Karimi v. 401 North Wabash Venture, LLC , 952 N.E.2d 1278 ( 2011 )


Menu:
  •                            ILLINOIS OFFICIAL REPORTS
    Appellate Court
    Karimi v. 401 North Wabash Venture, LLC, 
    2011 IL App (1st) 102670
    Appellate Court            FARID KARIMI and MAHMOBAH KASHANI, Plaintiffs-Appellants,
    Caption                    v. 401 NORTH WABASH VENTURE, LLC, a Delaware Limited
    Liability Company; TRUMP CHICAGO MANAGING MEMBER LLC,
    a Delaware Limited Liability Company; and DEUTSCH BANK TRUST
    COMPANY AMERICAS, Defendants-Appellees.
    District & No.             First District, Second Division
    Docket No. 1-10-2670
    Filed                      July 26, 2011
    Held                       In an action seeking a declaration that the condominium purchase
    (Note: This syllabus       agreement plaintiffs entered into with defendants was still in effect when
    constitutes no part of     the condominium was sold to a third party, the trial court properly
    the opinion of the court   dismissed plaintiffs’ complaint alleging breach of contract, unjust
    but has been prepared      enrichment, conversion and that the liquidated damages provision was
    by the Reporter of         unenforceable, since a declaratory judgment claim was not the proper
    Decisions for the          method to present breach of contract allegations, defendants properly
    convenience of the         terminated the contract before selling the unit to a third party, the claims
    reader.)
    that defendants improperly retained the earnest money and earned interest
    were based on conclusions of law or fact that were not supported by
    specific factual allegations, unjust enrichment is not applicable to a claim
    based on a specific contract, the earnest money at issue was not a proper
    subject of a conversion claim, and the liquidated damages provision was
    not an unenforceable penalty.
    Decision Under              Appeal from the Circuit Court of Cook County, No. 2009-CH-37433; the
    Review                      Hon. Peter Flynn, Judge, presiding.
    Judgment                    Affirmed.
    Counsel on                  John A. Kukankos, P.C., of Chicago (John A. Kukankos, of counsel), for
    Appeal                      appellants.
    Novack & Macey LLP, of Chicago (Stephen Novack, John F.
    Shonkwiler, and Rebekah H. Parker, of counsel), for appellees.
    Panel                       JUSTICE HARRIS delivered the judgment of the court, with opinion.
    Presiding Justice Cunningham and Justice Connors concurred in the
    judgment and opinion.
    OPINION
    ¶1           Plaintiffs Farid Karimi and Mahmobah Kashani appeal the trial court’s dismissal of their
    first amended complaint pursuant to section 2-615 of the Code of Civil Procedure (735 ILCS
    5/2-615 (West 2006)). On appeal, plaintiffs contend the trial court erred in dismissing counts
    I through VI of their complaint.1 In their complaint, plaintiffs sought a declaration that the
    condominium purchase agreement they entered into with defendants was still in effect when
    defendants sold the condominium unit to a third party and that defendants improperly
    retained as liquidated damages the earnest money and earned interest. Plaintiffs also alleged
    breach of contract, unjust enrichment, and conversion. Plaintiffs further argued that the
    liquidated damages provision in the purchase agreement is unenforceable because it fails to
    set a certain sum as liquidated damages and effectively operates as a penalty. For the reasons
    hereinafter set forth, we affirm.
    ¶2                                       JURISDICTION
    ¶3          The trial court entered a final judgment in the instant case on August 5, 2010, and
    1
    Although plaintiffs argue in their brief that they are appealing the dismissal of counts II
    through VII, in the argument section they address counts I through VI without mention of count VII.
    Therefore, plaintiffs have waived review of the dismissal of count VII pursuant to Illinois Supreme
    Court Rule 341(h)(7). Ill. S. Ct. R. 341(h)(7) (eff. Sept. 1, 2006).
