Morgan v. New Sweden Irrigation District , 156 Idaho 247 ( 2014 )


Menu:
  •                    IN THE SUPREME COURT OF THE STATE OF IDAHO
    Docket No.39624
    BRADLEY K. MORGAN,
    Boise, December 2013 Term
    Plaintiff-Appellant,
    2014 Opinion No.25
    v.
    NEW SWEDEN IRRIGATION DISTRICT,
    Filed: March 13,2014
    Stephen W. Kenyon, Clerk
    Defendant-Respondent.
    Appeal from the District Court of the Seventh Judicial District, State of Idaho,
    Bonneville County. Hon. Dane H. Watkins, Jr., District Judge
    District court's grant of partial summary judgment and trial judgment on
    easement, affirmed.
    M. Brent Morgan, chtd., Pocatello, for appellant. M. Brent Morgan argued.
    Hall Angell Starnes, LLP, Idaho Falls, for respondent. Blake G. Hall argued.
    BURDICK, Chief Justice
    This case arose after New Sweden Irrigation District ("New Sweden") mowed the canal
    banks on Bradley Morgan's property. Morgan claimed New Sweden negligently damaged his
    property. New Sweden counterclaimed for a declaratory judgment as to its easement's existence
    and scope, and then moved for summary judgment. The Bonneville County district court granted
    partial summa"ry judgment, holding that New Sweden's easement was sixteen feet wide and New
    Sweden was not liable for damaged items within its easement. The district court denied summary
    judgment as to Morgan's claim for damaged items outside the easement. At trial, the court held
    that Morgan failed to establish that New Sweden caused damage outside its easement. Morgan
    appeals the district court's grant of partial swnmary judgment and the court's trial judgment in
    favor of New Sweden. We remand to the district court for the court to enter a judgment that
    describes the precise location where the easement's sixteen-foot width measurement beeins. We
    otherwise affirm the district court.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    On June 25, 2009, New Sweden mowed the canal banks along Morgan's property in
    Bonneville County. New Sweden is an inigation district in Bonneville County that supplies
    irrigation water through canals. Because New Sweden owns the canal, it also holds an easement
    along the canal's banks. New Sweden owns two commercial mowers that it has used since 1995
    to maintain its 125 miles of canals. These mowers each use a tractor with a hvdraulic arm mower
    that is raised and lowered electronically.
    Morgan's property has several structures within sixteen feet of the canal bank. Morgan
    also has a tree that has grown eight feet from the canal for over thirty-five years. Several Russian
    Olive trees and wild roses grew along the canal banks. Before June 25, 2009, New Sweden had
    never asked Morgan to remove the structures or the plants. However, New Sweden and Morgan
    did once jointly remove Russian Olive trees. Morgan also has a well and a bam about twenty feet
    from the canal. Morgan installed these items without New Sweden's permission.
    On June 25, 2009, Morgan left his property to go to work. That same moming Kail
    Sheppard, New Sweden's manager, told his employee, Kent Ockerman,               to mow Morgan's
    property. Ockerman had mowed for New Sweden for about ten years and was trained on the
    mowers. Sheppard instructed his employees to remain within the easement when possible and to
    be "way more careful" when traveling outside the easement. Ockerman entered Morgan's
    property along the south side of Morgan's bam due to obstructions near the canal. Once on the
    property, Ockerman drove to the canal's edge and backed up behind Morgan's barn. While
    tuming around, he saw a pile of pipes under the barn's stairway and intentionally avoided the
    pipes and stairway. Ockerman then left the easement to get around a tree, which he accomplished
    by tuming off the mower blades and raising the mower. Ockerman stated that he knew he did not
    hit or damage any structure because the mower makes a noise and vibrates when it strikes a solid
    object.
    While at work, Morgan was informed that New Sweden had mowed his property.
