O'Gorman v. F.H. Paschen, S.N. Nielsen, Inc. , 2015 WL 1281750 ( 2015 )


Menu:
  •                              Illinois Official Reports
    Appellate Court
    O’Gorman v. F.H. Paschen, S.N. Nielsen, Inc., 
    2015 IL App (1st) 133472
    Appellate Court         KEVIN E. O’GORMAN and LAURA O’GORMAN, Plaintiffs-
    Caption                 Appellants, v. F.H. PASCHEN, S.N. NIELSEN, INC., an Illinois
    Corporation, Defendant-Appellee (Old Veteran Construction, Inc.,
    Defendant).
    District & No.          First District, Fifth Division
    Docket No. 1-13-3472
    Filed                   March 20, 2015
    Decision Under          Appeal from the Circuit Court of Cook County, No. 06-L-1567; the
    Review                  Hon. Kathy Flanagan, Judge, presiding.
    Judgment                Affirmed.
    Counsel on              William J. Harte, of Chicago, for appellants.
    Appeal
    Robert J. Winston and W. Scott Trench, both of Brady, Connolly &
    Masuda, P.C., of Chicago, for appellee.
    Panel                   JUSTICE GORDON delivered the judgment of the court, with
    opinion.
    Presiding Justice Palmer and Justice McBride concurred in the
    judgment and opinion.
    OPINION
    ¶1       Kevin O’Gorman (plaintiff) was injured while supervising a construction project at which
    defendant F.H. Paschen, S.N. Nielsen, Inc., was operating as a general contractor. Plaintiff
    alleged that he was injured due to the actions of employees of Old Veteran Construction, Inc.
    (Old Veteran), which was operating as a subcontractor for defendant and which is not a party to
    the instant appeal. Plaintiff and his wife, Laura O’Gorman, filed suit against both defendant
    and Old Veteran, alleging that they were negligent and that their negligence was a cause of
    plaintiff’s injuries. Defendant filed a motion for summary judgment, arguing that it owed no
    duty to plaintiff, and the trial court granted summary judgment in defendant’s favor. Plaintiffs
    appeal, and we affirm.
    ¶2                                         BACKGROUND
    ¶3                                           I. Complaint
    ¶4       On February 10, 2006, plaintiffs filed a complaint against defendant and Old Veteran; the
    complaint was amended twice and it was the second amended complaint that was the subject of
    defendant’s motion for summary judgment. The second amended complaint alleges that
    defendant contracted with the City of Chicago (the City) to act as a general contractor for
    portions of a construction/renovation project involving the conversion of former police
    department headquarters into a custodial youth center (the project). Part of defendant’s
    responsibilities included the construction of an elevator shaft within the building. “At all times
    relevant herewith, Paschen supervised and controlled or was obligated to supervise and control
    the work for which it contracted, as part of its duties and responsibilities as general contractor,
    including the construction of the elevator shaft.”
    ¶5       Defendant, in turn, retained Old Veteran to act as a masonry subcontractor on the project.
    Specifically, Old Veteran was hired to perform the masonry work involved in the construction
    of the elevator shaft, including an extension of the elevator shaft above the existing roofline of
    the building. “At all times relevant herewith, the defendant, Old Veteran, supervised and
    controlled or was obligated to supervise and control the work it was doing as Paschen’s
    masonry subcontractor, including the construction of the elevator shaft.”
    ¶6       On February 10, 2005, City employees cut a hole in the roof of the building to allow for
    extension of the elevator shaft above the roofline and placed a wooden cover over the hole. The
    second amended complaint alleges that on February 11, 2005, “Old Veteran removed the
    wooden cover in order to erect and place the courses of cinder block, and it thereafter erected
    and placed the courses of cinder block.” The second amended complaint further alleges that
    “[w]hen it removed the roof cover originally placed by the City, Old Veteran left a piece of
    wood, with a nail imbedded therein, upon the roof in proximity to” a roof hatch that was used
    to access the roof during construction.
    ¶7       Plaintiff was employed by the City and used the roof hatch on February 14, 2005, to access
    the roof. While attempting to exit the hatch, plaintiff stepped on the piece of wood with the nail
    embedded therein. In pulling the nail from his foot, plaintiff lost his balance and fell through
    the hatch opening to the floor below.
    -2-
    ¶8         The first count of the second amended complaint was for negligence against both
    defendant and Old Veteran and alleged that defendant was negligent in one or more of the
    following ways:
    “a. Failed to maintain a safe work site;
    b. Failed to assure that the roof cover was removed in a safe and appropriate
    manner;
    c. Failed to inspect the work area in which Old Veteran was involved to assure that
    its work was done in a safe and workmanlike manner;
    d. Failed to inspect the work area in which Old Veteran was involved to assure that
    such was clear of construction waste or debris;
    e. Failed to properly dispose of construction waste or debris or see to it that Old
    Veteran did so;
    f. Failed to warn the plaintiff and others of the risk inherent in leaving debris on the
    roof, including the nail imbedded in wood;
    g. Failed to place and provide safe, suitable and proper barricades or other fall
    protection devices for the hatch, or require their use;
    h. Failed to warn the plaintiff and others of the risk involved attendant to the [sic]
    its failure to to [sic] place barricades or other fall protection devices for the hatch, or
    require their use;
    i. Allowed the plaintiff and others to enter upon the roof when the nail imbedded in
    wood was present and when there were no fall protection devices for the hatch.”
    The second amended complaint alleges that, as a result of one or more of these negligent acts
    or omissions, plaintiff sustained severe injuries.
    ¶9         The second count of the second amended complaint was for loss of consortium against
    both defendant and Old Veteran.
    ¶ 10                                               II. Discovery
    ¶ 11                                  A. Discovery Deposition of Plaintiff
    ¶ 12        At his deposition, plaintiff testified that he began working for the City in 1996 as a
    journeyman carpenter and was currently working as a general foreman of general trades. The
    “general trades” were “[g]lazers, pipe fitters, sheet metal, carpenters, laborers, [and] iron
    workers,” and plaintiff’s responsibility was to coordinate work for the trades under his
    command at the jobsite. The work that could not be performed by the trades would be
    contracted out to a general contractor to complete the work. Plaintiff testified that when
    working on a jobsite, each contactor would have the responsibility of keeping its area clean.
    Plaintiff did not have the responsibility to supervise the work of any non-City contractors.
