TRI-G, Inc. v. Burke, Bosselman & Weaver ( 2006 )


Menu:
  •                 Docket Nos. 99584, 99595 cons.
    IN THE
    SUPREME COURT
    OF
    THE STATE OF ILLINOIS
    TRI-G, INC., et al., Appellees, v. BURKE, BOSSELMAN &
    WEAVER et al., Appellants.
    Opinion filed June 22, 2006.
    JUSTICE KARMEIER delivered the judgment of the court,
    with opinion.
    Chief Justice Thomas and Justices Kilbride and Garman
    concurred in the judgment and opinion.
    Justice Freeman concurred in part and dissented in part,
    with opinion, joined by Justices McMorrow and Fitzgerald.
    OPINION
    Tri-G, Inc. (Tri-G), brought a legal malpractice action in the
    circuit court of McHenry County against the law firm of Burke,
    Bosselman & Weaver (Burke) to recover damages it sustained
    as a result of Burke=s failure to prosecute a complaint Tri-G had
    previously filed against Elgin Federal Bank (Elgin Federal).
    Following a trial on the merits, a jury found that Burke had
    been negligent in handling Tri-G=s case against Elgin Federal
    and that but for that negligence, Tri-G would have recovered
    $1,168,775 in compensatory damages and an equal sum in
    punitive damages from Elgin Federal. Accordingly, the jury
    returned a verdict in favor of Tri-G and against Burke for
    $2,337,550.
    After the circuit court entered judgment on the jury=s
    verdict, Burke appealed. Tri-G cross-appealed. The appellate
    court affirmed the judgment in part, reversed in part, and
    remanded the cause to the trial court for further proceedings.
    
    353 Ill. App. 3d 197
    . In so ruling, the appellate court expressly
    rejected Burke=s arguments that the award of punitive to Tri-G
    was either improper as a matter of law or excessive in light of
    the evidence adduced at trial. It held that Illinois law permits a
    legal malpractice plaintiff to receive an award of lost punitive
    damages from a defendant attorney and concluded that the
    punitive damages award made in this case was justified by the
    