    Morgan met Ockerman and Sheppard on his property to discuss his concerns. That discussion
    became heated, and Sheppard called the Bonneville County ShenifPs Office. Morgan testified at
    trial that the next day he found damage to the stairway and discovered the well had lost water
    pressure. Morgan met      with New Sweden's Board of Directors a month later. but            never
    mentioned damage to the well or stairway. Morgan also submitted a Claim for Damage form to
    New Sweden that only stated that New Sweden had damaged landscaping and sprinklers.
    Morgan filed a complaint on October 20,2010, alleging New Sweden was negligent
    when it mowed his property. He sought to recover damages to plants, sprinklers, outbuildings,
    and a well. He never mentioned a stairway. New Sweden timely filed its answer. On July 12,
    201I, New Sweden filed a counterclaim for      (l)   declaratory judgment that   it held an easement;
    (2)    declaratory judgment regarding the easement's scope;         (3) removal of all       physical
    encroachments on the easement; and (4) an injunction preventing Morgan from restricting New
    Sweden's access to the easement.
    New Sweden then filed a summary judgment motion with supporting affrdavits from
    Ockerman and Sheppard. New Sweden asked the district court to dismiss Morgan's complaint
    and grant New Sweden's counterclaim. Morgan opposed summary judgment with his affidavit
    and a neighbor's affidavit. These affidavits stated that New Sweden had never used its mower on
    Morgan's property before, Morgan had always maintained his property himself, and his neighbor
    had also maintained the canal banks. Morgan's photos also showed that while his lawn was
    neatly maintained, other property owners in the area did not maintain their canal banks. The
    district court partially granted New Sweden's summary judgment motion. Specifically, the court:
    (l)   granted New Sweden's counterclaim for declaratory relief; (2) dismissed Morgan's claim for
    damage to items within the sixteen-foot easement; (3) denied dismissal of Morgan's claim for
    damage    to items outside the easement; and (4) denied Morgan's motion to add a claim for
    declaratory relief. The district court also held that New Sweden's easement was sixteen feet
    wide, vegetation removal within the easement was reasonable, Morgan must remove structures
    that unreasonably encroached on the easement, and New Sweden was not liable for damaged
    items within the easement.
    Morgan filed a motion to reconsider and a supporting affidavit. The district court denied
    this motion, holding that Morgan had not presented the court with any new law or argument. The
    court held that outbuildings, sprinklers, and a garden unreasonably interfered with New
    Sweden's ability to occupy the canal banks with its equipment.
    Morgan's remaining claim on whether New Sweden negligently damaged his property
    outside the easement went to trial. Morgan claimed New Sweden damaged the barn's stairway,
    which he knew because the day before New Sweden mowed the stairway was undamaged, but
    the day after   it was damaged. Morgan also claimed New Sweden damaged the well               because   it
    operated properly before New Sweden mowed and did not after the mowing. He testified that a
    well drilling service inspected the well and found a broken joint twenty-five feet below the
    surface. However, no witness testified that Ockerman hit the stairway or well, and no photo at
    trial showed damage to the stairway or well. The only evidence Morgan provided was testimony
    that the broken joint lacked rust, which suggested the break was recent.
    The district court held that New Sweden was not liable because New Sweden did not
    breach its duty of care on Morgan's property outside of the easement, res ipsa loquitur did not
    apply, and   if comparative   negligence applied, Morgan was at least as negligent as New Sweden.
    The court then entered its final judgment. Morgan timely filed his amended notice of appeal.
    II. ISSUES ON APPEAL
    l.   Whether the district court erred in granting summary judgment as to the scope of New
    Sweden's easement.
    2.   Whether the district court erred in granting summary judgment when the court ordered
    Morgan to remove all encroachments within New Sweden's easement.
    3.   Whether the district court abused its discretion in concluding that New Sweden did not
    breach a duty of reasonable care or cause damage to Morgan's stairway and well.
