-
Mr. Justice Dunn delivered the opinion of the court:
On February 19, 1906, the Globe Brewing Company bought of the American Malting Company 15,000 bushels of malt at fifty-one cents a bushel, to be shipped as ordered during the season ending' December 31, 1906. This suit was brought by the Globe Brewing Company, the defendant in error, in the municipal court of Chicago, to recover damages for a failure to deliver 3974 bushels of malt under the contract. The defendant, which is here the plaintiff in error, pleaded the general issue, and gave notice of a set-off of $1330.95 for malt delivered under the contract. A trial by the court without a jury resulted in a judgment in favor of the plaintiff in error for the amount of its set-off, which was not disputed. The Appellate Court reversed the judgment and rendered judgment in favor of the defendant in error for $20.21, being the amount claimed by it less the set-off of the plaintiff in error, and a writ of certiorari has been awarded to bring the record before us for feview.
The facts are undisputed, the evidence' being wholly documentary except the testimony of one witness, the manager of the defendant in error, who testified in its behalf. No propositions of law were submitted to the court and no objections were made to any evidence, but at the close of the evidence the plaintiff in error moved to strike out all the evidence and find the issues in its favor. Upon the hearing of such motion the court found the issues for the plaintiff in error. The defendant in error excepted, and thus the question was presented to the Appellate Court, and is presented here, as to whether there was any evidence tending to sustain the original cause of action declared on by the defendant in error.
In March, 1905, the Globe Brewing Company had purchased of the American Malting Company 40,000 bushels of malt at forty-nine cents a bushel, to be shipped as ordered by March 15, 1906. After the contract of February 19, 1906, the defendant in error continued to order and the plaintiff in error to deliver malt under the previous contract until August, 1906, when the delivery of the entire 40,000 bushels was completed, and no malt was ordered or delivered under the new contract until September, 1906. After that time deliveries were made under the new contract upon the orders' of the defendant in error, but on December 31, 1906, (the date of the expiration of the contract,) there remained undelivered 8900 bushels of the 15,-000 bushels sold,' and the price of malt had advanced to seventy-five cents or eighty cents a bushel. The defendant in error continued to order malt after the expiration of the contract, and during the months of January, February and March, 1907, the plaintiff in error delivered the malt at the price of fifty-one cents until March 14, 1907, when it notified defendant in error that, the contract having expired, the balance remaining undelivered had been canceled. The market price of malt was then between eighty-five and ninety cents a bushel and the quantity of malt remaining undelivered was 3974 bushels.
It is suggested on behalf of the defendant in error that the proviso in section 121 of the Practice act limits the right to issue a writ of certiorari in actions ex contractu and cases sounding in damages to cases in which the judgment, exclusive of costs, exceeds $1000. The judgment of the Appellate Court is usually for costs, only, and the proviso in section 121 refers, not to the judgment of that court, but to the judgment of the trial court.
After December 31, 1906, the plaintiff in error not having tendered the undelivered portion of the malt and the defendant in error not having demanded its delivery, the contract between them was by its terms at an end and neither party had any claim against the other for its breach. No contract existed between them, and their relation to one another was the same as if none ever had existed. If any liability afterward arose from one to the other it must have arisen out of an express or implied contract afterward made. It is the position of counsel for the defendant in error that upon the expiration of the thirty-first day of December without the delivery of the malt the plaintiff in error had an election to treat the contract as broken and sue for damages, or to waive the time limit fixed for delivery and continue to regard the contract in force. No such right of election existed. There had been no breach of the contract for which the plaintiff in error could sue, and it could not, at its option, continue in force a contract which had expired by its terms. The time of delivery was not a provision inserted for the benefit of either party, but was an essential part of the contract equally binding upon and for the benefit of either party. Neither party can be regarded as in default, because neither party had tendered performance. The fact that the plaintiff in error, after the expiration of the contract, filled an order of the defendant in error for malt at the price fixed in the contract has no tendency to prove a new contract to deliver the remainder of the malt. Such new contract must have a consideration. The time for the performance of the original contract having passed, the plaintiff in error was at liberty to refuse to deliver any more malt, or to deliver all that remained of the 15,000 bushels or such part as it saw fit. The plaintiff in error was not bound by the filling of any order, or the defendant in error by the giving of any order, beyond the amount of such order.
The doctrine of waiver has little or no application to the facts of this case and the doctrine-of estoppel none at all. In the case of executory contracts, if, after the time limited for performance, one party induces the other to go on and perform or accepts performance, the party so inducing or accepting performance will be held to performance on his part. Such is the character of the cases cited on behalf of the defendant in error, but such is not this case. The plaintiff in error did not induce the defendant in error to continue in the performance of its contract, and was under no obligation to continue performance on its part, at the -request of the defendant in error, longer than it saw fit.
The set-off of the plaintiff in error having been admitted in the trial court and there being no evidence to sustain the cause of action of the defendant in error, the judgment of the mtmicipal court was rightly rendered in favor of the plaintiff in error and the Appellate Court erred in reversing it. The judgment of the Appellate Court will therefore be reversed and that of the municipal court affirmed.
Judgment reversed.
Document Info
Citation Numbers: 247 Ill. 622, 93 N.E. 300
Judges: Dunn
Filed Date: 12/21/1910
Precedential Status: Precedential
Modified Date: 11/8/2024