Kreutzer v. Illinois Commerce Commission ( 2010 )


Menu:
  •                                No. 2-09-0007 Filed: 9-16-10
    ______________________________________________________________________________
    IN THE
    APPELLATE COURT OF ILLINOIS
    SECOND DISTRICT
    _______________________________________________________________________________
    FRANCES KREUTZER, MARIE CARANCI, ) On Petition for Administrative Review
    WILLIAM BYRNE, and LINDA BYRNE,        ) from the Illinois Commerce Commission.
    )
    Petitioners,                     )
    )
    v.                                     ) ICC Case No. 07--0310
    )
    ILLINOIS COMMERCE COMMISSION,          )
    COMMONWEALTH EDISON                    )
    COMPANY, THE VILLAGE OF HUNTLEY, )
    EXELON BUSINESS SERVICES               )
    COMPANY, NEUMANN HOMES, INC.,          )
    INDYMAC BANK, F.S.B., HOWARD           )
    E. REID, and THE VILLAGE OF GILBERTS, )
    )
    Respondents.                     )
    ______________________________________________________________________________
    JUSTICE O'MALLEY delivered the opinion of the court:
    Petitioners, Frances Kreutzer, Marie Caranci, William Byrne, and Linda Byrne, appeal from
    the order of the Illinois Commerce Commission (Commission) granting a certificate of public
    convenience and necessity to respondent Commonwealth Edison Co. (ComEd) for the construction
    of a new electrical transmission line in McHenry and Kane Counties. The line the Commission
    authorized ComEd to construct would cross petitioners' property. We agree with petitioners that the
    evidence before the Commission does not demonstrate the need for the amount of petitioner's
    property that the Commission's order authorized ComEd to seek though condemnation. We
    therefore reverse and remand.
    No. 2--09--0007
    ANALYSIS
    I. Motion to Dismiss the Appeal
    On February 20, 2009, the Commission moved this court to dismiss this appeal for lack of
    jurisdiction. We denied the motion on March 13, 2009. The Commission renews the motion,
    arguing that it was not given timely notice of petitioners' petition for review in this court. The
    Commission points to section 10--201 of the Public Utilities Act (Act) (220 ILCS 5/10--201 (West
    2008)). Section 10--201(a) states:
    "(a) Jurisdiction. Within 35 days from the date that a copy of the order or decision
    sought to be reviewed was served upon the party affected by any order or decision of the
    Commission refusing an application for a rehearing of any rule, regulation, order or decision
    of the Commission, including any order granting or denying interim rate relief, or within 35
    days from the date that a copy of the order or decision sought to be reviewed was served
    upon the party affected by any final order or decision of the Commission upon and after a
    rehearing of any rule, regulation, order or decision of the Commission, including any order
    granting or denying interim rate relief, any person or corporation affected by such rule,
    regulation, order or decision, may appeal to the appellate court of the judicial district in
    which the subject matter of the hearing is situated, or if the subject matter of the hearing is
    situated in more than one district, then of any one of such districts, for the purpose of having
    the reasonableness or lawfulness of the rule, regulation, order or decision inquired into and
    determined." 220 ILCS 5/10--201(a) (West 2008).
    The specific procedures for perfecting an appeal are set forth in section 10--201(b), which states:
    "(b) Pleadings and Record. No proceeding to contest any rule, regulation, decision
    -2-
    No. 2--09--0007
    or order which the Commission is authorized to issue without a hearing and has so issued
    shall be brought in any court unless application shall have been first made to the Commission
    for a hearing thereon and until after such application has been acted upon by the
    Commission, nor shall any person or corporation in any court urge or rely upon any grounds
    not set forth in such application for a hearing before the Commission, but the Commission
    shall decide the questions presented by the application with all possible expedition consistent
    with the duties of the Commission. The party taking such an appeal shall file with the
    Commission written notice of the appeal. The Commission, upon the filing of such notice
    of appeal, shall, within 5 days thereafter, file with the clerk of the appellate court to which
    such appeal is taken a certified copy of the order appealed from and within 20 days thereafter
    the party appealing shall furnish to the Commission either a copy of the transcript of the
    evidence, including exhibits, or enter into a stipulation that only certain questions are
    involved, which transcript or stipulation is to be included in the record provided for in
    Section 10--110 [(220 ILCS 5/10--110 (West 2008))]. The Commission shall certify the
    record and file the same with the clerk of the appellate court to which such appeal is taken
    within 15 days of being furnished the transcript or stipulation. The party serving such notice
    of appeal shall, within 5 days after the service of such notice upon the Commission, file a
    copy of the notice, with proof of service, with the clerk of the court to which such appeal is
    taken, and thereupon the appellate court shall have jurisdiction over the appeal. The appeal
    shall be heard according to the rules governing other civil cases, so far as the same are
    applicable." (Emphases added.) 220 ILCS 5/10--201(b) (West 2008).
    Finally, section 10--201(c) provides:
    -3-
    No. 2--09--0007
    (c) No appellate court shall permit a party affected by any rule, regulation, order or
    decision of the Commission to intervene or become a party plaintiff or appellant in such
    court who has not taken an appeal from such rule, regulation, order or decision in the manner
    as herein provided." (Emphasis added.) 220 ILCS 5/10--201(c) (West 2008).
    The Commission construes section 10--201 to require the party appealing a Commission
    decision to notify the Commission of the appeal within 35 days of the Commission's final order. The
    Commission sees the notification requirement as a jurisdictional prerequisite. The Commission
    argues that we lack jurisdiction here because the Commission issued its decision denying rehearing
    on December 1, 2008, but petitioners did not properly provide the Commission notice of their
    January 2, 2009, appeal to this court until March 2, 2009.
    The Commission misreads section 10--201. The section does not require simple notification
    of an appeal initiated elsewhere, i.e., in the appellate court; rather, it requires that the appeal be
    initiated with the Commission before jurisdiction will vest in the appellate court. In Consumers Gas
    Co. v. Illinois Commerce Comm'n, 
    144 Ill. App. 3d 229
    (1986), the Fifth District Appellate Court
    noted a conflict between section 10--201 and Supreme Court Rule 335 (155 Ill. 2d R. 335). Rule
    335 establishes "[t]he procedure for a statutory direct review of orders of an administrative agency
    by the Appellate Court" (155 Ill. 2d R. 335) and mandates the filing in the appellate court of a
    "petition for review" (155 Ill. 2d R. 335(a)), which in administrative review cases serves the function
    of the notice of appeal required in other civil cases (People ex rel. Madigan v. Illinois Commerce
    Comm'n, 
    231 Ill. 2d 370
    , 388 (2008)). Rule 335(a) incorporates the timing requirements of Supreme
    Court Rule 303(a)(1) (Official Reports Advance Sheet No. 8 (April 11, 2007), R. 303(a)(1), eff. May
    1, 2007) for the filing of a notice of appeal. 155 Ill. 2d R. 335(i)(1); County of Cook, Cermak Health
    -4-
    No. 2--09--0007
    Services v. Illinois State Local Labor Relations Board, 
    144 Ill. 2d 326
    , 329-30 (1991) (hereafter
    Cermak) ("Rule 335 incorporates the 30-day filing period established by Rule 303(a)"). Rule 335(b)
    also provides that the petitioner "shall serve the petition for review on the agency and on all other
    parties of record to the proceedings before the agency in the manner prescribed for serving and
    proving service of a notice of appeal in Rule 303(c)." 155 Ill. 2d 335(b).