    4.   Whether either party is entitled to attorney fees on appeal.
    III. ANALYSIS
    Morgan appeals the district court's grant of partial summary judgment and trial judgment
    in favor of New Sweden. Morgan argues that the district court did not construe all disputed facts
    in his favor on sunmary judgment, improperly construed the easement's width, and improperly
    ordered Morgan to remove all encroachments within the easement. Morgan further argues the
    district court's trial judgment was improper. New Sweden counters that the district court
    properly interpreted the statutes and Morgan never rebutted that New Sweden needed sixteen
    feet to maintain the canal. We affirm the district court's judgment.
    A. The district court properly granted summary judgment as to the scope of New Sweden's
    easement.
    We review a district court's grant of summary judgment using the same standard the
    district court used in ruling on the motion. Buckskin Props., Inc. v. Valley Cnty.,l54 Idaho 486,
    490,300 P.3d 18, 22 (2013). Therefore, we affirm sunmary judgment when "the pleadings,
    depositions, and admissions on file, together with the affidavits,      if   any, show that there is no
    genuine issue as to any material fact and that the moving party is entitled to a judgment as a
    matter   of law." I.R.C.P. 56(c). Under this     standard this Court and the district court liberally
    construe the record and draw all reasonable inferences in favor of the non-moving party. Drew v.
    Sorensen,133 Idaho 534, 537,989 P.2d276,279 (1999).
    l.
    Morgan initially ilgues that New Sweden's declaratory action to establish its easement's
    scope should have named other property owners. However, whether other property owners
    should have been named is a new issue Morgan raised on appeal. We do not consider issues
    raised for the first time on appeal. Crowley v. Critchfield, l45Idatro 509, 512, 
    181 P.3d 435
    , 438
    (2007). Also, this is a finite dispute between Morgan and New Sweden. New Sweden filed its
    counterclaim for declaratory judgment regarding Morgan's property only, so the easement's
    scope on other properties is irrelevant. Thus, we do not consider whether other property owners
    should have been included.
    2.
    The parties agree New Sweden has an easement over Morgan's property along the canal,
    but dispute the easement's scope. The district court held that there was no genuine dispute that
    New Sweden's easement was sixteen feet wide because Morgan failed to offer contradictory
    evidence regarding the space needed to operate equipment. Morgan argues that the district court
    erred   in applying I.C. $ 42-1102     and   $   42-1209 because Morgan's affrdavits show New
    Sweden's use was not reasonable and necessary.
    An easement is the right to use another's land for a specific purpose. McKay v. Boise
    Project Bd. of Control,   l4I Idatro 463, 471,1I I P.3d 148, 156 (2005). An inigation easement is
    not exclusive.   Pioneer lrr. Dist. v. City of Caldwetl, 
    153 Idaho 593
    , 601-02,288 p.3d 810, 8lg-
    19 (2012). The irrigation district is the dominant estate holder, whereas the land that the canal is
    located upon is the servient estate. Bratton v. Scott,l50 Idaho 530, 536, 249 p.3d, 1265,       l27l
    (201l). When specific easement privileges are granted, "the easement owner's rights are
    paramount to those of the servient owner." 
    McKay, 141 Idaho at 471
    , I I I p.3d at 156.Idaho
    Code section 42-1102 states that a right-of-way includes "the right to enter the land across which
    the right-of-way extends, for the purposes of cleaning, maintaining and repairing the ditch . . . .',
    Here, New Sweden held an easement, Morgan's land was the servient estate, and I.C. 42-1102
    S
    gave New Sweden the right to enter his land to clean, maintain, and repair the canal.
    An easement's width is generally a factual question, but when only one party presents
    evidence of width, there is no genuine issue of material fact and summary judgment is proper.
    SeeTurnerv. ColdSpringCanyonLtd. P'ship,l43Idatro 227,229,141 P.3d 1096, 1098 (2006).
    Idaho Code section 42-1102's plain language indicates that a right-of-way's width is the area
    "necessary to properly do the work of cleaning, maintaining and repairing . . . with personnel and
    with such equipment as is commonly used, or is reasonably adapted, to that work." Thus, the
    width must be necessary to properly clean, maintain, or repair the canal with the "equipment as is
    commonly used, or is reasonably adapted" to that work.
