Illinois Landowners Alliance, NFP v. Illinois Commerce Commission , 2017 Ill. LEXIS 671 ( 2017 )


Menu:
  •                                      
    2017 IL 121302
    IN THE
    SUPREME COURT
    OF
    THE STATE OF ILLINOIS
    (Docket Nos. 121302, 121304, 121305, 121308 cons.)
    ILLINOIS LANDOWNERS ALLIANCE, NFP, et al., Appellees, v. ILLINOIS
    COMMERCE COMMISSION et al., Appellants.
    Opinion filed September 21, 2017.
    CHIEF JUSTICE KARMEIER delivered the judgment of the court, with
    opinion.
    Justices Freeman, Thomas, Kilbride, Garman, Burke, and Theis concurred in
    the judgment and opinion.
    OPINION
    ¶1        This matter is before the court on administrative review of an order by the
    Illinois Commerce Commission (Commission) granting a certificate of public
    convenience and necessity to Rock Island Clean Line, LLC (Rock Island), for
    construction of a high voltage electric transmission line between O’Brien County,
    Iowa, and a converter station adjacent to a Commonwealth Edison Company
    (ComEd) substation in Grundy County, Illinois. The appellate court reversed the
    Commission’s order on the grounds that the Commission had no authority under
    the Public Utilities Act (Act) (220 ILCS 5/1-101 et seq. (West 2012)) to consider
    Rock Island’s application for a certificate of public convenience and necessity
    because the company did not qualify as a public utility under Illinois law. The
    Commission and various entities involved in the Commission proceedings sought
    further review by our court through separate petitions for leave to appeal (Ill. S. Ct.
    R. 315 (eff. Mar. 15, 2016)). We granted those petitions and consolidated the
    proceedings for briefing, argument, and disposition. For the reasons that follow, we
    agree with the appellate court that the Commission’s order must be reversed.
    ¶2                                     BACKGROUND
    ¶3       Rock Island is a Delaware limited liability company with its principal offices in
    Houston, Texas. It is a wholly owned subsidiary of Rock Island Wind Line, LLC,
    which is, in turn, a wholly owned subsidiary of Clean Line Energy Partners, LLC
    (Clean Line). Clean Line is owned in part by Grid America Holdings, Inc. Grid
    America is a subsidiary of National Grid USA, a business that owns and operates
    more than 8600 miles of high voltage transmission facilities in the United States.
    ¶4       Rock Island plans to construct and manage a high voltage direct current (DC)
    electric transmission line running from an alternating current (AC)-to-DC current
    converter station in O’Brien County, Iowa, to a planned DC-to-AC current
    converter station in Grundy County, Illinois. An additional four-mile segment of
    AC lines would run from the planned converter station to ComEd’s existing
    transmission system at or near its Collins substation, which is also in Grundy
    County.
    ¶5       The purpose of the proposed transmission line is to connect wind generation
    facilities in northwest Iowa, South Dakota, Nebraska, and Minnesota with
    electrical markets that utilize an electrical grid operated by PJM Interconnection,
    LLC (PJM), the regional transmission organization (RTO) responsible for
    coordinating the movement of wholesale electricity to markets in Illinois, Indiana,
    Michigan, Ohio, Kentucky, the District of Columbia, and eight states in the
    Northeast. Once completed, the line will extend for a total of 500 miles. Less than
    -2-
    one-fourth of that distance, 121 miles, will be in Illinois. The remainder will be in
    Iowa.
    ¶6       Rock Island has never constructed a high voltage transmission line and does not
    yet own, control, operate, or manage any plants, equipment, or property in Illinois
    or elsewhere used or to be used in the transmission of electricity or for any other
    purpose related to utilities. Rather, it has an option to purchase certain real property
    in Grundy County. The property subject to the option is the proposed site for the
    DC-to-AC converter station at which the transmission line would terminate.
    ¶7        Witnesses for Rock Island testified that the project will cost approximately $1.8
    billion to construct, operate, and maintain. As of December 2013, shareholders had
    committed approximately $95 million of equity to Clean Line, one of Rock Island’s
    parent companies. Only about $21.6 million of this sum, however, was specifically
    invested in the Rock Island project.
    ¶8        Under the system currently in place in the United States, new transmission lines
    are typically constructed after an RTO such as PJM has conducted a transmission
    study and concluded the new line is necessary for the reliability of the system or to
    relieve transmission congestion. When the necessity for the new line has been
    established by the RTO, the developer who constructs the line is entitled to recoup
    its costs and receive a regulated rate of return on its investment through cost-based
    rates billed to the customers who benefit from the improved service. Rock Island,
    however, is not a member of PJM or any RTO, and its proposed project is outside
    the RTO approval process. Because of that, it will not be eligible to recover any of
    its construction costs through cost-based electrical rates paid by ratepayers in
    Illinois. Rather, this is to be a “merchant transmission” project. See Transmission
    Planning & Cost Allocation by Transmission Owning & Operating Public Utilities,
    
