized knowledge will help the trier of fact understand the evidence or to determine a fact in issue;
    (b) the testimony is based on sufficient facts or data;
    (c) the testimony is the product of reliable principles and methods; and
    (d) the expert has reliably applied the principles and methods to the facts of the case.

    Plaintiff has submitted ample evidence of Erickson’s experience, including with surface water. [Decl. of David J. Erickson in Supp. of Pltf.’s Motion to Compel, filed 11/5/15 (dkt. no. 39), Exh. 1 (Curriculum Vitae of David. J. Erickson).] Further, in considering whether to strike an expert’s declaration, this district court has ruled that, when a party objecting to an expert’s declaration has not requested an evidentia-ry hearing to determine the relevant expert’s qualifications under Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579, 589, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993), “assertions ... do not, without more, establish that [a person] is not quali-fíed as an expert.” Haw. Wildlife Fund v. Cty. of Maui, 24 F.Supp.3d 980, 987 (D. Hawai’i 2014). This district court “therefore decline[d] to strike any part of’ the challenged declaration. Id. Here, too, Defendants have not requested a Daubert hearing, and the Court overrules Defendants’ objections with respect to the Erickson Declaration.

    II. Defendants’ Summary Judgment Motion

    Defendants’ Summary Judgment Motion argues that “the alleged Clean Water Act violations were not occurring or reasonably likely to recur at the time Plaintiff filed its Complaint, and Plaintiff lacks standing to bring its Clean Water Act causes of action.”11 [Mem. in Supp, of Defs.’ Summary Judgment Motion at 18.] Defendants rely heavily Gwaltney of Smithfield, Ltd. v. Chesapeake Bay Foundation, 484 U.S. 49, 56, 108 S.Ct. 376, 98 L.Ed.2d 306 (1987), and states that “citizens suits brought under the Clean Water Act were intended to address present or future violations, not violations which had wholly occurred in the past.” [Id. at 12.] According to Defendants, there were no ongoing violations in the instant matter because: on June 24, 2014, Defendants stopped construction on the Project Site; since that date, only agricultural work has been conducted on the Project Site; and experts have concluded that the precautions that were taken to control stormwa-ter runoff on the Project Site were sufficient to “satisfy applicable stormwater regulations.” [Id. at 15-17.]

    *1102A. Continuing Violations Under the Clean Water Act

    “To establish a violation of the [Clean Water] Act’s NPDES requirements, a plaintiff must prove that defendants (1) discharged, i.e., added (2) a pollutant (3) to navigable waters (4) from (5) a point source.” Comm. to Save Mokelumne River v. East Bay Mun. Util. Dist., 13 F.3d 305, 308 (9th Cir. 1993) (citation omitted). Each of these terms has a specific definition under the act. “Discharge of a pollutant” means “(A) any addition of any pollutant to navigable waters from any point source, [and] (B) any addition of any pollutant to the waters of the contiguous zone or the ocean from any point source other than a vessel or other floating craft.” 33 U.S.C. § 1362(12).12 Moreover, “pollutant” is defined as “dredged spoil, solid waste, incinerator residue, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials, heat, wrecked or discharged equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water.” § 1362(6). “Navigable waters” are “the waters of the United States, including the territorial seas.” § 1362(7). Finally, “point source” is defined as

    any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, or vessel or other floating craft, from which pollutants are or may b discharged. This term does not include agricultural stormwater discharges and return flows from irrigated agriculture.

    § 1362(14).

    Gwaltney concerned the interpretation of § 505(a) of the Clean Water Act, codified as 33 U.S.C. § 1365(a), which states, in relevant part:

    any citizen may commence a civil action on his own behalf—
    (1) against any person (including (i) the United States, and (ii) any other governmental instrumentality or agency to the extent permitted by the eleventh amendment to the Constitution) who is alleged to be in violation of (A) an effluent standard or limitation under this chapter or (B) an order issued by the Administrator or State with respect to such a standard or limitation, or
    (2) against the Administrator where there is alleged a failure of the Administrator to perform any act or duty under this chapter which is not discretionary with the Administrator.

    The United States Supreme Court held that the Clean Water Act did not allow “citizen suits for wholly past violations.” Gwaltney, 484 U.S. at 60, 108 S.Ct. 376. The Gwaltney Court further explained that “we agree that § 505 confers jurisdiction over citizen suits when the citizen-plaintiffs make a good-faith allegation of continuous or intermittent violation.” Id. at 64, 108 S.Ct. 376. Moreover, “[t]he statute does not require that a defendant ‘be in violation’ of the Act at the commencement of suit; rather, the statute requires that a defendant be ‘alleged to be in violation.’ ” Id. (emphasis in Gwaltney). The Ninth Circuit held that,