    The Consumers Gas court found section 10--201 in "direct contravention" of Rule 335:
    "Paragraph (a) of [Rule 335] requires that a petition for review shall be filed with the
    appellate court, unlike section 10--201(b) which requires that a notice of appeal shall be filed
    with [the Commission]. Paragraph (b) of the rule requires that the petitioner seeking
    appellate review serve a copy of the petition for review on the administrative agency and all
    other parties of record. In contrast, under section 10--201(b) it is the clerk of the appellate
    court who is served with a copy of the notice of appeal which was filed with the Commission
    in the first instance." (Emphasis added.) Consumers 
    Gas, 144 Ill. App. 3d at 235
    .
    The Consumers Gas court struck the jurisdictional provisions of section 10--201 as unconstitutional
    because they were an "improper legislative intrusion into the area of appellate practice by attempting
    to regulate the method for perfecting a direct appeal of an administrative decision." Consumers 
    Gas, 144 Ill. App. 3d at 236
    . In Cermak, the supreme court held that, in appeals from orders of the Illinois
    Local Labor Relations Board, Rule 335, rather than section 3--103 of the Administrative Review
    Law (Ill. Rev. Stat. 1987, ch. 110, par. 3--103), governs the time for filing an appeal. Cermak, 
    144 Ill. 2d 326
    . In reaching that conclusion, the court noted that "[t]he specific purpose for adoption of
    Rule 335 was to govern direct appeals to the appellate court from orders of administrative agencies."
    
    Cermak, 144 Ill. 2d at 335
    . The supreme court cited with approval Consumer Gas's holding (as the
    -5-
    No. 2--09--0007
    supreme court summarized it) that section 10--201 is "an improper legislative intrusion into the
    judiciary's constitutional power over appellate procedure and practice." 
    Cermak, 144 Ill. 2d at 338
    .
    It is not in our power to depart from Cermak.
    The Commission insists that "timeliness in notifying the Commission was not considered"
    in Consumers Gas. We agree, but the reason Consumers Gas did not concern "timeliness in
    notifying the Commission" of an appeal filed elsewhere is that section 10--201 requires filing the
    appeal with the Commission in the first instance. According to Consumers Gas, while section
    10--201(b) requires initial filing of the appeal in the Commission with notice to the appellate court,
    Rule 335, by contrast, requires initial filing of the appeal in the appellate court with notice to the
    Commission.
    The Commission's only argument in support of dismissal is that it did not receive proper
    notice under section 10--201(b). (The Commission says: "The jurisdictional issue being raised ***
    is the timely notification of [petitioners'] appeal.") Contrary to the Commission's position, section
    10--201(b) does not require that the Commission be given notice of an appeal filed elsewhere but,
    rather, that the appeal be initiated with the Commission. Hence the Commission's argument is a
    nonstarter. In any case, jurisdiction was vested here simply by the filing in this court of petitioners';
    petition for review as required by Rule 335. "[N]o step other than the timely filing of a notice of
    appeal is jurisdictional" where the petitioner seeks direct review by the appellate court of a
    Commission decision. Moncada v. Illinois Commerce Comm'n, 
    212 Ill. App. 3d 1046
    , 1051 (1991).
    We again deny the Commission's motion to dismiss this appeal, and we turn to the merits.
    II. The Certificate of Public Convenience and Necessity
    -6-
    No. 2--09--0007
    In an initial petition filed May 15, 2007, and an amendment filed August 14, 2007 (petition),
    ComEd requested from the Commission a certificate of public convenience and necessity. ComEd
    sought authorization to construct, operate, and maintain a new 138-kilovolt (kV) transmission line
    in Kane and McHenry Counties. ComEd gave the following informal description of the route for
    the proposed line, known as the Kreutzer Road route:
    "The proposed line will begin at ComEd's existing Gilberts substation, located south of
    Interstate 90 near Randall Road. It will exit the substation to the northwest, following the
    south side of Interstate 90 for about six miles to a new substation, to be known as the
    Sandwald substation. From a point on the south side of Interstate 90 ***, the line will also
    run north, cross the tollway, and continue north following property lines to the north side of
    Freeman Road. It will then run west along Freeman Road, and continue north along Smith
    Drive, continue east along a rail spur corridor, and then southeast along the Union Pacific
    Railway to Kreutzer Road. East of the railroad tracks, the line will parallel Kreutzer Road
    south of the roadway, continuing east across Huntley-Dundee Road to connect with ComEd's
    existing transmission line."
    ComEd described the need for the line:
    "The purpose of the proposed line is to provide capacity to portions of Kane and
    McHenry Counties, Illinois, where electrical load has been increasing and is expected to
    continue to increase. This project is the third phase of an overall strategy to provide adequate
    and reliable electrical energy to this rapidly growing area. The first two phases were
    approved by the [Commission] in Docket No. 96--0410 and have been put into service
    already. By completing the loop of substations that includes Gilberts, proposed Sandwald,
    -7-
    No. 2--09--0007
    Algonquin, and North Huntley, each of the substations in the area will be fed by two
    independent two-circuit lines, maintaining and enhancing reliability. The line is also
    necessary to power a new substation to serve the area, which ComEd will call the Sandwald
    Substation. Absent reinforcement, a number of existing transformers and 34 kV lines in this
    area would experience overloads as early as 2009. The proposed project will prevent each
    of these overloads by transferring the load in this area from the existing 34 kV system to the
    proposed transmission line. The construction of the proposed line is necessary to continue
    to provide adequate, reliable[,] and efficient service to these cities as well as the surrounding
    area."
    Exhibit B to ComEd's petition was a legal description of the Kreutzer Road route. It stated
    in pertinent part:
    "ONE PROPOSED DOUBLE CIRCUIT 138KV TRANSMISSION LINE TO BE
    LOCATED IN THE COUNTIES OF KANE AND MCHENRY IN ILLINOIS:
    SAID TRANSMISSION LINE TO BEGIN AT COMED'S EXISTING GILBERTS
    SUBSTATION LOCATED ON THE SOUTH SIDE OF I90 IN SECTION 30, TOWNSHIP
    42 NORTH, RANGE 8 EAST OF THE THIRD PRINCIPAL MERIDIAN IN KANE
    COUNTY, ILLINOIS ***.