    76 Fed. Reg. 49,842
     (Aug. 11, 2011).
    ¶9       Merchant transmission projects are a relatively new development in the
    electricity transmission business and have arisen with the development of wind and
    other variable energy resources. In contrast to traditional public utilities, which are
    allowed to recover a regulated, cost-based rate of return from electricity customers
    on transmission line projects and other investments, merchant transmission
    developers obtain revenue to cover the costs of constructing and operating
    transmission facilities exclusively from power-generating customers who purchase
    -3-
    transmission capacity and utilize the transmission service pursuant to negotiated
    contracts. Alexandra B. Klass & Jim Rossi, Reconstituting the Federalism Battle in
    Energy Transportation, 
    41 Harv. Envtl. L. Rev. 423
    , 440 n.73 (2017). Merchant
    transmission providers also differ from traditional public utilities in that they
    assume all of a project’s market risks. Alexandra B. Klass, Takings and
    Transmission, 
    91 N.C. L. Rev. 1079
    , 1096 n.99 (2013). They have no obligation to
    undertake transmission projects and will do so only when such projects are
    financially viable. Heidi Werntz, Let’s Make a Deal: Negotiated Rates for
    Merchant Transmission, 
    28 Pace Envtl. L. Rev. 421
    , 425 (2010).
    ¶ 10       Rock Island’s project is currently still at the developmental stage, and its
    prospects are uncertain. As part of its initial planning, the company secured three
    interconnection queue positions with PJM to allow it to deliver 3500 megawatts of
    power to the grid PJM operates. The assignment of queue positions ensures that the
    existing grid system is capable of accepting the additional power, and obtaining a
    queue position is necessary before an entity may connect to PJM’s grid. Since first
    obtaining its three queue positions, however, Rock Island has surrendered two of
    the positions and reduced the capacity it would add under the third to 1600
    megawatts. It did so because it was unwilling or unable at this stage of the process
    to undertake the additional engineering and design work necessary before an
    interconnection agreement with PJM could be executed. The surrender of the
    positions does not foreclose Rock Island from requesting additional queue
    positions in the future.
    ¶ 11       Testimony established that the company cannot and will not move forward with
    the project unless and until a sufficient number of customers contract for power
    transmitted by the line to enable the company to attract the requisite financing. At
    the present time, no potential customers have obtained rights to buy service on the
    transmission line. Indeed, the wind generators that might use the transmission line
    and that serve as the basis for Rock Island’s energy and financial simulation models
    do not yet exist.
    ¶ 12       Although there are not yet any customers for Rock Island’s planned
    transmission service, the company plans to offer that service to any “eligible
    customers” under an open access transmission tariff (OATT) pursuant to Federal
    Energy Regulatory Commission (FERC) regulations. The FERC defines “eligible
    -4-
    customers” broadly to include any buyer of transmission service, subject only to
    limitations contained in section 824k of the Federal Power Act (16 U.S.C.
    § 824k(h) (2012)).
    ¶ 13       The FERC has approved a proposal from Rock Island to “pre-subscribe” up to
    75% of the proposed line’s transmission capacity to anchor customers. Those
    customers will consist largely, if not entirely, of yet-to-be-built wind generators in
    the resource area of northwest Iowa, South Dakota, Nebraska, and Minnesota who
    seek to deliver the power they generate to the PJM grid. The remaining 25% of
    capacity will be sold at auction through a process known as “open season bidding.”
    The FERC has not mandated that Illinois entities participate in the bidding process,
    and the project does not designate any part of the energy transmitted along the
    proposed line for public use in Illinois.
    ¶ 14      If any transmission capacity remains available after the open season bidding
    process concludes, any eligible customer may request service under the OATT. In
    handling such requests, Rock Island must comply with the FERC’s open access
    requirements. The company will be prohibited from discriminating or showing
    undue preference in selling its transmission service.
    ¶ 15       The reason that the FERC is involved in the project is that under the Federal
    Power Act (16 U.S.C. § 791a et seq. (2012)), the FERC has exclusive authority to
    regulate “the sale of electric energy at wholesale in interstate commerce.” 
    16 U.S.C. § 824
    (b) (2012). Hughes v. Talen Energy Marketing, LLC, ___ U.S. ___,
    ___, 
    136 S. Ct. 1288
    , 1292 (2016). The FERC’s jurisdiction also extends to all
    facilities for transmission of electric energy in interstate commerce, authority that is
    not limited to the wholesale market. 
    16 U.S.C. § 824
    (b) (2012); New York v.
    Federal Energy Regulatory Comm’n, 
    535 U.S. 1
    , 17 (2002) (New York v. FERC).
    ¶ 16       Although Rock Island’s proposed transmission services are subject to the
    FERC’s jurisdiction, the existence of FERC jurisdiction does not mean that state
    regulatory authorities have no say in the project. To the contrary, the Federal Power
    Act makes federal and state powers “complementary” and “comprehensive,” so
    that there will be “no ‘gaps’ for private interests to subvert the public welfare.”
    (Internal quotation marks omitted.) Federal Energy Regulatory Comm’n v. Electric
    Power Supply Ass’n, ___ U.S. ___, ___, 
    136 S. Ct. 760
    , 780 (2016) (quoting
    Federal Power Comm’n v. Louisiana Power & Light Co., 
    406 U.S. 621
    , 631
    -5-
    (1972)). Identifying the precise contours of state and local authority under such
    collaborative programs can be difficult and delicate. See Allco Finance Ltd. v. Klee,
    