    On the matter of proving ongoing violations, we agree with the Fourth Circuit’s recent decision on remand from Gwaltney that a citizen plaintiff may prove ongoing violations “either (1) by proving violations that continue on or *1103after the date the complaint is filed, or (2) by adducing evidence from which a reasonable trier of fact could find a continuing likelihood of a recurrence in intermittent or sporadic violations.” Chesapeake Bay Foundation v. Gwaltney [of Smithfield, Ltd.], 844 F.2d 170, 171-72 (4th Cir. 1988), on remand from [484 U.S. 49] 108 S.Ct. 376 [98 L.Ed.2d 306] (1987). We also agree with the Fourth Circuit’s definition of what may constitute a continuing likelihood of violations. “Intermittent or sporadic violations do not cease to be ongoing until the date when there is no real likelihood of repetition.” Id. at 172 (emphasis added). Thus, the Fourth Circuit linked proof of ongoing violations to the Supreme Court’s discussion of mootness in Gwalt-ney:
    Consistent with the guidance of the Supreme Court majority and concurring opinions, the district court may wish to consider whether remedial actions were taken to cure violations, the ex ante probability that such remedial measures would be effective, and any other evidence presented during the proceedings that bears on whether the risk of defendant’s continued violation had been completely eradicated when citizen-plaintiffs filed suit.
    Id. (emphasis added). We believe this is the correct approach to proving ongoing violations or reasonable likelihood of continuing violations under Gwaltney.

    Sierra Club v. Union Oil Co. of Cal., 853 F.2d 667, 671 (9th Cir. 1988).

    B. Regulatory Framework of the Clean Water Act

    1. General Background

    This district court has described the background of the Clean Water Act:

    Congress enacted the Clean Water Act in 1972 “to restore and maintain the chemical, physical and biological integrity of the Nation’s waters.” 33 U.S.C. §§ 1251-1386. The [Clean Water] Act prohibits discharge of any pollutants into the nation’s waters except when specifically authorized under the [Clean Water] Act. 33 U.S.C. § 1311(a). Pursuant to section 402(a), National Pollutant Discharge Elimination System (“NPDES”) permits can be issued to particular entities, allowing them to discharge limited amounts of pollutants into surface waters. 33 U.S.C. § 1342(a). Section 402(b) also permits each state to implement the Clean Water Act through its own permit program, so long as the program conforms to federal guidelines approved by the [United States Environmental Protection Agency (“EPA”) ] administrator. 33 U.S.C. § 1342(b). The EPA administrator has authorized the Department of Health of Hawaii to issue and enforce discharge permits.
    The Act subjects applicants for and holders of state NPDES permits to both state and federal enforcement actions for failure to comply with the permit requirements. 33 U.S.C. §§ 1319, 1342(b)(7)....
    In 1987, Congress amended the Clean Water Act to address the threat of pollution carried by storm water runoff into nearby surface waters. Under the amendments, discharges resulting from commercial or industrial activities which disturb more than five acres of land require a permit. Section 402(p), 33 U.S.C. § 1342(p).

    Molokai Chamber of Commerce v. Kukui (Molokai), Inc., 891 F.Supp. 1389, 1392-93 (D. Hawai’i 1995).

    2. DOH Administration of Discharge Permits

    Molokai also discusses the role that the State of Hawai’i assumed in enforcing the *1104storm water requirements of the Clean Water Act:

    On October 29, 1992, Hawaii DOH amended its Water Pollution Control regulations to implement the new federal storm water permitting requirements.[13] [Haw. Admin. R. § ] 11-55. Like all state NPDES permit programs, state-issued general permits must at least meet the federal requirements contained in 40 C.F.R. § 122.28. [Haw. Admin. R.] § 11-55-34.01. The DOH regulations include general permit administrative rules and six general permits. [Haw. Admin. R.] § 11-55-84, et. seq. Under the rules, dischargers must comply with “Standard General Permit Conditions” specified in Appendix A, imposing the same obligations on the permittee as the EPA permit. 57 Fed. Reg. 44412, 22. Appendix C provides a general permit for storm water discharges associated with construction activity.
    A person seeking coverage under the general permit for discharge associated with construction “shall comply with the NOI requirements of § 11-55-34.08.” [Haw. Admin. R. § ] 11-55, Appendix C, § 3(a). In order to be covered under a general permit, an applicant must submit a NOI “no later than ninety calendar days before the start of activities or discharges.” [Haw. Admin. R.] § 11-55-34.08(j). Appendix C incorporates the 90-day requirement:
    The developer or operator, normally the general contractor, of a proposed site with storm water discharges associated with a construction activity shall submit a complete NOI no less than 90 days before the proposed construction starting date in order to be covered under this general permit.
    Id. at § 1(b). After receipt of a complete NOI:
    the director shall notify the NOI submitter in writing whether the proposed activity or discharge^] is or are covered under a general permit or an individual permit application is required. Notification is complete upon mailing or facsimile transmission.
    [Haw. Admin. R.] § 11-55-34.09(a). The general permit for discharge associated with construction provides that it covers discharges “for which a complete Notice of Intent (NOI) has been submitted and a Notice of General Permit Coverage (NGPC) has been issued by the director.” [Haw. Admin. R.] § 11-55, Appendix C, § 1(b). The NOI must include a “Best Management Plan,” which must meet the requirements of the regulations. Id., Appendix C, § 5(b), (d). “The 90-day period, as specified in subsection 1(b), shall not begin counting until the date the plan is deemed to be satisfied by the director.” Id., Appendix C, § 5(c).

    Id. at 1393-94 (some alterations in Molokai).