    -2-
    plaintiffs filed their notice of appeal on September 3, 2010. Accordingly, this court has
    jurisdiction pursuant to Illinois Supreme Court Rules 301 and 303 governing appeals from
    final judgments entered below. Ill. S. Ct. R. 301 (eff. Feb. 1, 1994); R. 303 (eff. May 30,
    2008).
    ¶4                                      BACKGROUND
    ¶5       The following facts are taken from plaintiffs’ first amended complaint and attached
    exhibits. On or about September 25, 2003, plaintiffs entered into an agreement with
    defendants to purchase condominium 46A (later renamed 47A) and parking spaces 253, 254
    and 255 at the Trump International Hotel and Tower. The total purchase price was
    $2,188,464 and pursuant to the purchase agreement, plaintiffs deposited $328,269.60 (15%
    of the purchase price) as earnest money. The agreement provided an anticipated closing date
    of late 2008.
    ¶6       On September 5, 2008, defendants notified plaintiffs that the unit would be substantially
    completed and ready to close on October 6, 2008. However, the closing was extended to May
    15, 2009, due to plaintiffs’ inability to obtain financing. Plaintiffs failed to close on May 15,
    2009, and in a letter dated July 6, 2009, defendants declared:
    “The time and date for closing and the applicable cure period per the default
    notice has elapsed and Purchaser has not closed on the unit. Therefore, Purchaser is
    in breach of and in default under the Purchase Agreement. Consequently, Seller
    hereby terminates the Purchase Agreement.”
    Whereupon, defendants retained the earnest money and earned interest as liquidated
    damages. In November 2009, defendants subsequently sold the unit and one less parking
    space to a third party for $2.5 million.
    ¶7       Plaintiffs filed a seven-count first amended complaint. Count I alleged that the purchase
    agreement was still in effect and sought a declaration of the parties’ rights under the
    agreement; count II alleged breach of contract; count III sought a declaration that the earnest
    money deposit should be returned; count IV sought a declaration, in the alternative, that the
    liquidated damages clause is unenforceable; count V alleged unjust enrichment; count VI
    alleged conversion; and count VII alleged a violation of the Illinois Consumer Fraud and
    Deceptive Business Practices Act (815 ILCS 505/1 et seq. (West 2006)). Defendants filed
    a motion to dismiss pursuant to section 2-615, and on August 5, 2010, the trial court granted
    the motion and dismissed the complaint with prejudice. Plaintiffs filed this timely appeal.
    ¶8                                       ANALYSIS
    ¶9      On appeal, plaintiffs challenge the trial court’s dismissal of counts I through VI. A
    motion to dismiss pursuant to section 2-615 challenges the legal sufficiency of the complaint.
    Dloogatch v. Brincat, 
    396 Ill. App. 3d 842
    , 846 (2009). In ruling on the motion, the court
    accepts as true all well-pleaded facts in the complaint as well as all reasonable inferences
    drawn therefrom. Vitro v. Mihelcic, 
    209 Ill. 2d 76
    , 81 (2004). Any exhibits attached to the
    complaint are also considered. Beahringer v. Page, 
    204 Ill. 2d 363
    , 365 (2003). Dismissal
    -3-
    under section 2-615 is proper if the pleadings and attachments, when construed in the light
    most favorable to the plaintiff, clearly show that plaintiff cannot prove any set of facts that
    would entitle him to relief. Board of Directors of Bloomfield Club Recreation Ass’n v.
    Hoffman Group, Inc., 
    186 Ill. 2d 419
    , 424 (1999). Review of the trial court’s dismissal of
    plaintiff’s complaint pursuant to section 2-615 is de novo. Doe v. McKay, 
    183 Ill. 2d 272
    ,
    274 (1998).
    ¶ 10        Counts I and III, respectively, request the court to issue a declaratory judgment. A claim
    for declaratory judgment, however, is not the proper vehicle for presenting what are, in
    essence, plaintiffs’ breach of contract allegations. The declaratory judgment process allows
    a court to address a controversy after a dispute arises but before steps are taken that give rise
    to a claim for damages or other relief. Beahringer, 
    204 Ill. 2d at 372-73
    . Although a
    declaratory judgment action is proper to determine the parties’ existing rights, a court may
    dismiss such an action if “a party, seeks to enforce his rights after the fact.” Senese v.