    Plaintiff’s presence on the jobsite would vary, and sometimes he was not present at the site at
    all, but on average, he visited the jobsite four to six times a week to attend weekly jobsite
    meetings, check manpower, and check the progress of the work.
    ¶ 13        Plaintiff testified that one of the tasks performed by City workers on the instant project was
    the removal of a portion of the building’s roof so that the elevator shaft could be extended.
    Plaintiff instructed his foreman, Anthony Pilas, to perform the work, who, in turn, instructed
    -3-
    two additional City employees–Jaime Martinez and Terry Regan–to cut the roof, which took
    approximately two days.
    ¶ 14       Plaintiff testified that approximately a week before his accident, the City workers cut the
    hole in the roof, and sometime between then and February 14, the day of the accident, the
    elevator shaft was extended by Old Veteran, the masonry subcontractor for defendant. On
    February 14, plaintiff observed Old Veteran workers on the third floor of the building taking
    down scaffolding that had been erected inside the elevator shaft. Plaintiff did not observe any
    Old Veteran workers on the roof.
    ¶ 15       Plaintiff testified that Tuesday or Wednesday of the week of February 7, he went to the
    roof of the building to ensure that his workers had properly secured the opening cut into the
    roof. The opening was covered with 3-by-14 planks across it, then plywood, with “strapping”
    of 2-by-4s and 1-by-4s nailed to the top of the plywood so that it would not blow away. When
    the workers cut the hole in the roof, they cleaned up their debris and threw it away into a
    dumpster located in the parking lot. Plaintiff testified that he accessed the roof via a ladder
    extending through a roof hatch. When he exited the roof hatch, the elevator shaft would have
    been a few feet to his left.
    ¶ 16       Plaintiff testified that on the day of the accident, he climbed the ladder through the roof
    hatch and stepped to the left upon exiting the hatch. He first stepped with his left foot and
    landed on a nail embedded in a blonde piece of wood approximately a foot to two feet long; the
    wood was new and was rectangular in shape, but plaintiff could not recall whether it was a
    1-by-4 or a 2-by-4. Plaintiff picked up his left foot and “hopped around trying to pull the nail
    out.” He placed a hand on the roof hatch to steady himself, but did not hold onto the hatch the
    entire time. As he hopped, plaintiff backed into the curb of the hatch and fell backward, hitting
    his head on the top of the hatch. When he fell, plaintiff stretched his arms out and caught
    himself on the sides of the hatch. Pilas and City architect John Albrecht came to plaintiff’s side
    and attempted to assist plaintiff, but were unsuccessful. Plaintiff fell through the hatch 13 to 15
    feet to the floor below and lost consciousness.
    ¶ 17       Plaintiff testified that he had previously complained to defendant about construction debris
    throughout the building at their regular jobsite meetings. Plaintiff believed the piece of wood
    and nail came from the cover of the elevator shaft and also believed that someone from Old
    Veteran disassembled the cover because “[t]hey had to complete their work” of extending the
    brickwork through the roof. On February 14, the brickwork was above the level of the roof.
    Plaintiff testified that if someone from Old Veteran wanted a City worker to remove the cover
    over the elevator shaft, “[h]e would have to go through me.” As of the time of the accident, no
    one from Old Veteran had asked plaintiff to remove the cover.
    ¶ 18                           B. Testimony From Other City Employees
    ¶ 19                          1. Discovery Deposition of Terrence Regan
    ¶ 20       Terrence Regan testified that he was a carpenter for the City’s department of general
    services and worked on the project at issue in the instant case. Pilas was his foreman and was
    the person Regan would turn to with any questions about his work. Regan testified that he was
    involved in cutting a hole in the roof for the extension of the elevator shaft and that plaintiff
    was the person requesting that Regan cut the hole.
    -4-
    ¶ 21       Regan testified that as they were cutting the hole, the workers would stack the old roofing
    materials to be later discarded. The roofing materials included pieces of wood with nails
    sticking out of them, and were thrown over the side of the building into the dumpster. All of the
    wood that was discarded was old wood; there were no new pieces of wood in the roofing
    material. However, some of the 1-by-4 that was used was newer wood that was blond in color.
    ¶ 22       Regan testified that Pilas asked the workers to cover the hole. They first laid timbers of
    3-by-16 down across the hole and nailed them to the roof deck using nail guns. They then
    nailed sheets of three-quarter plywood over the timbers, followed by 1-by-4 strapping that was
    nailed to the timbers through the plywood to hold it down. After the hole was cut and covered,
    Regan did not return to the roof.
    ¶ 23       When Regan was presented with a photograph of the roof from February 14, 2005, he
    identified masonry bricks, covered by plywood with cinder blocks on top of the plywood, in
    the area where he had cut the hole in the roof. He testified that the bricks, plywood, and cinder
    blocks were not the cover he had placed over the hole and that the cover had “definitely” been
    removed since he had installed it.
    ¶ 24                             2. Discovery Deposition of John Albrecht
    ¶ 25        John Albrecht testified that he was formerly an architect with the City’s department of
    general services. He served as a coordinating architect on the project at issue in the instant case
    and “was responsible for the design issues as they arose and making sure the architect would
    address those issues as they arose.” He visited the worksite every two weeks and tried to attend
    the regular construction meetings; Albrecht recalled plaintiff making general complaints about
    the cleanliness of the worksite at the meetings.
    ¶ 26        On February 14, 2005, Albrecht visited the worksite to inspect a heating and air
    conditioning unit on the roof of the building. When he arrived at the building, he met with
    plaintiff and Pilas and they headed for the roof. Albrecht and Pilas went to the roof via a ladder
    to the roof hatch, while plaintiff was temporarily delayed on the third floor. By the time
    plaintiff climbed to the roof, Albrecht and Pilas had moved to the side of the heating and air
    conditioning unit and did not observe him climbing through the hatch. Albrecht observed
    plaintiff on the roof near the hatch, balancing on one foot while pulling a piece of wood with a
    nail embedded in it out of his other foot. Albrecht described the piece of wood as
    approximately six inches, but could not recall whether it was a “two by two or three or four”;
    Albrecht testified that “[i]t was definitely new wood, so it looked like a construction scrap to
    me.”
    ¶ 27        Albrecht and Pilas had begun walking back in plaintiff’s direction and began hurrying
    when they observed plaintiff in distress. Plaintiff was able to remove the piece of wood, but
    lost his balance and fell backward into the hatch. Albrecht ran to plaintiff, who was holding
    himself up by his arms and legs. Albrecht grabbed plaintiff’s sweater and Pilas grabbed
    plaintiff’s right foot; plaintiff’s sweater began slipping, so Albrecht then grabbed plaintiff’s
    left foot. The upper part of plaintiff’s body slipped, so that plaintiff was hanging head down
    through the hatch. Albrecht could not hold on and plaintiff fell through the hatch to the third
    floor.