    evidence. 353 Ill. App. 3d at 232
    .
    Burke and Tri-G each filed petitions for leave to appeal.
    177 Ill. 2d R. 315(a). We allowed their respective petitions and
    consolidated the appeals for review. The primary issue before
    us is whether the appellate erred in upholding the award of lost
    punitive damages to Tri-G. For the reasons that follow, we hold
    that it did. The judgment of the appellate court is therefore
    affirmed in part and reversed in part.
    The basic principles governing legal malpractice claims are
    well established. To prevail on a legal malpractice claim, the
    plaintiff client must plead and prove that the defendant
    attorneys owed the client a duty of due care arising from the
    attorney-client relationship, that the defendants breached that
    duty, and that as a proximate result, the client suffered injury.
    Northern Illinois Emergency Physicians v. Landau, Omahana &
    Kopka, Ltd., 
    216 Ill. 2d 294
    , 306 (2005).
    The injury in a legal malpractice action is not a personal
    injury, nor is it the attorney=s negligent act itself. Rather, it is a
    pecuniary injury to an intangible property interest caused by
    the lawyer=s negligent act or omission. The fact that the
    attorney may have breached his duty of care is not, in itself,
    sufficient to sustain the client=s cause of action. Even if
    negligence on the part of the attorney is established, no action
    will lie against the attorney unless that negligence proximately
    caused damage to the client. The existence of actual damages
    is therefore essential to a viable cause of action for legal
    malpractice. Northern Illinois Emergency Physicians v. Landau,
    Omahana & Kopka, 
    Ltd., 216 Ill. 2d at 306-07
    .
    The theory underlying a cause of action for legal
    malpractice is that the plaintiff client would have been
    compensated for an injury caused by a third party, absent
    negligence on the part of the client=s attorney. Where the
    alleged legal malpractice involves litigation, no actionable claim
    exists unless the attorney=s negligence resulted in the loss of
    an underlying cause of action. If the underlying action never
    reached trial because of the attorney=s negligence, the plaintiff
    is required to prove that but for the attorney=s negligence, the
    plaintiff would have been successful in that underlying action. A
    legal malpractice plaintiff must therefore litigate a Acase within
    a case.@ See Cedeno v. Gumbiner, 
    347 Ill. App. 3d 169
    , 174
    (2004).
    The Acase within a case@ on which Tri-G=s malpractice
    claim is predicated was Tri-G=s cause of action against Elgin
    Federal. That cause of action arose from certain construction
    loans Tri-G received from the bank to build residential homes
    in a development known as Huntington Point. Tri-G=s
    complaint, filed in 1981, alleged breach of contract, common
    law fraud, and violation of the Consumer Fraud and Deceptive
    Business Practices Act (Consumer Fraud Act) (Ill. Rev. Stat.
    1983, ch. 1212, par. 261 et seq. (now 815 ILCS 505/1 et seq.
    (West 2002))).
    Trial of the case was postponed for several years, during
    which time Tri-G was represented by a succession of law firms.
    Eventually, a May 11, 1987, trial date was set by the court.
    Approximately three months before the trial was scheduled to
    begin, Tri-G retained Burke to handle the case. The attorney
    from Burke assigned to represent Tri-G did not file an
    appearance, however, until May 4, 1987. When the case was
    called for trial as scheduled the following week, the attorney
    answered Anot ready.@
    Because the attorney was not prepared to proceed, the
    trial court dismissed Tri-G=s case with prejudice. Tri-G, still
    represented by Burke, appealed the dismissal. On November
    13, 1987, the appellate court dismissed the appeal sua sponte
    -3-
    on the grounds that Tri-G had failed to comply with a previous
    order of that court.
    Tri-G subsequently replaced Burke with new legal counsel,
    who filed a second complaint against Elgin Federal. The new
    complaint alleged the existence of oral construction loan
    contracts between the parties, numerous breaches by Elgin
    Federal of those contracts, and fraud. On Elgin Federal=s
    motion, the circuit court dismissed the complaint based on res
    judicata. The court also imposed sanctions against Tri-G and
    its attorneys. The appellate court affirmed. Tri-G, Inc. v. Elgin
    Federal Savings & Loan Ass=n, 
    182 Ill. App. 3d 357
    (1989).
    With the failure of its substantive claims against Elgin
    Federal, Tri-G looked to Burke for recourse. In 1989 it filed a
    legal malpractice against the law firm. It voluntarily dismissed
    that action in 1994 and refiled it in 1995. Burke then moved to
    dismiss the complaint. Although Burke=s motion was allowed by
    the circuit court, the appellate court reversed and remanded.
    Tri-G, Inc. v. Burke, Bosselman & Weaver, No. 2B96B0980
    (1997) (unpublished order under Supreme Court Rule 23).
    Tri-G=s original and amended complaints against Burke
    each consisted of a single count claiming negligence. In its
    original complaint, Tri-G alleged that Burke was negligent for
    (1) failing to file an appearance until May 4, 1987; (2) failing to
    advise Tri-G=s witnesses and discuss their testimony in
    advance of depositions; (3) failing to attend certain depositions;
    (4) failing to properly prepare the case for trial; and (5) failing to
    seek a voluntary nonsuit on the date of trial.
    The 1981 complaint against Elgin Federal was attached as
    an exhibit to the malpractice complaint. The 1981 complaint
    contained 10 counts, claiming breach of contract, common law
    fraud, and violations of the Consumer Fraud Act (Ill. Rev. Stat.
    1981, ch. 1212, par. 261 et seq. (now 815 ILCS 505/1 et seq.
    (West 2002))). It alleged that in 1976, Tri-G was the general
    contractor for a residential real estate development in McHenry
    County known as the Huntington Point subdivision. First
    National Bank of Woodstock (First National) owned Huntington
    Point as the trustee of a land trust with Tri-G as beneficiary. In
    1978, Elgin Federal made construction loans to Tri-G to build
    residential homes on vacant lots in Huntington Point,
    -4-
    specifically enumerating 13 lots. Tri-G entered into a contract
    with Chain of Lakes Group (CLG), in which CLG agreed to
    complete construction on eight of those lots, specifically 7, 24,
    25, 30, 32, 35, 36, and 37.
    Counts I through VII of Tri-G=s complaint asserted claims
    for breach of contract regarding lots 7, 24, 25, 30, 32, 36, and
    37, respectively. Tri-G alleged that Elgin Federal breached its
    construction loan agreements by making payouts to CLG from
    the construction loans without the written authorization of Tri-G
    and allowing CLG to submit new contractor=s affidavits that
    Elgin Federal used as a basis for additional payouts in excess
    of the amounts stated in the original contractor=s affidavits
    submitted by Tri-G.
    Concurrent with the construction loans, Elgin Federal
    made a land loan to Tri-G for improvements to land
    surrounding the lots. In count VIII of its complaint, Tri-G alleged
    that Elgin Federal breached that land loan agreement by
    withholding payouts owed to Tri-G after it entered into the
    contract for CLG to complete construction on the eight above-
    listed lots.
    In count IX, Tri-G alleged that Elgin Federal committed
    common law fraud by: (1) making unauthorized payouts on the
    construction loans for lots 16, 17, 26, 28, and 31; (2)
    withholding money from Tri-G at the time of closing on lots 16,
    26, 28, 30, and 37; (3) withholding from Tri-G the fact that Elgin
    Federal had made unauthorized disbursements to CLG; (4)
    allowing CLG to substitute new contractor=s affidavits for the
    original contractor=s affidavits with respect to the construction
    loans on all 13 lots; and (5) misleading Tri-G into believing that
    an accounting would be done once all of the lots had been
    closed upon, at which time Tri-G would receive monies
    withheld by Elgin Federal. In pleading damages under this
    count, Tri-G itemized the damages incurred with respect to the
    construction loans on lots 7, 17, 24, 25, 26, 28, 30, 31, 36, and
    37. Tri-G further alleged that it was damaged by unauthorized
    payouts from the land loan it secured from Elgin Federal in the
    amount of $30,000. Tri-G claimed a total of $139,159 in
    compensatory damages and $140,000 in punitive damages. In
    -5-
    count X, Tri-G=s allegations under the Consumer Fraud Act
    essentially mirrored those of the common law fraud count.
    Discovery ensued. In January 2002, one month prior to
    trial, Tri-G was allowed to amend the malpractice complaint to
    add an allegation that Burke was negligent for failing to review
    and amend the 1981 complaint against Elgin Federal. Also, the
    trial court denied Burke=s motion in limine to exclude punitive
    damages. The court reasoned that if the jury assessed punitive
    damages against Elgin Federal in the underlying case, that
    amount would be compensatory damages to Tri-G in the
    malpractice action.
    During the trial, Irene Geschke testified that in June of
    1976, she and her husband, Clarence, purchased a 16.5-acre
    tract of land, intending to develop it as the Huntington Point
    subdivision. Irene was working as a real estate broker. Irene
    and Clarence obtained a loan from First National to purchase
    the property and placed it in a land trust with First National as
    trustee and Irene and Clarence as beneficiaries. Irene and
    Clarence formed Tri-G as general contractor for the
    development of the property. Clarence was the sole
    shareholder of Tri-G and Irene was principally responsible for
    Tri-G=s operation. Tri-G divided Huntington Point into 46 lots,
    45 of which were for single-family homes.
    Irene recounted that in 1977, she approached Dennis
    Neubert of Elgin Federal regarding financing for Tri-G. Tri-G
    subsequently obtained a loan from Elgin Federal to pay off the
    loan from First National. The loan was secured by the then-
    remaining 38 unsold Huntington Point lots, 37 of which were
    planned for single-family homes.                   Irene     also
    spoke with Neubert about financing for the construction of
    homes on Huntington Point. Neubert told Irene that Elgin
    Federal would finance the construction.
    Tri-G introduced into evidence a one-page document from
    Elgin Federal entitled AConstruction Loan Procedure,@ which
    dealt with such matters as Elgin Federal=s inspection of
    construction sites and its payout of loan proceeds to
    subcontractors and suppliers of materials. Tri-G also
    introduced into evidence several loan commitment letters from
    Elgin Federal that set forth specific terms for each construction
    -6-
    loan, e.g., the loan amount and the rate of interest. According
    to Irene, the documents, which purported to memorialize the
    loan agreements, actually included only some of the loan
    terms. Additional terms were agreed to orally.
    The oral terms identified by Irene were as follows: (1)
    payout from loans would be made only upon Tri-G=s written
    request; (2) each loan was separate so that funds advanced on
    one loan could not be used for construction on a lot that was
    subject to a different loan; (3) although interest on a particular
    loan would begin accruing once funds were disbursed, principal
    and interest payments on that loan would not be due until all
    the funds on that loan had been paid out; and (4) the purchaser
    of a completed home would be given a loan with the same
    interest rate and terms, i.e., 9% interest and no points, as the
    construction loan Tri-G had obtained for that house. Finally,
    Irene and Neubert agreed that if a subcontractor or supplier of
    materials required more funds than were originally stated in Tri-
    G=s affidavit itemizing the costs for constructing the home, Tri-
    G was required to submit an amended affidavit before the
    additional funds would be disbursed. According to Irene, the
    loan agreements contained no provision for when payouts
    could be terminated by Elgin Federal.
    Irene testified that Tri-G=s dealings with Elgin Federal
    initially went smoothly. Although she and Neubert agreed that
    interest payments on any particular loan would not be due until
    the proceeds had been entirely paid out, Elgin Federal initially
    billed her for interest, and she paid the interest as billed. Also,
    when Tri-G needed a payout from one of its loans, Elgin
    Federal would issue the payout within three days after Tri-G
    had submitted a payout authorization.
    Tri-G built and sold homes on eight of the Huntington Point
    lots. In each case, in accord with the construction loan
    agreements, the buyer of the home received a loan from Elgin
    Federal with the same interest rate and terms as Tri-G=s
    construction loan.
    In late 1977, Neubert left Elgin Federal and Edward Swartz
    assumed responsibility for the Huntington Point loans. Around
    this time, Tri-G began having difficulties with Elgin Federal. For
    example, Elgin Federal=s response to payout requests slowed
    -7-
    down in early 1978. According to Irene, the slowdown caused
    one of Tri-G=s suppliers, Hines Lumber, to file a lien in
    February 1978. Irene complained to Swartz about the
    slowdown in payouts, and Swartz responded that the delay
    was due to his having just taken over the construction loans
    from Neubert. Irene stopped paying interest in March 1978.
    During Irene=s testimony, the trial court, over Burke=s
    objection, allowed Tri-G to introduce evidence of breach of
    contract and fraud regarding lots not specified in the 1981
    complaint. The purpose of this evidence was to establish the
    existence of a scheme alleged to exist with respect to the lots
    that were specified in the 1981 complaint.
    Irene testified that on April 17, 1978, Swartz sent Tri-G
    several letters demanding regular monthly payments of
    principal and interest under three of the construction loans,
    even though the proceeds had not been paid out entirely on
    any of these loans. Irene testified that, without warning from
    Elgin Federal and without her independent knowledge, payouts
    stopped altogether on May 26, 1978, during Tri-G=s
    construction of homes on 14 projects: lots 7, 16, 17, 22, 24, 26,
    28, 30, 31, 32, 35, 36, 37, and 38. The total amount of the
    loans on these projects was $795,797. As of May 1978,
    $548,626 in loan proceeds had been paid out and $247,171
    remained unpaid. Irene testified that, contrary to Elgin
    Federal=s position, no interest was due on any of the open
    loans in May 1978 because the proceeds had not been paid
    out entirely on any of the loans.
    According to Irene, she received another letter from Swartz
    on June 16, 1978. In that letter, Swartz stated that there was a
    total of $21,688 in delinquent interest on the open construction
    loans and the land loan. Swartz demanded that the delinquent
    interest be paid within 45 days. Swartz also stated that Tri-G
    would have to complete construction of four of the homes on
    which Tri-G had open loans before Elgin Federal would open
    any further loans. Swartz demanded that Tri-G begin
    advertising its unsold homes at Arealistic prices.@ Swartz also
    stated that purchasers of Huntington Point houses would
    receive mortgages at 9.25% and one point. Swartz threatened
    -8-
    that if Tri-G did not comply with the terms of the letter, Elgin
    Federal would take legal action effective August 1, 1978.
    Irene testified that at no time before the June 16, 1978,
    letter did Elgin Federal suggest that Tri-G=s homes were
    overpriced. She also testified that the letter gave no indication
    that Elgin Federal had decided to terminate payouts, though in
    fact payouts had ceased several weeks before, unbeknownst
    to her. Irene noted that, although Elgin Federal required Tri-G
    to complete four homes before it could obtain any more loans,
    Elgin Federal continued to refuse to make payouts, which were
    necessary for construction. Irene testified that, had Elgin
    Federal continued the payouts and allowed construction to
    finish, Tri-G could have paid the allegedly delinquent interest
    with proceeds from sales of the homes. Irene also noted that
    the terms of the mortgages offered to potential buyers in the
    June 16, 1978, letter were less favorable than the terms that
    she and Neubert had agreed upon.
    Irene recounted that on June 20, 1978, Elgin Federal sent
    her bills for interest relative to the loans on several lots. Irene
    did not believe that she was obligated to pay any interest
    because the entire proceeds had not been paid out on any of
    the loans.
    Swartz sent Tri-G another letter on July 3, 1978,
    demanding payment of delinquent interest prior to Elgin
    Federal refinancing any of the existing construction loans to
    secure additional funds for construction. Swartz required Tri-G
    to cure the delinquency on the land loan interest before Elgin
    Federal would release its interest in any lots that Tri-G might
    wish to sell to a third party. Swartz also stated that the terms of
    the mortgages offered to potential buyers in the letter of June
    16, 1978, would be valid only until October 1, 1978, after which
    current market rates and fees would apply. Swartz threatened
    legal action if Tri-G took no action to complete the homes and
    establish an advertising plan to sell the homes Aat a realistic
    price.@ Swartz further stated that Elgin Federal=s Aboard feels
    that it is important to complete this project at an early date or
    we will ask for a deed in lieu of foreclosure or foreclosure
    proceedings will commence.@
    -9-
    Swartz informed Irene that Elgin Federal had found a
    buyer, CLG, for the 23 lots in Huntington Point that were still
    vacant. CLG proposed to pay $15,000 for each of the vacant
    lots. Based on her experience in the real estate market, Irene
    testified that the fair market value of the lots at that time was
    $25,000 each. Irene had found another party who wanted to
    buy the lots at a higher price, but Elgin Federal refused to
    release its mortgages on the lots unless the delinquencies in
    interest were paid.
    Elgin Federal subsequently presented Irene and Clarence
    with a contract for the sale to CLG of the 23 vacant lots at the
    price of $15,000 per lot. The contract provided that $9,300 of
    the purchase price for each lot would be paid to Elgin Federal
    for the release of the lot under the land loan agreement. The
    contract also provided that CLG would act as general
    contractor on 8 of the 14 lots where construction was partially
    completed, and Tri-G would finish construction on the
    remaining six partially completed lots. Tri-G would remain
    responsible for the loans on all 14 lots. To compensate for any
    shortfall should CLG fail to complete construction of the homes
    within 90 days of the signing of the contract, CLG was required
    to place $2,500 in escrow for each of the eight lots on which
    CLG agreed to complete construction (totaling $20,000). The
    contract also required Tri-G to pay Elgin Federal $51,300 to
    cover any deficiency in the open construction loans. The
    contract further provided that Irene and Clarence would
    execute the necessary documents to allow CLG to handle
    exclusively all payouts under construction loans on the partially
    completed lots to be completed by CLG.
    Irene=s attorney, Michael Poper, suggested changes to the
    contract, but Elgin Federal rejected them and essentially gave
    Tri-G the choice of signing the contract or facing foreclosure on
    the open loans. Irene and Clarence agreed to the terms. The
    contract was executed on August 17, 1978. The parties to the
    contract were First National, as trustee of the land trust; Irene
    and Clarence, as sole owners of the entire beneficial interest in
    the land trust; and CLG.
    After the contract with CLG was signed, Elgin Federal
    refused to make payouts on the six lots on which Tri-G was to
    -10-
    complete construction. Irene also discovered that Elgin Federal
    was permitting CLG to use payouts for purposes other than
    construction on the eight lots on which CLG was general
    contractor. Irene considered this practice to be a violation of
    the oral construction loan agreements, which did not allow
    payouts from a particular loan to be applied to a purpose other
    than construction on the lot for which that particular loan was
    obtained.
    Irene reviewed Elgin Federal=s ledger and determined the
    amount of funds that CLG used improperly. The total was
    $75,787. Irene complained to Swartz about Elgin Federal=s
    refusal to make payouts on the lots on which Tri-G was to
    complete construction and about the inappropriate payouts to
    CLG. Swartz told her that the contract between CLG and the
    Geschkes made CLG the agent of First National and deprived
    Tri-G of any control over the Huntington Point development.
    According to Irene, Elgin Federal made payouts from the
    land loan without Tri-G=s authorization, a practice contrary to
    the land loan=s terms. The trial court admitted into evidence
    portions of Elgin Federal=s ledger reflecting payouts to
    subcontractors during the years 1977 through 1979. Irene
    identified $21,725 in payouts that she did not authorize.
    Without Tri-G=s approval, CLG submitted its own
    contractor=s affidavits on the eight lots on which it had agreed
    to finish construction. Irene considered this a violation of the
    terms of the construction loan agreements on those lots. The
    costs specified in CLG=s affidavits exceeded the costs specified
    in Tri-G=s original affidavits, thus reducing Tri-G=s equity in the
    eight homes.
    Also, according to Irene=s testimony, Elgin Federal
    eventually foreclosed on the 14 open construction loans.
    Although CLG did not fulfill its contractual promise to complete
    construction on the eight lots, Elgin Federal returned the
    $20,000 in escrow funds to CLG without Irene=s knowledge or
    approval.
    Irene testified that she would never have entered into loan
    agreements with Elgin Federal had she known it did not intend
    to honor its oral agreements. She also would not have entered
    into the contract with CLG had Elgin Federal not threatened
    -11-
    foreclosure and disallowed her from selling the lots to any party
    other than CLG.
    Michael Poper was the Geschkes= attorney during their
    dealings with Elgin Federal. He testified that, without notice,
    Elgin Federal stopped making payouts on May 26, 1978. Poper
    noted that, even in June 1978, Elgin Federal still had not
    formally announced that it had stopped payouts. When Irene
    complained about the cessation of payouts, Elgin Federal told
    her that it would make no more payouts until interest was
    brought current.
    In Poper=s opinion, Elgin Federal=s demand for interest was
    premature under the construction loan agreements. In his view,
    if Elgin Federal had continued making payouts, thereby
    enabling Tri-G to finish constructing the homes, Tri-G could
    have used the proceeds from the sales of the homes to pay
    whatever interest was then due. By withholding payouts and
    thus halting construction, however, Elgin Federal effectively
    precluded payment of the interest it demanded. Over Burke=s
    objection, Poper testified that he had represented other
    developers whom Elgin Federal had placed in the same kind of
    predicament.
    John Brittain was a member of Elgin Federal=s board of
    directors when Elgin Federal extended the land and
    construction loans to Tri-G in 1977. He testified that Elgin
    Federal=s standard policy at that time was to require monthly
    interest payments on construction loans. Elgin Federal
    threatened foreclosure in June 1978 because Tri-G had fallen
    behind in interest payments. Brittain acknowledged that Irene
    had complained to him that Elgin Federal had paid proceeds
    from certain of Tri-G=s construction loans toward deficiencies
    on other construction loans. According to Brittain, Elgin Federal
    commingled funds in this fashion to avoid placing Tri-G in
    default. Brittain admitted, however, that such commingling was
    contrary to Elgin Federal=s policies. Tri-G rested its case.
    For its defense, Burke first called Brent Sherman, the
    founder and sole shareholder of CLG. Sherman testified to the
    events surrounding CLG=s contract with the Geschkes under
    which CLG agreed to purchase 23 vacant lots and to finish
    construction on several of the remaining lots. According to
    -12-
    Sherman, the contract gave him full authority to request
    payouts from Elgin Federal on the homes he was completing,
    but he nonetheless obtained Irene=s approval for all payouts he
    requested. Also, because he did not complete construction of
    the homes within the agreed time, Sherman disbursed to Tri-G
    $10,000 of the $20,000 CLG had placed in escrow to
    guarantee completion of the homes. Sherman admitted,
    however, that he had no documentation reflecting that
    payment. Sherman denied that he ever conspired with Elgin
    Federal to deprive Tri-G of control over the Huntington Point
    development. Also, Sherman had anticipated receiving a profit
    of $20,000 on each of the 23 lots once construction was
    complete.
    Burke next called Edward Swartz, who testified that he
    assumed responsibility for Tri-G=s loans after Dennis Neubert
    left Elgin Federal in late 1977. According to Swartz, Elgin
    Federal=s policies made borrowers responsible for monthly
    interest payments on their construction loans once funds were
    disbursed. Tri-G initially paid interest on the construction loans
    without protest but stopped paying in early 1978, giving rise to
    Elgin Federal=s delinquency notices and threats of foreclosure.
    Contrary to Irene=s interpretation, Swartz stated that the
    contract between CLG and Tri-G made CLG responsible for
    interest and principal on the loans relating to the construction it
    had agreed to finish. Swartz denied that funds from Tri-G=s
    loans were ever commingled with funds from the loans CLG
    took over.
    On cross-examination, Swartz conceded that the written
    construction loan agreements between Elgin Federal and Tri-G
    did not specify when interest was to be paid. Swartz admitted
    that Elgin Federal=s procedures were Ainformal@ and that not all
    policies were in writing. Swartz acknowledged that the total
    amount of delinquent interest reflected in his June 16, 1978,
    letter included interest for June 1978, which in fact was not due
    until after the date of the letter. According to Swartz, the
    characterization of the June interest as delinquent was an
    innocent error. Swartz categorically denied that Elgin Federal
    had ever stopped payouts on any of Tri-G=s loans. Shown
    documents from Elgin Federal reflecting that the bank had
    -13-
    made virtually no payouts between May 26 and September 19,
    1978, Swartz speculated that no payouts were made because
    Tri-G had not requested them.
    Swartz further admitted on cross-examination that, after
    the contract between CLG and Tri-G was signed, Irene told him
    several times that she did not want CLG authorizing payouts
    on the homes CLG agreed to finish and that she was revoking
    CLG=s authority under the contract to make such
    authorizations. In response, Swartz told Irene that she would
    have to cancel the contract in writing if she wanted to stop CLG
    from authorizing payouts.
    Swartz further admitted on cross-examination that he could
    point to no document memorializing CLG=s assumption of
    responsibility for interest and principal on the loans relating to
    the construction projects CLG agreed to complete. Swartz
    acknowledged that the fact that foreclosure proceedings were
    brought against Tri-G when these projects failed indicated that
    Tri-G remained responsible for the loans despite the contract
    with CLG. Swartz also admitted that Elgin Federal commingled
    funds on Tri-G=s loans and that Irene protested the practice on
    numerous occasions.
    At the conclusion of the evidence, the trial court instructed
    the jury on five specific categories of damages, with their
    respective elements, sought by Tri-G. In its closing argument,
    Tri-G sought damages in the following amounts: $75,787 for
    breach of the construction loan agreements; $21,675 for
    breach of the land loan agreement; $10,000 for breach of the
    escrow agreement; $361,000 for fraud that resulted in loss of
    profits on the 23 vacant lots; and $280,000 for fraud that
    resulted in lost profits on the 14 partially completed lots. These
    sums totaled $748,562.
    The jury ultimately returned a verdict in favor of Tri-G for
    $2,337,550, more than three times the amount Tri-G asked for.
    In four special interrogatories, the jury found that: (1) Burke
    was negligent in representing Tri-G in the underlying case; (2)
    Burke=s negligence proximately caused Tri-G to lose the
    underlying case; (3) had Tri-G prevailed in the underlying case,
    it would have recovered a verdict against Elgin Federal for
    $1,168,775 in compensatory damages; and (4) had Tri-G
    -14-
    prevailed in the underlying case, Elgin Federal would have
    been required to pay it an additional $1,168,775 in punitive
    damages.
    Burke filed a posttrial motion seeking alternative forms of
    relief. Tri-G filed a posttrial motion in which it requested interest
    on the judgment and an award of attorney fees and costs
    pursuant to the Consumer Fraud Act. Both motions were
    denied.
    Burke appealed and Tri-G cross-appealed. The appellate
    court rejected a contention by Burke that the amount of
    compensatory damages awarded to Tri-G was not supported
    by the 
    record. 353 Ill. App. 3d at 222-23
    . It upheld the award of
    punitive damages to Tri-G (
    353 Ill. App. 3d
    at 226-32), but
    rejected Tri-G=s claim for judgment interest (
    353 Ill. App. 3d
    at
    223-24). In addition, it reversed the trial court=s denial of Tri-G=s
    request for attorney fees and costs pursuant to the Consumer
    Fraud Act and remanded the cause to the trial court to allow
    Tri-G to request attorney fees and costs incurred in bringing
    the consumer fraud 
    claim. 353 Ill. App. 3d at 224-26
    .
    One justice dissented solely on the issue of lost punitive
    
