Eagle Rock Timber, Inc. v. Teton County ( 2023 )


Menu:
  •                  IN THE SUPREME COURT OF THE STATE OF IDAHO
    Docket No. 49373
    EAGLE ROCK TIMBER, INC., an Idaho )
    corporation,                       )
    )                           Boise, February 2023 Term
    Plaintiff-Appellant,            )
    )                           Opinion filed: June 13, 2023
    v.                                 )
    )                           Melanie Gagnepain, Clerk
    TETON COUNTY, IDAHO, a political )
    subdivision of the State of Idaho, )
    )
    Defendant-Respondent.           )
    Appeal from the District Court of the Seventh Judicial District of the State of Idaho,
    Teton County. Stevan H. Thompson, District Judge.
    The decisions of the district court are affirmed in part and reversed in part.
    Holden, Kidwell, Hahn & Crapo, PLLC, Idaho Falls, for Appellant. D. Andrew
    Rawlings argued.
    Hopkins Roden Crockett Hansen & Hoopes, PLLC, Idaho Falls, for Respondent.
    Steven Brown argued.
    _______________________________________________
    MOELLER, Justice.
    This appeal concerns a dispute over a public works contract involving 1.6 miles of road
    reconstruction in Teton County, Idaho. After submitting the winning bid, Eagle Rock Timber, Inc.
    (“Eagle Rock”), contracted with Teton County to reconstruct a stretch of road known as “Chapin
    Lane.” During the course of the project, Eagle Rock claims it discovered unsuitable base material
    under portions of the road. Eagle Rock maintains that Teton County’s agent, Darryl Johnson
    (“Johnson”), directed Eagle Rock to remove the material and said that the county would “make it
    right.” However, when Eagle Rock attempted to recover an amount in excess of the original
    Contract Price, Teton County denied Eagle Rock’s request, stating that it had not authorized any
    changes to the Contract. When the parties could not resolve this dispute over the amount owed,
    Eagle Rock brought suit.
    1
    Teton County moved twice for summary judgment. The district court denied the first
    motion, concluding that genuine issues of material fact existed concerning whether Johnson orally
    waived the writing requirement and whether Johnson had authorized Eagle Rock to remove the
    unsuitable base material, which could support an equitable remedy. However, when Teton County
    filed a subsequent motion for summary judgment, the district court granted it, ruling that since
    Teton County’s agent did not have actual or apparent authority to bind Teton County, the claims
    asserted by Eagle Rock failed as a matter of law.
    Eagle Rock appealed, asserting that the district court erred because there are still genuine
    issues of material fact that should be resolved by a jury. Additionally, Eagle Rock claims that the
    district court’s refusal to grant leave to amend its complaint to assert a separate cause of action
    against Johnson personally was an abuse of discretion. Eagle Rock further argues that since Teton
    County should not have prevailed below, the district court’s award of attorney fees should be
    vacated. For the reasons stated herein, we reverse the district court’s grant of summary judgment
    and denial of leave to amend. Accordingly, we also vacate the award of attorney fees to Teton
    County. However, we affirm the district court in not considering the ratification issue because it
    was beyond the scope of the pleadings at the time it was presented.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    In early 2018, Teton County opened bidding to licensed contractors on a public works road
    reconstruction project. The project entailed a 1.6-mile stretch of a county roadway near Victor,
    Idaho, called Chapin Lane. The plans for the project were designed by Jorgensen Associates, PC.
    Darryl Johnson, a licensed engineer previously employed by Jorgensen Associates, PC, from 2007
    to 2014, played a role in preparing many of the design documents in advance of Teton County
    soliciting bids for the project. However, by the time bidding was opened, Darryl Johnson had been
    hired by Teton County as its Public Works Director and County Engineer. He played a key role in
    the bidding process.
    After completing the bidding process, Eagle Rock’s bid was selected and it entered into a
    contract with Teton County for the project. According to both parties at oral argument, Johnson
    prepared the Contract documents. Per the terms of the agreement, the full Contract included: an
    eight-page agreement; performance bond; payment bond; a document entitled “General Conditions
    – Divisions 100 of the Idaho Standards for Public Works Construction”; supplementary conditions,
    drawings, and specifications; addenda; the contractor’s bid as an exhibit; and any subsequent
    2
    change orders or work change directives (these documents will be collectively referred to herein
    as the “Contract”). The Contract required that a project “Engineer” be designated to play a key role
    in specified functions of the Contract—including taking certain measurements, making
    recommendations, and holding authority to make certain minor changes as defined in the Contract.
    Jorgensen Associates was designated as the Engineer in the Contract.
    During construction, Eagle Rock asserts it discovered unsuitable base material under
    portions of the road in such amounts as could not be fully ascertained until it was removed.
    However, Eagle Rock was able to determine that it would require the removal of more material
    than originally estimated in the Contract. The original bid submitted by Eagle Rock, and
    incorporated into the Contract, was based on a projection of only 200 cubic yards of unsuitable
    material excavation, which was priced at a removal rate of $112 per cubic yard. Eagle Rock claims
    the discovery of the unsuitable base material was reported to Johnson on at least two occasions. In
    both instances, Eagle Rock claims Johnson instructed Eagle Rock, or its subcontractors, to go
    ahead and remove the unsuitable material and that Teton County would “make it right.” Teton
    County and Johnson deny that this ever occurred.
    After removal of the unsuitable base material, Eagle Rock submitted a change order. This
    change order, which included a corresponding price increase of $111,440 for the material used to
    infill where the unsuitable base material had been removed, was approved by Teton County. Eagle
    Rock then filed an “application for payment” for the removal of the unsuitable base material at the
    unit price contemplated in the Contract. Due to the unanticipated amount of material that had to
    be removed, the additional costs of removal exceeded the Contract Price by $649,600. Teton
    County denied Eagle Rock’s request, stating it had not authorized any changes in the Contract
    related to the removal of the unsuitable material. Teton County cited express provisions of the
    Contract that required any change in Contract Price or modification of the Contract to have prior
    written authorization approved by Teton County. Eagle Rock attempted to meet with Teton County
    and negotiate a unit price for the excess unsuitable base material, but Teton County maintained
    that Eagle Rock had been paid all it was due under the Contract. When the parties could not resolve
    this dispute over the amount owed, Eagle Rock brought suit.
