Dallas v. Cips ( 2010 )


Menu:
  •                           NO. 4-09-0753             Filed 6/21/10
    IN THE APPELLATE COURT
    OF ILLINOIS
    FOURTH DISTRICT
    CHARLES DALLAS,                        )   Appeal from
    Plaintiff-Appellee and       )   Circuit Court of
    Cross-Appellant,             )   Sangamon County
    v.                           )   No. 09MR123
    AMEREN CIPS,                           )
    Defendant-Appellant and      )   Honorable
    Cross-Appellee.              )   Patrick W. Kelley,
    )   Judge Presiding.
    _________________________________________________________________
    PRESIDING JUSTICE MYERSCOUGH delivered the opinion of
    the court:
    Defendant, Ameren CIPS, appeals an order of the circuit
    court entering judgment for plaintiff, Charles Dallas, pursuant
    to an application for entry of judgment filed by plaintiff under
    section 19(g) of the Workers' Compensation Act (Act) (820 ILCS
    305/19(g) (West 2008)).   Plaintiff cross-appeals, seeking costs
    and attorney fees on appeal.   For the reasons that follow, we
    affirm the circuit court and deny plaintiff's request for costs
    and attorney fees on appeal.
    I. BACKGROUND
    On December 14, 1998, plaintiff suffered an injury to
    his back while working for defendant.     On June 24, 2004, follow-
    ing a hearing, an arbitrator issued a decision granting plaintiff
    benefits under the Act.
    The arbitrator found plaintiff had a compensable injury
    that resulted in two lumbar surgeries.   Permanent restrictions
    placed on plaintiff precluded him from returning to his work with
    defendant as a lineman or his previous work as a farm laborer.
    Although the arbitrator found plaintiff did not meet his burden
    of proof in establishing permanent total disability, plaintiff
    did qualify for a wage differential (permanent wage loss) under
    section 8(d)(1) of the Act (820 ILCS 305/8(d)(1) (West 2002)).
    Specifically, the arbitrator made the following finding on the
    disputed issue of the nature and extent of the injury:
    "It is found [plaintiff] has sustained
    his burden of proof in establishing entitle-
    ment to a permanent wage loss under [s]ection
    8(d)(1) of the Act as of [the] date of maxi-
    mum medical improvement, January 9, 2003.
    This wage differential of $465.67 begins as
    of January 9, 2003[,] and shall apply as long
    as the disability lasts."
    The arbitrator ordered defendant to pay plaintiff temporary total
    disability benefits of $811.94 per week for 177 4/7 weeks (August
    12, 1999, through January 9, 2003).   The arbitrator also ordered
    defendant to pay plaintiff as follows:
    "the sum of $456.67 [sic] per week for a
    further period of 68 6/7 weeks, as provided
    in section 8(d)(1) of the Act because the
    - 2 -
    injuries sustained caused [w]age loss, lim-
    ited to the maximum PPD rate as set forth
    above of $465.67, from 01/09/03 through the
    date of trial, and ongoing thereafter for the
    duration of the disability." (Emphasis in
    original.)
    Neither party filed a petition for review of the arbitrator's
    decision.    The arbitrator's decision, therefore, became the
    decision of the Illinois Workers' Compensation Commission (Com-
    mission).    See 820 ILCS 305/19(b) (West 2002) (unless a petition
    for review is filed within 30 days, the arbitrator's decision
    shall become the decision of the Commission and, absent fraud,
    shall be conclusive).    (For the sake of clarity, this court will,
    like the parties, continue to refer to the decision as the
    arbitrator's decision.)
    On March 25, 2009, plaintiff filed in the circuit court
    an application for entry of judgment pursuant to section 19(g) of
    the Act (820 ILCS 305/19(g) (West 2008)).    In the application for
    entry of judgment, plaintiff asserted that no review of the
    arbitrator's decision was pending and the time for review of the
    arbitrator's decision had passed.    Plaintiff also alleged defen-
    dant was "out of time to challenge the arbitrator's decision or
    pursue any action to assert the disability of the employee has
    subsequently recurred, increased, diminished, or ended."