    damages. 353 Ill. App. 3d at 233
    (Gilleran Johnson, J.,
    concurring in part and dissenting in part). That justice would
    have followed precedent from New York and California and
    held that Aa plaintiff may not recover punitive damages lost by
    reason of attorney 
    malpractice.@ 353 Ill. App. 3d at 236
    (Gilleran Johnson, J., concurring in part and dissenting in part).
    Burke and Tri-G each filed petitions for leave to appeal.
    177 Ill. 2d R. 315(a). We allowed their respective petitions and
    consolidated the appeals for review. We subsequently granted
    leave to the Illinois Association of Defense Trial Counsel, and
    the Illinois Civil Justice League, the Du Page County Bar
    Association, and the Northwest Suburban Bar Association to
    file amicus curiae briefs in support of Burke. See 155 Ill. 2d R.
    345.
    In its appeal to our court, Burke contends that it was
    denied procedural due process when Tri-G was permitted to
    amend its complaint to add allegations regarding lots not
    specified in the 1981 complaint, that the amount of
    compensatory damages awarded was not supported by the
    -15-
    record, and that the award of lost punitive damages was
    erroneous. Because only the punitive damages issue was
    raised in Burke=s petition for leave to appeal (No. 99584). Tri-G
    filed motions to strike Burke=s additional two issues from its
    brief. We took the motions with the case and now deny them.
    Supreme Court Rule 315(b)(3) requires that a petition for
    leave to appeal contain Aa statement of the points relied upon
    for reversal of the judgment of the Appellate Court.@ 177 Ill. 2d
    R. 315(b)(3). A party=s failure to raise an issue in the petition
    for leave to appeal may be deemed a waiver of that issue.
    Central Illinois Light Co. v. Home Insurance Co., 
    213 Ill. 2d 141
    , 152 (2004); Sullivan v. Edward Hospital, 
    209 Ill. 2d 100
    ,
    124-25 (2004). In this case, however, Tri-G filed its own,
    separate petition for leave to appeal to contest the lower
    courts= denial of its claim for judgment interest (No. 99595) and
    that petition was allowed. Pursuant to Supreme Court Rule
    318(a) (155 Ill. 2d R. 318(a)), Burke, as appellee in that cause,
    is entitled to Aseek and obtain any relief warranted by the
    record on appeal without having filed a separate petition for
    leave to appeal or notice of cross-appeal or separate appeal.@
    This authorization encompasses the two additional issues
    asserted by Burke.
    In challenging this conclusion, Tri-G argues that to apply
    Rule 318(a) to permit Burke to assert the additional issues
    Aeviscerates the principle that points relied on by an appellant
    for reversal not contained in the petition for leave to appeal are
    waived.@ We disagree. Tri-G chose to file a separate petition for
    leave to appeal, and our application of Rule 318(a) is a natural
    consequence of Tri-G=s tactical decision. See, e.g.,
    Weatherman v. Gary-Wheaton Bank of Fox Valley, 
    186 Ill. 2d 472
    , 489-91 (1999); Zimmerman v. Village of Skokie, 
    183 Ill. 2d 30
    , 40-41 (1998). Tri-G=s motions to strike the additional issues
    from Burke=s brief are therefore denied.
    Turning then to the merits of this appeal, Burke first
    contends that it was denied procedural due process by the trial
    court=s decision to allow Tri-G to recover damages for the 23
    vacant lots and the 14 partially completed lots not specified in
    the 1981 complaint and by the appellate court=s review of that
    decision. As earlier noted, Tri-G was allowed to amend the
    -16-
    malpractice complaint prior to trial to add an allegation that
    Burke was negligent for failing to review and amend the 1981
    complaint against Elgin Federal. In allowing Tri-G=s motion to
    amend, the trial court stated:
    ABoth sides are dragging in the question of damages.
    *** [T]he proposed amendment has absolutely nothing
    to do with damages because you can=t back door the
    damages. I mean the damages if there are any, if it
    gets that far, would have to come from the 1981
    complaint. It doesn=t come from anywhere else.@
    The trial court reasoned that the amendment only went to the
    question of what negligence Tri-G intended to prove.
    During Irene=s testimony, the trial court allowed Tri-G to
    introduce evidence of breach of contract and fraud regarding
    the 23 vacant and 14 partially completed lots not specified in
    the 1981 complaint. The trial court admitted this evidence for
    the purpose of establishing an alleged scheme with respect to
    the lots that were specified in the 1981 complaint. Indeed, the
    trial court expressly stated that Tri-G would not be able to
    argue to the jury that it was entitled to damages based on the
    additional lots. However, at the jury instruction conference,
    over Burke=s objection, the trial court ruled that damages on
    the fraud claims properly included the additional lots. Tri-G
    sought such damages, which the jury awarded. In denying
    Burke=s posttrial motion, the trial court explained that the fraud
    claims relating to the additional lots were encompassed within
    the 1981 complaint.
    In the appellate court, Burke assigned error to this
    decision. The appellate court disagreed with the trial court that
    the 1981 complaint was sufficiently broad to encompass claims
    relating to the additional lots. Noting that it can affirm the trial
    court=s decision on any basis in the record, however, the
    appellate court held as follows:
    AWe hold that the claims outside the 1981 complaint
    were admissible at the malpractice trial on the basis
    that a reasonably competent attorney would have filed
    a motion to amend the complaint to add the claims
    within a reasonable time after being retained by Tri-G
    in January 1987, and that such a motion should have
    -17-
    been granted because it would have been proper
    under the prevailing rules of 
    pleading.@ 353 Ill. App. 3d at 214
    .
    The appellate court opined that a reasonably competent
    attorney retained by Tri-G in late January 1987, aware that
    May 11, 1987, was the date certain for trial, would have
    immediately reviewed the 1981 complaint. Further, according
    to the appellate court, given the interrelationship between the
    claims relating to the lots specified in the 1981 complaint and
    the same claims relating to the additional lots, a reasonably
    competent attorney would have sought to amend the 1981
    complaint prior to the May 11, 1987, 
    trial. 353 Ill. App. 3d at 214-15
    .
    In this court, Burke specifically contends that the lower
    courts= decisions cumulatively effected a deprivation of
    procedural due process because Burke was unable to present
    a defense to claims related to the additional lots. Burke argues
    that it was fundamentally unfair for the trial court to permit the
    jury to award damages on claims relating to the additional lots,
    which the trial court ruled, during trial, could not be the basis of
    recovery. Burke further argues that the appellate court, instead
    of correcting the trial court=s error, compounded it by upholding
    the trial court=s decision based on alternative reasoning. Thus,
    according to Burke, the appellate court=s conclusion Awas an
    integral part of the due process violation.@
    Procedural due process claims concern the
    constitutionality of the specific procedures employed to deny a
    person=s life, liberty, or property interest. East St. Louis
    Federation of Teachers, Local 1220 v. East St. Louis School
    District No. 189 Financial Oversight Panel, 
    178 Ill. 2d 399
    , 415
    (1997). The requirement of due process is met by having an
    orderly proceeding wherein a person is served with notice,
    actual or constructive, and has an opportunity to be heard and
    to enforce and protect his rights. The A >fundamental
    requirement of due process in any proceeding which is to be
    accorded finality is notice reasonably calculated, under the
    circumstances, to apprise interested parties of the pendency of
    the action and afford them an opportunity to present their
    objections.= @ People ex rel. Devine v. $30,700.00 United States
    -18-
    Currency, 
    199 Ill. 2d 142
    , 156 (2002), quoting Stratton v.
    Wenona Community Unit District No. 1, 
    133 Ill. 2d 413
    , 432
    (1990). Due process does not guarantee against erroneous or
    unjust decisions by courts which have jurisdiction of the parties
    and the subject matter, and a constitutional question is not
    presented where a court may have misconstrued the law or
    committed an error for which its judgment should be reversed.
    See Reyes v. Court of Claims, 
    299 Ill. App. 3d 1097
    , 1104-05
    (1998).
    Applying these principles to this case, it is clear that Burke
    was not denied procedural due process. There is no merit to
    Burke=s contention that Burke was not able to present a
    defense to claims relating to the additional lots. The issue of
    damages related to the additional lots permeated the entire
    trial, including Tri-G=s pretrial motion to amend the malpractice
    complaint to include an allegation that Burke was negligent for
    failing to review and amend the 1981 complaint. AAn element of
    damage anticipated by a pretrial motion can hardly be said to
    come as a surprise.@ Union Electric Power Co. v. Sauget, 
    1 Ill. 2d
    125, 132 (1953). Further, the evidence of the additional lots
    is nearly identical to allegations relating to the lots pled in the
    1981 complaint. If Burke were truly surprised by evidence of
    the additional lots, it would have requested a continuance to
    conduct further discovery. Instead, Burke chose to proceed.
    Indeed, Burke did not even introduce expert witnesses or other
    evidence valuating the lots that were specified in the 1981
    complaint. Burke does not explain how it was prevented from
    deposing any witness, pursuing any line of questioning, or
    presenting any avenue of proof. The absence of surprise or
    other prejudice militates against finding a procedural due
    process violation. See, e.g., McDermott v. Metropolitan
    Sanitary District, 
    240 Ill. App. 3d 1
    , 38-39 (1992); La Salle
    National Bank v. International Ltd., 
    129 Ill. App. 2d 381
    , 397-98
    (1970).
    In support of its position, Burke cites Delarosa v. Approved
    Auto Sales, Inc., 
    332 Ill. App. 3d 623
    (2002), Hiscott v. Peters,
    
