Illinois Power Company v. Illinois Commerce Commission ( 2008 )


Menu:
  •                              No. 3-06-0879
    consolidated with No. 3-07-0569
    _________________________________________________________________
    Filed April 11, 2008
    IN THE
    APPELLATE COURT OF ILLINOIS
    THIRD DISTRICT
    A.D., 2008
    ILLINOIS POWER COMPANY,        )
    d/b/a/ AMERENIP,               )
    ) Petition for Review of an
    Petitioner-Appellant,     ) Order of the Illinois
    ) Commerce Commission in
    v.                        ) Docket No. 03-0699 and
    ) Docket No. 04-0677.
    ILLINOIS COMMERCE COMMISSION   )
    and DYNEGY, INC.,              )
    )
    Respondents-Appellees.    )
    _________________________________________________________________
    JUSTICE LYTTON delivered the opinion of the court:
    _________________________________________________________________
    The   petitioner,    Illinois   Power   Company,   d/b/a   AmerenIP
    (Illinois Power), seek review of two orders issued by the Illinois
    Commerce Commission (Commission), finding that Illinois Power did
    not act prudently in remediating deliverability issues at its
    natural gas storage facility in Hillsboro, Illinois. As a result,
    the Commission concluded that the costs Illinois Power incurred to
    obtain natural gas to reinject the field in 2003 and 2004 could not
    be recovered from its customers. On appeal, Illinois Power argues
    that (1) the Commission’s findings are not supported by substantial
    evidence in the record, and (2) the Commission improperly applied
    the prudence standard.     We affirm.
    I.     Commerce Commission Proceedings
    This consolidated appeal concerns Illinois Power’s Hillsboro
    natural gas storage facility.         The Hillsboro facility is an
    underground reservoir that contains two different storage layers.
    The top layer of the reservoir contains working gas.             Working gas
    is the volume of gas in the reservoir that is injected for storage
    during the summer months and then withdrawn to be supplied to
    customers in the winter months.         The bottom layer houses base gas
    which is the volume of gas required to provide adequate pressure to
    cycle the working gas.         Generally, a utility does not remove the
    base gas from a reservoir field.
    Following an expansion project in 1993, Illinois Power began
    experiencing reduced inventory and deliverability problems at the
    Hillsboro plant and inadvertently began removing base gas from the
    field.   After years of investigation, the company determined that
    the problems were caused by improper metering. In 2003, they began
    reinjecting    the   field     to   restore   the    depleted    natural   gas
    inventory.    The reinjection process was not completed until the
    spring of 2004.      Pursuant to the Public Utilities Act (Act) (220
    ILCS    5/10-201   et   seq.    (West   2002)),     Illinois    Power   passed
    $6,879,109 in 2003 and $2,979,849 in 2004 onto its customers in the
    form of purchase gas adjustment (PGA) tariffs to recover the costs
    of the reinjection process.
    In November of 2003, the Commission commenced reconciliation
    hearings in accordance with section 9-220 of the Act and directed
    Illinois Power to present evidence showing its reconciliation of
    PGA tariff revenues with the actual cost of gas supplies prudently
    incurred for the 12 month period ending December 31, 2003 (Docket
    No. 03-0699).      One year later, the Commission initiated a second
    reconciliation proceeding directing Illinois Power to present
    2
    evidence for the 12 month period ending December 31, 2004 (Docket
    No. 04-0677).   The evidence presented at both proceedings was
    substantially the same.
    Illinois Power engineers and expert witnesses testified that
    the expansion of the Hillsboro field increased the working gas
    inventory from 3.1 billion cubic feet (Bcf) to 7.6 Bcf and
    increased the peak day capacity (the amount of gas to be withdrawn
    per day) from 50,000 million cubic feet (Mcf) to 125,000 Mcf.   The
    company operated Hillsboro at those levels for the 1993-1994
    season. In subsequent winters, however, Illinois Power was unable
    to withdraw the full amount of gas that had been previously
    injected into the field.
    Given the actions taken to expand the storage reservoir, the
    possibility existed that the reservoir was physically breached
    during the expansion process, thereby allowing the newly injected
    gas to escape or migrate into other areas of the reservoir from
    which the gas could not be accessed.       Other potential causes
    involved gas migration, gas leaks to the surface, or damage to the
    intake and withdrawing wells, which would have prevented efficient
    production of gas inventory.    Illinois Power conducted numerous
    tests in an attempt to determine the cause of the problem.      The
    company was concerned about taking corrective action without first
    properly identifying the cause of the problem.