    861 F.3d 82
    , 101-02 (2nd Cir. 2017). Controlling federal precedent makes clear,
    however, that the siting of new transmission lines is generally not a matter within
    the jurisdiction of the FERC. James J. Hoecker & Douglas W. Smith, Regulatory
    Federalism and Development of Electric Transmission: A Brewing Storm?, 
    35 Energy L.J. 71
    , 82 (2014). Rather, Congress left to the states significant authority to
    regulate the siting of transmission lines. New York v. FERC, 
    535 U.S. at 24
    .
    Accordingly, any company wishing to construct an interstate transmission line
    must normally obtain siting permission and eminent domain authority from every
    state through which the line will pass, in accordance with the states’ permitting
    processes and standards. Klass, Takings and Transmission, supra, at 1101. 1
    ¶ 17       As noted earlier, the bulk of Rock Island’s proposed transmission line will be
    located in the state of Iowa. In November 2014, Rock Island filed with the Iowa
    State Department of Commerce Utilities Board 16 petitions for electric
    transmission line franchises for the 16 different Iowa counties through which the
    proposed line would run. The Iowa Utilities Board established a procedural
    schedule to govern that state’s regulatory review of the project. Under that
    schedule, Rock Island was required to file certain documents beginning in January
    2017. On December 22, 2016, however, Rock Island asked the Iowa Utilities Board
    for leave to withdraw all 16 petitions it had filed in connection with the project. The
    Iowa Utilities Board granted that request the following day. Although Rock Island
    advised Iowa authorities that it might submit new filings in that state depending on
    how judicial review of the regulatory proceedings in our state was ultimately
    resolved, the Iowa section of the project is currently dead. In re Rock Island Clean
    Line LLC, Iowa Dep’t Com. Util. Bd. No. E-22248 (Dec. 23, 2016),
    https://efs.iowa.gov/cs/groups/external/documents/docket/mdax/njew/
    ~edisp/1610798.pdf.
    1
    A minority of states do not require state permitting and siting of transmission lines
    under certain circumstances, and in some situations transmission siting authority lies with
    the FERC. Hoecker & Smith, supra, at 82. See also Alexandra B. Klass & Elizabeth J.
    Wilson, Interstate Transmission Challenges for Renewable Energy: A Federalism
    Mismatch, 
    65 Vand. L. Rev. 1801
    , 1819 (2012) (discussing FERC “backstop siting
    authority” to override a state’s siting authority where, e.g., the state refuses to timely act or
    attaches project-killing conditions to a permit).
    -6-
    ¶ 18       In addition to seeking regulatory approval in Iowa, Rock Island submitted an
    application to the Illinois Commerce Commission for issuance of a certificate of
    public convenience and necessity under section 8-406 of our Public Utilities Act
    (220 ILCS 5/8-406(a), (b) (West 2012)) to permit it to operate as a transmission
    public utility in Illinois and construct, operate, and maintain the electric
    transmission line just described. Rock Island also made a request pursuant to
    section 8-503 of the Act (220 ILCS 5/8-503 (West 2012)) for entry of an order
    authorizing or directing construction of the proposed line. In addition, Rock Island
    sought authorization to use the FERC Uniform System of Accounts to file the
    annual financial information reports required by the Commission and requested
    permission to maintain its books and records at a location outside Illinois.
    ¶ 19       Numerous entities, individuals, and organizations sought and were granted
    leave to intervene in the proceedings. Among these were ComEd; four local unions
    of the International Brotherhood of Electrical Workers (collectively referred to in
    this opinion as the IBEW); the Illinois Agricultural Association, a/k/a the Illinois
    Farm Bureau; and the Illinois Landowners Alliance, NFP. Commission staff
    members also participated in the application process by submitting evaluations,
    reports, and recommendations.
    ¶ 20        The IBEW supported Rock Island’s petition. ComEd, the Illinois Agricultural
    Association and the Illinois Landowners Alliance all opposed it. The Illinois
    Agricultural Association and the Illinois Landowners Alliance also each filed
    motions to dismiss. As grounds for those motions, the organizations asserted that
    Rock Island did not meet the threshold criteria necessary to qualify as a public
    utility within the meaning of section 3-105 of the Act (220 ILCS 5/3-105 (West
    2012)) and that the company was therefore ineligible for the relief it sought from
    the Commission.
    ¶ 21       Both motions were denied by a Commission administrative law judge (ALJ).
    The ALJ rejected the argument that Rock Island could not apply for a certificate of
    public convenience because it did not already have in place the transmission
    infrastructure that would qualify it as a public utility. Looking at the language of the
    applicable provisions of the Public Utilities Act, the ALJ held that nothing therein
    required applicants to own public utility plants, equipment, or property at the time
    they apply for certificates to construct public utility facilities. To construe the
    -7-
    statutes as imposing such a requirement would, in the ALJ’s view, create an
    unworkable “Catch-22.” Specifically, it would mean that
    “an entity could not apply for a certificate to construct public utility facilities
    and transact public utility business unless the entity already owns public utility
    plant, equipment or property. Under Section 8-406(b), however, constructing
    the public utility facilities needed in order to apply for a certificate, without
    already possessing a certificate authorizing construction of those facilities, is
    prohibited.”
    ¶ 22       The ALJ also found support for this conclusion in the past practices of the
    Commission. The ALJ pointed out at least one other case in which the Commission
    had granted a certificate of public convenience and necessity for construction of an
    electric transmission line and for operation as a public utility to an entity that was
    not yet a certified public utility within the meaning of the Public Utility Act at the
    time that it first filed to obtain certification for construction of the transmission line.
    ¶ 23       Following denial of the motions to dismiss, the matter proceeded to a hearing.
    Extensive testimony was presented, and the matter was thoroughly briefed by the
    parties. Based on the evidence presented and the applicable law, the Commission
    issued a 226-page order in which it concluded that the ALJ had acted correctly in
    denying the motions to dismiss, found that the Commission had authority to
    consider Rock Island’s application, and granted Rock Island the certificate of