    AT A POINT ON THE *** ROUTE (SAID POINT BEING APPROXIMATELY 1/2
    MILE EAST OF THE I90 and ROUTE 47 INTERSECTION), THE PROPOSED
    TRANSMISSION LINE WILL EXTEND NORTHERNLY ALONG THE CENTERLINE
    OF SECTION 16, TOWNSHIP 42 NORTH, RANGE 7 EAST OF THE THIRD PRINCIPAL
    MERIDIAN IN KANE COUNTY APPROXIMATELY 2,877.8 FEET TO FREEMAN
    -8-
    No. 2--09--0007
    ROAD; *** THENCE EASTERLY ALONG KREUTZER ROAD APPROXIMATELY
    6,433.0 FEET TO THE INTERSECTION OF KREUTZER ROAD AND HUNTLEY ROAD
    LOCATED SECTION 2, TOWNSHIP 42 NORTH, RANGE 7 EAST OF THE THIRD
    PRINCIPAL MERIDIAN IN KANE COUNTY ***." (Emphasis added.)
    At issue in this appeal is the portion of the Kreutzer Road route that tracks Kreutzer Road,
    along which petitioners own property. Petitioners were allowed to intervene in the action before the
    Commission. In a formal position statement filed with the Commission, petitioners clarified that
    they had "no position on the need for the proposed transmission project" but objected only to the
    placement of the line on the portion of Kreutzer Road where they own property.
    ComEd attached to its petition the prepared testimony of various witnesses. Ronald Dyslin,
    a senior real estate agent with ComEd, testified that his duties for ComEd include acquiring "real
    property for use as transmission rights-of-way and substation sites." He "assess[es] the type, size[,]
    and location of land required for any lines, substation, or facility sites." Dyslin explained why
    ComEd chose the south side of Kreutzer Road:
    "Q. Why is ComEd proposing this alignment?
    A. To the east of the railroad tracks and to the north of Kreutzer Road is an existing
    residential subdivision built since the approval of phases 1 and 2 of the Northwest Reliability
    Project, and a detention pond associated with that subdivision. The south side of Kreutzer
    Road is currently undeveloped.
    Q. Are you aware of plans to widen Kreutzer Road?
    A. We have reviewed an intergovernmental agreement among the communities in the
    area to the effect that Kreutzer Road will be widened to five lanes when the area south of
    -9-
    No. 2--09--0007
    Kreutzer develops. I would not call these 'plans' at this time, as there is no timetable for
    either the development or the road project in the stretch of Kreutzer that our proposed line
    would parallel. So, for the time being, we are proposing to acquire the necessary 50-foot
    right-of-way for our transmission line adjacent to the south edge of the current road right-of-
    way. If the plans for the road development become more certain before the line must be built
    (which is currently projected to be 2010 or 2011), we may be able to negotiate a solution
    with the communities and landowners to shift our alignment."1 (Emphasis added.)
    Asked whether ComEd will need to purchase easements from every owner of land along the
    proposed route, Dyslin replied, "No. In some cases, the landowners from whom we need easements
    will depend on the exact alignment of the line."
    ComEd also attached the prepared testimony of Neil Kaup, an engineer for ComEd. Kaup
    described the alternative routes ComEd considered before deciding on the Kreutzer Road route.
    Kaup referred to the following comparative table:
    Route                   Description        Engineering Factors          Length        Estimated
    (mi.)         Cost ($M)
    I-90 and first leg      I-90 from          Use alley-arms to stay       7.1           $13.30
    north (common           Gilberts to        within I-90 [right of
    to all routes)          Sandwald. East     way]; need to address or
    side of Huntley    span wetlands north of
    Factory Shops to   tollway.
    Freeman Road.
    1
    There is no evidence that an expansion of Kreutzer Road has ever taken place.
    -10-
    No. 2--09--0007
    Kreutzer Road     Follow property     Following west property      4.6   $8.75
    (Com Ed's         lines north         line of Stade property
    proposed route)   across Powers       involves additional poles
    Road and Smith      compared to straight
    Road; use           north; tree clearing north
    ComEd               of Powers Road; possible
    easement            [e]ffect on parking lot in
    through Bernat      Bernat industrial park;
    industrial park;    one house near Kreutzer
    follow Kreutzer     Road on south side; need
    Road to existing    to consider timing of
    transmission        Kreutzer Road
    line.               improvements.
    Freeman/          Follow Freeman      Least use of existing        4.5   $9.19
    Galligan          Road to             easements; affects the
    Galligan Road;      Koppie [Airport] and
    follow Galligan     both runways of Reid
    Road to Dundee      [Airport]; need to address
    Road; continue      or span wetlands north of
    north along         tollway; need to acquire
    property lines to   extensive right-of-way
    existing            from Kane Co. Forest
    transmission        Preserve; may need to
    line.               cross back and forth to
    avoid existing homes in
    Freeman and Galligan;
    need to consider timing
    and location of Galligan
    Road improvements and
    relocation.
    -11-
    No. 2--09--0007
    Main & Haligus       Follow property    Maximizes use of               4.3           $8.61
    lines north        existing easements;
    across Powers      following west property
    Road and Smith     line of Stade property
    Road; use          involves additional poles
    ComEd              compared to straight
    easement           north; tree clearing north
    through Bernat     of Powers Road; going
    industrial park;   around the south side of
    use ComEd          planned Huntley City
    easement north     Center would involve
    along west side    numerous angles and
    of Wing Pointe;    poles.
    along north side
    of Wing Pointe;
    then north to
    Main & Haligus.
    Kaup described the advantages of the Kreutzer Road route:
    "The proposed route is least cost, although it is true that the proposed route and two
    alternative routes are similar in cost, so among alternatives, cost is not a major determinant
    of the route. The Tollway right-of-way is highly advantageous, allowing rapid construction,
    good access, very few angle points, a direct route to the substation, and little risk as to land
    acquisition.
    Off the Tollway, the proposed route has relatively few construction challenges. We
    do not expect problems with construction in wetlands, clearance problems, and will have
    minimal tree trimming. We parallel a railroad for a short stretch, so we will need to study
    the extent to which the proposed line will induce currents on the railroad, but we do not
    expect a problem. There is one house along the south side of Kreutzer Road that presents
    a conflict. Because that parcel is expected to be redeveloped in the coming years, that house
    would likely be sold and torn down as part of redevelopment."
    -12-
    No. 2--09--0007
    Asked how the Kreutzer Road route compared to the alternatives, Kaup said:
    "Each of these routes is a feasible alternative from an engineering standpoint.
    Compared to the proposed route, the Freeman-Galligan route requires more land acquisition
    from more landowners, requires substantial acquisition from the Kane County Forest
    Preserve District, would impact not one, but both of the Reid [Airport] landing strips, and
    would also impact Koppie [Airport]. Compared to the proposed route, the Main & Haligus
    Route would involve numerous changes of direction along the north side of the Wing Pointe
    subdivision to skirt the edge of the planned Huntley City Center, which would involve
    several large, expensive poles to accommodate sharp angles."
    ComEd also included the testimony of Donnell Murphy of Arcadis, an environmental
    consulting firm that prepared a siting study for ComEd concerning the placement of the transmission
    line. Murphy described how the Kreutzer Road route compared to alternatives:
    "Specific to environmental considerations, the proposed final route better optimized
    the use of dominant linear features having compatible associated rights-of-way. It also
    provided for the placement of the proposed transmission line behind planned developments
    rather than along a major frontage, and eliminated the potential for impacts to occur to
    proposed developments along Freeman and Galligan Roads that are almost exclusively
    residential and progressing more rapidly than planned developments in other areas. Finally,
    it eliminated the potential for impacts to occur to the existing and newly acquired forest
    preserve lands along Freeman Road."