    3. Specific Requirements Under Hawai’i Law

    Haw. Admin. R. § 11-55-04 explains the NPDES permitting process:

    (a) Before discharging any pollutant, or beginning construction activities that disturb one or more acres of land or construction activities that disturb less than one acre of total land area that is part of a larger common plan of development or sale if the larger common plan will ultimately disturb one acre or more of total land area, or substantially altering the quality of any discharges, or *1105substantially increasing the quantity of any discharges, a person shall submit a complete NPDES permit application (which shall include whole effluent toxicity testing data as specified in 40 CFR § 122.21(j)(5)), submit a complete notice of intent, except for the point source discharges from the application of pesticides, if not required (refer to Appendix M) or, for certain storm water discharges, meet all requirements for a conditional “no exposure” exclusion.

    “Disturbance of land” is defined as

    the penetration, turning, or moving of soil or resurfacing of pavement with exposure of the b course or the exposure of bare soil or ground surface, including the land surface exposed by construction roads, baseyards, staging areas, demolition, headquarters, and parking areas. It does not include grass or weed cutting, bush or tree trimming or felling that leaves soil or ground intact. It includes “grubbing” in its normal meaning of the use of equipment to knock down and push vegetation out of the way, typically uprooting vegetation and disturbing the ground surface.

    Haw. Admin. R. § 11-55, Appendix C, § 1.4.

    Further, the general permit associated with storm water discharges associated with construction activity notes that it

    covers discharges composed entirely of storm water runoff associated with construction activities, including, but not limited to, clearing, grading, excavation, and construction support activities that result in the disturbance of one acre or more of total land area. This general permit also covers activities that disturb less than one acre of total land area that is part of a larger common plan of development or sale if the larger common plan will ultimately disturb one acre or more of total land area.

    Id., § 1.1. “A larger common plan of development or sale” is defined as

    a contiguous area where multiple separate and distinct construction activities may be taking place at differing times on different schedules under on plan. “Common plan” is broadly defined as any announcement or piece of documentation (including a sign, public notice or hearing, sales pitch, advertisement, drawing, permit application, zoning request, computer design, etc.) or physical demarcation (including boundary signs, lot stakes, surveyor markings, etc.) indicating construction activities may occur on a specific plot.

    Id., § 1.5.

    C. Possible Exemptions

    Defendants argue that, pursuant to the DOH Sanitary Survey, they do not need an NPDES permit for their current activities at the Project Site. [Defs.’ Combined Mem. at 4.] The DOH Sanitary Survey states that “[h]igh enterococci bacteria levels have been measured in the Waiopoli Ditch,” and that “[ejnterococci has traditionally been used to indicate sewage contamination.” [DOH Sanitary Survey at 8.] In addition, DOH states that “[ajnimal fecal contamination of Waiopili Ditch could be a source of concern.” [Id. at 9.] With regard to Hawai’i Dairy, the DOH Sanitary Survey notes:

    DOH also received complaints from people citing potential ground water contamination, cattle manure discharge into State waters, odor, flies, and improper location of the proposed Hawaii Dairy Farms LLC (HDF) dairy. There is a claim that [Hawai’i Dairy] has already contaminated Waiopili Ditch, which is also in the same sub-watershed as the proposed farm. Currently, there are no dairy cattle on property. Several people have request that [Hawai’i Dairy] obtain *1106a[n NPDES] permit .... An NPDES permit is currently not a requirement for their proposed operation.

    [Id. at 12.] Plaintiff argues that DOH Sanitary Survey refers to a concentrated animal feeding operation (“CAFO”) NPDES permit, which “is distinct from, and in addition to, the requirement that Defendants obtain a[n] NPDES Permit for stormwater discharges from construction activities.” [Plaintiffs Reply at 11-12.] Plaintiff also argues that Defendants have acknowledged this distinction and that Defendants have admitted that they need an NPDES permit for some of their desired construction activities. As such, “Defendants’ arguments in its response are therefore entirely disingenuous.” [Id. at 12.]

    The federal regulations distinguish between NPDES permits for concentrated animal feeding operations (“CAFO”) and storm water discharges. See 40 C.F.R. § 122.23 (explaining NPDES permitting requirements for CAFOs); 40 C.F.R. § 122.26 (explaining NPDES permitting requirements for storm water). Defendants are also well aware of this distinction. See Deck of Charles M. Tebbutt (“Tebbutt Decl.”), filed 7/1/16 (dkt. no. 109), Exh. 2 (Hawai’i Dairy’s Draft Environmental Impact Statement, Volume I, dated May 2016) (“May 2016 EIS”) at 2 (listing the required permits for Defendants’ project, including an NPDES Construction Storm-water General Permit and a separate NPDES CAFO Permit). Defendants’ Summary Judgment Motion also argues that “[o]n May 7, 2016, [Hawai’I Dairy] submitted an application for an NPDES permit to [DOH], which is currently still under review.” [Mem. in Supp. of Defs.’ Summary Judgment Motion at 7.] At no point have Defendants informed the Court that they have withdrawn their NPDES permit application because it is no longer necessary or that DOH has responded to their application by telling them that a permit is not required. The meaning of the DOH Sanitary Survey is therefore a disputed issue of material fact. Accordingly, Defendants are not entitled to summary judgment based upon this document alone. See Fed. R. Civ. P. 56(a) (“The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”).