    324 Ill. App. 3d 114
    (2001), Koplin v. Hinsdale Hospital, 207 Ill.
    App. 3d 219 (1990), and Pettigrew v. National Accounts
    System, Inc., 
    67 Ill. App. 2d 344
    (1966). In each of those
    -19-
    cases, new causes of action were adjudicated on the merits
    without the appellant being given the opportunity to answer the
    new causes of action, take discovery, and prosecute or defend
    itself against the new causes of action at trial. Those cases are
    distinguishable from the matter before us. Unlike the appellants
    in those cases, Burke was not required to litigate new causes
    of action on short notice with no opportunity to answer the
    causes of action, take discovery, and present evidence in
    opposition to the new causes of action. Burke had ample time
    to take discovery on all claims related to Tri-G=s dealings with
    Elgin Federal.
    Absent its unsuccessful claim of prejudice, Burke=s
    contention amounts to nothing more than an argument that it
    was denied procedural due process because the decisions of
    the trial and appellate courts were erroneous. As we have
    previously indicated, however, procedural due process is not a
    guaranty against erroneous or unjust decisions, or the incorrect
    interpretation of statutes or rules of law. Neither an abuse of
    discretion nor an erroneous rule of law will support a reversal
    for a deprivation of procedural due process. Peoples Gas Light
    & Coke Co. v. Buckles, 
    24 Ill. 2d 520
    , 530 (1962); Benton v.
    Marr, 
    364 Ill. 628
    , 629 (1936), quoting Genslinger v. New
    Illinois Athletic Club of Chicago, 
    332 Ill. 316
    , 319 (1928). In this
    case, the trial court had within its discretion the power to rule
    as it did on the complained-of matters. Even if the challenged
    rulings of the lower courts may have been erroneousBwhich we
    expressly do not decideBthey did not deprive Burke of due
    process of law. See Kazubowski v. Kazubowski, 
    45 Ill. 2d 405
    ,
    413 (1970); Chicago Land Clearance Comm=n v. Darrow, 
    12 Ill. 2d
    365, 369-70 (1957).
    Burke next challenges the amount of the jury=s
    compensatory damages award. As earlier noted, the trial court
    instructed the jury on the elements of five specific categories of
    damages that Tri-G sought. In its closing argument, Tri-G
    requested $75,787 for breach of the construction loan
    agreements, $21,675 for breach of the land loan agreement,
    $10,000 for breach of the escrow agreement, $361,000 for
    fraud that resulted in loss of profits on the 23 vacant lots, and
    $280,000 for fraud that resulted in lost profits on the 14 partially
    -20-
    completed lots. These amounts totaled $748,562. The jury,
    however, determined that Tri-G was actually entitled to
    $1,168,775 in compensatory damages.
    In assailing the jury=s verdict, Burke contends that Tri-G
    should not have recovered compensation for lost profits on the
    14 partially completed lots. The firm also takes issue with the
    total amount of the compensatory damages awarded by the
    jury. Our consideration of these arguments is guided by the
    principle that A[t]he determination of damages is a question
    reserved to the trier of fact, and a reviewing court will not lightly
    substitute its opinion for the judgment rendered in the trial
    court.@ Richardson v. Chapman, 
    175 Ill. 2d 98
    , 113 (1997).
    Absent a clear indication in the record that the jury failed to
    follow some rule of law or considered some erroneous
    evidence, or that the verdict was the obvious result of passion
    or prejudice, a reviewing court will not upset the jury=s
    assessment of damages. See Perry v. Storzbach, 
    206 Ill. App. 3d
    1065, 1069 (1990).
    Burke challenges the jury=s award of $280,000 for lost
    profits on the 14 partially completed lots on the grounds that it
    was speculative and not supported by the evidence. This
    argument cannot be sustained. As we noted earlier, CLG
    president Brent Sherman testified that he reasonably
    anticipated a profit of $20,000 per lot for each completed
    house. During closing argument, Tri-G relied on Sherman=s
    testimony in requesting compensatory damages for lost profits
    in the amount of $20,000 for each of the 14 partially completed
    lots, which totals $280,000. The appellate court held that
    Sherman=s testimony as to the expected profits was an
    adequate basis for the jury=s 
    award. 353 Ill. App. 3d at 221-22
    .
    The controlling principles are well established. AA recovery
    may be had for prospective profits when there are any criteria
    by which the probable profits can be estimated with reasonable
    certainty.@ Barnett v. Caldwell Furniture Co., 
    277 Ill. 286
    , 289
    (1917). AIn order to recover lost profits, it is not necessary that
    the amount of loss be proven with absolute certainty. [Citation.]
    Being merely prospective, such profits will, to some extent, be
    uncertain and incapable of calculation with mathematical
    precision.@ Midland Hotel Corp. v. Reuben H. Donnelley Corp.,
    -21-
    
    118 Ill. 2d 306
    , 315-16 (1987); accord 
    Barnett, 277 Ill. at 289
    .
    The impossibility of proof of the exact amount of lost profits will
    not justify refusing damages. The law requires only that the
    plaintiff approximate the claimed lost profits by competent
    evidence. Such evidence must with a fair degree of probability
    tend to establish a basis for the assessment of damages for
    lost profits. 
    Barnett, 277 Ill. at 289
    . AHowever, recovery of lost
    profits cannot be based upon conjecture or sheer speculation.
    [Citation.] It is necessary that the evidence afford a reasonable
    basis for the computation of damages ***.@ Midland 
    Hotel, 118 Ill. 2d at 316
    .
    A plaintiff may satisfy the requirement of proving with a
    reasonable basis or with reasonable certainty damages for
    claimed lost profits through evidence of past profits in an
    established business. Generally speaking, however, courts
    consider evidence of lost profits in a new business too
    speculative to sustain the burden of proof. Chapman v. Kirby,
    