    Climatemp, Inc., 
    222 Ill. App. 3d 302
    , 314 (1991). Here, defendants have already terminated
    the purchase agreement and sold the unit to a third party. Plaintiffs are seeking “to enforce
    [their] rights after the fact” and these allegations are properly breach of contract allegations.
    The dismissal of the declaratory judgment counts was proper on that basis.
    ¶ 11        Even on the merits, plaintiffs’ allegations in counts I through III fail to state a cause of
    action upon which relief can be granted. Count I essentially contends that defendants
    breached the purchase agreement by selling the unit to a third party while the agreement was
    still in full force and effect. Count II, alleging straightforward breach of contract, echoes
    count I and adds that defendants further breached the agreement by failing to maintain
    plaintiffs’ earnest money in an interest-bearing account. Count III alleges that defendants
    failed to return plaintiffs’ earnest money and earned interest pursuant to paragraph 12 of the
    purchase agreement. Paragraph 12(a) states as follows:
    “Time is of the essence with regard to Purchaser’s obligations and covenants
    hereunder. In the event of a default or breach of this Purchase Agreement by
    Purchaser, Seller shall notify Purchaser of such breach or default and of the
    opportunity, which shall be given the Purchaser, to remedy such breach or default
    within twenty (20) days after the date such notice was received. If Purchaser fails to
    remedy such breach or default within twenty (20) days after receipt of Seller’s notice,
    then, subject to the limitations set forth below, Seller may terminate this Purchase
    Agreement and, as its sole and exclusive remedy upon termination, retain as
    liquidated damages from Purchaser an amount equal to the sum of (i) the amount set
    forth *** required to be paid as an Earnest Money deposit and (ii) all amounts paid
    or to be paid by Purchaser to Seller for any other services or work performed or to be
    performed by Seller. *** In accordance with Section 1703(d) of the Interstate Land
    Sales Full Disclosure Act, if Seller is otherwise entitled to the liquidated damages
    described above, Seller shall return to Purchaser amounts paid to Seller (excluding
    interest paid under the Purchase Agreement) in excess of: (x) 15% of the Purchase
    Price (excluding any interest owed under the Purchase Agreement) or (y) the amount
    of Seller’s actual damages, whichever is greater.”
    ¶ 12        Plaintiffs’ first amended complaint states that defendants first notified plaintiffs that the
    -4-
    unit would be ready to close on October 6, 2008. Due to plaintiffs’ inability to obtain
    financing, the closing was extended to May 15, 2009. Plaintiffs, however, failed to close on
    that date and on July 6, 2009, more than 20 days later, defendants sent a letter to plaintiffs
    terminating the purchase agreement. After terminating the agreement, defendants sold the
    unit to a third party. The facts alleged by plaintiffs show that defendants properly terminated
    the purchase agreement pursuant to paragraph 12(a) before selling the unit to a third party.
    Accordingly, plaintiffs’ allegation that the purchase agreement was in full force and effect
    when defendants sold the unit to a third party (counts I and II) is incorrect and plaintiffs
    cannot prove any set of facts entitling them to relief.
    ¶ 13        The remaining allegations contained in counts II and III also fail to state a cause of action
    upon which relief can be granted. In support of their contentions, plaintiffs merely conclude
    that “[u]pon information and belief, the account into which the Trump defendants placed the
    Earnest Money Deposit failed to pay any interest for a period of time” (count II); and,
    interpreting the purchase agreement against defendants, the liquidated damages provision in
    paragraph 12 requires the return of plaintiffs’ earnest money and earned interest because
    defendants suffered no damages (count III). In opposing a motion to dismiss pursuant to
    section 2-615, plaintiffs cannot rely on mere conclusions of law or fact unsupported by
    specific factual allegations. Dloogatch, 396 Ill. App. 3d at 850. Dismissal of counts I through
    III of plaintiffs’ complaint was proper.