    The company’s experts testified that because of the expansion,
    it was logical and appropriate to focus initially on a reservoir or
    structural defect.   Thus, Illinois Power decided to pursue an
    extensive structural investigation beginning in 1997.     Illinois
    3
    Power had a vertical seismic profile of the reservoir field
    prepared by outside consultants. This study concluded that a more
    detailed three dimensional seismic analyses was necessary.                       The
    preliminary results of the 3-D seismic study indicated                          that
    approximately 3.5 Bcf of gas had migrated to another structure
    northeast of the field.     In November 2000, based on the results of
    this study, Illinois Power drilled a new well but found no
    substructure below.        In light of these inconsistent findings,
    Illinois Power asked the consultants to reevaluate the 3-D seismic
    analysis. After collecting additional information and reprocessing
    the 3-D seismic data, the firm concluded that the additional
    structure that had been thought to exist to the northeast of the
    Hillsboro field did not exist. This conclusion was reached in the
    fall of 2001.
    While investigating the possibility of structural causes or
    reservoir     problems,    Illinois       Power    also      retained    Peterson
    Engineering to conduct an audit of the metering instruments at
    Hillsboro.    Peterson was retained in August of 1999 and issued its
    finding in December of 1999.        In its report, Peterson identified
    two problems with the Hillsboro meters.                 First, two new turbine
    injection meters were over-registering gas volumes under certain
    operating    conditions.      Specifically,        when      the   nearby   plant
    compressors operated at certain levels, they caused the meters to
    over-spin, thereby recording a greater amount of gas as having been
    injected than was actually passing through the meter. The turbine
    meter   over-registration     was     calculated        to   be    26%   when    the
    compressors    were   operating     at     50%    but    only     1.7%   when    the
    4
    compressors were operating at 100% loadings.                 Second, the orifice
    meter on one of the four withdrawal wells had an opening that was
    smaller than the size value stamped on the orifice plate.                      The
    diameter stamped on the plate was 10% larger than its actual
    diameter.     This meant that less gas was being withdrawn from the
    field that had been believed.          In basic terms, there was less gas
    going in and less gas coming out than the meters were indicating.
    According to Illinois Power, the amount of error on the
    withdrawal meter could be easily calculated based on the different
    sized orifice measurements.          However, the company maintained that
    the injection meter over-registration could not be as easily
    determined.     Illinois Power attempted to calculate the loss by
    estimating when the compressors were operating at certain levels.
    Using this estimation method, Illinois Power initially determined
    that   the    two   metering   errors       offset    each     other.     It   was
    subsequently discovered that the injection metering error was much
    larger than the withdrawal metering error.                   Illinois Power made
    several meter operating corrections to the facility to eliminate
    both meter measurement error.          These changes were implemented in
    May 2000.
    In   early   spring   2003,    Illinois       Power    conducted   another
    exhaustive set of structural analyses of the reservoir, including
    (1) neutron log analyses, (2) flame ionization surveys, (3) field
    metering     versus   plant    metering       comparisons,       (4)    reservoir
    performance tests, and (5) volumetric analyses.                     These tests
    indicated that the working gas and base gas volumes in the
    Hillsboro field had been significantly depleted over time due to
    5
    the injection metering problem.
    As a result, Illinois Power developed an estimate of the total
    gas inventory shortfall that had resulted from the metering error
    and created a plan to reinject gas to restore the Hillsboro base
    gas volume and working gas volume to the original post-expansion
    amounts.     Illinois Power commenced reinjection in the spring of
    2003.
    Commission Staff presented evidence in response to Illinois
    Power’s position. Eric Lounsberry, an engineer in the engineering
    department of the Commission’s energy division, testified that the
    information available to Illinois Power in 1999 pointed to metering
    errors as the most likely cause of the deliverability problems.
    Lounsberry    stated   that   if   Illinois   Power   had   used   existing
    information and available well data, it would have discovered that
    an inventory shortfall was the primary problem.
    First, Lounsberry testified that Illinois Power was aware of
    problems with its storage field metering equipment as early as
    1996 and was also aware of similar deliverability issues at another
    Illinois Power field, the Shanghai storage field.            The Peterson
    study noted that the company was aware in 1996 that computed
    volumes from the plant metering and well metering instruments had
    not been satisfactorily reconciled at Hillsboro or the Shanghai
    plant.     Lounsberry stated that these two similar situations
    indicated that Illinois Power’s ability to identify the root cause
    of the problem was inadequate.