    - 3 -
    Plaintiff further alleged that defendant paid the
    weekly wage-differential benefits to plaintiff for several years
    in accordance with the arbitrator's decision.   However, on
    January 24, 2009, defendant informed plaintiff the weekly wage-
    differential payments would be terminated.   Plaintiff had not
    received weekly wage-differential payments since the end of
    January 2009.   Plaintiff sought entry of judgment and an award of
    costs and attorney fees.
    On April 22, 2009, defendant filed a responsive plead-
    ing.   Defendant agreed that (1) the time for review of the
    arbitrator's decision had passed, (2) defendant had complied with
    the arbitrator's decision until "the recent developments, ques-
    tioning how long the disability has lasted," (3) defendant
    notified plaintiff as to the basis and date of termination of the
    wage-differential benefits, and (4) no benefits had been paid as
    of the date of the termination of the wage-differential benefits.
    Defendant disputed that defendant was out of time to challenge
    the arbitrator's decision or pursue any remedy, "in view of
    evidence subsequently gathered questioning whether the disabil-
    ity, that served as premise for the [d]ecision, has continued."
    Defendant also disputed whether the failure to pay was improper
    and its responsibility for costs and attorney fees.
    On June 18, 2009, plaintiff filed a motion for judgment
    on the pleadings.   On that same date, defendant filed a motion
    - 4 -
    for leave to file "[c]ounterclaim/[a]ffirmative [d]efenses for
    [e]quitable [r]elief" (hereinafter referred to as the counter-
    claim).   Defendant attached to its motion for leave a proposed
    counterclaim for equitable relief.
    In the motion for leave, defendant alleged that follow-
    ing plaintiff's injury, plaintiff was unable to return to work as
    a lineman for defendant.   After expiration of the time for review
    of the arbitrator's decision, plaintiff obtained full-time
    employment as a lineman at an hourly rate in excess of his rate
    of pay with defendant.   Defendant believed plaintiff's alleged
    disability had ended or diminished.    Therefore, in January 2009,
    defendant terminated plaintiff's wage-differential benefits.
    Defendant further asserted it had no adequate remedy at
    law because the time for review had passed.   Defendant argued
    plaintiff was entitled to the wage-differential benefits only so
    long as the disability lasted, and, because plaintiff was no
    longer incapacitated from working as a lineman, plaintiff was not
    entitled to receive the wage-differential benefits.   Defendant's
    proposed counterclaim sought an order that (1) defendant was no
    longer obligated to pay plaintiff wage-differential benefits and
    (2) the wage-differential benefits received by plaintiff after he
    became reemployed as a lineman should be held in constructive
    trust for the benefit of defendant and conveyed to defendant.
    Defendant also filed a motion seeking to stay entry or enforce-
    - 5 -
    ment of judgment under section 19(g) until the court determined
    whether defendant was entitled to equitable relief.
    On July 2, 2009, plaintiff filed a motion to strike
    defendant's motions for leave and for a stay.   Plaintiff argued
    the circuit court only had jurisdiction to determine whether the
    requirements of section 19(g) of the Act had been met and enter
    the workers' compensation award as a civil court judgment.
    On July 8, 2009, the circuit court held a hearing.    No
    transcript, bystander's report, or agreed statement of facts
    pertaining to this hearing has been provided on appeal.
    On September 1, 2009, the circuit court entered an
    order denying (1) defendant's motion for leave to file the
    counterclaim, (2) defendant's motion for stay, and (3) plain-
    tiff's motion to strike defendant's motions.    The court granted
    plaintiff's motion for judgment on the pleadings.   The court
    entered judgment in favor of plaintiff and against defendant (1)
    in accordance with the arbitrator's decision and (2) in the
    amount of $5,705.50 for attorney fees and costs.
    On October 1, 2009, defendant filed a notice of appeal.
    On October 7, 2009, plaintiff filed a notice of cross-appeal for
    the purpose of requesting additional fees and costs on appeal.
