Siegel Development, LLC v. Peak Construction LLC ( 2013 )


Menu:
  •                            ILLINOIS OFFICIAL REPORTS
    Appellate Court
    Siegel Development, LLC v. Peak Construction LLC, 
    2013 IL App (1st) 111973
    Appellate Court            SIEGEL DEVELOPMENT, LLC, an Illinois Limited Liability Company;
    Caption                    ROSS SIEGEL; and GARY SIEGEL, Plaintiffs-Appellants, v. PEAK
    CONSTRUCTION LLC and PEAK PROPERTIES LLC, Illinois Limited
    Liability Companies; COLIN O. HEBSON; MICHAEL L. ZUCKER;
    ERIC BERNSTEIN; and MICHAEL OBLOY, Defendants-Appellees
    (842 Wood, LLC, an Illinois Limited Liability Company; Richard E.
    Lane; and Brad Court, Defendants).
    District & No.             First District, Sixth Division
    Docket Nos. 1-11-1973, 1-12-0745 cons.
    Filed                      June 28, 2013
    Rehearing denied           July 24, 2013
    Held                       Summary judgment was properly entered for defendants in an action
    (Note: This syllabus       alleging that defendants engaged in a conspiracy to defraud plaintiffs in
    constitutes no part of     connection with the sale of a four-unit building for purposes of
    the opinion of the court   conversion into condominium units, since plaintiffs did not reasonably
    but has been prepared      rely on the representations made by defendants, most of the
    by the Reporter of         representations, including the costs involved, were not actionable, and the
    Decisions for the          record disclosed that there was no meeting of the minds as to the scope
    convenience of the         of the project, regardless of plaintiffs’ contention that “a deal was in
    reader.)
    place.”
    Decision Under             Appeal from the Circuit Court of Cook County, No. 06-L-11187; the
    Review                     Hon. Brigid Mary McGrath, Judge, presiding.
    Judgment                   Affirmed.
    Counsel on                  Donald L. Johnson and Julie A. Boynton, both of Donald L. Johnson,
    Appeal                      P.C., of Chicago, for appellants.
    Stuart M. Nagel, of Chalmers & Nagel, P.C., of Chicago, for appellees.
    Panel                       JUSTICE GORDON delivered the judgment of the court, with opinion.
    Presiding Justice Lampkin and Justice Hall concurred in the judgment
    and opinion.
    OPINION
    ¶1          The instant consolidated appeals concern a two-story four-unit building purchased by
    plaintiffs, Siegel Development, LLC, Gary Siegel, and Ross Siegel, for the purpose of
    converting the building into condominium units. Plaintiffs allege that they purchased the
    property in reliance on a promise from several of the defendants that defendant Peak
    Construction LLC would perform the renovations needed for the condominium conversion
    project for a price of $183,200. After closing on the purchase, Peak Construction, through
    defendant Michael Zucker, informed plaintiffs that it would be unable to perform the
    renovation work. Plaintiffs filed suit, claiming that defendants fraudulently induced them to
    purchase the property. The trial court granted defendants’ motion for summary judgment on
    plaintiffs’ fraud claims, finding that plaintiffs did not reasonably rely on defendants’
    representations and that most of the representations were not actionable. For the following
    reasons, we affirm.
    ¶2                                        BACKGROUND1
    ¶3                                             I. Parties
    ¶4          Plaintiff Siegel Development, LLC (Siegel Development), is an Illinois limited liability
    company, of which plaintiffs Ross and Gary Siegel are the members.
    ¶5          Plaintiff Gary Siegel is a licensed real estate agent employed by Coldwell Banker
    Residential Real Estate and the Matt Garrison Group, a real estate agency associated with
    Coldwell Banker, at the time of the transaction at issue. He has participated in four real estate
    transactions, not including the transaction at issue in the instant case, which includes: a 90%
    stake in a building purchased in 2000; a condominium unit purchased in 2002 and sold in
    2005; a condominium unit purchased in 2006; and a building purchased on an undisclosed
    1
    All facts arise from the verified complaint or the parties’ discovery responses, including
    testimony from the 19 depositions contained in the record on appeal.
    -2-
    date. During his deposition, Gary2 also testified that he owned his current home, which he
    purchased in 2008. Gary further testified that during his time at the Matt Garrison Group,
    Gary represented three buyers and two sellers in real estate transactions. When he represented
    the buyer, the agency was paid a commission of 2.5% by the seller, which was the standard
    in the Chicago real estate industry; Gary received a portion of the commission.
    ¶6        Plaintiff Ross Siegel graduated from the University of Wisconsin in 1997 with a
    bachelor’s degree in accounting and passed the certified public accountant exam the same
    year. He became a licensed real estate agent in December 2005, but has never purchased or
    sold any properties as an agent. He has participated in four real estate transactions, not
    including the transaction at issue in the instant case, which includes: a 50% stake in a “2-
    flat,” which was purchased in 1998 and sold in 2004; a townhouse used as a primary
    residence, purchased in 1999 and sold in 2005; a 33% stake in a one-story office building,
    purchased in 2004; and a house used as a primary residence, purchased in 2005. He also filed
    suit against the builder of the house purchased in 2005 on June 23, 2006, alleging that the
    house was set back 15 feet farther from the street than was provided for by the stamped,
    approved plans. Sam Borek, plaintiffs’ attorney during the transaction at issue, opined that
    Ross “is an extremely bright individual with a very sophisticated tax and business
    background.”
    ¶7        Defendant 842 Wood, LLC (842 Wood), is a member-managed Illinois limited liability
    company. Defendants Hebson and Lane are the members of 842 Wood. Only Hebson is a
    party to the instant appeal,3 as the claims against Lane were dismissed with prejudice
    pursuant to a settlement agreement and 842 Wood was voluntarily dismissed without
    prejudice on February 23, 2010. In addition to being a member of 842 Wood, Hebson is an
    Illinois-licensed real estate agent for @properties.
    ¶8        Defendants Peak Construction LLC (Peak Construction) and Peak Properties LLC (Peak
    Properties) are manager-managed Illinois limited liability companies. Together with Peak
    Construction Development LLC (Peak Development), a manager-managed Illinois limited
    liability company, Peak Construction and Peak Properties are sometimes referred to as the
    “Peak entities.”
    ¶9        Defendant Zucker is a property manager/partner with Peak Properties and is a partner in
    all three of the Peak entities. Zucker testified that defendant Michael Obloy (Obloy) is an
    employee of Peak Development whose role was “[f]inance,” meaning “[d]ue diligence on
    deals.” Defendant Eric Bernstein (Bernstein) was employed by Peak Properties in 2006,
    performing “spot jobs” as part of an “offset” that he described as “just a little separate
    2
    We refer to Gary and Ross Siegel by their first names for the sake of clarity and collectively
    refer to them as the Siegels.
    3
    According to the record, Hebson voluntarily filed for bankruptcy in the United States
    Bankruptcy Court for the Northern District of Illinois on November 4, 2010, while the motion for
    summary judgment in the instant case was pending. On July 12, 2011, the bankruptcy court approved
    Hebson’s voluntary waiver of discharge and, on October 3, 2011, Hebson’s bankruptcy case was
    closed without entry of a discharge.
    -3-
    company that Mike [Zucker] and I were in charge of.” Bernstein explained: “I was working
    for Peak Properties. I was just, kind of, a subsidiary. So I came on to try to establish, you
    know, an offset of, kind of like, Peak Construction, just running–again, just running some
    projects and trying to bring in more income.” Bernstein testified that Zucker was his
    supervisor.
    ¶ 10       Defendant Brad Court (Court) is an Illinois-licensed realtor associated with Coldwell
    Banker Residential Real Estate and the Matt Garrison Group. Court voluntarily filed for
    bankruptcy in the United States Bankruptcy Court for the Northern District of Illinois on
    February 12, 2008, and is not a party to the instant appeal.