    -13-
    No. 2--09--0007
    ComEd noted that it was unable to reach agreements with some landowners for the purchase of
    property along the proposed line. ComEd therefore sought authorization under section 8--509 of the
    Act (220 ILCS 5/8--509 (West 2008)) to use "eminent domain to obtain the necessary right-of-way."
    The Commission staff endorsed the Kreutzer Road route. The Commission staff filed the
    testimony of Greg Rockrohr, a staff engineer with the Commission. Regarding the comparative costs
    of the route options, Rockrohr said:
    "ComEd indicated that of the three routes, the highest cost route, Freeman/Galligan, would
    cost less than 7% more than the lowest cost route, Main & Haligus. Since the error within
    each of ComEd's cost estimates is more than 7%, the estimated costs for ComEd's three final
    route alternatives can be considered equal for discussion purposes, so that cost was not a
    significant factor when choosing one route over another."
    The Village of Huntley (Huntley) also intervened in the action before the Commission.
    Huntley claimed that there are planned commercial and residential areas in Huntley on which the
    Kreutzer Road route would impinge. Huntley proposed a modified version of the Freeman-Galligan
    route. This modified Freeman-Galligan route would avoid Huntley but traverse property owned by
    Neumann Homes, a developer with plans to build a subdivision called The Conservancy on the land.
    There was evidence that The Conservancy was platted and partially built. There was also evidence
    that the modified Freeman-Galligan route would traverse land owned by the Kane County Forest
    Preserve District, specifically, the Freeman Kame-Meagher Forest Preserve.
    Petitioners presented the testimony of Donald Byrne. Byrne stated that petitioners own 265
    acres on Kreutzer Road, with 40 acres on the north side of the road and the remainder on the south
    side. All but a small portion of the land is currently farmed. Petitioners have homes on both sides
    -14-
    No. 2--09--0007
    of Kreutzer Road. Byrne testified that portions of petitioners' farm have been in the Kreutzer family
    since 1868, and the rest since 1891, and that the farm has been certified as a Centennial Farm under
    the Illinois Department of Agriculture's Centennial Farm Program. Byrne testified to the detriment
    he believed the property would suffer if ComEd installed its line:
    "I realize that the actual acreage permanently taken out of farm production will be
    relatively small.    But during the construction phase the farming operations will be
    significantly interrupted. More importantly, however, the structures and lines will constitute
    a permanent intrusion upon the Farm. The Farm's character will be forever and significantly
    degraded by the presence of such a highly visible, man-made conglomeration of steel and
    wire. The structures and lines will contrast sharply with the natural farm landscape that
    exists, and has existed, for such a long time. The fact that the State has conferred the special,
    centennial farm designation on Kreutzer Farm just exacerbates the adverse impact of the
    project in such close proximity, when it is not necessary to do so."
    ComEd presented the rebuttal testimony of Rockrohr, who questioned the feasibility of the
    modified Freeman-Galligan route because it would traverse the property of a forest preserve district,
    against which, Rockrohr believed, eminent domain proceedings are not available. The Commission
    staff agreed with this position.
    Huntley presented the rebuttal testimony of Donald Robinson, a consultant in the area of
    utility line placement. Robinson testified that it is a "common practice to deviate from a tangent line
    in order to avoid sensitive areas and mitigate negative impacts." Robinson stated that, "[i]n [his]
    experience, it is commonplace for a utility to introduce minor variances when the actual design is
    engineered to handle the real-world conditions for placing its transmission facilities." Robinson
    -15-
    No. 2--09--0007
    believed that, "[b]y making a very few minor adjustments to the tangent alignment, the Modified
    Freeman-Galligan Route could avoid a major portion of the negative impact" on forest preserve
    lands. Specifically, Robinson believed that ComEd could situate the line just east of the tree line of
    the preserve without having to clear any trees on the preserve itself. Robinson noted that it is
    "important to bear in mind that even a 50' right of way does not require a 50' swath of complete
    vegetation clearance."
    ComEd presented the surrebuttal testimony of Dyslin, who testified:
    "Q. Huntley witness Robinson suggests that ComEd can construct the line east of the
    Powers Road trees ***. What comment do you have from a real estate perspective?
    A. The trees are on forest preserve property. ComEd understood that Huntley was
    proposing the line east of the trees. However, we cannot simply buy a 50-foot easement east
    of the trees without paying for the land containing the trees as well. Our 50-foot easement
    would abut at least a 40-foot wide strip, containing the trees, east of the centerline of Powers
    Road. So along the corridor, we would need to factor in the cost to obtain the entire 90-foot
    (at a minimum) width. Again, we'd have to pay whatever the forest preserve wanted to
    charge."
    On January 30, 2008, the proofs were closed and the administrative law judge (ALJ) marked
    the record "Heard and Taken." On July 11, 2008, the ALJ filed a proposed "order and certificate of
    public convenience and necessity" authorizing ComEd to install the transmission line along the
    proposed Kreutzer Road route. Appendix 1 to the proposed order adopted verbatim Exhibit B, the
    legal description attached to ComEd's petition. The ALJ set deadlines of August 8, 2008, for briefs
    on exceptions and August 22, 2008, for reply briefs on exceptions.
    -16-
    No. 2--09--0007
    On August 8, 2008, petitioners filed a "Motion to Take Administrative Notice Instanter."
    Petitioners represented that, on June 10, 2008, the Kane County Board passed a resolution
    designating petitioners' house on the south side of Kreutzer Road (the Kreutzer House) a "Kane
    County Historic Landmark." Section 16--94(a) of the Kane County Code (County Code) (Kane
    County Code §16--94, amended July 7, 2000) provides that a "certificate of appropriateness" shall
    be obtained from the Kane County Preservation Commission "before any significant alteration,
    construction, demolition or removal that affects pending or designated landmarks, preservation
    districts[,] and road corridors is undertaken." Petitioners argued that the landmark designation
    significantly impacted the analysis of the proper route for ComEd's line:
    "[Section 16--94(a) of the County Code] *** require[s] *** local county approval and
    present[s] an obstacle to property acquisition along the Kreutzer Road portion of the
    transmission line route, just as the Freeman Kame Forest Preserve may present an easement
    acquisition challenge to ComEd along the Modified Freeman-Galligan route. It is reasonable
    to conclude that either route presents the same easement acquisition challenge over a portion
    of the route for which eminent domain authority may not be available."
    Also on August 8, 2008, petitioners filed their brief on exceptions. Petitioners argued that
    the proposed order wrongly concluded that the Kreutzer Road route was the least-cost option.