    Teton County moved for summary judgment twice. In the first motion, Teton County
    argued that Eagle Rock “did not adhere to the contractual requirements for securing a Change
    Order and no Change Order exist[ed].” Teton County asserted that since the Contract Price could
    3
    not be changed absent a change order, Eagle Rock’s complaint should have been dismissed. The
    district court disagreed and denied the first motion due to the court’s concerns that genuine issues
    of material fact existed regarding whether Johnson orally waived the writing requirement and
    whether he gave authorization to Eagle Rock for the removal, which could implicate an equitable
    remedy. However, as summarized by the district court, “[i]n the first summary judgment decision,
    the [district court] did not delve into the scope of Johnson’s authority.”
    Less than two months after the district court issued its decision on the first motion, Teton
    County moved for summary judgment again. In the second motion for summary judgment, Teton
    County argued that Johnson had no authority to waive or modify any provisions in the Contract.
    Specifically, Teton County maintains that “the County Engineer and ‘representative’ in question,
    was not authorized to enter into, modify or amend public works contracts on behalf of the County,
    or to waive the terms thereof.” Eagle Rock asserts that this was a different position than Teton
    County had initially taken in the case and, even if it was unclear, Teton County’s argument raised
    the specter that Johnson was acting on his own. Accordingly, Eagle Rock timely moved to amend
    its complaint to name Johnson as a defendant and sought to bring independent claims against him
    personally.
    The district court granted Teton County’s second motion for summary judgment,
    concluding that because Johnson did not have actual or apparent authority to bind Teton County,
    Eagle Rock’s claims against Teton County failed as a matter of law. However, the district court
    did not rule on Eagle Rock’s pending motion to amend its complaint to seek relief against Johnson
    personally.
    While the motion to amend was still under advisement, the district court entered a judgment
    of dismissal on August 30, 2021. Eagle Rock moved for reconsideration and, among other
    arguments, asserted that the district court could not enter judgment because it had “not ruled on
    Eagle Rock’s Motion to Amend.” On November 17, 2021, the district court denied the motion to
    reconsider. Thereafter, on November 30, 2021, the district court issued a written decision denying
    Eagle Rock’s motion to amend. The district court determined that “Johnson did not have the
    required authority to alter the Contract after this motion was filed, but there has never been a
    change in Johnson’s status as an agent generally.” Further, the district court, citing DAFCO LLC
    v. Stewart Title Guar, Co., 
    156 Idaho 749
    , 756, 
    331 P.3d 491
    , 498 (2014), concluded that “there
    was a fairly significant delay in bringing the amendment without a change in stance from the
    4
    County to justify it and prejudice to the parties as raised in the Opposition and at the hearing.” For
    these reasons, the district court denied the motion to amend and issued a final judgment. Eagle
    Rock timely appealed.
    II. STANDARD OF REVIEW
    This Court reviews a grant of summary judgment de novo and employs the same standard
    of review used by the trial court in ruling on the motion for summary judgment. United Heritage
    Prop. & Cas. Co. v. Zech, 
    170 Idaho 764
    , 770, 
    516 P.3d 1035
    , 1041 (2022) (quoting AED, Inc. v.
    KDC Invest., LLC, 
    155 Idaho 159
    , 163, 
    307 P.3d 176
    , 180 (2013)). Accordingly, “[s]ummary
    judgment is appropriate ‘if the movant shows that there is no genuine dispute as to any material
    fact and the movant is entitled to judgment as a matter of law.’ ” Summerfield v. St. Luke’s McCall,
    Ltd., 
    169 Idaho 221
    , 
    494 P.3d 769
    , 776 (2021) (quoting I.R.C.P. 56(a)). “The moving party carries
    the burden of proving the absence of a genuine issue of material fact.” Banner Life Ins. Co. v. Mark
    Wallace Dixson Irrevocable Tr., 
    147 Idaho 117
    , 123, 
    206 P.3d 481
    , 487 (2009). “All disputed facts
    are to be construed liberally in favor of the nonmoving party, and all reasonable inferences that
    can be drawn from the record are to be drawn in favor of the nonmoving party.” Foster v. Traul,
    
    145 Idaho 24
    , 28, 
    175 P.3d 186
    , 190 (2007).
    When this Court reviews a discretionary decision of a lower court for an abuse of
    discretion, we must determine whether the court: “(1) correctly perceived the issue as one of
    discretion; (2) acted within the outer boundaries of its discretion; (3) acted consistently with the
    legal standards applicable to the specific choices available to it; and (4) reached its decision by the
    exercise of reason.” Lunneborg v. My Fun Life, 
    163 Idaho 856
    , 863, 
    421 P.3d 187
    , 194 (2018).
    III. ANALYSIS
    A. The district court erred because genuine issues of material fact preclude granting the
    second motion for summary judgment.
    In ruling on the second motion for summary judgment, the district court concluded that the
    express language of the Contract established as a matter of law that Johnson did not have actual or
    apparent authority to bind Teton County. After considering the inconsistent manifestations of
    authority in (1) the terms of the Contract and (2) the behavior of the parties, we disagree.
    In reviewing cases involving agency, this Court has often looked to the Restatement of
    Agency, both the Second and Third editions. See Jones v. HealthSouth Treasure Valley Hosp., 
    147 Idaho 109
    , 113, 
    206 P.3d 473
    , 477 (2009) (reviewing the definition of apparent authority); Nelson
    5
    v. Kaufman, 
    166 Idaho 270
    , 280, 
    458 P.3d 139
    , 149 (2020) (applying the definition of apparent
    authority from the Restatement (Third) of Agency); Clark v. Gneiting, 
    95 Idaho 10
    , 13, 
    501 P.2d 278
    , 281 (1972) (authoritatively applying the Restatement (Second) of Agency). 1 In the context of
    actual authority, express or implied, the Restatement (Third) of Agency provides that “[a]n agent
    acts with actual authority when, at the time of taking action that has legal consequences for the
    principal, the agent reasonably believes, in accordance with the principal’s manifestations to the
    agent, that the principal wishes the agent so to act.” RESTATEMENT (THIRD) OF AGENCY § 2.01
    (2006) (emphasis added). Conversely, the Restatement also provides: “Apparent authority is the
    power held by an agent or other actor to affect a principal’s legal relations with third parties when
    a third party reasonably believes the actor has authority to act on behalf of the principal and that
    belief is traceable to the principal’s manifestations.” Id. at § 2.03 (emphasis added); see also
    Nelson, 166 Idaho at 280, 458 P.3d at 149 (applying the Restatement’s definition of apparent
    authority). Thus, when evaluating actual authority, courts look to the reasonable belief of the agent;
    but when evaluating apparent authority, courts look to the reasonable belief of the third party.