    public convenience and necessity it had requested. The Commission also allowed
    the requests Rock Island had made regarding record keeping, subject to certain
    conditions. It did not grant the company’s request for relief under section 8-503 of
    the Act (authorizing or directing construction of the line) but specified that its
    determination was without prejudice to the company’s right to seek such relief in
    the future.
    ¶ 24       ComEd, the Illinois Agricultural Association, and the Illinois Landowners
    Alliance requested rehearing, which the Commission denied. They then sought
    administrative review in the appellate court. 220 ILCS 5/10-201(a) (West 2014).
    There, they raised two arguments: first, that the Commission lacked authority to
    grant Rock Island’s application for a certificate of public convenience and
    necessity because Rock Island does not qualify as a public utility within the
    meaning of the Public Utilities Act (220 ILCS 5/1-101 et seq. (West 2012)) and,
    -8-
    second, that the Commission’s findings in favor of Rock Island were not supported
    by substantial evidence. 
    2016 IL App (3d) 150099
    , ¶ 31.
    ¶ 25        The appellate court found the first of these arguments to be dispositive.
    Initially, it acknowledged that an applicant need not already have status as a public
    utility before seeking a certification of public convenience and necessity under
    sections 8-406(a) and (b) of the Public Utility Act (220 ILCS 5/8-406(a), (b) (West
    2012)). Rather, applicants may seek recognition as a public utility while, at the
    same time, applying for a certificate of public convenience and necessity to transact
    business and construct facilities within our state. 
    2016 IL App (3d) 150099
    , ¶ 49.
    The problem in this case, in the appellate court’s view, was that Rock Island failed
    to meet the qualifications to be a public utility as that term is defined by the Public
    Utilities Act because it neither owned, controlled, operated, or managed utility
    assets, directly or indirectly within the state, nor did it offer such assets for public
    use without discrimination. Id. ¶¶ 43-46.
    ¶ 26       In light of its conclusion that Rock Island could not meet the requirements to
    qualify as a public utility, the appellate court reasoned that the Commission had no
    legal authority to issue the company a certificate of public convenience and
    necessity. Id. ¶ 47. It therefore reversed the Commission’s order granting the
    certificate to Rock Island and remanded the cause to the Commission with
    directions to enter an appropriate order. Id. ¶ 53. The appellate court further
    concluded that it did not need to reach the additional question of whether the
    Commission’s order was also subject to reversal because it was not supported by
    substantial evidence. Id. ¶ 51.
    ¶ 27       The Commission, Rock Island, the IBEW, Wind on the Wires, and the Natural
    Resources Defense Council (hereinafter referred to collectively as appellants)
    sought leave to appeal to our court pursuant to Illinois Supreme Court Rule 315
    (eff. Mar. 15, 2016). As indicated at the outset of this opinion, we allowed
    appellants’ requests and consolidated the cases for briefing, argument, and
    disposition. We also allowed the State of Illinois, Infinity Renewables, the Citizens
    Utility Board, and LSP Transmission Holdings, LLC, to file friend of the court
    briefs in support of appellants. Ill. S. Ct. R. 345 (eff. Sept. 20, 2010).
    -9-
    ¶ 28                                          ANALYSIS
    ¶ 29       When our court grants leave to appeal from a judgment of the appellate court in
    an administrative review case, as we did here, it is the final decision of the
    administrative agency and not the judgment of the appellate court that is before us.
    Provena Covenant Medical Center v. Department of Revenue, 
    236 Ill. 2d 368
    , 386
    (2010). Review of final decisions of the Commission, the administrative agency
    whose ruling is being challenged in this case, involves the exercise of special
    statutory jurisdiction and is constrained by the provisions of the Public Utilities Act
    (220 ILCS 5/1-101 et seq. (West 2014)). People ex rel. Madigan v. Illinois
    Commerce Comm’n, 
    231 Ill. 2d 370
    , 387 (2008). Section 10-201(d) of the Act
    provides that “[t]he findings and conclusions of the Commission on questions of
    fact shall be held prima facie to be true and as found by the Commission” and
    “rules, regulations, orders or decisions of the Commission shall be held to be prima
    facie reasonable.” 220 ILCS 5/10-201(d) (West 2014). The Public Utilities Act
    further provides, however, that a “court shall reverse a Commission *** order or
    decision, in whole or in part, if it finds,” inter alia, that the “findings of the
    Commission are not supported by substantial evidence based on the entire record of
    evidence” or the “order or decision is without the jurisdiction of the Commission”
    or the “order or decision is in violation of the State or federal constitution or laws.”
    220 ILCS 5/10-201(e)(iv) (West 2014). 2 In addition, courts are not bound by the
    Commission’s rulings on questions of law. United Cities Gas Co. v. Illinois
    Commerce Comm’n, 
    163 Ill. 2d 1
    , 12 (1994). We review such questions de novo.
    See City of Elgin v. Illinois Commerce Comm’n, 
    2016 IL App (2d) 150047
    , ¶ 26.
    ¶ 30       Appellants contend that the Commission’s decision in this case was factually
    and legally sound and that in reversing that decision and remanding the cause to the
    Commission, the appellate court adopted an unreasonable and erroneous
    construction and application of the governing statutes, departed from established
    principles of administrative review, and impermissibly usurped the role of the
    2
    While the statute and this court’s precedent refer to the Commission’s “jurisdiction,”
    we have recently reiterated that the term “jurisdiction” is not strictly applicable when
    referring to an administrative agency. It may, however, be used as shorthand for describing
    the agency’s authority to act. Zahn v. North American Power & Gas, LLC, 
    2016 IL 120526
    , ¶ 14 n.2 (citing J&J Ventures Gaming, LLC v. Wild, Inc., 
    2016 IL 119870
    , ¶ 23
    n.6).
    - 10 -
    Commission in the regulatory process. For their part, ComEd, the Illinois
    Agricultural Association, and the Illinois Landowners Alliance (hereinafter
    appellees) argue, as they did in the appellate court, that the Commission’s decision
    granting Rock Island’s application for a certificate of public convenience and
    necessity is fatally infirm and should be set aside because Rock Island does not
    meet the qualifications to be considered a public utility within the meaning of the
    Public Utilities Act (220 ILCS 5/1-101 et seq. (West 2012)). Because it does not