    49 Ill. 211
    , 219 (1868); see Malatesta v. Leichter, 
    186 Ill. App. 3d
    602, 621 (1989); Drs. Sellke & Conlon, Ltd. v. Twin Oaks
    Realty, Inc., 
    143 Ill. App. 3d 168
    , 174 (1986).
    Reviewing the record, the appellate court observed that
    Sherman spent several years in the construction business,
    which he described as profitable, prior to becoming involved in
    Huntington Point. Each of the 23 vacant lots was comparable
    to the 14 partially completed lots. Also, Sherman=s, i.e., CLG=s,
    business of selling houses for profit was comparable to Tri-G=s
    business of selling houses for profit. In the appellate court=s
    view, Sherman=s testimony was an adequate basis for
    calculating Tri-G=s lost profits on the 14 partially completed 
    lots. 353 Ill. App. 3d at 221-22
    .
    Assigning error to the appellate court=s reasoning, Burke
    contends that, as a matter of law, evidence of past success in
    a similar enterprise is not sufficient to support an award of lost
    profits and, specifically, past success on one real estate project
    is not sufficient to support an award of lost profits on a
    subsequent real estate project. According to Burke,
    ASherman=s testimony about his expectations based on his
    prior successes on other real estate projects was [therefore]
    -22-
    not sufficient to support an award of lost profits of Tri-G on this
    project.@ (Emphases in original.)
    We cannot accept Burke=s contention. There is no inviolate
    rule that a new business can never prove lost profits. Rather, in
    some cases, Acourts have found that the rule that a new
    business= profits are too speculative did not fit the
    circumstances before them.@ Milex Products, Inc. v. Alra
    Laboratories, Inc., 
    237 Ill. App. 3d 177
    , 192 (1992); see, e.g.,
    Malatesta, 
    186 Ill. App. 3d
    at 620-22.
    The cases on which Burke relies determined that where
    lost profits are based solely upon speculation, such proof was
    inadequate to establish lost profits with reasonable certainty. In
    this case, CLG=s business was an established business. The
    14 houses to be completed cost the same amount to construct
    and had comparable prices as the completed houses. Given
    these facts, with Sherman=s testimony, Tri-G=s lost profits could
    be determined with reasonable certainty from CLG=s past
    experience. See, e.g., 
    Milex, 237 Ill. App. 3d at 193
    . We
    therefore uphold the jury=s award of $280,000 for lost profits on
    the 14 partially completed lots.
    Burke=s contention that the jury=s overall award was
    excessive presents a more difficult question. Tri-G requested a
    total of $748,562 in compensatory damages for five categories
    of damages on which the jury was instructed. The jury,
    however, awarded $1,168,775 in compensatory damages,
    which was $420,213Bover 50%Bmore than what Tri-G
    requested. Burke contends that such an award was not
    supported by the record and was the result of passion,
    prejudice, or confusion. It therefore requests that we remand
    the cause for a new trial solely on the issue of damages or,
    alternatively, that we order a remittitur in the amount of
    $420,213, thereby reducing the compensatory damages award
    to $748,562. We conclude that remittitur is necessary in this
    case.
    Under Illinois law, an award of damages will be deemed
    excessive if it falls outside the range of fair and reasonable
    compensation, results from passion or prejudice, or is so large
    that it shocks the judicial conscience. 
    Richardson, 175 Ill. 2d at 113
    . In Burke=s view, the jury=s decision to award Tri-G
    -23-
    $420,213 more than it had requested, Acould only have been
    produced by passion, prejudice, or confusion.@ We disagree. AA
    jury=s award of a verdict higher than that requested by counsel
    does not, by itself, indicate that the jury acted out of passion or
    prejudice.@ See Fedt v. Oak Lawn Lodge, Inc., 
    132 Ill. App. 3d 1061
    , 1072 (1985). Having said that, however, we must
    nevertheless conclude that the jury=s verdict, as rendered,
    cannot stand.
    In attempting to rationalize the jury=s compensatory
    damage award, Tri-G suggests that its trial counsel deliberately
    asked for less than it was entitled to recovery as a strategic
    maneuver. The record, however, belies that notion. During its
    closing argument, Tri-G referred extensively to evidence from
    documents and witnesses. In each of the five categories of
    damages on which the jury was instructed, Tri-G asked the jury
    to award it the dollar amount that corresponded to the loss
    reflected in the evidence. Indeed, in one category of damages,
    Tri-G presented the jury with a time range within which to
    determine damages and asked for the maximum amount within
    that range, which the jury awarded.
    In its brief, Tri-G additionally responds that the record
    contains Aample@ evidence to support the jury=s $1,168,775
    compensatory damages award. Citing again to documents and
    witness testimony, Tri-G argues that the award Aappears to
    consist@ of a list of categories of damages, assigning a dollar
    value to each category. Two of Tri-G=s claimed categories of
    damages, however, are outside of the five categories of
    damages on which the jury was instructed: A$255,336.00 paid
    by Tri-G to purchase the land and develop it into 24 lots,@ and
    A$240,754.00 loss of money paid by Tri-G in opening waivers
    for 14 houses.@
    Tri-G does not dispute that these two claimed categories of
    damages were not identified in the jury instructions. Rather,
    Tri-G contends that it is not reversible error for a jury to
    disregard the elements of damages identified in jury
    instructions as long as the ultimate damages award Ais
    consistent with the evidence and proven damages.@ This
    contention is meritless.
    -24-
    Jurors do not possess a roving commission to find such
    damages as they please. The damages awarded by a jury
    must be measured by a legal standard, and that standard must
    guide the jury=s determination as to what sum would
    compensate the injured party. Accordingly, while the amount of
    recoverable damages is a question of fact for the jury, the
    measure of damages upon which the jury=s factual computation
    is based is a question of law for the court (see United States
    for the Use of N. Maltese & Sons, Inc. v. Juno Construction
    Corp., 
    759 F.2d 253
    , 255 (2d Cir. 1985); Basic American, Inc.
    v. Shatila, 
    133 Idaho 726
    , 745, 
    992 P.2d 175
    , 194 (1999); 25A
    C.J.S. Damages '342 (2002); 
    15 Ill. L
    . & Prac. Damages '125,
    at 558 (2000)), and the court=s instructions should limit the
    jury=s consideration to facts that are properly a part of the
    damages allowable (Allied Vista, Inc. v. Holt, 
    987 S.W.2d 138
    ,
    141 (Tex. Ct. App. 1999); accord Creek v. Village of
    Westhaven, 
    144 F.3d 441
    , 447 (7th Cir. 1998) (AA jury=s
    discretion in awarding damages is limited by the parameters of
    what the law will allow [citations], and it is the court=s
    instructions which hopefully assist the jury@); C. McCormick,
    Damages '15, at 58 (1935) (observing that, in action for
    damages, trial judge has duty to include in jury instructions a
    rule or standard for measuring amount of award)).
    In the present case, the trial court instructed the jury: AIt is
    your duty to resolve this case by determining the facts and
    following the law given in the instructions.@ See Illinois Pattern
    Jury Instructions, Civil, No. 1.01(2) (2000). The trial court
    further instructed the jury on only the five above-stated
    categories of damages. Under the principles discussed above,
    Tri-G therefore cannot justify the jury=s award of compensatory
    damages by hypothesizing categories of damages on which
    the jury was not instructed.
    We are thus left with no basis in the law or the record to
    support a verdict $420,213 greater that Tri-G had requested.
    Where, as here, a jury=s award Aexceed[s] the proven
    damages, it must be corrected. The practice of entering or
    ordering a remittitur has long been an accepted practice in
    Illinois and it has been consistently acknowledged to be
    promotive of both the administration of justice and putting an
    -25-
    end to litigation.@ See McElroy v. Patton, 
    130 Ill. App. 2d 872
    ,
    877 (1970) (collecting authorities); see generally Best v. Taylor
    Machine Works, 
    179 Ill. 2d 367
    , 411-13 (1997).
    In this legal malpractice action, the underlying case was
    instituted with the filing of the 1981 complaintBapproximately 24
    years ago. ARather than prolong this litigation any further,
    remittitur will be utilized to correct the excessive verdict.@ Peter
    J. Hartmann Co. v. Capitol Bank & Trust Co., 
    353 Ill. App. 3d 700
    , 711 (2004).
    The applicable principles are widely recognized. A
    remittitur is an agreement by the plaintiff to relinquish, or remit,
    to the defendant that portion of the jury=s verdict which
    constitutes excessive damages and to accept the sum which
    has been judicially determined to be properly recoverable
    damages. It is a judicial determination of recoverable damages
    and should not be construed as an agreement between the
    parties or a concession by the plaintiff that the damages were
    excessive. See Carter v. Kirk, 
    256 Ill. App. 3d 938
    , 947-48
    (1993); Congregation of the Passion, Holy Cross Province v.
    Touche Ross & Co., 
    224 Ill. App. 3d 559
    , 588 (1991), aff=d, 
    159 Ill. 2d 137
    (1994); Haid v. Tingle, 
    219 Ill. App. 3d 406
    , 411
    (1991) (collecting authorities).
    Although a trial court may refuse to enter judgment on a
    verdict unless a portion of the verdict is remitted, the court
    does not have the authority to reduce the damages by entry of
    a remittitur if the plaintiff objects or does not consent. The trial
    court must afford the plaintiff the choice of agreeing or refusing
    to the entry of a remittitur, with the proviso that the plaintiff=s
    refusal to agree to the entry of a remittitur will result in the
    ordering of a new trial. The only alternative to a remittitur in a
    case where the verdict exceeds the damages properly proven,
    or where the verdict can be accounted on the sole basis that
    the jury acted from some improper motive, such as passion or
    prejudice, is for the trial judge to order a new trial. 
    Carter, 256 Ill. App. 3d at 947-48
    ; 
    Haid, 219 Ill. App. 3d at 411-12
    (and
    cases cited therein). Further, Supreme Court Rule 366(a)(5)
    specifically provides that a reviewing court has the power to
    grant any relief, including the entry of a remittitur. 155 Ill. 2d R.
    366(a)(5).
    -26-
    Accordingly, in the present case, we enter a remittitur of
    $420,213, thereby reducing Tri-G=s compensatory damages
    award to $748,562, conditioned upon Tri-G=s consent. Absent
    such consent, we order a new trial solely on the issue of
    damages. See, e.g., Peter J. Hartmann 
    Co., 353 Ill. App. 3d at 711-12
    ; 
    Haid, 219 Ill. App. 3d at 417
    ; Briante v. Link, 184 Ill.
    App. 3d 812, 815 (1989).
    We next consider Tri-G=s contention that the lower courts
    erred in denying its claim for judgment interest. In considering
    Tri-G=s arguments, which repeat those it presented in the
    appellate court, we observe that the pertinent facts are
    undisputed and the issues raised are purely legal. AIf the facts
    are uncontroverted and the issue is the trial court=s application
    of the law to the facts, a court of review may determine the
    correctness of the ruling independently of the trial court=s
    judgment.@ Norskog v. Pfiel, 
    197 Ill. 2d 60
    , 70-71 (2001).
    Tri-G divides the interest it seeks into two time periods,
    with the focal point being June 1, 1987. First, Tri-G seeks
    Aprejudgment@ interest, which covers the period from June
    1978, when Elgin Federal committed the acts from which the
    underlying case arose, to June 1, 1987, the approximate date
    that a verdict would have been entered against Elgin Federal
    but for Burke=s negligence. Prejudgment interest is recoverable
    only where authorized by agreement of the parties or by
    statute. In chancery proceedings, however, equitable
    considerations permit a court to allow interest as the equities of
    the case may demand. City of Springfield v. Allphin, 
    82 Ill. 2d 571
    , 576, 579 (1980) (collecting cases); Continental Casualty
    Co. v. Commonwealth Edison Co., 
    286 Ill. App. 3d 572
    , 577
    (1997) (collecting cases). Tri-G argues that, had a damages
    judgment been entered against Elgin Federal in 1987, Tri-G
    would have been entitled to prejudgment interest on equitable
    grounds.
    Tri-G also seeks Apostjudgment@ interest for the period
    from June 1, 1987, through February 28, 2002, when judgment
    against Burke was entered. Before the appellate court, Tri-G
    relied on section 2B1303 of the Code of Civil Procedure, which
    provides in relevant part:
    -27-
    AJudgments recovered in any court shall draw
    interest at the rate of 9% per annum from the date of
    the judgment until satisfied ***. When judgment is
    entered upon any award, report, or verdict, interest
    shall be computed at the above rate, from the time
    when made or rendered to the time of entering
    judgment upon the same, and included in the
    judgment.@ 735 ILCS 5/2B1303 (West 2002).
    Tri-G argues that, because Burke failed to obtain a judgment
    against Elgin Federal in 1987, Burke is responsible for
    Apostjudgment@ interest, extending from June 1, 1987, when
    the judgment should have been entered, through February 28,
    2002, when Tri-G finally recovered on its allegations against
    Elgin Federal.
    Relying on the plain language of the statute, the appellate
    court rejected Tri-G=s purported category of Apostjudgment@
    interest. ASection 2B1303 speaks of judgments recovered, not
    judgments that should have been recovered. Tri-G recovered
    no judgment in this action until February 28, 2002, and
    therefore this is the date by which interest will be 
    reckoned.@ 353 Ill. App. 3d at 224
    .
    Before this court, Tri-G concedes that its claim to what it
    characterizes as Apostjudgment@ interest Ais not based directly@
    on section 2B1303. Rather, according to Tri-G:
    ACombining section [2B1303] and the principle that the
    judgment in a legal malpractice case is supposed to
    give the plaintiff >those sums which would have been
    recovered if the underlying suit had been successfully
    prosecuted,= *** Tri-G is entitled to additional
    compensatory damages equal to the amount of post-
    judgment interest on a judgment that would have been
    entered in June 1987 but for Burke=s negligence.@
    Tri-G now contends that the appellate court=s rejection of its
    claim to Apostjudgment@ interest Acompletely ignored the
    principle that the prevailing plaintiff in a legal malpractice case
    is entitled to everything it would have recovered if the
    underlying action had been successfully prosecuted.@
    This argument is erroneous. A judgment is the final
    determination of a court upon matters submitted to it in an
    -28-
    action or proceeding. A judgment is the judicial act of the court.
    In contrast, the right to judgment interest, apart from contract,
    Adoes not emanate from the controversy, or from the judgment,
    or from anything of a judicial nature. *** The recovery of
    interest in this State, not contracted for, finds its only authority
    in the statute. It is purely statutory.@ Blakeslee=s Storage
    Warehouses, Inc. v. City of Chicago, 
    369 Ill. 480
    , 482-83
    (1938).
    In this case, as the appellate court reasoned, section
    2B1303 refers only to judgments recovered, not to judgments
    that should have been recovered. We must give effect to this
    statutory provision by giving its language its plain and ordinary
    meaning. Hall v. Henn, 
    208 Ill. 2d 325
    , 330 (2003). Therefore,
    we agree with the appellate court that the focus of this claim
    should not be June 1, 1987, the date of a purported,
    hypothetical judgment against Elgin Federal, but rather
    February 28, 2002, the date when the judgment against Burke
    was entered, which was the only judgment rendered in this
    legal malpractice action.
    Because February 28, 2002, is the operative date, the
    appellate court reasoned that the interest Tri-G was seeking
    was actually entirely prejudgment interest, but of two types. In
    the appellate court=s view, the interest covering the period from
    June 1978 to June 1, 1987, was sought from Burke only
    derivatively, its ultimate basis being Elgin Federal=s
    wrongdoing. By contrast, the interest for the period from June
    1, 1987, to February 28, 2002, was claimed directly on the
    basis of Burke=s own negligent 
    misconduct. 353 Ill. App. 3d at 224
    .
    In analyzing and rejecting Tri-G=s claims for this interest,
    the appellate court looked to the nature of the claims for which
    interest was sought. With respect to later period, ending
    February 28, 2002, the appellate court reasoned that the
    request for interest failed because the claim against Burke was
    one at law and our state does not allow nonstatutory
    prejudgment interest on any type of claim at law. We agree.
    As we have already suggested, A[i]t is well settled that
    interest is not recoverable absent a statute or agreement
    providing for it.@ 
    Alphin, 82 Ill. 2d at 576
    . An exception to this
    -29-
    rule exists in equity. AIn chancery proceedings, the allowance
    of interest lies within the sound discretion of the judge and is
    allowed where warranted by equitable considerations and
    disallowed if such an award would not comport with justice and
    equity.@ (Emphasis added.) 
    Alphin, 82 Ill. 2d at 579
    ; accord
    Groome v. Freyn Engineering Co., 
    374 Ill. 113
    , 131 (1940)
    (observing: AIn a proper case, equitable considerations permit a
    court of equity to allow or disallow interest as the equities of the
    case may demand@). The availability of equitable relief is not
    necessarily precluded merely because a case is heard in the
    law division of a circuit court, nor is equitable relief
    automatically awarded merely because a case is proceeding in
    the chancery division of a circuit court. Rather, it is the
    substance of the claim that determines the appropriate relief
    and the nature of the court. Continental Casualty Co., 286 Ill.
    App. 3d at 579; see, e.g., In re Estate of Wernick, 
    127 Ill. 2d 61
    , 86-87 (1989) (referring to Aproceedings sounding in
    equity@). There is no question, however, that this legal
    malpractice action was entirely an action at law. See 65A
    C.J.S. Negligence '649 (2000) (stating that negligence is an
    action at law); Cook v. Gould, 
    109 Ill. App. 3d 311
    , 314 (1982)
    (stating that legal malpractice action is no different than cause
    of action for ordinary nonprofessional negligence). AIllinois
    courts have declined to apply the rule governing equitable
    awards of prejudgment interest to cases at law,
    notwithstanding that an injured party who is eventually
    compensated may suffer detriment from the inability to use the
    money from the date of loss to the date of compensation.@
    Continental Casualty 
    Co., 286 Ill. App. 3d at 579
    (collecting
    cases). Prejudgment interest in therefore not available for the
    period ending February 28, 2002.
    In our view, the same rationale is applicable to the earlier
    period between June 1978 and June 1, 1987. The interest for
    that period was ultimately linked to the February 28, 2002,
    judgment and is therefore based on the legal malpractice claim
    against Burke, just as the interest for the latter period was.
    Because prejudgment interest is not available in legal
    malpractice cases, Tri-G=s claim for prejudgment interest for
    this earlier period was also properly rejected.
    -30-
    In reaching this conclusion, we are aware that our analysis
    on this point differs from that of the appellate court. It is
    axiomatic, however, that we are not bound by the appellate
    court=s reasoning and may affirm for any basis presented in the
    record. Raintree Homes, Inc. v. Village of Long Grove, 
    209 Ill. 2d
    248, 261 (2004).
    The final issue in this case, and the only one about which
    the members of the appellate court were in disagreement,
    concerns the jury=s decision to include in its judgment against
    Burke the sum of $1,168,775 to compensate Tri-G for lost
    punitive damages Tri-G would have received in the underlying
    action against Elgin Federal but for the Burke=s legal
    malpractice. As noted earlier in this opinion, Burke contended
    in the appellate court that allowing recovery of punitive
    damages was expressly prohibited by 2B1115 of the Code of
    Civil Procedure, which provides that A[i]n all cases, whether in
    tort, contract or otherwise, in which the plaintiff seeks damages
    by reason of legal, medical, hospital, or other healing art
    malpractice, no punitive, exemplary, vindictive or aggravated
    damages shall be allowed.@ 735 ILCS 5/2B1115 (West 2002).
    The appellate court rejected Burke=s position, over the
    dissent of one justice. It viewed Tri-G=s lost punitive damages
    in the underlying case as an element of compensatory
    damages in the malpractice action, and held that such
    compensatory damages were not prohibited by Code of Civil
    Procedure section 
    2B1115. 353 Ill. App. 3d at 226-32
    . In
    reaching this result, the appellate court acknowledged the
    divergence of authority on this issue. The court recognized that
    courts in New York and California have held, based on public
    policy, that lost punitive damages are not recoverable in a legal
    malpractice 
    action. 353 Ill. App. 3d at 226-27
    (citing Ferguson
    v. Lieff, Cabraser, Heimann & Bernstein, LLP, 
    30 Cal. 4th 1037
    , 
    69 P.3d 965
    , 
    135 Cal. Rptr. 2d 46
    (2003), and
    Summerville v. Lipsig, 
    270 A.D.2d 213
    , 
    704 N.Y.S.2d 598
    (2000)).
    The appellate court discussed Ferguson, which presented
    several reasons for prohibiting recovery of lost punitive
    damages in legal malpractice actions. First, according to
    Ferguson, allowing such recovery would defeat the punitive
    -31-
    and deterrent purposes of punitive damages because the
    negligent attorney in the legal malpractice action is usually not
    the tortfeasor who committed the intentional or malicious acts
    that gave rise to the punitive damages claim in the underlying
    case. Therefore, imposing liability for lost punitive damages on
    the negligent attorney would neither punish the culpable
    tortfeasor nor deter that tortfeasor and others from committing
    similar wrongful acts in the future. Also, the amount of the
    award bears no relationship to the gravity of the negligent
    attorney=s misconduct or the attorney=s 
    wealth. 353 Ill. App. 3d at 227
    , discussing 
    Ferguson, 30 Cal. 4th at 1046-48
    , 69 P.3d
    at 
    970-71, 135 Cal. Rptr. 2d at 52-54
    ; see 
    Summerville, 270 A.D.2d at 213
    , 704 N.Y.S.2d at 599.
    Second, according to Ferguson, allowing recovery of lost
    punitive damages in legal malpractice actions would violate
    public policy against speculative damages for several reasons.
    Compensatory damages in a legal malpractice action requires
    an objective determination. However, an award of punitive
    damages is an expression of the jury=s moral condemnation
    and thus necessarily requires a moral judgment. Because
    moral judgments are inherently subjective, a jury assessing
    damages in a legal malpractice action cannot objectively
    determine whether punitive damages would have been
    awarded or the proper amount of those damages with any legal
    certainty. Also, the standards of proof for compensatory and
    punitive damages differ. Accordingly, the standard of proof for
    lost punitive damages would be a standard in a standard. This
    pragmatic difficulty is so complex that it militates against
    recovery or such 
    damages. 353 Ill. App. 3d at 227
    , discussing
    