    ¶ 14        Count V of plaintiffs’ first amended complaint alleges unjust enrichment. Under this
    theory of recovery, plaintiffs must show that defendants “voluntarily accepted a benefit
    which would be inequitable for [them] to retain without payment.” People ex rel. Hartigan
    v. E&E Hauling, Inc., 
    153 Ill. 2d 473
    , 497 (1992). However, where a specific contract
    governs the relationship between the parties, the doctrine of unjust enrichment is
    inapplicable. La Throp v. Bell Federal Savings & Loan Ass’n, 
    68 Ill. 2d 375
    , 391 (1977). If
    the complaint expressly alleges a contract, the count alleging unjust enrichment is properly
    dismissed. Hartigan, 
    153 Ill. 2d at 497
    . Here, plaintiffs’ first amended complaint states that
    the parties executed a purchase agreement. Count V does not argue in the alternative that the
    contract was invalid, no longer in full force and effect, or otherwise unenforceable. Instead,
    it incorporates the allegations of counts I through IV, which allege the existence of an
    enforceable purchase agreement. Therefore, the trial court properly dismissed count V of
    plaintiffs’ first amended complaint.
    ¶ 15        Count VI alleges conversion based on defendants’ wrongful possession and ownership
    of plaintiffs’ earnest money and earned interest. Conversion is the improper “deprivation of
    one who has a right to the immediate possession of the object unlawfully held.” Bender v.
    Consolidated Mink Ranch, Inc., 
    110 Ill. App. 3d 207
    , 213 (1982). The subject of conversion
    must be “an identifiable object.” In re Thebus, 
    108 Ill. 2d 255
    , 260 (1985). Money may be
    the subject of conversion, but only if it is shown that the money “at all times belonged to the
    plaintiff and that the defendant converted it to his own use.” Thebus, 
    108 Ill. 2d at 261
    . The
    general rule, however, is that an action for conversion may not be maintained for money
    representing a general debt or obligation. Thebus, 
    108 Ill. 2d at 261
    . The purchase agreement
    states that “[e]arnest money so paid and deposited shall be held for the mutual benefit of
    Seller and Purchaser.” Thus, the earnest money at issue here does not belong to plaintiffs at
    -5-
    all times. Furthermore, it represents plaintiffs’ obligation to fulfill the contract. Since the
    earnest money here is not the proper subject of a conversion claim, dismissal of count VI was
    proper.
    ¶ 16        The dismissal of count IV presents a more complicated issue as it concerns the validity
    and enforceability of the liquidated damages clause contained in paragraph 12(a) of the
    purchase agreement. No fixed rule applies to all liquidated damages provisions, and courts
    must evaluate each one on its own facts and circumstances. Jameson Realty Group v.
    Kostiner, 
    351 Ill. App. 3d 416
    , 423 (2004). In general, under Illinois law a liquidated
    damages provision is “valid and enforceable in a real estate contract, when: (1) the parties
    intended to agree in advance to the settlement of damages that might arise from the breach;
    (2) the amount of liquidated damages was reasonable at the time of contracting, bearing some
    relation to the damages which might be sustained; and (3) actual damages would be uncertain
    in amount and difficult to prove.” Grossinger Motorcorp, Inc. v. American National Bank
    & Trust Co., 
    240 Ill. App. 3d 737
    , 749-50 (1992). Parties often include liquidated damages
    provisions in real estate transactions “to avoid the difficulty of ascertaining and proving
    damages by such methods as market value, resale value or otherwise.” Siegel v. Levy
    Organization Development Co., 
    182 Ill. App. 3d 859
    , 861 (1989).
    ¶ 17        In Siegel, we upheld as enforceable a clause in the purchase agreement providing that in
    case of buyer default all sums theretofore paid by the buyer, including earnest money, would
    be forfeited as liquidated damages. Siegel, 182 Ill. App. 3d at 862. We found that damages
    in the amount of $320,000 earnest money paid toward the purchase of a $1.6 million
    condominium was reasonable in light of losses that might have been anticipated at the time
    of contracting and the difficulty of ascertaining losses in the event of a breach. Id.