    ¶ 11                                    II. Transaction at Issue
    ¶ 
    12 A. 842
    Wood’s Ownership of the Property
    ¶ 13           Colin Hebson, a real estate agent and member of 842 Wood, testified that, during the
    spring of 2006, he learned that a two-story, four-unit building located at 1025 N. Wood
    Street was for sale. After a walk through the property, Hebson decided to make an offer to
    purchase it; Hebson did not obtain a professional inspection because “[w]e were buying it
    to convert to condominiums or hold as an apartment and we felt that it was fine as it were
    [sic].” He and Lane purchased the property for 842 Wood, even though title to the property
    was placed in Lane’s name.
    ¶ 14       Lane testified that he was the managing member of 842 Wood and that Hebson was the
    other member and Lane’s business partner. Lane took title to the property in his name, but
    considered 842 Wood the owner. Originally 842 Wood was going to develop the property,
    but instead decided to sell it because there was a great deal of interest from potential buyers.
    As Lane’s business partner, Hebson was authorized to sell the property if he located a buyer;
    Hebson was paid $20,000 for selling the property and also received 50% of the partnership
    distribution.
    ¶ 15       Hebson testified that after they purchased the property, he and Lane explored different
    opportunities for the property: “In real estate development, we run many different options
    at the same time. We’ll look at selling to people after we purchased a building, we’ll look
    at converting it [to] condos, we also look at keeping it as a rental building.” Hebson and Lane
    obtained a rough estimate of the renovation costs they were considering undertaking, which
    was obtained from Bernstein in the form of a one-page spreadsheet; Bernstein indicated that
    the work in the rough estimate could be completed with a repair and replace permit.
    ¶ 16       Bernstein testified that the first time he visited the property, he was with Lane and
    Hebson, where Lane discussed the renovations that he envisioned; Hebson also supplied
    some ideas while they were walking through the property. Bernstein testified that the project
    was going to be a “lipstick job,” meaning a remodel, as opposed to a “gut rehab,” meaning
    “complete demolition, down to the shell.” In order to complete a lipstick job, “[m]ost likely
    [the permit required] would be a repair or replace.” Within the next week, approximately the
    end of May to beginning of June 2006, Bernstein provided Hebson with a spreadsheet
    containing a proposed budget based on their walk-through; the amount was approximately
    $183,000. Nothing happened with the proposal; Hebson testified that he and Lane decided
    -4-
    not to perform the renovations and instead sold the property.
    ¶ 17       The instant appeal revolves in large part around the spreadsheet provided to Hebson by
    Bernstein. Thus, we reproduce the spreadsheet in full:
    DEMO                                             $10,000.00
    ROUGH CARPENTRY                                  $8,000.00
    FINISH CARPENTRY                                 $7,000.00
    PAINTING                                         $13,200.00
    TILE                                             $3,500.00
    ROOF (SHINGLES)                                  $8,000.00
    DECK                                             -
    INSULATION                                       -
    ELECTRIC                                         $12,000.00
    HVAC                                             $21,000.00
    PLUMBING                                         $7,000.00
    DRYWALL                                          $10,000.00
    CONCRETE                                         $12,000.00
    WINDOWS                                          $7,000.00
    SIDING/GUTTER/DOWN                               -
    SPOUTS
    HARDWOOD FLOORS                                  $18,000.00
    MASONRY                                          $6,000.00
    DOORS                                            $2,700.00
    K/B CABINETS                                     $6,000.00
    APPLIANCES                                       $12,000.00
    PLUMBING FINISH                                  $3,000.00
    GC/SUPERVISOR FEE                                $15,000.00
    INSURANCE                                        $1,800.00
    TOTAL       $183,200.00
    ¶ 18      Hebson testified that he “had put the word out to some different people that [1025 Wood
    -5-
    was for sale as] an off-market deal.” The affidavit of Joseph Zimmerman, a sales agent at
    @properties with whom Hebson had previously worked, stated that he signed an assignment
    and assumption of a real estate contract for the purchase of 1025 Wood on January 27, 2006.
    Zimmerman intended to purchase the property with other members of a limited liability
    company known as BSD LLC and to have BSD LLC hold title to the property. On February
    9, 2006, Zimmerman terminated the assignment and assumption of real estate contract for
    reasons unrelated to the condition of the property.
    ¶ 19       Obloy, an employee of Peak Development at the time, testified that he first learned of
    1025 Wood when Hebson informed him it was available for sale; Obloy knew Hebson
    because Peak Development had listed some projects that it had developed for sale through
    @properties, Hebson’s employer. Obloy had been actively purchasing apartment buildings,
    and he believed that Hebson approached him for that reason. Obloy visited the property and
    observed that it “generally needed rehab” consistent with an apartment building that was 80
    to 100 years old. Obloy submitted an offer to purchase the property for $625,000. Obloy
    intended to renovate the property to use for apartment rentals and estimated that it would cost
    approximately $200,000 based on his financial projections. Obloy canceled the offer during
    the attorney review period because he discovered that there was at least one long-term lease
    on the property.
    ¶ 20       Hebson testified that he also attempted to sell the property to a third person, whose name
    Hebson could not recall, but the deal did not go through.
    ¶ 21              B. The Siegels’ Search for a Condominium Conversion Project
    ¶ 22       The complaint alleges that in February or March 2006, Gary informed Court that he was
    looking for a condominium conversion opportunity, which was to be Gary’s first real estate
    project. Gary testified that Court was also an agent of the Matt Garrison Group, and was
    “showing [Gary] the business, going to teach [him] the ropes.” Ross testified that Gary and
    Court had a “[s]eemingly pretty close” relationship; Court “basically help[ed] [Gary] out,
    help[ed] him learn the business” of being a real estate agent.
    ¶ 23       Ross testified that once Court learned that Gary and Ross were interested in investing in
    a real estate project together, Court told Gary that he had a building to show Gary. Gary
    testified that Court “was being a nice guy trying to help [Gary] out,” but was also “going to
    play a major role in the resale of the units,” bringing in buyers and receiving a commission.
    Likewise, Ross testified that he believed that Court was going to help them with their
    purchase of the property because he wanted to help sell the units upon completion of the
    project; Court never told Ross that he wanted to help sell the properties, but Ross thought he
    did “[b]ecause he is a realtor.” Court also testified that he assumed that he would be one of
    the listing agents on the resold units if he was the one putting the project together, because
    “[t]hat’s just how the real estate went down.”
    ¶ 24       Obloy testified that Court called Obloy, who had met Court when Court acted as a listing
    agent for a property Peak Development developed, to inform him that a real estate
    professional was looking for a small condominium conversion project. Obloy called Hebson
    to ask him if he knew of any buildings for sale that would be suitable for the project. Hebson
    -6-
    informed Obloy that 1025 Wood was for sale. Obloy testified that he discussed compensation
    with Court; Court indicated that he wanted to receive a referral fee, and they agreed to split
    whatever the referral fee would be. Hebson informed Obloy that there would be a referral fee
    paid by the seller of approximately $20,000. Obloy did not inform plaintiffs that he or Court
    was being paid a fee.
    ¶ 25       Court testified that the project “was supposed to be an easy deal for somebody that was
    new; here’s a building, here’s all the stuff, here you go.” Accordingly, the complaint alleges
    that in early June 2006, Court arranged a meeting between Gary, Hebson, and Obloy. At
    approximately the same time, Court obtained from Hebson an itemized cost spreadsheet
    prepared by Peak Construction, listing various proposed repairs and upgrades to the building
    totaling $183,200. Court gave a copy of the spreadsheet to Gary.
    ¶ 26       Gary testified that Court informed him that Hebson had done a number of deals with
    Court and that Hebson was “a big time real estate developer. He gets his hands on the best
    deals in the city. If I had any desire–which at that point I was starting to spend more and
    more time in real estate. If I had any desire to be successful, this is a guy that I really wanted
    to have on my side.”
    ¶ 27                             C. Meetings With Defendants
    ¶ 28      Since the parties disagree as to some of the representations made during the various
    meetings between them, where necessary, we set forth plaintiffs’ version of events for each
    meeting, followed by defendants’ version.