    Ferguson, 30 Cal. 4th at 1048-49
    , 69 P.3d at 971-72, 135 Cal.
    Rptr. 2d at 54-55.
    Lastly, as the Ferguson court discussed, allowing
    malpractice plaintiffs to recover lost punitive damages would
    exact a societal cost. Exposing attorneys to such liability would
    likely increase legal malpractice premiums, cause insurers to
    exclude coverage for these damages, or discourage insurers
    from providing professional liability insurance in the jurisdiction.
    This financial burden on attorneys would probably make it
    more difficult and costly for consumers to obtain legal services,
    -32-
    or to obtain recovery for legal 
    malpractice. 353 Ill. App. 3d at 227
    , discussing 
    Ferguson, 30 Cal. 4th at 1050
    , 69 P.3d at 972-
    
    73, 135 Cal. Rptr. 2d at 55-56
    . Further, there is no compelling
    reason to take these risks. The recovery of lost punitive
    damages is not necessary to make a successful plaintiff whole
    in a legal malpractice action. Rather, a plaintiff is made whole
    by compensatory damages and punitive damages constitute an
    undeserved 
    windfall. 353 Ill. App. 3d at 227
    , discussing
    
    Ferguson, 30 Cal. 4th at 1050
    -51, 69 P.3d at 973, 135 Cal.
    Rptr. 2d at 56.
    The appellate court recognized that the view taken by the
    courts of California and New York is not universally accepted.
    Courts in several jurisdictions have held that a plaintiff in a
    legal malpractice action may recover as compensatory
    damages those damages that the plaintiff would have been
    awarded as punitive damages in the underlying action. 353 Ill.
    App. 3d at 226-27 (citing Jacobsen v. Oliver, 
    201 F. Supp. 2d 93
    (D.C. 2002) (interpreting District of Columbia law), Haberer
    v. Rice, 
    511 N.W.2d 279
    (S.D. 1994), Scognamillo v. Olsen,
    
    795 P.2d 1357
    (Colo. App. 1990), Elliott v. Videan, 
    164 Ariz. 113
    , 
    791 P.2d 639
    (1989), and Hunt v. Dresie, 
    241 Kan. 647
    ,
    
    740 P.2d 1046
    (1987)). Rather than focusing on the purpose
    behind punitive damages, these courts have focused on the
    concept of compensatory 
    damages. 353 Ill. App. 3d at 227
    -28.
    Compensatory damages for negligence are those which
    flow directly and proximately from a defendant=s breach of duty
    owed to a plaintiff. In a legal malpractice action based on an
    attorney=s breach of duty to represent the client in a prior case,
    it is the defendant attorney=s conduct and its consequences
    which govern the analysis of damages. See 
    Scognamillo, 795 P.2d at 1361
    . AIf an attorney=s negligence is the cause of
    dismissal of the underlying claim, the proper measure of
    damages is all compensatory and punitive damages awarded
    by the jury in the trial of the case within a case.@ 
    Elliott, 164 Ariz. at 119-20
    , 791 P.2d at 645-46. From the vantage point of
    the underlying case, some of a plaintiff=s damages might be
    designated Apunitive@ damages. However, from the vantage
    point of the legal malpractice action, all the damages are
    simply those which proximately resulted from the attorney=s
    -33-
    negligence. Indeed, they are no longer properly called punitive
    damages. 
    Hunt, 241 Kan. at 661
    , 740 P.2d at 1057. Thus, the
    punitive damages assessed in the underlying case Aare part
    and parcel@ of the damages which the plaintiff suffered as a
    result of the defendant=s alleged negligence. See 
    Haberer, 511 N.W.2d at 288
    ; 
    Scognamillo, 795 P.2d at 1361
    .
    These courts have also reasoned that allowance of lost
    punitive damages in a legal malpractice action furthers the goal
    of deterrence: AAttorneys who appreciate that they will be liable
    in malpractice actions for >lost punitives= will be motivated to
    exercise reasonable care in investigating or defending punitive
    damages claims.@ 
    Jacobsen, 201 F. Supp. 2d at 101-02
    , citing
    
    Hunt, 241 Kan. at 661
    , 740 P.2d at 1057.
    After discussing the two conflicting approaches, the
    appellate court adopted the view of the latter group of
    jurisdictions and concluded that it should regard lost punitive
    damages in the underlying case as compensatory damages in
    the malpractice case. In its view,
    Athe proper focus of our analysis [is] what would make
    the plaintiff whole with respect to the defendant
    attorney=s negligence. When, as in this case, a jury has
    determined that the plaintiff would have been entitled to
    punitive damages but for the negligence of the
    attorney, then such damages must be recoverable in
    order for the plaintiff to be made whole. We note that
    this result is consistent with the general principle in this
    state that >[a] legal malpractice plaintiff is entitled to
    recover those sums which would have been recovered
    if the underlying suit had been successfully
    prosecuted.= Weisman v. Schiller, Ducanto & Fleck,
    