    ¶ 18        Plaintiffs first contend that paragraph 12(a) is unenforceable because it fails to set a
    certain sum as liquidated damages. Plaintiffs argue that a set sum evidences the parties’
    agreement on the settlement of damages, and paragraph 12(a)’s reference to amounts paid
    for other services or work performed by defendants, in addition to the earnest money, shows
    that they did not agree to a liquidated sum. However, in a real estate contract liquidated
    damages specified as “ ‘all sums theretofore paid to Seller’ ” including earnest money and
    payment for extras, have been upheld as “reasonable in light of any losses that could have
    been anticipated at the time of the contract.” Siegel, 182 Ill. App. 3d at 862. See also Morris
    v. Flores, 
    174 Ill. App. 3d 504
    , 507 (1988) (enforceable liquidated damages clause provided
    that plaintiff would forfeit all money deposited under the contract, including earnest money).
    In their brief, plaintiffs acknowledge that “[a]t the time of contracting, it remained possible
    that Plaintiffs would, during the more than five-year period from execution of the Purchase
    Agreement to completion of the construction of the Unit, pay additional deposits for other
    services or work” performed by defendants. Plaintiffs, then, understood and agreed that the
    earnest money and additional deposits were the amount designated as liquidated damages in
    paragraph 12(a) when they executed the purchase agreement, and their argument that the
    parties did not agree to a set sum is not persuasive.
    ¶ 19        Plaintiffs dispute the applicability of Siegel, arguing that despite language in the
    liquidated damages provision referring to “all sums theretofore paid,” the Siegel court’s
    holding focused only on the earnest money deposited. The provision in Siegel stated that in
    -6-
    case of a purchaser breach, “ ‘all sums theretofore paid to Seller (including without limitation
    earnest money and payments for Extras) by Purchaser shall be forfeited as liquidated
    damages.’ ” Siegel, 182 Ill. App. 3d at 862. The Siegel court approved of the trial court’s
    reasoning evidenced as follows:
    “ ‘[I]t says including without limitation, but it does refer to the earnest money
    deposit, so it’s not only just saying all sums but it seems to me that the parties are
    specifically focusing in on at least the earnest money which is set forth in the
    contract and that is clear.’ ” (Emphasis added.). Siegel, 182 Ill. App. 3d at 862.
    Contrary to plaintiffs’ contention, the Siegel court did not interpret the liquidated damages
    amount to include only the earnest money deposit and not “ ‘all sums.’ ” Id. Rather, it
    reasoned that the provision adequately stipulated an amount of damages despite the
    “ ‘without limitation’ ” language because the parties clearly intended to make the earnest
    money amount, which was clearly set, central to the provision. Id. Here, as in Siegel, the set
    sum of plaintiffs’ earnest money was the focus of the liquidated damages amount, and the
    inclusion of payments for other work or services did not render the amount uncertain at the
    time of contracting.
    ¶ 20       Plaintiffs also contend that the liquidated damages provision is unenforceable because
    extrinsic evidence is required to determine the actual amount. As support, plaintiffs cite
    Hamming v. Murphy, 
    83 Ill. App. 3d 1130
     (1980), and First National Bank & Trust Co. of
    Barrington v. Maas, 
    26 Ill. App. 3d 733
     (1975). However, both cases involved installment
    contracts for the purchase of land and the subsequent forfeiture of installment payments,
    neither of which is at issue here. Furthermore, they do not support plaintiffs’ contention that
    a provision requiring the introduction of outside evidence is not adequately liquidated. The
    court in Hamming noted that under Illinois law, in order for the seller to retain all installment
    payments made as liquidated damages there must be proof that the amount did not exceed
    the fair rental value of the property. Hamming, 83 Ill. App. 3d at 1136. Since no such
    evidence was presented at trial, the court in Hamming held that the cause would be remanded
    to the trial court to determine whether the installment payments represented the fair rental
    value of the property. Hamming, 83 Ill. App. 3d at 1137. See also Maas, 26 Ill. App. 3d at
    739 (appellate court upheld the liquidated damages provision where the evidence showed the
    amount did not exceed the fair rental value of the property). In both cases, the courts
    considered evidence outside the information contained in the contracts to determine the
    liquidated amount.