    ¶ 29                   1. June 7 Meeting and Signing of Purchase Contract
    ¶ 30                                                   a. Plaintiffs
    ¶ 31       The complaint alleges that a meeting between Gary, Hebson, Court, and Obloy took place
    at 1025 Wood on June 7, 2006. At the meeting, Hebson told Gary that the building was “ ‘the
    perfect project’ ” for a first-time developer, with everything in place for a “ ‘huge’ ” return
    on investment. Hebson also told Gary that all the work necessary could be done after
    obtaining a “repair and replace” permit, instead of requiring other, more expensive, permits
    and that Hebson already had an arrangement with Peak Construction to perform all of the
    repair and remodeling work on the project. Hebson said, and Obloy confirmed, that the
    spreadsheet Gary received from Court was accurate and that all of the listed work was
    included in Hebson’s construction contract with Peak Construction; the work and $183,200
    price were “all agreed”; and Peak Construction was ready to begin work as soon as Gary
    closed on the purchase. Hebson explained that he had “done ‘a ton’ of similar projects
    previously” and would have converted 1025 Wood as well but was handling other, larger,
    projects.
    ¶ 32       Hebson walked through the building with Gary, informing Gary of what he could expect
    from the finished project, given the construction contract and pricing that Hebson had in
    place through Peak Construction. Hebson told Gary that he would be available throughout
    the project to assist Gary and would periodically visit the site to ensure that work was
    -7-
    proceeding according to the plan that Hebson and Bernstein had formulated.
    ¶ 33       Hebson said that Gary would be unable to obtain another deal like the one he was
    offering, with the rehabilitation and remodeling contract in place and at a favorable price, and
    that Gary needed to act quickly to accept the deal or else someone else would. Hebson and
    Court informed Gary that Hebson had other potential buyers who were ready and willing to
    purchase the building for a price of $700,000 or higher. However, Hebson was willing to sell
    the property to Gary “as a favor,” with the Peak Construction repair and remodeling contract
    included as a “package.”
    ¶ 34       Hebson informed Gary that the construction contract with Peak Construction had been
    created for Hebson, then offered to Obloy, who turned it down because of a conflict of
    interest arising from his responsibilities with Peak Construction; Hebson, Obloy, and
    Bernstein each explained to Gary that Hebson was an “ ‘important’ ” client of Peak
    Construction.
    ¶ 35       The complaint alleges that, “[w]hen Gary Siegel asked whether there were any
    unforeseen risks that a first-time developer should be aware of, Obloy and Hebson stated
    that, if Gary Siegel and Ross Siegel purchased the building, a ‘huge’ profit on the conversion
    to condominiums was almost guaranteed; the Siegels would have to really screw up to make
    only a small profit.”
    ¶ 36       The complaint alleges that, “[i]n reliance on Hebson’s and Obloy’s representations, on
    their own behalf and on behalf of their respective principals, 842 Wood and Peak
    Construction,” on June 13, 2006, Gary signed a contract to purchase the building for
    $680,000, with the right to assign the contact to a limited liability company. The next day,
    Hebson signed the purchase contract on behalf of 842 Wood, the seller. The purchase
    contract provided for an attorney modification period of 10 business days and a closing date
    of July 10, 2006. In July 2006, Gary assigned the purchase contract to Siegel Development.
    Gary testified that prior to closing, he visited the property between 8 and 12 times, half the
    time with Court accompanying him.
    ¶ 37                                       b. Defendants
    ¶ 38       Obloy testified that he first met Gary when Obloy, Gary, Court, and Hebson visited the
    property together in June 2006. Obloy was present at the meeting because Court asked him
    to attend; he “was there to walk through the building and if anybody had any questions about
    condominium conversion developments, if [he] had an opinion.” Obloy provided Court with
    the spreadsheet4 containing his financial projections, but did not know whether the
    spreadsheet was given to Gary; Obloy changed the acquisition price in the spreadsheet from
    $625,000 to $700,000, because Hebson informed him that the property was being sold for
    that amount. They walked through the building, and Gary and Hebson were discussing
    Hebson’s vision for the property. Obloy recalled that someone said “something to the extent
    4
    Obloy’s spreadsheet is not the same spreadsheet as that provided by Bernstein to Hebson
    and reproduced above.
    -8-
    [sic] of being a good project for a first-time project or a first-time developer.” Hebson also
    mentioned that Peak Construction had previously indicated that it would be able to perform
    construction work on the property during discussions with Hebson. Hebson and Gary “talked
    in generalities about interior renovation, walking through the units, put a kitchen here, move
    this wall there.”
    ¶ 39       Hebson testified that he met Gary, Court, and Obloy at 1025 Wood on June 7. Hebson
    informed Gary that Bernstein provided him with a rough estimate for some of the repairs and
    indicated that a repair and replace permit would suffice.
    ¶ 40                                       2. June 15 Meeting
    ¶ 41                                           a. Plaintiffs
    ¶ 42        The complaint alleges that, on June 15, 2006, plaintiffs met at 1025 Wood with Hebson,
    Court, and Bernstein. During the meeting, Hebson reiterated that the repair and remodeling
    contract with Peak Construction was in place, with Peak Construction to receive $183,200
    for the work, with the work to begin immediately after closing. Bernstein said that “he stood
    behind whatever Hebson said regarding the proposed [construction] contract with Peak
    Construction, and Hebson said he stood behind Bernstein’s representations as well.” “[T]his
    assurance by Bernstein was considered crucial by Gary Siegel and Ross Siegel, because the
    $183,200.00 ‘deal’ with Peak Construction made the project much more attractive to them
    than it otherwise would have been.”
    ¶ 43        Bernstein informed plaintiffs that he had walked through the building several times with
    Hebson and that he and Hebson had a clear and mutual understanding of what the finished
    product would be. Bernstein and Hebson told plaintiffs that there was “no need” for plaintiffs
    to hire a professional inspector to inspect the property, because “ ‘everything’ ” would be
    replaced and because an inspector would not find any additional information without
    “ripping up” the walls, floors, and ceilings, which would only create more work for Peak
    Construction and additional expense for plaintiffs. Bernstein assured plaintiffs that the
    structure of the building was “sound” and that the sloping of the floor would be fixed when
    the floors were replaced as part of the work included in the Peak Construction contract.
    Hebson and Bernstein indicated that the proposed work was within the scope of a repair and
    replace permit issued by the City of Chicago, and that they had frequently undertaken this
    type of project with that type of permit. Hebson and Bernstein “described it as a ‘lipstick’
    project rather than a ‘gut’ rehab.” They actively discouraged plaintiffs from consulting with
    others about the project, repeatedly saying that they were the experts, having previously
    completed many of the same type of project.
    ¶ 44        Plaintiffs asked what would happen if, after purchasing the building, they were unable
    to proceed with the conversion for some reason, and Hebson replied that they would still be
    able to resell the building for “ ‘well over $700,000.00.’ ” Hebson assured plaintiffs that if
    Bernstein or Peak Construction did not follow through, Hebson would “get involved.”
    ¶ 45        Ross testified that the first time he visited the property was on June 15, 2006, when he
    and Gary met Hebson, Court, and Bernstein and walked through the property; by that point,
    Gary had already signed a contract to purchase the property. Hebson led the walk-through
    -9-
    and pointed out everything that was going to be done pursuant to the construction agreement
    that Peak Construction had created for him.
    ¶ 46                                       b. Defendants
    ¶ 47       Hebson testified that he met the Siegels and Bernstein at 1025 Wood on June 15 so that
    Ross could walk through the property; he could not recall whether Obloy or Court was also
    present. During the meeting, Hebson and Bernstein discussed that the spreadsheet was a
    rough estimate for work at the property.
    ¶ 48       Bernstein testified that the meeting with Court, Hebson, Ross, and Gary at the property
    in the middle of June 2006 was the first time he met Gary or Ross. He believed that the
    Siegels had a copy of the spreadsheet he had provided to Hebson because, by the time they
    next met, the Siegels were aware that the price was going to be $183,200. Bernstein and
    Hebson discussed with the Siegels that the slope of the floor was going to be repaired and
    the roof would be replaced. After the first visit, Bernstein gave plaintiffs “our proposal,” and
    set up a meeting at the Peak Properties office.