    As we have said, ultimately “[i]t is the conduct of the principal, and not the agent, that
    binds the principal.” Chamberlain v. Amalgamated Sugar Co., 
    42 Idaho 604
    , 
    247 P. 12
    , 14 (1926)
    (citing Madill v. Spokane Cattle Loan Co., 
    39 Idaho, 754
    , 
    230 P. 45
     (1924); 2 C. J. sec. 214, p.
    574; and Anderson v. Patten, 
    157 Iowa, 23
    , 
    137 N. W. 1050
     (1912)). “Agency is a relationship
    resulting from ‘the manifestation of consent by one person to another that the other shall act on his
    behalf and subject to his control, and consent by the other so to act.’ ” Herbst v. Bothof Dairies,
    Inc., 
    110 Idaho 971
    , 973, 
    719 P.2d 1231
    , 1233 (Ct. App. 1986) (emphasis added) (citing
    RESTATEMENT (SECOND) OF AGENCY § 1, at 7 (1958)). Importantly, “[a]gency relationships are
    limited in scope to the express, implied, and apparent authority granted by the principal. Only acts
    by the agent that are within the scope of the agency relationship affect the principal’s legal
    liability.” Humphries v. Becker, 
    159 Idaho 728
    , 735, 
    366 P.3d 1088
    , 1095 (2016) (emphasis added)
    (citing RESTATEMENT (THIRD) OF AGENCY § 1.01). Thus, just as the manifestations of the principal
    create the relationship, the principal’s manifestations also define the scope of the authority granted
    to the agent.
    1
    There is no legally relevant difference between the Second and Third Restatement of Agency as it pertains to the
    issues raised by the parties below and on appeal. Compare RESTATEMENT (SECOND) OF AGENCY (1958) with
    RESTATEMENT (THIRD) OF AGENCY (2006).
    6
    Nevertheless, the principal’s manifestations that create and define the scope of an agency
    relationship are not evaluated in a vacuum—the manifestations are evaluated through reasonable
    belief. Importantly, “[a]n agent must interpret the principal’s manifestations and determine how to
    act. The context in which the relationship is situated, including the nature of the principal’s
    objectives and the custom generally followed in such circumstances, affects how the agent should
    interpret the principal’s manifestations.” RESTATEMENT (THIRD) OF AGENCY § 2.01, cmt c.
    “This Court has previously viewed the question of whether an agency relationship exists
    as a question of fact for the jury to determine.” Forbush v. Sagecrest Multi Fam. Prop. Owners’
    Ass’n, Inc., 
    162 Idaho 317
    , 330, 
    396 P.3d 1199
    , 1212 (2017) (quoting Humphries, 
    159 Idaho at
    735 n.2, 
    366 P.3d at
    1095 n.2). However, we also explained that “[w]hether facts sufficient to
    constitute an agency relationship exist is indeed a question of fact for the jury, however, whether
    a given set of facts are sufficient to constitute an agency relationship is a question of law
    appropriate for this Court’s consideration.” 
    Id.
     (quoting Humphries, 
    159 Idaho at
    735 n.2, 
    366 P.3d at
    1095 n.2).
    In this case, Johnson’s status as its agent is undisputed by Teton County. Instead, Teton
    County challenges the scope of Johnson’s authority as its agent. However, the fact that the scope
    of the agent’s authority is what is in dispute, rather than the existence of an agency relationship,
    makes this dispute no less a jury question. Determining the existence of an agency relationship
    involves the embedded question of determining the scope of the relationship: i.e., whether the
    relationship existed in regard to the disputed act. See Bailey v. Ness, 
    109 Idaho 495
    , 498, 
    708 P.2d 900
    , 903 (1985) (“[W]here the existence of an agency relationship is disputed—whether or not
    there is apparent authority on the agent’s part to act as he acted—it is a question for the trier
    of fact to resolve from the evidence.”) (citing Clark v. Gneiting, 
    95 Idaho 10
    , 12, 
    501 P.2d 278
    ,
    280 (1972); John Scowcroft & Sons Co. v. Roselle, 
    77 Idaho 142
    , 146, 
    289 P.2d 621
    , 623 (1955);
    and Thornton v. Budge, 
    74 Idaho 103
    , 108, 
    257 P.2d 238
    , 241 (1953)). Thus, under such
    circumstances, whether the facts are sufficient to conclude that an act was within the scope of the
    agency relationship is a question of fact for the jury.
    Although the interpretation of a complex contract is at the heart of this appeal, that alone
    does not mean there are no questions of fact for the jury. We have said that “[t]he existence of an
    agency relationship is a question of fact, but where the question depends on the construction of a
    legal instrument, the question becomes one of law.” Am. W. Enterprises, Inc. v. CNH, LLC, 155
    
    7 Idaho 746
    , 753, 
    316 P.3d 662
    , 669 (2013) (citing Idaho Lumber, Inc. v. Buck, 
    109 Idaho 737
    , 741,
    
    710 P.2d 647
    , 651 (1985) and Adkison Corp. v. Am. Bldg. Co., 
    107 Idaho 406
    , 409, 
    690 P.2d 341
    ,
    344 (1984)). However, the question only becomes one of law, and ripe for summary judgment,
    when the question entirely depends on the construction of the agreement. When the contract itself
    is unclear, ambiguous, or its interpretation depends on disputed facts, the question becomes a
    question of fact for a jury to resolve. See, e.g., Christiansen v. Potlatch #1 Fin. Credit Union, 
    169 Idaho 533
    , 540, 
    498 P.3d 713
    , 720 (2021) (“Summary judgment is appropriate if . . . ‘there is no
    genuine issue as to any material fact and that the moving party is entitled to judgment as a matter
    of law.’ ”).
    Based on our de novo review, we conclude that in addition to conflicting contractual
    manifestations, there are also external manifestations (or representations) by Teton County which
    conflict with the Contract and give rise to genuine issues of material fact related to Johnson’s
    authority. We will review these conflicting manifestations below.
    1. The unclear and contradictory Contract provisions provide genuine issues of material
    fact regarding Teton County’s contractual manifestations of Johnson’s authority as agent.