    -5-
    ¶ 28                             3. Discovery Deposition of Anthony Pilas
    ¶ 29        Anthony Pilas testified that he was an acting carpentry foreman for the City on the project
    at issue in the instant case. Pilas testified that the only work that City carpenters performed on
    the roof of the building was to cut a hole in the roof for the extension of the elevator shaft and
    further testified that the City carpenters would “[a]bsolutely” be responsible for cleaning up
    that debris.
    ¶ 30        Pilas was present on the roof when the City workers cut the hole and testified that the
    roofing materials were removed in pieces then discarded. The materials would be brought
    down by way of a scissors lift; City employees were not permitted to throw the roofing
    materials off the roof into the dumpster on the side of the building. The hole was then secured
    by a temporary frame made of large timbers covered with plywood; Pilas was not present when
    the cover was created or installed, but testified that the plywood would have been nailed or
    screwed to the timbers. Pilas never witnessed any mason remove the cover placed over the
    shaft by the City workers.
    ¶ 31        On the day of the accident, Pilas was at the site with plaintiff and they were going to the
    roof with Albrecht, who wished to inspect the chiller unit on the roof. Pilas climbed the ladder
    to the roof first, followed by Albrecht and then plaintiff; there was no one else on the roof at the
    time. Pilas observed debris on the roof, including rope, roofing paper, 2-by-4s, plywood, and
    buckets; Pilas did not know who put the debris on the roof, but testified that there was no debris
    on the roof when the City workers finished cutting the hole for the elevator shaft. Pilas and
    Albrecht were near the chiller unit when plaintiff stepped onto the roof. Pilas observed plaintiff
    come onto the roof and “all of a sudden he stepped on something” and began screaming that he
    had stepped on a nail. Pilas observed plaintiff reaching down to pull it out, then falling into the
    hatch. Pilas held onto to plaintiff’s hand and Albrecht grabbed plaintiff as well. Plaintiff began
    flailing his arms and Pilas lost hold of his hand. Plaintiff then fell through the opening and Pilas
    immediately called 911. Pilas testified that plaintiff stepped on a piece of 2-by-4 wood that was
    approximately four inches long.
    ¶ 32                             4. Discovery Deposition of Anthony Acres
    ¶ 33        Anthony Acres testified that he worked for the City’s department of general services as a
    construction laborer and worked on the construction project at issue in the instant case. Acres
    was present on the roof when the City carpenters were cutting the hole over the elevator shaft.
    The cutting generated debris, including pieces of wood with nails sticking out from them. The
    debris was placed near the work area while the carpenters were cutting. Acres’ job was to
    periodically clean up all of the debris and throw it over the edge of the roof into the dumpster
    below.
    ¶ 34        Acres testified that one of the carpenters created a cover and affixed it to the hole they cut
    into the roof. Once the carpenters were finished, they left and Acres disposed of all the debris
    left.
    ¶ 35                          C. Testimony From Old Veteran Employees
    ¶ 36                             1. Discovery Deposition of Jesus Cruz
    ¶ 37      Jesus Cruz testified that he was a superintendent for Old Veteran and was responsible for
    completion of work as well as “all aspects of safety for [the] workers,” including compliance
    -6-
    with the Occupational Safety and Health Act (OSHA) (29 U.S.C. § 651 et seq. (2006)). Cruz
    had completed a 10-hour OSHA class and had received additional safety training through his
    union. Old Veteran also had a safety plan that Cruz discussed with the workers under his
    supervision. In addition to his position as a superintendent, Cruz also performed tuckpointing
    work for Old Veteran.
    ¶ 38       Cruz testified that his brother Salvador was the superintendent assigned to the construction
    project at issue in 2004 and 2005. Cruz was employed on the project as a tuckpointer and was
    responsible for overseeing the work on the elevator shaft when Salvador was in Mexico
    between November 2004 and March 2005. Old Veteran had been retained as a subcontractor
    on the project by defendant, and while Cruz was overseeing work for Salvador, Cruz met Gary
    Swart, defendant’s superintendent. Cruz was overseeing the work during the time that the
    elevator shaft was extended through the roofline and had visited the roof, “inspecting if
    everything was going correctly, everything was going fine, cleanup, everything–they had
    enough material and everything to complete the job.” Cruz visited the worksite once or twice a
    week and went to the roof twice.
    ¶ 39       Cruz testified that when he was on the roof, he did not observe any plywood on the roof but
    observed that “Forty, 50 percent of the roof” contained discarding roofing material. Cruz
    further testified that if the Old Veteran workers discovered the elevator shaft covered by nailed
    boards, they would ask Swart to remove the boards; nobody made such a request of Swart
    during the project. However, if the workers observed the shaft covered by plywood with
    masonry blocks on it, they would simply remove the blocks and the plywood.
    ¶ 40       Cruz testified that Old Veteran’s workers had no need to use any nails to do their work on
    the elevator shaft and would have no reason to break any wood that had nails embedded in it
    and leave it on the roof. Cruz further testified that the Old Veteran workers understood that
    they were responsible for cleaning up after themselves and performing any “housekeeping.” If
    Cruz had observed any debris, even if not caused by Old Veteran’s workers, he would have
    brought it to someone’s attention or had it removed. Similarly, Cruz would expect any of Old
    Veteran’s workers to bring to his or Swart’s attention any safety hazard they observed in the
    area in which they were working, even if that hazard was created by someone else.
    ¶ 41                              2. Discovery Deposition of Paul Noble
    ¶ 42       Paul Noble testified that he was a bricklayer for Old Veteran on the construction project at
    issue in the instant case and that he and Adelbert Norwood added three rows of eight-inch
    masonry block to the existing elevator shaft. Noble testified that he added the rows of masonry
    block from the inside of the elevator shaft, while Norwood was on the roof. There was no
    covering over the elevator shaft when Noble arrived, nor did he or Norwood cover the elevator
    shaft when they left. He testified that the shaft should not have been left uncovered, so the
    laborers working with Noble and Norwood should have covered the shaft; however, he was
    unaware of anything that happened before or after he left the shaft.