    ¶ 21       Plaintiffs’ final contention is that the liquidated damages provision is an unenforceable
    penalty. Unlike the provisions upheld in Siegel and Morris discussed above, paragraph 12(a)
    refers to actual damages in determining the liquidated damages amount. The question is
    whether that reference is fatal to the enforcement of the liquidated damages provision. A
    provision that allows defendants the option to receive liquidated damages or seek actual
    damages is unenforceable as a penalty. Grossinger, 240 Ill. App. 3d at 752. In Grossinger,
    the purchase contract provided that if the plaintiff caused the contract to terminate, “ ‘the
    earnest money shall be forfeited to the [defendant] to be retained by the [defendant] as
    liquidated damages, or at [defendant]’s option, [defendant] may exercise any other remedy
    available at law.’ ” Grossinger, 240 Ill. App. 3d at 740. This court held that the provision
    -7-
    was unenforceable because it penalized the plaintiff by giving defendants a minimum
    recovery regardless of actual damages, and also allowed defendants to disregard liquidated
    damages if actual damages exceeded the specified amount. Grossinger, 240 Ill. App. 3d at
    751. See also Catholic Charities of the Archdiocese of Chicago v. Thorpe, 
    318 Ill. App. 3d 304
    , 311-13 (2000) (held that a liquidated damages provision giving the seller the option to
    claim the earnest money as liquidated damages is unenforceable as a penalty). Such a
    provision negates the purpose of liquidated damages, which is to provide parties with an
    agreed-upon, predetermined damages amount when actual damages may be difficult to
    ascertain. Hickox v. Bell, 
    195 Ill. App. 3d 976
    , 987-88 (1990).
    ¶ 22        Despite its reference to actual damages, paragraph 12(a) does not give defendants the
    option to seek actual damages. Although a calculation of actual damages may be necessary
    to determine a liquidated damages amount, defendants can receive no more than the amount
    plaintiffs have deposited pursuant to the agreement, even if actual damages prove greater
    than the sum deposited. Furthermore, unlike the clauses in Grossinger and Catholic
    Charities, no provision in the agreement allows defendants the option to pursue actual
    damages in case of plaintiffs’ breach. As discussed above, plaintiffs had knowledge of and
    agreed to the amounts included as liquidated damages at the time of contracting, and
    defendants have no option to disregard that amount. The liquidated damages provision at
    issue here is not an unenforceable penalty.
    ¶ 23        Plaintiffs also argue that paragraph 12(a) operates as a penalty because defendants
    suffered no actual damages. Instead, defendants sold the unit for approximately $400,000
    more than the contract price contained in the purchase agreement with plaintiffs. Citing
    Penske Truck Leasing Co. v. Chemetco, Inc., 
    311 Ill. App. 3d 447
     (2000), plaintiffs argue
    that “when a party receives both substantial liquidated damages and windfall profits, the
    court will consider the damages unreasonable.” Penske, however, concerned a provision with
    alternate methods of computing liquidated damages dependent on whether the nondefaulting
    party retained or sold the leased trucks at issue in the contract. Penske, 311 Ill. App. 3d at
    455. The court in Penske held that allowing the plaintiffs to retain the trucks, calculate
    liquidated damages based on that retention, then shortly thereafter sell the trucks at a profit
    would constitute unreasonable damages. Penske, 311 Ill. App. 3d at 457. It reasoned that “it
    was never the intention of the parties to permit plaintiff to proceed under the method of
    recovery used when plaintiff decides to retain the vehicles but later sells the vehicles and
    reaps a windfall in the process.” Penske, 311 Ill. App. 3d at 457. Unlike the liquidated
    damages provision in Penske, paragraph 12(a) does not contain alternate methods for
    computing damages depending on whether defendants retain or sell the condominium unit
    at issue. Defendants here properly claimed liquidated damages for plaintiffs’ default pursuant
    to the purchase agreement. Furthermore, unlike the provision in Penske, under the terms of
    this agreement whether defendants eventually sold the unit, and any proceeds from a sale,
    are irrelevant to the liquidated damages issue.2
    2
    The parties also argue whether the following federal cases or cases from other jurisdictions,
    Yockey v. Horn, 
    880 F.2d 945
     (7th Cir. 1989), Vanderbeek v. Barefoot, 226 F. App’x 3d 209 (3d Cir.