    Here, Sheppard stated that New Sweden needed sixteen feet to properly maintain the
    canals. He also stated that the equipment commonly used to maintain New Sweden's 125 miles
    of canals was a large mower with side and trailing mowers, and that other irrigation districts also
    used this same type of mower to maintain canals. These facts establish a sixteen-foot easement
    unless Morgan provides contradictory facts.
    When all material facts are construed in Morgan's favor, it still is undisputed that sixteen
    feet was "necessary to properly do the work" with "commonly used" equipment. Morgan's
    affrdavits do not rebut these facts. Instead, those affrdavits only show that other property owners
    had encroachments and Morgan had always mowed the canal himself. New Sweden provided
    competent evidence from those experienced in the field that it used a mower that needed sixteen
    feet of flat surface to properly maintain the canal and that other irrigation districts commonly
    used the same type of mower. Morgan provided only his opinion that he could mow the canal
    himself' Thus, the district court correctly held that Morgan "failed to offer contradictory
    evidence regarding the space needed to operate equipment commonly used to clean and maintain
    the canal" and properly granted summary judgment as to a sixteen-foot easement.
    Morgan contends that Nampa & Meridian lru. Dist. v. Washington Fed. Sav.,l35Idaho
    518, 
    20 P.3d 702
    (2001), establishes that an easement's width is determined by what is
    reasonable and necessary and New Sweden's activity was not necessary because Morgan's land
    was already mowed. However, these arguments also fail because Morgan did not provide
    competent evidence from those experienced in the field that it was unnecessary for New Sweden
    to use a sixteen-foot mower. Thus, the scope of New Sweden's easement on Morgan's property
    is sixteen feet. This holding does not mean that an irrigation district can simply declare its
    6
    easement to be the width of any mower    it owns. Instead, our holding is narrow and based only on
    the affidavits in this case.
    Also, Morgan argues that the district court erred by not explaining where the easement's
    width starts and ends, and where New Sweden may access its easement. Morgan is mostly
    concerned about the easement's width: whether it starts in the middle of the canal, the top of the
    canal's banks, or the high water mark. A judgment that determines an easement's existence on
    another's land "must set forth the location, width, and length      of the easement in order that
    conflicts between landowners may be avoided." Bedke v. Pickett Ranch & Sheep Co.,l43Idaho
    36,40,137 P.3d 423,427 (2006). The judgment "must describe the lands specifically and with
    such certainty that the court's mandate in connection therewith may be executed, and such that
    rights and liabilities are clearly fixed and that all parties affected thereby may readily understand
    and comply with the requirements thereof." Kosanke v. Kopp,74 ldaho 302, 307,261 p.2d            gl5,
    818 (1953). Thus, courts must specifically describe an easement's width and location.
    Here, the district court noted that the "right-of-way is sixteen (16) feet wide on each side
    of the irrigation canal based on the type of equipment that is commonly used to clean, maintain.
    or repair the irrigation canal" and "runs the length of Bradley Morgan's western boundary.,'This
    means the easement is sixteen feet wide   all along the canal that runs on the western side of
    Morgan's property. However, a court's general grant of "sixteen feet" does not necessarily
    ensure all parties affected readily understand and comply with the requirements. Here, the
    description is more than general because it notes that sixteen feet extends from ..each side of the
    irrigation canal." But nowhere in the judgment does the district court specifically state where
    "each side of the inigation canal" begins. Sheppard stated in his affrdavit that the mower
    needs
    "16 feet of flat surface" exclusive of any sloping banks. Morgan's affidavits did not rebut this
    fact. The description of the easement is not sufficient as to where on each bank a person starts
    measuring the sixteen feet. Actually, it could be argued the sixteen feet extends into the irrigation
    ditch. The easement's description needs further explanation of where on the canal the measuring
    starts. We remand so the district court can specifu the exact location on the canal where
    the
    parties should begin to measure the width of the easement.