    On September 2, 2008, the ALJ denied petitioners' motion to take administrative notice. The
    record contains no remarks from the ALJ himself concerning the reasons for the denial, but in its
    final order of October 8, 2008, the Commission summarized the ALJ' s reasons for the denial:
    "First, the ALJ noted that the record in this matter was marked 'Heard and Taken' on January
    [30], 2008. [Petitioners] did not seek this designation of their farm property until March
    -17-
    No. 2--09--0007
    2008. The Kane County Board did not act on the motion until June 10, 2008. The ALJ
    reasoned that this presented due process problems and it would be prejudicial to the other
    parties in this matter to allow this into the record without the opportunity to question the
    relevance of the designation. Moreover, he ruled that this designation does not supersede the
    authority of this Commission under the Public Utilities Act. Finally, because the exact
    location of the proposed transmission line has not been set, the route could still be positioned
    along Kreutzer Road, thereby avoiding any encroachment on the portion granted historic
    designation."
    ComEd did not file its own exceptions but on August 22, 2008, filed a reply to petitioners'
    exceptions. As to the landmark designation of the Kreutzer House, ComEd wrote:
    "As Huntley's witness Mr. Robinson testified, when a utility designates its alignment, it can
    use minor adjustments to avoid particular features. [Citation.] In this case, ComEd could
    simply align the line to the south side of the house if necessary. This would avoid any need
    to alter the designated building. To make clear that ComEd may parallel Kreutzer Road on
    the south side of the Kreutzer farmhouse, ComEd suggests that the [Commission]
    specifically allow such an alignment. Attached to this brief is a suggested addition to
    Appendix 1 to the order making this clear."
    ComEd attached a proposed Appendix 1 with the suggested modifications bolded and underscored
    as follows:
    "AT A POINT ON THE *** ROUTE (SAID POINT BEING APPROXIMATELY 1/2 MILE
    EAST OF THE I90 and ROUTE 47 INTERSECTION), THE PROPOSED TRANSMISSION
    LINE WILL EXTEND NORTHERNLY ALONG THE CENTERLINE OF SECTION 16,
    -18-
    No. 2--09--0007
    TOWNSHIP 42 NORTH, RANGE 7 EAST OF THE THIRD PRINCIPAL MERIDIAN IN
    KANE COUNTY APPROXIMATELY 2,877.8 FEET TO FREEMAN ROAD; ***
    THENCE EASTERLY ALONG KREUTZER ROAD WITHIN 175 FEET OF THE
    CENTERLINE OF THE ROAD RIGHT-OF-WAY FOR A DISTANCE OF
    APPROXIMATELY 6,433.0 FEET TO THE INTERSECTION OF KREUTZER ROAD
    AND HUNTLEY ROAD LOCATED SECTION 2, TOWNSHIP 42 NORTH, RANGE 7
    EAST OF THE THIRD PRINCIPAL MERIDIAN IN KANE COUNTY ***." (Emphasis
    in original.)
    On October 8, 2008, the Commission issued its final "order and certificate of public
    convenience and necessity." The Commission applied the criteria of section 8--406(b) of the Act
    (220 ILCS 5/8--406(b) (West 2008)) governing the issuance of certificates of public convenience and
    necessity. The Commission noted that there was no dispute among the parties that a new
    transmission line was necessary for ComEd to maintain adequate, reliable, and efficient service to
    its customers. Rather, the Commission noted, the issue was the placement of the line. Turning to
    that issue, the Commission first determined that the Kreutzer Road route was the least-cost option.
    Specifically, the Commission said:
    "ComEd presented evidence that its proposal is the least-cost means of meeting the
    area's needs. It presented the results of a detailed engineering study of practical alternatives.
    The study confirmed that the next-best alternative would cost approximately twice as much
    as its proposal."2
    2
    We are unsure of the source for the latter remark. The Commission did not identify this
    "next-best alternative" that would cost "approximately twice as much as [ComEd's] proposal." There
    -19-
    No. 2--09--0007
    As to the modified Freeman-Galligan route proposed by Huntley, the Commission said:
    "First, it is clear under Illinois law [that] the Kane County Forest Preserve District cannot be
    compelled to convey any interest in the Freeman Kame-Meagher Forest Preserve through
    eminent domain or condemnation. *** [T]hus, even if cost questions did not exist, the
    [Commission] would have grave reservations about ordering ComEd to use the route, in
    light of the fact that ComEd may be unable to obtain necessary easements even with eminent
    domain authority. Huntley offers no solution whatever to this problem.
    Further, despite asserting that the Modified Freeman-Galligan Route would be least-
    cost, Huntley does not proffer any evidence to support such claims. Moreover, no party can
    predict what ComEd would have to pay to acquire property rights in the Freeman Kame-
    Meagher Forest Preserve, even if it were to prove able to do so. *** The indefinite cost of
    the Modified Freeman-Galligan Route makes it difficult for us to approve it. In our view,
    the Modified Freeman-Galligan route, which would cut through the middle of a forest
    preserve, a partially constructed housing development, and would place poles in the front
    yards of existing homes, is not superior to ComEd's proposed route. While development is
    planned for areas along the Kreutzer Road route, the Commission finds that those future
    was no such margin of cost among any of the alternatives in the table to which Kaup referred. Kaup
    noted that costs among the alternatives were "similar" and that cost was not a "major determinant"
    of ComEd's selection of the Kreutzer Road route. In any event, since we are reversing the decision
    of the Commission on a different ground, we need not determine the comparative costs of the routes
    proposed by the parties.
    -20-
    No. 2--09--0007
    developments would not have the negative effect likely to be caused by traversing The
    Conservancy, which already has been platted and partially constructed."
    As for petitioners' objections to the Kreutzer Road route, the Commission said:
    "While the [Commission] appreciates the Centennial Farm status achieved by the Kreutzer
    Farm, such status nevertheless cannot be a determining factor in where to route a
    transmission line that is needed for the surrounding community. The future plans for
    Kreutzer Road to become a 5-lane, primary arterial further weakens [petitioners'] argument
    that a transmission line alone will alter the character of the farm."
    The Commission further found that ComEd was capable of financing the project and of managing
    and supervising the construction.
    Pursuant to sections 8--503 and 8--509 of the Act (220 ILCS 5/8--503, 8--509 (West 2008)),
    the Commission authorized ComEd to bring an eminent domain action to acquire property for the
    transmission line. The Commission said:
    "The proposed project has been demonstrated to be necessary and to serve the public
    convenience. The evidence shows that ComEd has tried diligently to acquire the right-of-
    way necessary for the project, but so far has been unable to do so. The record clearly shows
    that if the public in this area is to continue to receive adequate, efficient and reliable service
    at the least-cost means, this project must be constructed."
    Appendix 1 to the Commission's order was a verbatim copy of ComEd's proposed Appendix 1. The
    Commission granted "ComEd authority to assert eminent domain authority as necessary to construct
    the route described *** in Appendix 1."
    -21-
    No. 2--09--0007
    On November 7, 2008, petitioners filed an application for rehearing. Petitioners objected to
    the Commission's accession to ComEd's request, in its reply on exceptions, that it be authorized to
    place the transmission line within a range of 175 feet from the centerline of Kreutzer Road.
