Norman A. Koglin Associates v. Valenz Oro, Inc. ( 1997 )


Menu:
  • NOTICE: Under Supreme Court Rule 367 a party has 21 days after the

    filing of the opinion to request a rehearing. Also, opinions are

    subject to modification, correction or withdrawal at anytime prior

    to issuance of the mandate by the Clerk of the Court. Therefore,

    because the following slip opinion is being made available prior to

    the Court's final action in this matter, it cannot be considered

    the final decision of the Court. The official copy of the following

    opinion will be published by the Supreme Court's Reporter of

    Decisions in the Official Reports advance sheets following final

    action by the Court.

                                       

                 Docket No. 80695--Agenda 30--September 1996.

       NORMAN A. KOGLIN ASSOCIATES v. VALENZ ORO, INC., et al. (La Salle

          National Bank, as Trustee under Trust No.  113495, et al.,

                 Appellants; H.B. Barnard Company, Appellee).

                         Opinion filed March 20, 1997.

      

        JUSTICE NICKELS delivered the opinion of the court:

        In this appeal, we decide whether a mechanic's lien claimant

    may enforce its lien where it asserted its lien in an answer rather

    than a counterclaim.

        Plaintiff, Norman A. Koglin Associates (Koglin), is an

    architectural firm. One of the defendants, Valenz Oro, Inc.

    (Valenz), was a tenant in a downtown Chicago building. Koglin

    alleged that it entered into a contract with Valenz to perform

    architectural and interior design services in connection with the

    construction and improvement of Valenz's jewelry store. Koglin

    further alleged that it performed the services but was not fully

    paid. Koglin filed a complaint in the circuit court of Cook County

    to foreclose a mechanic's lien under the Mechanics Lien Act (the

    Act) (770 ILCS 60/0.01 et seq. (West 1992)). Koglin named four

    defendants in the foreclosure action: Valenz, the tenant; La Salle

    National Bank (La Salle), the owner of the building where the

    jewelry store was located; JMB/Urban 900 Development Partners

    (JMB), the manager of the building; and H.B. Barnard Company

    (Barnard), the general contractor. Koglin alleged that Barnard also

    had a mechanic's lien in connection with work performed on the

    jewelry store. Barnard filed a pleading captioned "Answer to

    Complaint to Foreclose Mechanic's Lien," in which it asserted its

    lien.

        While the suit was pending and before trial, Koglin negotiated

    a settlement with two of the defendants, La Salle and JMB. Barnard

    was not involved in the settlement. After settlement, Koglin sought

    voluntary dismissal of the entire action. Barnard objected, arguing

    that its rights under its mechanic's lien had not been adjudicated.

    The circuit court dismissed the entire action with prejudice. The

    appellate court vacated the dismissal order and remanded, thereby

    allowing Barnard to enforce its mechanic's lien. 277 Ill. App. 3d

    142. Defendants La Salle and JMB filed a petition for leave to

    appeal to this court (155 Ill. 2d R. 315), which was granted. We

    affirm the appellate court.

      

                                   BACKGROUND

        Koglin's complaint was filed on June 16, 1992. It stated that

    Koglin provided architectural services in connection with Valenz's

    jewelry store, located in Valenz's space at 900 North Michigan

    Avenue. In the complaint, Koglin alleged that its work was

    authorized or knowingly permitted by defendants La Salle and JMB.

    Koglin further alleged that defendant Barnard also performed work

    on the jewelry store. Koglin alleged, however, that its lien rights

    were superior to Barnard's.

        On July 20, 1992, Barnard filed a pleading designated as an

    answer. In the answer, Barnard alleged that it had also entered

    into a contract with Valenz involving work on the jewelry store.