    Morgan also contends that the district court's judgment allows New Sweden to cross
    Morgan's property at any place along the canal bank. Morgan appears to worry about this
    because a power transformer, a fence, and a head gate obstruct the entrance to the
    easement    from
    Morgan's property boundaries. Idatro Code section42-1102 gives New Sweden the right to enter
    the non-easement property to clean and maintain the canal, and provides: "The right-of-way shall
    include, but is not limited to, the right to enter the land across which the right-of-way extends,
    for the purposes of cleaning, maintaining and repairing the ditch . . . ." However, entry must take
    place in "a reasonable manner as not to increase needlessly the burden on the servient estate."
    Bedke,143 Idaho at 
    41, 137 P.3d at 428
    . Thus, in this case New Sweden cannot cross through
    Morgan's property at unreasonable entry points, but can access the easement from land other
    than the easement itself. In summary, the district court properly held the easement's width was
    sixteen feet based upon the evidence presented, but did not specify the exact location on the
    canal where the parties should begin the easement's width measurement.
    B. The district court properly concluded that Morgan must remove encroachments.
    Morgan's property had several structures, a tree, and other plants (including Russian
    Olive trees and wild rose bushes) within sixteen feet of the canal bank. Morgan contends that
    New Sweden could not remove encroachments within the easement because he did not need
    written permission for those encroachments and New Sweden did not prove as a matter of law
    that his encroachments were unreasonably interfering with the easement. Morgan also contends
    that New Sweden is not unequivocally entitled to damage anything inside of its easement
    because the easement holder has the burden to show unreasonable interference.
    The legislature addressed when an inigation district could remove encroachments in I.C.
    S 42-1209 and $       4z-I|D2.Idatro Code section42-1209 provides:
    Encroachments of any kind placed in such easement or right-of-way, without such
    express written permission shall be removed at the expense of the person or entity
    causing or permitting such encroachments, upon the request of the owner of the
    easement or right-of-way, in the event that any such encroachments unreasonably
    or materially interfere with the use and enjoyment of the easement or right-oi-
    way.
    Idaho Code section42-1102 has almost identical language.l Thus, a landowner must remove an
    encroachment that: (1) was constructed after LC. S 42-1209's effective date in 2004, (2) was
    ' Idaho Code section 42-ll02states:
    Encroachments of any kind placed in such right-of-way without express written permission of the
    owner of the right-of-way shall be removed at the expense of the person or intity causing or
    permitting such encroachment, upon the request of the owner of the righrof-way, in t-he event that
    any such encroachments unreasonably or materially interfere with the use and enjoyment of the
    right-of-way.
    constructed without permission, and (3) interferes unreasonably or materially with the use and
    enjoyment of the easement. Pioneer    lrr.   Dist., 153 Idatro at599,288 P.3d at 816. Finally, the
    inigation district must request that the party responsible remove the encroachrnent. 
    Id. The first
    issue is whether Morgan needed written permission for his encroachments. The
    district court noted Morgan needed written permission because I.C. $ 42-1102 and $ 42-1209
    both provide that "no person or entity shall cause or permit any encroachments" to the right-of-
    way without written permission. The court held that even      if   Morgan "caused" encroachments
    before the statute's 2004 effective date, Morgan had "permitted" those encroachments to stay in
    place without written permission.
    New Sweden argues that whether structures pre-dated I.C. $ 42-1209 and $ 42-1102 is
    irrelevant because the legislature made LC. $ 42-1102 apply to canals already existing when
    those statutes became effective. To support its argument, New Sweden refers to I.C. 42-1102's
    $
    last sentence: "This section shall apply to ditches, canals or other conduits existing on the
    effective date of this act, as well as to ditches, canals or other conduits constructed after such
    effective date." However, this plain language specifies that I.C. 42-l102 applies to canals, but
    $
    never mentions encroachments to canals. Also, in Pioneer we explained that to remove an
    encroachment "the encroachment must have been constructed after the effective date of I.C.