    Petitioners argued that there was no evidence to support this revision. Petitioners noted that
    whenever ComEd proposed in its evidence before the Commission a specific width for the right-of-
    way on Kreutzer Road, as in the testimony of Dyslin, it mentioned only a 50-foot right-of-way
    adjacent to Kreutzer Road.3 Petitioners argued that ComEd's calculation of cost was evidently based
    on a 50-foot width and that a 175-foot width might have implications for the cost analysis that were
    not explored in the proceedings:
    "[T]he filed testimony and exhibits, live testimony and cross-examination, briefs, and the
    ALJ Proposed Order, all contemplated a proposed route along Kreutzer Road that was to be
    within a 50-foot wide easement adjacent to the south side of the road and near the edge of
    the Kreutzer Farm, as ComEd had petitioned and supported. Because no one had even
    suggested a location intruding any further into the Kreutzer Farm, let alone up to 125 feet
    further, no party offered any evidence of the geographic features within that additional area,
    sensitivities, or other factors that may impact the location of the line in that area. ***
    Therefore, we do not know how this new 'Modified Kreutzer Road Route' would stack up
    in an analysis comparing it to the other routing alternatives."
    3
    In addition to Dyslin's testimony, petitioners point to ComEd's exhibit 8.1, referenced in the
    rebuttal testimony of Murphy. The only copy of exhibit 8.1 that we have found in the record is
    illegible.
    -22-
    No. 2--09--0007
    Petitioners attached an affidavit from Byrne, who averred that the portion of petitioners'
    property within 175 feet of the centerline of Kreutzer Road includes various buildings and wildlife
    habitat. Petitioners asked the Commission to open the record for further proceedings to determine
    the impact of the widened right-of-way.
    On November 20, 2009, the ALJ recommended to the Commission that it deny the
    application for rehearing. The ALJ reasoned:
    "In ComEd's response to [petitioners' motion to take administrative notice], the
    Company suggested that the utility could use minor adjustments to avoid particular features.
    ComEd could just align the line to the south of the house if necessary. So the Company
    proposed the additional change to help the property listed in the historical designation. The
    change was from 50 feet to 175 feet. This will give ComEd more leeway when the final
    alignment is determined.
    ***
    This change was made to help [petitioners] and ComEd work on a final alignment
    that would avoid the property contained in the historical designation. Just because the width
    was extended from 50 feet to 175 feet[] does not mean that the Company will use the whole
    area. It gives the construction engineers more flexibility to refine the final alignment thus
    avoiding potential problems. The route will remain the same and the final alignment will be
    made by the construction engineers for ComEd. Therefore, it will not really serve any
    purpose to rehear this issue, since the final alignment will be determined during construction
    and not in this hearing."
    -23-
    No. 2--09--0007
    The Commission adopted the ALJ's recommendation and, on December 1, 2008, denied petitioners'
    application for rehearing.
    On appeal, petitioners raise three arguments. First, they claim that the Commission erred
    when, after the proofs were closed, it authorized ComEd to align the transmission line within 175
    feet of the centerline of Kreutzer Road, when ComEd's witnesses, such as Dyslin, indicated only that
    ComEd needed a 50-foot-wide right-of-way adjacent to Kreutzer Road. Relatedly, petitioners
    suggest that the Commission may have violated the Open Meetings Act (5 ILCS 120/1.01 et seq.
    (West 2008)) in that, given the late insertion of the reference to the 175-foot margin, "there may have
    been input from some source other than the record." Second, they argue that the Kreutzer Road route
    was not the least-cost route for the proposed line in any case, and that the widening of the easement
    beyond that contemplated by ComEd's witnesses exacerbated the failure of proof. Third, they argue
    that the Commission was wrong to deny their request to take administrative notice of Kane Country's
    designation of the Kreutzer House as a historical landmark.
    ComEd and the Commission both claim that petitioners forfeited some of these arguments.
    Section 10--113(a) of the Act (220 ILCS 5/10--113(a) (West 2008)) states:
    "No appeal shall be allowed from any rule, regulation, order or decision of the Commission
    unless and until an application for a rehearing thereof shall first have been filed with and
    finally disposed of by the Commission ***. No person or corporation in any appeal shall
    urge or rely upon any grounds not set forth in such application for a rehearing before the
    Commission."
    "It is incumbent upon the party seeking review to specify in a petition for rehearing where the
    Commission erred so as to allow it an opportunity to correct the error [citation], and the allegations
    -24-
    No. 2--09--0007
    in the petition must be sufficiently specific to apprise the Commission and opposing parties of the
    actual points relied upon [citations]." Village of Montgomery v. Illinois Commerce Comm'n, 
    249 Ill. App. 3d 484
    , 491(1993); see also Citizens Utility Board v. Illinois Commerce Comm'n, 
    166 Ill. 2d
    111, 135-36 (1995) (court will consider no argument not specifically brought before the
    Commission).
    We agree with ComEd and the Commission that petitioners' argument for rehearing on the
    issue of the least-cost option was significantly narrower than the argument they now bring on the
    issue. We note first that petitioners did not question below, and do not question here, the general
    need for the transmission line. They challenge only the Commission's preferred layout for the line,
    the Kreutzer Road route. In arguing that specific point here, petitioners contend that the evidence
    before the Commission does not demonstrate that the Kreutzer Road route is the least-cost option
    either with a 50-foot corridor adjacent to Kreutzer Road, as Dyslin contemplated, or with the revised
    range of up to 175 feet from the centerline of Kreutzer Road. In their application for rehearing,
    however, petitioners objected only to ComEd's attempt to secure a right-of-way wider than 50 feet.
    Petitioners thus forfeited their challenge that the Kreutzer Road route was not the least-cost option,
    given a right-of-way of no wider than 50 feet adjacent to Kreutzer Road. Thus, we do not review
    whether the Kreutzer Road route was the least-cost option as laid out before the revision that ComEd
    prompted.
    Petitioners also forfeited their argument that the Commission erred by declining to take
    administrative notice of the designation of the Kreutzer House by Kane County. In their application
    for rehearing, petitioners mentioned the Commission's denial of the motion but did not assign error
    to it.
    -25-
    No. 2--09--0007
    We turn to petitioners' one preserved contention, that there was no evidence before the
    Commission to demonstrate the need for a 175-foot right-of-way reckoned from the centerline of
    Kreutzer Road or, for that matter, any right-of-way more expansive than a 50-foot corridor adjacent
    to Kreutzer Road. Here we note that petitioners assume that Appendix 1 to the Commission's order
    allows ComEd to acquire up to 175 feet of land from the centerline of Kreutzer Road. The order
    provides for a "TRANSMISSION LINE" to run "EASTERLY ALONG KREUTZER ROAD
    WITHIN 175 FEET OF THE CENTERLINE OF THE ROAD RIGHT-OF-WAY." This appears to
    contemplate that the transmission line will be located somewhere within 175 feet from the centerline
    of the road. At oral argument, ComEd insisted that the order simply allows it to position, somewhere
    within 175 feet of the centerline of Kreutzer Road, the 50-foot right of-way referenced by Dyslin.