    Barnard admitted the basic factual allegations of the complaint but

    denied that its lien rights were subordinate and inferior to

    Koglin's lien rights. Barnard alleged that it had a lien against

    the premises totalling $25,725.84 plus interest. With respect to

    its lien, Barnard specifically stated that "it last performed

    services on the premises under its contract on or after November

    23, 1991, and that it perfected its mechanics lien on the premises

    by recording a copy of notice of such lien with the Recorder of

    Deeds of Cook County, Illinois, on March 20, 1992, in accordance

    with the Mechanics' Lien Law."

        A copy of the recorded claim for mechanic's lien was attached

    as an exhibit to the answer. The claim for lien provided

    information about Barnard's work and identified La Salle and JMB,

    among others, as having an interest in the property. Barnard's

    answer also contained a prayer for relief. In the prayer for

    relief, Barnard asked the court: (1) to determine the amount of its

    mechanic's lien as $25,725.84 plus interest; (2) to determine that

    Barnard had a "first, prior and superior lien" against the premises

    under the Act; (3) to foreclose its mechanic's lien and to order

    the premises sold to satisfy any judgment; and (4) to award any

    other relief the court would deem proper.

        On September 10, 1993, La Salle and JMB filed a combined

    answer to the Koglin complaint. In their answer, they admitted that

    Barnard had provided certain labor and materials in connection with

    the construction and improvement of the jewelry store. They denied

    that they knew the terms of any contract between Valenz and

    Barnard, and further, they denied that they authorized or permitted

    such a contract. La Salle and JMB did not object to the form of

    Barnard's answer or make a motion to strike the affirmative relief

    requested in Barnard's answer.

        On December 21, 1993, the circuit court held a pretrial

    conference. Koglin moved to voluntarily dismiss its action because

    it had resolved its claims through a settlement with La Salle and

    JMB. Barnard had not been informed of Koglin's intent to seek a

    voluntary dismissal at the pretrial conference. Despite Barnard's

    objection, the circuit court dismissed the entire action with

    prejudice.

        On January 11, 1994, Barnard filed a motion titled "Motion by

    H. B. Barnard Company to Modify or Vacate the Order of December 21,

    1993, to Permit Filing of Amended Complaint and to Realign

    Parties." La Salle and JMB argued that, by this time, more than two

    years had passed since Barnard completed its work on the jewelry

    store. The Act provides that a claimant should enforce its lien

    within two years of completion of the work. 770 ILCS 60/9 (West

    1992). The circuit court denied Barnard's motion. The effect of

    this ruling was to preclude Barnard from enforcing its mechanic's

    lien against La Salle and JMB. Barnard appealed.

        The appellate court vacated the dismissal order and remanded

    the cause to allow Barnard to enforce its mechanic's lien. The

    appellate court relied on four alternative reasons. The court held

    that: (1) Barnard's answer complied with the Act and that a

    counterclaim was not required; (2) even if a counterclaim was

    required, the answer should have been treated as a counterclaim

    because it contained all the elements needed to state a claim; (3)

    if a counterclaim was required, Barnard should have been allowed to

    amend its pleading to assert a counterclaim; and (4) Koglin should

    have provided notice to Barnard before Koglin sought to voluntarily

    dismiss the entire action at the pretrial conference.

        On appeal, La Salle and JMB contest each of these four

    reasons. We note that defendant Valenz did not file an appearance

    or responsive pleading in the circuit court. Neither Valenz nor

    Koglin are involved in this appeal. We begin our analysis with a

    brief discussion of the Act.

      

                                    ANALYSIS

                      I. Overview of the Mechanics Lien Act

        Mechanic's liens were not recognized at common law and exist

    only by operation of the Act (770 ILCS 60/0.01 et seq. (West

    1992)). In general, the Act provides a lien to an individual who

    has provided labor, material, or services in connection with the

    improvement of real estate, pursuant to contract. See 770 ILCS 60/1

    (West 1992). The Act prescribes the elements required to state a

    claim. Section 11 provides:

                  "The complaint shall contain a brief statement of

             the contract or contracts on which it is founded, the

             date, when made, and when completed, if not completed,

             why, and it shall also set forth the amount due and

             unpaid, a description of the premises which are subject

             to the lien, and such other facts as may be necessary to

             a full understanding of the rights of the parties." 770

             ILCS 60/11 (West 1992).