    II. ANALYSIS
    A. Issues Raised in Defendant's Appeal
    In its direct appeal, defendant argues (1) defendant is
    - 6 -
    without an adequate remedy at law and a court of equity should
    determine whether defendant must continue to pay benefits to
    plaintiff and (2) defendant should have been granted leave to
    amend.
    Generally, a trial court's decision on whether to grant
    leave to file a counterclaim or an affirmative defense is re-
    viewed for an abuse of discretion.     See, e.g., Todd W. Musburger,
    Ltd. v. Meier, 
    394 Ill. App. 3d 781
    , 796, 
    914 N.E.2d 1195
    , 1210
    (2009) (involving leave to file amended affirmative defenses);
    Trustees of Schools of Township 42 North, Range 11, East of Third
    Principal Meridian, Cook County, Illinois v. Schroeder, 8 Ill.
    App. 3d 122, 124, 
    289 N.E.2d 247
    , 249 (1972) (holding that the
    "trial court had discretion to allow or deny filing of the
    counterclaim" postdecree).   Here, however, the issue raised by
    defendant requires statutory construction--whether the Act
    permitted such a defense in an action under section 19(g) of the
    Act.   Therefore, our review is de novo.    See, e.g., Cassens
    Transport Co. v. Illinois Industrial Comm'n, 
    218 Ill. 2d 519
    ,
    524-25, 
    844 N.E.2d 414
    , 418-19 (2006) (reviewing de novo whether
    the Commission had jurisdiction to reopen a 10-year-old wage-
    differential award de novo because the case required interpreta-
    tion of section 8(d)(1) of the Act).
    "Proceedings under the Workers' Compensation Act are
    purely statutory, and courts can obtain jurisdiction only in the
    - 7 -
    manner provided by that Act."    Beasley v. Industrial Comm'n, 
    198 Ill. App. 3d 460
    , 464, 
    555 N.E.2d 1172
    , 1174 (1990); see also
    Kavonius v. Industrial Comm'n, 
    314 Ill. App. 3d 166
    , 169, 
    731 N.E.2d 1287
    , 1290 (2000) (noting that circuit courts exercise
    special statutory jurisdiction in workers' compensation proceed-
    ings and strict compliance with the statute is required to vest
    the court with subject-matter jurisdiction).   Section 19(g) of
    the Act gives circuit courts the authority to render judgment in
    accordance with an award or decision of the Commission when a
    certified copy of the decision is presented to the court.    Ahlers
    v. Sears, Roebuck Co., 
    73 Ill. 2d 259
    , 264, 
    383 N.E.2d 207
    , 209
    (1978).   Section 19(g) provides as follows:
    "Except in the case of a claim against
    the State of Illinois, either party may pres-
    ent a certified copy of the award of the
    [a]rbitrator, or a certified copy of the
    decision of the Commission when the same has
    become final, when no proceedings for review
    are pending, providing for the payment of
    compensation according to this Act, to the
    Circuit Court of the county in which such
    accident occurred or either of the parties
    are residents, whereupon the court shall
    enter a judgment in accordance therewith.    In
    - 8 -
    a case where the employer refuses to pay
    compensation according to such final award or
    such final decision upon which such judgment
    is entered[,] the court shall in entering
    judgment thereon, tax as costs against him
    the reasonable costs and attorney fees in the
    arbitration proceedings and in the court
    entering the judgment for the person in whose
    favor the judgment is entered, which judgment
    and costs taxed as herein provided shall,
    until and unless set aside, have the same
    effect as though duly entered in an action
    duly tried and determined by the court, and
    shall with like effect, be entered and dock-
    eted."   820 ILCS 305/19(g) (West 2008).
    Section 19(g) is "designed to permit speedy entry of
    judgment on an award."   Aurora East School District v. Dover, 
    363 Ill. App. 3d 1048
    , 1055, 
    846 N.E.2d 623
    , 629 (2006).    The circuit
    court's inquiry is limited to determining whether the require-
    ments of section 19(g) have been met.   
    Ahlers, 73 Ill. 2d at 268
    ,
    383 N.E.2d at 211.   The court cannot question the jurisdiction of
    the Commission, question the legality of the Commission's ac-
    tions, review the Commission's decision, or "otherwise construe
    the Act, even if the decision appears too large on its face."