    qualify as a public utility, they assert, the company was ineligible to receive, and
    the Commission had no authority to grant, a certificate of public convenience and
    necessity.
    ¶ 31        In undertaking our review, we look first to the governing statutory framework.
    The Public Utilities Act, as its name reflects, was enacted to provide for the
    regulation of “public utilities.” Springfield Gas & Electric Co. v. City of
    Springfield, 
    292 Ill. 236
    , 243 (1920), aff’d, 
    257 U.S. 66
     (1921). It arose from a
    conviction that “the health, welfare and prosperity of all Illinois citizens require the
    provision of adequate, efficient, reliable, environmentally safe and least-cost public
    utility services at prices which accurately reflect the long-term cost of such services
    and which are equitable to all citizens.” 220 ILCS 5/1-102 (West 2012).
    Underlying the law is a belief that these objectives can best be met through
    governmental supervision of public utilities and regulation of competition between
    them. See Commerce Comm’n v. Chicago Rys. Co., 
    362 Ill. 559
    , 566 (1936).
    Because unrestrained competition prior to adoption of the Act had frequently
    resulted in the financial failure of utilities, the law adopted the principle of
    regulated monopoly (Local 777, DUOC, Seafarers International Union v. Illinois
    Commerce Comm’n, 
    45 Ill. 2d 527
    , 535 (1970); People v. City of Chicago, 
    349 Ill. 304
    , 326 (1932)) and aims to ensure efficient public utility service at reasonable
    rates by compelling established public utilities occupying a given field to provide
    adequate service while at the same time protecting them from ruinous competition
    (Gulf Transport Co. v. Illinois Commerce Comm’n, 
    402 Ill. 11
    , 19 (1948);
    Bartonville Bus Line v. Eagle Motor Coach Line, 
    326 Ill. 200
    , 202 (1927);
    - 11 -
    Fountain Water District v. Illinois Commerce Comm’n, 
    291 Ill. App. 3d 696
    , 701
    (1997)). 3 This court has therefore held that
    “before one utility is permitted to take the business of another already in the
    field it is but a matter of fairness and justice that it be shown that the new utility
    is in a position to render better service to the public than the one already in the
    field. *** The power of the State to regulate a utility carries with it the power to
    protect such utility against indiscriminate competition, and such power should
    be exercised to that end.” (Internal quotation marks omitted.) Chicago & West
    Towns Rys. v. Illinois Commerce Comm’n, 
    383 Ill. 20
    , 26 (1943).
    ¶ 32       Because the Public Utilities Act was created to regulate public utilities, a
    threshold inquiry when determining the reach of the Act is whether a particular
    entity actually qualifies as a public utility. Entities that are not public utilities are
    generally not subject to regulation under the Public Utilities Act or to supervision
    and control by the Commission. Fountain Water District, 291 Ill. App. 3d at
    701-02; but see Zahn v. North American Power & Gas, LLC, 
    2016 IL 120526
    , ¶ 21
    (noting that alternative regional energy suppliers, while not public utilities, remain
    subject to certain requirements under the Commission’s authority). At the same
    time, however, such entities are foreclosed from the market protections and other
    advantages that the Public Utilities Act confers.
    ¶ 33        In this case, the Commission did not reach out to compel Rock Island to submit
    to its regulatory authority. Rather, Rock Island has undertaken to place itself under
    the Commission’s authority voluntarily. Why it has done so is contested.
    Opponents of the project assert that the company is motivated by a desire to obtain
    the eminent domain power available to public utilities under the Public Utilities
    Act. See 220 ILCS 5/8-509 (West 2012). Rock Island disputes this, arguing that it is
    not currently seeking eminent domain authority and may never do so if it succeeds
    in obtaining the easements it will need for the project through negotiated
    agreements with affected landowners.
    3
    As discussed in our recent decision in Zahn, 
    2016 IL 120526
    , ¶ 20, Illinois has taken
    steps to partially deregulate its electricity market through enactment of the Electric Service
    Customer Choice and Rate Relief Law of 1997 (220 ILCS 5/16-101 et seq. (West 2012)).
    While appellants make references to the goals of that statute, they have failed to explain
    how its substantive provisions apply to the regulatory process involved in this appeal.
    - 12 -
    ¶ 34       Rock Island’s explanation for why it has proceeded as it has is twofold. First, it
    contends that it simply wants to comply with the law. It believes that if it ultimately
    moves forward with the project, its transmission system will, in fact, qualify as a
    public utility facility and that the service it provides will constitute a public utility
    service within the meaning of the Public Utilities Act and that it therefore needs to
    obtain a certificate of public convenience and necessity pursuant to section 8-406
    of the Act (220 ILCS 5/8-406 (West 2012)) before moving forward. While it may
    seem counterintuitive for a corporation to voluntarily submit to the state’s
    regulatory authority, especially where, as here, it disavows any intention to exercise
    the primary benefit of doing so—obtaining eminent domain authority—there is one
    advantage to obtaining the proper certifications in advance. If the corporation were
    to proceed without first obtaining regulatory approval and was subsequently found
    to be a public utility within the meaning of the Public Utilities Act and operating
    without the requisite legal authorization, the Illinois Commerce Commission could
    bring an action in circuit court to enjoin the company’s violation or threatened
    violation of the law, and the project could be halted. See 220 ILCS 5/4-202 (West
    2012).
    ¶ 35       The company’s second justification for seeking to place itself within the
    provisions of the Public Utilities Act and obtaining a certificate of public
    convenience and necessity from the Commission is similarly pragmatic. If it is
    under state regulatory authority, it will avoid the need to obtain local approval from
    each governmental unit through which the project will pass. See Commonwealth
    Edison Co. v. City of Warrenville, 
    288 Ill. App. 3d 373
    , 380 (1997) (“Public
    Utilities Act preempts enforcement of ordinances adopted by home rule units and
    non-home-rule units that regulate or effectively regulate public utilities, at least
    where *** the subject matter involves Commission-approved construction projects
    that are intended to facilitate the transmission of electric service”).
    ¶ 36       While the parties dispute what is driving Rock Island’s strategy, resolution of