    ¶ 49                                      3. June 20 Meeting
    ¶ 50                                          a. Plaintiffs
    ¶ 51       The complaint alleges that, on the morning of June 20, 2006, plaintiffs met with Zucker
    and Bernstein at Peak Construction’s offices, where Zucker and Bernstein provided plaintiffs
    with a draft construction contract for Peak Construction’s expected work at the building site,
    with a total price of $183,200, and including as an attachment the spreadsheet that Court had
    earlier provided Gary. Zucker and Bernstein informed plaintiffs that the terms of the draft
    construction contract were agreed to by Peak Construction. Zucker informed plaintiffs that
    he would soon visit the property to familiarize himself with it and that he would follow the
    progress of Peak Construction’s work on the project; Zucker also indicated that he “stood
    behind everything Bernstein said or did.”
    ¶ 52       During that meeting, a woman whom Bernstein identified as Peak Construction’s
    “ ‘permit expediter’ ” came into the room, and after Bernstein reviewed the project with her,
    she told plaintiffs that a repair and replace permit would be sufficient for the project.
    ¶ 53                                         b. Defendants
    ¶ 54       Zucker testified that the first time he met the Siegels, they were meeting in a conference
    room and Bernstein asked Zucker to stop by, which he did for 10 minutes. Bernstein testified
    that, during the meeting, a permit expediter entered and Zucker stated that she would be the
    person dealing with the regulatory issues in terms of obtaining permits; Bernstein was not
    involved with the permit expediter on a day-to-day basis.
    ¶ 55       Bernstein testified that at the meeting at Peak Properties’ office, Bernstein and Zucker
    gave the Siegels a copy of their construction contract. The price of $183,200 was listed in the
    construction contract, as was an estimated start date of July 10, 2006. The Siegels expressed
    interest in moving forward and Bernstein agreed to connect them with an architect. The
    -10-
    Siegels did not sign the construction contract at that time because they wanted their attorney
    to review it.
    ¶ 56                     4. June 21 Meeting with Bernstein and Architect
    ¶ 57                                         a. Plaintiffs
    ¶ 58       The complaint alleges that on June 21, 2006, Gary and Bernstein met at 1025 Wood,
    where Bernstein again confirmed that Peak Construction would begin the repair and
    remodeling work within three days after the closing, expecting that it would take two to three
    days to obtain the permit before work could begin. At the same meeting, Gary and Bernstein
    met with an architect, who walked through the building to review the project. The architect
    expressed concern about the project and proposed work requiring full permits. Later, outside
    the presence of the architect, Bernstein told Gary that the architect was only concerned about
    obtaining more work for himself and that Gary should request a more basic proposal from
    the architect. Bernstein also repeated that he had done similar projects many times with only
    a repair and replace permit, that there was no need to obtain a full permit, and that Gary had
    nothing to worry about. Bernstein promised to speak with the architect and have the architect
    prepare basic plans.
    ¶ 59       Ross testified that Gary met with the architect, who sent a proposal on June 26. Ross
    emailed Bernstein on June 27, stating that after receiving the proposal, he and Gary “ha[d]
    a bunch of questions”; Ross did not discuss the architect’s proposal or the architect’s
    concerns about the permits with his attorney. Ross testified that “we were comfortable” with
    Bernstein’s response to the architect’s concerns, which was “[t]hat, basically, [Bernstein] had
    done numerous projects exactly like this in the past and that repair and replace he had worked
    under and that [the architect] was probably just looking to try and increase the cost of his
    services.”
    ¶ 60                                       b. Defendants
    ¶ 61       Bernstein testified that he visited the property once with the Siegels and L. Jean
    DuFresne, an architect whom Bernstein referred the Siegels to because they wanted someone
    to “draw up some plans.” Bernstein testified that when they were walking through the
    property, “[t]here were certain things that the Siegels were requesting. They were asking, I
    know, if they could put in stairs here, if we can move a wall here, if there was electric, new
    services, putting on decks, incorporating some other space into other units. It was
    significantly different than what my original proposal was because what I wanted and what
    Lane and Hebson had originally–what we had gone through was, again, just a remodel job.
    It wasn’t a complete gut rehab.” Bernstein testified that the Siegels were discussing additions
    that were not included in the $183,200 proposal.
    ¶ 62       The record on appeal contains several emails between plaintiffs and L. Jean DuFresne,
    an architect with SPACE Architects + Planners, that were attached to defendants’ motion for
    summary judgment. One email, dated June 26, 2006, contained a proposal for architectural
    services. The proposal noted that “[t]he current structure is in great shape,” but stated: “Due
    to the nature of the work, you will be required to get a permit from the City of Chicago
    -11-
    Department of Construction and Permits, the City Hall location, before starting the work.”
    The next day, Ross replied to the email: “Perhaps there was a miscommunication, but what
    Gary and I are looking for is simply floor plans to facilitate the construction for a repair and
    replace permit–I think just number 6 in your list. It looks like your proposal is for a full
    permit and a significantly greater project.” DuFresne replied the next day: “Due to the scope
    of the work that was outlined in the field by Eric [Bernstein] and Gary, you will have to
    apply for a full building permit. Repair and replace allows for very limited work within an
    existing building.” DuFresne’s email also provided a link to the City of Chicago website
    outlining the situations where a permit was needed.
    ¶ 63                       5. No Inspection and Purchase Contract Rider
    ¶ 64       In their requests to admit, plaintiffs admitted to the accuracy of certain email
    communications between them and their counsel. One set of emails was between Ross and
    Marc Engel, plaintiffs’ counsel at the time, and concerned a proposed rider to the purchase
    contract; the email from Engel concerning the rider included a question from Engel as to
    whether the Siegels were planning on having the property inspected. In an email dated June
    21, 2006, Ross made a comment concerning the rider that “we are not going to do an
    inspection.” In a reply, dated June 24, 2006, Engel included the comment: “Also, are you
    sure that you don’t want to have a professional inspection done–to look at the foundation and
    structural integrity of the building?” Ross responded on June 25, 2006: “We are not going
    to have an inspection done. I appreciate your concern, but after discussing it with the
    inspector and the GC, we will take a pass.”
    ¶ 65       The email “ask[ing] Ross whether or not he wanted to have a professional inspection
    done to look at the foundation and structural integrity of the building” was provided by
    Engel, and was the only document produced by Engel, which Engel saved despite moving
    to a different law firm “[i]n the event I was ever deposed and for purposes of litigation.”
    Engel testified that he represented the Siegels in their purchase of the property; he was an
    associate with the firm, supervised by Sam Borek. Engel opined that, by purchasing the
    property without having a professional inspection, plaintiffs were taking a risk of latent
    defects in the property.
    ¶ 66       Gary testified that, if a buyer asked him whether he or she should have an inspection, he
    would tell them yes, depending on the circumstances; Gary opined that an individual would
    not need an inspection for a “[n]ew construction or a condo conversion. Or if they were
    educated enough on their own to make their own inspection.” Gary further testified that he
    and Ross did not have the property inspected “[b]ecause Bernstein and Hebson, they all
    thought it was a bad idea because an inspection would be invasive and cause more work. And
    the issues that we thought were going to come up, they said they are not issues.”
    ¶ 67       Luke Fonash, a real estate agent with the Matt Garrison Group at the same time as Gary,
    testified that “I don’t know anyone in their right mind that would buy a property and waive
    inspection. I don’t care if it’s a $50,000 condo or a $12 million mansion.” Fonash further
    testified that no matter the type of property, he would never advise a buyer to purchase a
    property without an inspection “[b]ecause that’s not how you do it. That’s [the] number one
    -12-
    rule.” Fonash visited the property four to five times with Gary. The first time he visited the
    property, he observed that the building was “definitely something that needed to be
    refurbished.” He did not notice any particular problems with the building, other than the floor
    sloped. Fonash testified: “Gary purchased a property, didn’t do the due diligence, waived
    inspection. It turned out the building didn’t come to what he wanted to do with it and now
    we are all sitting here.”