    ¶ 43       Noble testified that he received his instructions to do the roofing work from Salvador Cruz
    and did not speak to anyone from defendant’s office; Noble did not know either Swart or David
    Roy, defendant’s project manager.
    -7-
    ¶ 44                         3. Discovery Deposition of Adelbert Norwood
    ¶ 45       Adelbert Norwood testified that he retired in 2004, but performed odd jobs, including
    working for Old Veteran as a bricklayer to extend the elevator shaft on the project at issue in
    the instant case. He was asked to work by Salvador Cruz, and he and Noble added three
    courses of eight-inch masonry block to the elevator shaft. They were assisted by two laborers,
    but Norwood was unable to recall their names.
    ¶ 46       Norwood testified that he added the courses of block from the roof, which he accessed
    through the nearby roof hatch. When he came onto the roof, the elevator shaft was uncovered.
    Norwood identified three-quarter inch plywood covering the elevator shaft in a photograph he
    was shown as an exhibit, but testified that “[i]t wasn’t there when I was there.” Norwood did
    not cover the shaft when they were done and was unaware of whether the laborers did so.
    Norwood did not observe any debris around the elevator shaft.
    ¶ 47       Norwood was unaware of the company for which Old Veteran was providing masonry
    work and did not know Swart or Roy.
    ¶ 48                            4. Discovery Deposition of Jose Maldonado
    ¶ 49       Jose Maldonado testified that he was the owner of Old Veteran and that under Old
    Veteran’s subcontract with defendant, Old Veteran employees were responsible for cleaning
    up after themselves when they installed the elevator shaft; nobody else was responsible for
    cleaning up after Old Veteran. Maldonado testified that it was Old Veteran’s practice to
    dispose of garbage daily and Old Veteran employees would not leave garbage behind when
    they left for the day.
    ¶ 50       Maldonado testified that he would expect the company that cut the hole in the roof to have
    covered it. If such a cover was present, then the company that cut the hole would be required to
    remove it for Old Veteran workers to complete their work and would replace it afterwards;
    “[t]hat’s normally how the procedure’s followed.” The Old Veteran workers would not have
    been permitted to remove the cover as “that’s against our regulations.”
    ¶ 51       Maldonado testified that Swart would call him when defendant needed work done. Swart
    did not tell Old Veteran how to do its work and did not direct the means and methods of the
    work.
    ¶ 52                           D. Testimony From Defendant’s Employees
    ¶ 53                              1. Discovery Deposition of Gary Swart
    ¶ 54       Gary Swart testified that he was a superintendent for defendant and served in that capacity
    on the construction project at issue in the instant case. His responsibilities as superintendent
    were to “[s]chedule my subcontractors, keep an eye on the job they performed, basically be
    safety guy, that type of stuff.” Swart had completed a 10-hour OSHA training course in 2000
    and a 30-hour OSHA training course in 2002.
    ¶ 55       Swart testified that his responsibilities on the worksite included making sure that the
    subcontractors kept the worksite clean and safe and to identify any potential violations of
    OSHA. During the course of the project, he would walk the jobsite daily, including areas in
    which defendant’s subcontractors were working. If he observed a safety hazard that had been
    created by defendant’s subcontractor, “I would be responsible for it. I would have to have my
    contractors clean it.” Similarly, if he observed the subcontractors doing something wrong, he
    -8-
    would instruct them to “fix it” and if he observed them doing something unsafe, he would
    order them to stop. Swart testified that he would not be responsible for cleaning up areas
    worked on by a different general contractor, such as the City.
    ¶ 56        Swart testified that defendant’s project manager for the project was David Roy, and Roy
    visited the site weekly, typically on the days that there were meetings relating to the site. Leo
    Wright was a senior project manager for defendant’s “JOC division” and visited the site
    “[o]ccasionally.”
    ¶ 57        Swart testified that defendant had a safety plan and that he would consult the safety plan as
    specific issues occurred on-site. He further testified that it was his responsibility to enforce
    defendant’s safety manual at the jobsite. If a subcontractor encountered a safety hazard, Swart
    would expect the subcontractor to bring it to his attention.
    ¶ 58        Swart testified that there were regular Tuesday meetings for the jobsite concerning
    “[c]oordination and job schedule,” as well as problems on the jobsite. These meetings would
    be attended by “[l]ots of different people,” including plaintiff and many others from the City.
    Swart did not recall any complaints as to defendant’s or Old Veteran’s work at the meetings.
    ¶ 59        Swart testified that he spoke to the Old Veteran workers on February 11 about finishing up
    their work that day. Swart spoke to the workers on the third floor of the building and was able
    to observe sunlight through the elevator shaft, indicating that there was no cover over the shaft.
    Swart instructed the workers to cover the hole in the roof when they left. Swart believed that
    after the City workers cut the hole in the roof for the elevator shaft, they covered it, because it
    was “just basic common sense that you wouldn’t leave a big gaping hole in the roof.” Swart
    testified that if the City workers had nailed the cover to the hole, Old Veteran workers could
    have removed the cover using their hammers and would not have needed to ask his permission,
    but further testified that he was not aware of whether the cover had been nailed down; Swart
    later testified that the hammers that the Old Veteran workers carried were masonry hammers,
    which did not have a “claw” end to remove nails but instead had a “chisel” end.
    ¶ 60        Swart testified that on February 14, 2005, he arrived at the worksite at approximately 7
    a.m. and left at approximately 11 a.m. Upon arriving, Swart noticed that it was raining and
    searched for his two laborers inside the elevator shaft, who were the only subcontractors
    defendant had on-site that day. Swart observed them for approximately five minutes, “[j]ust
    long enough to make sure they were there on site doing what I needed,” which was cleaning
    out the interior of the elevator shaft. Swart then generally checked the stairwell, which was
    empty due to the rain, and sat in his vehicle completing paperwork and making phone calls.
    ¶ 61        At approximately 10:30 a.m., Swart was in his vehicle preparing to leave the worksite
    when he observed a fire truck pulling in. As this was an unusual occurrence, Swart “figured I
    better go back in and see what’s going on.” Swart was standing in the building’s foyer when he
    learned of plaintiff’s accident. Pilas informed Swart that plaintiff had stepped on a nail and in
    the process of jumping on one foot to remove the nail, plaintiff fell through the roof hatch.
    Pilas further informed Swart that Pilas and Albrecht had tried to hold onto plaintiff as long as
    possible but that plaintiff “pulled away” and fell through the hatch.