    the question is unimportant. Whatever Rock Island’s motives for seeking a
    certificate of public necessity and convenience, the central question remains: Does
    it even qualify as a public utility under Illinois law so as to be eligible for such a
    certificate under section 8-406 of the Public Utilities Act (220 ILCS 5/8-406 (West
    2012))?
    - 13 -
    ¶ 37       Under the Act, “public utility” is defined to mean and include, except where
    otherwise expressly provided,
    “every corporation, company, limited liability company, association, joint
    stock company or association, firm, partnership or individual, their lessees,
    trustees, or receivers appointed by any court whatsoever that owns, controls,
    operates or manages, within this State, directly or indirectly, for public use, any
    plant, equipment or property used or to be used for or in connection with, or
    owns or controls any franchise, license, permit or right to engage in:
    (1) the production, storage, transmission, sale, delivery or furnishing of
    heat, cold, power, electricity, water, or light, except when used solely for
    communications purposes[.]” 220 ILCS 5/3-105(a) (West 2012).
    ¶ 38       The mere fact that a company sells heat, cold, water, electricity or any of the
    various other things ordinarily sold by public utilities does not, in itself, make the
    enterprise a public utility. Mississippi River Fuel Corp. v. Illinois Commerce
    Comm’n, 
    1 Ill. 2d 509
    , 516 (1953); Peoples Energy Corp. v. Illinois Commerce
    Comm’n, 
    142 Ill. App. 3d 917
    , 930 (1986). A company could, for example, build
    power generation and transmission systems to service a select group of industrial
    customers without falling subject to the Public Utilities Act or the regulatory
    oversight of the Commission. See, e.g., Highland Dairy Farms Co. v. Helvetia Milk
    Condensing Co., 
    308 Ill. 294
     (1923) (private companies that had constructed water
    delivery system for their own use and use by limited number of other persons and
    concerns not subject to the Public Utilities Act).
    ¶ 39       In order to qualify as a public utility, the company must meet additional
    requirements. First, pursuant to the express language of section 3-105 of the Act
    (220 ILCS 5/3-105 (West 2012)), the company must also own, control, operate or
    manage, within this State, directly or indirectly, a plant, equipment, or property
    used or to be used for or in connection with (or must own or control any franchise,
    license, permit, or right to engage in) the production, transmission, sale, etc. of one
    of the specified commodities or services. Second, it must own, control, operate, or
    manage the plant, equipment, property, franchise, etc. “for public use.” 
    Id.
    ¶ 40      Rock Island fails to meet the first of these requirements. When referring to the
    ownership, control, management, and operation of a plant, equipment, property,
    - 14 -
    franchise, etc., the statute is phrased in the present tense. As our discussion has
    indicated, however, Rock Island does not presently own, control, manage, or
    operate any plant, equipment, property franchise, etc., in Illinois or elsewhere to be
    used for or in connection with the production, transmission, or sale of electricity or
    any of the other commodities or services covered by the Public Utilities Act. It
    merely holds an option to acquire a parcel of real property. That is insufficient.
    Even though the parcel is the planned location for part of the yet-to-be-built
    transmission system, having an option to buy something is not the same as owning
    or even controlling it. Under Illinois law, an option agreement is simply a contract
    by which the owner of property agrees with another person that he or she shall have
    the right to buy the property at a fixed price within a time certain. In re Estate of
    Frayser, 
    401 Ill. 364
    , 373-74 (1948). It does not involve the transfer or property or
    an interest therein. Terraces of Sunset Park, LLC v. Chamberlin, 
    399 Ill. App. 3d 1090
    , 1096 (2010).
    ¶ 41        Agreeing with its ALJ, the Commission sought to avoid this problem by
    interpreting the statute’s ownership requirement as encompassing situations in
    which a company did not currently own or operate utility-related assets but
    intended to acquire such assets after regulatory approval was granted in the future.
    Under a prior version of the Public Utilities Act, such an interpretation would have
    been valid. Section 10 of the Public Utilities Act of 1913 (Ill. Rev. Stat. 1965, ch.
    111⅔, ¶ 10.3), the predecessor to section 3-105 of the current law, defined a public
    utility to mean and include every corporation, company, association, joint stock
    company or association, firm, partnership, or individual that “now or hereafter ***
    may own, control, operate or manage” specified plants, equipment, or property.
    (Emphasis added.) Ill. Rev. Stat. 1965, ch. 111⅔, ¶ 10.3; State Public Utilities
    Comm’n v. Noble Mutual Telephone Co., 
    268 Ill. 411
    , 414 (1915); Jacksonville Bus
    Line Co. v. Watson, 
    344 Ill. App. 175
    , 181 (1951). That language plainly and
    unambiguously encompassed situations where, as in this case, a company did not
    presently own any utility-related equipment or property but planned on acquiring
    some in the future. 4
    4
    Wabash, Chester & Western Ry. Co. v. Commerce Comm’n, 
    309 Ill. 412
     (1923), a
    case cited by appellants in support of their position, was decided under this version of the
    law. Because the earlier version of the law did not require present ownership, that issue was
    - 15 -
    ¶ 42        When the General Assembly repealed the prior Public Utilities Act and
    replaced it with the present statute, the “now or hereafter *** may” language was
    removed. With it went all reference to ownership in the future. As noted, the current
    law speaks only of ownership in the present tense. It is axiomatic that when the
    legislature amends an unambiguous statute by deleting certain language, it is
    presumed that the legislature intended to change the law in that respect. Chicago
    Teachers Union, Local No. 1 v. Board of Education of the City of Chicago, 
    2012 IL 112566
    , ¶ 21. We have not found, and appellees have not cited, anything that would
    bring that presumption into question here. Accordingly, we must read the current
    law as evincing an intention by the legislature to limit the definition of “public
    utility” to situations where the subject entity meets the ownership test at the present
    time. To hold otherwise would require not only that we read into the statute
    language that is not there but that we rewrite the statute to reinsert language the
    General Assembly affirmatively removed. That is something we may not do. Zahn,
    