    While this case turns on a relatively straightforward question of agency law, the Contract
    at issue greatly complicates its resolution. The collection of incorporated documents making up
    the Contract is, at best, inartfully drafted. 2 In addition to inapplicable provisions, there are many
    inconsistencies throughout the collection of “Contract Documents” that make up the integrated
    contract—most notably the confusion of what role or roles Johnson was to play. This lack of clarity
    as to Johnson is significant. In its memorandum decision and order granting the second motion for
    summary judgment, the district court concluded that there were no genuine issues of material fact
    because the Contract’s express provisions foreclosed any actual express authority, actual implied
    authority, or apparent authority of Johnson. However, we disagree that such a conclusion is
    supported by the record when it is unclear how the Contract applies to Johnson or defines his role.
    For example, while the Contract is between Teton County, as Owner, and Eagle Rock, as
    Contractor, another key party listed in the Contract is the Engineer. Importantly, the Contract
    defines the Engineer as “[t]he individual or entity named as such in the Agreement.” (Emphasis
    added). The Contract lists Jorgensen Associates, P.C., as Engineer—with the Engineer playing a
    2
    To be clear, while some of the individual documents may be well drafted, it is the inconsistencies created by the
    combination of documents that renders the finished product problematic.
    8
    significant role in how the Contract operated. During the proceedings below and now on appeal,
    Teton County argues that the limitations of the Engineer’s authority apply to Johnson. However,
    there is nothing in the record to indicate that the Contract was ever amended to name Johnson as
    Engineer.
    At oral argument, counsel for Teton County simply argued: “The way I see it, under the
    terms of the Contract, [Johnson] was the Engineer.” Eagle Rock seems to agree that Johnson was
    the Engineer 3 and points to Supplementary Condition 8.12 as the provision that designated
    Johnson as the Engineer. 4 We disagree. As we read this provision, Condition 8.12 did nothing to
    change the designated Engineer from Jorgensen Associates to Johnson, as required in Section 3.01
    of the Agreement. Instead, Supplementary Condition 8.12 concerned another role in the Contract
    altogether—that of “Project Representative.” However, the Supplementary Condition does little
    to clarify that role. The Supplementary Condition provides:
    SC-8.12 Owner as Project Representative
    SC-8.12 Add new paragraph immediately following paragraph 8.11 of the
    General Conditions as follows:
    A. Owner will furnish Project representation during the construction
    period. The duties, responsibilities and limitations of the authority
    specified for the Engineer in Article 9-ENGINEERS STATUS
    DURING CONSTRUCTION, and elsewhere in the Contract
    Documents will be those of the Owner.
    (Emphasis in original). Putting aside the confounding title “Owner as Project Representative,” it
    is unclear how Teton County was to provide notice of who the Project Representative was. There
    is nothing in the record to indicate that Teton County ever provided written notice that it designated
    Johnson as the Project Representative. Further, this provision directly contradicts Section 9.01 of
    the General Conditions, 5 which provides that the “Engineer will be Owner’s representative during
    3
    Eagle Rock asserts that because Johnson was the Engineer, he was imbued with extra authority to modify the
    Contract. However, this argument is premised on Johnson being the Engineer on the Contract. This cannot be. The
    Contract unambiguously names Jorgensen Associates as Engineer. It defines the Engineer as “the person or entity”
    named in the Contract. Further, the Contract requires any modification to be made in writing and signed by both
    parties. Since there is no written amendment modifying the Contract to change the Engineer from Jorgensen Associates
    to Johnson, on these facts Johnson cannot be the Engineer as designated and defined in the Contract. However, as
    discussed below, his Role as County Engineer does have significance to whether there was a genuine issue of material
    fact in this case.
    4
    At oral argument, when this Court inquired of Teton County about the meaning of Supplementary Condition 8.12.,
    Counsel for Teton County responded: “I haven’t thought about that . . . I am not sure. I would have to sit and study it
    in a little more detail I think before I could give a fair answer.”
    5
    “General Conditions – Divisions 100 of the Idaho Standards for Public Works Construction” will be referred to as
    “General Conditions.”
    9
    the construction period. The duties and responsibilities and the limitations of authority of Engineer
    as Owner’s representative during construction are set forth in the Contract Documents.” 6
    (Emphasis added).
    There are more provisions which further befog the role of Project Representative. Section
    9.03, titled “Project Representative,” states:
    If Owner and Engineer agree, Engineer will furnish Resident Project
    Representative to assist Engineer in providing more extensive observation of the
    Work. The authority and responsibilities of any such Resident Project
    Representative and assistants will be as provided in the Supplementary Conditions,
    and limitations on the responsibilities thereof will be as provided in Paragraph 9.09.
    If Owner designates another representative or agent to represent Owner at the Site
    who is not Engineer’s consultant, agent or employee, the responsibilities and
    authority and limitations thereon of such other individual or entity will be as
    provided in the Supplementary Conditions.
    (Emphasis added). Thus, this section, using the same term from Supplementary Condition 8.12,
    references the defined term “Resident Project Representative.” However, the definitions section
    defines the “Resident Project Representative” as “[t]he authorized representative of Engineer who
    may be assigned to the Site or any part thereof.” (Emphasis added). Thus, the Resident Project
    Representative cannot be the Engineer because the definitions define it as the representative of the
    Engineer.
    Taken together, these significant inconsistencies and unresolved issues regarding
    Johnson’s role and authority under the Contract render the district court’s sole reliance on the
    Contract misplaced. Accordingly, the district court erred in granting summary judgment because
    there are genuine issues of material fact regarding the Contract upon which it relied to define the
    scope of Johnson’s authority as agent.
    2. Other manifestations by Teton County and Johnson are unclear and separately
    contradict the Contract, thus providing additional genuine issues of material fact.
    While the Contract itself is problematic, complicating the matter further is the uncertainty
    stemming from Johnson’s role with Teton County under the Contract. Johnson serves as the
    County Engineer and Public Works Director for Teton County. The Contract provides that Teton
    County was the Owner. However, there is no “attached evidence” to the Contract in the record
    6
    While some of the Supplementary Conditions included deletions of conflicting provisions, Supplementary Condition
    8.12 was added without deleting or in any way referencing Section 9.01 of the General Conditions.