    $
    42'1209' as the statute's provision      for 'such express written permission,' which clearly
    references preceding language in the statute, was not a requirement prior to that date.', 153 Idaho
    at 599,288 P.3d at 816. Given this intelpretation and the similarity between I.C. 42-1209 and
    $              $
    42-1102, the statutes do not apply to encroachments constructed before the effective date. Hence,
    Morgan did not need written permission and LC. $ 42-1209 and g 42-1109 do not apply.
    Instead, we must use the case law that existed prior to these statutes. A servient estate
    owner "is entitled to make uses of the property that do not unreasonably interfere with the
    dominant estate owner's enjoyment of the easement." Nampa & Meridian         lrr.,l35   Idaho at 522,
    20 P.3d' at 706. This means that an easement holder gets relief "upon a showing that he is
    obstructed from exercising privileges granted in the easement." 1d. Thus, an easement holder has
    the burden of showing unreasonable interference. If he meets that burden, then the servient estate
    must remove those encroachments. The second issue is therefore whether New Sweden has
    shown that Morgan's structures and plants unreasonably interfere with its easement.
    The district court concluded that Morgan could use his land within the easement, but not
    "in   a manner that unreasonably burdens New Sweden's right to occupy the area          with equipment
    it commonly     uses   to clean and maintain" the canal. The court also dismissed the complaint for
    items damaged within the easement because of New Sweden's statutory duty to maintain the
    canal and its banks. The district court's final judgment asserted that New Sweden was entitled to
    clean the canal within its easement and        'lhat any and all     encroachments located within the
    sixteen (16) foot right-of-way . . . must be removed."
    Morgan relies on Nampa       & Meridian Inigation to       argue that a lack    of prior heavy
    equipment maintenance means that Morgan's encroachments did not umeasonably interfere with
    the easement. There, we noted that the irrigation district provided no record of canal maintenance
    with heavy equipment for over twenty years and this lack of prior use suggested that the district's
    "activity will be so infrequent that its easement rights will not be unreasonably interfered with."
    Nampa & Meridian lrr.,l35 Idaho at523,20P.3dat707.Indeed, these facts are similarto the
    facts Morgan alleged prior to 2009. However, in this case, New Sweden drove its equipment on
    the easement, unlike in Nampa         & Meridian lrrigation    where the district never used heavy
    equipment. In fact, New Sweden's maintenance attempt is the reason why this case arose. Even
    if New Sweden mowed Morgan's land for the very first time on June 25,200g,that              one mowing
    sets this case apart.
    Whether a landowner's particular use unreasonably interferes with the easement holder's
    enjoyment of the easement is a question of fact. See Nampa & Meridian          lrr.,l35   Idaho at 522-
    23,20 P.3d at     70A7.     However, even when the facts are viewed in the light most favorable to
    Morgan, there is still no genuine issue of material fact as to whether his encroachments are
    unreasonable. New Sweden established with unrebutted and competent evidence that it required
    sixteen feet to maintain the canal because of the space needed for its commonly used mower.
    Thus, New Sweden established that it is unreasonable to have any obstruction within sixteen feet
    of the canal because it would interfere with mowing. Testimony that unmovable obstructions
    caused employees to temporarily leave the easement is unrebutted evidence that these
    obstructions unreasonably interfere with canal maintenance. New Sweden therefore met its
    burden.
    Additionally, Morgan argues that the district court erred by denying his motion for leave
    to amend to add a claim for declaratory relief         because the   claim would have compelled the
    10
    district court to address necessary issues. This Court does not consider an issue when             an
    argument generally attacks the district court's findings and conclusions without any specific
    reference to evidentiary or legal errors. Bettwieser v. New York   lrr. Dist.,l54   Idaho 317,325,
    
    297 P.3d 1134
    ,   lI42   (2013). Morgan never specifically argues why the district court needed to
    address those issues and why the court ened by holding his claim was without merit and futile.