    ¶ 62        Swart spoke to David Roy, his boss, who asked him to take photographs of the roof and to
    try to locate the piece of wood. Swart remained in the foyer for 30 to 45 minutes, then went to
    the roof to try to locate the board that plaintiff had stepped on and was unable to locate it. Pilas
    had informed Swart that plaintiff stepped on a “small piece of wood with a nail in it.” After 5 to
    -9-
    10 minutes, Swart left the worksite. When Swart went to the roof, he observed that the
    extended elevator shaft was covered with plywood held down by cinder blocks.
    ¶ 63       Swart testified that the Old Veteran workers would not have been on the roof that day
    because “they had no reason to be on the roof,” since they were cleaning the elevator shaft and
    disassembling the scaffolding inside it, which did not require access to the roof.
    ¶ 64                             2. Discovery Deposition of Leo Wright
    ¶ 65       Leo Wright testified that he was currently vice president with defendant but that he had
    formerly been Chicago job order contracting division manager, a position which concerned
    term contracts with the City. Wright testified that defendant had a four-term contract with the
    City’s department of general services and that as part of the contract, defendant agreed to be
    bound by the City’s general conditions.
    ¶ 66       Wright testified that Swart was defendant’s superintendent on the project at issue in the
    instant case, and David Roy was defendant’s project manager. Wright’s responsibilities were
    “to manage my project managers and superintendents, review budgets, review subcontracts,
    establish manpower for each contract, be the liaison with the owners.” As superintendent,
    Wright would have expected Swart “to visit [the site] on a regular basis, being daily or multiple
    times during the day if required depending on what activities were happening at the time,
    ensuring that subcontractors were putting work in place correctly, general housekeeping and to
    track the progress.” Wright testified that “general housekeeping” included making sure that
    any of defendant’s subcontractors were cleaning up after themselves and not leaving any
    debris.
    ¶ 67       Wright testified that under the general conditions of defendant’s contract with the City,
    defendant was required “to take all precautions that might be necessary to render all portions of
    the work secure in every respect or to decrease the liability of accidents from any cause or to
    avoid contingencies which are liable to delay the completion of the work.” Defendant also
    agreed to be “solely responsible for safety” and had “sole and complete responsibility for
    implementation of a safety program.” Finally, defendant agreed that during construction, it
    would “keep the work site and adjacent premises as free from material, debris and rubbish as
    [was] practicable and, when directed, would immediately remove same entirely when *** such
    material, debris or rubbish constitute[d] a nuisance, a safety hazard or [was] objectionable in
    any way to the public.”
    ¶ 68                               3. Discovery Deposition of David Roy
    ¶ 69        David Roy testified that he was a project manager for defendant on the construction project
    at issue in the instant case. Roy testified that it was a subcontractor’s responsibility to dispose
    of debris in the immediate work area as work progressed, but the subcontractor would not be
    responsible for cleaning up another subcontractor’s work. In that case, however, the
    subcontractor would have the obligation to alert someone of the debris.
    ¶ 70                                           III. Contract
    ¶ 71       The record on appeal contains the subcontract agreement between defendant and Old
    Veteran, entered into on April 9, 2004. Paragraph 2 of the subcontract agreement provides that
    “the provisions of the contract between the Contractor and the Owner (hereinafter the ‘General
    - 10 -
    Contract’) including but not limited to, the General and Supplementary Conditions, the Plans
    and Specifications, all Contract Requirements, and the particular Specifications relating to the
    Work of Subcontractor, insofar as they are applicable, are hereby incorporated herein by this
    reference and are binding upon the Subcontractor.”
    ¶ 72       Paragraph 19 of the subcontract agreement is entitled “Safety” and provides in relevant
    part:
    “Subcontractor agrees and understands that neither Contractor nor Architect will
    make continuous or exhaustive inspections to assure Subcontractor’s compliance with
    applicable safety rules, regulations or requirements. Subcontractor shall be solely
    responsible to assure the safety of its own equipment, appliances, material, and
    working conditions, techniques, and procedures, and Contractor is not responsible in
    any manner for the safety of Subcontractor’s Work. If the Subcontractor fails to correct
    unsafe procedures, acts or conditions within a reasonable time of notification by
    Contractor, however, Contractor may (but has no contractual obligation to do so)
    correct the unsafe practice and backcharge the Subcontractor for these costs. Repeated
    failures to correct unsafe practices may result in the termination of this Agreement. In
    the event Contractor receives a penalty from OSHA as a result of a violation of OSHA
    by Subcontractor and Contractor is cited under the multi-employer worksite rule,
    Subcontractor agrees to defend, indemnify and hold harmless Contractor for the
    imposition of any fines and/or penalties.”
    ¶ 73       Paragraph 20 of the subcontract agreement is entitled “Clean-Up” and provides, in full:
    “a) Subcontractor shall, at its own cost and expense [1)] keep the premises free at
    all times from all waste materials, packing materials and other rubbish generated by
    Subcontractor in locations or containers as designated by Contractor, 2) clean and
    remove from its own Work and from all contiguous work areas any soiling, staining,
    mortar, plaster, concrete, or dirt resulting from the execution of its Work in each area,
    3) perform such cleaning as may be required to leave the Work area ‘broom clean’ and
    4) at the completion of its Work, remove all of its tools, equipment, scaffolds, shanties,
    and surplus materials and perform final clean-up as required by Contractor.
    b) If the Subcontractor is lax in its cleaning, the Contractor will give notice to the
    Subcontractor’s field personnel and written notice to the Subcontractor that the
    cleaning is not being kept current. If after twenty four hours (24) notice, Subcontractor
    has failed to abide with clean-up requirements, Contractor shall perform the
    Subcontractor’s cleaning and backcharge the Subcontractor for the costs.”
    ¶ 74                               IV. Motion for Summary Judgment
    ¶ 75       On July 23, 2013, defendant filed a motion for summary judgment. Defendant argued, first,
    that plaintiffs had provided no evidence establishing that the debris upon which plaintiff
    stepped was created by defendant or by Old Veteran and, therefore, defendant owed no duty to
    plaintiff. Instead, defendant claimed that all facts pointed to City employees as the source of
    the nail-embedded piece of wood. Defendant also argued that it owed no duty to plaintiff
    because it had delegated safety and housekeeping responsibilities to Old Veteran.
    ¶ 76       On August 26, 2013, the trial court granted defendant’s motion for summary judgment.