    10
    specifying who had authority to sign on behalf of Teton County, as contemplated on the signature
    page of the Agreement. 7
    While there may be other contracts or manifestations from Teton County that limit
    Johnson’s authority in his capacity as County Engineer or Public Works Director, it cannot be said
    that this Contract, as a matter of law, does so. Should the limitations of authority applicable to the
    Engineer and the Project Representative not apply to Johnson, there is nothing in the Contract
    itself, nor in the record on appeal for that matter, that precludes Johnson from acting on behalf of
    Teton County as Owner should Teton County have authorized him to do so. Importantly, in a
    request for admission, Teton County admitted that Johnson was an agent, but did not specify
    whether this agency was by virtue of his position as Public Works Director, County Engineer, or
    grounded in the Contract. 8
    This is particularly important here because on at least one occasion Johnson referred to
    himself as the “Owner” under the Contract during the early stages of the dispute with Eagle Rock.
    In December 2018, the President of Eagle Rock sent an email to Johnson requesting a meeting
    with him and Jorgensen Associates to discuss the disputed unsuitable base material. 9 The same
    day, Johnson responded, stating:
    I’m happy to meet but let me first share some thoughts for you to consider; When
    designing a project, there are few variables that aren’t exact. Grubbing is one of
    those uncertainties. So you make some assumptions. In this case, the designer10
    assumed 6” of material be removed at the catch line and the quantity for the prism
    to be removed for the design “key” was calculated. That is how the model was run
    and how the grubbing quantities were determined. Obviously more than 6” was
    excavated and removed. After weeks of trying to figure things out, that is the
    determination I have come to. As the owner, I’m not allowed to tell you how to do
    your work. ERT was obviously not tracking material removed per lineal feet or we
    would have caught this discrepancy before Paul dropped a $100,000 change order
    7
    The signature page of the Agreement—which was seemingly never signed by Teton County—includes the following
    statement: “If Owner is a public body, attach evidence of authority to sign resolution or other documents authorizing
    execution of this Agreement.”
    8
    “REQUEST FOR ADMISSION NO. 24.: Please admit that Daryl Johnson was an agent, acting on behalf of the
    County, in relation to the Project.
    RESPONSE TO RFA NO. 24: Admitted. Darryl Johnson was identified as the point of contact for Teton County and
    was an agent, acting on behalf of the County. Paul Hamilton was identified as the point of contact for Eagle Rock
    Timber.” (Emphasis added).
    9
    In the email, Eagle Rock’s President indicates that he wants to meet with Johnson and Jorgensen Associates—
    implying Eagle Rock’s belief that it was Jorgensen, not Johnson, who was the Engineer under the project.
    10
    Johnson refers to the “designer.” Importantly, according to the Contract, the project was designed by Jorgensen
    Associates. It appears from the record that Johnson was employed by Jorgensen at some point in the design process
    and may have worked on the project’s design.
    11
    on me for additional pit run material. Whose [sic] to say at this point whether the
    project could have been successful with less material having been removed. I’m not
    sure Teton County is responsible for extra material having been removed from the
    shoulders. ERT was compensated for the import overage.
    Again, happy to discuss with you. I’m happy to invite Jorgensen to the party as well
    but guaranteed you will get the same story above in more detail.
    Let’s discuss.
    Regards;
    Darryl Johnson PE, PLS
    Teton County Public Works Director
    (Emphasis added).
    In this email, Johnson clearly represented to Eagle Rock that he was “the owner” under the
    Contract. In addition to directly establishing how Johnson represented himself to Eagle Rock, this
    also evidences Johnson’s belief that he was acting as the Owner at that time. As mentioned above,
    “[a]n agent acts with actual authority when, at the time of taking action that has legal consequences
    for the principal, the agent reasonably believes, in accordance with the principal’s manifestations
    to the agent, that the principal wishes the agent so to act.” RESTATEMENT (THIRD) OF AGENCY §
    2.01 (2006). (Emphasis added). Thus, since Johnson portrayed himself as the Owner under the
    Contract in December, there is at least a disputed issue of fact as to whether he believed that his
    authority was that of Owner under the Contract during the critical discussions with Eagle Rock
    when the unsuitable base materials were first discovered.
    Another unavoidable factor in seeking to understand the divergent roles and authority
    Johnson had in this transaction is the unusual position in which he found himself. After working
    for Jorgensen Associates, and apparently playing a significant role in designing this project, he
    was hired by Teton County and given the task of managing the same project he helped design. The
    record also indicates that Johnson played a role in the bidding process for the project and drafting
    the Contract while employed at Teton County. Thus, Johnson appears to have played a key role in
    the design, bidding, drafting of contracts, and oversight of the project.
    Importantly, the genesis of this dispute concerns the projected amount of unsuitable base
    material—a projection made by Jorgensen Associates at a time when Johnson worked on the road
    project for Jorgensen Associates. The Contract indicates a subsurface report was prepared by
    Jorgensen Associates in 2017 for Johnson, who at the time worked for Teton County; however,
    the field exploration that the subsurface report was based on was completed in September 2014,
    12
    when Johnson still worked for Jorgensen Associates. Johnson began work at Teton County in
    November 2014.
    While the record indicates that Johnson was still employed by Jorgensen Associates at the
    time of the field exploration, it is unclear from the record what role he played in that work. Still,
    the Contract provided that Eagle Rock “may rely upon the accuracy of the ‘technical data’
    contained in such reports and drawings, but such reports and drawings are not Contract
    Documents. Such ‘technical data’ is identified in the Supplementary Conditions.” The
    Supplementary Conditions provide that “[t]he technical data contained upon which [Eagle Rock]
    may rely is sub-surface soil conditions.” (Emphasis added). Importantly, at oral argument, we
    inquired of Teton County whether “the assumptions that were made in the bid were based on
    [Johnson’s] work?” Teton County’s attorney replied: “I would concede mostly his work, your
    Honor, although there were others involved I believe.” 11 (Emphasis added).
    Thus, Johnson worked for Jorgensen Associates and gathered information contained in a
    report submitted to Eagle Rock. Eagle Rock had the contractual right to rely on this technical data
    in making its bid. While it is unclear whether Eagle Rock’s reliance on this technical data in any
    way contributed to the miscalculation of the unsuitable base material, this again illustrates a
    troubling fact in this case: Johnson was personally involved with this project at every stage of its
    development—holding key roles at both Jorgensen Associates and Teton County.