    D. Alleged Violations of the Clean Water Act

    In the instant matter, it is undisputed that Defendants have never had an NPDES permit. In addition, Defendants admit that:

    5. The scope of construction performed at the [Project Site] from February 2014 until June 2014 consisted of the following:
    (a) Installation of one eight inch water main to feed one irrigation pivot sprinkler;
    (b) Installation and connection of one stationary pivot irrigation system that operates today;
    (c) Construction of one stationary pivot irrigation system that is not connected or operating as of today;
    (d) Placement of bridges over drain lines above the grade to allow pivot irrigation system to cross over drain lines;
    (e) Installation of several small diameter lateral water lines feeding several circular concrete water troughs; and
    (f) Installation of the water trough pads above the grade, which generally included the importing of locally-sourced granular material to build up to a level surface for *1107their placement rather than excavating.
    [[Image here]]
    7. In addition, between February and April of 2015, ground work, drilling, casing and grouting work was completed on four separate vertical monitor wells. Final locking caps were installed on the wells in May and June of 2015.

    [Decl. of James Garmatz (“Garmatz Decl.”),14 filed 11/25/15 (dkt. no. 43), at ¶¶ 5-7.] Garmatz also states that:

    Since construction and development was stopped, I have done only agricultural work on the property. That ongoing work is limited to maintaining the grass and the borders, irrigating/watering, mowing grass, trimming trees for installation of new fencing, and the application of fertilizer at agronomic rates. To irrigate the approximate 85 acres on a timely basis is to apply at least 0.3 inches of water daily. This process allows the circular pivot sjfetem to cross the drain lines via the bridges enabling the pivot to reach all the acres. The application of fertilizer is done every 18 days with a mechanical fertilizer spreader. The fertilizer being spread is a custom formula that is mixed after soil samples are taken and analyzed and the proper mixture of [sic] is recommended by an agronomist. I also mow all the approximately 85 acres to a level of 7-8 inches tall and this, in most part, is done weekly.

    [Id. at ¶ 12.]

    In addition to these activities, the record establishes that a thirty-nine acre area was harrowed five times fi’om July 2015 to August 2015, [Tebbutt Decl., Exh. 3 (6/13/16 Depo. of James J. Garmatz) (“Pitt’s Garmatz Depo.”) at 77,] and Defendants continue to disc a perimeter around a four-acre nursery to a depth of six inches [id. at 110-11]. Moreover, on July 1, 2015, Defendants admit that they used a baekhoe to replace bolts in an irrigation pivot, [Defs.’ Concise State of Facts in Opposition to Plaintiffs Summary Judgment Motion (“Defs.’ CSOF in Opp.”), filed 9/1/16 (dkt. no. 219), Decl. of Dirk. B. Paloutzian (“Paloutzian Deck”), Exh. A (6/13/16 Depo. of James J. Garmatz) (“Defs.’ Garmatz Depo.”) at 121,] and, on August 3, 2015, they used a baekhoe to fix a broken irrigation line riser [id. at 123-24].15

    1. Common Plan of Development

    Defendants argue that the “development of land for the purpose of growing crops, and all incidental construction that entails, is not a construction activity subject to NPDES requirements.” [Defs.’ Combined Mem. at 5.] However, this distinction is only relevant if the activity is not part of a common plan of development. This district court has stated:

    The “plan” in a common plan of development is broadly defined by the EPA as any announcement or piece of documentation or physical demarcation indicating construction activities may occur on a specific plot. The EPA further clarified what is meant by a “larger common plan of development”:
    “Part of a larger common plan of development or sale” is a contiguous area where multiple separate and distinct construction activities may be taking place at different times on dif*1108ferent schedules under one plan. Thus, if a distinct construction activity has been identified onsite by the tune the [NPDES] application would be submitted, that distinct activity should be included as part of a larger plan.

    Na Mamo O ’Aha’ino v. Galiher, 28 F.Supp.2d 1258, 1263 (D. Hawai'i 1998) (alterations in Na Mamo) (citing NPDES Storm Water Program Question and Answer Document Volume I, March 1992, page 16), abrogated on other grounds by, Nw. Envtl. Def. Ctr. v. Decker, 728 F.3d 1085 (9th Cir. 2013). In Na Mamo, this district court ruled that because access roads used for farming purposes fall within the agricultural exception to NPDES permit requirements, and that “[the defendants’ remaining activities did not result in the disturbance of more than five acres and were not carried out pursuant to a ‘larger common plan of development,’ ” an NPDES permit was not required. Id. The plaintiff in Na Mamo challenged the construction of, inter alia, a “helipad and utility barn,” but could only point to a document dated after the relevant time period and a document that showed that the defendants “intended to develop their land for agriculture and farming,” not “that they intended to carry out construction activities.” Id. at 1260, 1263.