    Second, Lounsberry asserted that the 1994 well data from the
    intake/withdrawal wells at Hillsboro could have been accurately
    6
    extrapolated and would have quickly determined that the intake
    metering error was much larger than the withdrawal error.                 He
    testified that Illinois Power had actually integrated some of the
    daily well measurement to calculate the volume of gas injected and
    that the company could have used that data to integrate all of the
    measurements between 1994 and 1999. He stated that the integrated
    volume    measurements   would    have   been   more   accurate   than   the
    estimation method used by Illinois Power and would have immediately
    alerted the company that the injection meter error was the source
    of the deliverability issue. Lounsberry concluded that if Illinois
    Power had conducted a more thorough review of the metering issues
    after the Peterson study was completed, it would have discovered
    the true magnitude of the injection metering error and could have
    started replacing the gas in the Hillsboro field during the 2000
    season.
    II.   The Commission Orders
    The Commission issued orders finding Illinois Power’s actions
    imprudent in both cases.         In docket No. 03-0699, the Commission
    defined prudence as "that standard of care which a reasonable
    person would be expected to exercise under the same circumstances
    encountered by utility management at the time decisions had to be
    made." Applying this standard, the Commission determined that the
    delay in discovering the meter error and Illinois Power’s decision
    to delay reinjecting the Hillsboro storage field were imprudent.
    The Commission agreed with the Staff’s assessment that Illinois
    Power should have started replacing the inventory in the Hillsboro
    field during the 2000 season.
    7
    The Commission was also persuaded that the Staff’s "overall
    storage concerns" were indications that Illinois Power was less
    than prudent at the Hillsboro site. The Commission order provided:
    "In   the    Commission’s    view,    [Illinois    Power]
    imprudently selected the easy path when it discovered
    there might be a problem at Hillsboro.           It appears that
    with inadequate thought, [Illinois Power] decided the
    problems at Hillsboro must be structural and began hiring
    consultants to identify the exact nature of the problem.
    This followed the ineffective pattern established for the
    Shanghai Storage Field. *** [C]learly something is amiss
    in   [Illinois    Power’s]   operations    and    management   of
    storage fields."
    In conclusion, the Commission held that Illinois Power was
    imprudent in its operation of the Hillsboro field because it "(1)
    failed to conduct a thorough study of the injection error at the
    time it was identified, (2) failed to conduct any inspections to
    assure that the orifice meters were working properly, [and] (3)
    failed to begin returning the inventory to the field when the
    working gas volumes fell below the pre-expansion volume of 3.1 Bcf
    after the 1999-2000 winter season."      Consequently, the Commission
    ruled that $6,870,109 of incurred costs related to Illinois Power’s
    remediation of the Hillsboro depleted gas levels could not be
    recovered from its customers through PGA tariffs.
    The order in docket No. 04-0677 reiterated most of the
    findings contained in the 2003 case. Based on the evidence adduced
    at the 2004 hearings and premised upon the Commission’s order
    8
    entered in docket No. 03-0699, the Commission found that Illinois
    Power imprudently incurred $2,979,849 in additional gas costs in
    2004.
    III.   STANDARD OF REVIEW
    An appellate court’s jurisdiction of direct appeals from the
    Commission is governed by section 10-201 of the Act (220 ILCS 5/10-
    201 (West 2002)).   Section 10-201(e)(iv) states that we may only
    reverse a Commission order if we conclude that "[t]he findings of
    the Commission are not supported by substantial evidence based on
    the entire record of evidence presented to or before the Commission
    for and against such *** order."       220 ILCS 5/10-201(e)(iv) (West
    2002).   The Commission’s findings of fact are to be accepted as
    prima facie true.    Business and Professional People for Public
    Interest v. Illinois Commerce Comm’n, 
    146 Ill. 2d 175
    (1991); 220
    ILCS 5/10-201(d) (West 2002).      Merely showing that the evidence
    presented would support a different conclusion than the one reached
    by the Commission is not sufficient.       Rather, the appellant must
    affirmatively demonstrate that the opposite conclusion is "clearly
    evident."   Continental Mobile Telephone Co. v. Illinois Commerce
    Comm’n, 
    269 Ill. App. 3d 161
    (1994).
    IV.   ANALYSIS
    The General Assembly allows utilities to recover their gas
    cost directly from the consumer through purchase gas adjustments
    (PGA) clauses.   See 220 ILCS 5/9-220 (West 2002).    The Act clearly
    places upon those utilities taking advantage of a PGA clause the
    burden of proving the prudence of their gas purchases during the
    course of yearly reconciliation proceedings.        220 ILCS 5/9-220
    9
    (West 2002).    Prudence is not defined within the Act.         Commerce
    Commission proceedings and our court have defined prudence as "that
    standard of care which a reasonable person would be expected to
    exercise under the same circumstances encountered by utility
    management at the time decisions had to be made."               Illinois
    Commerce Comm’n v. Commonwealth Edison Co., Docket No. 84-0395, p.