    Further illustrating Johnson’s deep involvement was another statement from Teton
    County’s attorney at oral argument. When this Court asked who prepared the Contract in question,
    Teton County responded: “I believe it was Mr. Johnson.” Thus, we add contract draftsmen to the
    litany of potential hats Johnson wore in this project. While it is difficult to measure the degree to
    which having Johnson serve in these multiple roles may have contributed to the confusion at the
    heart of this controversy, at the very least it raises serious questions about how both Johnson and
    Eagle Rock perceived the extent of his authority to modify and interpret the Contract he apparently
    drafted.
    Additionally, Teton County’s course of conduct—and the manifestations of authority that
    flowed therefrom—is inconsistent with its position on appeal and throughout the litigation below.
    11
    When we inquired further whether Johnson might potentially feel responsibility for the miscalculation of the
    subsurface material report, counsel for Teton County qualified his concession to note that the subsurface condition
    investigation, presumably for the subsurface condition report by Jorgensen Associates in the record, was completed
    by another firm on behalf of Jorgensen Associates.
    13
    Teton County maintains that there was no unsuitable base material discovered, that Johnson never
    indicated that Teton County would “make it right,” and that Johnson had no authority to modify
    the Contract. If that is true, it is unclear why Teton County would have initially granted a change
    in Contract Price to pay for additional infill materials used to construct the road, while not also
    agreeing to pay the cost of removing the noncomplying materials that necessitated the additional
    infill. This is especially paradoxical because Teton County maintains that the removal was not
    required in the first place; yet it paid for the additional infill without offering a specific explanation
    as to why it did so.
    The district court concluded that the Contract itself forecloses any claim of actual authority.
    We disagree for three reasons. First, as discussed above, the Contract is unclear as to Johnson’s
    role. The plain language of the Contract demonstrates that Johnson was not named as the
    designated Engineer in the Contract. Since the Contract was never amended to name Johnson as
    Engineer, the limitations of the Engineer’s authority in the Contract may not even apply to
    Johnson. Further, even if the inconsistencies of the Project Representative role can be resolved,
    there is a question as to how Johnson assumed that role. There are suggestions in the record that
    Johnson was the Project Representative, but there is no written notice or incorporated modification
    indicating the appointment of Johnson as Project Representative. While it is unclear whether
    written notice was required under the terms of the Contract, there are still no facts in the record
    indicating how Johnson was appointed or how Eagle Rock was informed of such. Importantly,
    Johnson’s name only appears in Addendum #1 in the Contract. This was a document created prior
    to execution of the Contract, on Teton County letterhead, concerning the bid process. It indicates
    that it was submitted “BY: Public Works Director: Darryl Johnson, PE, PLS.” This passing
    reference was the only time Johnson’s name appears in the Contract. 12 Thus, Johnson’s actual role
    is not plainly evident from the four corners of the multiple documents comprising the Contract
    because Johnson is never referenced or mentioned in any of the incorporated documents in
    connection with any role—other than that of the Public Works Director.
    Second, the Contract also contains conflicting manifestations. On one hand it limits the
    authority of the Engineer but on the other it contemplates an “agent” who is only bound by the
    limitations, if any, stated only in the Supplementary Conditions. In other words, the Contract
    12
    In Change Order Number 1, the Engineer’s name and signature are left blank.
    14
    contemplates that the Owner can designate an agent to represent the Owner who is not the Engineer
    and not bound by any of the General Conditions. As referenced above, Section 9.03 states in part,
    “If Owner designates another representative or agent to represent Owner at the Site who is not
    Engineer’s consultant, agent or employee, the responsibilities and authority and limitations
    thereon of such other individual or entity will be as provided in the Supplementary Conditions.”
    (Emphasis added). Therefore, if Johnson was an agent of Teton County, and not the project
    representative or Engineer, there is no Supplementary Condition that would limit his authority.
    Third, even if the Contract did apply to Johnson, an agent’s reasonable belief of his or her
    own authority can still be in conflict with direct instructions of the principal. The Restatement
    explains:
    A principal’s instructions may not address prior occasions on which the agent has
    contravened instructions. On prior occasions the principal may have affirmatively
    approved of the agent’s unauthorized act or silently acquiesced in it by failing to
    voice affirmative disapproval. This history is likely to influence the agent’s
    subsequent interpretation of instructions. If the principal’s subsequent instructions
    do not address the history, the agent may well infer from the principal’s silence that
    the principal will not demand compliance with the instructions to any degree greater
    than the principal has done in the past. It is a question of fact whether the agent is
    reasonable in drawing such an inference.
    RESTATEMENT (THIRD) OF AGENCY § 2.02 cmt. f (2006).
    Similarly, “[a]pparent authority is based on a third party’s understanding of signals of all
    sorts concerning the actor with whom the third party interacts.” RESTATEMENT (THIRD) OF AGENCY
    § 2.03 cmt f (2006) (emphasis added). “When the third party knows the actor is an agent and knows
    the identity of the principal, the presence of apparent authority turns on the tie between these
    signals and the principal in the mind of the reasonable third party.” Id. This is a fact-intensive
    question that looks to the reasonable belief of the agent. Accordingly, “[i]t is usually a question
    for the trier of fact whether a reasonable person in the position of a third party would believe that
    an agent had the authority or the right to do a particular act. It is a separate but related question of
    fact whether such a belief is traceable to a manifestation of the principal.” RESTATEMENT (THIRD)
    OF AGENCY § 2.03 cmt. d (2006).
    3. These genuine issues of material fact preclude a grant of summary judgment.
    As discussed above, the unclear and contradictory provisions of the Contract provide
    genuine issues of material fact as to Teton County’s manifestations of Johnson’s authority as agent.