    2007), and Wasserman’s Inc. v. Township of Middletown, 
    645 A.2d 100
     (N.J. 1994), support
    -8-
    ¶ 24         A term fixing unreasonably large liquidated damages, however, may be unenforceable
    as a penalty on public policy grounds. Penske, 311 Ill. App. 3d at 454. The reasonableness
    of the amount, though, depends not on the actual damages suffered by the nonbreaching
    party, but on whether the amount reasonably forecasts and bears some relation to the parties’
    potential loss as determined at the time of contracting. Jameson, 351 Ill. App. 3d at 423.
    Courts have considered earnest money representing up to 20% of the purchase price a
    reasonable sum as liquidated damages. See Siegel, 182 Ill. App. 3d at 860. Here, the earnest
    money represented 15% of the purchase price, and plaintiffs acknowledge they did not make
    further payments for other services or work. Liquidated damages in the amount of 15% of
    the purchase price is a reasonable amount considering the potential loss each party faced at
    the time of contracting. Siegel, 182 Ill. App. 3d at 862. Furthermore, plaintiffs’ argument
    concerning defendant’s sale of the unit for $400,000 more than the contract price proves the
    validity of the liquidated damages provision because it shows how uncertain and difficult it
    was for the parties to ascertain actual damages at the time of contracting. See Jameson, 351
    Ill. App. 3d at 427.
    ¶ 25        Finally, plaintiffs contend that in a case such as the one at bar, where the nonbreaching
    party suffered no actual damages but instead reaped a handsome profit, enforcing the
    liquidated damages clause would be “obnoxious.” As support, plaintiffs cite Radloff v.
    Haase, 
    196 Ill. 365
     (1902). Radloff concerned a liquidated damages provision contained
    within a covenant not to compete. Radloff, 196 Ill. at 366. The defendant sold his bakery to
    the plaintiff and in the contract promised not to engage in the bakery business within a five-
    block radius. Id. The contract further stated that the defendant agreed to pay a sum of $2,000
    if he violated the agreement. Id. The plaintiff subsequently sold the bakery to a third party
    and moved out of Illinois. Id. at 366-67. Approximately one year later, the defendant opened
    a bakery business across the street from his former business without the plaintiff’s consent.
    Id. at 367. The plaintiff brought suit, seeking damages from defendant’s violation of the
    initial contract although he presented no evidence of actual damages from the breach.
    Radloff, 196 Ill. at 367. Our supreme court noted that the terms of the contract in Radloff did
    not make clear whether the damages provision contained therein was a liquidated damages
    provision or a penalty. Id. In determining whether or not the amount specified was liquidated
    damages, the court in Radloff reasoned that “the idea of the courts is to ascertain, if possible,
    the actual damages sustained, and if it is possible to ascertain the actual damages, or if the
    amount of liquidated damages mentioned in the contract is exorbitant, the court will construe
    the amount as a penalty, rather than as liquidated damages.” Radloff, 196 Ill. at 368. It found
    that the plaintiff “has not been engaged in the bakery business at Chicago a single day since
    [the defendant] re-entered the restricted territory, nor has he been in any way injured by the
    action of [the defendant] *** and to construe this contract as liquidated damages would work
    absurdity and oppression.” Radloff, 196 Ill. at 369.
    plaintiffs or defendants. These cases state the Restatement (Second) of Contracts’ position that the
    reasonableness of a liquidated damages provision may be determined either at the time of contracting
    or at the time of injury. Since Illinois law adequately addresses the issue, we need not consider these
    cases any further.