    - 9 -
    Aurora East School 
    District, 363 Ill. App. 3d at 1055
    , 846 N.E.2d
    at 629; see also 
    Ahlers, 73 Ill. 2d at 268
    , 383 N.E.2d at 211
    (the court can refuse to "enter judgment only, for example, when
    a lack of jurisdiction appears on the face of the record").   The
    only defense to a section 19(g) petition is full payment of the
    final award.    Aurora East School 
    District, 363 Ill. App. 3d at 1055
    , 846 N.E.2d at 630.
    In this appeal, defendant does not challenge whether
    the requirements of section 19(g) have been met; nor does defen-
    dant assert that full payment has been tendered.   Defendant only
    challenges the circuit court's refusal to consider defendant's
    claim that plaintiff was no longer entitled to a wage-differen-
    tial payment.
    Such an argument is not appropriately raised in a
    section 19(g) proceeding.   See McCormick v. McDougal-Hartmann
    Co., 
    47 Ill. 2d 340
    , 343, 
    265 N.E.2d 610
    , 612 (1970) (employer
    could not raise, in an action to enforce an award of compensation
    under section 19(g), its claim that it was entitled to credit for
    recovery the employee received from a third party); Franklin v.
    Wellco Co., 
    5 Ill. App. 3d 731
    , 734, 
    283 N.E.2d 913
    , 915 (1972)
    ("An employer cannot have the award reviewed by filing an answer
    in an action brought by the employee under section 19(g) to
    enforce the award").    Therefore, the circuit court did not have
    jurisdiction to review the award and did not err by denying
    - 10 -
    defendant leave to file its counterclaim.
    Defendant was not without a remedy.   As noted, the
    arbitrator awarded plaintiff a wage differential pursuant to
    section 8(d)(1) of the Act (820 ILCS 305/8(d)(1) (West 2002)).
    Section 8(d)(1) of the Act "provides that an employee who is
    partially incapacitated from pursuing his usual and customary
    line of employment shall receive a portion of the difference
    between his former wages and the wages he earns or is able to
    earn in his new employment."   
    Cassens, 218 Ill. 2d at 522
    , 844
    N.E.2d at 417, citing 820 ILCS 305/8(d)(1) (West 2002).   "An
    employee receiving an installment award under section 8(d)(1) is
    entitled to compensation 'for the duration of his disability.'"
    
    Cassens, 218 Ill. 2d at 522
    , 844 N.E.2d at 417, quoting 820 ILCS
    305/8(d)(1) (West 2002).
    Section 8(d)(1) itself does not "authorize the Commis-
    sion to reopen final installment awards for partial disability."
    
    Cassens, 218 Ill. 2d at 528
    , 844 N.E.2d at 421.   However, under
    section 19(h) of the Act, the Commission has the authority, for a
    proscribed period of time, to review an installment award.   See
    Alvarado v. Industrial Comm'n, 
    216 Ill. 2d 547
    , 555, 
    837 N.E.2d 909
    , 915 (2005) (under section 19(h), where the employee's
    disability has recurred, increased, diminished, or ended, the
    Commission may review an award); Eschbaugh v. Industrial Comm'n,
    
    286 Ill. App. 3d 963
    , 966, 
    677 N.E.2d 438
    , 441 (1996) (finding
    - 11 -
    section 19(h) of the Act gives the Commission continuing juris-
    diction over an award providing for compensation in installments
    for a proscribed period of time, and the time provision of
    section 19(h) jurisdictional).
    Section 19(h) provides as follows:
    "An agreement or award under this Act
    providing for compensation in installments,
    may at any time within 18 months after such
    agreement or award be reviewed by the Commis-
    sion at the request of either the employer or
    the employee, on the ground that the disabil-
    ity of the employee has subsequently re-
    curred, increased, diminished[,] or ended.