        The defendants in a mechanic's lien proceeding include all

    persons having an interest in the premises. 770 ILCS 60/11 (West

    1992). These defendants may include individuals having an ownership

    interest in the property, such as tenants and landlords. When a

    tenant has contracted for work that is the subject of a lien, the

    lien may be enforced against the landlord if the landlord has

    "authorized or knowingly permitted" work to be done on the

    premises. 770 ILCS 60/1 (West 1992); see also Abbott Electrical

    Construction Co. v. Ladin, 144 Ill. App. 3d 974, 978 (1986). Other

    mechanic's lien claimants are also included in the proceeding. The

    Act presumes that all claims and rights of interested parties can

    be adjudicated in one proceeding. 770 ILCS 60/11 (West 1992).

        A contractor's rights under the Act are dependent on its

    taking the necessary steps to perfect a lien. Section 7 provides

    for the recording of a "claim for lien" in the office of the

    recorder of the county in which the property is located. 770 ILCS

    60/7 (West 1992). It also prescribes the contents of this claim for

    lien. 770 ILCS 60/7 (West 1992). A contractor must record its claim

    for lien within four months after completion of the work in order

    to subsequently assert a lien against a "creditor or incumbrancer

    or purchaser." 770 ILCS 60/7 (West 1992). The four-month recording

    requirement is intended to give third parties dealing with the

    property, other than those with an ownership interest, notice of

    the lien. Federal Savings & Loan Insurance Corp. v. American

    National Bank & Trust Co., 115 Ill. App. 3d 426, 429 (1983). If the

    lien has been recorded within the four-month period, the contractor

    can then seek to enforce the lien within two years of completion of

    the work. 770 ILCS 60/9 (West 1992).

        The recording of a claim for lien is less significant where a

    contractor seeks to enforce a lien against a party with an

    ownership interest. As to a party with an ownership interest, the

    contractor may record a claim for lien within two years after

    completion of the contract. 770 ILCS 60/7 (West 1992). Regardless

    of whether a claim for lien has been recorded, the contractor must

    seek to enforce the lien within two years after completion of the

    contract. 770 ILCS 60/9 (West 1992). Thus, with respect to both

    owners and third parties, a contractor must assert its lien within

    two years of completion of the work.

      

    II. Section 9 of the Act

        Section 9 of the Act describes the enforcement of a lien.

    Section 9 provides:

                  "If payment shall not be made to the contractor

             having a lien by virtue of this act of any amount due

             when the same becomes due, then such contractor may bring

             suit to enforce his lien in the circuit court in the

             county where the improvement is located ***. Any two or

             more persons having liens on the same property may join

             in bringing such suit, setting forth their respective

             rights in their complaint; all lien claimants not made

             parties thereto may upon filing a petition to intervene

             become defendants and enforce their liens by counterclaim

             against all the parties to the suit; and the complaint

             shall not thereafter be dismissed as to any lien claimant

             *** without the consent of such lien claimant. The

             plaintiff and all defendants to such complaint may

             contest each other's right without any formal issue of

             record made up between them other than that shown upon

             the original complaint, as well with respect to the

             amount due as to the right to the benefit of the lien

             claimed: Provided, that if by such contest by co-

             defendants any lien claimants be taken by surprise, the

             court may, in its discretion, as to such claim, grant a

             continuance. The court may render judgment against any

             party summoned and failing to appear, as in other cases

             of default. Such suit shall be commenced or counterclaim

             filed within two years after the completion of the

             contract, or completion of the extra or additional work,

             or furnishing of extra or additional material

             thereunder." (Emphasis added.) 770 ILCS 60/9 (West 1992).

    The parties dispute the meaning of section 9. La Salle and JMB

    argue that a mechanic's lien claimant should assert its lien in a

    complaint or counterclaim. Barnard argues that the Act permits the

    assertion of a lien in an answer. On this issue, we agree with

    La Salle and JMB.