    Further, other manifestations by Teton County and Johnson contradict the Contract and create
    15
    additional issues of material fact. In sum, there are ample questions of fact that should be decided
    by a jury, rather than by the district court on summary judgment. These include, but are not limited
    to, questions of Johnson’s authority to act: (1) did Johnson have actual authority; (2) what was the
    scope of any actual authority; (3) did Johnson have apparent authority; (4) what was the scope of
    any apparent authority; (5) what role, if any, did the Contract have on Johnson’s authority; (6)
    were there other external manifestations by Teton County and Johnson, beyond the terms of the
    Contract, that manifested to Eagle Rock that Johnson had apparent authority to vary from the terms
    of the Contract? 13
    It must be remembered that, so far, these questions have only been considered by the
    district court in the context of summary judgment where “[d]isputed facts should be construed in
    favor of the non-moving party, and all reasonable inferences that can be drawn from the record are
    to be drawn in favor of the non-moving party.” Berian v. Berberian, 
    168 Idaho 394
    , 
    483 P.3d 937
    ,
    944 (2020) (quoting Nelson v. Kaufman, 
    166 Idaho 270
    , 274, 
    458 P.3d 139
    , 143 (2019)). At this
    stage, it is difficult to look at all the hats Johnson is purported to have worn as not lending at least
    some support to Eagle Rock’s position that Johnson reasonably believed or projected himself as
    one clothed in authority. He was the County Engineer and Public Works Director for Teton
    County. At times in this litigation, Teton County has argued that Johnson was the project
    “Engineer” under the Contract, and at other times it claimed that he was the “Project
    Representative.” Johnson also referred to himself as “the owner.” He also previously worked for
    Jorgensen, played a role in designing the Chapin Lane project, and purportedly prepared the
    Contract in question. Given the many hats Johnson is alleged to have worn, we conclude that there
    are genuine issues of disputed fact as to whether one of the hats he wore gave him authority to
    waive or orally modify the Contract.
    If Johnson had authority, actual or apparent, to act on behalf of Teton County and modify
    the Contract or waive provisions, then questions still remain as to whether Johnson waived the
    Contract, orally modified it, or acted in a way to implicate the other equitable remedies discussed
    by the district court in its decision on the first motion for summary judgment. Accordingly, we
    13
    Of course, at trial these questions may all be subordinate to the primary factual question for the jury at the core of
    this dispute: whether Johnson actually told Eagle Rock to remove the inadequate base material and promised that
    Teton County would “make it right.”
    16
    reverse the district court’s grant of summary judgment and remand for further proceedings
    consistent with this opinion.
    Inasmuch as we find that the district court erred in granting summary judgment, we need
    not address the other points of error raised by Eagle Rock.
    B. Eagle Rock’s ratification argument went beyond the scope of the pleadings at
    summary judgment.
    During the hearing on the motion to reconsider, Eagle Rock also argued that Teton County
    ratified Johnson’s action. In response, Teton County argues that ratification was beyond the scope
    of the pleadings because Eagle Rock did not assert it as a defense nor allege any facts to support
    that a ratification had occurred. Further, Teton County argues that since ratification was beyond
    the scope of the pleadings, it could not be considered by the district court when ruling on the
    motion to reconsider. We agree.
    “This Court has repeatedly held that ‘issues considered on summary judgment are those
    raised by the pleadings.’ ” Conner v. Hodges, 
    157 Idaho 19
    , 26, 
    333 P.3d 130
    , 137 (2014)
    (emphasis added) (quoting Vanvooren v. Astin, 
    141 Idaho 440
    , 443, 
    111 P.3d 125
    , 128 (2005));
    Gardner v. Evans, 
    110 Idaho 925
    , 939, 
    719 P.2d 1185
    , 1199 (1986); Argyle v. Slemaker, 
    107 Idaho 668
    , 669, 
    691 P.2d 1283
    , 1284 (Ct. App.1984). This longstanding principle is also bolstered by
    our notice pleading jurisprudence. As we have recognized, “[o]ur Rules of Civil Procedure
    establish a system of notice pleading.” Youngblood v. Higbee, 
    145 Idaho 665
    , 668, 
    182 P.3d 1199
    ,
    1202 (2008) (emphasis added) (citing Cook v. Skyline Corp., 
    135 Idaho 26
    , 33, 
    13 P.3d 857
    , 864
    (2000)). We have held that a “complaint need only contain a concise statement of the facts
    constituting the cause of action and a demand for relief.” 
    Id.
     (emphasis added) (quoting Clark, 
    110 Idaho at 325
    , 715 P.2d at 995). Importantly, “[t]he general policy behind the current rules of civil
    procedure is to provide every litigant with his or her day in court . . . [and] the purpose of a
    complaint is to inform the defendant of the material facts upon which the plaintiff bases his action.”
    Massey v. Conagra Foods, Inc., 
    156 Idaho 476
    , 484, 
    328 P.3d 456
    , 464 (2014) (emphasis added)
    (quoting Clark, 
    110 Idaho at 325
    , 715 P.2d at 995); see also Loveland v. State, 
    141 Idaho 933
    , 936,
    
    120 P.3d 751
    , 754 (Ct. App. 2005) (“[T]he purpose of pleadings is to frame the issues upon which
    a cause is to be tried”).
    Here, no facts alleged in the complaint suggested a cause of action grounded in a principal’s
    ratification of an agent’s unauthorized act. In reading the complaint, Teton County would not have
    17
    been on notice that the issue of ratification was before the district court on summary judgment;
    thus, it was improper to consider it on reconsideration. The general facts in the complaint stress
    that the removal was “required” and allege that the “Project’s engineer agreed that the Removal
    was necessary and consented to its completion.” There were no facts alleged suggesting ratification
    by Teton County. The specific count for breach of contract, as alleged in the complaint, does not
    mention ratification. The alternative counts in the complaint seek only equitable relief based on
    the completion of the work and in no way reference the agent of Teton County or any act of
    ratification.
    While the complaint need only contain a concise statement of the facts constituting the
    cause of action and a demand for relief, Eagle Rock’s complaint contains no such concise statement
    that would put Teton County on notice that the material issue of ratification was the basis of its
    breach of contract claim. Accordingly, the district court did not err in not considering the issue
    beyond the scope of the pleadings. However, nothing in our decision precludes Eagle Rock from
    moving the district court for leave to amend its complaint on remand to include the issue of
    ratification.
    C. The district court erred by denying Eagle Rock’s motion to amend its complaint.
    Eagle Rock argues that the district court erred in not granting it leave to amend its
    complaint to add Johnson as a party and to assert claims against him personally. Specifically, Eagle
    Rock asserts that “[Teton] County had admitted that Darryl Johnson was its agent in relation to the
    Project, and had not raised any issue in relation to his authority until the County’s second motion
    for summary judgment, filed on April 14, 2021. Only then was the issue of authority raised.”
    (Internal citation omitted.) Thus, Eagle Rock contends that, in light of this change in position, the
    district court abused its discretion in not freely granting leave to amend. We agree.