    The court noted that there was no allegation that defendant created the debris that caused
    - 11 -
    plaintiff’s injury and that defendant’s liability was based on its role as the general contractor of
    the project and its duty to maintain safety at the worksite. The court found that while plaintiff
    referenced the duties delineated in the contract between defendant and the City, it was the
    subcontract between defendant and Old Veteran that was at issue. The subcontract between
    defendant and Old Veteran delegated the responsibility for jobsite safety and cleanup to Old
    Veteran; the court also noted that the contract between the City and defendant did not prohibit
    this delegation of duty.
    ¶ 77       The court also noted that a general contractor requiring OSHA compliance by a
    subcontractor did not create a duty on the part of the general contractor to ensure that those
    standards were met, and there was nothing in the record to indicate that defendant in any way
    attempted to assert or exercise any control over the safety or cleanliness of Old Veteran’s
    work. Consequently, the court found that defendant owed no duty to plaintiff and that
    summary judgment in defendant’s favor was appropriate. The court further found that there
    was no just reason to delay the enforcement or appeal of its order.
    ¶ 78       Plaintiffs filed a motion to reconsider on September 25, 2013, which was denied on
    October 4, 2013. This appeal follows.
    ¶ 79                                             ANALYSIS
    ¶ 80        On appeal, plaintiffs argue that the trial court erred in granting summary judgment in
    defendant’s favor on the basis that defendant owed no duty to plaintiff. As an initial matter,
    defendant raises several issues with plaintiffs’ brief on appeal, primarily with the brief’s lack
    of citation to the record on appeal. Defendant argues that plaintiffs’ statement of facts violates
    Illinois Supreme Court Rule 341(h)(6) (eff. Feb. 6, 2013), which requires the statement of facts
    to be “stated accurately and fairly without argument or comment, and with appropriate
    reference to the pages of record on appeal,” and makes a similar argument with respect to
    several areas of the argument portion of plaintiffs’ brief. Plaintiffs’ brief lacks citations to the
    record in the first six pages of the statement of facts and the recitation of the provisions of
    defendant’s contract with the City combines portions of several provisions summarized under
    plaintiffs’ descriptive captions. While we may strike the statement of facts or dismiss the
    appeal due to violations of Rule 341(h)(6), we will not do so in the instant case as plaintiffs’
    violations do not hinder our review. See Szczesniak v. CJC Auto Parts, Inc., 
    2014 IL App (2d) 130636
    , ¶ 8. However, we will disregard the noncompliant portions of plaintiffs’ statement of
    facts in our review. Szczesniak, 
    2014 IL App (2d) 130636
    , ¶ 8. We reach a similar result as to
    the lack of citations in the argument portion of plaintiffs’ brief. We now turn to the merits of
    plaintiffs’ appeal.
    ¶ 81        A trial court is permitted to grant summary judgment only “if the pleadings, depositions,
    and admissions on file, together with the affidavits, if any, show that there is no genuine issue
    as to any material fact and that the moving party is entitled to a judgment as a matter of law.”
    735 ILCS 5/2-1005(c) (West 2008). The trial court must view these documents and exhibits in
    the light most favorable to the nonmoving party. Home Insurance Co. v. Cincinnati Insurance
    Co., 
    213 Ill. 2d 307
    , 315 (2004). We review a trial court’s decision to grant a motion for
    summary judgment de novo. Outboard Marine Corp. v. Liberty Mutual Insurance Co., 
    154 Ill. 2d
    90, 102 (1992). De novo consideration means we perform the same analysis that a trial
    judge would perform. Khan v. BDO Seidman, LLP, 
    408 Ill. App. 3d 564
    , 578 (2011).
    - 12 -
    ¶ 82        “Summary judgment is a drastic measure and should only be granted if the movant’s right
    to judgment is clear and free from doubt.” Outboard Marine Corp., 
    154 Ill. 2d
    at 102.
    However, “[m]ere speculation, conjecture, or guess is insufficient to withstand summary
    judgment.” Sorce v. Naperville Jeep Eagle, Inc., 
    309 Ill. App. 3d 313
    , 328 (1999). A defendant
    moving for summary judgment bears the initial burden of proof. Nedzvekas v. Fung, 374 Ill.
    App. 3d 618, 624 (2007). The defendant may meet his burden of proof either by affirmatively
    showing that some element of the case must be resolved in his favor or by establishing “ ‘that
    there is an absence of evidence to support the nonmoving party’s case.’ ” Nedzvekas, 374 Ill.
    App. 3d at 624 (quoting Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 325 (1986)). In other words,
    there is no evidence to support the plaintiffs’ complaint.
    ¶ 83        “ ‘The purpose of summary judgment is not to try an issue of fact but *** to determine
    whether a triable issue of fact exists.’ ” Schrager v. North Community Bank, 
    328 Ill. App. 3d 696
    , 708 (2002) (quoting Luu v. Kim, 
    323 Ill. App. 3d 946
    , 952 (2001)). We may affirm on any
    basis appearing in the record, whether or not the trial court relied on that basis or its reasoning
    was correct. Ray Dancer, Inc. v. DMC Corp., 
    230 Ill. App. 3d 40
    , 50 (1992).
    ¶ 84        In the case at bar, plaintiffs challenge the trial court’s finding that defendant owed plaintiff
    no duty as a matter of law. Plaintiffs’ theory of recovery is grounded in common-law
    negligence. “The essential elements of a cause of action based on common-law negligence are
    the existence of a duty owed by the defendant to the plaintiff, the breach of that duty, and the
    injury proximately caused by that breach.” Cochran v. George Sollitt Construction Co., 
    358 Ill. App. 3d 865
    , 873 (2005) (citing Ward v. K mart Corp., 
    136 Ill. 2d 132
    , 140 (1990)). As
    noted, here, plaintiffs’ arguments focus on the duty element. “Whether there is common law
    negligence, in the context of a construction-related injury, is analyzed under section 414 of the
    Restatement (Second) of Torts.” Kotecki v. Walsh Construction Co., 
    333 Ill. App. 3d 583
    , 587
    (2002) (citing Bokodi v. Foster Wheeler Robbins, Inc., 
    312 Ill. App. 3d 1051
    , 1057-58 (2000)).
    ¶ 85                         I. Section 414 of the Restatement (Second) of Torts
    ¶ 86       “Generally, one who employs an independent contractor is not liable for the latter’s acts or
    omissions.” Joyce v. Mastri, 
    371 Ill. App. 3d 64
    , 73 (2007) (citing Downs v. Steel & Craft
    Builders, Inc., 
    358 Ill. App. 3d 201
    , 204-05 (2005)). However, section 414 of the Restatement
    (Second) of Torts (1965), “which has long been recognized as an expression of law in Illinois,”
    provides an exception to the general rule, referred to as the “retained control” exception.