        In reaching this conclusion, we note the history of the

    statute. Prior to 1976, the statute provided that defendants could

    "enforce their liens by answer to the complaint or petition in the

    nature of an intervening petition, and the same shall be taken as

    a counterclaim." Ill. Rev. Stat. 1975, ch. 82, par. 9. The statute

    further provided that "[s]uch suit shall be commenced or answer

    filed within two years after the completion of the contract ***."

    Ill. Rev. Stat. 1975, ch. 82, par. 9. Thus, before 1976, a

    defendant could assert its lien by answer. See, e.g., Rochelle

    Bldg. Co. v. Oak Park Trust & Savings Bank, 121 Ill. App. 2d 274,

    277 (1970). In 1976, the statute was amended and the portions of

    the statute allowing enforcement of a lien by answer were deleted.

    The amended language of the statute provides that a defendant may

    enforce a lien by counterclaim. Accordingly, the amended statute

    contemplates that a defendant will assert its lien by counterclaim,

    rather than by answer.

        We further note that section 12 of the Act expressly provides

    that the circuit court should generally use the same pleading

    procedure in a mechanic's lien proceeding as is used in other civil

    actions. Section 12 provides:

                  "The court shall permit amendments to any part of

             the pleadings, and may issue process, make all orders,

             requiring parties to appear, and requiring notice to be

             given, that are or may be authorized in other civil

             actions and shall have the same power and jurisdiction of

             the parties and subject matter, and the rules of practice

             and proceedings in such cases shall be the same as in

             other civil cases, except as is otherwise provided in

             this act." 770 ILCS 60/12 (West 1992).

    The rules of civil procedure ordinarily apply to mechanic's lien

    cases, as in other civil cases.

        Barnard did not follow the proper civil pleading procedure in

    asserting its lien. In civil cases, a counterclaim should be used

    by a defendant to make a claim against another defendant. 735 ILCS

    5/2--608(a) (West 1992). A counterclaim differs from an answer or

    affirmative defense. A counterclaim is used when seeking

    affirmative relief, while an answer or affirmative defense seeks to

    defeat a plaintiff's claim. Section 2--608(b) of the Code of Civil

    Procedure provides that "[t]he counterclaim shall be a part of the

    answer, and shall be designated as a counterclaim." 735 ILCS 5/2--

    608(b) (West 1992). In its pleading, Barnard should have formally

    asserted its lien as a counterclaim.

        In support of its position, Barnard emphasizes certain

    language of the statute to argue that the legislature changed the

    rules of pleadings with respect to mechanic's liens. The statute

    provides that "all lien claimants not made parties thereto [to the

    complaint] may upon filing a petition to intervene become

    defendants and enforce their liens by counterclaim ***." 770 ILCS

    60/9 (West 1992). Barnard argues that the statute only requires

    that intervening claimants file counterclaims. Barnard argues that

    the statute does not require it to file a counterclaim because it

    was an original party to the suit, and therefore, it may assert its

    lien in an answer.

        We disagree. The statute provides that claimants who are not

    involved in the original proceeding may intervene to assert their

    liens. It expressly gives these claimants the right to become

    involved in the proceeding. The statute, as amended, does not alter

    the rules of civil procedure in connection with claimants who are

    already parties to the proceeding.

        Additionally, Barnard notes that section 9 provides that

    "[t]he plaintiff and all defendants to such complaint may contest

    each other's right without any formal issue of record made up

    between them other than that shown upon the original complaint

    ***." 770 ILCS 60/9 (West 1992). Barnard contends that this

    language establishes a simplified pleading procedure. Barnard

    argues that this language eliminates the need for the filing of

    counterclaims entirely.