    Thus. we will not consider this issue.
    We affirm the district court's decision. Again, our holding does not mean that an
    irrigation district can do whatever it wants within its easement. Our holding also does not leave a
    landowner with no recourse for activities within an irrigation district's easement. Our holding is
    narrowly limited to the facts and affrdavits in this case.
    C. The district court did not abuse its discretion in awarding judgment to New Sweden.
    Morgan's case went to trial only on one issue: whether New Sweden negligently caused
    damages outside the easement. Negligence requires (1) a legal duty that requires a defendant to
    conform to a certain standard      of conduct; (2)  of that duty; (3) a causal connection
    breach
    between the defendant's conduct and the resulting injury; and (a) actual loss or damage.
    Grabicki v. City of Lewiston, 
    154 Idaho 686
    , 691, 
    302 P.3d 26
    ,     3l   (2013) (quoting Fragnella   v.
    Petrovich, 
    153 Idaho 266
    , 272,281 P.3d 103, 109 (2012)). The plaintiff has the burden to
    establish every element. 
    Id. Morgan argues
    the district court erred in holding New Sweden did
    not breach its duty and that Morgan provided insufficient evidence of causation.
    On appeal, we limit our review of the district court's decision to whether the evidence
    supports the findings of fact, and whether the findings of fact support the conclusions of law.
    Nampa & Meridian 1rr.,135 Idatro at 521,20 P.3d at705. We liberally construe a district court,s
    findings of fact in a bench trial in favor of the judgment entered because
    [i]t is the province of the district judge acting
    as trier of fact to weigh conflicting
    evidence and testimony and to judge the credibility of the witnesses. We will not
    substitute our view of the facts for the view of the district court. Instead, where
    findings of fact are based on substantial evidence, even if the evidence is
    conflicting, those findings will not be overturned on appeal.
    
    Id. (intemal citations
    omitted).
    l.   Res ipsa loquitur
    At trial Morgan   argued that res ipsa loquitur applied to show that New Sweden breached
    its duty of care. Res ipsa loquitur "creates an inference of the breach of the duty imposed and
    replaces direct evidence with a permissive inference of negligen ce." Christensen v. Potratz, 100
    ll
    Idaho 352,355,597 P.2d,595, 598 (1979). Res ipsa loquitur only applies when a plaintiff proves
    two   elements:     (1) the   defendant exclusively controlled and managed         the agency    or
    instrumentality that caused the injury; and (2) the circumstances permit "an average layperson to
    infer, based upon common knowledge and experience, that the plaintiff would not have suffered
    those injuries in the absence of the defendant's negligence." Enriquez v. Idaho Power      Co.,I52
    Idaho 562, 566, 
    272 P.3d 534
    , 538 (2012).
    We have stated that for res ipsa loquitur to apply it is "necessary that the cause of the
    injury point to the defendant's negligence." S. H. Kress & Co. v. Godman, 
    95 Idaho 614
    , 617,
    515 P.2d 561,564 (1973).In other words, where the injury has other probable causes, a plaintiff
    must show the defendant was negligent in some way. Enriquez, l52Idaho at 566,272 P.3d, at
    538. In Godman, a company repaired a boiler, which exploded an hour and a half later, damaging
    the plaintifPs store. 95 Idaho at 615,515 P.2d at 562. About a half hour before the explosion, the
    plaintiff   s manager   went to the boiler room and found the boiler's water pressure normal. 
    Id. The court
    held that res ipsa loquitur did not apply because there were other probable explanations    of
    the boiler's explosion. 
    Id. at617,5l5P.2dat 564.