    The description itself, however, specifies neither the width of the transmission line nor the additional
    right-of-way, if any, necessary to place the line, and hence the language poses no bar to ComEd
    using, if needed, a whole 175-foot corridor reckoned from the centerline of Kreutzer Road. Notably,
    in commenting that "[j]ust because the width has been extended from 50 feet to 175 feet[] does not
    mean that [ComEd] will use the whole area," the ALJ did not reassure petitioners that the right-of-
    way, wherever placed, would not exceed 50 feet in width.
    We agree with petitioners that the Commission's order was deficient. To explain, we set
    forth the procedures under the Act for a utility to acquire the Commission's approval for a project
    and its authorization to use the condemnation power to acquire property for the project.
    Section 8--406(b) of the Act provides that, before a public utility may undergo "the
    construction of any new plant, equipment, property or facility which is not in substitution of any
    existing plant, equipment, property or facility or any extension or alteration thereof or in addition
    -26-
    No. 2--09--0007
    thereto," the utility must obtain from the Commission "a certificate that public convenience and
    necessity require such construction" (220 ILCS 5/8--406(b) (West 2008)). A certificate of public
    convenience and necessity authorizing the proposed construction will issue:
    "only if the utility demonstrates: (1) that the proposed construction is necessary to provide
    adequate, reliable, and efficient service to its customers and is the least-cost means of
    satisfying the service needs of its customers or that the proposed construction will promote
    the development of an effectively competitive electricity market that operates efficiently, is
    equitable to all customers, and is the least cost means of satisfying those objectives; (2) that
    the utility is capable of efficiently managing and supervising the construction process and has
    taken sufficient action to ensure adequate and efficient construction and supervision thereof;
    and (3) that the utility is capable of financing the proposed construction without significant
    adverse financial consequences for the utility or its customers." 220 ILCS 5/8--406(b) (West
    2008).
    Section 8--503 of the Act provides in relevant part:
    "Whenever the Commission, after a hearing, shall find that additions, extensions,
    repairs or improvements to, or changes in, the existing plant, equipment, apparatus, facilities
    or other physical property of any public utility or of any 2 or more public utilities are
    necessary and ought reasonably to be made or that a new structure or structures is or are
    necessary and should be erected, to promote the security or convenience of its employees or
    the public or promote the development of an effectively competitive electricity market, or
    in any other way to secure adequate service or facilities, the Commission shall make and
    serve an order authorizing or directing that such additions, extensions, repairs, improvements
    -27-
    No. 2--09--0007
    or changes be made, or such structure or structures be erected at the location, in the manner
    and within the time specified in said order ***." 220 ILCS 5/8--503 (West 2008).
    Only the State has inherent power to condemn property for public use, but the State may
    delegate that power to municipalities and private corporations such as railroads and utilities. Illinois
    Power Co. v. Lynn, 
    50 Ill. App. 3d 77
    , 78 (1977). Under section 8--509 of the Act, the Commission
    may authorize a utility to file condemnation proceedings to acquire property for specific
    improvements approved under section 8--503. Section 8--509 states:
    "When necessary for the construction of any alterations, additions, extensions or
    improvements ordered or authorized under Section 8--503 *** of this Act, any public utility
    may enter upon, take or damage private property in the manner provided for by the law of
    eminent domain." 220 ILCS 8--509 (West 2008).
    In two cases, Lynn and Albin v. Illinois Commerce Comm'n, 
    87 Ill. App. 3d 434
    (1980), the
    appellate court described the relationship between section 55, section 50, and section 59 of the Act
    (in Albin, Ill. Rev. Stat. 1977, ch. 111 2/3, pars. 56, 50, 59; in Lynn, Ill. Rev. Stat. 1973, ch. 111 2/3,
    pars. 56, 50, 63), now sections 8--406, 8--503, and 8--509 of the Act, respectively. In Lynn, the court
    drew an analogy between the grant of condemnation power to a municipality and the grant of such
    power to a utility:
    "[I]f a city seeks to build a public building for a public use on privately owned
    property, the city council will appoint a commission to explore the needs and develop plans.
    Public hearings may be held. Recommendations are then made to the city council which
    enacts an ordinance. The statement of public use and the required area of land are set out in
    the ordinance. Condemnation proceedings follow." 
    Lynn, 50 Ill. App. 3d at 78
    .
    -28-
    No. 2--09--0007
    Lynn observed that this "basic pattern" is followed in the Act:
    "[Section 8--406] provides that no utility shall begin the construction of a new plant or
    facility without first obtaining a certificate of convenience and necessity. [Section 8--503]
    provides after a hearing the Commission shall made [sic] and serve an order authorizing the
    structures to be erected on the location in the manner and within the time specified.
    [Section 8--509] authorizes the utility, armed with the certificate and order, to use the
    power of eminent domain through the courts to acquire the land necessary for the project."
    
    Lynn, 50 Ill. App. 3d at 79
    .
    We develop the analogy further. "The law is also clear that the property to be condemned
    must be reasonably described in the enabling action of the condemnor, be it an ordinance or a
    resolution, and the failure to so describe is fatal to the petition to condemn." Illinois State Toll
    Highway Authority v. DiBenedetto, 
    275 Ill. App. 3d 400
    , 405 (1995); cf. 735 ILCS 30/10--5--10(a)
    (West 2008) (complaint by municipality to condemn property "shall set forth *** a description of
    the property"). It has been alternatively stated that there must be "reasonable certainty" in the
    description of the property sought to be condemned (City of Chicago v. Arnold, 
    261 Ill. 142
    , 146
    (1913)).
    For instance, in City of Rockford v. Rockford Life Insurance Co., 
    16 Ill. 2d 287
    , 288-89
    (1959) (Rockford Insurance), the enabling ordinance recited Rockford's intent to extend an existing
    street and to seek condemnation of the defendant's property for that purpose. The supreme court held
    that the ordinance was formally deficient because it did not specify which part of the defendant's
    property was sought. That is, the ordinance did not state whether the existing street was to be
    extended in the same direction or at some other angle. Moreover, though the ordinance sought an
    -29-
    No. 2--09--0007
    80-foot strip of the defendant's land, the existing street was only 50 feet wide. Rockford 
    Insurance, 16 Ill. 2d at 288-89
    .
    We think that, like an ordinance enabling a municipality to seek certain property by
    condemnation, a section 8--406/8--503/8--509 order, which authorizes the making of certain
    improvements and the initiating of eminent domain proceedings to acquire the necessary property,
    must describe with reasonable certainty the portion of the property sought to be condemned. As
    Lynn notes, the inquiry under sections 8--406, 8--503, and 8--509 concerns "the proposed plan for
    development of the project and the extent of the property to be sought" (emphasis added) 
    (Lynn, 50 Ill. App. 3d at 82
    ).
    An authorization for condemnation must also have an adequate evidentiary basis. The
    appellate court in Albin explained that sections 8--406, 8--503, and 8--509 require distinct showings
    of necessity. Section 8--406 requires necessity for the project in general, i.e., here (as in Albin) the
    provision of "more reliable electrical service" to the subject area; section 8--503 requires necessity
    for "the additions and improvements to implement the more reliable service"; and section 8--509
    requires necessity for the "means of obtaining easements for right-of-way for the additions and
    improvements." 