    17 (1987); Illinois Power Co. v. Commerce Comm’n, 
    339 Ill. App. 3d 425
    , 428 (2003).   In determining whether a judgment was prudently
    made, only those facts available at the time judgment was exercised
    can be considered. Illinois Power Co. v. Commerce Comm’n, 245 Ill.
    App. 3d 367 (1993).
    A.
    Illinois Power claims that the Commission’s order should be
    reversed because the record demonstrates that it met the imposed
    burden by showing that the gas costs it incurred in 2003 and 2004
    as a result of the reduction of the withdrawal capacity were
    prudent. First, Illinois Power argues that substantial evidence in
    the record shows that its decisions and actions were reasonable
    when made based on the information known to management at the time.
    Second, Illinois Power claims that to begin reinjecting replacement
    gas   into   Hillsboro   in   2000,    when   the   company   was   still
    investigating structural and geological issues, would have been
    imprudent.   Finally, Illinois Power complains that the order must
    be reversed because the Commission’s prudence determination was
    based, in part, on unsupported concerns at the Shanghai storage
    facility.
    The Commission’s findings of fact are to be accepted as prima
    10
    facie true, and the burden of proof on all issues raised on appeal
    is on the party appealing the Commission’s order. See Business and
    Professional People, 
    146 Ill. 2d 175
    (1991); see also 220 ILCS
    5/10-201(d) (West 2002). Here, nothing in the record in docket No.
    03-0699 or docket No.      04-0677 demonstrates that an opposite
    conclusion is clearly evident.
    Initially, the record indicates that Illinois Power failed to
    promptly pursue potential metering problems that were plainly
    stated and thoroughly analyzed in the 1999 Peterson report.            The
    Peterson study further noted that the company was aware in 1996
    that computed volumes from the facility metering and well metering
    had not been satisfactorily reconciled since 1994.         At that time,
    Illinois Power was also aware of injection metering instrument
    errors at the Shanghai station.
    Evidence further indicated that Illinois Power had accurate
    injection well data from 1994.         That information could have been
    integrated to determine an accurate estimate of the total amount of
    gas that had been injected into the field between 1994 and 1999.
    Illinois Power claims that all of the data from those years had not
    been extrapolated and was therefore unrealiable.         However, no one
    on behalf of Illinois Power testified that it would have been
    unduly burdensome to integrate the data to use as a comparison. As
    a   means   of   verification,   the    data   was   available   and   was
    sufficiently reliable.     In addition, Illinois Power neglected to
    use those years for which it actually had integrated values. Given
    the extent to which it tested the structural integrity of the
    reservoir, it seems unreasonable to have ignored the 1994 well data
    11
    as a means of testing the metering measurements of the reservoir.
    In light of these facts, the Commission’s decision that Illinois
    Power acted imprudently based on the information known to the
    company at the time is sufficiently supported by the records.
    Next, we disagree with Illinois Power’s assertion that it
    would have been imprudent to reinject the field with natural gas
    inventory in 2000 when working gas volumes fell below pre-expansion
    levels.    The record demonstrates that Illinois Power pursued the
    potential structural and geological issues vigorously beginning in
    1996 and even repeated and reassessed numerous geological tests
    based on their assumption that the problem was caused by the
    structural identity of the reservoir. However, beginning in 1999,
    several reports and analyses indicated that the deliverability
    issue was caused by a field metering error rather than a structural
    one.    Thus, the Staff claimed that once Illinois Power corrected
    the metering errors in 2000, testing those corrections during the
    2000 injection season would have been appropriate.    Lounsberry’s
    testimony showed that many, if not most, of Illinois Power’s
    concerns with reinjecting the field too soon were unfounded based
    on a review of the 1999 Petersen report and the inconsistent 3-D
    seismic data on hand. Thus, the Commission position that Illinois
    Power should have attempted to reinject the field in 2000 to test
    the metering corrections is not unreasonable.     By waiting three
    more years before even attempting to begin replacement efforts,
    Illinois Power unnecessarily depleted the base gas volumes of the
    reservoir and exponentially increased the cost of injection. Based
    on the entire record in both proceedings, a conclusion that
    12
    Illinois Power was prudent is not clearly evident.