    2016 IL 120526
    , ¶ 15. Nor, of course, may the Commission. An administrative
    body is limited by the powers granted to it by the enabling statute. It is without
    authority to replace a statutory definition the legislature has deleted. See Julie Q. v.
    Department of Children & Family Services, 
    2013 IL 113783
    , ¶ 35.
    ¶ 43        Seeking to recast the question of legislative intent, appellants assert that, in the
    past, the Commission has actually granted certificates of public convenience and
    necessity to applicants who were not yet public utilities and did not yet own or
    control assets in Illinois. Several Commission orders are cited, including decisions
    from 1970, 2003, and 2007. Appellants contend that because the legislature has not
    amended section 8-406 of the Public Utilities Act (220 ILCS 5/8-406 (West 2012))
    in light of these orders, we should deem it to have acquiesced in the Commission’s
    interpretation of the law. This argument is without merit.
    ¶ 44       While appellees point out some significant factual distinctions between the
    administrative proceedings cited by appellants and the situation before us here,
    appellants’ argument suffers from an even more fundamental problem. Cases
    where we have referenced the “acquiescence rule” in the context of administrative
    action have involved situations involving consistently followed, long-standing
    neither raised nor reached in the Wabash case. Appellants’ reliance on that case is therefore
    misplaced.
    - 16 -
    administrative rules, regulations, or interpretations of ambiguous statutes. See, e.g.,
    People ex rel. Spiegel v. Lyons, 
    1 Ill. 2d 409
     (1953); People ex rel. Watson v. House
    of Vision, 
    59 Ill. 2d 508
     (1974); People ex rel. Birkett v. City of Chicago, 
    202 Ill. 2d 36
     (2002). These factors are not present here. With respect to the requirement of
    present ownership, control, operation, or management, the provisions of the Public
    Utilities Act relevant to the issuance of certificates of public convenience and
    necessity are not ambiguous, and the smattering of administrative decisions cited
    by appellants, to the extent that they bear any factual similarity to this case, can
    scarcely be said to represent a long-standing, consistent, and uniform construction
    of the law. We note, moreover, that acquiescence requires knowledge. We may
    presume that the legislature is aware of decisions we issue (Kozak v. Retirement
    Board of Firemen’s Annuity & Benefit Fund, 
    95 Ill. 2d 211
    , 218 (1983)), but there
    is no basis for assuming that the legislature had any knowledge of the particular
    administrative rulings invoked by appellants, none of which were the subject of
    published court opinions.
    ¶ 45       Appellants further argue that the appellate court failed to give sufficient
    deference to the Commission’s factual findings and improperly usurped its
    statutory authority to determine whether Rock Island qualified as a public utility.
    This argument must also fail. The facts relevant to the question on which this
    appeal turns—Rock Island’s lack of ownership, control, management, etc. of
    property as specified in section 3-105 of the Public Utilities Act at the time it sought
    certification from the Commission—are undisputed. The real disagreement
    concerns the construction of law. Where, as here, the historical facts are admitted or
    established but there is a dispute as to whether the governing legal provisions were
    interpreted correctly by the administrative body, the case presents a purely legal
    question for which judicial review is de novo. Goodman v. Ward, 
    241 Ill. 2d 398
    ,
    406 (2011).
    ¶ 46       Of course, even when review is de novo, an agency’s construction of the law
    may be afforded substantial weight and deference if the meaning of the terms used
    in a statute is doubtful or uncertain. Courts accord such deference in recognition of
    the fact that agencies make informed judgments on the issues based upon their
    experience and expertise and serve as an informed source for ascertaining the
    legislature’s intent. Provena Covenant Medical Center, 
    236 Ill. 2d at
    387 n.9.
    When statutory language is unambiguous, however, the agency’s role as an
    - 17 -
    interpreter of doubtful law does not come into play (see Dusthimer v. Board of
    Trustees of the University of Illinois, 
    368 Ill. App. 3d 159
    , 165 (2006)), and an
    official’s interpretation of a statute cannot alter the law’s plain language. Apple
    Canyon Lake Property Owners’ Ass’n v. Illinois Commerce Comm’n, 
    2013 IL App (3d) 100832
    , ¶ 21.
    ¶ 47       As we have already indicated, this is such a case. The language of section 3-105
    (220 ILCS 5/3-105 (West 2012)) stands in clear contrast to its predecessor in
    plainly and unambiguously requiring present ownership, management, or control
    of defined utility property or equipment in order to qualify as a public utility.
    Because only public utilities are eligible to receive certificates of public
    convenience and necessity under section 8-406 of the Public Utilities Act (220
    ILCS 5/8-406 (West 2012)) and because Rock Island cannot meet the ownership
    test necessary to qualify as a public utility, the Commission’s order granting Rock
    Island a certificate of public convenience and necessity fails as a matter of law and
    cannot be sustained.
    ¶ 48        Echoing the “Catch-22” concerns expressed by the Commission’s
    administrative law judge, appellants protest that interpreting section 3-105 of the
    Act (220 ILCS 5/3-105 (West 2012)) to require present ownership of utility
    infrastructure assets will effectively bar new entrants from qualifying as public
    utilities and obtaining certificates of public convenience and necessity under
    section 8-406 of the Act (220 ILCS 5/8-406 (West 2012)) so they may transact
    business as such. This concern is not well founded. Nothing in the Public Utilities
    Act prohibits new entrants such as Rock Island from commencing development of
    transmission lines immediately as a purely private project. So long as they do not
    transact business as a public utility, they will not be subject to the Public Utilities
    Act and will not require Commission authority to proceed. Once their projects are
    further underway and they have obtained the ownership, management, or control of
    utility-related property or equipment required to qualify as public utilities, they
    may then seek certification to operate as public utilities if they wish to conduct their
    business in a way that would make them subject to the Public Utilities Act’s
    regulatory framework.
    ¶ 49       Requiring new entrants to proceed in this way may make the initial phase of
    their operations more difficult and cumbersome. For example, they will not have
    - 18 -
    the benefit of eminent domain to obtain the property on which their facilities will be
    located. In Rock Island’s case, however, that particular problem should be no
    obstacle. As we have noted, the company has not sought, is not seeking, and
    represents that it may never ask for eminent domain power.
    ¶ 50       In any case, the fact that there may be barriers and significant costs to new
    companies wishing to enter the state to establish a new public utility is in no way
    incompatible with the theory and operation of the Public Utilities Act. The Act,
    after all, is based on a model of limited monopoly and reflects a policy of
    preventing rather than promoting competition with existing utilities. Gulf
    Transport Co., 
    402 Ill. at 19-20
    . One may disagree with that model, but the wisdom
    of this state’s regulatory system is a matter for the legislature, not our court. Of all
    the principles of statutory construction, few are more basic than that a court may
    not rewrite a statute to make it consistent with the court’s own idea of orderliness
    and public policy. Board of Education of Roxana Community School District No. 1
    v. Pollution Control Board, 
    2013 IL 115473
    , ¶ 25.
    ¶ 51       Because Rock Island cannot meet the ownership requirement for qualification
    as a public utility, there is no need to reach the additional question of whether it also
    fails the “public use” requirement, as the appellate court concluded. Should the
    company elect to move forward with the project and reapply for a certificate of
    public necessity and convenience as a public utility once it moves beyond planning
    and actually owns, controls, operates, or manages transmission assets, the question
    of public use can be revisited under the facts and circumstances then present. Any
    ruling on the question now would be purely advisory. That being so, there is
    likewise no need to address appellants’ argument that the appellate court’s
    construction of the public use requirement imposes an impermissible burden on
    interstate commerce in violation of the commerce clause of the United States
    Constitution (U.S. Const., art. I, § 8, cl. 3).
    ¶ 52                                      CONCLUSION
    ¶ 53       For the foregoing reasons, we agree with the appellate court that the
    Commission erred in finding that Rock Island is a public utility. The company does
    not qualify as a public utility under Illinois law and was ineligible for a certificate
    of public convenience and necessity from the Commission. The appellate court was
    - 19 -
    therefore correct when it reversed the Commission’s order granting a certificate of
    public convenience and necessity to the company, and it properly remanded the
    cause to the Commission with directions to enter an order consistent with its
    opinion. Accordingly, its judgment is affirmed.
    ¶ 54      Affirmed.
    - 20 -
    