    ¶ 68       Borek testified that he generally advised clients to have an inspection because “I just
    think it makes good sense to have a good understanding of the condition of the property if
    the developer isn’t qualified in the same manner that the inspector is.” When Borek learned
    that the Siegels were not planning on having an inspection, “[m]y response was that[,] when
    I was told they weren’t going to do an inspection[,] that they didn’t need one because they
    had the information from the general contractor, that they had met with the general contractor
    and that he had communicated to Ross and to Gary all of the information that an inspector
    would be provided if they were to hire a different one.”
    ¶ 69       The complaint alleges that, on July 6, 2006, plaintiffs’ attorney faxed a letter and a
    proposed purchase contract rider to 842 Wood’s attorney. The rider contained various
    contract modifications, including extension of the closing date to July 31, 2006, and addition
    of a warranty from the seller to the buyer that “[t]he roof, walls, and foundation of the
    building on the premises will not allow any water leakage and will be in good working
    condition on the date of closing.” The rider was signed on behalf of 842 Wood on July 10,
    2006.
    ¶ 70                         6. July 17 and 26 Meetings and Plaintiffs’
    Proposed Construction Contract
    ¶ 71       The complaint alleges that, on July 17, 2006, Gary met with Bernstein at 1025 Wood.
    They discussed the timing, materials, pricing, and other details of the proposed construction
    contract between Peak Construction and plaintiffs for repair and remodeling of the building.
    Bernstein again assured Gary that everything was agreed as set forth in the draft construction
    contract and that Peak Construction would begin work within a few days of the closing. At
    the same meeting, Gary and Bernstein met with a representative from a remodeling design
    firm as part of the process of preparing new floor plans for the remodeling work. Gary and
    Bernstein agreed that Bernstein would make a few changes to the plans.
    ¶ 72       Engel testified that he used the figures in Peak Construction’s construction proposal for
    work on the property to draft a construction contract “[j]ust to provide some more details or
    provisions to fine-tune, perhaps, agreement between the parties.” Engel explained: “This
    document just has work, and it has figures, but it doesn’t have contract language.” Engel
    testified that there were changes between Peak Construction’s proposal and the construction
    contract he prepared, but that there was no change to the list of items that were to be repaired
    or to the price.
    ¶ 73       Engel opined that the construction proposal from Peak Construction was not a contract,
    because it was not signed and “[n]othing is certain until it’s signed.” Borek testified that he
    asked Engel to draft the construction contract in anticipation of using it, but was later
    -13-
    informed by Ross that it would not be necessary “because they already had an agreement that
    they were going to use which was the same agreement that the general contractor had with
    the seller.”
    ¶ 74       The complaint alleges that, on July 26, 2006, plaintiffs met with Bernstein at 1025 Wood
    to discuss final construction details and to sign the construction contract between plaintiffs
    and Peak Construction. They agreed that the start date for the work would likely be August
    3 or 4, but no later than August 7, 2006. They walked through the building again and
    confirmed the previously-agreed contract terms for the repair and remodeling work.
    Bernstein said that he wanted to review the construction contract again prior to signing it, so
    plaintiffs and Bernstein agreed to meet again at 9:30 a.m. on August 1, 2006, the day after
    the closing, to sign the construction contract for Peak Construction to perform the repair and
    remodeling work.
    ¶ 75                                          D. Closing
    ¶ 76        The complaint alleges that, “in reliance on the representations by Hebson, Court, Obloy,
    Bernstein, Zucker, 842 Wood and Peak Construction,” plaintiffs closed on the purchase of
    1025 Wood on July 31, 2006. The warranty deed conveying the property to Siegel
    Development was signed by Lane. Following the closing, either 842 Wood or Hebson paid
    Court $10,000 in cash for his role in facilitating the transaction, a payment that was not listed
    on the HUD-1 Settlement Statement for the closing.
    ¶ 77        Engel testified that he was the attorney representing the Siegels at closing, and he was
    not aware at that time whether there was a signed construction contract with Peak
    Construction. Engel testified that he did not feel it was important to determine whether there
    was a signed construction contract prior to closing: “My general feeling was that they were
    going to do the work either before or after closing, and they would execute a contract to have
    work done.”
    ¶ 78        Ross testified that he knew that Peak Construction had not signed the proposed
    construction contract but proceeded to close on the property regardless. Ross testified that
    he and Gary “weren’t concerned about” the fact that Peak Construction had not signed the
    proposed construction contract because they “had a deal in place” that “was discussed with
    all the defendants numerous times.”
    ¶ 79        The complaint alleges that, at approximately 8:30 p.m. on July 31, 2006, Bernstein called
    Gary to cancel their August 1 meeting, informing Gary that he was not ready to sign the
    construction contract because he needed to review some details of the proposed construction
    contract with Zucker. The phone call was the first notice that plaintiffs had received that
    Peak Construction had not fully agreed to the terms of the proposed construction contract.
    Over the next 10 days, Gary repeatedly attempted to call Bernstein and told Court in person
    that he was attempting to contact Bernstein; Gary asked Court for his assistance in contacting
    Bernstein and in finding a new buyer for the building, which Court had previously said
    existed. Bernstein never answered the phone or returned Gary’s calls. Court never provided
    the names of any new buyers for the building and, on approximately August 14, 2006,
    informed Gary that Court was “done with the matter and was no longer involved.”
    -14-
    ¶ 80        Bernstein testified that he did not return the Siegels’ phone calls in early August because
    “at that time I didn’t have an answer for them.” Bernstein knew their closing was at the
    beginning of August, and attempted to set up a meeting “because there was so many changes
    and so many questions, I was trying to put it all together”; however, unbeknownst to him,
    Zucker had gone out of town at the end of July. The Siegels wanted the signed construction
    contract, but Bernstein could not provide it because Zucker had gone out of town and would
    not return until the middle of the first week of August; Bernstein did not have the authority
    to sign the construction contract but needed Zucker.
    ¶ 81        Gary testified that, approximately a week after the closing, Court informed him that
    Court had received a $10,000 payment in connection with the sale of the property; Gary also
    heard people at the office discussing it. Court testified that he received $10,000 from Hebson
    in connection with the sale of the property. He did not explicitly inform the Siegels of the
    payment, but believed that they knew, since they were not paying him and “[w]hen there’s
    property not on the market, somebody is paying the guys putting it together. *** If I wasn’t
    getting paid by them, then the Siegels were going to have to pay me.”
    ¶ 82        The complaint alleges that Gary was eventually able to contact Zucker, who arranged a
    meeting at 1025 Wood on August 10, 2006, between plaintiffs and Zucker, Bernstein, and
    an unnamed employee of Zucker. During the meeting, Zucker stated that he supported
    everything that Bernstein had told plaintiffs about the construction contract and the project,
    but wished to examine the contract pricing and other terms, requesting a few days to do so.
    At that time, Zucker also walked through the property with plaintiffs.
    ¶ 83        Zucker testified that he met the Siegels at 1025 Wood, along with Bernstein and another
    contractor who “tag[ged] along,” in order to discuss the scope of the project. They walked
    around the building and the Siegels pointed to specific renovations they wanted done “such
    as [they] want to do this electric work, move this wall, put steps here, put a new kitchen here;
    so that gene[r]ic type of talk.” Zucker testified that the projects the Siegels were proposing
    went beyond the “guesstimate” provided by Bernstein’s spreadsheet. Bernstein testified that
    Zucker determined that “based on the scope of work, the changes that were occurring that
    the Siegels had wanted, that there was just no way that we could do the project for”
    $183,200. Gary objected, and Zucker said that he would need to get back to him. Zucker and
    Bernstein ultimately concluded that they could not perform the work for that price.
    ¶ 84        The complaint alleges that, on August 14, 2006, Zucker called Ross and informed him
    that Peak Construction could not agree to the $183,200 price in the draft construction
    contract and could not agree to perform the work under a repair and replace permit. Ross told
    Zucker that this information significantly changed the costs and timing of the project, which
    were important in plaintiffs’ decision to purchase the property. Ross told Zucker that
    plaintiffs wanted the package that had been repeatedly presented to them, but Zucker “said
    he would not do anything.”