    Aside from amendments as a matter of right, Rule 15(a) of the Idaho Rules of Civil
    Procedure provides that “[i]n all other cases, a party may amend its pleading only with the
    opposing party’s written consent or the court’s leave. The court should freely give leave when
    justice so requires.” I.R.C.P. 15(a). “Under Idaho law, motions for leave to amend pleadings are
    to be liberally granted . . . .” Taylor v. McNichols, 
    149 Idaho 826
    , 847, 
    243 P.3d 642
    , 663 (2010).
    Further, “ ‘[i]n the absence of any apparent or declared reason ... the leave sought should, as the
    rules require, “be freely given” ’ because an ‘outright refusal to grant the leave without any
    justifying reason appearing for the denial ... is merely [an] abuse of [ ] discretion and inconsistent
    18
    with the spirit’ of the Rules of Civil Procedure.” 
    Id.
     (quoting Clark, 
    110 Idaho at 326
    , 715 P.2d at
    996). However, a district court can act within the bounds of its discretion when denying a motion
    to amend.
    Grounds for denial include but are not limited to: “Undue delay; Bad faith and dilatory
    motive on the part of the movant; Repeated failure to cure deficiencies by amendments previously
    allowed; Undue prejudice to the opposing party, and Futility.” Zeyen v. Pocatello/Chubbuck Sch.
    Dist. No. 25, 
    165 Idaho 690
    , 695, 
    451 P.3d 25
    , 30 (2019) (capitalization in original) (citing Foman
    v. Davis, 
    371 U.S. 178
    , 182 (1962)). Further, in Zeyen, this Court reiterated that while “[t]imeliness
    is important in view of the Foman factors[,]” it is not dispositive because “timeliness alone is not
    a sufficient reason to deny a motion to amend.” 
    Id.
     (quoting DAFCO LLC, 
    156 Idaho at 756
    , 
    331 P.3d at 498
    .
    Here, Eagle Rock moved for leave to amend its complaint in May 2021. More than six
    months later, in November 2021, the district court, citing DAFCO LLC v. Stewart Title Guar, Co.,
    
    156 Idaho 749
    , 756, 
    331 P.3d 491
    , 498 (2014), denied the motion, finding that “there was a fairly
    significant delay in bringing the amendment without a change in stance from the County to justify
    it and prejudice to the parties as raised in Opposition and at the hearing.” That is the extent of the
    district court’s analysis.
    Importantly, in its first motion for summary judgment, Teton County focused on the
    express agreement of the parties and the lack of a written modification under the terms of the
    Contract. In the supporting memorandum, while the Engineer is mentioned, Teton County never
    mentions Darryl Johnson. However, in the second motion, much of Teton County’s brief was
    dedicated to the scope of Johnson’s authority. Specifically, Teton County argued “the County
    Engineer and ‘representative’ in question, was not authorized to enter into, modify or amend public
    works contracts on behalf of the County, or to waive the terms thereof.” This argument was not
    framed in the alternative and its ambiguous nature leaves Teton County able to argue both that
    Johnson did not alter, amend, or waive any provision of the Contract and, even if he did so act,
    Johnson acted beyond the scope of his authority.
    In ruling on the second motion for summary judgment, the district court concluded that
    Johnson did not have authority to modify the Contract. In reaching this conclusion, the district
    court noted that there had “never been a change in Johnson’s status as an agent generally.”
    However, the district court did not address whether Teton County changed its position on the scope
    19
    of Johnson’s authority and raised the possibility that he acted on his own. Further, while the district
    court faulted Eagle Rock for the “fairly significant delay” in moving to amend, it concluded that
    the County had not changed its stance as to Johnson’s status as an agent—again, without
    addressing whether Teton County changed its position as to the scope of Johnson’s authority as
    agent. This is particularly relevant because, consistent with Eagle Rock’s view that this was a new
    position taken by Teton County, Eagle Rock filed the motion to amend shortly after the second
    motion for summary judgment was filed by Teton County in which it asserts that Johnson acted
    outside his authority.
    The district court also addressed “prejudice” generally, without explaining or making any
    other finding on how granting the motion to amend would result in “unfair prejudice” to Teton
    County under Clark, Zeyen, and Foman. Arguably, based on the district court’s second summary
    judgment ruling, Teton County would have been dismissed from the case even if the amendment
    had been granted and Johnson was added as a party to the complaint. Ultimately, because the
    district court failed to set forth the basis for its conclusions, its reasons for denying the motion to
    amend are conclusory. Thus, the district court failed to exercise reason in making its conclusions
    on the motion to amend.
    Further, the district court did not act consistently within the legal framework set forth in
    Rule 15. Given the liberal nature of this rule, and in light of Teton County’s new argument in its
    second motion for summary judgment, it appears that the district court did not “freely give” leave
    for Eagle Rock to amend its complaint. Taylor, 
    149 Idaho at 847
    , 
    243 P.3d at 663
    . Accordingly,
    we conclude that the district court also abused its discretion by not freely giving leave to Eagle
    Rock to amend its pleading.
    D. Attorney Fees
    The district court awarded attorney fees to Teton County pursuant to Idaho Code section
    12-120(3), concluding that Teton County prevailed and the gravamen of the claim was a
    commercial transaction. Eagle Rock argues that attorney fees should not have been granted below
    because Teton County should not have prevailed. For the reasons set forth above, we agree.
    Idaho Code section 12-120(3) only applies to a prevailing party. See I.C. § 12-120(3)
    (“[T]he prevailing party shall be allowed a reasonable attorney’s fee to be set by the court, to be
    taxed and collected as costs.”). Given the result on appeal, Teton County should not have prevailed
    20
    below. Accordingly, we vacate the award of attorney fees to Teton County. On remand, the district
    court may reconsider whether attorney fees should be assessed once the matter is fully adjudicated.
    IV. CONCLUSION
    The district court’s grant of summary judgment is reversed because there are genuine issues
    of material fact that preclude the grant of summary judgment. Further, the district court’s denial
    of leave to amend the complaint is also reversed. Given the result on appeal, we also reverse the
    award of attorney fees below because Teton County is not the prevailing party at this stage of the
    litigation. See I.C. § 12-120(3). However, we affirm the district court in not considering the
    ratification issue because it was beyond the scope of the pleadings at the time it was presented.
    Accordingly, this matter is remanded for further proceedings consistent with this opinion. Costs
    on appeal are awarded to Eagle Rock as a matter of course. I.A.R. 40.
    Chief Justice BEVAN, Justices BRODY, STEGNER and ZAHN CONCUR.
    21