    314 Ill. App. 3d 577
    , 580 (2000). Based on (1) our view
    of lost punitive damages as compensatory and (2) the
    fact that such damages are not imposed for the
    purpose of punishing the attorney who commits
    malpractice, we hold that section 2B1115 does not bar
    the recovery of lost punitive damages in a legal
    malpractice 
    case.@ 353 Ill. App. 3d at 228-29
    .
    -34-
    The appellate court lastly concluded that the evidence adduced
    at trial justified the award of punitive 
    damages. 353 Ill. App. 3d at 232
    .
    The dissenting justice, who rejected the majority=s
    approach, observed that punitive damages are not awarded for
    compensation and have nothing to do with a plaintiff=s loss or
    making the plaintiff whole. Rather, the purpose of punitive
    damages is similar to a criminal penalty, i.e., to punish a
    defendant for wrongdoing and to deter that defendant and
    others from committing similar misconduct in the future. Also,
    section 2B1115 of the Code of Civil Procedure (735 ILCS
    5/2B1115 (West 2002)) bars recovery of punitive damages in a
    legal malpractice action. The dissent viewed the appellate court
    majority as attempting to Acircumvent@ these limitations by
    Amischaracterizing@ lost punitive damages as compensatory
    
    damages. 353 Ill. App. 3d at 233
    -34 (Gilleran Johnson, J.,
    concurring in part and dissenting in part). The dissent also
    observed: AIt is inconsistent with Illinois public policy to transfer
    punishment and deterrence intended for a malicious,
    fraudulent, or deliberately oppressive wrongdoer to another
    who has not acted with such a wanton disregard.@ 
    353 Ill. App. 3d
    at 234 (Gilleran Johnson, J., concurring in part and
    dissenting in part). Based on these considerations, the
    dissenting justice concluded that Aa plaintiff may not recover
    punitive damages lost by reason of attorney 
    malpractice.@ 353 Ill. App. 3d at 236
    (Gilleran Johnson, J., concurring in part and
    dissenting in part).
    Burke assigns error to the reasoning and conclusion of the
    appellate court majority on this issue, and points to the dissent
    as Acogent and correct, and ably describ[ing] why the majority
    was wrong and why this Court should reverse the award of
    underlying punitive damages.@ Supported by amici, Burke
    focuses on the nature of punitive damages. It is well
    established that such damages are not awarded as
    compensation to a plaintiff. Rather, they serve to punish the
    defendant and to deter the defendant and others from
    committing similar misconduct in the future. Misconduct for
    which punitive damages are imposed must be outrageous,
    because it is committed with an evil motive or a reckless
    -35-
    indifference to the rights of others. See Loitz v. Remington
    Arms Co., 
    138 Ill. 2d 404
    , 414-16 (1990) (collecting
    authorities). Indeed, the punitive and deterrent function of
    punitive damages is similar to that of a criminal penalty.
    ABecause of their penal nature, punitive damages are not
    favored in the law, and the courts must take caution to see that
    punitive damages are not improperly or unwisely awarded.@
    Kelsay v. Motorola, Inc., 
    74 Ill. 2d 172
    , 188 (1978).
    Burke correctly observes that it was not a wanton or
    malicious wrongdoer. Elgin Federal was. Elgin Federal,
    however, will bear none of the consequences of its
    wrongdoing. If the punitive damage award is allowed to stand,
    those consequences will fall entirely on Burke.
    Burke argues that punitive damages imposed against a
    wrongdoer in the underlying case do not become
    compensatory when paid by the attorney in the legal
    malpractice action. In Burke=s view, shifting the punishment
    from the wrongdoer in the underlying case to the law firm in the
    legal malpractice action does not make the punishment less
    punitive. Rather, Burke continues, it makes the punishment
    unjust because it is inflicted on the wrong party.
    In support of its argument, Burke notes the following
    comment from the Restatement (Third) of the Law Governing
    Lawyers:
    AA few decisions allow a plaintiff to recover from a
    lawyer punitive damages that would have been
    recovered from the defendant in an underlying action
    but for the lawyer=s misconduct. However, such
    recovery is not required by the punitive and deterrent
    purposes of punitive damages. Collecting punitive
    damages from the lawyer will neither punish nor deter
    the original tortfeasor and calls for a speculative
    reconstruction of a hypothetical jury=s reaction.@
    Restatement (Third) of the Law Governing Lawyers
    '53, Comment h, at 393 (2000).
    According to Burke: AA lost opportunity to punish does not
    become >compensatory= and should not be recoverable from
    someone other than the person for whom the punishment was
    intended.@
    -36-
    Burke further cites section 2B1115 of the Code of Civil
    Procedure, which bars recovery of punitive damages in a legal
    malpractice action. 735 ILCS 5/2B1115 (West 2002). Burke
    reasons that if punitive damages cannot, by statute, be
    imposed on a law firm in a legal malpractice action for its own
    negligence, it follows that punitive damages cannot be imposed
    on the firm for the intentional or reckless wrongdoing of
    someone else. Burke contends that the appellate court erred
    Aby shifting Elgin Federal=s punishment onto Burke.@
    Burke next contends that the award of lost punitive
    damages that would have been imposed against Elgin Federal
    in the underlying case Agrants Tri-G a windfall@ in this legal
    malpractice action. Burke notes this court=s recognition of the
    effect of punitive damages imposed against a defendant on the
    plaintiff=s compensation. See Mattyasovszky v. West Towns
    Bus Co., 6
    1 Ill. 2d
    31, 36 (1975) (AThe fine that is imposed
    upon the defendant in a criminal case goes to the State. But in
    a civil case the exaction taken from the defendant, under the
    label of exemplary damages, becomes a windfall for the
    plaintiff@). According to Burke, granting a legal malpractice
    plaintiff the punitive damages it would have recovered in the
    underlying case Ais not a >make-whole,= compensatory
    recovery. It is a windfall.@
    In further support of its position, Burke urges this court to
    adopt what it considers to be the Awell-reasoned@ rationale of
    the above-mentioned Ferguson and Summerville decisions.
    Burke also criticizes the cases that allow recovery of lost
    punitive damages in the underlying case as compensatory
    damages in the legal malpractice action. In Burke=s view, the
    case law allowing such recovery is wrongfully decided, or at
    least factually distinguishable.
    Finally, Burke warns that allowing recovery for lost punitive
    damages in the underlying case as compensatory damages in
    a legal malpractice action will necessarily result in increased
    professional liability insurance premiums or denials of
    coverage. According to Burke, attorneys representing plaintiffs
    will be encouraged to seek punitive damages in cases where
    they would not have done so, motivated by a fear that Atheir
    -37-
    failure to make the claim could be the seed from which a
    malpractice claim might grow.@
    Whether a plaintiff in a legal malpractice action may
    recover as an element of damages punitive damages he or she
    would have recovered in the underlying action but for the
    attorney=s professional negligence is a question of first
    impression in Illinois. It is a question on which reasonable
    minds can certainly disagree. The dissent in the appellate
    court, the dissent which follows in this case, and the split
    among courts from other jurisdictions illustrates that sound
    arguments can be made for both sides of the issue. In the end,
    however, we have concluded that the approach taken by the
    courts of California and New York and urged by Burke in this
    case represents the sounder view. Lost punitive damages are
    not recoverable in a subsequent action for legal malpractice.
    Disallowing lost punitive damages means that plaintiffs in
    legal malpractice actions may not receive as much money as
    they might have if the underlying action had been handled
    properly. Compensating plaintiffs, however, is but one of
    several factors that must be balanced in assessing whether
    lost punitive damages should be recognized in legal
    malpractice actions. There is no reason in logic or the law why
    it should be given preeminent effect where, as here, the jury
    has already awarded full compensation to the plaintiff for all the
    damages it actually sustained.
    Punitive, or exemplary, damages are not awarded as
    compensation, but serve instead to punish the offender and to
    deter that party and others from committing similar acts of
    wrongdoing in the future. Loitz v. Remington Arms Co., 
    138 Ill. 2d
    at 414. Allowing Tri-G to recover its lost punitive damages
    from Burke would not advance that policy in any way. To the
    contrary, by holding the firm liable for the intentional or willful
    and wanton misconduct of a third party, it tears the concept of
    punitive damages from its doctrinal moorings.
    Section 2B1115 of the Code of Civil Procedure (735 ILCS
    5/2B1115 (West 2002)) expressly bars recovery of punitive
    damages in a legal malpractice action. By characterizing lost
    punitive damages as Acompensatory,@ Tri-G is attempting to
    -38-
    evade reach of this statute. In our view, its efforts are ultimately
    unpersuasive. If the General Assembly has determined that
    lawyers cannot be compelled to pay punitive damages based
    on their own misconduct, as section 2B1115 decrees, it would
    be completely nonsensical to hold that they can nevertheless
    be compelled to pay punitive damages attributable to the
    misconduct of others. Any construction of the law that permits
    such a result would be absurd and unjust. 1
    For the foregoing reasons, we reverse that portion of the
    appellate court=s judgment which upheld the award of
    $1,168,775 in lost punitive damages to Tri-G. The judgment in
    favor of Tri-G and against Burke is hereby reduced by that
    amount. We also reverse the appellate court=s judgment to the
    extent that it sustained the full $1,168,775 in compensatory
    damages awarded to the company by the jury. Pursuant to
    1
    Contrary to the claim made by Justice Freeman in his separate
    opinion, this characterization is not meant to castigate him or anyone
    else on the court. It is simply an application of the Ano absurdity@ rule
    for statutory construction. The rule has been formulated in various
    ways, but essentially it holds that statutes should be construed in a
    manner that avoids absurd, unreasonable, unjust or inconvenient
    results. See, e.g., In re Mary Ann P., 
    202 Ill. 2d 393
    , 406 (2002). Our
    court invokes the rule frequently. It appeared in In re Donald A.G.,
    No. 100965 (April 19, 2006), an opinion we just filed, and is regularly
    cited by this court and our appellate court. Justice Freeman, himself,
    has discussed it in cases he has authored. See, e.g., Antunes v.
    Sookhakitch, 
    146 Ill. 2d 477
    , 485-488 (1992).
    -39-
    Supreme Court Rule 366(a)(6) (155 Ill. 2d R. 366(a)(5)), we
    enter a remittitur of $420,213 on the compensatory damage
    award and affirm the judgment entered in favor of Tri-G for the
    reduced amount of $748,562. If Tri-G does not consent to the
    entry of a remittitur within 21 days of the filing of this opinion, or
    any further period in which the mandate is stayed, the cause
    will be remanded to the circuit court of McHenry County for a
    new trial solely on the issue of damages. In all other respects,
    the judgment of the appellate court is affirmed.
    Appellate court judgment
    affirmed in part and reversed in part;
    circuit court judgment
    affirmed in part and reversed in part;
    remittitur entered.
    JUSTICE FREEMAN, concurring in part and dissenting in
    part:
    My colleagues in the majority hold that lost punitive
    damages are not recoverable in a legal malpractice action. See
    slip op. at 28-36. The majority offers insufficient justification for
    allowing legal malpractice plaintiffs to be candidly
    undercompensated. Further, the majority disregards the
    fundamental distinction between the nature of the damages
    that would have been awarded to Tri-G in the underlying case
    and the nature of the damages that were actually awarded to
    Tri-G in this legal malpractice action. Accordingly, I dissent
    specifically from this portion of the court=s opinion.
    After recognizing that this Ais a question on which
    reasonable minds can certainly disagree,@ and Athat sound
    arguments can be made for both sides of the issue,@ this court
    now holds: ALost punitive damages are not recoverable in a
    subsequent action for legal malpractice.@ Slip op. at 35. The
    court then frankly concedes: ADisallowing lost punitive
    damages means that plaintiffs in legal malpractice actions may
    not receive as much money as they might have if the
    underlying action had been handled properly.@ Slip op. at 35.
    After making this candid admission, my colleagues in the
    -40-
    majority attempt to justify this gross injustice by positing:
    ACompensating plaintiffs, however, is but one of several factors
    that must be balanced in assessing whether lost punitive
    damages should be recognized in legal malpractice actions.@
    Slip op. at 35.
    This declaration leads the reader to anticipate a thorough
    discussion of the reasons why this court is going to allow legal
    malpractice plaintiffs to be candidly undercompensated.
    However, the court points to only one reason for its conclusion:
    the attorney in the legal malpractice action was not the
    wrongdoer in the underlying case. I cannot accept this
    reasoning.
    A bare majority of this court accepts Burke=s emphasis on
    the nature of punitive damages and relies solely thereon in
    bluntly denying full compensation to legal malpractice plaintiffs.
    However, I consider reference to the nature of compensatory
    damages to be more helpful in resolving this case. An award of
    compensatory damages is intended to compensate an injured
    person for the wrong or injury that person sustained. The goal
    is to make the injured party whole and restore the injured party,
    as nearly as reasonably possible, to the position in which he or
    she would have held absent the injury. See Harris v. Peters,
    