    However, as to accidents occurring sub-
    sequent to July 1, 1955, which are covered by
    any agreement or award under this Act provid-
    ing for compensation in installments made as
    a result of such accident, such agreement or
    award may at any time within 30 months, or 60
    months in the case of an award under [s]ecti-
    on 8(d)1, after such agreement or award be
    reviewed by the Commission at the request of
    either the employer or the employee on the
    ground that the disability of the employee
    - 12 -
    has subsequently recurred, increased, dimin-
    ished[,] or ended.
    On such review, compensation payments
    may be re-established, increased, dimin-
    ished[,] or ended."    820 ILCS 305/19(h) (West
    2008).
    As such, section 19(h) provides a period of time in which the
    Commission may consider whether an injury has recurred, in-
    creased, decreased, or ended.    Behe v. Industrial Comm'n, 
    365 Ill. App. 3d 463
    , 466, 
    848 N.E.2d 611
    , 614 (2006).    The 30-month
    time period applies here because the 60-month time period applies
    only to injuries that occurred on or after February 1, 2006.      See
    Pub. Act. 94-277, §95, eff. July 20, 2005 (2005 Ill. Legis. Serv.
    1911, 1965 (West)).   Therefore, in this case, defendant could
    have petitioned the Commission, within 30 months of the wage-
    differential award, and argued the injury diminished or ended.
    See 
    Cassens, 218 Ill. 2d at 528
    , 844 N.E.2d at 421 (noting that
    the employer could have asked the Commission to reopen an in-
    stallment award on the ground that the employee's disability
    diminished or ended but had to do so within 30 months of the
    issuance of the award).
    While this outcome seems unfair, this court is bound by
    the statute and Cassens to so rule and encourages the legislature
    to revisit this situation.   A totally and permanently disabled
    - 13 -
    employee's benefits may be terminated upon the employer learning
    the disability no longer exists, but a partially permanently
    disabled employee's benefits pursuant to section 8(d)(1) (wage
    differential) may not.   See 820 ILCS 305/8(f) (West 2008) (pro-
    viding that in cases of complete disability, if the employee
    returns to work or is able to do so and earns as much as before
    the accident or is able to do so, payments under the award shall
    cease); 
    Cassens, 218 Ill. 2d at 527
    , 
    529, 844 N.E.2d at 421
    (finding "[s]ection 8(f) indicates that employers may cease
    payments when a totally and permanently disabled employee returns
    to the workforce, giving the employee authorization to petition
    the Commission for review of the award" and construing the
    statute as authorizing "ongoing review" by the Commission).
    Concededly, just as the employer can only petition to terminate
    benefits on a wage differential within 60 months (for injuries
    occurring on or after February 1, 2006), an employee may not seek
    an increase in his wage differential even if further disabled
    after 60 months.
    Defendant also argues on appeal that it should have
    been allowed to amend its pleading.    Nothing in the record
    demonstrates defendant sought leave to amend or shows what that
    amendment entailed.   In any event, one of the factors considered
    when determining whether to permit amendment to a pleading is
    whether the amendment would cure the defect in the pleading.    See
    - 14 -
    Gurnitz v. Lasits-Rohline Service, Inc., 
    368 Ill. App. 3d 1129
    ,
    1132, 
    859 N.E.2d 1156
    , 1159 (2006).    Here, defendant could not
    cure the defect in the pleading because its counterclaim was not
    a proper defense to the section 19(g) action, and, in any event,
    the trial court was not the proper forum in which to raise its
    claim that plaintiff's injury diminished or ended.     See 820 ILCS
    305/19(h) (West 2008) (providing the method and means for chal-
    lenging an installment award under the Act before the Commis-
    sion).   Consequently, we affirm the circuit court's judgment.
    B. Plaintiff Not Entitled to Costs and
    Attorney Fees Incurred on Appeal
    In his cross-appeal, plaintiff argues he is entitled to
    costs and attorney fees incurred on appeal either under section
    19(g) of the Act or pursuant to Supreme Court Rule 375, which
    pertains to frivolous appeals.