    ¶ 85                  E. The Siegels’ Post-Peak Construction Efforts
    to Renovate the Property
    ¶ 86      The complaint alleges that, on August 15, 2006, Ross sent an email to Hebson, stating
    -15-
    that plaintiffs were interested in quickly reselling the building and asking for the names of
    the other people who Hebson had indicated were interested in buying the property; Hebson
    did not respond to the email.
    ¶ 87       In mid- to late August, Gary informed Court that plaintiffs “wanted to get out” of the
    project. Court promised to speak with Hebson and Obloy, but plaintiffs never learned of the
    results of the discussion. In the last week of August, Gary attempted to call Obloy and left
    Obloy a voicemail asking for assistance concerning the property. Obloy returned the call
    approximately five weeks later, but offered no assistance. The same day Gary called Obloy,
    he also called Hebson and left a voicemail asking for assistance with the property and asking
    to be put in touch with other potential buyers for the property; Hebson never returned the
    call.
    ¶ 88       In late August and early September, plaintiffs were informed by contractors and a
    structural engineer who visited the building that there were structural problems with the
    building, including that the foundation was sinking in places; the walls were bowing out,
    especially in the attic; the floors were sloping around the major supports; and the roof needed
    to be replaced. Earlier, in June and July 2006, Hebson, Obloy, Bernstein, and Zucker had
    failed to mention to plaintiffs that there were any problems with the foundation, walls, or
    other structural components of the building; in fact, Hebson and Bernstein had specifically
    denied that there were any structural problems.
    ¶ 89       On September 7, 2006, plaintiffs received a quote of $425,000 from a contractor to
    perform the repair and remodeling work on the project, which did not include roof repairs
    or necessary structural repairs to the foundation, walls, and floors. They also received a
    separate quote of $17,000 for roof repairs. Plaintiffs were unable to obtain a quote for the
    necessary structural repairs without an engineer performing an invasive investigation.
    ¶ 90       Jason Patrinos testified that he operated a real estate management business and purchased
    the property from the Siegels in December 2007, where he renovated it for use as rental
    properties. Patrinos, through his company, acted as general contractor, and Patrinos
    performed the plumbing and demolition work on the property. Patrinos did not pay himself
    for the general contractor duties and did not perform structural repairs. Patrinos’ affidavit
    also provided that Patrinos replaced the roof, repaired the exterior masonry walls, repaired
    the sloping of the floors, and performed a general rehabilitation of the property to make the
    building’s existing units into four salable units. The renovations were completed at a total
    cost of $234,500, and all four units were being rented to tenants as of the August 20, 2009,
    date of the affidavit.5
    ¶ 91                                      III. Complaint
    ¶ 92      On October 24, 2006, plaintiffs filed a four-count verified complaint against defendants,
    which was amended on July 24, 2007. Counts I and II, the counts at issue in the instant
    appeal, allege conspiracy to defraud and fraud, respectively.
    5
    The record indicates that all four units were sold between October 2009 and April 2010.
    -16-
    ¶ 93       Count I of the complaint alleges that the conduct of defendants was part of a conspiracy
    to defraud plaintiffs in order to sell the property for a price substantially in excess of its fair
    market value. As part of the conspiracy, Hebson, Bernstein, Obloy, and Zucker knowingly
    made false representations, including statements (1) that the only repairs or remodeling
    required on the building for a successful condominium conversion were included on the
    spreadsheet provided to Gary by Court; (2) that the roof, walls, and foundation of the
    building would not allow water leakage and would be in good working condition on the date
    of closing; (3) that Peak Construction was willing to perform the work listed in the
    spreadsheet and referenced in the draft construction contract for a total price of $183,200;
    and (4) that a repair and replace permit would authorize the performance of all of the
    necessary repair and remodeling work. At the time the statements were made, Hebson,
    Bernstein, Obloy, and Zucker knew their representations to plaintiffs were false and intended
    that plaintiffs rely on those representations. Plaintiffs relied on defendants’ representations
    in deciding to purchase the property and in closing on that purchase. As a result of the
    conspiracy to defraud, plaintiffs were damaged in that they purchased the property for a price
    substantially in excess of its fair market value and became owners of a property that could
    not be converted into condominiums in such a way as to afford plaintiffs a return on their
    investment. Plaintiffs were also damaged in that they incurred substantial costs in purchasing
    and continuing to own the property, including interest, taxes, and other expenses.
    Accordingly, plaintiffs requested an award of compensatory damages of no less than
    $500,000, punitive damages of no less than $1 million, and an award of all costs incurred by
    them in the action.
    ¶ 94       Count II of the complaint is against 842 Wood, Peak Construction, Hebson, and
    Bernstein, and alleges fraud, repeating the same allegations as count I of the complaint and
    requesting the same relief. Counts III and IV of the complaint, not at issue on appeal, are
    against 842 Wood; count III is for breach of the purchase contract and count IV is for
    rescission.
    ¶ 95                             IV. Motion for Summary Judgment
    ¶ 96       On September 10, 2010, defendants Hebson, Zucker, Obloy, Bernstein, Peak Properties,
    and Peak Construction filed a joint motion for summary judgment on counts I and II of
    plaintiffs’ amended complaint. The motion claimed that the undisputed facts proved that
    plaintiffs were sophisticated businessmen who were aware of the property defects they claim
    they were deceived about prior to the closing and nevertheless proceeded to close on the
    property, against the advice of counsel and without obtaining a professional inspection or a
    written executed construction contract with Peak Construction. Accordingly, the motion
    claimed that plaintiffs did not reasonably rely on defendants’ representations but instead took
    a known risk that turned out badly.
    ¶ 97       The motion further claimed that defendants were entitled to summary judgment because
    the alleged false statements were puffery or opinions regarding future events and could not
    constitute actionable fraud, nor did the alleged undisclosed commission to Court and Obloy.
    Additionally, the motion claimed that the alleged misrepresentations did not cause any
    -17-
    damages, as plaintiffs received the full benefit of their bargain under the real estate contract
    for the purchase of the property, demonstrated by the fact that the appraised value of the
    property at the time of the purchase was $680,000, which is the price that plaintiffs paid.
    Finally, the motion claimed that there was no conspiracy to fraudulently induce plaintiffs to
    purchase the property.
    ¶ 98      In their response to defendants’ motion for summary judgment, plaintiffs claimed that
    the facts demonstrated that defendants knowingly and intentionally acted in concert to
    defraud plaintiff and made actionable misrepresentations that plaintiffs relied upon in
    purchasing the property and that caused them damage. Plaintiffs further argued that, at a
    minimum, there were genuine issues of material fact that precluded summary judgment.
    ¶ 99      On April 1, 2011, the parties came before the trial court for a hearing on the motion for
    summary judgment and, on June 21, 2011, the trial court entered summary judgment on
    counts I and II of the complaint in favor of Peak Construction, Peak Properties, Zucker,
    Obloy, and Bernstein; Hebson was in bankruptcy at the time. The court stated that “the major
    premise underlying the fraud claim is that at the time the plaintiffs agreed to buy the
    property, they believed they were getting a package deal for construction from Peak
    Construction.” However, the court noted that the purchase agreement for the property did not
    reference a package deal or any repair work, and the spreadsheet, “which is really the
    lynchpin underlying the fraud theory,” was very general, containing only categories of work
    and round numbers. The spreadsheet also did not indicate anything about the scope of the
    repairs, leaving the question of whether it was to be a lipstick job requiring a repair and
    replace permit or a gut rehab requiring a full permit. The court noted that plaintiffs were
    provided a construction contract from Peak Construction that totaled $183,200, but that
    plaintiffs’ attorneys prepared another construction contract in response; neither contract was
    executed. The court observed that “[i]n looking at all of this, I think the problem I see is that
    the defendants [sic] are attempting to enforce a contract through a claim for fraud.”
    ¶ 100     The trial court disagreed with plaintiffs’ argument that they believed they had an
    enforceable oral construction contract and that no written contract was necessary. The court
    pointed out that plaintiffs did not sign the Peak Construction contract but instead proffered
    their own contract. The court further noted that nobody had been able to testify as to the
    specific work the parties agreed was to be performed–“that is, the terms of the contract.”