    -9-
    ¶ 26        Unlike the contract in Radloff, the purchase agreement here concerns a real estate
    transaction with a provision explicitly designating an amount as liquidated damages. Where
    damages for breach of contract would be uncertain or difficult to calculate, our supreme court
    has upheld a reasonable amount stipulated at the time of contracting as liquidated damages
    without regard to actual damages. See Weiss v. United States Fidelity & Guaranty Co., 
    300 Ill. 11
    , 17 (1921). In Weiss, the plaintiff contracted with the defendant to remodel a three-
    story building he owned. Weiss, 300 Ill. at 12-13. The contract provided that the project
    would be completed no later than January 15, 1917, and defendant would pay as liquidated
    damages $15 per day for each day thereafter until completion. Id. at 13. The defendant
    subsequently failed to complete the project and the plaintiff hired another contractor who
    finished the job on July 10, 1917, at an additional cost of $872.64. Weiss, 300 Ill. at 14-15.
    The supreme court held that under the terms of the contract, the plaintiff was entitled to
    $2,625 in liquidated damages. Weiss, 300 Ill. at 18-19. It reasoned that at the time of
    contracting, the parties reasonably presumed that any delay that might occur would be minor
    and the amount of $15 per day was not excessive in light of that time frame. Weiss, 300 Ill.
    at 18. It acknowledged that a liquidated damages provision specifying a certain amount per
    day “ ‘could be extended to such length of time as to become grossly excessive,’ ” but the
    “ ‘fact that the delay in the particular case was long continued to a time that may be said to
    be unreasonable or unusual cannot be looked to’ ” in determining whether to enforce a
    liquidated damages provision. Weiss, 300 Ill. at 19.
    ¶ 27        The purpose of a liquidated damages provision is to provide parties with a reasonable
    predetermined damages amount where actual damages may be difficult to ascertain. Hickox,
    195 Ill. App. 3d at 987-88. Courts generally give effect to such provisions “if the parties have
    expressed their agreement in clear and explicit terms and there is no evidence of fraud or
    unconscionable oppression.” Hartford Fire Insurance Co. v. Architectural Management,
    Inc., 
    194 Ill. App. 3d 110
    , 115 (1990). As discussed above, plaintiffs here understood and
    agreed to the explicit terms of paragraph 12(a) when they entered into the purchase
    agreement, and they make no claim that fraud or unconscionable oppression played a role in
    inducing them to sign the contract. The nature of a liquidated damages provision is such that
    the set amount may at times exceed actual damages, and other times actual damages may
    exceed the set amount. In entering into the purchase agreement, both parties here agreed to
    accept this inherent risk. Newcastle Properties, Inc. v. Shalowitz, 
    221 Ill. App. 3d 716
    , 725
    (1991). Although defendants could have elected not to seek liquidated damages given the
    circumstances here, they have the right to pursue such damages under paragraph 12(a), and
    the provision is valid and enforceable. The trial court properly dismissed plaintiffs’
    complaint.
    ¶ 28        Defendants argue in their brief that paragraph 12(a) is valid and enforceable because its
    provision that the seller would return amounts paid “in excess of: (x) 15% of the Purchase
    Price (excluding any interest owed under the Purchase Agreement) or (y) the amount of
    Seller’s actual damages, whichever is greater” tracks the language of the Interstate Land
    Sales Full Disclosure Act (
    15 U.S.C. § 1703
    (d) (2006)). Due to our disposition of the appeal,
    we need not consider this argument.
    ¶ 29        For the foregoing reasons, the judgment of the circuit court is affirmed.
    -10-
    ¶ 30   Affirmed.
    -11-