    
    Cochran, 358 Ill. App. 3d at 873-74
    (citing Larson v. Commonwealth Edison Co., 
    33 Ill. 2d 316
    , 325 (1965)); Calloway v. Bovis Lend Lease, Inc., 
    2013 IL App (1st) 112746
    , ¶ 47.
    ¶ 87       Section 414 provides:
    “One who entrusts work to an independent contractor, but who retains the control
    of any part of the work, is subject to liability for physical harm to others for whose
    safety the employer owes a duty to exercise reasonable care, which is caused by his
    failure to exercise his control with reasonable care.” Restatement (Second) of Torts
    § 414 (1965).
    ¶ 88       “The Restatement describes a continuum of control, explaining [that] the employer is
    subject to liability as master under the principles of agency where the employer retains control
    over the operative detail of any part of the contractor’s work. [Citation.] If the employer retains
    only supervisory control, i.e., power to direct the order in which work is done, or to forbid its
    being done in a dangerous manner, then the employer is subject to liability under section 414
    - 13 -
    unless he exercised supervisory control with reasonable care.” Martens v. MCL Construction
    Corp., 
    347 Ill. App. 3d 303
    , 314 (2004) (citing Restatement (Second) of Torts § 414, cmt. a
    (1965)). Thus, “[a]s comment a to section 414 clarifies, the general contractor, by retaining
    control over the operative details of its subcontractor’s work, may become vicariously liable
    for the subcontractor’s negligence; alternatively, even in the absence of such control, the
    general contractor may be directly liable for not exercising his supervisory control with
    reasonable care.” 
    Cochran, 358 Ill. App. 3d at 874
    .
    ¶ 89        However, the “retained control” concept is limited by comment c to section 414:
    “In order for the rule stated in this Section to apply, the employer must have
    retained at least some degree of control over the manner in which the work is done. It is
    not enough that he has merely a general right to order the work stopped or resumed, to
    inspect its progress or to receive reports, to make suggestions or recommendations
    which need not necessarily be followed, or to prescribe alterations and deviations. Such
    a general right is usually reserved to employers, but it does not mean that the contractor
    is controlled as to his methods of work, or as to operative detail. There must be such a
    retention of a right of supervision that the contractor is not entirely free to do the work
    in his own way.” Restatement (Second) of Torts § 414, cmt. c (1965).
    Thus, negligence and, specifically, the existence of a duty under section 414 “turn[ ] on
    whether the defendant controls the work in such a manner that he should be held liable.”
    
    Martens, 347 Ill. App. 3d at 315
    ; Calloway, 
    2013 IL App (1st) 112746
    , ¶ 50. “Whether a
    contractor retained such control over a subcontractor’s work so as to give rise to liability is an
    issue reserved for a trier of fact, unless the evidence presented is insufficient to create a factual
    question.” Joyce v. Mastri, 
    371 Ill. App. 3d 64
    , 74 (2007) (citing Bokodi v. Foster Wheeler
    Robbins, Inc., 
    312 Ill. App. 3d 1051
    , 1059 (2000)).
    ¶ 90        In the case at bar, the trial court found that defendant had not retained control over Old
    Veteran’s work as a matter of law. On appeal, plaintiffs argue that defendant exerted sufficient
    control over Old Veteran’s work for direct liability under section 414. We note that while
    plaintiffs make a reference to vicarious liability in the “Issues Presented for Review” section of
    their brief, they make no arguments concerning vicarious liability in the argument section of
    their brief. Accordingly, we do not consider it in our analysis. Roiser v. Cascade Mountain,
    Inc., 
    367 Ill. App. 3d 559
    , 568 (2006) (by failing to offer supporting legal authority or “any
    reasoned argument,” plaintiffs waived consideration of their theory for asserting personal
    jurisdiction over defendants); People v. Ward, 
    215 Ill. 2d 317
    , 332 (2005) (“point raised in a
    brief but not supported by citation to relevant authority *** is therefore forfeited”); In re
    Marriage of Bates, 
    212 Ill. 2d 489
    , 517 (2004) (“A reviewing court is entitled to have issues
    clearly defined with relevant authority cited.”); Ferguson v. Bill Berger Associates, Inc., 
    302 Ill. App. 3d 61
    , 78 (1998) (“it is not necessary to decide this question since the defendant has
    waived the issue” by failing to offer case citation or other support as Supreme Court Rule 341
    requires); Ill. S. Ct. R. 341(h)(7) (eff. Feb. 6, 2013) (argument in appellate brief must be
    supported by citation to legal authority and factual record).
    ¶ 91                              II. Direct Liability Under Section 414
    ¶ 92      As noted, “the general contractor may be directly liable for not exercising his supervisory
    control with reasonable care,” even in the absence of control sufficient to subject the general
    contractor to vicarious liability. 
    Cochran, 358 Ill. App. 3d at 874
    . Here, plaintiffs argue that
    - 14 -
    they presented at least a question of fact as to direct liability under section 414 because (1) the
    contract between defendant and the City contemplated close supervision and control by
    defendant and (2) defendant took an active role in scheduling and coordinating the work and in
    safety matters.
    ¶ 93        Plaintiffs first argue that the trial court erred in not giving any consideration to the contract
    between defendant and the City, which provided that even if the City consented to the general
    contractor’s use of a subcontractor (as occurred in the instant case), “in no [event] shall such
    consent relieve the Contractor from his obligations, or change the terms of the Contract.” We
    do not find this argument persuasive.
    ¶ 94        While defendant’s contract with the City made defendant responsible for the safety of the
    work, defendant’s subcontract with Old Veteran delegated this duty to Old Veteran. Plaintiffs
    point to no provision of the contract prohibiting such a delegation. The subcontract provides
    that the provisions of the contract between the City and defendant were binding upon Old
    Veteran and expressly provides that “Subcontractor shall be solely responsible to assure the
    safety of its own equipment, appliances, material, and working conditions, techniques, and
    procedures, and Contractor is not responsible in any manner for the safety of Subcontractor’s
    Work.” “The best indicator of whether a contractor has retained control over the
    subcontractor’s work is the parties’ contract, if one exists.” Downs v. Steel & Craft Builders,
    Inc., 
    358 Ill. App. 3d 201
    , 205 (2005); Wilfong v. L.J. Dodd Construction, 
    401 Ill. App. 3d 1044
    , 1061 (2010). Here, the contract demonstrates that defendant did not retain control over
    Old Veteran’s conduct. Accordingly, the trial court did not err in giving the subcontract more
    weight than the contract between defendant and the City.