    Here, it is clear that Defendants’ actions were undertaken pursuant to a common plan of development. Defendants’ NPDES Form C Application,16 submitted to DOH on March 7, 2015, describes the project:

    A pasture-based rotational grazing, dairy facility for 699 cows (DOH Waste Management Plan) reviewed will be constructed. Construction items at the facility include the following: Paved access road and truck turnaround near the facility, concrete holding yards and gravel arm races, a milking parlor, implement shed, calving sheds, waste settling pond and storage pond, effluent and sludge pumps and distribution system, feed silos, potable water tanks for the milking parlor and livestock consumption, and an individual wastewater system (IWS).
    Additional improvements around the farm and not at the dairy facility include the following: Installation of an irrigation water supply, storage, and distribution system, livestock paddocks for grazing areas, cow walkways/races and farm roads, potable water distribution systems for livestock consumption with watering facilities and concrete troughs, upgrades to the existing potable water well and new transmission mains for the dairy facility, and an animal cemetery.
    Potential future expansion to up to 2000 cows will be considered for the site, following the review of other applicable permits or reviews needed for expansion. Potential expansion would occur at a date to be determined, following completion of the work indicated herein. A separate NPDES Permit, for Construction Stormwater Activities, will be obtained for disturbances greater than 1 acre, as needed, should expansion work be performed in the future.

    [Decl. of Kyle Datta (“Datta Decl.”),17 filed 11/25/15 (dkt. no. 44), Exh. A at 5.] The May 2016 EIS also states that the project area is 557 acres and describes the “Proposed Use & Components” as: “Agriculture (Dairy) use for dairy buildings, roads, sheds and ponds, paddocks, cow races, farm roads, irrigation system, water storage, drainage ways, setbacks/vegetated *1109buffers.” [May 2016 EIS at 2.] The Court therefore FINDS that, for purposes of the Summary Judgment Motions, because Defendants’ actions were undertaken as part of a common plan of development, they needed an NPDES permit for all of their activities.18

    2. Discharge of Pollutant to Navigable Waters

    It is clear to the Court that Defendants engaged in activities pre-and post-Complaint that required an NPDES permit. The Court must still consider whether any pollutants created as a result of these actions were discharged into navigable waters.

    i. Navigable Waters

    According to Tom Nance, President of Tom Nance Water Resource Engineering:

    8. The [Project Site] drains into two major ditches running mauka to ma-kai. Additionally, runoff from offsite drains in the [Project Site] area. The offsite tributary area is about 1200 acres, most of which is the steep lands which enclose Maha’ulepu Valley.
    9. Generally, runoff from the west side of the valley sheet flows or is conveyed via shallow concentrated flow through the various system of ridges and valleys along the west side of Maha’ulepu Valley. Runoff concentrates into several ditches created by prior agricultural operations, before ultimately collecting into one of the major ditches that runs mauka to makai along the west side of the far, and along the proposed location of the dairy facility. This ditch conveys both water collected from the various tributary ditches, and also sheet flow from the west side of the farm, to the makai boundary of the farm along Maha’ulepu Road, before leaving he site and ultimately flowing into the ocean
    10.Similarly, runoff from the east side of the valley sheet flows or is conveyed via shallow concentrated flow through the various system of natural drainageways along the east side of Maha’ulepu Valley. Runoff concentrates into several ditches, created by prior agricultural operations, before ultimately collecting into one of the major ditches that runs mauka to makai along the central or east side of the farm. This ditch conveys both water collected from various tributary ditches and sheet flow from the central and eastern areas of the farm, to the makai boundary of the farm along Maha’ulepu Road, before leaving the site and ultimately flows into the ocean.

    [Defs.’ CSOF in Opp., Decl. of Tom Nance (“Nance Deck”) at ¶¶ 8-10.] It is undisputed that the Pacific Ocean is a “navigable water” under the Clean Water Act. Moreover, this district court has explained:

    The plurality in Rapanos [v. United States] made clear that the prohibition in the Clean Water Act is not limited to “the addition of any pollutant directly to navigable waters from any points source,” but rather extends to “the addition of any pollutant to navigable wa-*1110tere.” Rapanos, 547 U.S. [715,] 743, 126 S.Ct. 2208 [165 L.Ed.2d 159 (2006) ] (emphasis in original) (internal quotation marks omitted). “Thus, ... lower courts have held that the discharge into intermittent channels of any pollutant that naturally washes downstream likely violates § 1311(a), even if the pollutants discharged from a point source do not emit directly into covered waters, but pass through conveyances in between.” Id. (internal quotations marks omitted).

    Haw. Wildlife Fund, 24 F.Supp.3d at 995.

    ii. Point Source

    This Court has concluded that the Project Site is part of a common plan of development to which the agricultural exemptions under the relevant regulations do not apply. In Na Mamo, this district court determined that “[construction, as described in 40 C.F.R. § 122.26(b)(14)(x), is a point source activity.”19 28 F.Supp.2d at 1261. Moreover, in California Sportfishing Protection Alliance v. Diablo Grande, Inc., the district court found that “[the defendant's development of well over five acres of the [property is ‘construction activity’ not within the agricultural, silvicultural, or any other exception to the permit requirements or point source definition. By identifying [the defendant’s construction activity on the [property, [the pjlaintiff has sufficiently identified a ‘point source.’ ” 209 F.Supp.2d 1059, 1077 (E.D. Cal. 2002) (citation omitted). The Court FINDS that, for purposes of the Summary Judgment Motions, the construction that Plaintiff has identified on the Project Site, see supra Section H.D., identifies a point source under the Clean Water Act.