    These explanations included the plaintiffs
    negligence when he controlled the boiler's maintenance. 1d
    Here, Morgan never established that the well and staircase damage would not have
    happened without New Sweden's negligence. Morgan alleged that the stairway was undamaged
    before Ockerman mowed and damaged immediately after. However, that temporal proximity is
    similar to the temporal proximity between the boiler repair and explosion in Godman.In both
    cases, there were other probable causes. Here, the stairway was over twenty years     old. The well
    was thirty-five years old. Morgan never presented any other evidence that New Sweden caused
    the damage. Thus, res ipsa loquitur does not apply.
    2.   Cause
    Morgan argues the district court erred by not allowing him to establish causation with
    expert testimony. The decision to admit expert testimony "is within the sound discretion of the
    trial court, and will not be overtumed except upon a showing of abuse of discretio n." Kolln v. St.
    Luke's Reg'l Med. Ctr., 130 Idaho 323,327,940 P.2d 1142, 1146 (1997). The test for abuse of
    discretion is: "(1) whether the court correctly perceived that the issue was one of discretion; (2)
    whether the court acted within the outer boundaries of its discretion and consistently with the
    legal standards applicable to the specific choices available to it; and (3) whether it reached its
    t2
    decision by an exercise of reason." White v. Mock, 
    140 Idaho 882
    , 888, 
    104 P.3d 356
    , 362
    (2004). Here, the district court denied Morgan's expert testimony because Morgan disclosed his
    expert after the discovery deadline. The court noted that this denied New Sweden the opportunity
    to fully prepare for trial. Because the district court used its discretion to make a         reasoned
    decision, we hold the district court did not abuse its discretion.
    Substantial evidence supports the district court's finding of no causation because it could
    have found New Sweden's direct evidence outweighed Morgan's circumstantial evidence.
    Ockerman's direct testimony was that the mower never contacted the stairway or well because he
    did not notice the noise and vibration that the mower makes when          it   strikes a solid object.
    Morgan's evidence was that the day before New Sweden mowed the well and stairway were
    undamaged, but the day after the stairway was damaged and the well had no water pressure.
    Morgan also provided testimony that the well drilling service found a broken joint twenty-five
    feet below the ground. That joint was not rusted, which Morgan suggested meant the break was
    recent' The district court merely had a choice of which presentation was more credible. The court
    decided for New Sweden. Substantial competent evidence supports that choice. Thus, we hold
    the district court did not abuse its discretion when it held Morgan did not establish that New
    Sweden caused the damage. Therefore, the district court properly found New Sweden was not
    negligent and entered   a   judgment in favor ofNew Sweden.
    D. Neither party is entitled to attorney fees on appeal.
    Morgan argues he is entitled to attorney fees on appeal pursuant to I.C. 12-l2l because
    $
    New Sweden pursued its declaratory judgment frivolously. This statute awards attorney fees to
    the prevailing party. Because we affirm part of the district court's judgment, Morgan is not the
    prevailing party.
    New Sweden seeks attorney fees under I.C. S 12-117. A court awards reasonable attorney
    fees under I.C. $ l2'll7 to the prevailing party.City of Osburnv. Randel,l52 Idatro 906,g10,
    
    277 P.3d 353
    , 357 (2012). Because we remand for the district court to provide a more precise
    description of the easement, New Sweden is not the prevailing        party. Thus, neither party    is
    awarded attorney fees on appeal.
    l3
    IV. CONCLUSION
    We remand for the distict court to enter a judgment that describes the precise location
    where the easement's sixteen-foot width meastrement begins. We otherwise affirm the district
    court's judgment. No afforney fees are awarded on appeal. Costs to New Sweden.
    Justice EISMANN, J. JONES,    HoRToN      and SCHROEDER, J, Pro tem,   coNCUR
    t4
    

Document Info

Docket Number: 39624

Citation Numbers: 156 Idaho 247, 322 P.3d 980, 2014 Ida. LEXIS 74

Judges: Burdick, Eismann, Jones, Horton, Schroeder

Filed Date: 3/13/2014

Precedential Status: Precedential

Modified Date: 10/19/2024