    Section 19(g) of the Act provides for an award of costs
    and attorney fees in certain circumstances:
    "In a case where the employer refuses to pay
    compensation according to such final award or
    such final decision upon which such judgment
    is entered the court shall in entering judg-
    ment thereon, tax as costs against him the
    reasonable costs and attorney fees in the
    arbitration proceedings and in the court
    entering the judgment for the person in whose
    - 15 -
    favor the judgment is entered, which judgment
    and costs taxed as therein provided shall,
    until and unless set aside, have the same
    effect as though duly entered in an action
    duly tried and determined by the court, and
    shall with like effect, be entered and dock-
    eted."   (Emphasis added.)    820 ILCS 305/19(g)
    (West 2008).
    In this case, the circuit court did, in conformance with section
    19(g), award plaintiff his reasonable costs and attorney fees.
    Plaintiff now seeks costs and attorney fees incurred on appeal.
    Section 19(g) does not, however, specifically provide for payment
    of attorney fees incurred on appeal.
    In support of his argument that he is entitled to costs
    and attorney fees incurred on appeal, plaintiff cites McAnally v.
    Butzinger Builders, 
    263 Ill. App. 3d 504
    , 
    636 N.E.2d 19
    (1994).
    In McAnally, the trial court dismissed the plaintiff's section
    19(g) petition.     
    McAnally, 263 Ill. App. 3d at 506
    , 636 N.E.2d at
    20.   On appeal, the appellate court reversed and remanded,
    directing the trial court to calculate the amount due and to
    enter a judgment in favor of plaintiff.      McAnally, 
    263 Ill. App. 3d
    at 
    509, 636 N.E.2d at 22
    .    The appellate court also found
    "plaintiff [was] entitled to costs and attorney fees for the
    employer's refusal to pay, and the fee award shall include those
    - 16 -
    incurred in prosecuting the appeal."   McAnally, 
    263 Ill. App. 3d
    at 
    509, 636 N.E.2d at 22
    .   The court reasoned that although the
    right to appeal is important, the injured worker also has the
    right to be promptly compensated for the full amount of the final
    award.   McAnally, 
    263 Ill. App. 3d
    at 
    509, 636 N.E.2d at 22
    .
    In contrast here, the circuit court granted plaintiff's
    19(g) petition and awarded costs and attorney fees as provided by
    section 19(g) of the Act.   No remand is required here, as entry
    of judgment has occurred.   Nothing in the language of section
    19(g) compels an award of attorney fees under these circum-
    stances.   Section 19(g) refers to an award of costs and attorney
    fees incurred in the arbitration proceedings and in the court
    entering judgment.   Unlike the situation in McAnally, where the
    circuit court was directed to enter judgment to include costs and
    attorney fees incurred on appeal, no remand is required here.    As
    such, section 19(g) of the Act does not require this court to
    award plaintiff his costs and attorney fees incurred on appeal,
    and we decline to do so.
    Plaintiff also seeks costs and attorney fees incurred
    on appeal pursuant to Supreme Court Rule 375(b) (155 Ill. 2d R.
    375(b)).   Supreme Court Rule 375(b) calls for sanctions where an
    appeal is not reasonably well grounded in law or fact and is made
    in bad faith or to avoid paying an award.   155 Ill. 2d R. 375(b).
    The imposition of sanctions under Rule 375(b) is within the
    - 17 -
    appellate court's discretion.    See Residential Carpentry, Inc. v.
    Illinois Workers' Compensation Comm'n, 
    389 Ill. App. 3d 975
    , 976,
    
    910 N.E.2d 109
    , 111 (2009).   We find that although defendant's
    argument on appeal was unpersuasive, the argument was not so
    lacking in foundation and law and evidence as to merit sanctions.
    Greene Welding & Hardware v. Illinois Workers' Compensation
    Comm'n, 
    396 Ill. App. 3d 754
    , 759, 
    919 N.E.2d 1129
    , 1134 (2009).
    Therefore, we deny plaintiff's request for costs and attorney
    fees on appeal.
    III. CONCLUSION
    For the reasons stated, we affirm the circuit court's
    judgment and deny plaintiff's request on cross-appeal for costs
    and attorney fees.
    Affirmed.
    KNECHT and TURNER, JJ., concur.
    - 18 -