    Thus, the court found that there was no meeting of the minds sufficient to create an oral or
    written contract “and that permeates the claim for fraud *** as well.”
    ¶ 101     The trial court found that, while the issue of reasonable reliance was normally a question
    of fact, under the facts of this case, there was no reasonable reliance as a matter of law. The
    court cited Kopley Group V., L.P. v. Sheridan Edgewater Properties, Ltd., 
    376 Ill. App. 3d 1006
    , 1018 (2007), for the proposition that “if the purchaser’s reliance is unreasonable in
    light of the information open to him, which includes the fact that there was actual knowledge
    in any, he might have discovered, by the exercise of ordinary prudence, the loss is considered
    his own responsibility and summary judgment against the purchaser is required because no
    fair-minded person could find otherwise.”
    ¶ 102     The trial court noted that the transaction was an arm’s-length transaction and that
    -18-
    plaintiffs chose not to obtain an inspection because they claim defendants told them it was
    not necessary since the property would be renovated. However, a licensed real estate agent
    visited the property and believed that an inspection was warranted, and plaintiffs were not
    discouraged from hiring an architect to go through the property. Nevertheless, they ignored
    the architect’s advice that, due to the scope of work, a full building permit was required and
    the inclusion of the internet link to the City of Chicago website. The court concluded, “[a]ll
    of this evidence shows that there is no genuine issue of material fact that the plaintiffs took
    a known risk when they ultimately closed on the property.” The court noted that while there
    was an issue of fact as to whether defendants discouraged plaintiffs from following through
    with the inspection or following the architect’s advice, “there is no issue of fact that the
    defendants did not prohibit them from doing so, and that’s an important distinction.” The
    court pointed to the case of Smith v. Ethell, 
    144 Ill. App. 3d 171
    (1986), stating that “the gist
    of the case is *** that it is at an arm’s length transaction that’s so long and the purchasers
    aren’t prohibited by the sellers from undertaking further investigation, that it does not go to
    the issue of reasonable reliance.”
    ¶ 103       The trial court also found that, in addition to the lack of reasonable reliance, most of the
    false statements were not actionable. The court noted that the statements regarding the
    potential of the property were puffery. The court further noted that, as to the claim that the
    only repairs necessary were those on the spreadsheet for $183,200, the spreadsheet was “too
    vague” about what repairs were required and there was no evidence that the $183,200
    number was false. The court found that the representation as to the type of permit required
    may or may not have been false, but the type of permit required was an opinion of law, and
    plaintiffs could have discovered any inconsistency by reviewing the applicable building and
    zoning ordinances that they were directed to by the architect.
    ¶ 104       Finally, the court found that there was no reasonable reliance as to statements concerning
    the structural elements–that the foundation, the roof, and the walls were sound and did not
    leak. The court found that plaintiffs, instead of relying on the statements made by defendants,
    obtained warranties from the seller as to those elements. The court concluded: “I thought
    about it long and hard and it may be that there was some–may be have been–you know, led
    down a path, but I just don’t think it got to the point where it was actionable.”
    ¶ 105       On February 22, 2012, the trial court entered summary judgment as to counts I and II of
    the complaint in Hebson’s favor, for the reasons stated in granting summary judgment in
    favor of the other defendants.
    ¶ 106       Plaintiffs filed notices of appeal for both cases, and we consolidated the appeals on
    March 30, 2012.6
    ¶ 107                                       ANALYSIS
    ¶ 108       On appeal, plaintiffs claim that the trial court erred in granting summary judgment in
    defendants’ favor because the evidence established that they were defrauded by defendants
    6
    We note that Hebson has not filed an appearance in the matter.
    -19-
    or, at a minimum, genuine issues of material fact precluded the entry of summary judgment.
    A trial court is permitted to grant summary judgment only “if the pleadings, depositions, and
    admissions on file, together with the affidavits, if any, show that there is no genuine issue as
    to any material fact and that the moving party is entitled to a judgment as a matter of law.”
    735 ILCS 5/2-1005(c) (West 2004). The trial court must view these documents and exhibits
    in the light most favorable to the nonmoving party. Home Insurance Co. v. Cincinnati
    Insurance Co., 
    213 Ill. 2d 307
    , 315 (2004). We review a trial court’s decision to grant a
    motion for summary judgment de novo. Outboard Marine Corp. v. Liberty Mutual Insurance
    Co., 
    154 Ill. 2d 90
    , 102 (1992). De novo consideration means we perform the same analysis
    that a trial judge would perform. Khan v. BDO Seidman, LLP, 
    408 Ill. App. 3d 564
    , 578
    (2011).
    ¶ 109        “Summary judgment is a drastic measure and should only be granted if the movant’s right
    to judgment is clear and free from doubt.” Outboard Marine 
    Corp., 154 Ill. 2d at 102
    . “Mere
    speculation, conjecture, or guess is insufficient to withstand summary judgment.” Sorce v.
    Naperville Jeep Eagle, Inc., 
    309 Ill. App. 3d 313
    , 328 (1999). A defendant moving for
    summary judgment bears the initial burden of proof. Nedzvekas v. Fung, 
    374 Ill. App. 3d 618
    , 624 (2007). The defendant may meet his burden of proof either by affirmatively
    showing that some element of the case must be resolved in his favor or by establishing “ ‘that
    there is an absence of evidence to support the nonmoving party’s case.’ ” Nedzvekas, 374 Ill.
    App. 3d at 624 (quoting Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 325 (1986)). In other words,
    there is no evidence to support the plaintiff’s complaint.
    ¶ 110        “ ‘The purpose of summary judgment is not to try an issue of fact but *** to determine
    whether a triable issue of fact exists.’ ” Schrager v. North Community Bank, 
    328 Ill. App. 3d
    696, 708 (2002) (quoting Luu v. Kim, 
    323 Ill. App. 3d 946
    , 952 (2001)). “ ‘To withstand
    a summary judgment motion, the nonmoving party need not prove his case at this preliminary
    stage but must present some factual basis that would support his claim.’ ” Schrager, 328 Ill.
    App. 3d at 708 (quoting 
    Luu, 323 Ill. App. 3d at 952
    ). We may affirm on any basis appearing
    in the record, whether or not the trial court relied on that basis or its reasoning was correct.
    Ray Dancer, Inc. v. DMC Corp., 
    230 Ill. App. 3d 40
    , 50 (1992).
    ¶ 111        To state a claim for fraud, a plaintiff must allege five elements: “(1) a false statement of
    material fact; (2) by one who knows or believes it to be false; (3) made with the intent to
    induce action by another in reliance on the statement; (4) action by the other in reliance on
    the truthfulness of the statement; and (5) injury to the other resulting from that reliance.”
    State Security Insurance Co. v. Frank B. Hall & Co., 
    258 Ill. App. 3d 588
    , 592 (1994) (citing
    Soules v. General Motors Corp., 
    79 Ill. 2d 282
    , 286 (1980)).
    ¶ 112        In the case at bar, plaintiffs state that “[a]t the heart of the fraud claims in this case was
    the representation made by the defendants to the plaintiffs that the transaction was a package
    deal[,] namely[,] the purchase of Property and an agreement for the Property to be rehabbed
    at a cost of $183,200.” Plaintiffs’ amended verified complaint indicates that these alleged
    misrepresentations made by defendants fall into four categories: “[1] that the only repairs or
    remodeling required on 1025 N. Wood for a successful condominium conversion were
    included on the spreadsheet that Court provided to Gary Siegel (as Hebson, Bernstein, Obloy
    and Zucker repeatedly represented); [2] that the roof, walls and foundation of the building
    -20-
    will not allow water leakage and will be in good working condition on the date of closing (as
    made by Hebson on behalf of 842 Wood in the [purchase] contract Rider); [3] that Peak
    Construction was willing to perform all the work listed in the spreadsheet, and referenced
    in the draft [construction] contract, for a total price of $183,200.00 (as Hebson, Bernstein,
    Obloy and Zucker repeatedly represented); and [4] that a ‘repair and replace’ permit from the
    City of Chicago would authorize the performance of all of the necessary repair and
    remodeling work at 1025 N. Wood, among other misrepresentations.” We agree with the trial
    court’s conclusions concerning all four categories of statements.