    274 Ill. App. 3d 206
    , 207 (1995); Rodrian v. Seiber, 194 Ill.
    App. 3d 504, 508-09 (1990); Roark v. Musgrave, 
    41 Ill. App. 3d 1008
    , 1011 (1976); 25 C.J.S. Damages '21 (2002). In this
    case, the appellate court reasoned:
    AOf course, a punitive damages award was not
    imposed against [Burke]. The verdict form designates
    the $2,337,550 simply as >damages,= and one of the
    special interrogatories specifies what amount of that
    award represents punitive damages that Tri-G would
    have recovered but for [Burke=s] negligence. Thus, the
    judgment against [Burke] is designed to compensate,
    not punish.@ 
    353 Ill. App. 3d
    at 229.
    I agree. I view the punitive damages that would have been
    imposed against Elgin Federal in the underlying case as an
    element of Tri-G=s compensatory damages in this legal
    malpractice action.
    -41-
    It is indisputable that Burke=s negligence deprived Tri-G of
    a punitive damages award and that Tri-G will not receive all
    sums to which it was entitled in the underlying case unless
    Burke is directed to pay an amount equal to the underlying
    punitive damages. AThe legal malpractice action places the
    plaintiff in the same position he or she would have occupied
    but for the attorney=s negligence.@ Bloome v. Wiseman,
    Shaikewitz, McGivern, Wahl, Flavin & Hesi, P.C., 
    279 Ill. App. 3d
    469, 478 (1996). Thus, a plaintiff=s damages in a legal
    malpractice action are limited to the actual amount the plaintiff
    would have recovered had he or she been successful in the
    underlying case. 
    Eastman, 188 Ill. 2d at 412
    ; see Weisman v.
    Schiller, Ducanto & Fleck, 
    314 Ill. App. 3d 577
    , 580 (2000) (AA
    legal malpractice plaintiff is entitled to recover those sums
    which would have been recovered if the underlying suit had
    been successfully prosecuted.@ In this case, A[Burke] simply
    has been called to account for the full consequences of its
    professional negligence.@ 
    353 Ill. App. 3d
    at 229.
    Further, this court relies on section 2B1115 of the Code of
    Civil Procedure, which bars recovery of punitive damages in a
    legal malpractice action. 735 ILCS 5/2B1115 (West 2002). My
    colleagues in the majority explain:
    ABy characterizing lost punitive damages as
    >compensatory,= Tri-G is attempting to evade reach of
    this statute. In our view, its efforts are ultimately
    unpersuasive. If the General Assembly has determined
    that lawyers cannot be compelled to pay punitive
    damages based on their own misconduct, as section
    2B1115 decrees, it would be completely nonsensical to
    hold that they can nevertheless be compelled to pay
    punitive damages attributable to the misconduct of
    others. Any construction of the law that permits such a
    result would be absurd and unjust.@ Slip op. at 36.
    My colleagues in the majority misperceive the nature of the
    damages that the jury awarded in this legal malpractice action.
    As revealed by a special interrogatory, the jury in this legal
    malpractice action awarded Tri-G $1,168,775 in compensatory
    damages for lost punitive damages that would have been
    -42-
    imposed against Elgin Federal in the underlying case. The
    jury=s assessment of lost punitive damages was not a finding
    that Burke=s conduct was outrageously willful and wanton; it
    was a finding that Elgin Federal=s conduct was. Although
    Burke=s conduct was only negligent, it nevertheless caused Tri-
    G to lose its entire underlying claim. See Elliott v. Videan, 
    164 Ariz. 113
    , 119, 
    791 P.2d 639
    , 645 (1989). In this case, the
    appellate court reasoned as follows:
    A[A]s we noted above, a punitive damages award has
    not been imposed against any party to this dispute.
    Rather, [Burke] has been made to compensate Tri-G
    for the recovery, composed in part of punitive
    damages, that was denied it by [Burke=s] negligence.
    Elgin Federal, the party that should have been
    punished, was insulated by [Burke=s] negligence, and
    now [Burke] is being held liable for the full
    consequences of that negligence, in accord with the
    dictate that a legal malpractice plaintiff is entitled to
    whatever sums it would have recovered in the
    underlying action but for the malpractice. [Burke] is not
    being punished; it is being made to compensate.@ 
    353 Ill. App. 3d
    at 230.
    I agree with the appellate court=s view of the record. 2
    This court expressly adopts the rationale of the above-
    discussed Ferguson and Summerville decisions. Slip op. at 35.
    However, I view as better reasoned the decisions that allow the
    recovery of lost punitive damages in the underlying case as an
    element of compensatory damages in the legal malpractice
    2
    Parenthetically, the court correctly recognizes that this Ais a
    question on which reasonable minds can certainly disagree,@ and
    Athat sound arguments can be made for both sides of the issue.@ Slip
    op. at 35. It is curious that my colleagues in the majority
    subsequently castigate this viewpoint of Tri-G, shared by their
    dissenting colleagues, as Anonsensical@ and Aabsurd and unjust.@
    Slip op. at 36. The use of such rhetoric in this case is unfortunate
    and uncivil.
    -43-
    action. See Jacobsen v. Oliver, 
    201 F. Supp. 2d 93
    (D.C. 2002)
    (interpreting District of Columbia law); Haberer v. Rice, 
    511 N.W.2d 279
    (S.D. 1994); Scognamillo v. Olsen, 
    795 P.2d 1357
    (Colo. App. 1990); Elliott v. Videan, 
    164 Ariz. 113
    , 
    791 P.2d 639
    (1989); Hunt v. Dresie, 
    241 Kan. 647
    , 
    740 P.2d 1046
    (1987).
    These cases are in accord with a fundamental principle of
    tort law. AThe general rule of damages in a tort action is that
    >the wrongdoer is liable for all injuries resulting from the
    wrongful acts ***, provided the particular damages are the legal
    and natural consequences of the wrongful act imputed to the
    defendant, and are such as might reasonably have been
    anticipated.= @ Haudrich v. Howmedica, Inc., 
    169 Ill. 2d 525
    , 543
    (1996), quoting Siemieniec v. Lutheran General Hospital, 
    117 Ill. 2d 230
    , 259 (1987). I agree with the court in Jacobsen that
    Apermitting recovery of punitive damages as compensatory
    damages in a legal malpractice action is consistent with [this
    principle].@ 
    Jacobsen, 201 F. Supp. 2d at 102
    , citing Haymon v.
    Wilkerson, 
    535 A.2d 880
    , 885 (D.C. 1987) (AThe normal
    measure of tort damages is the amount which compensates
    the plaintiff for all of the damages proximately caused by the
    defendant=s negligence@). I agree with these cases that, from
    the vantage point of the legal malpractice action, all the
    damages are simply those which proximately resulted from the
    attorney=s negligence. Accordingly, the punitive damages
    assessed in the underlying case are included in the damages
    which the plaintiff suffered as a result of the defendant=s
    negligence. See, e.g., 
    Jacobsen, 201 F. Supp. 2d at 100-02
    ;
    
    Haberer, 511 N.W.2d at 288
    ; 
    Elliott, 164 Ariz. at 119-20
    , 791
    P.2d at 645-46. As the dissent in Ferguson correctly explained:
    AIn a malpractice action, punitive damages lost because of
    attorney error are not true punitive damages but are merely a
    measure of some of the injury resulting from the attorney=s
    malpractice. Thus, lost punitive damages are a form of
    compensatory damages.@ (Emphasis in original.) 
    Ferguson, 30 Cal. 4th at 1055
    , 69 P.3d at 
    976, 135 Cal. Rptr. 2d at 59
    (Kennard, J., concurring and dissenting, joined by Werdegar
    and Moreno, JJ.).
    -44-
    To be sure, the divergence of opinion in the appellate
    court=s decision as well as in the above-cited cases from
    foreign jurisdictions reveals a A[r]ough equality in the
    persuasiveness of the competing arguments.@ C. Thatcher,
    Recovery of ALost Punitive Damages@ as ACompensatory
    Damages@ in Legal Malpractice Actions: Transference of
    Liability or Transformation of Character?, 
    49 S.D. L
    . Rev. 1, 3-4
    (2003). However, after careful consideration, I would adopt the
    reasoning of the courts that have allowed recovery of lost
    punitive damages in the underlying case as compensatory
    damages in the legal malpractice action. As a learned
    commentator recently explained:
    AEven if the competing arguments are considered to
    be about equally persuasive, it does not seem
    appropriate *** to adopt an exception to the general
    rule entitling plaintiff-clients in legal malpractice actions
    to recover the full value of their lost claim, including any
    punitive damages they would have collected but for the
    defendant-lawyer=s negligence. *** [T]he punitive
    damages portion of the award the client should have
    collected from the original tortfeasor is legitimately
    transformed into a portion of the compensatory
    damages the client must be able to recover from the
    negligent lawyer in order to make the client whole and
    vindicate the client=s expectation interest.@ (Emphasis
    omitted.) 
    49 S.D. L
    . Rev. at 30.
    I agree with the appellate court that section 2B1115 of the
    Code of Civil Procedure does not bar recovery of lost punitive
    damages in a legal malpractice action.
    Although I would have upheld the award of lost punitive
    damages as a component of Tri-G=s compensatory damages in
    the legal malpractice action, I note that a remittitur would have
    been required. The jury assessed Tri-G=s compensatory and
    punitive damages in the underlying case in the amount of
    $1,168,775 for each component, a ratio of one-to-one. Earlier
    in this opinion, this court entered a remittitur of $420,213 in
    compensatory damages, reducing the compensatory damages
    award to $748,562. Consequently, to maintain the jury=s one-
    -45-
    to-one ratio of compensatory and punitive damages, I would
    have entered a remittitur of $420,213 in punitive damages,
    thereby reducing the punitive damages award to $748,562.
    Therefore, in my view, the total amount remitted should be
    $840,426, thereby reducing the total amount of Tri-G=s award
    to $1,497,124. See 155 Ill. 2d R. 366(a)(5).
    Lastly, I agree with the court=s conclusions regarding the
    following issues. The trial court=s decision to allow Tri-G to
    recover damages for the 23 vacant lots and the 14 partially
    completed lots not specified in the 1981 complaint and the
    appellate court=s review of that decision did not deprive Burke
    of procedural due process. Slip op. at 15-19. The evidence
    supported the award of lost profits on the 14 partially
    completed lots. Slip op. at 19-21. The jury=s award of
    $1,168,775 was excessive and required a remittitur, thereby
    reducing Tri-G=s compensatory damages award to $748,562.
    Slip op. at 21-25. Also, the lower courts correctly rejected Tri-
    G=s claim for judgment interest. Slip op. at 25-28. Indeed, I
    embrace the court=s analysis of these issues as though it were
    my own.
    For the foregoing reasons, I concur in part and dissent in
    part.
    JUSTICES McMORROW and FITZGERALD join in this
    partial concurrence and partial dissent.
    -46-