        We also reject this argument. Although the statute provides

    that the parties "may contest each other's right without any formal

    issue of record," it still contemplates that they will assert their

    claims as in other civil cases. Mechanic's lien litigation often

    involves a number of counterclaims by claimants and by other

    parties claiming an interest in the property. This provision simply

    makes it easier to challenge the liens asserted by others. It does

    not affect how liens should be asserted in the first place.

      

                     III. Liberal Construction of Pleadings

        Even though Barnard failed to formally assert a counterclaim,

    it prevails on other grounds. The appellate court held that, even

    if Barnard should have asserted its lien by counterclaim, Barnard's

    pleading should be liberally construed. The court determined that

    Barnard's assertion of the lien and request for affirmative relief

    should be treated as the functional equivalent of a counterclaim.

    We agree.

        As noted, section 12 of the Act adopts the same general rules

    of procedure that apply in other civil cases. The Code of Civil

    Procedure is to be liberally construed, so that cases are decided

    on the basis of the substantive rights of the litigants. 735 ILCS

    5/1--106 (West 1992); Superior Bank FSB v. Golding, 152 Ill. 2d

    480, 486 (1992). It also states that "[n]o pleading is bad in

    substance which contains such information as reasonably informs the

    opposite party of the nature of the claim or defense which he or

    she is called upon to meet." 735 ILCS 5/2--612(b) (West 1992).

    Section 2--603(c) further provides that "[p]leadings shall be

    liberally construed with a view to doing substantial justice

    between the parties." 735 ILCS 5/2--603(c) (West 1992). "Pleadings

    are not intended to create obstacles of a technical nature to

    prevent reaching the merits of a case," but instead are intended

    "to facilitate the resolution of real and substantial

    controversies." People ex rel. Scott v. College Hills Corp., 91

    Ill. 2d 138, 145 (1982); see also Geary v. Dominick's Finer Foods,

    Inc., 129 Ill. 2d 389, 407-08 (1989).

        Given these principles, the circuit court should have

    liberally construed the affirmative relief requested in the answer.

    Section 2--608(c) of the Code of Civil Procedure provides that a

    counterclaim "shall be pleaded in the same manner and with the same

    particularity as a complaint." 735 ILCS 5/2--608(c) (West 1992).

    Barnard did, in fact, allege the elements needed to state a claim

    under the Act. It alleged that Barnard and Valenz entered into a

    contract on October 15, 1991, that the work was completed on

    November 23, 1991, and that the amount due was $25,725.84 plus

    interest. Barnard further alleged that it recorded its claim for

    mechanic's lien in the recorder's office and attached the claim for

    lien as an exhibit. See 735 ILCS 5/2--606 (West 1992) (written

    instrument attached to pleading "constitutes a part of the pleading

    for all purposes"). The claim for lien contained a legal

    description of the property and asserted a claim "against the

    interest" of La Salle and JMB, among others. In its prayer for

    relief in the answer, Barnard asserted its lien and sought

    foreclosure based on the lien. As the appellate court stated,

    "[t]he only thing missing from the document was the word

    ``counterclaim.' " 277 Ill. App. 3d at 151. Accordingly, Barnard's

    claim should not have been dismissed without its consent. See 770

    ILCS 60/9 (West 1992); 735 ILCS 5/2--1009 (West 1992).

        La Salle and JMB argue that the Act is in derogation of the

    common law and the provisions of the Act are to be strictly

    construed. The strict construction rule, however, applies to the

    provisions of the Act that specify the substantive requirements

    upon which the right to a lien is based. The procedure established

    in the Act for perfecting a lien must be strictly followed in order

    to create the lien. See, e.g., Mutual Services, Inc. v. Ballantrae

    Development Co., 159 Ill. App. 3d 549, 552-53 (1987) (contractor's

    failure to timely record a claim for lien within four months of

    completion of the work made lien unenforceable against third

    parties). In light of section 12, the strict construction rule does

    not generally apply to technical objections to pleadings. See

    United Cork Cos. v. Volland, 365 Ill. 564, 572 (1937) (strict

    construction rule is applied where a "material requirement of the

    statute" is lacking but was not intended "as a pitfall to the

    unwary, in good faith pursuing the path marked by the statute, nor

    as an ambuscade from which an adversary can overwhelm him for an

    immaterial misstep"); Fitzgerald v. Van Buskirk, 96 Ill. App. 2d

    432, 434-40 (1968) (allegations in complaint construed liberally);

    see also Abbott Electrical Construction Co. v. Ladin, 144 Ill. App.