    ¶ 113      With regard to the defendants’ alleged misrepresentations concerning the spreadsheet,
    which the trial court noted were “really the lynchpin underlying the fraud theory,” we agree
    with the trial court that there was no meeting of the minds concerning the work to be
    performed on the property. The spreadsheet itself was vague and only described broad
    categories of renovations, affixing a round-number estimate to each category. For instance,
    one line provides for “WINDOWS” for “$7,000.00,” while another provides for “DOORS”
    for “$2,700.00.” Plaintiffs point to the several walkthroughs of the property and claim in
    their brief that “it was not just the spread sheet that formed the [construction] contract but
    the spread sheet and discussion which were had which formed the contract.” However,
    despite plaintiffs’ argument, neither Gary nor Ross was able to provide very many details
    about the scope of the work during their deposition testimony. Additionally, as the trial court
    noted, when provided with a written construction contract, the Siegels did not sign it and
    knowingly closed on the property without a signed construction contract. Accordingly, we
    cannot agree with plaintiffs that there was a “deal in place” at the time of the closing. See
    Midland Hotel Corp. v. Reuben H. Donnelley Corp., 
    118 Ill. 2d 306
    , 314 (1987) (“The
    essential terms of a contract must be definite and certain in order for a contract to be
    enforceable.”). Since there was no definite agreement in place as to the scope of Peak
    Construction’s work and plaintiffs never formalized an agreement with Peak Construction
    as to the scope of the work, there cannot have been a “false statement of material fact” about
    Peak Construction’s willingness to perform the work that would form the basis of a fraud
    claim and the trial court properly granted summary judgment in defendants’ favor regarding
    the claims concerning the spreadsheet.
    ¶ 114      With regard to the permit issue and the questions of the property’s structural integrity,
    we agree with the trial court that plaintiffs’ reliance on defendants’ alleged
    misrepresentations was not reasonable. As part of its fraud claim, a plaintiff must show that
    its reliance on the misrepresentation was justified. Adler v. William Blair & Co., 
    271 Ill. App. 3d
    117, 125 (1995). In other words, the reliance must be reasonable. In re Marriage of
    Broday, 
    256 Ill. App. 3d 699
    , 703 (1993). Generally, the question of whether a plaintiff’s
    reliance was reasonable is a question of fact; however, where only one conclusion can be
    drawn from the undisputed facts, the question becomes one for the court to determine. Doe
    v. Dilling, 
    371 Ill. App. 3d 151
    , 174 (2006) (citing Neptuno Treuhand-Und
    Verwaltungsgesellschaft MBH v. Arbor, 
    295 Ill. App. 3d 567
    , 575 (1998)). “In determining
    whether reliance was justifiable, all of the facts which the plaintiff knew, as well as those
    facts the plaintiff could have learned through the exercise of ordinary prudence, are taken
    into account.” Adler, 
    271 Ill. App. 3d
    at 125. “ ‘[A] person may not enter into a transaction
    -21-
    with his eyes closed to available information and then charge that he has been deceived by
    another.’ ” D.S.A. Finance Corp. v. County of Cook, 
    345 Ill. App. 3d 554
    , 561 (2003)
    (quoting Chicago Export Packing Co. v. Teledyne Industries, Inc., 
    207 Ill. App. 3d 659
    , 663
    (1990)). However, “ ‘Illinois law has long held that, where the representation is made as to
    a fact actually or presumptively within the speaker’s knowledge, and contains nothing so
    improbable as to cause doubt of its truth, the hearer may rely upon it without investigation,
    even though the means of investigation were within the reach of the injured party and the
    parties occupied adversary positions toward one another.’ ” Schrager, 
    328 Ill. App. 3d
    at 709
    (quoting Sims v. Tezak, 
    296 Ill. App. 3d 503
    , 511 (1998)). “If the party’s reliance is
    unreasonable in light of the information open to him, the loss is considered his own
    responsibility.” D.S.A. 
    Finance, 345 Ill. App. 3d at 561
    (citing 
    Neptuno, 295 Ill. App. 3d at 575
    ).
    ¶ 115      In the case at bar, we agree with the trial court that plaintiffs’ reliance on defendants’
    statement that a repair and replace permit would suffice was not reasonable. Prior to the
    closing, plaintiffs received an architectural proposal from DuFresne that noted that “[t]he
    current structure is in great shape,” but specifically stated that, “[d]ue to the nature of the
    work, you will be required to get a permit from the City of Chicago Department of
    Construction and Permits, the City Hall location, before starting the work.” The next day,
    Ross replied to the email: “Perhaps there was a miscommunication, but what Gary and I are
    looking for is simply floor plans to facilitate the construction for a repair and replace
    permit–I think just number 6 in your list. It looks like your proposal is for a full permit and
    a significantly greater project.” DuFresne replied the next day: “Due to the scope of the work
    that was outlined in the field by Eric [Bernstein] and Gary, you will have to apply for a full
    building permit. Repair and replace allows for very limited work within an existing
    building.” DuFresne’s email also provided a link to the City of Chicago website outlining the
    situations where a permit was needed. Thus, prior to closing, plaintiffs were informed by a
    professional that repair and replace permits would not be sufficient for the renovations they
    were planning. Even if, as Ross testified, “[the Siegels] were comfortable” with Bernstein’s
    response “[t]hat, basically, [Bernstein] had done numerous projects exactly like this in the
    past and that repair and replace he had worked under and that [the architect] was probably
    just looking to try and increase the cost of his services,” they were on notice that their
    planned renovation might not proceed as they had expected and should have investigated
    further.7 Accordingly, the trial court property granted summary judgment in defendants’
    favor on the statements concerning the type of permit required.
    ¶ 116      Additionally, we agree with the trial court that there was no reliance on defendants’
    representations concerning the structural integrity of the property. Plaintiffs obtained a rider
    to the purchase contract in which 842 Wood warranted that “[t]he roof, walls, and foundation
    of the building on the premises will not allow any water leakage and will be in good working
    condition on the date of closing.” Consequently, there need not have been a reliance on
    7
    We also agree with the trial court’s comment that statements as to what permit was required
    are representations of law, not fact.
    -22-
    defendants’ oral statements concerning the structural integrity of the property when it was
    warranted in the purchase contract. Moreover, plaintiffs did not have the property inspected
    prior to closing, although they were entitled to do so and their counsel specifically asked
    them, “are you sure that you don’t want to have a professional inspection done–to look at the
    foundation and structural integrity of the building?” Thus, the trial court properly granted
    summary judgment in defendants’ favor on the statements concerning the structural integrity
    of the property because plaintiffs had a written contractual right to sue if the roof, walls, and
    foundation were not water-leakage free.8
    ¶ 117     As a final matter, we do not agree with plaintiffs’ contention that the payment to Court
    and Obloy constituted fraud, nor did Obloy’s changing of the acquisition price on his
    financial projection spreadsheet constitute fraud. Plaintiffs claim that, had they been aware
    of the payments to Court and Obloy and Obloy’s altering of his financial projection, they
    would have been more skeptical of what was being promised by defendants. However, as
    noted, there was no “deal” in place for Peak Construction to perform renovations on the
    property because there was no meeting of the minds between Peak Construction and
    plaintiffs as to the scope of work. Thus, plaintiffs’ skepticism, or lack thereof, does not
    impact the existence of a fraud claim.
    ¶ 118                                      CONCLUSION
    ¶ 119       The trial court properly granted summary judgment in defendants’ favor because there
    was no meeting of the minds regarding the scope of work to be performed by defendants and
    plaintiffs did not reasonably rely on defendants’ representations.
    ¶ 120       Affirmed.
    8
    Indeed, count III of the instant complaint, not at issue on appeal, was against 842 Wood,
    the seller, for breach of the warranty contained in the purchase contract.
    -23-