    Albin, 87 Ill. App. 3d at 439
    . An authorization for condemnation may issue only
    upon evidence justifying the "proposed plan for development of the project and the extent of the
    property to be sought." 
    Lynn, 50 Ill. App. 3d at 82
    .
    With this backdrop, we turn to petitioners' argument. Petitioners argue that the evidence
    before the Commission did not support revising its proposed order to allow ComEd to acquire along
    the south side of Kreutzer Road a right-of-way of up to 175 feet from the centerline of the road.
    Petitioners argue that ComEd's claimed justification for the revision, that it would allow ComEd the
    -30-
    No. 2--09--0007
    flexibility to position the transmission line so as to avoid the features of historical value on
    petitioners' property, begged the question of why a margin of 175 feet was necessary rather than
    some other margin.
    We agree. First, apart from the issue of evidentiary support, the Commission's order does
    not adequately describe the portion of property ComEd is authorized to seek. The order provides
    for a "TRANSMISSION LINE" to run "EASTERLY ALONG KREUTZER ROAD WITHIN 175
    FEET OF THE CENTERLINE OF THE ROAD RIGHT-OF-WAY." This description is even more
    tentative than the description found wanting in Rockford Insurance. There, the ordinance declared
    Rockford's intent to seek an 80-foot corridor from the defendant but did not specify which 80 feet.
    Here, the description does not even venture to identify a size for the portion of land to be taken from
    petitioners, much less specify from where on petitioner's property that portion would be taken.
    Instead, it allows for placement of a transmission line of unidentified width within a range of well
    over 100 feet (even allowing for a substantial width for the road right-of-way) on petitioners'
    property. Moreover, as ComEd acknowledged at oral argument, the order does not even specify on
    which side of Kreutzer Road ComEd must place the line.
    Second, even if such an uncertain description were sufficient, the record does not support a
    margin of 175 feet from the centerline of Kreutzer Road (in whichever direction) rather than some
    other margin. The Commission's decision had to be supported by substantial evidence, which is
    "evidence that a reasonable person would accept as sufficient to support a certain conclusion."
    Ameropan Oil Corp. v. Illinois Commerce Comm'n, 
    298 Ill. App. 3d 341
    , 347 (1998). There was
    literally no evidence to explain why ComEd sought in particular a margin of 175 feet from the
    centerline. Also, it is unclear from the record whether ComEd believed it might have a need for the
    -31-
    No. 2--09--0007
    whole 175 feet from the centerline. Though Dyslin testified early in ComEd's case that it needed
    only a 50-foot right-of-way for the transmission line, ComEd in urging the revision to the
    Commission's proposed order did not specify any width for the line. If ComEd's intent was simply
    to request a range in which to place a transmission line of a certain width, then it is notable that
    ComEd did not commit itself to a specific width for the line in requesting the range. This would
    have assured petitioners that, no matter where the line was placed, ComEd would take a certain
    amount of property and nothing more.
    The Commission and ComEd make various points whose common thread is that ComEd did
    not need to specify the actual width of the right-of-way along Kreutzer Road, because the dimensions
    could properly be determined later. ComEd believes that the "precise alignment in the right-of-way
    along Kreutzer Road" can be determined during construction of the transmission line. For support,
    ComEd points to Robinson's testimony that it is the "common practice" of utilities to "deviate from
    a tangent line in order to avoid sensitive areas and mitigate negative impacts."
    The Commission, for its part, admits that the width of the right-of-way along Kreutzer Road
    was "not raised to the Commission as any evidentiary matter," but the Commission maintains that
    there is "no law which requires that the limitation proposed by ComEd be presented as an evidentiary
    matter" before the Commission. Rather, petitioners and ComEd "will either negotiate the placement
    of this transmission line on [petitioners'] property or, under the worst case scenario, a court in
    condemnation will make that determination." The Commission goes so far as to suggest that, since
    it was unnecessary for ComEd to propose, or the Commission to authorize, a specific width for the
    right-of-way, ComEd's suggestion that it locate the line within 175 feet of the centerline was a
    voluntary limitation, to which "only ComEd can object."
    -32-
    No. 2--09--0007
    These arguments all fail. As the authorities discussed above show, the Commission's order
    had to describe with reasonable certainty the amount of land it authorized ComEd to acquire, and
    that description had to be supported by substantial evidence. Hence we see as fundamentally
    misconceived the Commission's suggestion that the description in its order did not need "to be
    supported by evidence." As for ComEd's points, we recognize that a utility, in proceedings before
    the Commission, might not yet be able to foresee a route for its line with certainty. We need not
    determine to what extent the Commission may accommodate a utility's uncertainty, for here ComEd
    made no attempt to explain why it needed a range of 175 feet in particular to make adjustments.
    The Commission believes we must excuse any laxity in the proceedings before it in this case.
    The Commission cites section 10--101 of the Act (220 ILCS 5/10--101 (West 2008)), which
    provides:
    "[N]o informality in any proceeding or in the manner of taking testimony before the
    Commission, any commissioner or hearing examiner of the Commission shall invalidate any
    order, decision, rule or regulation made, approved, or confirmed by the Commission in the
    absence of prejudice."
    It seems the reason the Commission believes there is no prejudice to petitioners is that they will have
    an opportunity to argue before the condemnation court what specific portion of their property, if any,
    they believe ComEd may acquire. We think the prejudice to petitioners would lie in subjecting them
    to the trouble and expense of additional proceedings for ComEd to prove what it already should have
    proven.
    As to how to proceed from here, ComEd prefers that we simply direct the Commission to
    delete the reference to the 175-foot width rather than "remand for further proceedings on whether
    -33-
    No. 2--09--0007
    the 175-foot provision should be included." The Commission, however, "will accept remand to
    either hear evidence on the matter or to strike the 175 foot limitation out of the legal description."
    Petitioners request a remand to "reopen the hearing" but give no specifics.
    We do not opt simply to have the 175-foot reference stricken. That would eliminate all
    measure of definiteness in the width of the right-of-way sought by ComEd and render the
    Commission's decision entirely out of compliance with the standards we set forth above. Notably,
    neither ComEd nor the Commission asks us to hold that the evidence at least supports a 50-foot
    right-of-way adjacent to Kreutzer Road, as described by Dyslin. We could not do so anyway because
    Appendix 1 to the Commission's order does not specify a 50-foot right-of-way. We simply remand
    this matter for further proceedings before the Commission, governed by the principles set forth
    above.
    CONCLUSION
    For the foregoing reasons, we reverse the decision of the Commission and remand this case
    for further proceedings consistent with this opinion.
    Reversed and remanded.
    JORGENSEN and HUDSON, JJ., concur.
    -34-
    

Document Info

Docket Number: 2-09-0007 Rel

Filed Date: 9/16/2010

Precedential Status: Precedential

Modified Date: 10/22/2015