    3d 974, 981 (1986); Armco Steel Corp. v. La Salle National Bank, 31

    Ill. App. 3d 695, 699 (1975).

      

                           IV. Amendment of Pleadings

        Alternatively, the appellate court held that Barnard should be

    allowed to enforce its lien on a separate, but related, ground.

    Section 12 of the Act permits amendments to any part of the

    pleadings, as allowed generally in civil cases. 770 ILCS 60/12

    (West 1992). Even if Barnard's pleading could not be liberally

    construed, the appellate court held that the trial judge should

    have allowed Barnard to amend its answer to formally assert a

    counterclaim. We agree.

        We note that Barnard sought to file an amended pleading more

    than two years after it completed its work. Section 2--616(b) of

    the Code of Civil Procedure, however, provides that an amended

    pleading may relate back to the date of filing of the original

    pleading. Specifically, section 2--616(b) provides:

                  "(b) The cause of action, cross claim or defense set

             up in any amended pleading shall not be barred by lapse

             of time under any statute or contract prescribing or

             limiting the time within which an action may be brought

             or right asserted, if the time prescribed or limited had

             not expired when the original pleading was filed, and if

             it shall appear from the original and amended pleadings

             that the cause of action asserted, or the defense or

             cross claim interposed in the amended pleading grew out

             of the same transaction or occurrence set up in the

             original pleading, *** and for the purpose of preserving

             the cause of action, cross claim or defense set up in the

             amended pleading, and for that purpose only, an amendment

             to any pleading shall be held to relate back to the date

             of the filing of the original pleading so amended." 735

             ILCS 2--616(b) (West 1992).

    In applying section 2--616(b), this court recently stated:

             "The purpose of the relation back provision has been

             construed as the preservation of causes of action ***

             against loss by reason of technical rules of pleading.

             [Citation.] To further this purpose, courts should

             liberally construe the requirements of section 2--616(b)

             in order to allow the resolution of litigation on the

             merits and to avoid elevating questions of form over

             substance. [Citation.] The rationale behind the same

             transaction or occurrence rule is that a defendant will

             not be prejudiced by an amendment so long as ``his

             attention was directed, within the time prescribed or

             limited, to the facts that form the basis of the claim

             asserted against him.' [Citation.]" Boatmen's National

             Bank v. Direct Lines, Inc., 167 Ill. 2d 88, 102 (1995).

    See also Wolf v. Meister-Neiberg, Inc., 143 Ill. 2d 44, 47-48

    (1991) (an amended pleading will relate back where a defendant has

    information about the claim and will not be prejudiced).

    Although both Boatmen's National Bank and Wolf involved amendments

    to a complaint, the same principle applies here.

        We further note that section 2--616, and its predecessors,

    have been applied in mechanic's lien cases to preserve claims. See

    Douglas Lumber Co. v. Chicago Home for Incurables, 380 Ill. 87

    (1942) (amendment to complaint was timely even though made after

    time for bringing suit had expired because amended complaint

    related back to date of filing of original complaint); Charles A.