    Last, we find that the Commission properly considered the
    deliverability     issues    at   Illinois    Power’s      Shanghai    storage
    facility.    We noted that the Act does not prohibit the Commission
    from considering power utilities’ actions beyond the specific
    conduct in question.        See 220 ILCS 5/9-201 et seq. (West 2002).
    Thus, when the Staff provided testimony of a similar metering error
    that arose at the Shanghai field, the Commission did not err in
    reviewing those "concerns" in its decision.             Further, we believe
    Commission consideration was appropriate based on the similar
    deliverability issues in the Shanghai case.
    In Illinois Commerce Comm’n v. Illinois Power Co., Docket No.
    01-0701, 2004 Ill. Puc Lexis 101 (2004), the Commission filed a
    reconciliation proceeding involving Illinois Power’s Shanghai field
    for the year ending in December of 2001.           As in this case, there
    was a deliverability issue which was eventually associated with an
    injection metering problem. The error in that case caused Illinois
    Power to withdraw approximately 743,313 Mcf of natural gas above
    the meter indications.       The error existed from 1995 until it was
    identified in January 2000.        In that case, the Commission found
    that Illinois Power’s actions "were not imprudent."              The decision
    in that case indicates that by early 2000, Illinois Power had
    discovered    a   metering    error   was    the   cause    of   the   company
    withdrawing 20.6% more gas above what its meters reflected from the
    Shanghai storage field.
    While the Commission was unwilling to find Illinois Power’s
    conduct at the Shanghai facility imprudent in 2001, the issue here
    13
    is whether Illinois Power acted prudently by reserving its decision
    to reinject the Hillsboro field until the summer of 2003. Here, by
    early 2000, Illinois Power had not only the information from the
    Peterson study regarding metering problems at Hillsboro, but the
    knowledge that there had been nearly identical metering problems at
    Shanghai. This information, coupled with the information from the
    well chart data, would have allowed Illinois Power to calculate the
    magnitude of the metering problems in 2000 to the extent necessary
    to begin reinjection much in advance of the 2003-2004 season.           In
    essence, the metering error identified at the Shanghai field in
    2000 undercuts the argument that it was prudent for Illinois Power
    to concentrate its investigation on structural as opposed to
    metering causes beyond the 2000 injection season.                Thus, the
    "overall concerns" presented by the Staff were properly utilized as
    additional support for the Commission’s finding of imprudence.
    B.
    Illinois Power also asks us to consider the Commission’s
    application of the prudence standard.          Illinois Power maintains
    that the Commission created an "after-the-fact" standard of care
    that a reasonable person should have followed in 2000 when deciding
    whether to reinject the Hillsboro field.          We disagree.
    The Commission has stated that in utility cases the prudence
    standard   conforms   to   the   dictionary    definition   of   prudence.
    Business & Professional People for the Public Interest v. Commerce
    Comm’n, 
    279 Ill. App. 3d 824
    (1996).          In Business & Professional
    People, the court noted that prudence is commonly defined as "skill
    or good judgment in the use of 
    resources." 279 Ill. App. 3d at 831
    14
    (citing Webster’s Ninth Collegiate Dictionary 949 (1985)). When we
    apply the prudence standard, only those facts available at the time
    judgment was exercised can be considered, and imprudence cannot be
    sustained by substituting one’s judgment for that of another.
    Illinois Power 
    Co., 339 Ill. App. 3d at 428
    .
    As discussed, the record suggests that the Peterson report
    presented a clear indication that the deliverability issues at
    Hillsboro were due to injection metering problems. That report was
    issued in the fall of 1999.      Illinois Power took the necessary
    actions in 2000 and corrected the metering issues outlined in the
    report. Thus, the Staff’s position that Illinois Power could have
    reinjected the field as early as 2000 is based on facts available
    to Illinois Power in 2000. Accordingly, the Commission’s decision
    that it was imprudent to wait to reinject the field for three more
    years is not based on an after-the-fact record.     It is   supported
    by substantial evidence in the record dating back to 1996 and is
    based on information known to Illinois Power during the 2000
    injection season.
    V.   CONCLUSION
    For the above reasons, we affirm the Commission finding that
    Illinois Power’s decision to forego reinjecting the Hillsboro
    storage field until 2003 was imprudent.     The Commission orders in
    case No. 03-699 and case No. 04-677 are therefore affirmed.
    No. 3-06-879 -- Affirmed.
    No. 3-07-569 -- Affirmed.
    CARTER, J., and MCDADE, PJ., concurring.
    15
    

Document Info

Docket Number: 3-06-0879, 3-07-0569 Cons. Rel

Filed Date: 4/11/2008

Precedential Status: Precedential

Modified Date: 10/22/2015