Document Info

Docket Number: 121302121304121305121308

Citation Numbers: 2017 IL 121302, 90 N.E.3d 448, 2017 Ill. LEXIS 671

Judges: Karmeier

Filed Date: 9/21/2017

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (24)

The Board of Education of Roxana Community Unit School ... , 2013 IL 115473 ( 2013 )

Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n , 136 S. Ct. 760 ( 2016 )

Springfield Gas & Electric Co. v. City of Springfield , 42 S. Ct. 24 ( 1921 )

Provena Covenant Medical Center v. Department of Revenue , 236 Ill. 2d 368 ( 2010 )

United Cities Gas Co. v. Illinois Commerce Commission , 163 Ill. 2d 1 ( 1994 )

New York v. Federal Energy Regulatory Commission , 122 S. Ct. 1012 ( 2002 )

Julie Q. v. Department of Children & and Family Services , 2013 IL 113783 ( 2013 )

Local 777, DUOC, Seafarers International Union of North ... , 45 Ill. 2d 527 ( 1970 )

People Ex Rel. Spiegel v. Lyons , 1 Ill. 2d 409 ( 1953 )

Kozak v. RETIREMENT BOARD OF FIREMEN'S ANNUITY AND BENEFIT ... , 95 Ill. 2d 211 ( 1983 )

Goodman v. Ward , 241 Ill. 2d 398 ( 2011 )

In Re Estate of Frayser , 401 Ill. 364 ( 1948 )

J&J Ventures Gaming, LLC v. Wild, Inc , 2016 IL 119870 ( 2017 )

Zahn v. North American Power & Gas, LLC , 2016 IL 120526 ( 2017 )

People Ex Rel. Madigan v. Illinois Commerce Commission , 231 Ill. 2d 370 ( 2008 )

Mississippi River Fuel Corp. v. Illinois Commerce Commission , 1 Ill. 2d 509 ( 1953 )

Chicago Teachers Union v. Board of Education of the City of ... , 2012 IL 112566 ( 2012 )

Commerce Commission v. Chicago Railways Co. , 362 Ill. 559 ( 1936 )

Gulf Transport Co. v. Illinois Commerce Commission , 402 Ill. 11 ( 1948 )

The People v. City of Chicago , 349 Ill. 304 ( 1932 )

View All Authorities »