    iii. Effectiveness of BMPs

    On September 9, 2015, licensed civil engineer Ross Dunning (“Dunning”) visited the Project Site (“Dunning Visit”).20 [Deck of Ross Dunning (“Dunning Deck”), filed 11/25/15, dkt. no. 45, at ¶¶ 1, 6.] During the Dunning Visit, he observed thirty-five-foot “vegetative buffers” that “were still in place and that ... were of a height and density that suggested to me that the vegetation had been in place before the commencement of construction reported to be in February of 2014.” [Id. at ¶ 12.] Dunning contends that the vegetative buffer is a sediment control Best Management Practice (“BMP”) and that “the vegetated buffers should have adequately reduced the discharge of sediments from soils disturbed during construction and pasture renovation activities.” [Id. at ¶ 13.] Moreover, Dunning notes that there was a “significant rainfall event” before his visit and “though water was observed in the drainage channels shown to me, flowing water from the fields into the onsite drainage channels was not observable from my vantage point.” [Id. at ¶ 11.] Dunning also provided his opinion on the effectiveness of the vegetative buffers, explaining: “I did not directly observe runoff from the [Ha-wai’i Dairy] fields into the discharge channels that transect the [Project Site] due to the presence of the dense, well-established vegetated buffers described above aligning the banks of the drainage channels.” [Id. at ¶ 14.]

    *1111On March 29 and 30, 2015, Erickson visited the Project Site (“Erickson Visit”). [Erickson Decl. at ¶ 7.] During the Erickson Visit, he collected water and soil samples, and also noted the extensive -construction activity that had taken place at the Project Site. [Id. at ¶¶ 7, 9.] After analyzing the soil samples Erickson collected, he concluded that “[t]he fíne nature of these soil types means that precipitation events, especially intense rainfall,[21] will quickly move through and across the [Project Site], finding its way to ditches and other conduits that eventually converge with the Waiopili Stream.” [Id. at ¶ 28.] Moreover, “the extensive network of-drainage ditches and canals were installed to promote rapid runoff and prevent ponding on crop land to allow farming on the [Project Site].” [Id.] Erickson observed “no effort to maintain any vegetative buffer and we did not observe any evidence of a BMP on the [Project Site],” and “[contrary to Mr. Dunning’s opinion, I do not believe that any Best Management Practices have been implemented effectively such that any discharges have been and are being prevented.”22 [Id. at ¶¶ 36, 43.]

    There is some dispute about the amount of rain that has fallen in Maha’ulepu Valley since June 1, 2015. Compare Erickson Decl. at ¶ 39 (“Since June 1, 2015, there have been at least 46 days of recorded rainfall at 0.5 inches or greater, any and all of which would have been enough to transport the dirt, sediment, or other pollutants from [Hawai’i Dairy’s] ground-disturbances into ditches and surface waters on the proposed dairy site.”), with Defs.’ CSOF in Opp., Decl. of Peter Munn (“Munn Decl”) at ¶¶ 11-12 (explaining that his company did not recognize that the rain data from the rain gauges was incorrect “because of unfamiliarity with the U.S. standard units of measurement and because of unfamiliarity with the climate at the [Hawai’i Dairy] site,” and that the amount of rainfall recorded in 2015 is was actually 31.7 inches, not 124.7 inches).23 However, Defendants do not dispute that, since June 1, 2015, there have been some days on which it has rained 0.5 inches or more at the Project Site.

    In Molokai, this district court explained that the “[defendants apparently believe that on the day construction ceases, the violations become ‘wholly past’ under the Gwaltney doctrine,” but that this “fails to account for the interplay of rainwater and the construction site, an in*1112teraction that the [Clean Water] Act and its regulatory scheme is intended to manage.” 891 F.Supp. at 1400. “It is the discharge of water without permit coverage that violates the [Clean Water] Act, not the construction activity itself.” Id. As such, “for [the defendants to show that they were not in violation of the [Clean Water] Act, they would have to eliminate all issues of fact concerning whether any pollutants were discharged during the period in which [the plaintiffs filed their Complaint.” Id. at 1401 (emphasis in Molokai).24 Here, Plaintiff has identified a pollutant (the storm water runoff from Defendants’ construction activities) from a point source (the Project Site) that was discharged to navigable waters (the drainage systems at the Project Site and the path they follow to the Pacific Ocean).25 The record also establishes that these activities took place before and after the Complaint was filed. Though there are questions of material fact regarding the sufficiency of Defendants’ vegetative buffers and the effect of rainfall on the Project Site, the Court concludes that Plaintiff has “ad-ducted] evidence from which a reasonable trier of fact could find a continuing likelihood of a recurrence in intermittent or sporadic violations.” Sierra Club, 853 F.2d at 671 (citation and internal quotation marks omitted). Moreover, “[i]f the defendant fails to convince the court that there are no genuine issues of fact after the plaintiff offers evidence to support the allegations of ongoing noncompliance, the cause goes to trial on the merits.” Id. at 669 (citing Gwaltney, 484 U.S. at 66, 108 S.Ct. 376). Defendants’ Summary Judgment Motion is therefore DENIED.

    III. Plaintiffs Summary Judgment Motion

    Plaintiffs Summary Judgment Motion seeks “partial summary judgment finding Defendants liable for illegally undertaking facility construction without a required [NPDES] permit.” [Pltf.’ Combined Mem. at 1.] Specifically, Plaintiff argues that: since filing the Complaint, Defendants have continued construction at the Project Site; there have been many instances of rainfall that exceeds 0.5 inches since that time; and “[r]ainfall events of this magnitude interact with the disturbed ground causing surface runoff.” [Id.] The Court has already determined that there are *1113questions of material fact about the effect of rainfall on the Project Site and the existence and/or effectiveness of the vegetative buffers. See supra Section I.D.2.iii. As such, there is a genuine dispute of material fact regarding the discharge of pollutants, and Plaintiffs Summary Judgment Motion must be DENIED.