    ¶ 95        Furthermore, we cannot agree with plaintiffs’ contention that defendant took an active role
    in scheduling and coordinating the work and in safety matters. While defendant coordinated
    the schedules of the subcontractors, this is not sufficient for direct liability. The deposition
    testimony indicates that defendant never directed the manner in which Old Veteran employees
    performed their work. For instance, Swart, defendant’s superintendent, testified that on the day
    of plaintiff’s accident, he observed Old Veteran’s workers for approximately five minutes,
    “[j]ust long enough to make sure they were there on site doing what I needed,” which was
    cleaning out the interior of the elevator shaft. Swart then generally checked the stairwell,
    which was empty due to the rain, and sat in his vehicle completing paperwork and making
    phone calls. Additionally, Maldonado, the owner of Old Veteran, testified that Swart did not
    tell Old Veteran how to do its work and did not direct the means and methods of the work. The
    two bricklayers responsible for extending the elevator shaft, Noble and Norwood, testified that
    they did not speak to anyone from defendant’s office and did not even know who Swart or Roy
    were; they further testified that they received direction only from Old Veteran’s
    superintendent. Accordingly, there is no evidence that Swart or anyone else from defendant’s
    office ever directed the manner in which Old Veteran workers performed their work.
    ¶ 96        We find the cases relied on by plaintiffs to be factually distinguishable. For instance, in
    Bokodi v. Foster Wheeler Robbins, Inc., 
    312 Ill. App. 3d 1051
    , 1063 (2000), the subcontract
    between the general contractor and the subcontractor purported to leave the subcontractor in
    control of its work, but nevertheless “went to great lengths to control the safety standards at the
    work site.” Additionally, the general contractor’s actions “indicated a substantial level of
    involvement in the incidental activities at the work site,” with a full-time safety manager
    conducting weekly safety meetings and checking for compliance, as well as having the power
    - 15 -
    to halt the subcontractors’ work if there were safety violations. 
    Bokodi, 312 Ill. App. 3d at 1063
    . The general contractor was also authorized “to instruct the subcontractors’ employees to
    comply with safety standards in even the most minute details.” 
    Bokodi, 312 Ill. App. 3d at 1063
    . Finally, “due to the fact that defendants were constantly monitoring this work site,” they
    should have known of the methods employed in the case that led to the plaintiff’s injury.
    
    Bokodi, 312 Ill. App. 3d at 1063
    .
    ¶ 97         Similarly, in Wilkerson v. Paul H. Schwendener, Inc., 
    379 Ill. App. 3d 491
    , 497 (2008),
    “[a]lthough the contract between Monarch [(the subcontractor)] and defendant [(the general
    contractor)] seemingly left to Monarch control of the operative details of its work and the
    safety of its employees, defendant’s actions on the jobsite show defendant retained more than a
    general right of supervision.” The court specifically pointed to a letter asserting the
    defendant’s discretionary authority to stop the subcontractor’s work as the “best evidence” of
    the control, and also noted that the subcontractor had a contractual obligation to attend safety
    meetings, to comply with the defendant’s list of 21 safety procedures, and to submit for the
    defendant’s approval a site-specific safety plan and minutes of the subcontractor’s own weekly
    safety meetings. 
    Wilkerson, 379 Ill. App. 3d at 497
    .
    ¶ 98         Likewise, in Aguirre v. Turner Construction Co., 
    501 F.3d 825
    , 831 (7th Cir. 2007), the
    Seventh Circuit noted that, as in Bokodi, the subcontract placed the subcontractor in control of
    its work but the actions of the general contractor demonstrated retained control. The court
    pointed to specific safety and design requirements, regular monitoring and the authority to halt
    unsafe work, and further noted that the general contractor required the subcontractor to follow
    23 rules specific to scaffold construction and that the general contractor had imposed specific
    alternative design requirements on the scaffold that led to the plaintiff’s injury. 
    Aguirre, 501 F.3d at 830-31
    .
    ¶ 99         In the case at bar, by contrast to the three cases cited by plaintiffs, the subcontract leaves to
    Old Veteran the control of its work and does not purport to control the safety standards at the
    work site. Indeed, the subcontract specifically notes that “neither Contractor nor Architect will
    make continuous or exhaustive inspections to assure Subcontractor’s compliance with
    applicable safety rules, regulations or requirements,” making the subcontract almost the
    opposite of the one at issue in Bokodi. Additionally, there was no evidence that anyone from
    defendant’s office conducted safety meetings or attempted to control safety in any way.
    Finally, there was no evidence that anyone from defendant’s office was aware of any debris
    left on the roof.
    ¶ 100        Finally, we note that there is no evidence that defendant knew or should have known of the
    alleged safety violation. “According to comment b to section 414, the general contractor’s
    knowledge, actual or constructive, of the unsafe work methods or a dangerous condition is a
    precondition to direct liability.” 
    Cochran, 358 Ill. App. 3d at 879-80
    ; Lee v. Six Flags Theme
    Parks, Inc., 
    2014 IL App (1st) 130771
    , ¶ 102; Calderon v. Residential Homes of America, Inc.,
    
    381 Ill. App. 3d 333
    , 347 (2008). Thus, in Cochran, we found that the general contractor was
    not directly liable for a worker’s injury in falling off an unsafe ladder where the unsafe
    condition was in existence for an hour at most and the general contractor had no knowledge of
    the unsafe condition. 
    Cochran, 358 Ill. App. 3d at 880
    .
    ¶ 101        In the case at bar, we note that it is not clear whether the nail was even left by Old Veteran
    employees or the precise day that the nail was left on the roof, as no one testified that he or she
    was actually present when the nail was left on the roof. Additionally, none of defendant’s
    - 16 -
    employees went onto the roof until after plaintiff’s accident, when Swart went to the roof to try
    to locate the nail. Accordingly, in the absence of any evidence as to actual or constructive
    knowledge of Old Veteran’s allegedly unsafe work methods, there can be no direct liability
    against defendant.
    ¶ 102                                          CONCLUSION
    ¶ 103       For the reasons set forth above, the trial court did not err in granting summary judgment in
    defendant’s favor.
    ¶ 104      Affirmed.
    - 17 -