    Hohmeier Lumber Co. v. Knight, 350 Ill. 248 (1932) (amended

    complaint would relate back to date of filing of original complaint

    where amended complaint introduced no new claim or ground for

    relief); Martinez v. Knochel, 123 Ill. App. 3d 555 (1984)

    (subcontractor was allowed to amend answer after two years from

    completion of work to assert counterclaim where the subcontractor

    asserted a timely claim in its answer); Ceco Corp. v. Bank of

    Hickory Hills, 126 Ill. App. 3d 188, 191 (1984) (strict

    construction rule did not apply to proposed amendment to complaint

    where the plaintiff named the correct party but the wrong trust

    number because "[a]mending the pleadings to name the correct trust

    number would not have prejudiced any substantial right of defendant

    Bank"); cf. C.S. Lewis, Inc. v. Cabot Corp., 85 Ill. App. 3d 708

    (1980) (appearance, which did not set forth any transaction or

    occurrence, was not sufficient to serve as original pleading that

    could be amended after the two-year period expired). Given that the

    answer was timely filed and asserted the elements needed for a

    claim under the Act, Barnard should have been allowed to amend its

    answer to explicitly assert a counterclaim. Essentially, Barnard

    sought to do so by attempting to file an "amended complaint."

    Accordingly, the circuit court erred in failing to apply section 2-

    -616 in the instant case.

        In arguing that the answer cannot be amended, La Salle and JMB

    rely primarily on Well Done Heating & Sheet Metal Co. v. Ralph

    Schwartz & Associates, 112 Ill. App. 3d 438 (1983). In Well Done

    Heating, a contractor was named as a defendant in a foreclosure

    suit. As here, the contractor filed an answer but did not file a

    counterclaim within the statutory two-year period. Later, the

    contractor sought to amend its answer to add a counterclaim.

        Well Done Heating is distinguishable from the instant case. In

    Well Done Heating, the contractor did not, in any manner, assert

    its lien within the requisite two-year period or seek foreclosure.

    The contractor did not seek to enforce its lien at all until six

    years after the work was completed. In fact, the contractor first

    asserted its lien two years after the suit was settled and the

    complaint dismissed with prejudice. Based on these facts, the Well

    Done Heating court properly refused to allow the contractor to

    amend its answer to assert a counterclaim:

                  "While Illinois allows a party to amend its

             pleading, even sometimes to the extent of altering the

             nature of the claim previously made, it is still the law

             that generally an amendment asserting a new cause of

             action is not permitted once the statute of limitations

             has expired [citations], particularly where, as here,

             there had been no attempt of any kind to set forth the

             claim prior to the running of the statute." (Emphasis

             added.) Well Done Heating, 112 Ill. App. 3d at 443-44.

    Here, in contrast, Barnard asserted its lien prior to the running

    of the two-year period and sought foreclosure. Barnard asserted its

    lien in a timely manner although it failed to correctly label its

    lien as a counterclaim.

        In Well Done Heating, 112 Ill. App. 3d at 445, the court also

    stated that the answer could not be amended to assert a claim

    against "new" defendants. Relying on Well Done Heating, La Salle

    and JMB argue that they were not specifically named as defendants

    in Barnard's pleading. Thus, they argue that they are also "new"

    defendants. La Salle and JMB contend that Barnard did not seek to

    assert its lien against them specifically until after the two-year

    period had passed. They argue that a party seeking relief against

    others should name those other parties in the body of its pleading.

    See 735 ILCS 5/2--401(c) (West 1992).

        Given the circumstances of this case, we reject this argument.

    La Salle and JMB were parties to the foreclosure suit brought by

    Koglin. They were not new parties. They were served with copies of

    Barnard's answer and were on notice of Barnard's lien and the

    relief it sought at an early point in the proceedings. They were

    clearly implicated given the nature of the foreclosure proceeding,

    the prayer for relief in Barnard's answer, and the language of

    Barnard's claim for lien. To the extent the analysis in Well Done

    Heating is inconsistent with this analysis, we reject it.

      

      

                                   CONCLUSION

        Barnard asserted its lien in a timely manner although it

    failed to correctly label its claim as a counterclaim. Under the

    facts of this case, the circuit court should have either liberally

    construed the answer or allowed an amendment to the answer. We

    express no opinion on the ultimate outcome of the litigation on

    remand to the circuit court. For the foregoing reasons, the

    judgment of the appellate court is affirmed.

      

                                                                     Affirmed.