    IV. Motion for Leave

    The Motion for Leave seeks permission from the Court to file two additional declarations and corresponding documents related to: the corrected rainfall data; Erickson’s qualifications; and “exhibits necessary to respond to arguments raised in Defendants’ [Combined Memorandum].” [Motion for Leave at 2.] The Court has not considered these declarations or documents in reaching its conclusions on the Summary Judgment Motions. Moreover, it is clear to the Court that Plaintiffs additional submissions would not alter its decision on Defendants’ Summary Judgment Motion, nor, given the competing evidence with regard to the sufficiency of the vegetative buffers, its decision on Plaintiffs Summary Judgment Motion. The Motion for Leave is therefore DENIED AS MOOT.

    CONCLUSION

    On the basis of the foregoing, Defendants’ Motion for Summary Judgment, filed on November 25, 2015, Plaintiffs Motion for Summary Judgment on Liability, filed on July 1, 2016, and Plaintiffs Ex Parte Motion for Leave to File Supplemental Declarations in Support of Reply to Motion for Partial Summary Judgment, filed on September 1, 2016, are all HEREBY DENIED.

    IT IS SO ORDERED.

    . Defendants’ Motion for Summary Judgment was originally set for hearing on February 16, 2016. However, on January 4, 2016, Plaintiff filed a Fed. R. Civ. P. 56(d) Motion to Defer Consideration of Defendants' Motion for Summary Judgment (ECF No. 41) (“Rule 56(d) Motion”), which the Court granted on February 29, 2016. [Dkt. nos. 68 (Rule 56(d) Motion), 89 (order granting Rule 56(d) Motion).]

    . Plaintiff's Summary Judgment Motion includes a Memorandum of Points and Authorities in Support of its Motion for Partial Summary Judgment on Liability and Opposition to Defendants’ Motion for Summary Judgment (ECF No. 41) ("Plaintiff's Combined Memorandum”).

    . Both parties had a very difficult time complying with the Local Rules and using this district court's electronic case filing system. In an Entering Order filed on August 25, 2016, the Court deemed many of the incorrectly filed documents withdrawn without prejudice. [Dkt. no. 159.] In an Entering Order filed on August 29, 2016, after the parties again filed documents incorrectly, the Court struck a number of documents from the record. [Dkt. no. 204.] At a status conference on August 31, 2016, the Court granted the parties leave to re-file certain documents. [Minutes, filed 8/31/16 (dkt. no, 211).] While the Court is confident that it has sufficiently addressed this matter, the parties are warned that, in the future, any filings in violation of the Local Rules will not be accepted. Further, the Court may consider revoking the pro hac vice status of the offending party.

    .After reviewing the documents closely, it is clear to the Court that docket number 221 is a continuation of docket number 215.

    . According to Plaintiff, these activities include

    removal of Guinea grass and other “grubbing” activities to make the ground suitable for planting of non-native Kikuyu grass; installation of irrigation systems and associated piping, some of which may be underground; construction and in-ground installation of concrete watering troughs, including associated piping; digging of an effluent pond to store manure generated by the dairy herd; installation of monitoring wells; road improvements; and the staging of materials and equipment to accomplish the above and other activities.

    [Complaint at ¶ 36.]

    . On December 3, 2015, Defendants filed the First Request for Judicial Notice a second time, [Dkt. no. 55.] The Court therefore deems docket number 55 withdrawn.

    . Defendants state that the Complaint is attached as Exhibit A, but the attachment is actually Defendants’ Answer to Complaint. See First Request for Judicial Notice, Exh. A.

    . This appears to be a misspelling of Kaohe-lauli'i.

    , All of the documents in support of Plaintiff’s Summary Judgment Motion and Defendants’ Summary Judgment Motion are incorrectly filed. See Local Rule LR100.2.5 ("Each exhibit referenced in a document shall be submitted as a separate CM/ECF attachment to the main document”). For the sake of clarity, the Court will refer to the documents as filed.

    .Erickson is the President/Principal Hydro-geologist of Water & Environmental Technologies, Inc., located in Butte, Montana, and is also a Professional Geologist in Utah and Wyoming, and a Certified Professional Geologist with the American Institute of Professional Geologists. [Erickson Decl. at ¶ 3.]

    . The Court notes that Defendants do not challenge Plaintiff’s standing based upon any claim that Plaintiff cannot bring the instant suit on its members’ behalf. Instead, Defendants standing argument is based on their belief that Plaintiff did not have "the required facts to have standing to bring this case or that any, let alone, all material facts have been established without any genuine dispute of material fact.” [Defs.’ Combined Mem. at 17.]

    . In addition, 40 C.F.R. § 122.2(b) states that "[t]his ion includes additions of pollutants into waters of the Definition United States from: surface runoff which is collected or channelled by man[.]”

    . "Storm water” is defined as "storm water runoff, snow melt runoff, and surface runoff and drainage.” 40 C.F.R. § 122.26(b)(13).

    . James Garmatz ("Garmatz”) is the Farm Manager at Hawai’i Dairy and the sole employee of the company. [Garmatz Decl. at ¶¶ 1, 4.]

    . The use of the baekhoe on August 3, 2015, involved digging “down like, again, 8 or 12 inches and reset the riser on the main line.” [Pltf.’s Garmatz Depo. at 123-24.]

    . This is an application for coverage under the general permit for storm water discharged related to construction activities pursuant to Haw. Admin. R. § 11-55, Appendix C.

    . Kyle Datta is the General Partner of Ulu-pono. [Datta Decl. at ¶ 1.]

    . Defendants also cite the 2/5/1998 Pender-gast Letter to support their position that "the EPA has explained that pre-operation construction and post-construction operations are treated differently under stormwater permitting regulations.” [Defs.’ Combined Mem. at 8.] The distinction that Defendants attempt to draw is irrelevant here because the Court has determined that Defendants’ activities are part of a common plan of development, and therefore any agricultural exclusion does not apply.

    . 40 C.F.R. § 122.26(b)(14)(x) defines "industrial activity,” in part, as:

    Construction activity including clearing, grading, and excavation, except operations that result in the disturbance of less than five acres of total land area. Construction activity also includes the disturbance of less than five acres of total land area that is part of a larger common plan of development or sale if the larger common plan will ultimately disturb five acres or more[.]

    . In addition to being a "licensed profession Civil Engineer and Certified Erosion and Sediment Control Lead in the State of Washington,” Dunning is also the "Stormwater Practice Leader and Principal for Kennedy/Jenks Consultants.” [Dunning Decl. at ¶¶ 1-2.]

    . Erickson states that any rainfall of half an inch or more "would have been enough to transport the dirt, sediment, or other pollutants from [Hawai'i Dairy’s] ground-disturbances into ditches and surface waters on the proposed dairy site.” [Erickson Decl. at ¶ 39.] Defendants disagree. See Nance Decl. at ¶ 13 ("Erickson’s contention that a rainfall event of 0.5 inches is sufficient to transport pollutants to the ditches is unsupported by facts and/or reasoning.’’).

    . Defendants dispute Erickson's findings, See, e.g., Nance Decl. at ¶ 13 (noting that Erickson’s "contention that a rainfall event of 0.5 inches is sufficient to transport pollutants to the ditches is unsupported by facts and/or reasoning”); id. at ¶ 28 (asserting that Erickson’s "opinions heavily rely on general references to soil and water quality samples without providing any explanation of how he reaches his conclusions from those samples, or any specificity as to location, date, and/or time of any alleged pollutant discharge”). However, on a motion for summary judgment, "[t]he court does not make credibility determinations or weigh conflicting evidence.” Kauhako v. State of Haw. Bd. of Educ. Dep't of Educ., Civil No. 13-00567 DKW-BMK, 2015 WL 5312359, at *7 (D. Hawai'i Sept. 9, 2015) (citing Nelson v. City of Davis, 571 F.3d 924 (9th Cir. 2009)).

    .Peter Munn is the Chief Executive Officer and Managing Director of Harvest Electronics, the company that monitors Hawai’i Dairy’s rain gauge data, among other things. [Munn Decl. at ¶¶ 1, 5.]

    . Defendants argue that, even if pollutants were discharged from a point source at the Project Site after the Complaint was filed, "the continued contribution of discharge from these point sources would not constitute further discharge because the continuing effects of any purported prior discharges do not constitute present discharges in violation of the [Clean Water Act].” [Defs.' Combined Mem. at 11-12.] To support their position, Defendants cite Hamker v. Diamond Shamrock Chemical Co., where the Fifth Circuit found that "[m]ere continuing residual effects resulting from a discharge are not equivalent to a continuing discharge.” 756 F.2d 392, 397 (5th Cir. 1985). In Hamker, however, "[t]he complaint allege[d] facts constituting only one discharge of oil from defendant’s pipe.” Id. (internal quotation marks omitted). The instant case is easily distinguishable because, as this district court stated in Molokai, "[e]ven if construction had ceased and erosion control measures were in place, [the defendants were in violation of the [Clean Water] Act ... failing proof of a complete absence of storm runoff.” 891 F.Supp. at 1402 (footnote omitted).

    . At the hearing, Defendants represented that Plaintiff had not shown any ditch or other conduit for pollutants that was created by Hawai'i Dairy during construction. However, "defendants need not construct the conveyances 'so long as they are reasonably likely to be the means by which pollutants are ultimately deposited into a navigable body of water.’ ” Evtl. Prot. Info. Ctr. v. Pac. Lumber Co., 469 F.Supp.2d 803, 821 (N.D. Cal. 2007) (quoting Concerned Area Residents for Env't v. Southview Farm, 34 F.3d 114, 118 (2d Cir. 1994)).

Document Info

Docket Number: CIVIL 15-00205 LEK-BMK

Citation Numbers: 224 F. Supp. 3d 1094, 2016 WL 7031286, 83 ERC (BNA) 1737, 2016 U.S. Dist. LEXIS 166853

Judges: Kobayashi

Filed Date: 12/1/2016

Precedential Status: Precedential

Modified Date: 10/18/2024